Mobile prefabricated mortar tank construction method
Through the construction method of mobile prefabricated mortar tanks, using line laying devices and template casting technology, the problem of the inability to move and reuse of existing mortar tank foundations is solved, and construction efficiency and resource utilization are improved.
Patent Information
- Application Number
- CN202411186342.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-28
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2044-08-28
AI Technical Summary
The foundation of the existing mortar tank cannot be moved and cannot be reused, resulting in low construction efficiency and waste of resources.
The construction method of mobile prefabricated mortar tank is adopted, and the position of the ground embedded parts is determined through the wiring arrangement, the waterproof oil cloth is laid, the combined parts are poured in the formwork, and the positioning components are quickly disassembled and assembled.
It realizes flexible movement and reuse of mortar tanks, improves construction efficiency, and reduces labor costs and material waste.
Smart Images

Figure CN118933350A_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of mobile prefabricated mortar tanks, and in particular, relates to a construction method of a mobile prefabricated mortar tank. Background Art
[0002] In the field of construction, in order to improve the efficiency and convenience of plastering operations, mortar tanks are widely used around single buildings as key equipment. In order to ensure the stable operation of the mortar tank and effectively distribute its load, a dedicated foundation structure is usually built underneath it, mainly in two forms: brick mortar tank foundation and cast-in-place concrete mortar tank foundation.
[0003] Brick mortar tank foundations have been widely used in previous projects due to their easy availability and construction. However, once built, this foundation is fixed and cannot adapt to the dynamic changes in the construction site. As the project progresses, the distance that workers have to travel to pick up materials may gradually increase, causing the mortar tank foundation at the original site to no longer meet actual needs, affecting construction efficiency.
[0004] On the other hand, although cast-in-place concrete mortar tank foundations have higher bearing capacity and stability, they also face the problem of being immovable. More importantly, whether it is brickwork or cast-in-place concrete foundations, it is difficult to reuse the materials after the project is completed. These foundation structures often need to be broken down manually, and the materials are often damaged in the process and cannot be effectively recycled, which increases construction costs and causes waste of resources. Summary of the invention
[0005] In view of this, the present invention provides a construction method of a mobile prefabricated mortar tank, which can solve the problem that the existing mortar tank cannot be moved and reused.
[0006] The present invention is achieved in that:
[0007] The present invention provides a construction method for a mobile prefabricated mortar tank, which comprises the following specific steps:
[0008] S10: Clean the construction site, compact the ground, calibrate the horizontal plane, and then lay out the lines using a laying-out device. The range of the laying-out should match the size of the mortar tank.
[0009] S20: fixing the embedded parts on the horizontal plane after the laying out, laying the tarpaulin, and fixing the tarpaulin to the embedded parts;
[0010] S30: Casting each part of the structure of the prefabricated mortar tank according to the drawing of the prefabricated mortar tank, and fixing an anti-sticking layer on the surface;
[0011] S40: moving the first assembly component, the second assembly component and the third assembly component constituting the prefabricated mortar tank to the construction site, and fixing the first assembly component and the second assembly component to the embedded part;
[0012] S50: installing a positioning assembly on the top of the first assembly component and the second assembly component, so that the third assembly component is quickly docked with the top of the first assembly component and the second assembly component and then plugged and fixed;
[0013] S60: After water is injected, the sealing of the assembled mortar tank is checked, and the construction of the mortar tank is completed after it is confirmed to be completely sealed;
[0014] S70: After the mortar tank is used up, it is disassembled and moved.
[0015] On the basis of the above technical solution, the construction method of a mobile prefabricated mortar tank of the present invention can also be improved as follows:
[0016] Wherein, the line-laying device comprises a central shaft, a support assembly, a level assembly and a marking assembly, wherein the central shaft is arranged at a central position, the support assembly is fixed on the side wall of the central shaft, the marking assembly is sleeved on the central shaft and supported by the support assembly, and the support assembly is used to determine the horizontal plane of the marking assembly rotating on the side wall of the central shaft; the top of the central shaft is connected to the level assembly, and the level assembly is used to ensure the verticality of the central shaft and keep the central shaft fixed by gravity;
[0017] The central axis includes a fixed rod, a slide rail and an insertion drill, wherein the insertion drill is fixed to the top of the fixed rod and is used to fix the line-releasing device on the ground; the fixed rod is a vertical rod structure, and the slide rail is arranged on the side wall of the fixed rod; the insertion drill is a hexagonal structure, and a channel is passed from the bottom to the top, and the channel is used to guide the soil at the bottom when rotating and drilling below the ground;
[0018] The support assembly is fixed to the upper and lower sides of the slide rail, and includes a fixed part and a movable part. The fixed part is fixed to the bottom of the slide rail and is flush with the bottom edge of the slide rail. The movable part is fixed to the top of the slide rail by a thread and is flush with the top edge of the slide rail. The diameter of the fixed part is larger than the diameter of the movable part. The top of the slide rail is provided with a thread, and the thread matches the thread on the inner wall of the movable part.
[0019] The marking assembly is sleeved on the slide rail and fixed in the slide rail by the fixing member and the movable member; the fixing member is used to support the weight of the marking assembly; the marking assembly includes an inner rotating ring, a gear, an outer rotating ring and a support rod, the gear includes a fixed gear and a rotating gear, the fixed gear is fixed on the outer wall of the slide rail, the rotating gear is fixed on the inner wall of the inner rotating ring, and the fixed gear is meshed and connected with the rotating gear; the height of the fixed gear and the rotating gear is the same as the height between the fixing member and the movable member; the outer rotating ring is a double-ring structure, and 4 triangles are symmetrically fixed inside it, and the triangles are all equilateral triangles, and the corresponding positions of adjacent triangles are 90° apart; two of the corners of the triangle are respectively fixed to the double rings of the outer rotating ring, and the other corner is set at the center position of the double rings of the outer rotating ring; nozzles are fixed at the bottom of the three corners of the triangle, and marking powder is placed inside the nozzle. The bottom of the nozzle is vertically downward, which is used to lay out the horizontal plane by spraying marking powder;
[0020] The level assembly includes a support rod, a vertical line and a weight. A plug rod is fixed on the top of the central axis. A through hole is provided at the center of the support rod. The support rod is fixed to the top of the central axis by inserting the plug rod through the through hole. The weights are fixed to the left and right sides of the support rod symmetrically through the vertical line. The central axis is kept in a vertical downward state by the gravity of the weights at the symmetrical positions.
