Method for reducing underground dry spraying operation dust

Through the atomization pipe and nozzle device, the uniform mixing of water and materials in the underground dry spray operation is solved, and the problem of dust overflowing in the underground dry spray operation is achieved, and the environmentally friendly and efficient dust reduction effect is achieved, which improves the construction environment.

CN118933976AInactive Publication Date: 2024-11-12ANHUI SCORSESE ENG TECH CO LTD
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202411293695.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-14
Publication Date
2024-11-12
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

In the underground dry spray operation, due to the short mixing time of water and materials, dust overflows, resulting in harsh on-site environment. The existing technology is difficult to effectively reduce dust and is not environmentally friendly.

Method used

A combination device of atomization pipe, connecting hose, water control valve and atomization spray head is used to spray evenly into the material after incoming water atomization, ensuring that the water and the material are fully mixed, adjusting the water content of the sprayed material, and reducing dust.

Benefits of technology

It effectively reduces the dust generated by dry spraying operations, improves the construction environment, improves the utilization rate and solidification strength of materials, and is simple, energy-saving and environmentally friendly, and does not require the use of dust inhibitors.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118933976A_ABST
    Figure CN118933976A_ABST
Patent Text Reader

Abstract

The invention discloses a method for reducing underground dry spraying operation dust, which comprises a section of atomizing pipe, a section of connecting hose, two water quantity control valves and four atomizing nozzles, one end of the atomizing pipe is provided with a spraying pipe, the other end of the atomizing pipe is provided with the connecting hose, one end of the connecting hose is provided with a nozzle with a seat, and the other end of the connecting hose is provided with a water quantity control valve. A nozzle water inlet control valve is mounted at the top of the mounted nozzle; during dry spraying operation, the whole process is very easy to adjust, long-time use can be achieved through one-time adjustment under the condition that materials are evenly discharged, manual intervention is not needed, other energy consumption is avoided in the process, the dust raising problem of guniting can be solved, the process is free of potential safety hazards, energy is saved, environment friendliness is achieved, and a dust inhibitor is not needed. And the influence on the environment is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of dust reduction, and in particular to a method for reducing dust from underground dry spraying operations. Background Art

[0002] In the current underground dry spraying operation, underground tunnel support requires a large amount of concrete spraying operation. The traditional method is to manually load the mixed dry materials to the traditional dry spraying machine or the remote spraying machine or the new remote spraying device for spraying operation. The spraying operation is to add water and mix at the nozzle and then spray it directly. Due to the short mixing time of water and materials, the mixing is not uniform, and a large amount of dust will float when spraying, causing an extremely harsh on-site environment.

[0003] Therefore, an efficient and environmentally friendly solution is needed. Summary of the invention

[0004] In view of this, the present invention provides a method for reducing dust in underground dry spraying operations, which can effectively reduce dust generated by dry spraying operations. The method is used in conjunction with an underground building material pneumatic conveying system, is more environmentally friendly, has a higher material utilization rate, and has a higher strength after solidification. During continuous and uninterrupted operations, the construction environment of the operators is greatly improved.

[0005] The present invention provides the following technical solutions:

[0006] A section of atomizing pipe, a section of connecting hose, two water volume control valves, and four atomizing nozzles. A spray pipe is installed at one end of the atomizing pipe, a connecting hose is installed at the other end of the atomizing pipe, a nozzle with a seat is installed at one end of the connecting hose, and a nozzle water inlet control valve is installed on the top of the nozzle with a seat;

[0007] Preferably, four nozzle mounting seats are arranged on the top of the atomizing pipe, four atomizing nozzles are arranged on the atomizing pipe through the nozzle mounting seats, a snap-on elbow is arranged on one atomizing nozzle, and snap-on tees are arranged on three atomizing nozzles, the snap-on elbow and the snap-on tees are connected through a connecting water pipe, and a water volume control valve is installed at one end of the connecting water pipe;

[0008] Preferably, the atomizing pipe; the spraying pipe, adopts a DN40-80 carbon steel pipe, the atomizing pipe is about 300-1000mm; it is used to atomize water and then spray it into the material;

[0009] Preferably, the connecting hose is about 8 to 20 m long and is used to fully mix the atomized water with the material;

[0010] Preferably, the nozzle with seat is a polyurethane nozzle.

