High-penetrating-power double-pipe vibration immersed pipe pedestal pile construction technology and equipment

Through the high-penetration double-tube vibrating immersed tube construction technology, the high-power high-frequency vibrating hammer and internal and external double casing technology are used to solve the penetration difficulties of immersed tube expansion piles in the deep gravel filling layer, and realize the penetration of the immersed tube expansion pile. Stable hole formation and efficient reinforcement improve the bearing capacity and construction efficiency of the piles.

CN118932994APending Publication Date: 2024-11-12SHANGHAI HARBOUR SOFT SOIL TREATMENT ENG (GRP) CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411055152.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-02
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

The existing immersed pipe expansion piles are difficult to penetrate deep gravel fillings, which cannot meet the depth requirements of foundation reinforcement, resulting in construction difficulties and insufficient bearing capacity.

Method used

The construction process of high penetration double-tube vibrating immersive tube is adopted. Through a high-power high-frequency vibrating hammer and an inner and outer double sleeve, the inner tube is used as a solid alloy steel prefabricated pile tip to impact the fragmented stone, the outer tube is used as a protective wall to form a hole, and passes through The vibrating filler forms an enlarged head until the design depth and bearing capacity are reached.

Benefits of technology

Effectively penetrate complex strata, solve the problems of neck shrinkage and collapse after hole formation, achieve stable hole formation and efficient reinforcement of deep gravel fill layers, and improve the bearing capacity and construction efficiency of piles.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118932994A_ABST
    Figure CN118932994A_ABST
Patent Text Reader

Abstract

The invention discloses a high-penetrating power double-tube vibration immersed tube pedestal pile construction technology and equipment, and relates to the technical field of foundation treatment, the high-penetrating power double-tube vibration immersed tube pedestal pile construction technology comprises the following steps: 1) double-tube immersed tube equipment is in place; (2) the holes are led to the designed pile bottom elevation through the double pipes, specifically, a vibratory hammer is started, the vibratory hammer drives the inner pipe and the outer pipe to synchronously sink, and the inner pipe and the outer pipe are sequentially vibrated to sink into a block gravel filling layer, a soft soil layer and a supporting layer from top to bottom to form holes till the designed pile bottom elevation is reached; (3) the filler is vibrated and compacted to form an expanded head; (4) the step (3) is repeated until the design requirement for the diameter of the expanded head is met; and (5) the inner pipe is pulled out, and pile body construction is completed. And 6) vibrating and pulling the outer pipe by a vibratory hammer, and combining the inner pipe and the outer pipe. The construction equipment comprises a vibratory hammer, a pile gripper, an inner pipe and an outer pipe, the outer pipe is sleeved with the inner pipe to form an inner sleeve and an outer sleeve, the inner pipe and the outer pipe are fixed through the pile gripper, and the vibratory hammer is arranged at the top of the pile gripper. The method solves the problem that current conventional immersed tube pedestal pile and carrier pile construction is difficult to penetrate through a block gravel filling layer.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of foundation treatment, and in particular to a high-penetration double-tube vibration sinking pipe bottom expansion pile construction process and equipment. Background Art

[0002] The sunken tube expanded base pile is a type of pile frequently used in the field of foundation reinforcement of construction projects at home and abroad. It includes an expanded head and a concrete pile body. Conventional sunken tube expanded base piles are made by sinking a casing into the foundation, filling the casing with filling material, and tamping the filling material with a heavy hammer or an internal tamping tube to form an expanded head at the pile end. The upper load can be effectively transferred to a better bearing layer through the pile body and the expanded head under the pile body, thereby improving the bearing capacity of the pile. It has the advantages of high single pile bearing capacity and economical cost.

[0003] At present, there is such a geological situation in foundation reinforcement. The soil layer contains block gravel fill or miscellaneous fill mainly composed of construction waste. The particle size distribution of the fill layer is very uneven, the soft and hard distribution is extremely uneven, and the thickness varies greatly. The maximum diameter is 1.2m and the maximum thickness is 22m. There is also a certain thickness of soft soil layer under the block gravel fill layer. The pile length is required to pass through the soft soil layer and reach a certain depth in the lower bearing layer. The maximum depth of soil is about 30m or more. In view of this geological situation, the pile sinking resistance is large, and the penetration force requirements of the construction equipment are very high. In the conventional bottom expansion pile construction process, it is difficult to sink the steel casing, making the construction difficult.

