Filling method for plant subsidence area and closed conduit

By confirming the distribution and exploration of the culverts, the casing and grouting pipe reinforcement are used to replenish concrete and grouting reinforcement, the import and export of culverts are blocked, and the foundation conditions are monitored, the problem of foundation collapse in the factory construction is solved and the construction is smooth Progress and reduce impact.

CN118932982APending Publication Date: 2024-11-12CCCC (CHANGSHA) CONSTR CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411257351.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-09
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

During the construction of the factory, the operation of the culvert at the bottom of the site causes the foundation to collapse, affecting the progress of the factory construction.

Method used

By confirming the distribution and exploration of the culvert, using casing and grouting pipe reinforcement, filling concrete and grouting reinforcement, sealing the import and export of the culvert, monitoring the foundation status, stabilize the foundation and reduce the impact of construction.

Benefits of technology

It effectively solved the problem of foundation collapse, ensured the smooth progress of factory building, and reduced the impact of foundation construction on the factory building.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118932982A_ABST
    Figure CN118932982A_ABST
Patent Text Reader

Abstract

The invention provides a plant subsidence area and closed conduit filling method. The plant subsidence area and closed conduit filling method comprises the following steps of S1, closed conduit distribution and confirmation; s2, arrangement of exploration work; s3, collapse position treatment measures are taken; s4, filling and reinforcing the closed conduit; s5, blocking an inlet and an outlet of the closed conduit; s6, grouting reinforcement is conducted; and S7, monitoring. The invention provides a plant subsidence area and closed conduit filling method. The method comprises the following steps: distributing and confirming closed conduits; through the operation modes of exploration work arrangement, collapse position treatment measures, closed conduit filling and reinforcing treatment, closed conduit inlet and outlet blocking, grouting reinforcement and monitoring, after a closed conduit appears in the selected foundation, the closed conduit can be filled in a blocking mode, and the construction influence can be reduced during foundation construction.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of construction engineering, and in particular to a method for filling a factory building subsidence area and a culvert. Background Art

[0002] A construction project refers to an engineering entity formed through the construction of various types of buildings and their ancillary facilities and the installation of supporting lines, pipelines, and equipment. Among them, "buildings" refer to projects with roofs, beams, columns, walls, foundations, and internal spaces that can meet people's needs for production, residence, study, and public activities.

[0003] In current construction projects, construction operations are carried out in different industries. When building a factory, a site will be selected, and after the site is selected, the factory foundation will be constructed. However, when constructing the foundation in the selected site, if a culvert operation occurs at the bottom of the site, it will cause the foundation to collapse and affect the construction of the factory.

[0004] Therefore, it is necessary to provide a method for filling a plant subsidence area and a culvert to solve the above technical problems. Summary of the invention

[0005] The invention provides a method for filling a subsided area of ​​a plant building and a culvert, which solves the problem that when a culvert is operated at the bottom of a site, the foundation will collapse and the construction of the plant building will be affected.

[0006] In order to solve the above technical problems, the present invention provides a method for filling a subsidence area of ​​a factory building and a culvert, comprising the following steps:

[0007] S1. The location and direction of the underground drains found on the ground of the factory building are confirmed by using professional equipment;

[0008] S2. After confirming the location and direction of the underground canal in S1, arrange professionals to conduct the exploration of the canal and draw the blueprint after the exploration is completed;

[0009] S21. After the culvert exploration in S2, according to the culvert distribution map of the plant area that has been verified to be basically correct in the early stage, exploration holes are arranged every 24m from the culvert entrance position, and the culvert distribution position is further surveyed and verified to confirm the top and bottom burial depths of the culvert, and the thickness of the silt at the bottom of the culvert is measured, and whether there are any collapsed parts in other parts of the culvert are explored as much as possible;

[0010] S22. After the exploration hole is constructed, a φ20 PPR grouting pipe is buried in the hole. The buried pipe depth is to the top of the culvert, 0.50m above the ground. Four φ10 grouting holes are evenly arranged 1.00m below the bottom of the grouting pipe. Cement mortar is used to seal the 0.50m below the ground to facilitate the subsequent grouting reinforcement construction.

[0011] S23. According to the previous inspection of silt at the bottom of the culvert inlet and outlet, the culvert inlet is deposited with about 0.50m thick silt. After going 10m deep into the culvert from the inlet, the silt thickness at the bottom of the channel is reduced to 0.20m. The silt is mainly mud and sand. The silt thickness at the bottom of the outlet channel is 0.10m. The silt is mainly mud and sand. Manual dredging is required at the inlet section of the culvert to remove the silt at the inlet section.

[0012] S3. When the culvert collapses, measures need to be taken to deal with the collapsed location;

[0013] S31. First, lower the casing into the collapsed area of ​​the culvert. After the casing is lowered, install a hopper on the top of the casing. After the hopper is installed, use a sky pump to pump C15 concrete into the collapsed area of ​​the culvert, so that the C15 concrete can flow freely into the culvert.

[0014] S32, after pouring C15 concrete 13 into the collapsed area 13 of the culvert 10, the upper part is backfilled with leveling concrete 14 to 1.20m below the indoor floor elevation of the plant;

[0015] S33. Three days after the C15 concrete and the filling concrete are poured, the cap is chiseled out, and grouting holes are arranged at the steel structure foundation position according to the specified numerical spacing, passing through the poured C15 concrete and the filling concrete layer until the bottom of the culvert, and grouting pipes are placed in the holes. The grouting pipes are placed to the bottom of the grouting, and the grouting pipes are 0.50m above the ground. Four grouting holes are evenly arranged 1.00m below the bottom of the grouting pipes. Cement mortar is used to seal the 0.50m below the ground, and a return grouting pipe is buried to grout and reinforce the fill layer collapsed at the bottom of the culvert;

[0016] S4, underground channel filling and reinforcement treatment;

[0017] S41. After the collapse area of ​​the culvert is sealed, the construction of filling the culvert with concrete begins from the collapse area to the inlet and outlet directions of the culvert. Pile holes are opened every 8.00m on the surface of the ground and above the collapse area. The top of the culvert is penetrated, and the casing is lowered to the bottom of the culvert. A hopper is connected to the top of the casing, and concrete is pumped to the bottom of the culvert through a sky pump to squeeze the accumulated water that cannot be discharged at the bottom of the culvert to be discharged freely in the inlet and outlet directions. Because the concrete pouring volume of each section is large, in order to speed up the concrete pouring speed, the roadbed can be used in the parts with conditions, and the concrete can be poured in a self-unloading manner;

