Method for approximately depicting boundary of flexible load regulation capability
Through multi-parameter planning theory and optimal segmentation method, the flexible adjustment ability of multi-energy load is quantified, which solves the problem of multi-energy load resource regulation in the power grid, provides accurate adjustment capability boundaries and evaluation standards, and helps the power grid dispatching agencies improve scheduling efficiency.
Patent Information
- Application Number
- CN202410944009.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-15
- Publication Date
- 2024-11-08
AI Technical Summary
The prior art is difficult to effectively aggregate and adjust the flexibility of multi-energy load resources, which leads to difficulty in balancing the power grid source load, and the performance of flexible regulation capability is difficult to be used in actual engineering.
Using multi-parameter planning theory, build an operating economic scheduling model, determine the feasible domain of steady-state transmission of the contact line through optimal segmentation and critical domain methods, quantify the flexible regulation ability of multi-energy loads, and evaluate the remaining loads with standard energy storage as a reference. Adjust the effect.
It provides accurate boundaries for flexible multi-energy load regulation capabilities, helps the power grid dispatching agency to formulate effective scheduling plans, and improves the quantitative characterization and evaluation capabilities of the power grid's flexible load regulation capabilities.
Smart Images

Figure CN118920450A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of power systems, and in particular to a method for approximately characterizing the boundary of flexible load regulation capability. Background Art
[0002] With the surge in uncertainty in power grid operation, the pressure on power grid source-load balance caused by the sudden change in new energy output and load demand has increased dramatically. In recent years, with the rapid growth of summer peak load and the further widening of peak-to-valley difference, regional energy demand peaks have emerged, and the problem of power source-load balance has become prominent. For the increasingly severe power source-load balance problem, load-side resource regulation is currently the most low-carbon, low-cost and efficient method. At present, a large number of dispersed and small-capacity adjustable load resources are aggregated into load-side resource response entities. Through the regulation of the energy management center, they participate in the operation of the power system as a subject. The interactive power capacity they can provide at the system coupling port is the interconnection line power. However, among the adjustable load resources, the adjustable characteristics of flexible loads such as temperature control, energy storage, and electric vehicles are related to the external environment such as the operating parameters of the load equipment itself, user usage habits, temperature and humidity, etc. The parameters of the same load are heterogeneous and the characteristics of different loads are heterogeneous. Aggregating them is a challenge. Previous studies often use mathematical methods to aggregate flexibility resources in a more complex form. After aggregation, the effect of characterizing its flexible adjustment ability is difficult to be truly used in actual engineering. Summary of the invention
[0003] In view of the defects such as heterogeneous characteristics of multi-energy loads and complicated calling effects, the present invention will analyze the heterogeneous characteristics of multi-energy loads in urban power grids such as cooling loads and electric vehicle loads, and based on multi-parameter planning theory, realize the equivalent characterization of the external characteristics of load regulation capability for multiple types of load demand response targets, and define the indicator for quantifying the external characteristics of the flexible regulation capability of multi-energy loads as the regional power system interconnection line power. Considering the safety constraints such as the balance of the interconnected power grid flow, the capacity of the generator and the limit transmission power of the branch, an accurate flexible regulation capability boundary is provided for the multi-energy load. After using mathematical models to characterize the external characteristics of the regulation capability of multi-energy loads, in order to further apply the multi-energy load regulation capability indicator of the regional power system to practice, a new quantitative indicator is established and standard energy storage is used as a reference indicator for the flexible regulation capability of loads in the regional power system to compare and evaluate the regulation effects of other flexible loads, thereby providing a basis for the decision-making of the dispatching agency.
[0004] The present invention discloses a method for approximating the boundary of flexible load regulation capability, which comprises:
[0005] Step 1: Construct an operation economic dispatch model containing the load-side resource aggregation response subject; the constraints of the operation economic dispatch model include regional power grid security constraints, branch power flow constraints, dispatch operation constraints, interconnection line capacity constraints, energy storage device related constraints and air conditioning model related constraints;
[0006] Step 2: Treat the boundary coupling variables in the reconstructed economic dispatch model as variable planning parameters and establish a multi-parameter planning model;
[0007] Step 3: Use "optimal segmentation" and "critical region" to solve the multi-parameter planning model to find all feasible combinations of interconnection line coupling variables and determine the feasible region of steady-state transmission of interconnection lines;
[0008] Step 4: Use the amount of electricity transmitted by the regional power system as a quantitative indicator to quantitatively describe the transmission capacity of the regional power system, that is, the flexibility load regulation capacity within the region; set standard energy storage, use quantitative indicators to calculate the impact of standard energy storage on the flexible regulation capacity of the regional power system, and use it as a reference standard for evaluating other flexible loads in the regional power system.
