Smoke-discharging and flat-guiding drainage tunnel structure for karst tunnel and using method of smoke-discharging and flat-guiding drainage tunnel structure
By designing a smoke exhaust flat guide drainage tunnel structure in karst tunnels, combining water discharge and smoke exhaust functions, the problems of smoke exhaust and water discharge in karst tunnel construction and operation are solved, and safe and efficient tunnel operation and construction are achieved, reducing the number of tunnels Construction costs.
Patent Information
- Application Number
- CN202310522789.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2023-05-10
- Publication Date
- 2024-11-12
AI Technical Summary
The existing technology is difficult to meet the smoke exhaust and water discharge needs of karst tunnels during the construction of separate double-hole tunnels on highways, and there are construction safety hazards and high construction costs.
A smoke exhaust flat guide and drainage hole structure for karst tunnels is designed. By setting parallel guide holes on the left or right side of the main tunnel of the tunnel, it contains drainage channels and smoke exhaust channels of the upper and lower structures, and through drainage branches The hole and smoke exhaust branch hole are connected to it, sealed with prefabricated partitions and secondary linings, and a sand sink and a maintenance horizontal hole are installed to achieve rapid drainage and smoke exhaust.
It realizes rapid drainage and discharge of water in the tunnel and rapid discharge of fire smoke and dust, reduces construction volume, ensures safe and reliable operation in the later stage, reduces construction complexity, and prevents silt through slope structures and sand sinks, improving construction Security and operational efficiency.
Smart Images

Figure CN118933839A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of highway tunnels, and in particular relates to a smoke exhaust horizontal drainage tunnel structure for a karst tunnel and a use method thereof. Background Art
[0002] With the rapid development of mountain highways, more and more long and large tunnels will be built in mountainous areas, especially in Yunnan, Guizhou, Sichuan and other regions in China, where karst landforms are well developed. As a result, many long and large tunnels will encounter unfavorable geological conditions such as developed underground caves and underground rivers during construction, which not only poses safety risks to construction safety during the construction period, but also poses hidden dangers to tunnel operation safety. For highway tunnels crossing karst underground rivers, due to the large amount of water discharge from karst underground rivers, most of them also have the risk of pressurized water and mud. Therefore, the control of water hazards is the focus of safety during construction and operation. Most existing technologies mainly use special drainage tunnels for drainage.
[0003] Patent CN202210698084.5 "Evacuation, rescue and drainage structure of Changda Fu Shui karst tunnel using flat guide" provides a structure using flat guide for rescue, evacuation and smoke exhaust, which can quickly carry out evacuation and rescue and water disaster treatment, ensure rapid and efficient excavation and safe and reliable operation in the later stage. This invention is suitable for single-hole double-track ultra-long railway tunnel structures of more than 20 kilometers, but the cavern structure is complex, the construction cost is high, and it cannot meet the construction of separated double-hole tunnels on highways. Summary of the invention
[0004] In view of the above problems, the purpose of the present invention is to provide a smoke exhaust horizontal drainage tunnel structure and a use method for karst tunnels, which can quickly handle sudden water surges in the tunnel through drainage branch tunnels and drainage channels in parallel guide tunnels. At the same time, the upper smoke exhaust channel can be used as a smoke exhaust channel when a fire occurs in the tunnel, ensuring the safe and reliable operation of the tunnel in the later stage, reducing the construction workload, and realizing an integrated design of smoke exhaust and drainage, which is safe and efficient.
[0005] The technical solution of the present invention is: a horizontal drainage water tunnel structure for smoke exhaust for a karst tunnel, the karst tunnel includes a tunnel main tunnel, the tunnel main tunnel is a separated double-tunnel structure, including a main tunnel left tunnel and a main tunnel right tunnel, the horizontal drainage water tunnel structure for smoke exhaust is located on the left side of the left tunnel of the main tunnel or on the right side of the right tunnel of the main tunnel or in the middle of the left tunnel and the right tunnel of the main tunnel, the horizontal drainage water tunnel structure for smoke exhaust includes parallel guide tunnels, a plurality of drainage branch tunnels and a plurality of smoke exhaust branch tunnels respectively connected to the parallel guide tunnels, the parallel guide tunnels are an upper and lower structure, including a smoke exhaust channel located at the upper part and a drainage channel located at the lower part, a prefabricated partition is provided between the smoke exhaust channel and the drainage channel, one end of the drainage branch tunnel is connected to the drainage channel, and the other end is connected to the water gushing point of the tunnel main tunnel, one end of the smoke exhaust branch tunnel is connected to the smoke exhaust channel, and the other end is connected to the tunnel main tunnel.
