Pumping method, device and system, readable storage medium and engineering machinery

By establishing the correspondence between the stirring data and the pumping control strategy, and automatically adjusting the pumping logic and piston movement, the phenomenon of air suction at the tail of the pumping cylinder during concrete pumping is solved, the discharge continuity and equipment life are improved, and energy consumption is reduced .

CN118934577APending Publication Date: 2024-11-12SANY AUTOMOBILE MFG CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411112255.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-14
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

During the concrete pumping process, there is a phenomenon of emptying at the tail of the pump cylinder, resulting in discontinuous conveying of concrete, causing the pump truck boom to shake and discontinuous discharge, increasing fuel consumption and shortening the service life of the equipment.

Method used

By establishing the corresponding relationship between the stirring data and the pumping control strategy, obtain the stirring data during the rotation of the stirring blade in the hopper, match the pumping control strategy corresponding to the stirring data according to the corresponding relationship, automatically adjust the pumping logic, and control the piston speed and stroke. , to avoid pumping air and boom shaking.

Benefits of technology

It improves the discharge continuity of the pumping process, reduces the energy consumption of the equipment, extends the service life of the boom and boom cylinders, and achieves the fuel-saving effect.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118934577A_ABST
    Figure CN118934577A_ABST
Patent Text Reader

Abstract

The invention provides a pumping method, device and system, a readable storage medium and engineering machinery, and relates to the technical field of engineering machinery, and the pumping method comprises the following steps: establishing a corresponding relation between stirring data and a pumping control strategy; and stirring data in the rotating process of the stirring blades in the hopper are obtained, and a pumping control strategy corresponding to the stirring data is matched according to the corresponding relation to control the pumping system to conduct pumping. By means of the technical scheme, the shaking condition of the arm frame in the pumping process can be effectively reduced, the service life of the arm frame and the service life of the arm frame oil cylinder are prolonged, the discharging continuity in the pumping process is improved, and energy consumption of equipment can be effectively reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of engineering machinery, and in particular to a pumping method and device, a system, a readable storage medium, and engineering machinery. Background Art

[0002] The pumping system is mainly composed of a hopper, a mixing mechanism, a concrete distribution valve, a concrete delivery cylinder, and a main oil cylinder. Through the push-pull action of the oil cylinder, the hydraulic energy is converted into mechanical energy, so that the concrete overcomes the resistance of the pipeline and is transported to the pouring site. During the concrete pumping process, the hopper is filled with concrete, and the mixing blades are placed in the hopper. The main function is to use the rotation of the mixing blades to stir the concrete in the hopper to prevent the concrete from segregating and agglomerating.

[0003] At present, there is a vacuum phenomenon at the tail of the delivery cylinder during concrete pumping, that is, the concrete in the pump truck pipeline system will be discontinuous during the pumping process, which will cause the concrete pump truck arm to shake and discontinuous discharge. The fuel consumption of the equipment will increase, and at the same time it will also aggravate the wear of wearing parts and reduce the service life of the arm and arm cylinder. Summary of the invention

[0004] The embodiments according to the present application are intended to improve at least one of the technical problems existing in the prior art or related art.

[0005] To this end, a first object of the present application is to provide a pumping method.

[0006] A second object of the present application is to provide a pumping device.

[0007] The third object of the present application is to provide a pumping system.

[0008] A fourth object of the present application is to provide a pumping system.

[0009] The fifth object of the present application is to provide a readable storage medium.

[0010] The sixth objective of the present application is to provide a construction machine.

[0011] In order to achieve the first purpose of the present application, the technical solution of the first aspect of the present application provides a pumping method, including: establishing a correspondence between stirring data and pumping control strategy; obtaining stirring data during the rotation of stirring blades in the hopper, and matching the pumping control strategy corresponding to the stirring data according to the correspondence to control the pumping system for pumping.

[0012] According to the pumping method provided in the present application, firstly, a correspondence between the mixing data and the pumping control strategy is established. Then, the mixing data during the rotation of the mixing blades in the hopper is obtained, and the pumping control strategy corresponding to the mixing data is matched according to the corresponding relationship, and the pumping system is controlled to perform pumping according to the corresponding pumping control strategy. The pumping logic is automatically adjusted according to the different quality states of the concrete, and the control system is adapted to ensure that there is no pumping of air during the operation of the pump truck, which causes the boom to shake and high fuel consumption. This can effectively increase the service life of the boom and the boom cylinder, while improving the discharge continuity of the pumping process, effectively reducing the energy consumption of the equipment, and achieving the effect of saving fuel.