[0009] Furthermore, the step 1 comprises:
[0010] The objective function of the operation economic dispatch model containing the load-side resource aggregation response subject is:
[0011]
[0012] Where Z is the power system operating cost; c G,t is the quotation of regional power grid unit, P G,t is the active power vector of the adjustable units of the virtual power plant in period t, x t Standard forms for optimizing variables in scheduling models;
[0013] The regional power grid security constraints are:
[0014] P N,t =e G P G,t +e dis P dis,t -e q P q,t -e ch P ch,t -e o P o,t (2)
[0015] Among them, P N,t is the active power injected into the node, e G is the correlation matrix between the adjustable units and each node; dis , e ch , e q , e o are the association matrices of energy storage discharging state, energy storage charging state, air conditioning load power consumption, multi-energy system gateway nodes and each node; P G,tis the active power vector of the adjustable units of the virtual power plant in period t; q,t P is the cooling power of the air conditioner during period t; dis,t , P ch,t are the discharging active power vector and charging active power vector of the energy storage system in period t respectively; o,t is the active power exchanged by the boundary nodes of the multi-energy system in time period t;
[0016] The branch power flow constraints, dispatching operation constraints, and tie line capacity constraints are as follows:
[0017]
[0018] Among them, P L,t is the line active power vector in period t; P L,min , P L,mqx They are the upper and lower limits of the line active power respectively; They are the upper and lower limits of the active power of the adjustable units of the virtual power plant in time period t respectively; G is the upper and lower limits of active power exchanged by the boundary nodes of the multi-energy system in time period t; θ is the node voltage phase angle relationship matrix; θ t is the node voltage phase angle during time period t;
[0019] There are energy storage and air conditioning temperature control loads in the regional power grid. The relevant constraints of the energy storage device are as follows:
[0020]
[0021]
[0022] in, are the discharge active power vector and charging active power vector of the energy storage system at node i in time period t, as its upper limit; is the state of charge of the energy storage device at time i, is its upper limit; α is the charging efficiency; β is the discharging efficiency; is the charge state at the initial moment, is the charge state at time T;
[0023] The constraints related to the air conditioning model are as follows:
[0024]
[0025] Among them, T in,t is the indoor temperature during period t; T out,t is the outdoor temperature during period t; k is the temperature heat coefficient; τ is the building heat dissipation coefficient; T min , T maxare the upper and lower limits of acceptable room temperature respectively; R is the equivalent thermal resistance of the building; C air is the indoor heat capacity of the building.
[0026] Furthermore, the step 2 comprises:
[0027] Based on formulas (1) to (5), the reconstructed economic dispatch model of the i-th regional power grid is obtained after relaxation:
[0028] Where:
[0029] A, B and C are known constant matrices determined by equations (1) to (5);
[0030] The boundary coupling variable w in the reconstructed economic dispatch model is regarded as a variable planning parameter, and equation (6) is a typical multi-parameter planning model established.
[0031] Furthermore, the step 3 comprises:
[0032] Step 31: define the optimal solution of the multi-parameter programming model, divide the effective constraints and the ineffective constraints to rewrite the equivalent optimality conditions;
[0033] Step 32: The optimal solution x in the equivalent optimality condition * Expressed as a linear function of the planning parameter w;
[0034] Step 33: Based on the concept of optimal partitioning, the space W where the planning parameter w is located is divided into several critical regions; when the planning parameter w changes in any bounded closed space W, the space W is divided into several critical regions; each critical region uniquely corresponds to a combination of a set of effective constraints and ineffective constraints;
[0035] Step 34: Study the feasible domain of steady-state transmission of the interconnection line, obtain the critical domain, and then use the union of all critical domains as the feasible domain of steady-state transmission of the regional power system interconnection line to transform the optimization space of the optimization problem.
[0036] Furthermore, the step 31 comprises:
[0037] The optimal solution of the multi-parameter planning model is defined as x*, and the effective constraints and ineffective constraints are expressed as:
[0038] The constraints in effect are:
[0039] A J x * =B J w+C (7)
[0040] Invalid constraints:
[0041]
[0042] Where: subscripts J and J C Subscripts for active constraints and inactive constraints respectively;
[0043] Consider the optimality conditions of multi-parameter programming models, including stationary point conditions, complementary relaxation conditions, primal feasibility conditions, and dual feasibility conditions;
[0044] The stationary conditions are:
[0045] C+A T λ=0 (9)
[0046] Among them, λ is the dual multiplier vector of the constraint condition;
[0047] The complementary relaxation condition is:
[0048] λ⊥(Ax-Bw-C)=0 (10)
[0049] Where: ⊥ is the symbol of the orthogonal operator;
[0050] The original feasibility conditions are:
[0051] Ax-Bw-C≤0 (11)
[0052] The dual feasibility condition is:
[0053] λ≥0 (12)
[0054] If the given parameter w = w i , we can obtain the optimal solution x*, the constraints that work and the constraints that do not work; at this point, the optimality condition can be equivalently rewritten as:
[0055]
[0056] In the formula, λ J and λ K are the dual multiplier vectors for active and inactive constraints, respectively.
[0057] Further, the step 32 comprises:
[0058] A J is a full rank matrix, and the optimal solution x * It is expressed as a linear function of the planning parameter w, that is:
[0059]
[0060] Among them, G xi 、F xiis the coefficient of the linear function of the planning parameter w; when the optimization problem degenerates, it does not have a unique solution. The consistent bond breaking criterion is used to ensure the uniqueness of the calculation result, and then obtain formula (15);
[0061] Substituting formula (13) into formula (12), we can obtain:
[0062]
[0063]
[0064] Substituting equation (14) or (15) into the objective function, we can obtain:
[0065]
[0066] Where: z * is the optimal objective function value;
[0067] When the planning parameter w satisfies formula (15), the optimality condition (13) holds. Formula (15) is a convex polyhedron composed of multiple inequality constraints, namely the critical domain. On each critical domain, the optimal solution x is obtained. * And the optimal objective function value z * The mapping relationship with the planning parameter w.
[0068] Further, the step 34 includes:
[0069] Step 341: Obtain the critical region, and use the union of all critical regions as the feasible region for steady-state transmission of the regional power system tie line;
[0070] Step 342: Based on the feasible region of steady-state transmission of the tie line, obtain the critical region W i , the feasible region of steady-state transmission of the tie line W F and the optimal objective function;
[0071] Step 343: Based on the critical region W i , the feasible region of steady-state transmission of the tie line W F And the optimal objective function in the feasible domain of steady-state transmission of the tie line is * (w), the optimization space of the optimization problem is transformed from x to w.