[0004] For example, a Chinese invention patent with an existing patent authorization announcement number of CN105821836B discloses a construction method for a carrier pile, and the steps are as follows: 1) sink the casing to a set depth; 2) sink a heavy hammer into the casing, and the gap between the heavy hammer and the casing can form an airflow channel and the cement mixture can pass smoothly; 3) perform filling and heavy hammer tamping operations simultaneously, and the bottom end of the heavy hammer does not go out of the upper mouth of the casing when it is lifted up, and the bottom end does not knock out of the casing when it is dropped and tamped, so as to ensure low drop distance and low energy tamping; 4) repeat step 3) to reinforce and compact the soil at the pile end; 5) control the density by three-hit penetration or filling amount standards to form a pile end carrier; 6) pour cement slurry or cement mortar; 7) construct a cast-in-place or prefabricated concrete pile body. The above construction method adopts the method of sinking the casing and tamping with a heavy hammer, and the casing is difficult to meet the penetration requirements of the block gravel fill layer and cannot penetrate the thick block gravel fill layer.

[0005] The existing Chinese invention patent with the patent authorization announcement number CN 114517472 B discloses a method for constructing a carrier pile. The technical solution provides a method for constructing a carrier pile, which directly uses the center hole of a prefabricated pipe pile to make a pile end carrier, fully combining the advantages of prefabricated pipe piles and carrier piles, significantly improving the bearing capacity of the pile and effectively avoiding the quality problems that are prone to occur in the pile body. Although the above construction method combines prefabricated pipe piles with carrier piles to solve the difficulties of drilling and blocking groundwater during the construction of ordinary carrier piles, prefabricated pipe piles are also unable to penetrate the thick block gravel fill layer and are difficult to meet the requirements. Summary of the invention

[0006] The purpose of the present invention is to solve the shortcomings of the prior art and to propose a high-penetration double-tube vibration sinking pipe expansion pile construction process and equipment to solve the problem that conventional sinking pipe expansion piles and carrier piles are difficult to penetrate the gravel fill layer.

[0007] In order to achieve the above object, the present invention adopts the following technical solutions:

[0008] A high-penetration double-tube vibration sinking pipe bottom expansion pile construction process comprises the following steps:

[0009] Step 1) The double-tube sinking equipment is in place: the inner and outer tubes are fixed by a vibrating hammer through a pile clamp, and the pile frame is aligned with the pile position;

[0010] Step 2) Double-tube hole leading to the designed pile bottom elevation: Turn on the vibrating hammer, which drives the inner and outer tubes to sink synchronously, and vibrate and sink them from top to bottom in the block gravel filling layer, soft soil layer, and bearing layer to form holes until the designed pile bottom elevation is reached. Then the vibrating hammer pulls out the inner tube, leaving the outer tube protective wall in the hole;

[0011] Step 3) Vibrating and compacting the filler to form an enlarged head: pour a portion of filler for forming the enlarged head from the upper opening of the outer tube to the bottom end of the outer tube, sink the inner tube into the outer tube, and vibrate and impact the filler with a vibrating hammer so that the filler is extruded from the bottom end of the outer tube to the bearing layer. The extruded filler and the soil within a certain depth and range under the pile end are reinforced and compacted to form an enlarged head;

[0012] Step 4) Repeat step 3) until the design requirements of the enlarged head diameter are met;

[0013] Step 5) Pull out the inner tube to complete the pile construction;

[0014] Step 6) Vibrate and pull out the outer tube with a vibrating hammer, and combine the inner and outer tubes: Vibrate and pull out the outer tube with a vibrating hammer, reassemble the inner and outer double casings, and move to the next pile position.

[0015] Furthermore, in step 2), after the vibration hammer pulls out the inner tube, the inner tube remains on the pile frame waiting for the next construction step.

[0016] Furthermore, in the step 3), the filler is a dry and hard material.

[0017] Furthermore, in step 4), when the bottom expansion diameter does not meet the design value, the filler is continuously vibrated and expanded until the design value is met.

[0018] Furthermore, in the step 5), the construction method of the pile body is as follows: a steel cage is placed in the outer tube, and the pile body concrete is poured until the pile top reaches the designed construction elevation, and then the outer tube is raised to form a pile. For plain concrete piles, the step of placing the steel cage is omitted.

[0019] A high-penetration double-tube vibration pipe sinking and bottom-enlarging pile construction equipment comprises a vibration hammer, a pile clamp, an inner tube and an outer tube. The inner tube is sleeved outside the outer tube to form an inner and outer double sleeve. The inner tube and the outer tube are fixed by the pile clamp. The vibration hammer is arranged on the top of the pile clamp.

[0020] Furthermore, the vibration hammer adopts a high-power and high-frequency vibration hammer.

[0021] Furthermore, the inner tube head is a solid alloy steel prefabricated conical pile tip, and the inner tube pile tip extends out of the outer tube head.

[0022] Furthermore, the outer diameter of the inner tube is consistent with the inner diameter of the outer tube, or the outer diameter of the inner tube is slightly smaller than the inner diameter of the outer tube.

