Construction method for steel-concrete combined section of railway hybrid beam with steel truss
By using steel trusses and steel cantilever beams as temporary fixing devices in railway bridge construction, the problem of steel beam hoisting height deviation was solved, enabling precise positioning and stable connection of the steel-concrete composite section, reducing deformation, and forming a solid steel-concrete composite section.
Patent Information
- Application Number
- CN202411348653.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-26
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2044-09-26
AI Technical Summary
In existing technologies, during the construction of steel-concrete composite sections, there is a deviation between the steel beams after they are hoisted into place and the design height, resulting in a height difference between the concrete beams and the steel beams, which affects the transmission of internal forces and is prone to causing large deformations, especially in railway bridges.
Steel trusses and steel cantilever beams are used as temporary fixing devices. The steel trusses are pre-embedded to the ends of the concrete beams. After the steel beams are hoisted to the design height, they are fixed by the steel trusses and steel cantilever beams to form a stable steel-concrete composite section structure. After the wet joint section concrete is poured, the steel trusses remain in the concrete as permanent devices.
This improved the accuracy of steel beam hoisting and positioning, reduced the height difference between the concrete beam and the steel beam, avoided large deformations, and formed a stable steel-concrete composite section structure.
Smart Images

Figure CN118932880A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of railway bridge construction, and in particular relates to a construction method for a steel-concrete combined section of a railway hybrid beam with a steel truss. Background Art
[0002] At present, the construction method of the steel-concrete combined section of the highway hybrid beam bridge is to set up temporary steel components between the steel beam segment and the concrete segment. The steel components are not connected and are discretely distributed in space. During the construction of the steel-concrete combined section, there is often a problem that there is a slight deviation from the design height after the steel beam is hoisted into place. This causes a height difference between the concrete beam and the steel beam, which affects the transmission of internal forces. Therefore, before pouring the wet joint concrete, it is necessary to adjust the height of the steel beam through the hoisting system. This construction method is more likely to cause large deformation in the steel-concrete combined section with a relatively high beam height in the railway bridge. Therefore, there is an urgent need for a construction method for the steel-concrete combined section of a railway hybrid beam with a steel truss to solve the problem. Summary of the invention
[0003] The purpose of the present invention is to provide a method for constructing a steel-concrete combined section of a railway hybrid beam with a steel truss to solve the above-mentioned problem.
[0004] To achieve the above object, the present invention provides the following solutions:
[0005] A construction method for a steel-concrete combined section of a railway hybrid beam with a steel truss comprises the following steps:
[0006] S1. Make steel trusses and steel cantilever beams;
[0007] S2. Before pouring the concrete beam, pre-embed the steel truss to the end of the concrete beam, pour the concrete beam and maintain it;
[0008] S3. After the concrete beam reaches the designed strength, the steel beam is hoisted to the designed height;
[0009] S4, fixing the steel beam to the concrete beam through the steel truss and the steel cantilever beam;
[0010] S5. Cast the joint between the concrete beam and the steel beam to form a wet joint section. After the wet joint section reaches the designed strength, the construction of the steel-concrete joint section is completed.
[0011] Preferably, in step S1, the steel truss is made up of chords, webs and node plates.
[0012] Preferably, in step S1, the steel cantilever beam is formed by splicing a plurality of I-beams end to end, and two adjacent I-beams are fixedly connected.
[0013] Preferably, in step S2, the outer formwork of the concrete beam is set up, the steel truss is placed at the designed position, the steel bars of the concrete beam are tied and ensure that the steel bars pass through the installation holes of the steel truss, prestressed pipes and prestressed steel bundles are installed, the inner formwork is built, and pouring and curing of concrete are started.
[0014] Preferably, in step S3, the steel beam is moved to a position directly below the position to be installed, and the steel beam is lifted by means of staged loading.
[0015] Preferably, during the lifting process of the steel beam, the symmetrical two sides of the top of the steel beam are loaded in stages according to the load graded loading of 20%→40%→60%→80%→100%, and whether there are any abnormal conditions during the loading process; the loads on the symmetrical two sides of the top of the steel beam are kept the same during the lifting process.
[0016] Preferably, in step S3, after the steel beam is lifted to the designed height, the position of the steel beam is fine-tuned, and the axis, elevation, transverse slope and longitudinal slope of the steel beam are reviewed and fine-tuned using a total station and a level to ensure that the assembled steel beam and the lifted steel beam are on the same plumb line up and down. After confirming that it meets the design and monitoring requirements, the steel truss is fixed to the steel beam so that the steel beam is supported on the concrete beam only by the steel truss.