[0006] The drainage branch tunnels include a left drainage branch tunnel and a right drainage branch tunnel. One end of the left drainage branch tunnel is connected to the drainage channel, and the other end is connected to the water gushing point of the left tunnel of the main tunnel. The position connected to the water gushing point of the left tunnel of the main tunnel is higher than the position connected to the drainage channel. One end of the right drainage branch tunnel is connected to the drainage channel, and the other end is connected to the water gushing point of the right tunnel of the main tunnel. The position connected to the water gushing point of the right tunnel of the main tunnel is higher than the position connected to the drainage channel.
[0007] The smoke exhaust branch hole includes a left smoke exhaust branch hole and a right smoke exhaust branch hole. One end of the left smoke exhaust branch hole is connected to the smoke exhaust passage, and the other end is connected to the left hole of the main hole. One end of the right smoke exhaust branch hole is connected to the smoke exhaust passage, and the other end is connected to the right hole of the main hole. Fireproof isolation doors are respectively provided at the positions where the left smoke exhaust branch hole and the left hole of the main hole are connected, and the right smoke exhaust branch hole and the right hole of the main hole are connected.
[0008] The parallel guide tunnel surface is provided with a secondary lining, and the connection between the prefabricated partition and the secondary lining is provided with a caulking seal, and the height of the prefabricated partition is lower than the height of the bottom of the invert arch of the tunnel main tunnel.
[0009] An upper occlusal body and a lower occlusal body are respectively provided at both ends of the prefabricated partition, and the upper occlusal body and the lower occlusal body are L-shaped. Filling is provided at the connection between the upper occlusal body and the lower occlusal body and the secondary lining. The width range of the prefabricated partition is 0.5m~1.5m, and the width of the upper occlusal body and the lower occlusal body is 10cm, and the thickness is 5cm.
[0010] A first grit chamber is provided at the position where the drainage branch tunnel is connected to the drainage channel, and a second grit chamber is provided every 100m in the drainage channel along the extension direction parallel to the guide tunnel, and the depth of the first grit chamber is greater than the depth of the second grit chamber.
[0011] A plurality of maintenance cross tunnels are also provided between the parallel guide tunnel and the tunnel main tunnel. Fireproof isolation doors are provided at the connection points between the maintenance cross tunnel and the parallel guide tunnel and the tunnel main tunnel. The distance between the maintenance cross tunnel and the drainage branch tunnel ranges from 500m to 1000m.
[0012] A method for using the above-mentioned smoke exhaust and drainage tunnel structure for a karst tunnel comprises the following steps: S1: A parallel guide tunnel is set along the left side of the left main tunnel or the right side of the right main tunnel or the middle of the left main tunnel and the right main tunnel of the tunnel, and the prefabricated partitions are centrally prefabricated outside the parallel guide tunnel and then transported to the parallel guide tunnel for installation; S2: The water gushing point outside the tunnel main tunnel is connected to the drainage channel in the parallel pilot tunnel through a drainage branch tunnel, and the tunnel main tunnel is connected to the smoke exhaust channel in the parallel pilot tunnel through a smoke exhaust branch tunnel. The water gushing in the tunnel main tunnel can be directly discharged into the drainage channel through the drainage branch tunnel, and the smoke can be directly discharged into the smoke exhaust channel through the smoke exhaust branch tunnel.
[0013] In step S2, a fireproof isolation door is installed at the junction of the tunnel main tunnel and the smoke exhaust branch tunnel, and a first sedimentation tank is provided at the junction of the drainage branch tunnel and the parallel guide tunnel.