[0013] In addition, the technical solution provided by this application may also have the following additional technical features:

[0014] In some technical schemes, optionally, stirring data during the rotation of the stirring blades in the hopper is obtained, and a pumping control strategy corresponding to the stirring data is matched according to the corresponding relationship to control the pumping system to perform pumping, including: obtaining the torque value during the rotation of the stirring blades in the hopper; matching a preset torque value according to the torque value, and controlling the speed and stroke of the piston in the pumping system according to the pumping control strategy corresponding to the preset torque value.

[0015] In this technical solution, the stirring data during the rotation of the stirring blades in the hopper is obtained, and the pumping control strategy corresponding to the stirring data is matched according to the corresponding relationship to control the pumping system to pump. Specifically, the torque value during the rotation of the stirring blades in the hopper is first obtained. Then the preset torque value is matched according to the torque value, and the speed and stroke of the piston in the pumping system are controlled according to the pumping control strategy corresponding to the preset torque value. Under different concrete conditions, setting different piston strokes can effectively avoid the problem of air in the pump truck pumping system sucking materials. When the stroke becomes shorter, the displacement of the pump truck's pumping system can be guaranteed by increasing the piston movement speed. The control system is self-adapted to ensure that there is no pumping air during the operation of the pump truck, causing the boom to shake and high fuel consumption. The service life of the boom and the boom cylinder can be effectively improved, while improving the discharge continuity of the pumping process, effectively reducing the energy consumption of the equipment, and achieving the effect of saving fuel.

[0016] In some technical solutions, optionally, a correspondence between mixing data and pumping control strategy is established, including: obtaining mixing data and an optimal pumping control strategy corresponding to the mixing data; corresponding different concretes to different mixing data, and corresponding different mixing data to different optimal pumping control strategies.

[0017] In this technical solution, the preset torque value is matched according to the torque value, and the speed and stroke of the piston in the pumping system are controlled according to the pumping control strategy corresponding to the preset torque value. Specifically, the mixing data and the optimal pumping control strategy corresponding to the mixing data are first obtained. Then different concretes are matched with different mixing data, and different mixing data are matched with different optimal pumping control strategies. It can be understood that in the case of a mixing data, there are many pumping control strategies, and the best one needs to be found. Under different mixing data, there are corresponding different optimal pumping control strategies, that is, there is no air suction, there is no air in the delivery pipe, and the pumping efficiency is also high.

[0018] In some technical solutions, different concretes are optionally matched with different mixing data, and different mixing data are matched with different optimal pumping control strategies, including: grading the concrete quality according to the torque value in the mixing system corresponding to different concretes to obtain multiple concrete quality grades; matching different concrete quality grades with different piston speeds and strokes.

[0019] In this technical solution, different concretes are matched with different mixing data, and different mixing data are matched with different optimal pumping control strategies. Specifically, the concrete quality is first graded according to the torque value in the mixing system corresponding to different concretes to obtain multiple concrete quality grades. Then, different concrete quality grades are matched with different piston speeds and strokes, so as to obtain pumping control strategies corresponding to different concrete quality grades.

[0020] In some technical solutions, optionally, matching a preset torque value according to the torque value includes: determining whether the torque value is within a preset torque value range; if the torque value is within the preset torque value range, matching the torque value with the preset torque value.

[0021] In this technical solution, the preset torque value is matched according to the torque value, specifically, it is determined whether the torque value is within the preset torque value range. If the torque value is within the preset torque value range, the torque value is matched with the preset torque value. By matching the torque value with the preset torque value, the speed and stroke of the piston in the pumping system can be controlled according to the pumping control strategy corresponding to the preset torque value.

[0022] In some technical schemes, optionally, the speed and stroke of the piston in the pumping system are controlled according to a pumping control strategy corresponding to a preset torque value, including: when the preset torque value is a first torque value, controlling the speed of the piston in the pumping system to a first speed, and controlling the stroke of the piston to a first stroke; or when the preset torque value is a second torque value, controlling the speed of the piston in the pumping system to a second speed, and controlling the stroke of the piston to a second stroke; or when the preset torque value is a third torque value, controlling the speed of the piston in the pumping system to a third speed, and controlling the stroke of the piston to a third stroke.