[0018] S42. When pouring concrete into the underground channel in the subsidence area, four adjacent holes can be drilled on both sides at a spacing of 8.00m. When pouring concrete into the underground channel in the subsidence area, the adjacent pile holes should be observed and the fluidity of the concrete poured in the first pile hole should be checked to facilitate timely adjustment of the hole spacing;

[0019] S43, after it is determined that the concrete poured in the first pile hole can flow to the second pile hole and squeeze out the water at the bottom of the culvert of the second pile hole, concrete can be poured in the second pile hole at the same time, and the culvert is solidified. The concrete pouring can adopt a secondary or tertiary pouring process, and the second pouring is carried out after the initial setting of the last poured concrete, until the concrete is poured to the culvert arch;

[0020] S44. The design filling concrete grade is C15 concrete, and the concrete slump is required to be 18-22cm, so that the concrete can flow freely into the culvert;

[0021] S45. After the concrete pouring of the pile hole is completed, a grouting pipe is placed in the pile hole. The grouting pipe is placed to the top surface of the poured concrete. The grouting pipe is 0.50m above the ground. Four grouting holes with a diameter of φ10 are evenly arranged 2.00m below the bottom of the grouting pipe. Sand and gravel are backfilled in the hole. Concrete is used to seal the hole 0.50m below the ground, and a return grouting pipe is buried;

[0022] S5. Blocking of the entrance and exit of the culvert;

[0023] S51. After pumping and dredging the culvert inlet and the first sandbag waterproof dam section, a 9.00m long grouting pipe is installed on the culvert arch. The grouting pipe is 0.50m beyond the culvert inlet. Six grouting holes are evenly arranged 3.00m below the grouting pipe to facilitate the subsequent grouting backfilling of the gap in the arch. Backfill soil at the culvert inlet and the first sandbag waterproof dam section and compact it layer by layer to the level of the culvert top. A concrete inlet is reserved at the top of the culvert inlet;

[0024] S52. When pouring concrete in the culvert to a position of 8m from the outlet, at outlet point D, first use a fan to supply air to the underground, then arrange professional personnel to go down the well, lower sandbags from the wellhead into the well, and pile up sandbags multiple times within 3.00m of the outlet culvert. The height of the first pile of sandbags must be sufficient to drain the accumulated water and silt in the culvert, and the height of the subsequent piles of sandbags must be sufficient to ensure that the concrete poured into the culvert cannot enter the drainage pipe outside the outlet. After the sandbags block the outlet, a 370mm brick wall must be built at the culvert outlet to block the outlet. During the construction of blocking the outlet by underground personnel, the air supply in the hole cannot be interrupted.

[0025] S6, grouting reinforcement;

[0026] S7. Monitoring.

[0027] Preferably, the S1 comprises the following steps:

[0028] S11. Conduct a careful survey of the ground along the culvert to find out whether there is any ground subsidence or cracking in other parts;

[0029] S12. The plant general map has marked the distribution of the culverts, of which the AB section is 345.47m; the BC section is 110.92m; and the DE section is 54.39m. It is necessary to measure and locate the locations of the existing culvert inlets, outlets, and exposed collapsed parts, and put them on the general map to verify whether the culvert distribution is accurate. The elevations of the culvert inlets, outlets, and collapsed parts of the arches and bottoms are measured to confirm the buried depth of the culverts.

[0030] S13. Two sandbag dams have been set up outside the culvert inlet to divert the water flow from the culvert inlet. It is necessary to fill clay soil outside the sandbag dam near the culvert inlet and compact it appropriately to prevent the water flow from the culvert inlet from continuing to enter the culvert, so as to stop the water from the culvert inlet. Then, a water pump is used to remove the remaining water from the culvert inlet, measure the plane dimensions and top and bottom elevations of the culvert, and measure the silt thickness at the culvert inlet.

[0031] S14. Drainage pipes have been buried at the outlet of the culvert, and a wellhead has been reserved to connect with the culvert. To verify the plane dimensions of the culvert at the outlet, a fan must be used to supply air to the well first, and then professional personnel must be arranged to go down the well to take measurements. The air supply cannot be interrupted during this period.

[0032] Preferably, the concrete slump requirement in S31 is 18-22 cm, the arch height of the culvert 10 is 3.50 m, and according to the designed concrete slump, the maximum horizontal flow distance of the concrete in the culvert will exceed 12 m;

[0033] In S32, since the depth of the collapsed area reaches 9.00 meters, the thickness of the backfill concrete reaches 8.00 meters, and the volume of the backfill concrete is as high as 400 square meters, in order to eliminate the influence of hydration heat caused by concrete solidification, low hydration heat concrete materials can be used. If low hydration heat concrete cannot be provided locally, layered concrete pouring should be adopted.

[0034] Preferably, the standard value of the bearing capacity of the composite foundation after the grouting reinforcement treatment of the collapsed fill in the lower part of S3 is recommended to be 180Kpa;

[0035] After the pedestal and surrounding areas are reinforced by grouting, an independent foundation is designed on the backfill concrete. The surrounding area of ​​the independent foundation is backfilled with graded sand and gravel to the bottom elevation of the indoor ground cushion layer as a cushion layer to avoid uneven settlement with the surrounding foundation soil.

[0036] Preferably, a grouting pipe 20 is buried in S45 to facilitate the subsequent grouting reinforcement of the collapsed soil layer section that may not be found in the culvert vault, thereby eliminating the adverse hidden dangers caused thereby.

[0037] Preferably, S6 comprises the following steps:

[0038] S61. There may be undiscovered collapsed soil layers at the top of the culvert or unfilled concrete layers at the site. In the excavation area, another grouting hole is set between the two pile holes. In the filling area, two rows of grouting holes are set at 10-20cm on both sides of the culvert between the two pile holes at a spacing of @3200. The grouting holes in the excavation area are drilled with a φ110 drill rig and pass through the top of the culvert until the concrete layer is poured. The grouting holes in the filling area are drilled to the elevation of the top of the culvert, and a φ20PPR grouting pipe is placed in the hole. The grouting pipe is placed to the bottom of the drill hole, and the grouting pipe is 0.50m above the ground. Four φ10 grouting holes are evenly arranged 1.00m below the bottom of the grouting pipe. Cement mortar is used to seal the 0.50m below the ground, and a φ20PPR return grouting pipe is buried to facilitate grouting to reinforce the undiscovered collapsed soil layer and avoid uneven settlement of the indoor floor in the later stage.