[0072] Furthermore, the step 341 includes:
[0073] Define the i-th critical region W of the optimization problem i for:
[0074]
[0075] Where: n is the number of critical regions; G wi and Fxi It can be obtained by formula (15);
[0076] Each critical region W j are all convex domains, and any two critical domains W j With W k Mutually exclusive, j, k = 1, 2, 3, ..., n, j ≠ k, there is no hole between two adjacent critical regions, and the feasible domain of planning parameters W that makes the optimization problem feasible F For all critical regions W j The union of F =W1∪W2∪…∪W n , recorded as:
[0077]
[0078] Where: coefficient matrix G w and coefficient vector F w It can be obtained by merging all critical regions;
[0079] The optimal objective function z * (w) is the feasible domain W F A continuous piecewise convex function on the critical region W j Up, z * (w) is a linear function of w
[0080] Based on formulas (17) and (18), the critical region is obtained by enumerating the types of constraints that work and those that do not work, and then the union of all critical regions is used as the feasible region W of the steady-state transmission of the regional power system tie line. F ;
[0081] The step 342 includes:
[0082] The i-th critical region W i The analytical expression of G wi w≤F wi , where G wi and F wi is the parameter to be solved;
[0083] Feasible region of steady-state transmission of tie line W F The analytical expression of G w w≤F w , where G w and F w is the parameter to be solved, obtained by the union of all critical regions;
[0084] The optimal solution x*(w) is:
[0085]
[0086] Where: G xi and F xi is the parameter to be solved;
[0087] The optimal objective function z*(w) is:
[0088]
[0089] Where: G zi and F zi is the parameter to be solved;
[0090] The step 343 includes:
[0091] By introducing a 0-1 integer variable k i , the optimization problem can be rewritten as follows:
[0092]
[0093] Since the optimal objective function z * (w) is a piecewise function on the feasible domain of steady-state transmission of the tie line, and is expressed by the integer variable k i , to determine whether the optimal solution is in the i-th critical region, where k i =1 means selecting the i-th critical region, k i =0 means that the i-th critical region is not selected; the constraint ensures that the optimal solution is only in one critical region.
[0094] Furthermore, according to z * (w) is the feasible region W of steady-state transmission of the tie line F Based on the continuous convex function characteristics of the above, the continuous variable y is introduced to represent the minimum operating cost of the regional power system. Based on the convex relaxation idea, the optimization problem is equivalently transformed into the following linear programming problem:
[0095]
[0096] An equivalent solution is obtained in the feasible domain of steady-state transmission of the interconnection line through a multi-parameter planning model.
[0097] Furthermore, the quantitative index E is defined as the transmission capacity of the regional power system to evaluate the flexible regulation capability of multi-energy loads:
[0098]
[0099] Among them, P o,t is the active power exchanged by the boundary nodes of the multi-energy system in time period t, that is, w, Δt is the time difference, and T is the time period;
[0100] Definition E max The maximum transmission capacity of the regional power system is:
[0101]
[0102] Assuming that the output power of the adjustable units in the region is constant, max As standard energy storage.
[0103] Due to the adoption of the above technical solution, the present invention has the following advantages: based on the multi-parameter planning theory, a new method for determining the external characteristics of the flexible adjustment capacity of multi-energy loads is proposed, and the quantitative index of the external characteristics of the flexible adjustment capacity of multi-energy loads is set as the power of the regional power system interconnection line, thereby providing an accurate boundary for the external characteristics of the flexible adjustment capacity of multi-energy loads; after using the multi-parameter planning theory to characterize the external characteristics of the flexible adjustment capacity of multi-energy loads, a quantitative index regional power system transmission capacity is established to quantitatively characterize the regional flexible adjustment capacity. In order to facilitate the grid dispatching agency to formulate a dispatching plan, the flexible load adjustment capacity in the regional power system is evaluated with unit energy storage as a reference object, thereby providing a decision-making basis for the dispatching agency. BRIEF DESCRIPTION OF THE DRAWINGS
[0104] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments recorded in the embodiments of the present invention. For ordinary technicians in this field, other drawings can also be obtained based on these drawings.
[0105] Figure 1 A schematic diagram of a calculation idea based on multi-parameter planning theory according to an embodiment of the present invention;
[0106] Figure 2 It is a schematic diagram of a calculation flow of a feasible region of steady-state transmission of a tie line based on multi-parameter planning theory according to an embodiment of the present invention;
[0107] Figure 3(a) is a representation of the flexible regulation capability of multi-energy loads in a regional power system in three time periods with a single tie line (tie line power feasible space);
[0108] Figure 3(b) is another representation of the flexible regulation capability of multi-energy loads in a regional power system in three time periods of a single tie line (tie line power feasible space);
[0109] FIG4( a ) is a schematic diagram showing the transmission capacity of a regional power system;
[0110] FIG4( b ) is another schematic diagram showing the transmission capacity of a regional power system. DETAILED DESCRIPTION
[0111] The present invention is further described in conjunction with the accompanying drawings and embodiments, and the described embodiments are only a part of the embodiments of the present invention, rather than all the embodiments. All other embodiments obtained by ordinary technicians in this field should fall within the scope of protection of the embodiments of the present invention.
[0112] The present invention aims to provide a method for approximating the boundary of the flexible adjustment capability of the load-side resource aggregation response subject under the premise of taking into account the security constraints of the regional power grid, so as to solve the problem of practical application difficulties in the prior art due to the cumbersome characterization calculation technology.
[0113] See also Figure 1 and Figure 2 , the technical solution adopted in this embodiment is as follows:
[0114] Construct an operation economic dispatch model with load-side resource aggregation response subject; the constraints of the operation economic dispatch model include regional power grid security constraints, branch power flow constraints, dispatch operation constraints, interconnection line capacity constraints, energy storage device related constraints and air conditioning model related constraints;
[0115] The boundary coupling variables in the reconstructed economic dispatch model are regarded as variable planning parameters, and a multi-parameter planning model is established;
[0116] Use "optimal partitioning" and "critical region" to solve multi-parameter planning models;
[0117] On the basis of solving the feasible domain of the interconnection line coupling variables that meet the constraints of the regional power system dispatch decision, a quantitative indicator of regional power system transmission quantity is established to quantitatively describe the transmission capacity of the regional power system, that is, the flexible load regulation capacity within the region.