[0021] The outer ring diameter and the inner ring diameter of the outer rotating ring are respectively the same as the outer wall diameter and the inner wall diameter of the prefabricated mortar tank.
[0022] Furthermore, the construction site is cleaned, the ground is compacted, and the horizontal plane is calibrated before laying out the line through a laying-out device. The specific steps for matching the size of the mortar tank with the laying-out range are as follows:
[0023] The first step is to remove debris and garbage on the site, check whether there are obvious potholes and cracks on the ground and repair them;
[0024] The second step is to compact the entire ground evenly by vibrating the ground to improve its density and bearing capacity;
[0025] The third step is to calibrate the levelness of the ground using an optical level;
[0026] The fourth step is to move the wire-laying device to the construction site for assembly;
[0027] The fifth step is to quickly lay out the ground to determine the fixed position of the embedded parts;
[0028] The specific steps of moving the wire-laying device to the construction site for assembly include:
[0029] The first step is to select the center of the mortar tank installation and vertically insert the fixing rod into the ground corresponding to the center;
[0030] The second step is to fix the scribing assembly on the fixing member, and screw the movable member on the top of the scribing assembly;
[0031] The third step is to fix the level assembly on the top of the fixing rod, and adjust the position of the vertical line and the weight so that the fixing rod is always perpendicular to the ground;
[0032] Step 4: placing marking powder inside the nozzle;
[0033] The specific steps of quickly laying out the ground and determining the fixed position of the embedded part include:
[0034] Rotate the marking assembly to mark the starting point of the angle where the four triangles are away from the outer rotating ring, and then mark the angular position where the four triangles are away from the outer rotating ring in sequence every time the circumference of the gear is rotated by 1 / 12, and calibrate by rotating multiple times;
[0035] The central shaft, the support assembly and the scribing assembly are all made of lightweight materials.
[0036] Furthermore, the embedded parts include 12 pieces, which are respectively fixed at the marking positions of the scribing assembly; the embedded parts include a fixing part and a clamping part, the fixing part is a quadrangular pyramid structure, and is embedded at the marking position; the clamping part is arranged at the top of the fixing part, and the clamping part includes a compression plate and a connecting spring, one end of the connecting spring is fixed to both sides of the top of the fixing part, and the other end is connected to the connecting spring; there are at least two compression plates and connecting springs, and the two compression plates are arranged obliquely, and the angle between the top inner walls they contact is 30-60°.
[0037] Furthermore, the specific steps of fixing the embedded parts on the horizontal plane after laying out the wires include:
[0038] The first step is to dig a hole with a diameter larger than the bottom diameter of the fixing part at each of the 12 positions marked when the marking assembly is laid out, and then tamp the surroundings of the hole after pre-burying the fixing part in the corresponding hole;
[0039] The second step is to adjust the embedded parts to be vertically upward during the compaction process;
[0040] The specific steps of laying the tarpaulin and fixing the tarpaulin to the embedded parts include:
[0041] The first step is to draw a circle on the top of the tarpaulin with a compass that is identical to the inner and outer walls of the bottom of the mortar tank;
[0042] Step 2: Draw points in the middle of the two circles according to the positions of the 12 marks;
[0043] Step 3: Draw cross lines at 12 points respectively, wherein the cross lines are limited between two circles;
[0044] Step 4, fix the tarpaulin on a horizontal plane, with each corresponding cross line passing through the embedded part;
[0045] Step 5: Clean up the edges of the cross lines.
[0046] Further, the first assembly component and the second assembly component are symmetrical structures, respectively being semi-arc structures cast in concrete, with an inward depression on one side and an outward protrusion on the other side, the inward depression and the outward protrusion being arranged correspondingly, for splicing and fixing the first assembly component and the second assembly component; the diameters of the depression and the protrusion are smaller than the outer wall diameters of the first assembly component and the second assembly component, and larger than the inner wall diameters of the first assembly component and the second assembly component;
[0047] The tops of the first assembly component and the second assembly component are provided with downward plugging slots;
[0048] Six grooves are evenly distributed at the center of the bottom of the first assembly component and the second assembly component, and the size of the grooves is the same as the size of the pressing part;
[0049] The third component is a circular ring structure, and a plug-in protrusion is provided at the bottom thereof, and the plug-in protrusion has the same size as the plug-in grooves at the tops of the first component and the second component; a lifting ring is provided at the top of the third component, and the lifting ring is used to facilitate the installation of the third component after lifting;
[0050] The bottom of the inner concave surface of the first assembly component and the second assembly component is provided with an inwardly recessed double-layer annular groove, and a rubber ring of the same shape is fixed correspondingly during installation to seal the bottom of the mortar tank composed of the first assembly component and the second assembly component.
[0051] The beneficial effects of adopting the above-mentioned improvement scheme are: the symmetrical structure facilitates the installation and disassembly of the mortar tank, and the setting of the protrusions and recesses facilitates the docking of the first assembly component and the second assembly component, the docking of the first assembly component and the third assembly component, and the docking of the second assembly component and the third assembly component.
[0052] The annular third assembly component is used to prevent the first assembly component and the second assembly component from being separated from the top during use, thereby extending the service life after installation.
[0053] Furthermore, the specific steps of casting each part of the structure of the prefabricated mortar tank according to the drawing of the prefabricated mortar tank and fixing the anti-sticking layer on the surface include:
[0054] The first step is to clean the mold and ensure that the inner surface of the template is clean, free of oil and dust;
[0055] The second step is to install the various parts of the template according to the drawing dimensions, ensuring that the template is firmly fixed and accurately built according to the design dimensions;
[0056] In the third step, use a level and measuring tools to check the alignment of the template to ensure that it meets the design requirements in all directions;
[0057] The fourth step is to support the formwork to ensure its stability during the pouring process;
[0058] Step 5: Evenly apply the anti-sticking layer material on the inner surface of the template;
[0059] Step 6: Mix cement, sand, gravel and water according to the required proportions and stir into uniform concrete;
[0060] Step 7: Pour the concrete into the formwork, making sure to evenly fill each part, and use a vibrator to vibrate the concrete to remove air bubbles and ensure that the concrete is dense.