[0039] S62. Grouting uses PO42.5 acid cement, and the water-cement ratio of cement slurry is 1:1. The principle of compaction grouting is to inject slurry into the stratum evenly through the grouting pipe. The slurry takes up its position after driving away the moisture and air between soil particles or rock and soil cracks by filling, infiltration and compaction. After a certain period of artificial control, the slurry consolidates the original loose soil, thereby increasing the bearing capacity of the fill and avoiding uneven settlement of the fill. The grouting pressure should be 0.5-2.0MPa. After the collapsed cavity at the intersection of the 24 axis and the J axis is backfilled with C15 concrete, the grouting under the cap is mainly used to reinforce the fill layer collapsed at the bottom of the culvert. The grouting pressure should be 1.0-2.0MPa, and the grouting pressure in other parts can be 0.5-1.0MPa.

[0040] S63. After the grouting starts and the thick cement slurry emerges from the return grouting pipe, the return grouting pipe should be sealed with a closed piston, and then pressure grouting should be carried out;

[0041] S64: Grouting can be stopped when the grouting speed is less than 5L / min or grouting appears on the ground surface;

[0042] S65. When groundwater emerges from the surface during the grouting process, drainage ditches must be set up around the construction site and personnel must be arranged to use submersible pumps to drain the water out. Grouting should be carried out in a skip-hole interval grouting manner, with the grouting construction method starting from the outside and then the inside.

[0043] Preferably, a cleaning device is used when cleaning the sludge in S24, and the cleaning device includes a movable seat, a base is installed on the surface of the movable seat, a box is installed on the surface of the base, a conveying device is provided on the surface of the base and on the side opposite to the box, and the conveying device includes a suction pump, and the input and output ends of the suction pump are respectively connected to a first conveying pipe and a second conveying pipe, one end of the first conveying pipe is connected to the box, a suction assembly is provided on the surface of the base, a storage box is provided inside the box, and a feed hopper is provided on one side of the box.

[0044] Preferably, the suction assembly includes a telescopic rod, one end of the telescopic rod is connected to a suction tube, one side of the suction tube is connected to a plurality of suction heads, and one end of the second conveying tube is connected to one end of the suction head.

[0045] Preferably, a placement rack is provided on the surface of the telescopic rod, and the bottom of the placement rack is connected to the surface of the base.

[0046] Preferably, a suspension assembly is provided on one side of the box body, and the suspension assembly includes a circular rod, a movable sleeve is provided on the surface of the circular rod, one side of the movable sleeve is connected to a circular connecting block, one end of the circular connecting block is connected to a rectangular plate, one side of the rectangular plate is connected to a fixing ring, a connecting bolt is provided inside the movable sleeve, the top and bottom ends of the circular rod are both connected to positioning blocks, and one end of the positioning block is connected to the side of the box body.

[0047] Compared with the related art, the method for filling a subsidence area and a culvert provided by the present invention has the following beneficial effects:

[0048] The present invention provides a method for filling a subsidence area of ​​a factory building and a culvert, through the distribution and confirmation of culverts; arrangement of exploration work, measures for handling the subsidence position, filling and reinforcement of culverts, plugging of culvert inlets and outlets, grouting reinforcement and monitoring operations. When a culvert appears inside a selected foundation, the culvert can be filled by plugging it, thereby reducing the impact of construction during foundation construction. BRIEF DESCRIPTION OF THE DRAWINGS

[0049] Figure 1 A schematic structural diagram of a first embodiment of a method for filling a subsidence area of ​​a factory building and a culvert provided by the present invention;

[0050] Figure 2 for Figure 1 The structural schematic diagram of the first cross-sectional dimensions of the culvert entrance and exit is shown;

[0051] Figure 3 for Figure 1 The structural schematic diagram of the second cross-sectional dimensions of the culvert entrance and exit shown;

[0052] Figure 4 This is a schematic diagram of the treatment of the subsidence area;

[0053] Figure 5 This is the plan layout of the grouting holes in the collapse area;

[0054] Figure 6 This is a schematic diagram of the vertical surface of rotary drilling and pouring;

[0055] Figure 7 It is a schematic elevation diagram of the grouting hole arrangement;

[0056] Figure 8 This is a schematic diagram of the entrance blocking;

[0057] Fig. 9 This is a schematic diagram of the blockage at the exit;

[0058] Fig.10 It is the large-scale drawing of type II and type I grouting pipe;

[0059] Fig.11 This is the construction flow chart for the culvert collapse area;

[0060] Fig.12 A schematic structural diagram of a second embodiment of a method for filling a subsidence area of ​​a factory building and a culvert provided by the present invention;

[0061] Fig.13 for Fig.12 An enlarged schematic diagram of part A is shown;

[0062] Fig.14 for Fig.12 A schematic diagram of the overall three-dimensional structure of the device shown;

[0063] Fig.15 for Fig.12 A schematic diagram of the three-dimensional structure of the entire internal structure of the device shown;

[0064] Fig.16 A schematic structural diagram of a third embodiment of a method for filling a plant subsidence area and a culvert provided by the present invention.

[0065] Numbers in the figure: 1, mobile seat; 2, base; 3, box body;

[0066] 4. conveying device; 41. suction pump; 42. first conveying pipe; 43. second conveying pipe;

[0067] 5. Suction assembly; 51. Telescopic rod; 52. Suction tube; 53. Suction head; 54. Placement rack;

[0068] 6. Storage box; 7. Feed hopper;

[0069] 8. Suspension assembly; 81. Round rod; 82. Movable sleeve; 83. Round connecting block; 84. Rectangular plate; 85. Fixed ring; 86. Connecting bolt; 87. Positioning block. DETAILED DESCRIPTION

[0070] The present invention will be further described below in conjunction with the accompanying drawings and implementation modes.