[0011] Another object of the present invention is to provide a dust reduction method, comprising the following steps:

[0012] Preferably, the device of the method is first connected to the end shotcrete pipe of the dry shotcrete machine or the underground building material pneumatic conveying system for shotcrete operation to ensure the connection is sealed;

[0013] Preferably, a water volume control valve; the nozzle water inlet control valve is connected to the downhole water pipe;

[0014] Preferably, start the dry spraying machine or underground building materials pneumatic conveying system spraying operation, wait for the compressed air flow in the spraying pipe to be normal, the gas flows from the spraying pipe to the atomizing pipe, and then passes through the connecting hose and is sprayed out from the nozzle with seat. After 10 seconds, open the water volume control valve, open 1 / 3, water passes through the water volume control valve; connect the water pipe; the snap-on tee and snap-on elbow reach the atomizing nozzle, the atomizing nozzle atomizes the water and sprays it evenly into the atomizing pipe, and sprays it out with the air flow in the pipe through the connecting hose to the nozzle with seat, observe the atomized water output at the nozzle with seat, if it is normal, open the nozzle water inlet control valve, open 1 / 3, and observe the atomized water at the nozzle with seat again. This process does not exceed 2 minutes.

[0015] Preferably, the premixed concrete dry powder material or the underground building material pneumatic conveying system is added to the dry spraying machine to start discharging. The material enters the atomizing pipe through the spraying pipe, and the atomizing nozzle atomizes the water and evenly sprays it onto the dry powder material in the atomizing pipe, and fully mixes it in the connecting hose. This is the initial mixing of water and material, and the mixing time lasts about 2 to 3 seconds. The water content of the material after the initial mixing does not exceed 40%, and it flows smoothly in the connecting hose, and the dust after the initial mixing is reduced by 50%.

[0016] Preferably, the materials after the initial mixing reach the nozzle with seat, and water enters the nozzle with seat through the nozzle water inlet control valve, and is evenly mixed with the materials after the initial mixing. At this time, the nozzle water inlet control valve is adjusted to make the sprayed materials have moderate water content and no dust. If there is still a lot of dust at this time, the water volume control valve can be opened wider, and the water volume of the atomization pipe can be increased to increase the water content of the initial mixing. Then the water volume of the nozzle water inlet control valve can be adjusted to achieve the effect of no dust.

[0017] Preferably, when the spraying operation is completed, first stop adding premixed concrete dry powder materials to the dry spray machine or stop discharging materials from the underground building materials pneumatic conveying system. After no material is sprayed out from the nozzle with seat, close the water volume control valve, then close the nozzle water inlet control valve, and then observe whether there is water spraying out from the nozzle with seat. This process takes about 2 minutes. If no water is sprayed out, turn off the dry spray machine or the underground building materials pneumatic conveying system.

[0018] Compared with the prior art, the present invention has the following beneficial effects:

[0019] 1. When the present invention is performing dry spraying operation, the whole process adjustment is very simple. Under the condition that the material is discharged evenly, long-term use can be achieved by adjusting once without manual intervention.

[0020] 2. This process does not consume any other energy and can solve the dust problem of spraying. The process has no safety hazards and is energy-saving and environmentally friendly.

[0021] 3. Environmentally friendly: No need to use dust suppressants, reducing the impact on the environment. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] Figure 1 It is a schematic diagram of the method steps of the present invention;

[0023] In the figure: 1. Atomizing pipe; 2. Water volume control valve; 3. Connecting water pipe; 4. Atomizing nozzle; 5. Nozzle mounting seat; 6. Snap-on tee; 7. Snap-on elbow; 8. Spraying pipe; 9. Nozzle water inlet control valve; 10. Nozzle with seat; 11. Connecting hose. DETAILED DESCRIPTION

[0024] The following will be combined with the drawings in the embodiments of the present invention to clarify the technical solutions in the embodiments of the present invention; it is clearly described in detail. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0025] See also Figure 1 The embodiment provided by the present invention: a method for reducing dust in underground dry spraying operation, comprising a section of atomizing pipe 1; a section of connecting hose 11; two water volume control valves 2; four atomizing nozzles 4, a spraying pipe 8 is installed at one end of the atomizing pipe 1, a connecting hose 11 is installed at the other end of the atomizing pipe 1, a nozzle with a seat 10 is installed at one end of the connecting hose 11, and a nozzle water inlet control valve 9 is installed on the top of the nozzle with a seat 10;