[0014] The technical effects of the present invention are as follows: 1. By setting drainage channels and smoke exhaust channels in parallel guide tunnels, the present invention can use drainage branch tunnels to quickly drain water gushing points in the tunnel. At the same time, through the smoke exhaust branch tunnel and the upper smoke exhaust channel, rapid smoke exhaust can be achieved in the event of a fire in the tunnel, ensuring safe and reliable operation in the later stage, reducing the construction workload, and realizing an integrated design of smoke exhaust and drainage, which is safer and more efficient; 2. In the drainage channels of the parallel guide tunnels, the present invention respectively sets a first grit tank and a second grit tank to guide the tunnel gushing water through the drainage branch tunnel to the parallel guide drainage channel. The functions are reliable, maintenance is convenient, drainage is timely, and siltation caused by excessive sediment can be prevented; 3. During the construction of parallel guide tunnels, in order to avoid the gushing point being too large to be constructed, the present invention adopts a maintenance cross tunnel as a construction cross passage. On the basis of not increasing the construction volume, the construction working surface can be increased, ensuring the smooth and safe progress of the construction; 4. The position where the drainage branch tunnel of the present invention is connected to the gushing point of the main tunnel of the tunnel is higher than the position where it is connected to the drainage channel, forming a down-slope structure. Each gushing point adopts down-slope drainage. If a large amount of water gushing occurs in the later operation, there is no need for an artificial water pump to assist in drainage.
[0015] The following is a further description with reference to the accompanying drawings. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 The present invention is a schematic cross-sectional view of a horizontal smoke exhaust and drainage tunnel structure for a karst tunnel according to an embodiment of the present invention.
[0017] Figure 2 The present invention is a schematic cross-sectional view of a horizontal smoke exhaust and drainage tunnel structure for a karst tunnel according to an embodiment of the present invention.
[0018] Figure 3 This is a schematic diagram of the prefabricated partition structure according to an embodiment of the present invention.
[0019] Figure 4 It is a schematic diagram of the structure of the left branch tunnel for water discharge according to an embodiment of the present invention.
[0020] Figure 5 It is a schematic diagram of the structure of the right branch tunnel for water discharge according to an embodiment of the present invention.
[0021] Figure 6This is a schematic diagram of the structure of the left branch hole of smoke exhaust according to an embodiment of the present invention.
[0022] Figure 7 It is a schematic diagram of the structure of the right branch hole of smoke exhaust according to an embodiment of the present invention.
[0023] Figure numerals: 1-tunnel main tunnel, 2-parallel guide tunnel, 3-drainage branch tunnel, 4-smoke exhaust branch tunnel, 5-drainage channel, 6-smoke exhaust channel, 7-fire isolation door, 8-maintenance cross tunnel, 9-first grit chamber, 10-second grit chamber, 11-left tunnel of main tunnel, 12-right tunnel of main tunnel, 21-secondary lining, 22-prefabricated partition, 23-caulking, 221-upper bite body, 222-lower bite body, 31-left drainage branch tunnel, 32-right drainage branch tunnel, 41-left smoke exhaust branch tunnel, 42-right smoke exhaust branch tunnel. Implementation
[0024] Example 1 Figure 1 , Figure 2 As shown, a horizontal drainage tunnel structure for smoke exhaust for a karst tunnel, the karst tunnel comprises a tunnel main tunnel 1, the tunnel main tunnel 1 is a separated double tunnel structure, comprising a main tunnel left tunnel 11 and a main tunnel right tunnel 12, the horizontal drainage tunnel structure for smoke exhaust is located on the left side of the main tunnel left tunnel 11 or on the right side of the main tunnel right tunnel 12 or in the middle of the main tunnel left tunnel 11 and the main tunnel right tunnel 12, the horizontal drainage tunnel structure for smoke exhaust comprises a parallel guide tunnel 2, a plurality of drainage branch tunnels 3 and a plurality of smoke exhaust branch tunnels 4 respectively connected to the parallel guide tunnels 2, the parallel guide tunnels 2 are an upper and lower structure, comprising a smoke exhaust channel 6 located at the upper part and a drainage channel 5 located at the lower part, a prefabricated partition 22 is provided between the smoke exhaust channel 6 and the drainage channel 5, one end of the drainage branch tunnel 3 is connected to the drainage channel 5, and the other end is connected to the water gushing point of the tunnel main tunnel 1, one end of the smoke exhaust branch tunnel 4 is connected to the smoke exhaust channel 6, and the other end is connected to the tunnel main tunnel 1.