[0071] First embodiment

[0072] Please refer to Figure 1 , Figure 2 , Figure 3 , Figure 4 , Figure 5 , Figure 6 , Figure 7 , Figure 8 , Fig. 9 , Fig.10 and Fig.11 ,in, Figure 1 A schematic structural diagram of a first embodiment of a method for filling a subsidence area of ​​a factory building and a culvert provided by the present invention; Figure 2 for Figure 1 The structural schematic diagram of the first cross-sectional dimensions of the culvert entrance and exit is shown; Figure 3 for Figure 1 The structural schematic diagram of the second cross-sectional dimensions of the culvert entrance and exit shown; Figure 4 This is a schematic diagram of the treatment of the subsidence area; Figure 5 This is the plan layout of the grouting holes in the collapse area; Figure 6 This is a schematic diagram of the vertical surface of rotary drilling and pouring; Figure 7 It is a schematic elevation diagram of the grouting hole arrangement; Figure 8 This is a schematic diagram of the entrance blocking; Fig. 9 This is a schematic diagram of the blockage at the exit; Fig.10 It is the large-scale drawing of type II and type I grouting pipe; Fig.11 A method for filling a factory building subsidence area and a culvert includes the following steps:

[0073] S1. The location and direction of the underground channel 10 found in the ground 9 of the factory building are confirmed by using professional equipment;

[0074] S2. After confirming the position and direction of the underground channel 10 under the ground 9 in S1, arrange professionals to conduct exploration of the underground channel 10, and draw a blueprint after the exploration is completed;

[0075] S21. After the exploration of the culvert 10 in S2, according to the culvert distribution map of the plant area that has been verified to be basically correct in the early stage, exploration holes are arranged every about 24m from the entrance of the culvert 10, and the distribution position of the culvert 10 is further surveyed and verified, the top and bottom burial depths of the culvert 10 are confirmed, the thickness of the silt at the bottom of the culvert 10 is measured, and whether there are any collapsed parts in other parts of the culvert 10 are explored as much as possible;

[0076] S22. After the exploration hole is constructed, a φ20 PPR grouting pipe is buried in the hole. The buried pipe depth is to the top of the culvert, 0.50m above the ground. Four φ10 grouting holes are evenly arranged 1.00m below the bottom of the grouting pipe. Cement mortar is used to seal the 0.50m below the ground to facilitate the subsequent grouting reinforcement construction.

[0077] S23. According to the previous inspection of silt at the bottom of the culvert inlet and outlet, the culvert inlet is deposited with about 0.50m thick silt. After going 10m deep into the culvert from the inlet, the silt thickness at the bottom of the channel is reduced to 0.20m. The silt is mainly mud and sand. The silt thickness at the bottom of the outlet channel is 0.10m. The silt is mainly mud and sand. Manual dredging is required at the inlet section of the culvert to remove the silt at the inlet section.

[0078] S3. When the culvert 10 collapses, measures are required to deal with the collapsed position;

[0079] S31. First, lower the casing 12 into the collapsed area 11 of the culvert 10. After the casing 12 is lowered, a hopper is installed on the top of the casing 12. After the hopper is installed, a sky pump is used to pump C15 concrete 13 into the collapsed area 11 of the culvert 10, so that the C15 concrete 13 can flow freely into the culvert 10.

[0080] S32, after pouring C15 concrete 13 into the collapsed area 13 of the culvert 10, the upper part is backfilled with leveling concrete 14 to 1.20m below the indoor floor elevation of the plant;

[0081] S33, three days after the pouring of C15 concrete 13 and filling concrete 14 is completed, the cap 15 is chiseled out, and grouting holes 16 are arranged at the steel structure foundation position according to the specified numerical spacing, passing through the poured C15 concrete 13 and filling concrete 14 layers to the bottom of the culvert 10, and grouting pipes 17 are placed in the holes, and the grouting pipes 17 are placed to the bottom of the grouting, and at the same time, the grouting pipes 13 are 0.50m above the ground, and four grouting holes 16 are evenly arranged 1.00m from the bottom of the grouting pipes 13, and 0.50m below the ground is sealed with cement mortar, and a return grouting pipe is buried to grout and reinforce the fill layer collapsed at the bottom of the culvert 10;

[0082] S4, filling and reinforcement treatment of the culvert 10;

[0083] S41. After the collapse area 11 of the culvert 10 is sealed, the construction of filling concrete 13 of the culvert 10 begins from the collapse area 11 to the inlet and outlet directions of the culvert 10. Pile holes 18 are opened every 8.00m on the surface of the ground 9 and above the collapse area 11. The top of the culvert 10 is penetrated, and the casing 12 is lowered to the bottom of the culvert 10. A hopper is connected to the top of the casing 12, and concrete 13 is pumped to the bottom of the culvert 10 through a sky pump, squeezing the accumulated water that cannot be discharged from the bottom of the culvert 10 to be discharged freely in the inlet and outlet directions. Because the concrete pouring volume of each section is large, in order to speed up the concrete pouring speed, the road base plate can be used in the parts with conditions, and the concrete can be poured in a self-unloading manner;

[0084] S42, when the culvert 10 in the subsidence area 11 is filled with concrete, four adjacent holes 18 may be first drilled at a spacing of 8.00 m on both sides. When the culvert 10 in the subsidence area 11 is filled with concrete, the fluidity of the concrete poured in the first pile hole 181 is observed and checked for the adjacent pile holes 18, so as to adjust the hole spacing in time;

[0085] S43, after it is determined that the concrete 13 poured into the first pile hole 181 can flow to the second pile hole 182 and squeeze out the water at the bottom of the culvert 10 of the second pile hole 182, the concrete 13 can be poured into the second pile hole 182 at the same time, and the culvert 10 is coagulated. The pouring of the concrete 13 can adopt a secondary or tertiary pouring process, and the second pouring is performed after the initial coagulation of the last poured concrete, until the concrete is poured to the culvert arch;

[0086] S44. The design filling concrete grade is C15 concrete, and the concrete slump is required to be 18-22cm, so that the concrete can flow freely into the culvert;

[0087] S45, after the concrete pouring of pile hole 18 is completed, a grouting pipe 19 is placed in the pile hole 18, and the grouting pipe 19 is placed to the top surface of the poured concrete, and the grouting pipe 19 is 0.50m above the ground. Four grouting holes with a diameter of φ10 are evenly arranged 2.00m below the bottom of the grouting pipe 19, and the holes are backfilled with sand and gravel. The 0.50m below the ground is sealed with concrete, and a return grouting pipe 20 is buried;