[0023] Compared with the prior art, the present invention has the following beneficial effects:

[0024] The bottom-enlarged pile construction process of the present invention adopts a vibrating hammer combined with a double-tube vibrating pipe sinking to penetrate a deep gravel-containing block-containing fill layer, that is, a high-power high-frequency vibrating hammer is used for vibration impact to form a hole, and the inner and outer tubes are synchronously sunk by a vibrating hammer fixture. The end of the inner tube is equivalent to a solid alloy steel prefabricated pile tip, which can impact and crush the block stone directly below, and the outer tube is used for wall protection after the hole is formed, until the bottom-enlarged pile is formed by vibration impact of the block gravel fill layer, soft soil layer, and bearing layer, and then it is pulled out. It can not only effectively overcome the disadvantage that it is impossible to penetrate and form holes in complex formations such as pebbles, large boulders, and large stones, but also solve the problem of poor filling and obstruction of the hole mouth due to necking and collapse of the hole after the hole is formed in the conventional process. In addition, the bottom-enlarged pile of the present invention can be made of concrete throughout. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] Figure 1 The overall schematic diagram of the steel cage pile body is shown for the present invention;

[0026] Figure 2 The figure is an overall schematic diagram showing the plain concrete pile body of the present invention.

[0027] In the figure: 1. Vibratory hammer; 2. Pile clamp; 3. Inner pipe; 4. Outer pipe;

[0028] 100, gravel fill layer; 200, soft soil layer; 300, bearing layer. DETAILED DESCRIPTION

[0029] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments.

[0030] Figure 1 and Figure 2 They are schematic diagrams of the overall construction under two embodiments, wherein Figure 1 Shown is a schematic diagram of placing a steel cage pile body in one embodiment; Figure 2 Shown is a schematic diagram of a plain concrete pile body without a reinforcement cage in another embodiment.

[0031] like Figure 1-2 As shown, a high-penetration double-tube vibration pipe sinking and bottom-enlarging pile construction equipment includes a vibratory hammer 1, a pile clamp 2, an inner tube 3 and an outer tube 4. The inner tube 3 is sleeved outside the outer tube 4 to form an inner and outer double sleeve. The inner tube 3 and the outer tube 4 are fixed by the pile clamp 2, and the vibratory hammer 1 is provided on the top of the pile clamp 2.

[0032] The vibration hammer 1 adopts a high-power high-frequency vibration hammer 1. Preferably, the vibration hammer 11 adopts a high-power high-frequency vibration impact hammer of more than 300KW.

[0033] The head of the inner tube 3 is a solid alloy steel prefabricated conical pile tip, and the pile tip of the inner tube 3 extends out of the head of the outer tube 4. The solid alloy steel prefabricated conical pile tip is used to impact and crush the block stone directly below.

[0034] In a possible embodiment, the outer diameter of the inner tube 3 is consistent with the inner diameter of the outer tube 4.

[0035] Alternatively, the outer diameter of the inner tube 3 is slightly smaller than the inner diameter of the outer tube 4. Preferably, the outer diameter of the inner tube 3 is 5-20 mm smaller than the inner diameter of the outer tube 4.

[0036] In addition, the construction equipment of this embodiment also includes a pile frame (not shown in the figure). It should be noted that the pile frame is a prior art and will not be described in detail here.

[0037] Based on the given construction equipment, this embodiment also provides a high-penetration double-tube vibration sinking and bottom-expanding pile construction process, in which the inner tube 3 and the outer tube 4 are driven by a vibration hammer 1 to lead the double-tube holes to the designed pile bottom elevation, the filler is vibrated and compacted to form an enlarged head, and then the outer tube 4 is pulled out.

[0038] See also Figure 1-2 , specifically including the following steps:

[0039] Step 1) The double-tube sinking equipment is in place: the vibrating hammer 1 fixes the sleeved inner tube 3 and outer tube 4 through the pile clamp 2, and the pile frame is aligned with the pile position;

[0040] Step 2) Double-tube hole leading to designed pile bottom elevation: Turn on the vibrating hammer 1, the vibrating hammer 1 drives the inner tube 3 and the outer tube 4 to sink synchronously, and vibrates and sinks to the block gravel filling layer 100, the soft soil layer 200, and the bearing layer 300 from top to bottom in sequence to form holes until the designed pile bottom elevation is reached, and then the vibrating hammer 1 pulls out the inner tube 3, leaving the outer tube 4 in the hole to protect the wall; wherein, after the vibrating hammer 1 pulls out the inner tube 3, the inner tube 3 is retained on the pile frame waiting for the next step of construction;

[0041] Step 3) Vibrating and compacting the filler to form an enlarged head: pour a portion of the filler for forming the enlarged head from the upper opening of the outer tube 4 to the bottom end of the outer tube 4, sink the inner tube 3 into the outer tube 4, and vibrate and impact the filler with a vibrating hammer 1, so that the filler is extruded from the bottom end of the outer tube 4 to the bearing layer 300, and the extruded filler and the soil within a certain depth and range under the pile end are reinforced and compacted to form an enlarged head;