[0017] Preferably, in step S3, the steel cantilever beam is accurately adjusted to the designed position, the tail end of the steel cantilever beam is fixed to the concrete beam by an anchoring device, the middle part of the steel cantilever beam is connected to the embedded ear plate on the concrete beam by a hinge support, the front end of the steel cantilever beam is connected to the steel beam by another hinge support, and the steel cantilever beam is locked so that the steel beam and the concrete beam form a firm and stable structure, so that the steel cantilever beam and the steel truss become the force-bearing structure for casting the wet joint.
[0018] Preferably, in step S5, formwork is supported at the wet joint position, steel bars are tied, prestressed pipes and prestressed steel strands are installed, concrete is poured and cured, and after the concrete of the wet joint reaches the designed strength, the formwork and the steel cantilever beam are removed, the prestressed steel strands are tensioned, and the construction is completed.
[0019] Compared with the prior art, the present invention has the following advantages and technical effects:
[0020] The present invention adopts steel cantilever beams and steel trusses as temporary fixing devices for the construction of steel-concrete joint sections, which greatly improves the accuracy of positioning the hoisted steel beams and reduces the height difference between the concrete beams and the steel beams. After pouring the wet joint concrete, the steel trusses are left in the concrete as permanent devices, and large deformation is not easy to occur between the concrete beams and the steel beams. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments are briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For those of ordinary skill in the art, other drawings can be obtained based on these drawings without creative labor:
[0022] Figure 1 This is a schematic diagram of pouring a cantilever concrete beam according to the present invention;
[0023] Figure 2 It is a schematic diagram of installing a steel truss before hoisting a steel beam according to the present invention;
[0024] Figure 3 This is a schematic diagram of the steel beam of the present invention being hoisted into place;
[0025] Figure 4 This is a schematic diagram of installing a steel cantilever beam according to the present invention;
[0026] Figure 5 This is a schematic diagram of pouring wet joint concrete according to the present invention;
[0027] Figure 6 Schematic diagram of completing the pouring of wet joint concrete and removing the formwork and steel cantilever beams in the present invention;
[0028] Figure 7 The cross-sectional view corresponding to the installation of the steel cantilever beam and the steel truss of the present invention;
[0029] Among them, 1. hanging basket; 11. hanging basket main truss; 12. hanging basket rear anchoring system; 13. hanging basket slide and walking system; 14. bottom formwork platform; 15. inner and outer formwork system; 16. hanging system; 2. bridge deck crane; 21. crane main truss; 22. lifting system; 23. crane rear anchoring system; 24. crane slide and walking system; 3. steel truss; 31. chord; 32. web member; 33. node plate; 4. steel cantilever beam; 41. anchoring device; 42. hinged support; 5. concrete beam; 6. steel beam; 7. steel-concrete combined section. DETAILED DESCRIPTION
[0030] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0031] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, the present invention is further described in detail below with reference to the accompanying drawings and specific embodiments.
[0032] Reference Figures 1 to 7 The present invention discloses a construction method for a steel-concrete combined section of a railway hybrid beam with a steel truss, comprising the following steps:
[0033] S1, manufacturing steel trusses 3 and steel cantilever beams 4;
[0034] S2. Before pouring the concrete beam 5, pre-embed the steel truss 3 to the end of the concrete beam 5, pour the concrete beam 5 and maintain it;
[0035] S3. After the concrete beam 5 reaches the designed strength, the steel beam 6 is hoisted to the designed height;
[0036] S4, fix the steel beam 6 and the concrete beam 5 through the steel truss 3 and the steel cantilever beam 4;
[0037] S5. Cast the joint between concrete beam 5 and steel beam 6 to form a wet joint section. After the wet joint section reaches the designed strength, the construction of the steel-concrete joint section is completed.
[0038] The present invention adopts steel cantilever beam 4 and steel truss 3 as temporary fixing devices for the construction of steel-concrete joint section, which greatly improves the accuracy of positioning of hoisted steel beams, and the height difference between concrete beam 5 and steel beam 6 is small; after pouring the wet joint concrete, steel truss 3 is left in the concrete as a permanent device, and it is not easy to produce large deformation between concrete beam 5 and steel beam 6.