[0061] Step 8: Use a scraper or trowel to smooth the concrete surface to ensure it is smooth and flat;
[0062] The ninth step is to maintain the poured concrete and keep it moist;
[0063] Step 10: After the concrete reaches the designed strength, remove the formwork at the prescribed time;
[0064] Step 11: Check whether the surface of the prefabricated mortar tank after demolding meets the requirements and ensure that there are no defects;
[0065] In the twelfth step, an anti-sticking layer is fixed on the surface of each part of the prefabricated mortar tank.
[0066] The beneficial effects of adopting the above-mentioned improvement scheme are as follows: Further, the material of the anti-sticking layer is polytetrafluoroethylene, polyurethane, epoxy resin, silicone rubber or special anti-sticking coating.
[0067] Furthermore, the specific steps of fixedly connecting the first assembly component and the second assembly component to the embedded part include:
[0068] The first step is to lift the first combined component and set it at the top adjustment position of the embedded part;
[0069] The second step is to slowly lower the first assembly component and align it with the six embedded parts by shaking it left and right, and then put it down;
[0070] The third step is to repeat the above process to fix the second assembly component to the corresponding six embedded parts;
[0071] In the fourth step, the construction personnel enter the structure composed of the first assembly component and the second assembly component, and fix the rubber ring in the double-layer ring groove.
[0072] The beneficial effect of adopting the above-mentioned improvement scheme is: by arranging the first and second combined components to be fixedly connected to the embedded parts, the first and second combined components are prevented from shaking during use, and the risk of collapse of the first and second combined components is reduced.
[0073] The provision of the rubber ring prevents cement from overflowing from the bottom of the first assembly component and the second assembly component.
[0074] Furthermore, the rubber ring is made of chloroprene rubber, butyl rubber or ethylene propylene rubber.
[0075] Furthermore, the positioning assembly includes docking ears and a guide rope, the docking ears include at least one group, each group includes two, which are respectively fixed at corresponding positions of the first assembly component, the second assembly component and the third assembly component, one end of the guide rope is fixed in the docking ears on the first assembly component and the second assembly component, and the other end passes through the corresponding docking ears on the third assembly component.
[0076] The beneficial effect of adopting the above-mentioned improvement scheme is that by setting the positioning component, the third assembly component can be conveniently docked above the first assembly component and the second assembly component, which reduces the time consumed repeatedly during lifting and improves efficiency.
[0077] Furthermore, the specific steps of installing a positioning assembly on the top of the first assembly component and the second assembly component so that the third assembly component is quickly docked with the top of the first assembly component and the second assembly component and then plugged and fixed include:
[0078] The third assembly component is hoisted so that the guide rope passes through the docking ear on the third assembly component, and the guide rope is retracted inward to guide the third assembly component to a corresponding position for plugging and fixing.
[0079] Compared with the prior art, the beneficial effects of the mobile prefabricated mortar tank construction method provided by the present invention are:
[0080] Freedom of site selection: the present invention can hoist and assemble the first assembly component, the second assembly component and the third assembly component at any time for installation and disassembly, and the installation site can be freely selected according to the user's wishes.
[0081] High efficiency and low labor cost: The present invention has a fast installation and disassembly speed and saves labor. Compared with the traditional manual laying out and masonry, or formwork pouring and concrete pouring, it only needs to prefabricate the concrete components in advance, drag them with the truck, and immediately hoist and assemble them, which takes less time.
[0082] Saving materials: The present invention saves materials, is installed once and can be recycled. After the project is completed, the separated parts can be hoisted to reduce the floor space, put into the warehouse, and continue to be put into use at the next construction site.
[0083] High precision and convenient construction: The present invention uses a positioning component to facilitate the docking of the third assembly component with the first assembly component and the second assembly component during hoisting, thereby improving the docking accuracy and reducing the docking time. BRIEF DESCRIPTION OF THE DRAWINGS
[0084] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the accompanying drawings required for use in the description of the embodiments of the present invention will be briefly introduced below. Obviously, the accompanying drawings in the following description are only some embodiments of the present invention. For ordinary technicians in this field, other accompanying drawings can be obtained based on these accompanying drawings without paying creative labor.
[0085] Figure 1 It is a schematic diagram of a construction method of a mobile prefabricated mortar tank;
[0086] Figure 2 It is a schematic diagram of a wire-laying device in a construction method of a mobile prefabricated mortar tank;
[0087] Figure 3 It is a vertical cross-sectional schematic diagram of a wire-laying device in a mobile prefabricated mortar tank construction method;
[0088] Figure 4 It is a cross-sectional schematic diagram of a wire-laying device in a mobile prefabricated mortar tank construction method;
[0089] Figure 5 It is a schematic diagram of embedded parts in a construction method of a mobile prefabricated mortar tank;
[0090] Figure 6 A schematic diagram of a prefabricated mortar tank for a mobile prefabricated mortar tank construction method;
[0091] In the accompanying drawings, the components represented by the reference numerals are listed as follows:
[0092] 10. Pay-off device; 11. Center axis; 111. Fixed rod; 112. Slide rail; 113. Insert drill; 12. Support assembly; 121. Fixed part; 122. Movable part; 13. Level assembly; 131. Support rod; 132. Plumb line; 133. Weight; 14. Marking assembly; 141. Inner rotating ring; 142. Gear; 1421. Fixed gear; 1422. Rotating gear; 143. Outer rotating ring; 144. Support rod; 20. Embedded part; 21. Fixed part; 22. Pressing part; 221. Compression plate; 222. Connecting spring; 30. First assembly component; 40. Second assembly component; 50. Third assembly component; 60. Positioning assembly; 61. Docking ear; 62. Guide rope. DETAILED DESCRIPTION
[0093] In order to make the purpose, technical solution and advantages of the embodiments of the present invention more clear, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the present invention.