[0118] Taking 300MW energy storage as the standard energy storage, the quantitative indicator of regional power system transmission power is used to calculate the impact of standard energy storage on the flexible adjustment capability of the regional power system, which is used as a reference standard for evaluating other flexible loads in the regional power system.
[0119] In one embodiment, the objective function of the operation economic dispatch model including the load-side resource aggregation response subject is:
[0120]
[0121] Where Z is the power system operating cost; c G,t is the quotation of regional power grid unit, P G,t is the active power vector of the adjustable units of the virtual power plant in period t, x t Standard form of optimization variables for scheduling models.
[0122] The regional power grid security constraints are:
[0123] P N,t =e G P G,t +e dis P dis,t -e q P q,t -e ch P ch,t -e o P o,t (2)
[0124] Among them, P N,t is the active power injected into the node, e G is the correlation matrix between the adjustable units and each node; dis , e ch , e q , e o are the association matrices of energy storage discharging state, energy storage charging state, air conditioning load power consumption, multi-energy system gateway nodes and each node; P G,t is the active power vector of the adjustable units of the virtual power plant in period t; q,t P is the cooling power of the air conditioner during period t; dis,t , P ch,t are the discharging active power vector and charging active power vector of the energy storage system in period t respectively; o,t is the active power exchanged by the boundary nodes of the multi-energy system in time period t;
[0125] The branch power flow constraints, dispatching operation constraints, and tie line capacity constraints are as follows:
[0126]
[0127] Among them, P L,t is the line active power vector in period t; P L,min , P L,max They are the upper and lower limits of the line active power respectively; They are the upper and lower limits of the active power of the adjustable units of the virtual power plant in time period t respectively; G is the upper and lower limits of active power exchanged by the boundary nodes of the multi-energy system in time period t; θ is the node voltage phase angle relationship matrix; θ t is the node voltage phase angle during time period t;
[0128] There are energy storage and air conditioning temperature control loads in the regional power grid. The relevant constraints of the energy storage device are as follows:
[0129]
[0130] in, are the discharge active power vector and charging active power vector of the energy storage system at node i in time period t, as its upper limit; is the state of charge of the energy storage device at time i, is its upper limit; α is the charging efficiency; β is the discharging efficiency; is the charge state at the initial moment, is the charge state at time T.
[0131] The constraints related to the air conditioning model are as follows:
[0132]
[0133] Among them, T in,t is the indoor temperature during period t; T out,t is the outdoor temperature during period t; k is the temperature heat coefficient; τ is the building heat dissipation coefficient; T min , T max are the upper and lower limits of acceptable room temperature respectively; R is the equivalent thermal resistance of the building; C air is the indoor heat capacity of the building.
[0134] In one embodiment, the economic dispatch problem with energy storage can relax the complementary constraint of energy storage charging and discharging states without affecting the optimality of the original model. The relaxed optimization model (1)-(5) of the i-th regional power grid can be reconstructed as:
[0135] Where:
[0136] A, B and C are known constant matrices determined by equations (1)-(5).
[0137] In one embodiment, the boundary coupling variable w in the reconstructed economic dispatch model is regarded as a variable planning parameter, and equation (6) is a typical multi-parameter linear programming problem. By solving the above multi-parameter linear programming problem, all feasible combinations of tie line coupling variables can be found, and the feasible domain of steady-state transmission of the tie line can be determined.
[0138] In one embodiment, the above model is solved using “optimal segmentation” and “critical region”.
[0139] The "optimal segmentation" and "critical region" solutions to the above model mainly include the following steps:
[0140] ① Define the optimal solution of the linear programming model, divide the constraints that work and the constraints that do not work, and rewrite the equivalent optimality conditions.
[0141] The optimal solution of the linear programming model is defined as x*, and the constraints that work and do not work can be expressed as:
[0142] The constraints in effect are:
[0143] AJ x * =B J w+C (7)
[0144] Invalid constraints:
[0145] A J C x * J C w+C (8)
[0146] Where: subscripts J and J C Subscripts for active and inactive constraints respectively.
[0147] The optimality conditions of the linear programming model are considered, including stationary point conditions, complementary slack conditions, primal feasibility conditions and dual feasibility conditions.
[0148] The stationary conditions are:
[0149] C+A T λ=0 (9)
[0150] Among them, λ is the dual multiplier vector of the constraint condition;
[0151] The complementary relaxation condition is:
[0152] λ⊥(Ax-Bw-C)=0 (10)
[0153] Where: ⊥ is the symbol of the orthogonal operator;
[0154] The original feasibility conditions are:
[0155] Ax-Bw-C≤0 (11)
[0156] The dual feasibility condition is:
[0157] λ≥0 (12)
[0158] In one embodiment, if the given parameter w=w i , by solving the optimization problem, we can obtain the optimal solution x*, the effective constraints and the ineffective constraints. At this time, the optimality condition can be equivalently rewritten as:
[0159]
[0160] In the formula, λ J and λ K are the dual multiplier vectors for active and inactive constraints, respectively.
[0161] ② The optimal solution x * It is expressed as a linear function of the planning parameter w.