[0088] S5, blocking the entrance and exit of the culvert;

[0089] S51. After pumping and dredging the culvert inlet and the first sandbag waterproof dam section, a 9.00m long grouting pipe 19 is installed on the culvert arch. The grouting pipe 19 is 0.50m beyond the culvert inlet. Six grouting holes 21 are evenly arranged 3.00m below the bottom of the grouting pipe 19 to facilitate the subsequent grouting backfilling of the gap in the arch. Backfill soil at the culvert inlet 22 and the first sandbag waterproof dam section and compact it layer by layer to the top elevation of the culvert 10. A concrete inlet is reserved at the top of the culvert inlet 22;

[0090] S52. When pouring concrete 13 in the culvert 10 to the position of 8m from the outlet, at the outlet D point, first use a fan to supply air to the well, then arrange professional personnel to go down the well, lower sandbags from the wellhead into the well, and pile up sandbags several times within 3.00m of the outlet culvert. The height of the first pile of sandbags must be guaranteed to be able to drain the accumulated water and silt in the culvert, and the height of the subsequent piles of sandbags must be guaranteed to ensure that the concrete poured in the culvert cannot enter the drainage pipe outside the outlet. After the sandbags block the outlet, a 370mm brick wall must be built at the culvert outlet to block the outlet. During the construction of blocking the outlet by the underground personnel, the air supply in the hole cannot be interrupted.

[0091] S6, grouting reinforcement;

[0092] S7. Monitoring.

[0093] The S1 comprises the following steps:

[0094] S11. Conduct a careful and thorough survey of the ground along the culvert to find out whether there is any ground subsidence or cracking in other parts;

[0095] S12. The plant general map has marked the distribution of the culverts, of which the AB section is 345.47m; the BC section is 110.92m; and the DE section is 54.39m. It is necessary to measure and locate the locations of the existing culvert inlets, outlets, and exposed collapsed parts, and put them on the general map to verify whether the culvert distribution is accurate. The elevations of the culvert inlets, outlets, and collapsed parts of the arches and bottoms are measured to confirm the buried depth of the culverts.

[0096] S13. Two sandbag dams have been set up outside the culvert inlet to divert the water flow from the culvert inlet. It is necessary to fill clay soil outside the sandbag dam near the culvert inlet and compact it appropriately to prevent the water flow from the culvert inlet from continuing to enter the culvert, so as to stop the water from the culvert inlet. Then, a water pump is used to remove the remaining water from the culvert inlet, measure the plane dimensions and top and bottom elevations of the culvert, and measure the silt thickness at the culvert inlet.

[0097] S14. Drainage pipes have been buried at the outlet of the culvert, and a wellhead has been reserved to connect with the culvert. To verify the plane dimensions of the culvert at the outlet, a fan must be used to supply air to the well first, and then professional personnel must be arranged to go down the well to take measurements. The air supply cannot be interrupted during this period.

[0098] The concrete slump requirement in S31 is 18-22 cm, and the arch height of the culvert 10 is 3.50 m. According to the designed concrete slump, the maximum horizontal flow distance of the concrete in the culvert will exceed 12 m.

[0099] In S32, since the depth of the collapsed area reaches 9.00 meters, the thickness of the backfill concrete reaches 8.00 meters, and the volume of the backfill concrete is as high as 400 square meters, in order to eliminate the influence of hydration heat caused by concrete solidification, low hydration heat concrete materials can be used. If low hydration heat concrete cannot be provided locally, layered concrete pouring should be adopted.

[0100] The standard value of the composite foundation bearing capacity after the grouting reinforcement treatment of the collapsed fill in the lower part of S3 is recommended to be 180Kpa;

[0101] After the pedestal and surrounding areas are reinforced by grouting, an independent foundation is designed on the backfill concrete. The surrounding area of ​​the independent foundation is backfilled with graded sand and gravel to the bottom elevation of the indoor ground cushion layer as a cushion layer to avoid uneven settlement with the surrounding foundation soil.

[0102] The grouting pipe 20 is buried in the S45 to facilitate the subsequent grouting reinforcement of the collapsed soil layer section that may not be found in the arch of the culvert, and eliminate the adverse hidden dangers caused by it.

[0103] The S6 comprises the following steps:

[0104] S61. There may be undiscovered collapsed soil layers at the top of the culvert or unfilled concrete layers at the site. In the excavation area, another grouting hole is set between the two pile holes. In the filling area, two rows of grouting holes are set at 10-20cm on both sides of the culvert between the two pile holes at a spacing of @3200. The grouting holes in the excavation area are drilled with a φ110 drill rig and pass through the top of the culvert until the concrete layer is poured. The grouting holes in the filling area are drilled to the elevation of the top of the culvert, and a φ20PPR grouting pipe is placed in the hole. The grouting pipe is placed to the bottom of the drill hole, and the grouting pipe is 0.50m above the ground. Four φ10 grouting holes are evenly arranged 1.00m below the bottom of the grouting pipe. Cement mortar is used to seal the 0.50m below the ground, and a φ20PPR return grouting pipe is buried to facilitate grouting to reinforce the undiscovered collapsed soil layer and avoid uneven settlement of the indoor floor in the later stage.

[0105] S62. Grouting uses PO42.5 acid cement, and the water-cement ratio of cement slurry is 1:1. The principle of compaction grouting is to inject slurry into the stratum evenly through the grouting pipe. The slurry takes up its position after driving away the moisture and air between soil particles or rock and soil cracks by filling, infiltration and compaction. After a certain period of artificial control, the slurry consolidates the original loose soil, thereby increasing the bearing capacity of the fill and avoiding uneven settlement of the fill. The grouting pressure should be 0.5-2.0MPa. After the collapsed cavity at the intersection of the 24 axis and the J axis is backfilled with C15 concrete, the grouting under the cap is mainly used to reinforce the fill layer collapsed at the bottom of the culvert. The grouting pressure should be 1.0-2.0MPa, and the grouting pressure in other parts can be 0.5-1.0MPa.