[0094] like Figure 1 , Figure 5 , Figure 6 FIG. 1 is a first embodiment of a mobile prefabricated mortar tank construction method provided by the present invention. In this embodiment, the method comprises the following specific steps:
[0095] S10: Clean the construction site, compact the ground, calibrate the horizontal plane, and then lay out the lines through the laying device 10. The range of the laying out matches the size of the mortar tank.
[0096] S20: fixing the embedded component 20 on the horizontal plane after the line is laid, and laying a tarpaulin to fix the tarpaulin and the embedded component 20;
[0097] S30: Casting each part of the structure of the prefabricated mortar tank according to the drawing of the prefabricated mortar tank, and fixing an anti-sticking layer on the surface;
[0098] S40: moving the first assembly component 30, the second assembly component 40 and the third assembly component 50 constituting the prefabricated mortar tank to the construction site, and fixing the first assembly component 30 and the second assembly component 40 to the embedded part 20;
[0099] S50: Install the positioning assembly 60 on the top of the first assembly component 30 and the second assembly component 40, so that the third assembly component 50 is quickly docked with the top of the first assembly component 30 and the second assembly component 40 and then plugged and fixed;
[0100] S60: After water is injected, the sealing of the assembled mortar tank is checked, and the construction of the mortar tank is completed after it is confirmed to be completely sealed;
[0101] S70: After the mortar tank is used up, it is disassembled and moved.
[0102] like Figure 2 , Figure 3 , Figure 4 Among them, in the above technical solution, the line-releasing device 10 includes a central shaft 11, a support assembly 12, a level assembly 13 and a marking assembly 14. The central shaft 11 is arranged at a central position, the support assembly 12 is fixed on the side wall of the central shaft 11, the marking assembly 14 is sleeved on the central shaft 11 and is limitedly supported by the support assembly 12, and the support assembly 12 is used to determine the horizontal plane of the marking assembly 14 rotating on the side wall of the central shaft 11; the top of the central shaft 11 is connected to the level assembly 13, and the level assembly 13 is used to ensure the verticality of the central shaft 11 and keep the central shaft 11 fixed by gravity;
[0103] The central shaft 11 includes a fixed rod 111, a slide rail 112 and an insert drill 113. The insert drill 113 is fixed to the top of the fixed rod 111 and is used to fix the line-releasing device 10 on the ground. The fixed rod 111 is a vertical rod structure, and the slide rail 112 is arranged on the side wall of the fixed rod 111. The insert drill 113 is a hexagonal structure, and a channel is passed from the bottom to the top, and the channel is used to guide the soil at the bottom when rotating and drilling below the ground.
[0104] The support assembly 12 is fixed to the upper and lower sides of the slide rail 112, and includes a fixed part 121 and a movable part 122. The fixed part 121 is fixed to the bottom of the slide rail 112 and is flush with the bottom edge of the slide rail 112; the movable part 122 is fixed to the top of the slide rail 112 by threads and is flush with the top edge of the slide rail 112; the diameter of the fixed part 121 is larger than the diameter of the movable part 122; the top of the slide rail 112 is provided with threads, and the threads match the threads on the inner wall of the movable part 122;
[0105] The marking assembly 14 is sleeved on the slide rail 112 and fixed in the slide rail 112 by means of a fixing member 121 and a movable member 122; the fixing member 121 is used to support the weight of the marking assembly 14; the marking assembly 14 includes an inner rotating ring 141, a gear 142, an outer rotating ring 143 and a support rod 144, the gear 142 includes a fixed gear 1421 and a rotating gear 1422, the fixed gear 1421 is fixed on the outer wall of the slide rail 112, the rotating gear 1422 is fixed on the inner wall of the inner rotating ring 141, and the fixed gear 1421 is meshed and connected with the rotating gear 1422; the fixed gear 1421 is meshed and connected with the rotating gear 1422; 421, the height of the rotating gear 1422 is the same as the height between the fixed part 121 and the movable part 122; the outer rotating ring 143 is a double-ring structure, and 4 triangles are symmetrically fixed inside it, and the triangles are all equilateral triangles, and the corresponding positions of adjacent triangles are 90° apart; two corners of the triangle are respectively fixed to the double rings of the outer rotating ring 143, and the other corner is set at the center position of the double rings of the outer rotating ring 143; nozzles are fixed at the bottom of the three corners of the triangle, and marking powder is placed inside the nozzle. The bottom of the nozzle is vertically downward, which is used to lay out the horizontal plane by spraying the marking powder;
[0106] The level assembly 13 includes a support rod 131, a vertical line 132 and a weight 133. A plug rod is fixed on the top of the central axis 11. A through hole is provided at the center of the support rod 131. The support rod 131 is fixed on the top of the central axis 11 by inserting the plug rod into the through hole. Weights 133 are fixed to the left and right sides of the support rod 131 at symmetrical positions through the vertical line 132. The gravity of the weights 133 at the symmetrical positions keeps the central axis 11 in a vertical downward state.
[0107] The outer ring diameter and the inner ring diameter of the outer rotating ring 143 are respectively the same as the outer wall diameter and the inner wall diameter of the prefabricated mortar tank.
[0108] Furthermore, in the above technical solution, the construction site is cleaned, the ground is compacted, and the horizontal plane is calibrated before laying out the line through the laying-out device 10. The specific steps for matching the size of the mortar tank with the range of laying out the line are as follows:
[0109] The first step is to remove debris and garbage on the site, check whether there are obvious potholes and cracks on the ground and repair them;
[0110] The second step is to compact the entire ground evenly by vibrating the ground to improve its density and bearing capacity;
[0111] The third step is to calibrate the levelness of the ground using an optical level;
[0112] The fourth step is to move the wire-laying device 10 to the construction site for assembly;
[0113] The fifth step is to quickly lay out the ground to determine the fixed position of the embedded part 20;
[0114] The specific steps of moving the wire-laying device 10 to the construction site for assembly include:
[0115] The first step is to select the center of the mortar tank installation and vertically insert the fixing rod 111 into the ground corresponding to the center;
[0116] The second step is to fix the scribing assembly 14 on the fixing member 121 and screw the movable member 122 on the top of the scribing assembly 14;
[0117] The third step is to fix the level assembly 13 on the top of the fixed rod 111, and adjust the positions of the vertical line 132 and the weight 133 so that the fixed rod 111 is always perpendicular to the ground;
[0118] Step 4: Place marking powder inside the nozzle;
[0119] The specific steps of quickly laying out the ground and determining the fixed position of the embedded part 20 include:
[0120] Rotate the marking assembly 14 to mark the starting point of the angle of the four triangles away from the outer rotating ring 143, and then mark the angular position of the four triangles away from the outer rotating ring 143 in sequence every 1 / 12 of the circumference of the gear 142, and rotate multiple times for calibration;
[0121] The central shaft 11 , the support assembly 12 and the scribing assembly 14 are all made of lightweight materials.