[0162] In the linear optimization problem of the present invention, there is no degeneration of the original problem or the dual problem, and there is a unique optimal solution. In other words, A J is a full rank matrix (i.e., the rank of the matrix is the same as x * Therefore, the optimal solution x * It is expressed as a linear function of the planning parameter w, that is:
[0163]
[0164] Among them, G xi 、F xi is the coefficient of the linear function of the planning parameter w. When the optimization problem degenerates and does not have a unique solution, the consistent bond breaking criterion is used to ensure the uniqueness of the calculation result, and then obtain formula (15);
[0165] Substituting formula (13) into formula (12), we can obtain:
[0166]
[0167] Substituting equation (14) or (15) into the objective function, we can obtain:
[0168]
[0169] Where: z * is the optimal objective function value;
[0170] In summary, when the planning parameter w satisfies formula (15), the optimality condition (13) holds. Formula (15) is a convex polyhedron composed of multiple inequality constraints, which is mathematically called a critical domain. On each critical domain, the optimal solution x can be obtained. * And the optimal objective function value z * The mapping relationship with the planning parameter w.
[0171] ③ Based on the concept of optimal partitioning, the space W where the planning parameter w is located is divided into several critical regions.
[0172] When the planning parameter w changes in a bounded closed space W (such as the space formed by the upper and lower limits of the tie line coupling variables), the space W can be divided into several critical regions based on the concept of optimal partitioning. Each critical region uniquely corresponds to a combination of a set of effective constraints and ineffective constraints.
[0173] ④ Study the feasible domain of steady-state transmission of interconnection lines, obtain the critical domain, and then use the union of all critical domains as the feasible domain of steady-state transmission of regional power system interconnection lines, transform the optimization space of the optimization problem from x to w, so that the original optimization problem can be equivalently rewritten.
[0174] Based on the following properties 2.1 and 2.2, the feasible domain of steady-state transmission of the tie line and the operating cost on the feasible domain of steady-state transmission of the tie line are studied.
[0175] Property 2.1: Define the i-th critical region W of the optimization problem i for:
[0176]
[0177] Where: n is the number of critical regions; G wi and F xi It can be obtained by formula (15);
[0178] Each critical region W j are all convex domains, and any two critical domains W j With W k (j, k = 1, 2, 3, ..., n, j ≠ k) are mutually exclusive, and there is no hole between two adjacent critical regions. The feasible domain W of the planning parameters that make the optimization problem feasible F For all critical regions W j The union of F =W1∪W2∪…∪W n , recorded as:
[0179]
[0180] Where: coefficient matrix G w and coefficient vector F w It can be obtained by merging all critical regions. This concludes the description of Property 2.1.
[0181] Property 2.2: Optimal objective function z * (w) is the feasible domain W F A continuous piecewise convex function on . In particular, in the critical region W j Up, z * (w) is a linear function of w This concludes the description of Property 2.2.
[0182] Based on properties 2.1 and 2.2, the critical region is obtained by enumerating the types of constraints that work and those that do not work, and then the union of all critical regions is used as the feasible region W of the steady-state transmission of the regional power system tie line. F At the same time, the optimal economic dispatch cost can also be expressed as a continuous piecewise convex function of the tie-line coupling variables.
[0183] Based on the calculation of the feasible region of steady-state transmission of the tie line, we can get:
[0184] (1) The i-th critical region W i The analytical expression of G wi w≤F wi, where G wi and F wi are the parameters to be solved.
[0185] (2) Feasible region W of steady-state transmission of tie lines F The analytical expression of G w w≤F w , where G w and F w is the required parameter, which can be obtained by the union of all critical regions.
[0186] (3) The optimal solution x*(w) is:
[0187]
[0188] Where: G xi and F xi (i=1,2,…,n) are the parameters to be solved.
[0189] (4) The optimal objective function z*(w) is:
[0190]
[0191] Where: G zi and F zi (i=1,2,…,n) are the parameters to be solved.
[0192] In one embodiment, based on the critical region W i , the feasible region of steady-state transmission of the tie line W F And the optimal objective function in the feasible domain of steady-state transmission of the tie line is * (w), the optimization space of the optimization problem can be transformed from x to w. By introducing a 0-1 integer variable k i (i=1,2,…,n), the optimization problem can be equivalently rewritten as the following optimization problem:
[0193]
[0194] In one embodiment, in order to ensure the convergence and optimality of the optimization problem based on the feasible region of steady-state transmission of the tie line, according to z * (w) is the feasible region W of steady-state transmission of the tie line F Based on the continuous convex function characteristics of the above, the continuous variable y is introduced to represent the minimum operating cost of the regional power system. Based on the convex relaxation idea, the optimization problem is equivalently transformed into the following linear programming problem:
[0195]
[0196]
[0197] In summary, the economic dispatch optimization model of the regional power system can be equivalently solved in the feasible domain of steady-state transmission of the interconnection line through the proposed model, which provides a model basis for realizing the hierarchical dispatch of the power system based on the feasible domain of steady-state transmission of the interconnection line.
[0198] In one embodiment, the flexible load regulation capability characterization based on the multi-parameter planning method is essentially a characterization of the transmission capacity of the regional power system. This indicator is expressed as a multidimensional convex polyhedron in multiple time periods of a single interconnection line, and the dimension is determined by the number of time periods in the multiple time periods. The representation form of the multidimensional convex polyhedron is relatively complex, and it is necessary to establish a new quantitative indicator to evaluate the flexible regulation capability of multi-energy loads. Define E as the transmission capacity of the regional power system:
[0199]
[0200] Among them, P o,t is the active power exchanged by the boundary nodes of the multi-energy system in time period t, that is, w, Δt is the time difference, and T is the time period.
[0201] When E≥0, the regional power system as a whole transmits energy to the outside, and the generators, energy storage and other equipment within the regional power system fully meet the regional load requirements. The larger the E value, the greater the regional power system's external transmission capacity, and the better the effect of reducing unnecessary electricity consumption through flexible adjustment capabilities; when E<0, when the regional power system as a whole absorbs energy from the outside, the generators, energy storage and other equipment within the region cannot meet the regional load requirements. The smaller the E value, the more external energy the regional power system receives, which damages the stability of the power system and brings huge negative benefits to environmental protection.