[0026] Four nozzle mounting seats 5 are arranged on the top of the atomizing pipe 1, and four atomizing nozzles 4 are arranged on the atomizing pipe 1 through the nozzle mounting seats 5. A snap-on elbow 7 is arranged on one atomizing nozzle 4, and snap-on tees 6 are arranged on three atomizing nozzles 4. The snap-on elbow 7 is connected to the snap-on tees 6 through a connecting water pipe 3, and a water volume control valve 2 is installed at one end of the connecting water pipe 3;

[0027] Atomizing pipe 1; spraying pipe 8, using DN40-80 carbon steel pipeline, atomizing pipe 1, about 300-1000mm; used for atomizing water and then spraying it into the material;

[0028] Connecting hose 11, about 8 to 20 m, is used to fully mix the atomized water with the material;

[0029] The nozzle with seat 10 is a polyurethane nozzle.

[0030] The present invention also provides a method for using the above device, comprising the following steps:

[0031] S1; firstly, the device of the present method is connected to the end shotcrete pipe 8 of the dry shotcrete machine or the underground building materials pneumatic conveying system to ensure the connection is sealed;

[0032] S2; water control valve 2; sprinkler water inlet control valve 9 connected to the downhole water pipe;

[0033] S3; Start the dry spraying machine or underground building materials pneumatic conveying system spraying operation, wait for the compressed air flow in the spraying pipe 8 to be normal, the gas flows from the spraying pipe 8 to the atomizing pipe 1, and then passes through the connecting hose 11 and is sprayed out from the nozzle with seat 10. After 10 seconds, open the water control valve 2, open 1 / 3, water passes through the water control valve 2; connect the water pipe 3; snap-on tee 6 and snap-on elbow 7 to the atomizing nozzle 4, the atomizing nozzle 4 atomizes the water and sprays it evenly into the atomizing pipe, and sprays it out with the air flow in the pipe through the connecting hose 11 to the nozzle with seat 10, observe the atomized water output at the nozzle with seat 10, if it is normal, open the nozzle water inlet control valve 9, open 1 / 3, and observe the atomized water at the nozzle with seat 10 again. This process does not exceed 2 minutes.

[0034] S4: Add premixed concrete dry powder material or underground building material pneumatic conveying system to the dry spraying machine to start discharging. The material enters the atomizing tube 1 through the spraying pipe 8, and the atomizing nozzle 4 atomizes the water and evenly sprays it to the dry powder material in the atomizing tube 1, and fully mixes it in the connecting hose 11. This is the initial mixing of water and material, and the mixing time lasts about 2 to 3 seconds. The water content of the material after the initial mixing does not exceed 40%, and it flows smoothly in the connecting hose 11, and the dust after the initial mixing is reduced by 50%.

[0035] S5; the material after initial mixing reaches the nozzle with seat 10, and water enters the nozzle with seat 10 through the nozzle water inlet control valve 9, and is evenly mixed with the material after initial mixing. At this time, adjust the nozzle water inlet control valve 9 to make the sprayed material have moderate water content and no dust. If there is still a lot of dust at this time, you can open the water control valve 2 wider, increase the water output of the atomizing pipe 1, and increase the water content of the initial mix. Then adjust the water output of the nozzle water inlet control valve 9 to achieve a dust-free effect.

[0036] S6; When the spraying operation is completed, first stop adding premixed concrete dry powder materials to the dry spraying machine or stop discharging the underground building materials pneumatic conveying system. After no material is sprayed out from the nozzle 10 with a seat, close the water volume control valve 2, then close the nozzle water inlet control valve 9, and then observe whether there is water spraying out from the nozzle 10 with a seat. This process takes about 2 minutes. If no water is sprayed out, turn off the dry spraying machine or the underground building materials pneumatic conveying system.

[0037] It will be apparent to those skilled in the art that the invention is not limited to the details of the exemplary embodiments described above and that the invention can be implemented in other specific forms without departing from the spirit or essential features of the invention. Therefore, the embodiments should be considered exemplary and non-limiting in all respects, and the scope of the invention is defined by the appended claims rather than the foregoing description, and it is intended that all variations falling within the meaning and scope of the equivalent elements of the claims be included in the invention. Any reference numeral in a claim should not be considered as limiting the claim to which it relates.