[0122] Among them, lightweight materials are composed of aluminum alloy, magnesium alloy, carbon fiber and other materials.
[0123] Furthermore, in the above technical solution, the embedded parts 20 include 12 pieces, which are respectively fixed at the marking positions of the scribing assembly 14; the embedded parts 20 include a fixing portion 21 and a clamping portion 22, the fixing portion 21 is a quadrangular pyramid structure, and is embedded at the marking position; the clamping portion 22 is arranged at the top of the fixing portion 21, and the clamping portion 22 includes a compression plate 221 and a connecting spring 222, one end of the connecting spring 222 is fixed on both sides of the top of the fixing portion 21, and the other end is connected to the connecting spring 222; there are at least two compression plates 221 and connecting springs 222, and the two compression plates 221 are inclined, and the angle between the top inner walls they contact is 30-60°.
[0124] Furthermore, in the above technical solution, the specific steps of fixing the embedded part 20 on the horizontal plane after laying out the wires include:
[0125] The first step is to dig a hole with a diameter larger than the bottom diameter of the fixing part 21 at each of the 12 positions marked when the marking assembly 14 is laid out, and then tamp the surroundings of the hole after pre-burying the fixing part 21 in the corresponding hole;
[0126] The second step is to adjust the embedded part 20 to be vertically upward during the compaction process;
[0127] The specific steps of laying the tarpaulin and fixing the tarpaulin to the embedded part 20 include:
[0128] In the first step, use a compass to draw a circle on the top of the tarpaulin that is the same as the inner and outer walls of the bottom of the mortar pot;
[0129] Step 2: Draw points in the middle of the two circles according to the positions of the 12 marks;
[0130] The third step is to draw cross lines at 12 points, and the cross lines are limited to between two circles;
[0131] Step 4, fix the tarpaulin on a horizontal surface, with each corresponding cross line passing through the embedded part 20;
[0132] Step 5: Clean up the edges of the cross lines.
[0133] Further, in the above technical solution, the first assembly component 30 and the second assembly component 40 are symmetrical structures, which are semi-arc structures cast in concrete, one side of which is provided with an inward depression, and the other side is provided with an outward protrusion, and the inward depression and the outward protrusion are correspondingly arranged to splice and fix the first assembly component 30 and the second assembly component 40; the diameter of the depression and the protrusion is smaller than the outer wall diameter of the first assembly component 30 and the second assembly component 40, and larger than the inner wall diameter of the first assembly component 30 and the second assembly component 40;
[0134] The tops of the first assembly component 30 and the second assembly component 40 are provided with downward insertion slots;
[0135] Six grooves are evenly distributed at the center of the bottom of the first assembly component 30 and the second assembly component 40, and the size of the grooves is the same as the size of the pressing portion 22;
[0136] The third assembly component 50 is a circular ring structure, and a plug-in protrusion is provided at the bottom thereof, and the plug-in protrusion has the same size as the plug-in grooves at the top of the first assembly component 30 and the second assembly component 40; a lifting ring is provided at the top of the third assembly component 50, and the lifting ring is used to facilitate the installation of the third assembly component 50 after lifting;
[0137] The bottom of the inner concave surface of the first assembly component 30 and the second assembly component 40 is provided with an inwardly recessed double-layer annular groove, and a rubber ring of the same shape is fixed correspondingly during installation to seal the bottom of the mortar tank composed of the first assembly component 30 and the second assembly component 40.
[0138] Furthermore, in the above technical solution, the specific steps of casting each part of the structure of the prefabricated mortar tank according to the drawing of the prefabricated mortar tank and fixing the anti-sticking layer on the surface include:
[0139] The first step is to clean the mold and ensure that the inner surface of the template is clean, free of oil and dust;
[0140] The second step is to install the various parts of the template according to the drawing dimensions, ensuring that the template is firmly fixed and accurately built according to the design dimensions;
[0141] In the third step, use a level and measuring tools to check the alignment of the template to ensure that it meets the design requirements in all directions;
[0142] The fourth step is to support the formwork to ensure its stability during the pouring process;
[0143] Step 5: Evenly apply the anti-sticking layer material on the inner surface of the template;
[0144] Step 6: Mix cement, sand, gravel and water according to the required proportions and stir into uniform concrete;
[0145] Step 7: Pour the concrete into the formwork, making sure to evenly fill each part, and use a vibrator to vibrate the concrete to remove air bubbles and ensure that the concrete is dense.
[0146] Step 8: Use a scraper or trowel to smooth the concrete surface to ensure it is smooth and flat;
[0147] The ninth step is to maintain the poured concrete and keep it moist;
[0148] Step 10: After the concrete reaches the designed strength, remove the formwork at the prescribed time;
[0149] Step 11: Check whether the surface of the prefabricated mortar tank after demolding meets the requirements and ensure that there are no defects;
[0150] In the twelfth step, an anti-sticking layer is fixed on the surface of each part of the prefabricated mortar tank.
[0151] Furthermore, in the above technical solution, the specific steps of fixing the first assembly component 30 and the second assembly component 40 to the embedded component 20 include:
[0152] The first step is to lift the first assembly component 30 and set it at the top adjustment position of the embedded part 20;
[0153] The second step is to slowly lower the first assembly component 30 and align the six embedded components 20 by shaking left and right, and then lower the first assembly component 30;
[0154] Step 3: Repeat the above process to fix the second assembly component 40 to the corresponding six embedded parts 20;
[0155] In the fourth step, the construction personnel enter the structure composed of the first assembly component 30 and the second assembly component 40 and fix the rubber ring in the double-layer ring groove.