[0039] According to a further optimization scheme, in step S1 , the steel truss 3 is made up of a chord 31 , a web member 32 and a node plate 33 .
[0040] The steel truss 3 is composed of a chord 31, a web 32 and a node plate 33. The chord 31 and the web 32 are preferably I20a channel steels. The node plate 33 is made of rectangular steel plates. The web 32 and the chord 31 are connected by three-sided fillet welds. The node plate 33 is divided into two types: a node plate with separate holes and a node plate without holes.
[0041] According to a further optimized solution, in step S1, the steel cantilever beam 4 is formed by splicing a number of I-beams end to end, and two adjacent I-beams are fixedly connected.
[0042] The steel cantilever beam 4 is formed by splicing two I80a I-beams, and the flanges of the two I-beams are connected by butt welding in the length direction.
[0043] To further optimize the solution, in step S2, set up the outer formwork of the concrete beam 5, place the steel truss 3 at the designed position, tie the steel bars of the concrete beam 5 and ensure that the steel bars pass through the installation holes of the steel truss 3, install the prestressed pipes and prestressed steel strands, build the inner formwork, and start pouring and curing concrete.
[0044] Before pouring the concrete beam 5 , the steel truss 3 is arranged at the end of the concrete beam 5 , and then the reinforcement of the concrete beam 5 and the installation of the prestressed duct are carried out, and the concrete beam 5 is poured using the hanging basket 1 .
[0045] The hanging basket 1 mainly includes a hanging basket main truss 11, a hanging basket rear anchoring system 12, a hanging basket slide and walking system 13 and a hanging system 16, and the formwork system includes a bottom formwork platform 14 and an inner and outer formwork system 15, and the inner and outer formwork system 15 includes an outer formwork and an inner formwork.
[0046] The hanging basket slide and walking system 13 are installed on the beam section that has been cast. After the hanging basket main truss 11 is moved to the specified position through the hanging basket slide and walking system 13, it is fixed by the hanging basket rear anchoring system 12, and the bottom formwork platform 14 is hoisted by the hanging system 16, so that the bottom formwork platform 14 is moved to the bottom of the concrete beam 5 that needs to be cast. The bottom formwork platform 14 is fixed to the beam section that has been cast during casting.
[0047] Before pouring the concrete beam 5, the outer formwork is first set up, and then the node plate 33 on the side with the hole of the steel truss 3 and the chord 31 and the web member 32 connected thereto are embedded in the designed position. Finally, the steel bars are tied and ensured to pass through the holes of the node plate 33 on the side with the hole of the steel truss 3, the prestressed pipes and prestressed steel strands are installed, the inner formwork is set up, and the pouring and curing of concrete begins.
[0048] To further optimize the solution, in step S3, the steel beam 6 is moved to just below the location to be installed, and the steel beam 6 is lifted by means of graded loading.
[0049] After the concrete beam 5 reaches sufficient strength, the hanging basket 1 is transformed into a bridge crane 2, wherein the hanging basket main truss 11 serves as the crane main truss 21, the hanging basket rear anchoring system 12 serves as the crane rear anchoring system 23, the hanging basket slide and walking system 13 serves as the crane slide and walking system 24, and the hanging system 16 serves as the lifting system 22.
[0050] Move the bottom mold platform 14 and the inner and outer mold system 15 away from the steel beam 6, and install the lifting hanger on the lifting system 22 and accurately position it. Use a beam transporter to transport the steel beam 6 of the steel-concrete joint section to be hoisted to the water platform directly below the bridge installation position. Set a lifting lug directly below the hanger and close to the web of the steel beam 6. The lifting lug is welded and fixed to the top plate of the steel beam 6. A stiffening plate is set at the position of the lifting lug on the web to strengthen it and weld it to the steel beam 6. Lower the lifting hanger, connect the hanger to the lifting lug of the steel beam, and start lifting the steel beam.
[0051] To further optimize the solution, during the lifting process of the steel beam 6, the symmetrical two sides of the top of the steel beam 6 are loaded in stages according to the load graded loading of 20% → 40% → 60% → 80% → 100%, and whether there are any abnormal conditions during the loading process; the loads on the symmetrical two sides of the top of the steel beam 6 are kept the same during the lifting process.