[0025] During actual use, the present invention sets a parallel guide tunnel 2 along the left side of the left main tunnel 11 of the tunnel main tunnel 1 or the right side of the right main tunnel 12 or the middle position between the left main tunnel 11 and the right main tunnel 12, and the prefabricated partitions 22 are centrally prefabricated outside the tunnel main tunnel 1, and then transported to the tunnel main tunnel 1 for installation. The water gushing point outside the tunnel main tunnel 1 is connected to the drainage channel 5 in the parallel guide tunnel 2 through the drainage branch tunnel 3, and is connected to the smoke exhaust channel 6 in the parallel guide tunnel 2 through the smoke exhaust branch tunnel 4 in the tunnel main tunnel 1. The gushing water in the tunnel main tunnel 1 can be directly discharged into the drainage channel 5 through the drainage branch tunnel 3, and the smoke can be directly discharged into the smoke exhaust channel 6 through the smoke exhaust branch tunnel 4. The present invention arranges drainage channel 5 and smoke exhaust channel 6 in parallel with guide tunnel 2, and can use drainage branch tunnel 3 to quickly drain water from water gushing point in tunnel. Meanwhile, smoke exhaust branch tunnel 4 and upper smoke exhaust channel 6 can realize rapid smoke exhaust in case of fire in tunnel, thus ensuring safe and reliable operation in later stage, reducing construction workload, realizing integrated design of smoke exhaust and drainage, and being safer and more efficient. Embodiment 2 Preferably, on the basis of Embodiment 1, Figure 4 , Figure 5 As shown, in this embodiment, the drainage branch hole 3 includes a left drainage branch hole 31 and a right drainage branch hole 32. One end of the left drainage branch hole 31 is connected to the drainage channel 5, and the other end is connected to the water gushing point of the left hole 11 of the main tunnel. The position connected to the water gushing point of the left hole 11 of the main tunnel is higher than the position connected to the drainage channel 5. One end of the right drainage branch hole 32 is connected to the drainage channel 5, and the other end is connected to the water gushing point of the right hole 12 of the main tunnel. The position connected to the water gushing point of the right hole 12 of the main tunnel is higher than the position connected to the drainage channel 5.
[0026] During actual use, one end of the left branch drainage hole 31 of the present invention is connected to the drainage channel 5, and the other end is connected to the water gushing point of the left hole 11 of the main tunnel, and the position connected to the water gushing point of the left hole 11 of the main tunnel is higher than the position connected to the drainage channel 5. One end of the right branch drainage hole 32 is connected to the drainage channel 5, and the other end is connected to the water gushing point of the right hole 12 of the main tunnel, and the position connected to the water gushing point of the right hole 12 of the main tunnel is higher than the position connected to the drainage channel 5, forming a downslope structure. Each gushing point adopts downslope drainage. If a large amount of water gushing occurs in the later operation, there is no need for artificial water pumps to assist in drainage.
[0027] Embodiment 3 Preferably, on the basis of Embodiment 1 or Embodiment 2, as Figure 6 , Figure 7As shown, in this embodiment, the smoke exhaust branch hole 4 includes a left smoke exhaust branch hole 41 and a right smoke exhaust branch hole 42. One end of the left smoke exhaust branch hole 41 is connected to the smoke exhaust passage 6, and the other end is connected to the left hole 11 of the main tunnel. One end of the right smoke exhaust branch hole 42 is connected to the smoke exhaust passage 6, and the other end is connected to the right hole 12 of the main tunnel. Fireproof isolation doors 7 are respectively provided at the positions where the left smoke exhaust branch hole 41 and the left hole 11 of the main tunnel are connected, and the right smoke exhaust branch hole 42 and the right hole 12 of the main tunnel are connected.