[0156] Furthermore, in the above technical solution, the positioning assembly 60 includes a docking ear 61 and a guide rope 62, the docking ear 61 includes at least one group, each group includes two, which are respectively fixed at corresponding positions of the first assembly component 30, the second assembly component 40 and the third assembly component 50, one end of the guide rope 62 is fixed in the docking ear 61 on the first assembly component 30 and the second assembly component 40, and the other end passes through the docking ear 61 on the corresponding third assembly component 50.
[0157] Further, in the above technical solution, the positioning assembly 60 is installed on the top of the first assembly component 30 and the second assembly component 40, so that the third assembly component 50 is quickly docked with the top of the first assembly component 30 and the second assembly component 40 and then plugged and fixed. The specific steps include:
[0158] The third assembly component 50 is hoisted so that the guide rope 62 passes through the docking ear 61 on the third assembly component 50 , and the guide rope 62 is retracted inward to guide the third assembly component 50 to the corresponding position for plugging and fixing.
[0159] A second embodiment of a construction method of a mobile prefabricated mortar tank provided by the present invention includes the following specific steps:
[0160] Construction preparation
[0161] Before construction, the following preparations need to be done:
[0162] Personnel training: All personnel involved in the construction should receive training on equipment use, safe operation and emergency response.
[0163] Equipment inspection: Conduct a comprehensive inspection of the layout equipment, concrete pouring equipment and other construction tools to ensure their performance is in good condition.
[0164] Material preparation: Prepare the required cement, sand, gravel, water and other auxiliary materials and tools in advance.
[0165] Construction steps
[0166] Cleaning up the construction site
[0167] Clean up the site: remove debris and garbage from the construction site to ensure that the construction area is clean and tidy.
[0168] Check the ground: Check whether there are obvious potholes and cracks on the ground, and make necessary repairs to ensure that the foundation is solid.
[0169] Ground compaction and calibration
[0170] Ground compaction: Use a vibrating rammer to compact the entire ground evenly to improve the density and bearing capacity of the ground.
[0171] Level calibration: Use an optical level to calibrate the level of the ground to ensure the accuracy of subsequent construction.
[0172] Wire-laying: Assembling the wire-laying device: The wire-laying device 10 is moved to the construction site for assembly.
[0173] The fixing rod 111 is vertically inserted into the center of the ground.
[0174] The scribing assembly 14 is fixed on the fixing member 121 , and the movable member 122 is screwed on.
[0175] The level assembly 13 is fixed to the top of the fixing rod 111 to ensure that it is vertical.
[0176] Quick line laying: Rotate the marking assembly 14 to mark the starting points of the four triangles, and perform continuous marking to determine the fixed position of the embedded part 20.
[0177] Fixed embedded parts 20
[0178] Dig a hole at the marked position, bury the fixing part 21, ensure that it is vertically upward, and compact the surrounding area.
[0179] Installation of the pressing part 22: The pressing part 22 is arranged on the top of the fixing part 21 to ensure its stability.
[0180] Laying down tarpaulin
[0181] Tarpaulin preparation: Draw a circle on the top of the tarpaulin that is the same as the inner and outer walls of the mortar pot bottom and make a crosshatch at the marked locations.
[0182] Tarpaulin fixing: Fix the tarpaulin on a horizontal surface, making sure that the cross line passes through the position of the embedded part 20.
[0183] Formwork pouring: Mold cleaning: Clean the mold to ensure it is free of oil and dust.
[0184] Formwork erection: Install the formwork according to the drawing dimensions and check the alignment with a level.
[0185] Concrete pouring: Pour the mixed concrete into the formwork, use a vibrating rod to remove bubbles, and keep it moist until the designed strength is reached.
[0186] Assembling a mobile mortar tank
[0187] The first and second combined components are connected: the first combined component 30 and the second combined component 40 are fixedly connected to the embedded component 20 to ensure that they are aligned.
[0188] Positioning assembly installation: Install the positioning assembly 60 on the top of the first assembly component 30 and the second assembly component 40, and quickly dock and plug the third assembly component 50 to fix it.
[0189] Sealing check: Water injection check: Fill water into the mortar tank to check its sealing, and complete the construction after confirming that there is no leakage.
[0190] Disassembly and moving
[0191] Disassemble after use: After the mortar tank has been used, disassemble it in the reverse order and move each component to the new construction site.
[0192] Specifically, the principle of the present invention is:
[0193] When in use, clean the construction site, compact the ground, calibrate the horizontal plane, and then lay out the lines through the laying-out device 10, and the range of the laying-out matches the size of the mortar tank; fix the embedded parts 20 on the horizontal plane after laying out the lines, and lay out the waterproof tarpaulin, and fix the waterproof tarpaulin and the embedded parts 20; cast each part of the structure according to the drawing of the prefabricated mortar tank, and fix the anti-sticking layer on the surface; move the first assembly component 30, the second assembly component 40 and the third assembly component 50 that constitute the prefabricated mortar tank to the construction site, and fix the first assembly component 30 and the second assembly component 40 to the embedded parts 20; install the positioning component 60 on the top of the first assembly component 30 and the second assembly component 40, so that the third assembly component 50 can be quickly connected with the top of the first assembly component 30 and the second assembly component 40 and then plugged and fixed; check the sealing of the assembled mortar tank after water injection, and complete the construction of the mortar tank after confirming that it is completely sealed; after the mortar tank is used, disassemble it and move it.
Claims
1. A mobile prefabricated mortar tank construction method, characterized in that: The specific steps include: S10: cleaning the construction site, compacting the ground, calibrating the horizontal plane, and laying out the lines through a laying-out device (10), wherein the range of the laying-out matches the size of the mortar tank; S20: fixing the embedded component (20) on the horizontal plane after the wire is laid out, laying a tarpaulin, and fixing the tarpaulin and the embedded component (20) in a fixed connection; S30: Casting each part of the structure of the prefabricated mortar tank according to the drawing of the prefabricated mortar tank, and fixing an anti-sticking layer on the surface; S40: moving the first assembly component (30), the second assembly component (40) and the third assembly component (50) constituting the prefabricated mortar tank to a construction site, and fixing the first assembly component (30) and the second assembly component (40) to the embedded part (20); S50: installing a positioning assembly (60) on the top of the first assembly component (30) and the second assembly component (40), so that the third assembly component (50) is quickly docked with the top of the first assembly component (30) and the second assembly component (40) and then plugged and fixed; S60: After water is injected, the sealing of the assembled mortar tank is checked, and the construction of the mortar tank is completed after it is confirmed to be completely sealed; S70: After the mortar tank is used up, it is disassembled and moved.