Claims

1. A method for reducing dust in underground dry spraying operations, comprising a section of atomizing pipe (1), a section of connecting hose (11), two water volume control valves (2), and four atomizing nozzles (4), characterized in that: A spraying pipe (8) is installed at one end of the atomizing pipe (1), a connecting hose (11) is installed at the other end of the atomizing pipe (1), a nozzle with a seat (10) is installed at one end of the connecting hose (11), and a nozzle water inlet control valve (9) is installed on the top of the nozzle with a seat (10); The top of the atomizing pipe (1) is provided with four nozzle mounting seats (5); the atomizing pipe (1) is provided with four atomizing nozzles (4) via the nozzle mounting seats (5); one of the atomizing nozzles (4) is provided with a snap-on elbow (7); the three atomizing nozzles (4) are provided with snap-on tees (6); the snap-on elbow (7) is connected to the snap-on tee (6) via a connecting water pipe (3); a water volume control valve (2) is installed at one end of the connecting water pipe (3); The atomizing pipe (1) and the spraying pipe (8) are made of DN40-80 carbon steel pipes. The atomizing pipe (1) is about 300 to 1000 mm and is used to atomize water and then spray it into the material. The connecting hose (11), about 8 to 20 m long, is used to fully mix the atomized water with the material; The nozzle with seat (10) is a polyurethane nozzle.

2. The method for reducing dust in underground dry spraying operations according to claim 1, characterized in that: The following steps are involved: S1; firstly, the device of the present method is connected to the end shotcrete pipe (8) of the dry shotcrete machine or the underground building materials pneumatic conveying system to ensure the connection is sealed; S2; water volume control valve (2); the nozzle water inlet control valve (9) is connected to the downhole water pipe; S3: Start the dry spraying machine or underground building material pneumatic conveying system spraying operation, wait until the compressed air in the spraying pipe (8) flows normally, the gas flows from the spraying pipe (8) to the atomizing pipe (1), and then passes through the connecting hose (11) and is sprayed out from the nozzle with seat (10). After 10 seconds, open the water control valve (2), open 1 / 3, and the water passes through the water control valve (2); connect the water pipe (3); the snap-on tee (6) and the snap-on elbow (7) to the atomizing nozzle (4). The atomizing nozzle (4) atomizes the water and sprays it evenly into the atomizing pipe. With the air flow in the pipe, it passes through the connecting hose (11) to the nozzle with seat (10) and sprays out. Observe the atomized water output at the nozzle with seat (10). If it is normal, open the nozzle water inlet control valve (9), open 1 / 3, and observe the atomized water at the nozzle with seat (10) again. This process does not exceed 2 minutes. S4: Add premixed concrete dry powder material or underground building material pneumatic conveying system to the dry spraying machine to start discharging. The material enters the atomizing pipe (1) through the spraying pipe (8), and the atomizing nozzle (4) atomizes the water and evenly sprays it onto the dry powder material in the atomizing pipe (1), and fully mixes it in the connecting hose (11). This is the initial mixing of water and material, and the mixing time lasts about 2 to 3 seconds. The water content of the material after the initial mixing does not exceed 40%, and it flows smoothly in the connecting hose (11), and the dust after the initial mixing is reduced by 50%. S5; The material after the initial mixing reaches the nozzle with seat (10), and water enters the nozzle with seat (10) through the nozzle water inlet control valve (9), and is evenly mixed with the material after the initial mixing. At this time, the nozzle water inlet control valve (9) is adjusted to make the sprayed material have a moderate water content and no dust. If there is still a lot of dust at this time, the water volume control valve (2) can be opened wider, and the water output of the atomizing pipe (1) can be increased to increase the water content of the initial mixing. Then, the water output of the nozzle water inlet control valve (9) can be adjusted again to achieve the effect of no dust. S6; When the spraying operation is completed, first stop adding premixed concrete dry powder to the dry spraying machine or stop discharging the underground building materials pneumatic conveying system. After no material is sprayed out from the nozzle with seat (10), close the water control valve (2), then close the nozzle water inlet control valve (9), and then observe whether there is water spraying out from the nozzle with seat (10). This process takes about 2 minutes. If no water is sprayed out, turn off the dry spraying machine or the underground building materials pneumatic conveying system.

Citation Information

Patent Citations

  • Coal full mechanical remote grouting technique

    CN108049889A

  • Guniting device for mine laneway

    CN219953374U

  • Dry, wet shotcrete

    KR1020120006268A

  • Spray drier

    RU2324872C1

  • Method of Spray Application of Monolithic Refractory, Spray Material for Use Therein, and Application Apparatus

    US20070241204A1