[0042] Step 4) Repeat step 3) until the design requirements of the enlarged head diameter are met; if the enlarged bottom diameter does not meet the design value, continue to vibrate and expand the filler until it meets the design value;

[0043] Step 5) pull out the inner tube 3 to complete the pile construction;

[0044] Step 6) The vibrating hammer 1 vibrates and pulls out the outer tube 4, and combines the inner and outer tubes 4: The vibrating hammer 1 vibrates and pulls out the outer tube 4, and recombines the inner and outer double casings, and moves to the next pile position.

[0045] More specifically, in step 3), the filler is a dry hard material, and the filler amount is not less than 0.5m 3 .

[0046] In step 5), the construction method of the pile body is as follows: a steel cage is placed in the outer tube 4, and the pile body concrete is poured until the pile top is designed and constructed at the elevation, and then the outer tube 4 is raised to form a pile. For plain concrete piles, the step of placing the steel cage is omitted (see Figure 2 ).

[0047] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical scheme and inventive concept of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.

Claims

1. A high-penetration double-tube vibration sinking pipe expansion pile construction process, characterized in that: The following steps are involved: Step 1) The double-tube sinking equipment is in place: the inner and outer tubes are fixed by a vibrating hammer through a pile clamp, and the pile frame is aligned with the pile position; Step 2) Double-tube hole leading to the designed pile bottom elevation: Turn on the vibrating hammer, which drives the inner and outer tubes to sink synchronously, and vibrate and sink them from top to bottom in the block gravel filling layer, soft soil layer, and bearing layer to form holes until the designed pile bottom elevation is reached. Then the vibrating hammer pulls out the inner tube, leaving the outer tube protective wall in the hole; Step 3) Vibrating and compacting the filler to form an enlarged head: pour a portion of filler for forming the enlarged head from the upper opening of the outer tube to the bottom end of the outer tube, sink the inner tube into the outer tube, and vibrate and impact the filler with a vibrating hammer so that the filler is extruded from the bottom end of the outer tube to the bearing layer. The extruded filler and the soil within a certain depth and range under the pile end are reinforced and compacted to form an enlarged head; Step 4) Repeat step 3) until the design requirements of the enlarged head diameter are met; Step 5) Pull out the inner tube to complete the pile construction; Step 6) Vibrate and pull out the outer tube with a vibrating hammer, and combine the inner and outer tubes: Vibrate and pull out the outer tube with a vibrating hammer, reassemble the inner and outer double casings, and move to the next pile position.

2. The high-penetration double-tube vibration sinking and bottom-enlarging pile construction process according to claim 1 is characterized in that: In step 2), after the inner pipe is pulled out by the vibration hammer, the inner pipe remains on the pile frame and waits for the next construction step.

3. The high-penetration double-tube vibration sinking and bottom-enlarging pile construction process according to claim 1 is characterized in that: In the step 3), the filler is a dry and hard material.

4. The high-penetration double-tube vibration sinking and bottom-enlarging pile construction process according to claim 1 is characterized in that: In step 4), when the bottom expansion diameter does not meet the design value, the filler is continuously vibrated and expanded until the design value is met.

5. The high-penetration double-tube vibration sinking and bottom-enlarging pile construction process according to claim 1 is characterized in that: In step 5), the construction method of the pile body is as follows: a steel cage is placed in the outer tube, and the pile body concrete is poured until the pile top is designed to be at the construction elevation, and then the outer tube is raised to form a pile. For plain concrete piles, the step of placing the steel cage is omitted.

6. A high-penetration double-tube vibration sinking pipe bottom expansion pile construction equipment, characterized in that: It comprises a vibrating hammer, a pile clamp, an inner tube and an outer tube. The inner tube is sleeved outside the outer tube to form an inner and outer double sleeve. The inner tube and the outer tube are fixed by the pile clamp. The vibrating hammer is arranged on the top of the pile clamp.

7. The high-penetration double-tube vibration sinking and bottom-enlarging pile construction equipment according to claim 6 is characterized in that: The vibration hammer adopts a high-power high-frequency vibration hammer.

8. The high-penetration double-tube vibration sinking and bottom-enlarging pile construction equipment according to claim 6 is characterized in that: The inner tube head is a solid alloy steel prefabricated conical pile tip, and the inner tube pile tip extends out of the outer tube head.

9. The high-penetration double-tube vibration sinking and bottom-enlarging pile construction equipment according to claim 6 is characterized in that: The outer diameter of the inner tube is consistent with the inner diameter of the outer tube, or the outer diameter of the inner tube is slightly smaller than the inner diameter of the outer tube.