[0028] During actual use, in the present invention, the smoke exhaust branch hole 4 includes a left smoke exhaust branch hole 41 and a right smoke exhaust branch hole 42. One end of the left smoke exhaust branch hole 41 is connected to the smoke exhaust passage 6, and the other end is connected to the left hole 11 of the main tunnel. One end of the right smoke exhaust branch hole 42 is connected to the smoke exhaust passage 6, and the other end is connected to the right hole 12 of the main tunnel. Fireproof isolation doors 7 are respectively provided at the positions where the left smoke exhaust branch hole 41 is connected to the left hole 11 of the main tunnel, and the right smoke exhaust branch hole 42 is connected to the right hole 12 of the main tunnel. When a fire accident occurs in the left tunnel 11 of the main tunnel, the smoke and dust of the left tunnel 11 can be discharged into the smoke exhaust channel 6 of the parallel guide tunnel 2 through the left smoke exhaust branch tunnel 41, and then discharged from the tunnel opening along the smoke exhaust channel 6; the right smoke exhaust branch tunnel 42 is connected to the right tunnel 12 of the main tunnel. When a fire accident occurs in the right tunnel 12 of the main tunnel, the smoke and dust of the right tunnel 12 of the main tunnel can be discharged into the smoke exhaust channel 6 of the parallel guide tunnel 2 through the right smoke exhaust branch tunnel 42, and then discharged from the tunnel opening along the smoke exhaust channel 6. When the parallel guide tunnel 2 is located on one side of the tunnel, the main tunnel near one side is directly connected to the smoke exhaust channel 6 through the uphill smoke exhaust branch tunnel 41, which is convenient for rapid smoke and dust discharge. The main tunnel 12 far away from the parallel guide tunnel 2 needs to cross the main tunnel 11, adopt a "herringbone slope" setting, and then connect to the smoke exhaust channel 6. Fireproof isolation doors 7 are provided at the positions where the left smoke exhaust branch tunnel 41 and the left main tunnel 11 are connected, and at the positions where the right smoke exhaust branch tunnel 42 and the right main tunnel 12 are connected, to prevent smoke and dust from entering the main tunnel 1 through the smoke exhaust branch tunnel 4 when a fire accident occurs in the main tunnel 1, thereby ensuring the emergency effect of smoke exhaust.
[0029] Embodiment 4 Preferably, on the basis of Embodiment 1 or Embodiment 3, in this embodiment, a secondary lining 21 is provided on the surface of the parallel guide tunnel 2, a caulking 23 is provided for sealing at the connection between the prefabricated partition 22 and the secondary lining 21, and the height of the prefabricated partition 22 is lower than the height of the bottom of the invert arch of the tunnel main tunnel 1.
[0030] In actual use, in order to prevent smoke from flowing back through the drainage channel, the present invention uses caulking 23 to seal between the prefabricated partition 22 and the secondary lining 21 and between adjacent prefabricated partitions 22. The caulking 23 can be made of materials such as micro-expansive concrete or sealant to ensure the sealing effect of the smoke exhaust channel. The height of the prefabricated partition 22 is lower than the height of the bottom of the invert of the tunnel main hole 1 to ensure smooth drainage.
[0031] Embodiment 5 Preferably, on the basis of Embodiment 1 or Embodiment 4, Figure 3 As shown, in this embodiment, an upper bite body 221 and a lower bite body 222 are respectively provided at both ends of the prefabricated partition 22, the upper bite body 221 and the lower bite body 222 are L-shaped, and a caulking 23 is provided at the connection between the upper bite body 221 and the lower bite body 222 and the secondary lining 21, the width of the prefabricated partition 22 ranges from 0.5m to 1.5m, the width of the upper bite body 221 and the lower bite body 222 is 10cm, and the thickness is 5cm.
[0032] During actual use, the prefabricated partition 22 of the present invention is provided with an upper bite body 221 and a lower bite body 222 at both ends respectively, and the upper bite body 221 and the lower bite body 222 are L-shaped. The prefabricated partition 22 adopts an upper and lower bite seam form, wherein the bite bodies 221 and 222 are 10 cm wide and 5 cm thick. By overlapping up and down, the overlapping position is tightly bitten, thereby ensuring the integrity and sealing of the overlap between adjacent prefabricated partitions 22.
[0033] Embodiment 6 Preferably, on the basis of Embodiment 1 or Embodiment 5, in the present embodiment, a first grit chamber 9 is provided at the position where the drainage branch tunnel 3 is connected to the drainage channel 5, and a second grit chamber 10 is provided every 100 m in the drainage channel 5 along the extension direction parallel to the guide tunnel 2, and the depth of the first grit chamber 9 is greater than the depth of the second grit chamber 10.
[0034] During actual use, a first grit chamber 9 is provided at the position where the drainage branch tunnel 3 of the present invention is connected to the drainage channel 5, and a second grit chamber 10 is provided every 100m in the drainage channel 5 along the extension direction parallel to the guide tunnel 2. The first grit chamber 9 and the second grit chamber 10 are used to precipitate the silt brought by the gushing water, which is convenient for centralized treatment and prevents blockage of the drainage channel 5.