[0106] S63. After the grouting starts and the thick cement slurry emerges from the return grouting pipe, the return grouting pipe should be sealed with a closed piston, and then pressure grouting should be carried out;

[0107] S64: Grouting can be stopped when the grouting speed is less than 5L / min or grouting appears on the ground surface;

[0108] S65. When groundwater emerges from the surface during the grouting process, drainage ditches must be set up around the construction site and personnel must be arranged to use submersible pumps to drain the water out. Grouting should be carried out in a skip-hole interval grouting manner, with the grouting construction method starting from the outside and then the inside.

[0109] Compared with the related art, the method for filling a subsidence area and a culvert provided by the present invention has the following beneficial effects:

[0110] The present invention provides a method for filling a subsidence area of ​​a factory building and a culvert, through the distribution and confirmation of culverts; arrangement of exploration work, measures for handling the subsidence position, filling and reinforcement of culverts, plugging of culvert inlets and outlets, grouting reinforcement and monitoring operations. When a culvert appears inside a selected foundation, the culvert can be filled by plugging it, thereby reducing the impact of construction during foundation construction.

[0111] Second embodiment

[0112] Please refer to Fig.12 , Fig.13 , Fig.14 and Fig.15 Based on a method for filling a subsidence area and a culvert provided in the first embodiment of the present application, another method for filling a subsidence area and a culvert is proposed in the second embodiment of the present application. The second embodiment is only a preferred method of the first embodiment, and the implementation of the second embodiment will not affect the independent implementation of the first embodiment.

[0113] Specifically, the difference between the method for filling a subsidence area of ​​a factory building and a culvert provided in the second embodiment of the present application is that, in the method for filling a subsidence area of ​​a factory building and a culvert, a cleaning device is used when cleaning the sludge in S24, and the cleaning device includes a movable seat 1, a base 2 is installed on the surface of the movable seat 1, a box 3 is installed on the surface of the base 2, a conveying device 4 is provided on the surface of the base 2 and on the side opposite to the box 3, the conveying device 4 includes a suction pump 41, the input end and the output end of the suction pump 41 are respectively connected to a first conveying pipe 42 and a second conveying pipe 43, one end of the first conveying pipe 42 is connected to the box 3, a suction assembly 5 is provided on the surface of the base 2, a storage box 6 is provided inside the box 3, and a feed hopper 7 is provided on one side of the box 3.

[0114] The use of the feed hopper 7 facilitates the manual cleaning of the sludge into the storage box 6 inside the box body 3 .

[0115] The suction assembly 5 includes a telescopic rod 51 , one end of which is connected to a suction tube 52 , one side of which is connected to a plurality of suction heads 53 , and one end of the second conveying tube 42 is connected to one end of the suction head 53 .

[0116] A placement frame 54 is disposed on the surface of the telescopic rod 51 , and the bottom of the placement frame 54 is connected to the surface of the base 2 .

[0117] The working principle of a method for filling a plant subsidence area and a culvert provided by the present invention is as follows:

[0118] During use, when sucking sludge, first take out the suction tube 52 with multiple suction heads 53 from the placement rack 54, then bring the suction tube 52 with multiple suction heads 53 into contact with the sludge, and then start the delivery pump 41 to transport the sludge through the suction tube 52 with multiple suction heads 53, the first delivery tube 42 and the second delivery tube 43 to the interior of the storage box 6 inside the box body 3.

[0119] Compared with the related art, the method for filling a subsidence area and a culvert provided by the present invention has the following beneficial effects:

[0120] The present invention provides a method for filling a subsidence area of ​​a factory building and a culvert. A box body 3, a conveying device 4, a suction component 5 and a storage box 6 are arranged on a mobile seat 1 with a base 2, and the cooperation between them can clean up the sludge generated at the culvert blocking position after the culvert is blocked.

[0121] Third embodiment

[0122] Please refer to Fig.16 Based on the method for filling a subsidence area and a culvert provided in the first embodiment of the present application, the third embodiment of the present application proposes another method for filling a subsidence area and a culvert. The third embodiment is only a preferred method of the first embodiment, and the implementation of the third embodiment will not affect the independent implementation of the first embodiment.

[0123] Specifically, the difference of a method for filling a subsidence area of ​​a factory building and a culvert provided in the third embodiment of the present application is that, in a method for filling a subsidence area of ​​a factory building and a culvert, a suspension assembly 8 is provided on one side of the box body 3, and the suspension assembly 8 includes a circular rod 81, and the surface of the circular rod 81 is provided with a movable sleeve 82, and one side of the movable sleeve 82 is connected to a circular connecting block 83, one end of the circular connecting block 83 is connected to a rectangular plate 84, one side of the rectangular plate 84 is connected to a fixing ring 85, and a connecting bolt 86 is provided inside the movable sleeve 82, and the top and bottom ends of the circular rod 81 are both connected to a positioning block 87, and one end of the positioning block 87 is connected to the side of the box body 3.

[0124] A connection hole matched with the connection bolt 86 is opened on the surface of the round rod 81 .

[0125] The working principle of a method for filling a plant subsidence area and a culvert provided by the present invention is as follows:

[0126] When using, when hanging the tool to be used, first take out the connecting bolt 86 inside the movable sleeve 82. After the connecting bolt 86 is taken out, the position of the rectangular plate 84 with the fixing ring 85 is adjusted under the action of the movable sleeve 82. After the rectangular plate 84 with the fixing ring 85 is adjusted, use the connecting bolt 86 to pass through the movable sleeve 82 and connect it to the round rod 81.

[0127] Compared with the related art, the method for filling a subsidence area and a culvert provided by the present invention has the following beneficial effects:

[0128] The present invention provides a method for filling a subsidence area of ​​a factory building and a culvert. A hanging assembly 8 is arranged on one side of a box body 6 so that tools used during construction can be hung and stored, and it is also convenient for workers to take them when in use.

[0129] The above descriptions are merely embodiments of the present invention and are not intended to limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made using the contents of the present invention specification and drawings, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.