[0052] Two continuous jacks are arranged on the front upper crossbeam of the lifting system 22 near the main truss 21 of the crane as lifting devices for the combined section steel beam. During the lifting process, the loading should be graded (symmetrically on both sides), according to the load graded loading of 20% → 40% → 60% → 80% → 100%. The steel beam 6 and the lifting system 22 should be observed during the loading process, and loading can only be continued if there is no abnormality. During the lifting process, the loads applied at both ends should be kept the same to ensure that the steel beam 6 rises smoothly. The lifting system 22 consists of a lifting control system, a continuous jack, a lifting pressure sensor, a steel strand, a steel strand reel and a hoist. After lifting the steel beam to the designed height, temporarily lock the lifting system.
[0053] To further optimize the plan, in step S3, after the steel beam 6 is lifted to the designed height, the position of the steel beam 6 is fine-tuned, and the axis, elevation, transverse slope and longitudinal slope of the steel beam 6 are reviewed and fine-tuned using a total station and a level to ensure that the assembled steel beam 6 and the lifted steel beam 6 are on the same plumb line. After confirming that it meets the design and monitoring requirements, the steel truss 3 is fixed to the steel beam 6 so that the steel beam 6 is supported on the concrete beam 5 only by the steel truss 3.
[0054] The position of the steel beam 6 is fine-tuned to make the steel beam 6 reach the designed position, and then the steel beam 6 is connected to the steel truss 3. When installing the steel cantilever beam 4, the position of the steel beam is adjusted to ensure that the assembled steel beam 6 and the lifted steel beam 6 are on the same plumb line. The axis, elevation, transverse slope and longitudinal slope of the steel beam are checked with a total station and a level. If they do not meet the requirements, the lifting system 22 is used for fine adjustment. After confirming that the review or adjustment meets the design and monitoring requirements, the node plate of the steel truss 3 at one end of the steel beam 6 is welded to the T rib of the web of the steel beam 6 to complete the rigid connection between the steel beam 6 and the concrete beam 5.
[0055] To further optimize the solution, in step S3, the steel cantilever beam 4 is accurately adjusted to the designed position, the tail end of the steel cantilever beam 4 is fixed to the concrete beam 5 by the anchor device 41, the middle part of the steel cantilever beam 4 is connected to the embedded ear plate on the concrete beam 5 by the hinge support 42, and the front end of the steel cantilever beam 4 is connected to the steel beam 6 by another hinge support 42, and the steel cantilever beam 4 is locked, so that the steel beam 6 and the concrete beam 5 form a firm and stable structure, so that the steel cantilever beam 4 and the steel truss 3 become the force-bearing structure of the cast wet joint section.
[0056] The connection between the hanger of the lifting system 22 and the steel beam ear plate is untied, and the hanger of the bridge crane 2 is removed, so that the steel beam 6 is supported on the concrete beam 5 only by the steel truss 3.
[0057] Install the steel cantilever beam 4, and accurately adjust the steel cantilever beam 4 to the designed position during the installation process. The steel cantilever beam 4 is made of double-jointed I-beams, the rear end of which is fixed to the concrete beam 5 through an anchor device 41, the front end is connected to the steel beam 6 through a hinge support 42, and the middle is connected to the ear plate of the embedded part of the concrete beam 5 through another hinge support 42, and then the steel cantilever beam 4 is locked, so that the steel beam 6 and the concrete beam 5 form a more solid overall stable structure, so that the steel cantilever beam 4 and the steel truss 3 become the force-bearing structure for the subsequent pouring of wet joint concrete.
[0058] To further optimize the solution, in step S5, formwork is supported at the wet joint location, steel bars are tied, prestressed pipes and prestressed steel strands are installed, concrete is poured and cured, and after the concrete of the wet joint reaches the designed strength, the formwork and steel cantilever beam 4 are removed, the prestressed steel strands are tensioned, and the construction is completed.
[0059] The previously retreated bottom formwork platform 14 and inner and outer formwork system 15 are moved forward to the wet joint position, and the bottom formwork platform 14 and inner and outer formwork system 15 are modified to serve as a formwork system for pouring the wet joint. The formwork system is then locked onto the bottom plates of the concrete beam 5 and the steel beam 6, and the formwork system is connected to the bridge deck crane 2.
[0060] Tie the steel bars, install the prestressed pipes and prestressed steel strands, and start pouring wet joint concrete and curing concrete.
[0061] After the concrete of the wet joint section reaches the required strength, the formwork system and steel cantilever beam 4 are removed, the prestressed steel strands are tensioned, and the construction of the steel-concrete joint section is completed.