[0202] Definition E max The maximum transmission capacity of the regional power system is:
[0203]
[0204] Assuming that the output power of adjustable units in the region is constant, E max To characterize the indicators of load regulation of regional power systems, including energy storage, electric vehicles, air conditioning loads, etc., this invention mainly studies the flexible regulation capability of air conditioning temperature control loads.
[0205] In one embodiment, when the staff of the power grid dispatching organization actually formulates the dispatching plan, the common equipment such as the units, energy storage equipment, and fixed loads are easier for the dispatching staff to be familiar with than the specific values. Therefore, according to the equivalence of different flexible load regulation capabilities in the regional power grid, the energy storage equipment with a maximum capacity of 300MW is used as the unit indicator for evaluating different flexible load regulation capabilities.
[0206] For ease of understanding, the present invention provides a more specific embodiment:
[0207] (1) Test system
[0208] A modified IEEE 9-node system is used as an example for testing. The system includes 3 generators, 1 standard energy storage, 1 central air conditioner and 3 other loads. Assuming that several generator systems with the same network topology but different operating states supply power to the same grid node, the total interconnection line transmission power of the node in each period is the flexible adjustment capability provided by the multi-energy load defined in the present invention to the power system.
[0209] The scenarios used for testing are described as follows:
[0210] S1: Configure standard energy storage, install central air conditioning, and set the minimum temperature to 23°C;
[0211] S2: standard energy storage configuration, no central air conditioning installed;
[0212] S3: No standard energy storage is configured, central air conditioning is installed, and the minimum temperature is set to 23°C;
[0213] S4: No standard energy storage is configured and no central air conditioning is installed.
[0214] Three examples were tested using the present invention:
[0215] M0: Compare the transmission capacity of the regional power system in the S1 and S3 scenarios, and obtain the effect of standard energy storage on the transmission capacity of the regional power system when air conditioning is installed.
[0216] M1: Compare the transmission capacity of the regional power system in the S2 and S4 scenarios to obtain the effect of standard energy storage on the transmission capacity of the regional power system when no air conditioning is installed.
[0217] M2: Based on the existing S3 scenario, the central air-conditioning temperature is gradually increased, and the changes in the transmission capacity of the regional power system under different air-conditioning temperature ranges are analyzed and compared to obtain the effect of the central air-conditioning temperature control load on the transmission capacity of the regional power system.
[0218] (2) Test results
[0219] According to the simulation results of four groups S1, S2, S3 and S4, the regulation effect of energy storage equivalent is obtained respectively, as shown in Table 1:
[0220] Table 1 Regulation effect of energy storage equivalent
[0221]
[0222] According to Table 1, without energy storage and air conditioning, the transmission capacity of the regional power system is 56.2607MWh; with energy storage but no air conditioning, the transmission capacity of the regional power system is 58.2607MWh; without energy storage but with air conditioning (the lowest temperature is 23°C), the transmission capacity of the regional power system is 48.5837MWh; with energy storage and air conditioning, the transmission capacity of the regional power system is 50.5837MWh. Therefore, it can be found that the impact of a single standard energy storage on the transmission capacity of the regional power system is 2MWh.
[0223] Based on the existing S3 scenario, the central air conditioning temperature is gradually increased. As the air conditioning temperature range changes, the transmission capacity of the regional power system will also change, which means that the flexible load adjustment capacity will also change. The relevant results are shown in Table 2:
[0224] Table 2 Correspondence between the change of air conditioning temperature range and the amount of electricity transmitted by the regional power system
[0225]
[0226]
[0227] The impact of a single standard energy storage on the transmission capacity of the regional power system is 2MWh, while the flexible adjustment capability of the air-conditioning temperature control load depends on the temperature: when the air-conditioning temperature range changes from 23℃~27℃ to 24℃~28℃, the regional power system transmission capacity increases by 1.0772, which is about 0.5386 units of energy storage effect; when the air-conditioning temperature range changes from 24℃~28℃ to 25℃~29℃ and when the air-conditioning temperature range changes from 25℃~29℃ to 26℃~30℃, the regional power system transmission capacity increases by 0.6954, which is about 0.34725 units of energy storage effect; when the air-conditioning temperature range changes from 25℃~29℃ to 26℃~30℃ , the amount of energy transmitted by the regional power system increased by 0.1064.0532 units of energy storage; when the air-conditioning temperature range changed from 23℃~27℃ to 26℃~30℃, the amount of energy transmitted by the regional power system increased by 1.8781, which was about 0.93905 units of energy storage; when the air-conditioning temperature range changed from 23℃~27℃ to 25℃~29℃, the amount of energy transmitted by the regional power system increased by 1.7717, which was about 0.88585 units of energy storage; it is not difficult to find that when the air-conditioning temperature is at a low level, the air-conditioning temperature is increased, and the adjustment ability of the temperature control load is obvious. As the air-conditioning temperature increases, the adjustment effect of the temperature control load weakens.
[0228] Figure 3(a) is a representation of the flexible regulation capability of multi-energy loads in a certain regional power system with a single interconnection line in three time periods (interconnection line power feasible space), and Figure 3(b) is another representation of the flexible regulation capability of multi-energy loads in a certain regional power system with a single interconnection line in three time periods (interconnection line power feasible space); Figure 4(a) is a schematic diagram of the transmission capability representation of a regional power system, and Figure 4(b) is another schematic diagram of the transmission capability representation of a regional power system.