2. A mobile prefabricated mortar tank construction method according to claim 1, characterized in that: The line-releasing device (10) comprises a central axis (11), a support assembly (12), a level assembly (13) and a marking assembly (14); the central axis (11) is arranged at a central position; the support assembly (12) is fixed on the side wall of the central axis (11); the marking assembly (14) is sleeved on the central axis (11) and supported by the support assembly (12); the support assembly (12) is used to determine the horizontal plane of the marking assembly (14) rotating on the side wall of the central axis (11); the top of the central axis (11) is connected to the level assembly (13); the level assembly (13) is used to ensure the verticality of the central axis (11) and keep the central axis (11) fixed by gravity; The central axis (11) comprises a fixing rod (111), a slide rail (112) and an insert drill (113); the insert drill (113) is fixed to the top of the fixing rod (111) and is used to fix the line-releasing device (10) on the ground; the fixing rod (111) is a vertical rod structure, and the slide rail (112) is arranged on the side wall of the fixing rod (111); the insert drill (113) is a hexagonal structure, and a channel is passed through from the bottom to the top, and the channel is used to guide the soil at the bottom when rotating and drilling a hole below the ground; The support assembly (12) is fixed to the upper and lower sides of the slide rail (112), and comprises a fixed part (121) and a movable part (122); the fixed part (121) is fixed to the bottom of the slide rail (112) and is flush with the bottom edge of the slide rail (112); the movable part (122) is fixed to the top of the slide rail (112) by means of threads and is flush with the top edge of the slide rail (112); the diameter of the fixed part (121) is greater than the diameter of the movable part (122); the top of the slide rail (112) is provided with threads, and the threads match the threads on the inner wall of the movable part (122); The marking assembly (14) is sleeved on the slide rail (112) and fixed in the slide rail (112) through the fixing member (121) and the movable member (122); the fixing member (121) is used to support the weight of the marking assembly (14); the marking assembly (14) comprises an inner rotating ring (141), a gear (142), an outer rotating ring (143) and a support rod (144); the gear (142) comprises a fixed gear (1421) and a rotating gear (1422); the fixed gear (1421) is fixed on the outer wall of the slide rail (112); the rotating gear (1422) is fixed on the inner wall of the inner rotating ring (141); the fixed gear (1421) and the rotating gear (1422) are connected to each other. (1422) meshing connection; the height of the fixed gear (1421) and the rotating gear (1422) is the same as the height between the fixed part (121) and the movable part (122); the outer rotating ring (143) is a double ring structure, and 4 triangles are symmetrically fixed inside it, and the triangles are all equilateral triangles, and the corresponding positions of adjacent triangles are 90° apart; two corners of the triangle are respectively fixed to the double rings of the outer rotating ring (143), and the other corner is set at the center position of the double rings of the outer rotating ring (143); nozzles are fixed at the bottom of the three corners of the triangle, and marking powder is placed inside the nozzle. The bottom of the nozzle is vertically downward and is used to lay out the horizontal plane by spraying marking powder; The level assembly (13) comprises a support rod (131), a vertical line (132) and a weight (133); a plug rod is fixed to the top of the central axis (11); a through hole is provided at the center of the support rod (131); the support rod (131) is fixed to the top of the central axis (11) by inserting the plug rod through the through hole; the weight (133) is fixed to the left and right symmetrical positions of the support rod (131) through the vertical line (132); the central axis (11) is kept in a vertical downward state by the gravity of the weight (133) at the symmetrical position; The outer ring diameter and the inner ring diameter of the outer rotating ring (143) are respectively the same as the outer wall diameter and the inner wall diameter of the prefabricated mortar pot.
3. A mobile prefabricated mortar tank construction method according to claim 2, characterized in that: The steps of cleaning the construction site, compacting the ground, calibrating the horizontal plane, and laying out the lines through the laying-out device (10), wherein the range of the laying-out matches the size of the mortar tank, are as follows: The first step is to remove debris and garbage on the site, check whether there are obvious potholes and cracks on the ground and repair them; The second step is to compact the entire ground evenly by vibrating the ground to improve its density and bearing capacity; The third step is to calibrate the levelness of the ground using an optical level; The fourth step is to move the wire-releasing device (10) to a construction site for assembly; The fifth step is to quickly lay out the ground to determine the fixed position of the embedded part (20); The specific steps of moving the wire-releasing device (10) to the construction site for assembly include: The first step is to select the center of the mortar tank installation, and vertically insert the fixing rod (111) into the ground corresponding to the center; The second step is to fix the scribing assembly (14) on the fixing member (121), and to screw the movable member (122) on the top of the scribing assembly (14); The third step is to fix the level assembly (13) on the top of the fixing rod (111), and adjust the positions of the vertical line (132) and the weight (133) so that the fixing rod (111) is always perpendicular to the ground; Step 4: placing marking powder inside the nozzle; The specific steps of quickly laying out the ground and determining the fixed position of the embedded part (20) include: Rotate the marking assembly (14) to mark the starting point of the angle where the four triangles are away from the outer rotating ring (143), and then mark the angular position where the four triangles are away from the outer rotating ring (143) in sequence every time the gear (142) rotates by 1 / 12 of the circumference, and perform calibration by rotating multiple times; The central shaft (11), the supporting assembly (12) and the marking assembly (14) are all made of lightweight materials.
4. A mobile prefabricated mortar tank construction method according to claim 3, characterized in that: The embedded parts (20) include 12 pieces, which are respectively fixed at the marking positions of the scribing assembly (14); the embedded parts (20) include a fixing part (21) and a pressing part (22); the fixing part (21) is a quadrangular pyramid structure, which is embedded at the marking position; the pressing part (22) is arranged at the top of the fixing part (21); the pressing part (22) includes a compression plate (221) and a connecting spring (222); one end of the connecting spring (222) is fixed to both sides of the top of the fixing part (21), and the other end is connected to the connecting spring (222); there are at least two compression plates (221) and two connecting springs (222); the two compression plates (221) are arranged obliquely, and the angle between the top inner walls they contact is 30-60 degrees.