[0062] Compared with the prior art, the present invention has the following advantages:
[0063] (1) The steel cantilever beam 4 and the steel truss 3 are used as temporary fixing devices for the steel-concrete joint section construction, which greatly improves the positioning accuracy of the hoisting steel beam 6;
[0064] (2) For the pouring of the concrete beam 5, the outer formwork is first erected, and then the node plate with the opening on the side of the steel truss 3 and the connected chord 31 are embedded in the designed position. Finally, the steel bars are tied and ensured to pass through the holes of the node plate 33 of the steel truss 3. The prestressed pipes and steel strands are installed, the inner formwork is erected, and the pouring and curing of concrete begins.
[0065] (3) The steel truss 3 is composed of a chord 31, a web 32 and a node plate 33. The chord 31 and the web 32 are made of I20a channel steel and are used as the upper and lower chords and webs of the truss. The node plate 33 is divided into two types: a perforated steel plate and a non-perforated steel plate.
[0066] (4) The construction hanging basket 1 is mainly composed of a hanging basket main truss 11, a hanging basket rear anchoring system 12, a hanging basket slide and walking system 13, a bottom mold platform 14, an inner and outer mold system 15 and a hanging system 16.
[0067] (5) After the cantilever concrete beam 5 is poured, the hanging basket 1 is transformed into a bridge crane 2. The bridge crane 2 is mainly composed of a crane main truss 21, a lifting system 22, a crane rear anchoring system 23, a crane slide and walking system 24, a construction operation platform, etc.
[0068] (6) In order to prevent the lifting of steel beams from being affected, the inner and outer guide beams of the hanging basket 1, the bottom mold platform 14, and the inner and outer mold system 15 are moved backwards.
[0069] (7) Lower the lifting bracket and connect it to the lifting lug on the top plate of the steel beam 6. The lifting device of the lifting bracket is made of welded steel plates and connected as a whole by a pin shaft. A lifting lug is set just below the bracket and close to the web of the steel beam. The lifting lug is welded and fixed to the top plate of the steel beam 6 at the joint section. A stiffening plate is set to strengthen the top plate of the steel beam 6 at the lifting lug position at the side web and welded to the steel beam 6.
[0070] (8) The entire steel beam 6 lifting process is loaded in stages. During the process, the loads at both ends of the steel beam 6 should be kept the same to prevent tilting. After lifting, the steel beam 6 is on the same vertical line as the initial position of the steel beam 6.
[0071] (9) After accurately adjusting the steel beam 6 to the designed position, the node plate of the steel truss 3 at one end inside the steel beam 6 is welded to the corresponding steel beam web T rib, and the steel cantilever beam 4 is locked, so that the steel beam 6 and the concrete beam 5 form an integrally stable structure.
[0072] (10) The rear end of the steel cantilever beam 4 is fixed to the concrete beam 5 through an anchor device 41, the front end is connected to the steel beam 6 through a hinge support 42, and the middle is connected to the embedded ear plate of the concrete beam 5 through a hinge support 42.
[0073] (11) The steel cantilever beam 4 adopts a double-jointed I-beam section. After the steel-concrete joint section is completed, it can be dismantled and reused.
[0074] (12) The bottom formwork and inner and outer formworks for pouring concrete beam 5 are modified to form a formwork system for wet joint concrete.
[0075] (13) After pouring the wet joint concrete, the steel truss 3 is left in the concrete as a permanent device.
[0076] (14) When the concrete of the wet joint section reaches the design strength, the bottom formwork platform 14 is first removed, then the formwork system is removed, and finally the steel cantilever beam 4 is removed, and then the prestressed steel strands are tensioned to complete the construction of the steel-concrete joint section.
[0077] In the description of the present invention, it should be understood that the terms "longitudinal", "lateral", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside" and "outside" etc., indicating orientations or positional relationships, are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.
[0078] The embodiments described above are only descriptions of the preferred modes of the present invention, and are not intended to limit the scope of the present invention. Without departing from the design spirit of the present invention, various modifications and improvements made to the technical solutions of the present invention by ordinary technicians in this field should all fall within the protection scope determined by the claims of the present invention.