Claims

1. A method for filling a factory building subsidence area and a culvert, characterized in that: The following steps are involved: S1. Use professional equipment to confirm the location and direction of the underground channel; S2. After confirming the location and direction of the underground canal in S1, arrange professionals to conduct the exploration of the canal and draw the blueprint after the exploration is completed; S21. After the culvert exploration in S2, according to the culvert distribution map of the plant area that has been verified to be basically correct in the early stage, exploration holes are arranged every 24m from the culvert entrance position, and the culvert distribution position is further surveyed and verified to be confirmed, the top and bottom burial depths of the culvert are confirmed, the silt thickness at the bottom of the culvert is measured, and whether there are any collapsed parts in other parts of the culvert 10 are explored as much as possible; S22. After the exploration hole is constructed, a φ20 PPR grouting pipe is buried in the hole. The buried pipe depth is to the top of the culvert, 0.50m above the ground. Four φ10 grouting holes are evenly arranged 1.00m below the bottom of the grouting pipe. Cement mortar is used to seal the 0.50m below the ground to facilitate the subsequent grouting reinforcement construction. S23. According to the previous inspection of silt at the bottom of the culvert inlet and outlet, the culvert inlet is deposited with about 0.50m thick silt. After going 10m deep into the culvert from the inlet, the silt thickness at the bottom of the channel is reduced to 0.20m. The silt is mainly mud and sand. The silt thickness at the bottom of the outlet channel is 0.10m. The silt is mainly mud and sand. Manual dredging is required at the inlet section of the culvert to remove the silt at the inlet section. S3. When the culvert collapses, measures need to be taken to deal with the collapsed location; S31. First, lower the casing into the collapsed area of ​​the culvert. After the casing is lowered, install a hopper on the top of the casing. After the hopper is installed, use a sky pump to pump C15 concrete into the collapsed area of ​​the culvert, so that the C15 concrete can flow freely into the culvert. S32. After pouring C15 concrete into the collapsed area of ​​the culvert, the upper part is backfilled with leveling concrete to 1.20m below the indoor floor elevation of the plant; S33. Three days after the C15 concrete and the filling concrete are poured, the cap is chiseled out, and grouting holes are arranged at the steel structure foundation position according to the specified numerical spacing, passing through the poured C15 concrete and the filling concrete layer until the bottom of the culvert, and grouting pipes are placed in the holes. The grouting pipes are placed to the bottom of the grouting, and the grouting pipes are 0.50m above the ground. Four grouting holes are evenly arranged 1.00m below the bottom of the grouting pipes. Cement mortar is used to seal the 0.50m below the ground, and a return grouting pipe is buried to grout and reinforce the fill layer collapsed at the bottom of the culvert; S4, underground channel filling and reinforcement treatment; S41. After the collapse area of ​​the culvert is sealed, the construction of filling the culvert with concrete begins from the collapse area to the inlet and outlet directions of the culvert. Pile holes are opened every 8.00m on the surface of the ground and above the collapse area. The top of the culvert is penetrated, and the casing is lowered to the bottom of the culvert. A hopper is connected to the top of the casing, and concrete is pumped to the bottom of the culvert through a sky pump to squeeze the accumulated water that cannot be discharged at the bottom of the culvert to be discharged freely in the inlet and outlet directions. Because the concrete pouring volume of each section is large, in order to speed up the concrete pouring speed, the roadbed can be used in the parts with conditions, and the concrete can be poured in a self-unloading manner; S42. When pouring concrete into the underground channel in the subsidence area, four adjacent holes can be drilled on both sides at a spacing of 8.00m. When pouring concrete into the underground channel in the subsidence area, the adjacent pile holes should be observed and the fluidity of the concrete poured in the first pile hole should be checked to facilitate timely adjustment of the hole spacing; S43, after it is determined that the concrete poured in the first pile hole can flow to the second pile hole and squeeze out the water at the bottom of the culvert of the second pile hole, concrete can be poured in the second pile hole at the same time, and the culvert is solidified. The concrete pouring can adopt a secondary or tertiary pouring process, and the second pouring is carried out after the initial setting of the last poured concrete, until the concrete is poured to the culvert arch; S44. The design filling concrete grade is C15 concrete, and the concrete slump is required to be 18-22cm, so that the concrete can flow freely into the culvert; S45, after the concrete pouring of pile hole 18 is completed, a grouting pipe is placed in the pile hole. The grouting pipe is placed to the top surface of the poured concrete. The grouting pipe is 0.50m above the ground. Four grouting holes with a diameter of φ10 are evenly arranged 2.00m below the bottom of the grouting pipe. Sand and gravel are backfilled in the hole. Concrete is used to seal the 0.50m below the ground, and a return grouting pipe is buried; S5. Blocking of the entrance and exit of the culvert; S51. After pumping and dredging the culvert inlet and the first sandbag waterproof dam section, a 9.00m long grouting pipe is installed on the culvert arch. The grouting pipe is 0.50m beyond the culvert inlet. Six grouting holes are evenly arranged 3.00m below the grouting pipe to facilitate the subsequent grouting backfilling of the gap in the arch. Backfill soil at the culvert inlet and the first sandbag waterproof dam section and compact it layer by layer to the level of the culvert top. A concrete inlet is reserved at the top of the culvert inlet; S52. When pouring concrete 13 in the culvert 10 to the position of 8m from the outlet, at the outlet D point, first use a fan to supply air to the well, then arrange professional personnel to go down the well, lower sandbags from the wellhead into the well, and pile up sandbags several times within 3.00m of the outlet culvert. The height of the first pile of sandbags must be guaranteed to be able to drain the accumulated water and silt in the culvert, and the height of the subsequent piles of sandbags must be guaranteed to ensure that the concrete poured in the culvert cannot enter the drainage pipe outside the outlet. After the sandbags block the outlet, a 370mm brick wall must be built at the culvert outlet to block the outlet. During the construction of blocking the outlet by the underground personnel, the air supply in the hole cannot be interrupted. S6, grouting reinforcement; S7. Monitoring.