5. A mobile prefabricated mortar tank construction method according to claim 4, characterized in that: The specific steps of fixing the embedded part (20) on the horizontal plane after laying out the wires include: The first step is to dig a hole with a diameter larger than the bottom diameter of the fixing part (21) at each of the 12 positions marked when the marking assembly (14) is laid out, and the fixing part (21) is pre-buried in the corresponding hole and then the surroundings of the hole are compacted; The second step is to adjust the embedded part (20) to be vertically upward during the compaction process; The specific steps of laying the waterproof tarpaulin and fixing the waterproof tarpaulin and the embedded part (20) include: The first step is to draw a circle on the top of the tarpaulin with a compass that is identical to the inner and outer walls of the bottom of the mortar tank; Step 2: Draw points in the middle of the two circles according to the positions of the 12 marks; Step 3: Draw cross lines at 12 points respectively, wherein the cross lines are limited between two circles; Step 4, fix the tarpaulin on a horizontal plane, with each corresponding cross line passing through the embedded part (20); Step 5: Clean up the edges of the cross lines.
6. A mobile prefabricated mortar tank construction method according to claim 5, characterized in that: The first assembly component (30) and the second assembly component (40) are symmetrical structures, respectively being semi-arc structures cast in concrete, with an inward depression on one side and an outward protrusion on the other side, the inward depression and the outward protrusion being arranged correspondingly, and being used to splice and fix the first assembly component (30) and the second assembly component (40); the diameters of the depression and the protrusion are smaller than the outer wall diameters of the first assembly component (30) and the second assembly component (40), and larger than the inner wall diameters of the first assembly component (30) and the second assembly component (40); The tops of the first combined component (30) and the second combined component (40) are provided with downward plugging grooves; Six grooves are evenly distributed at the center of the bottom of each of the first combined component (30) and the second combined component (40), and the size of the grooves is the same as the size of the pressing portion (22); The third assembly component (50) is a circular ring structure, and a plug-in protrusion is arranged at the bottom thereof, and the plug-in protrusion has the same size as the plug-in grooves at the tops of the first assembly component (30) and the second assembly component (40); a lifting ring is arranged at the top of the third assembly component (50), and the lifting ring is used to facilitate the installation of the third assembly component (50) after lifting; The bottom of the inner concave surface of the first assembly component (30) and the second assembly component (40) is provided with a double-layer annular groove recessed inwardly, and a rubber ring of the same shape is fixed correspondingly during installation, so as to seal the bottom of the mortar tank formed by the first assembly component (30) and the second assembly component (40).
7. A mobile prefabricated mortar tank construction method according to claim 6, characterized in that: The specific steps of casting each part of the structure of the prefabricated mortar tank according to the drawing and fixing the anti-sticking layer on the surface include: The first step is to clean the mold and ensure that the inner surface of the template is clean, free of oil and dust; The second step is to install the various parts of the template according to the drawing dimensions, ensuring that the template is firmly fixed and accurately built according to the design dimensions; In the third step, use a level and measuring tools to check the alignment of the template to ensure that it meets the design requirements in all directions; The fourth step is to support the formwork to ensure its stability during the pouring process; Step 5: Evenly apply the anti-sticking layer material on the inner surface of the template; Step 6: Mix cement, sand, gravel and water according to the required proportions and stir into uniform concrete; Step 7: Pour the concrete into the formwork, making sure to evenly fill each part, and use a vibrator to vibrate the concrete to remove air bubbles and ensure that the concrete is dense. Step 8: Use a scraper or trowel to smooth the concrete surface to ensure it is smooth and flat; The ninth step is to maintain the poured concrete and keep it moist; Step 10: After the concrete reaches the designed strength, remove the formwork at the prescribed time; Step 11: Check whether the surface of the prefabricated mortar tank after demolding meets the requirements and ensure that there are no defects; In the twelfth step, an anti-sticking layer is fixed on the surface of each part of the prefabricated mortar tank.
8. A mobile prefabricated mortar tank construction method according to claim 7, characterized in that: The specific steps of fixedly connecting the first combined component (30) and the second combined component (40) to the embedded component (20) include: The first step is to lift the first combined component (30) and place it at a corresponding adjustment position on the top of the embedded component (20); The second step is to slowly lower the first assembly component (30) and align it with the six embedded components (20) by shaking it left and right, and then lower it; The third step is to repeat the above process to fix the second assembly component (40) to the corresponding six embedded parts (20); In the fourth step, the construction personnel enter the structure composed of the first assembly component (30) and the second assembly component (40) to fix the rubber ring in the double-layer ring groove.
9. A mobile prefabricated mortar tank construction method according to claim 8, characterized in that: The positioning assembly (60) comprises a docking ear (61) and a guide rope (62); the docking ear (61) comprises at least one group, each group comprises two, and the docking ears (61) are respectively fixed at corresponding positions of the first assembly component (30), the second assembly component (40) and the third assembly component (50); one end of the guide rope (62) is fixed in the docking ear (61) on the first assembly component (30) and the second assembly component (40), and the other end passes through the docking ear (61) on the corresponding third assembly component (50).
10. A mobile prefabricated mortar tank construction method according to claim 9, characterized in that: The specific steps of installing a positioning assembly (60) on the top of the first assembly component (30) and the second assembly component (40) so that the third assembly component (50) is quickly docked with the top of the first assembly component (30) and the second assembly component (40) and then plugged and fixed include: The third assembly component (50) is hoisted so that the guide rope (62) passes through the docking ear (61) on the third assembly component (50), and the guide rope (62) is retracted inward to guide the third assembly component (50) to a corresponding position for plugging and fixing.
Citation Information
Patent Citations
Construction method of cement tank
CN112281900A
Installation and construction method for section steel stock bin greenhouse capable of rotating
CN115822339A
Assembly type stock bin
CN216240006U
Plate type combined silo
CN219822412U
Assembly structure and procedure for concrete towers used in wind turbines
US20080040983A1