[0035] Embodiment 7 Preferably, on the basis of Embodiment 1, in this embodiment, a plurality of maintenance cross tunnels 8 are further provided between the parallel guide tunnel 2 and the tunnel main tunnel 1, and fire-proof isolation doors 7 are respectively provided at the connecting parts between the maintenance cross tunnel 8 and the parallel guide tunnel 2 and the tunnel main tunnel 1, and the distance between the maintenance cross tunnel 8 and the drainage branch tunnel 3 ranges from 500m to 1000m.
[0036] In actual use, a plurality of maintenance transverse tunnels 8 are provided between the parallel guide tunnel 2 and the tunnel main tunnel 1 of the present invention, which facilitates the desilting work in the drainage channel during operation, and can increase the construction working surface without increasing the construction volume, thereby ensuring the smooth and safe progress of the construction. At the same time, it can be used as a construction channel during construction to increase the parallel guide construction working surface. The maintenance transverse tunnel 8 is provided with a fireproof isolation door 7 at the connection point with the parallel guide tunnel 2 and the tunnel main tunnel 1, respectively, to prevent smoke and dust from running wildly in case of fire.
[0037] Embodiment 8 A method for using the above-mentioned smoke exhaust and drainage tunnel structure for a karst tunnel comprises the following steps: S1: a parallel guide tunnel 2 is arranged along the left side of the left main tunnel 11 of the tunnel main tunnel 1 or the right side of the right main tunnel 12 or the middle position of the left main tunnel 11 and the right main tunnel 12, and a prefabricated partition 22 is centrally prefabricated outside the parallel guide tunnel 2 and then transported to the parallel guide tunnel 2 for installation; S2: The water gushing point outside the tunnel main tunnel 1 is connected to the drainage channel 5 in the parallel guide tunnel 2 through the drainage branch tunnel 3, and is connected to the smoke exhaust channel 6 in the parallel guide tunnel 2 through the smoke exhaust branch tunnel 4 in the tunnel main tunnel 1. The water gushing in the tunnel main tunnel 1 can be directly discharged into the drainage channel 5 through the drainage branch tunnel 3, and the smoke can be directly discharged into the smoke exhaust channel 6 through the smoke exhaust branch tunnel 4.
[0038] In step S2, a fireproof isolation door 7 is installed at the junction of the tunnel main tunnel 1 and the smoke exhaust branch tunnel 4, and a first sedimentation tank 9 is provided at the junction of the drainage branch tunnel 3 and the parallel guide tunnel 2.
[0039] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any changes or substitutions that can be easily conceived by any technician familiar with the technical field within the technical scope disclosed by the present invention should be covered within the protection scope of the present invention.
Claims
1. A smoke exhaust and drainage tunnel structure for a karst tunnel, the karst tunnel comprising a tunnel main tunnel (1), the tunnel main tunnel (1) being a separated double tunnel structure, comprising a main tunnel left tunnel (11) and a main tunnel right tunnel (12), characterized in that: The horizontal drainage tunnel structure for smoke exhaust is located on the left side of the left tunnel (11) of the main tunnel or on the right side of the right tunnel (12) of the main tunnel or in the middle of the left tunnel (11) and the right tunnel (12). The horizontal drainage tunnel structure for smoke exhaust comprises a parallel guide tunnel (2), a plurality of drainage branch tunnels (3) respectively connected to the parallel guide tunnel (2) and a plurality of smoke exhaust branch tunnels (4). The parallel guide tunnel (2) is an upper and lower structure, comprising a smoke exhaust channel (6) located at the upper part and a drainage channel (5) located at the lower part. A prefabricated partition (22) is provided between the smoke exhaust channel (6) and the drainage channel (5). One end of the drainage branch tunnel (3) is connected to the drainage channel (5) and the other end is connected to the water gushing point of the main tunnel (1) of the tunnel. One end of the smoke exhaust branch tunnel (4) is connected to the smoke exhaust channel (6) and the other end is connected to the main tunnel (1) of the tunnel.
2. According to claim 1, a smoke exhaust and drainage tunnel structure for a karst tunnel is characterized by: The drainage branch hole (3) comprises a drainage left branch hole (31) and a drainage right branch hole (32); one end of the drainage left branch hole (31) is connected to the drainage channel (5), and the other end is connected to the water gushing point of the left hole (11) of the main hole; the position where the drainage left branch hole (31) is connected to the water gushing point of the left hole (11) of the main hole is higher than the position where the drainage right branch hole (32) is connected to the drainage channel (5); one end of the drainage right branch hole (32) is connected to the drainage channel (5), and the other end is connected to the water gushing point of the right hole (12) of the main hole; the position where the drainage right branch hole (32) is connected to the water gushing point of the right hole (12) of the main hole is higher than the position where the drainage right branch hole (32) is connected to the drainage channel (5).