[0229] In summary, based on the multi-parameter planning theory, the present invention proposes a new method for determining the external characteristics of the flexible capacity of multi-energy loads, and defines the indicator for quantifying the external characteristics of the flexible adjustment capacity of multi-energy loads as the regional power system interconnection line power. Considering the safety constraints such as the balance of the interconnected power grid flow, the generator capacity and the branch limit transmission power, an accurate flexible adjustment capacity boundary is provided for the multi-energy load. After using a mathematical model to characterize the external characteristics of the adjustment capacity of the multi-energy load, in order to further highlight the regulating role of the air-conditioning load in the multi-energy load of the regional power system, an evaluation index for the external characteristics of the adjustment capacity of the air-conditioning load is established, and the air-conditioning temperature control load adjustment capacity is evaluated with common energy storage as a reference object, thereby providing a basis for the decision-making of the dispatching agency.
[0230] According to the results and comparison of the present invention, the following conclusions are drawn:
[0231] (1) The flexible regulation capability of multi-energy loads established by the present invention includes output units such as thermal power, hydropower, and renewable energy, and flexible load regulation resources such as energy storage and air-conditioning loads, with a wide coverage range. At the same time, other flexible load forms such as electric vehicles can be added, and the applicability is strong.
[0232] (2) The quantitative evaluation index of flexible regulation capacity established in this paper, namely the transmission capacity of the regional power system, can quantitatively evaluate the regulation effect of various flexibility resources and provide a basis for demand response.
[0233] (3) In order to facilitate the dispatching agency to formulate dispatching plans, this paper takes 300MW standard energy storage as a reference object to evaluate the air conditioning temperature control load regulation capability, which is convenient for the dispatching agency to formulate plans. At the same time, it is found that the temperature control load regulation effect of the central air conditioning in the region weakens as the temperature increases.
[0234] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the above embodiments, ordinary technicians in the relevant field should understand that the specific implementation methods of the present invention can still be modified or replaced by equivalents. Any modification or equivalent replacement that does not depart from the spirit and scope of the present invention should be covered within the scope of protection of the claims of the present invention.
Claims
1. A method for approximating the boundary of flexible load regulation capability, characterized in that: include: Step 1: Construct an operation economic dispatch model containing the load-side resource aggregation response subject; the constraints of the operation economic dispatch model include regional power grid security constraints, branch power flow constraints, dispatch operation constraints, interconnection line capacity constraints, energy storage device related constraints and air conditioning model related constraints; Step 2: Treat the boundary coupling variables in the reconstructed economic dispatch model as variable planning parameters and establish a multi-parameter planning model; Step 3: Use "optimal segmentation" and "critical region" to solve the multi-parameter planning model to find all feasible combinations of tie line coupling variables and determine the feasible region of steady-state transmission of the tie line; Step 4: Use the amount of electricity transmitted by the regional power system as a quantitative indicator to quantitatively describe the transmission capacity of the regional power system, that is, the flexibility load regulation capacity within the region; set standard energy storage, use quantitative indicators to calculate the impact of standard energy storage on the flexible regulation capacity of the regional power system, and use it as a reference standard for evaluating other flexible loads in the regional power system.
2. The method according to claim 1, characterized in that The step 1 comprises: The objective function of the operation economic dispatch model containing the load-side resource aggregation response subject is: Where Z is the power system operating cost; c G,t is the quotation of regional power grid unit, P G,t is the active power vector of the adjustable units of the virtual power plant in period t, x t Standard forms for optimizing variables in scheduling models; The regional power grid security constraints are: P N,t =e G P G,t +e dis P dis,t -e q P q,t -e ch P ch,t -e o P o,t (2) Among them, P N,t is the active power injected into the node, e G is the correlation matrix between the adjustable units and each node; e dis , e ch , e q , e o are the association matrices of energy storage discharging state, energy storage charging state, air conditioning load power consumption, multi-energy system gateway nodes and each node; P G,t is the active power vector of the adjustable units of the virtual power plant in period t; q,t P is the cooling power of the air conditioner during period t; dis,t , P ch,t are the discharging active power vector and charging active power vector of the energy storage system in period t respectively; o,t is the active power exchanged by the boundary nodes of the multi-energy system in time period t; The branch power flow constraints, dispatching operation constraints, and tie line capacity constraints are as follows: Among them, P L,t is the line active power vector in period t; P L,min , P L,max They are the upper and lower limits of the line active power respectively; They are the upper and lower limits of the active power of the adjustable units of the virtual power plant in time period t respectively; G is the upper and lower limits of active power exchanged by the boundary nodes of the multi-energy system in time period t; θ is the node voltage phase angle relationship matrix; θ t is the node voltage phase angle during time period t; There are energy storage and air conditioning temperature control loads in the regional power grid. The relevant constraints of the energy storage device are as follows: in, are the discharge active power vector and charging active power vector of the energy storage system at node i in time period t, as its upper limit; is the state of charge of the energy storage device at time i, is its upper limit; α is the charging efficiency; β is the discharging efficiency; is the charge state at the initial moment, is the charge state at time T; The constraints related to the air conditioning model are as follows: Among them, T in,t is the indoor temperature during period t; T out,t is the outdoor temperature during period t; k is the temperature heat coefficient; τ is the building heat dissipation coefficient; T min , T max are the upper and lower limits of acceptable room temperature respectively; R is the equivalent thermal resistance of the building; C air is the indoor heat capacity of the building.
3. The method according to claim 1, characterized in that The step 2 comprises: Based on formulas (1) to (5), the reconstructed economic dispatch model of the i-th regional power grid is obtained after relaxation: Where: A, B and C are known constant matrices determined by equations (1) to (5); The boundary coupling variable w in the reconstructed economic dispatch model is regarded as a variable planning parameter, and equation (6) is a typical multi-parameter planning model established.