2. The method for filling a subsidence area and a culvert according to claim 1, characterized in that: The S1 comprises the following steps: S11. Conduct a careful and thorough survey of the ground along the culvert to find out whether there is any ground subsidence or cracking in other parts; S12. The plant general map has marked the distribution of the culverts, of which the AB section is 345.47m; the BC section is 110.92m; and the DE section is 54.39m. It is necessary to measure and locate the locations of the existing culvert inlets, outlets, and exposed collapsed parts, and put them on the general map to verify whether the culvert distribution is accurate. The elevations of the culvert inlets, outlets, and collapsed parts of the arches and bottoms are measured to confirm the buried depth of the culverts. S13. Two sandbag dams have been set up outside the culvert inlet to divert the water flow from the culvert inlet. It is necessary to fill clay soil outside the sandbag dam near the culvert inlet and compact it appropriately to prevent the water flow from the culvert inlet from continuing to enter the culvert, so as to stop the water from the culvert inlet. Then, a water pump is used to remove the remaining water from the culvert inlet, measure the plane dimensions and top and bottom elevations of the culvert, and measure the silt thickness at the culvert inlet. S14. Drainage pipes have been buried at the outlet of the culvert, and a wellhead has been reserved to connect with the culvert. To verify the plane dimensions of the culvert at the outlet, a fan must be used to supply air to the well first, and then professional personnel must be arranged to go down the well to take measurements. The air supply cannot be interrupted during this period.

3. The method for filling a factory building subsidence area and a culvert according to claim 1, characterized in that: The concrete slump requirement in S31 is 18-22 cm, and the arch height of the culvert 10 is 3.50 m. According to the designed concrete slump, the maximum horizontal flow distance of the concrete in the culvert will exceed 12 m. In S32, since the depth of the collapsed area reaches 9.00 meters, the thickness of the backfill concrete reaches 8.00 meters, and the volume of the backfill concrete is as high as 400 square meters, in order to eliminate the influence of hydration heat caused by concrete solidification, low hydration heat concrete materials can be used. If low hydration heat concrete cannot be provided locally, layered concrete pouring should be adopted.

4. The method for filling a factory building subsidence area and a culvert according to claim 1, characterized in that: The standard value of the composite foundation bearing capacity after the grouting reinforcement treatment of the collapsed fill in the lower part of S3 is recommended to be 180Kpa; After the pedestal and surrounding areas are reinforced by grouting, an independent foundation is designed on the backfill concrete. The surrounding area of ​​the independent foundation is backfilled with graded sand and gravel to the bottom elevation of the indoor ground cushion layer as a cushion layer to avoid uneven settlement with the surrounding foundation soil.

5. The method for filling a factory building subsidence area and a culvert according to claim 1, characterized in that: The grouting pipe is buried in S45 to facilitate the subsequent grouting reinforcement of the collapsed soil layer section that may not be found in the arch of the culvert, thereby eliminating the adverse hidden dangers caused by it.

6. The method for filling a factory building subsidence area and a culvert according to claim 1, characterized in that: The S6 comprises the following steps: S61. There may be undiscovered collapsed soil layers at the top of the culvert or unfilled concrete layers at the site. In the excavation area, another grouting hole is set between the two pile holes. In the filling area, two rows of grouting holes are set at 10-20cm on both sides of the culvert between the two pile holes at a spacing of @3200. The grouting holes in the excavation area are drilled with a φ110 drill rig and pass through the top of the culvert until the concrete layer is poured. The grouting holes in the filling area are drilled to the elevation of the top of the culvert, and a φ20PPR grouting pipe is placed in the hole. The grouting pipe is placed to the bottom of the drill hole, and the grouting pipe is 0.50m above the ground. Four φ10 grouting holes are evenly arranged 1.00m below the bottom of the grouting pipe. Cement mortar is used to seal the 0.50m below the ground, and a φ20PPR return grouting pipe is buried to facilitate grouting to reinforce the undiscovered collapsed soil layer and avoid uneven settlement of the indoor floor in the later stage. S62. Grouting uses PO42.5 acid cement, and the water-cement ratio of cement slurry is 1:

1. The principle of compaction grouting is to inject slurry into the stratum evenly through the grouting pipe. The slurry takes up its position after driving away the moisture and air between soil particles or rock and soil cracks by filling, infiltration and compaction. After a certain period of artificial control, the slurry consolidates the original loose soil, thereby increasing the bearing capacity of the fill and avoiding uneven settlement of the fill. The grouting pressure should be 0.5-2.0MPa. After the collapsed cavity at the intersection of the 24 axis and the J axis is backfilled with C15 concrete, the grouting under the cap is mainly used to reinforce the fill layer collapsed at the bottom of the culvert. The grouting pressure should be 1.0-2.0MPa, and the grouting pressure in other parts can be 0.5-1.0MPa. S63. After the grouting starts and the thick cement slurry emerges from the return grouting pipe, the return grouting pipe should be sealed with a closed piston, and then pressure grouting should be carried out; S64: Grouting can be stopped when the grouting speed is less than 5L / min or grouting appears on the ground surface; S65. When groundwater emerges from the surface during the grouting process, drainage ditches must be set up around the construction site and personnel must be arranged to use submersible pumps to drain the water out. Grouting should be carried out in a skip-hole interval grouting manner, with the grouting construction method starting from the outside and then the inside.

7. The method for filling a factory building subsidence area and a culvert according to claim 1, characterized in that: A cleaning device is used when cleaning the sludge in S24, and the cleaning device includes a movable seat, a base is installed on the surface of the movable seat, a box is installed on the surface of the base, a conveying device is provided on the surface of the base and on the side opposite to the box, and the conveying device includes a suction pump, and the input end and the output end of the suction pump are respectively connected to a first conveying pipe and a second conveying pipe, one end of the first conveying pipe is connected to the box, a suction assembly is provided on the surface of the base, a storage box is provided inside the box, and a feed hopper is provided on one side of the box.

8. The method for filling a factory building subsidence area and a culvert according to claim 7, characterized in that: The suction assembly comprises a telescopic rod, one end of which is connected to a suction tube, one side of which is connected to a plurality of suction heads, and one end of the second conveying tube is connected to one end of the suction head.

9. The method for filling a factory building subsidence area and a culvert according to claim 8, characterized in that: A placement frame is arranged on the surface of the telescopic rod, and the bottom of the placement frame is connected to the surface of the base.

10. The method for filling a factory building subsidence area and a culvert according to claim 7, characterized in that: A suspension assembly is provided on one side of the box body, and the suspension assembly includes a circular rod, a movable sleeve is provided on the surface of the circular rod, a circular connecting block is connected to one side of the movable sleeve, one end of the circular connecting block is connected to a rectangular plate, one side of the rectangular plate is connected to a fixing ring, a connecting bolt is provided inside the movable sleeve, the top and bottom ends of the circular rod are both connected to positioning blocks, and one end of the positioning block is connected to the side of the box body.