3. The smoke exhaust and drainage tunnel structure for a karst tunnel according to claim 1, characterized in that: The smoke exhaust branch hole (4) comprises a left smoke exhaust branch hole (41) and a right smoke exhaust branch hole (42); one end of the left smoke exhaust branch hole (41) is connected to the smoke exhaust passage (6), and the other end is connected to the left main hole (11); one end of the right smoke exhaust branch hole (42) is connected to the smoke exhaust passage (6), and the other end is connected to the right main hole (12); fireproof isolation doors (7) are respectively provided at the positions where the left smoke exhaust branch hole (41) and the left main hole (11) are connected, and where the right smoke exhaust branch hole (42) and the right main hole (12) are connected.
4. The smoke exhaust and drainage tunnel structure for a karst tunnel according to claim 1, characterized in that: The surface of the parallel guide tunnel (2) is provided with a secondary lining (21), and the connection between the prefabricated partition (22) and the secondary lining (21) is provided with a caulking (23) for sealing, and the height of the prefabricated partition (22) is lower than the height of the bottom of the invert of the tunnel main tunnel (1).
5. The smoke exhaust and drainage tunnel structure for karst tunnels according to claim 4 is characterized by: An upper occlusal body (221) and a lower occlusal body (222) are respectively provided at both ends of the prefabricated partition (22); the upper occlusal body (221) and the lower occlusal body (222) are L-shaped; a caulking (23) is provided at the connection between the upper occlusal body (221) and the lower occlusal body (222) and the secondary lining (21); the width of the prefabricated partition (22) ranges from 0.5 m to 1.5 m; the width of the upper occlusal body (221) and the lower occlusal body (222) is 10 cm, and the thickness is 5 cm.
6. The smoke exhaust and drainage tunnel structure for karst tunnels according to claim 1, characterized in that: A first grit chamber (9) is provided at a position where the drainage branch tunnel (3) is connected to the drainage channel (5), and a second grit chamber (10) is provided in the drainage channel (5) at intervals of 100 m in a direction parallel to the extension of the guide tunnel (2), wherein the depth of the first grit chamber (9) is greater than the depth of the second grit chamber (10).
7. The smoke exhaust and drainage tunnel structure for karst tunnels according to claim 1, characterized in that: A plurality of maintenance transverse tunnels (8) are also provided between the parallel guide tunnel (2) and the tunnel main tunnel (1), and fireproof isolation doors (7) are provided at the connection points between the maintenance transverse tunnel (8) and the parallel guide tunnel (2) and the tunnel main tunnel (1), respectively. The distance between the maintenance transverse tunnel (8) and the drainage branch tunnel (3) ranges from 500m to 1000m.
8. A method for using the smoke exhaust and drainage tunnel structure for a karst tunnel as claimed in claim 1, characterized in that: The following steps are involved: S1: a parallel guide tunnel (2) is arranged along the left side of the left main tunnel (11) of the tunnel main tunnel (1) or the right side of the right main tunnel (12) or the middle position between the left main tunnel (11) and the right main tunnel (12), and a prefabricated partition (22) is centrally prefabricated outside the parallel guide tunnel (2) and then transported to the parallel guide tunnel (2) for installation; S2: The water gushing point outside the tunnel main tunnel (1) is connected to the drainage channel (5) in the parallel guide tunnel (2) through the drainage branch tunnel (3), and the tunnel main tunnel (1) is connected to the smoke exhaust channel (6) in the parallel guide tunnel (2) through the smoke exhaust branch tunnel (4). The water gushing in the tunnel main tunnel (1) can be directly discharged into the drainage channel (5) through the drainage branch tunnel (3), and the smoke can be directly discharged into the smoke exhaust channel (6) through the smoke exhaust branch tunnel (4).
9. The method for using the smoke exhaust and drainage tunnel structure for a karst tunnel according to claim 8, characterized in that: In the step S2, a fireproof isolation door (7) is installed at the junction of the tunnel main tunnel (1) and the smoke exhaust branch tunnel (4), and a first sedimentation tank (9) is provided at the junction of the drainage branch tunnel (3) and the parallel guide tunnel (2).