4. The method according to claim 1, characterized in that: The step 3 comprises: Step 31: define the optimal solution of the multi-parameter programming model, divide the effective constraints and the ineffective constraints to rewrite the equivalent optimality conditions; Step 32: The optimal solution x in the equivalent optimality condition * Expressed as a linear function of the planning parameter w; Step 33: Based on the concept of optimal partitioning, the space W where the planning parameter w is located is divided into several critical regions; when the planning parameter w changes in any bounded closed space W, the space W is divided into several critical regions; each critical region uniquely corresponds to a combination of a set of effective constraints and ineffective constraints; Step 34: Study the feasible domain of steady-state transmission of the interconnection line, obtain the critical domain, and then use the union of all critical domains as the feasible domain of steady-state transmission of the regional power system interconnection line to transform the optimization space of the optimization problem.
5. The method according to claim 4, characterized in that The step 31 comprises: The optimal solution of the multi-parameter planning model is defined as x*, and the effective constraints and ineffective constraints are expressed as: The constraints in effect are: A J x * =B J w+C (7) Invalid constraints: A J cx * <B J cw+C (8) Where: subscripts J and J C Subscripts for active constraints and inactive constraints respectively; Consider the optimality conditions of multi-parameter programming models, including stationary point conditions, complementary relaxation conditions, primal feasibility conditions, and dual feasibility conditions; The stationary conditions are: C+A T λ=0 (9)where λ is the dual multiplier vector of the constraint condition; The complementary relaxation condition is: λ⊥(Ax-Bw-C)=0 (10) Where: ⊥ is the symbol of the orthogonal operator; The original feasibility conditions are: Ax-Bw-C≤0 (11) The dual feasibility condition is: λ≥0 (12) If the given parameter w = w i , we can obtain the optimal solution x*, the constraints that work and the constraints that do not work; at this point, the optimality condition can be equivalently rewritten as: In the formula, λ J and λ K are the dual multiplier vectors for the active and inactive constraints, respectively.
6. The method according to claim 5, characterized in that The step 32 comprises: A J is a full rank matrix, and the optimal solution x * It is expressed as a linear function of the planning parameter w, that is: Among them, G xi 、F xi is the coefficient of the linear function of the planning parameter w; when the optimization problem degenerates, it does not have a unique solution. The consistent bond breaking criterion is used to ensure the uniqueness of the calculation result, and then obtain formula (15); Substituting formula (13) into formula (12), we can obtain: Substituting equation (14) or (15) into the objective function, we can obtain: Where: z * is the optimal objective function value; When the planning parameter w satisfies formula (15), the optimality condition (13) holds. Formula (15) is a convex polyhedron composed of multiple inequality constraints, namely the critical domain. On each critical domain, the optimal solution x is obtained. * And the optimal objective function value z * The mapping relationship with the planning parameter w.
7. The method according to claim 6, characterized in that The step 34 comprises: Step 341: Obtain the critical region, and use the union of all critical regions as the feasible region for steady-state transmission of the regional power system tie line; Step 342: Based on the feasible region of steady-state transmission of the tie line, obtain the critical region W i , the feasible region of steady-state transmission of the tie line W F and the optimal objective function; Step 343: Based on the critical region W i , the feasible region of steady-state transmission of the tie line W F And the optimal objective function in the feasible domain of steady-state transmission of the tie line is * (w), the optimization space of the optimization problem is transformed from x to w.
8. The method according to claim 7, characterized in that The step 341 includes: Define the i-th critical region W of the optimization problem i for: Where: n is the number of critical regions; G wi and F xi It can be obtained by formula (15); Each critical region W j are all convex domains, and any two critical domains W j With W k Mutually exclusive, j, k = 1, 2, 3, ..., n, j ≠ k, there is no hole between two adjacent critical regions, and the feasible domain of planning parameters W that makes the optimization problem feasible F For all critical regions W j The union of F =W1∪W2∪…∪W n , recorded as: Where: coefficient matrix G w and coefficient vector F w It can be obtained by merging all critical regions; The optimal objective function z * (w) is the feasible domain W F A continuous piecewise convex function on the critical region W j Up, z * (w) is a linear function of w Based on formulas (17) and (18), the critical region is obtained by enumerating the types of constraints that work and those that do not work, and then the union of all critical regions is used as the feasible region W of the steady-state transmission of the regional power system tie line. F ; The step 342 includes: The i-th critical region W i The analytical expression of G wi w≤F wi , where G wi and F wi is the parameter to be solved; Feasible region of steady-state transmission of tie line W F The analytical expression of G w w≤F w , where G w and F w is the parameter to be solved, obtained by the union of all critical regions; The optimal solution x*(w) is: Where: G xi and F xi is the parameter to be solved; The optimal objective function z*(w) is: Where: G zi and F zi is the parameter to be solved; The step 343 includes: By introducing a 0-1 integer variable k i , the optimization problem can be rewritten as follows: Since the optimal objective function z * (w) is a piecewise function on the feasible domain of steady-state transmission of the tie line, and is expressed by the integer variable k i , to determine whether the optimal solution is in the i-th critical region, where k i =1 means selecting the i-th critical region, k i =0 means that the i-th critical region is not selected; the constraint ensures that the optimal solution is only in one critical region.
9. The method according to claim 8, characterized in that According to z * (w) is the feasible region W of steady-state transmission of the tie line F Based on the continuous convex function characteristics of the above, the continuous variable y is introduced to represent the minimum operating cost of the regional power system. Based on the convex relaxation idea, the optimization problem is equivalently transformed into the following linear programming problem: An equivalent solution is obtained in the feasible domain of steady-state transmission of the interconnection line through a multi-parameter planning model.
10. The method according to claim 9, characterized in that The quantitative index E is defined as the transmission capacity of the regional power system to evaluate the flexible regulation capability of multi-energy loads: Among them, P o,t is the active power exchanged by the boundary nodes of the multi-energy system in time period t, that is, w, Δt is the time difference, and T is the time period; Definition E max The maximum transmission capacity of the regional power system is: Assuming that the output power of the adjustable units in the region is constant, max As standard energy storage.
Citation Information
Cited By
Load flexibility value evaluation method based on vertex search method
CN119623973A