Claims
1. A method for constructing a steel-concrete combined section of a railway hybrid beam with a steel truss, characterized in that: The steps include: S1, manufacturing steel trusses (3) and steel cantilever beams (4); S2. Before pouring the concrete beam (5), pre-embed the steel truss (3) to the end of the concrete beam (5), pour the concrete beam (5) and maintain it; S3, after the concrete beam (5) reaches the designed strength, hoist the steel beam (6) to the designed height; S4, fixing the steel beam (6) and the concrete beam (5) through the steel truss (3) and the steel cantilever beam (4); S5, pouring the joint between the concrete beam (5) and the steel beam (6) to form a wet joint section. After the wet joint section reaches the designed strength, the construction of the steel-concrete joint section is completed.
2. The method for constructing a steel-concrete combined section of a railway hybrid beam with a steel truss according to claim 1, characterized in that: In the step S1, the steel truss (3) is made up of a chord (31), a web member (32) and a node plate (33).
3. The method for constructing a steel-concrete combined section of a railway hybrid beam with a steel truss according to claim 1, characterized in that: In the step S1, the steel cantilever beam (4) is formed by splicing a plurality of I-beams end to end, and two adjacent I-beams are fixedly connected.
4. The method for constructing a steel-concrete combined section of a railway hybrid beam with a steel truss according to claim 1, characterized in that: In step S2, the outer formwork of the concrete beam (5) is set up, the steel truss (3) is placed at the designed position, the steel bars of the concrete beam (5) are tied and ensured to pass through the installation holes of the steel truss (3), the prestressed pipes and prestressed steel strands are installed, the inner formwork is built, and the pouring and curing of concrete begins.
5. The method for constructing a steel-concrete combined section of a railway hybrid beam with a steel truss according to claim 1, characterized in that: In the step S3, the steel beam (6) is moved to a position directly below the position to be installed, and the steel beam (6) is lifted by means of staged loading.
6. The method for constructing a steel-concrete combined section of a railway hybrid beam with a steel truss according to claim 5, characterized in that: During the lifting process of the steel beam (6), the symmetrical two sides of the top of the steel beam (6) are loaded in stages according to the load levels of 20% → 40% → 60% → 80% → 100%, and whether there are any abnormal conditions during the loading process; during the lifting process, the loads on the symmetrical two sides of the top of the steel beam (6) are kept the same.
7. The method for constructing a steel-concrete combined section of a railway hybrid beam with a steel truss according to claim 1, characterized in that: In step S3, after the steel beam (6) is lifted to the designed height, the position of the steel beam (6) is fine-tuned, and the axis, elevation, transverse slope and longitudinal slope of the steel beam (6) are checked and fine-tuned using a total station and a level to ensure that the assembled steel beam (6) and the lifted steel beam (6) are on the same vertical line. After confirming that the design and monitoring requirements are met, the steel truss (3) is fixed to the steel beam (6) so that the steel beam (6) is supported on the concrete beam (5) only by the steel truss (3).
8. The method for constructing a steel-concrete combined section of a railway hybrid beam with a steel truss according to claim 7, characterized in that: In step S3, the steel cantilever beam (4) is precisely adjusted to the designed position, the tail end of the steel cantilever beam (4) is fixed to the concrete beam (5) through an anchoring device (41), the middle part of the steel cantilever beam (4) is connected to the embedded ear plate on the concrete beam (5) through a hinge support (42), the front end of the steel cantilever beam (4) is connected to the steel beam (6) through another hinge support (42), and the steel cantilever beam (4) is locked, so that the steel beam (6) and the concrete beam (5) form a firm and stable structure, so that the steel cantilever beam (4) and the steel truss (3) become the load-bearing structure for casting the wet joint section.
9. The method for constructing a steel-concrete combined section of a railway hybrid beam with a steel truss according to claim 1, characterized in that: In step S5, a formwork is supported at the wet joint position, steel bars are tied, prestressed pipes and prestressed steel strands are installed, concrete is poured and cured, and after the concrete of the wet joint reaches the designed strength, the formwork and the steel cantilever beam (4) are removed, and the prestressed steel strands are tensioned to complete the construction.
Citation Information
Patent Citations
Construction method for steel-concrete composite girder
CN104727226A
Construction method of steel-concrete mixed combined continuous rigid frame bridge
CN113882280A
Construction method for steel-concrete mixed section of cable-stayed bridge
CN115897397A
Recyclable steel truss embedded part mounting foundation
CN212866603U
Non-geocell steel-concrete combined section structure based on UHPC (Ultra High Performance Concrete)
CN217149895U