[0023] In this technical solution, when the preset torque value is the first torque value, the speed of the piston in the pumping system is controlled to be the first speed, and the stroke of the piston is controlled to be the first stroke. When the preset torque value is the second torque value, the speed of the piston in the pumping system is controlled to be the second speed, and the stroke of the piston is controlled to be the second stroke. When the preset torque value is the third torque value, the speed of the piston in the pumping system is controlled to be the third speed, and the stroke of the piston is controlled to be the third stroke.

[0024] In some technical solutions, optionally, obtaining the torque value during the rotation of the stirring blade in the hopper includes: obtaining the torque value during the rotation of the stirring blade in the hopper through a torque sensor.

[0025] In this technical solution, the torque value during the rotation of the mixing blades in the hopper is obtained, specifically, the torque value during the rotation of the mixing blades in the hopper is obtained through a torque sensor, so that the quality of concrete can be graded according to the torque value.

[0026] To achieve the second purpose of the present application, a pumping device is provided according to the technical solution of the second aspect of the present application, including: a hopper, on which a stirring system is provided, the stirring system including stirring blades; a conveying cylinder connected to the hopper, in which a piston is provided; a torque sensor for real-time collection of the torque value during the rotation of the stirring blades; a control system for grading the quality of concrete according to the torque value, and controlling the speed and stroke of the piston according to the concrete quality grade.

[0027] The pumping device provided in the present application includes a hopper, a delivery cylinder, a torque sensor and a control system. The torque sensor is used to collect the torque value in real time during the rotation of the mixing blade. The control system is used to judge the quality grade of the concrete in the hopper according to the torque value. Different concrete quality grades correspond to different pumping control strategies, and the speed and stroke of the piston are controlled according to the concrete quality grade. Under different concrete conditions, setting different piston strokes can effectively avoid the problem of air in the pump truck pumping system sucking materials. When the stroke becomes shorter, the displacement of the pump truck's pumping system can be guaranteed by increasing the piston movement speed. The control system is self-adapted to ensure that there is no pumping of air during the operation of the pump truck, causing the arm frame to shake and high fuel consumption, which can effectively increase the service life of the arm frame and the arm frame cylinder, and at the same time improve the discharge continuity of the pumping process, effectively reduce the energy consumption of the equipment, and achieve the effect of saving fuel.

[0028] To achieve the third purpose of the present application, the technical solution of the third aspect of the present application provides a pumping system, including: a matching module, used to establish a correspondence between stirring data and pumping control strategy; a control module, used to obtain stirring data during the rotation of the stirring blades in the hopper, and match the pumping control strategy corresponding to the stirring data according to the corresponding relationship to control the pumping system to pump.

[0029] The pumping system provided in the present application includes a matching module and a control module. Among them, the matching module is used to establish a corresponding relationship between the mixing data and the pumping control strategy. The control module is used to obtain the mixing data during the rotation of the mixing blades in the hopper, and match the pumping control strategy corresponding to the mixing data according to the corresponding relationship to control the pumping system to pump. The pumping logic is automatically adjusted according to the different quality states of the concrete, and the control system is adapted to ensure that there is no pumping of air during the operation of the pump truck, which causes the boom to shake and high fuel consumption. The service life of the boom and the boom cylinder can be effectively improved, while the discharge continuity of the pumping process is improved, effectively reducing the energy consumption of the equipment and achieving the effect of saving fuel.

[0030] In order to achieve the fourth purpose of the present application, the technical solution of the fourth aspect of the present application provides a pumping system, including: a memory and a processor, wherein the memory stores programs or instructions that can be run on the processor, and when the processor executes the program or instruction, it implements the pumping method of any one of the technical solutions of the first aspect, so it has the technical effect of any one of the technical solutions of the first aspect above, which will not be repeated here.

[0031] In order to achieve the fifth purpose of the present application, the technical solution of the fifth aspect of the present application provides a readable storage medium on which a program or instruction is stored. When the program or instruction is executed by the processor, the steps of the pumping method of any one of the technical solutions of the first aspect are implemented, and thus the technical effect of any one of the technical solutions of the first aspect is achieved, which will not be repeated here.

[0032] To achieve the sixth purpose of the present application, the technical solution of the sixth aspect of the present application provides an engineering machinery, including: a pumping device such as any one of the technical solutions in the second aspect of the present application; and / or a pumping system such as any one of the technical solutions in the third aspect of the present application; and / or a pumping system such as any one of the technical solutions in the fourth aspect of the present application; and / or a readable storage medium such as any one of the technical solutions in the fifth aspect of the present application.

[0033] The engineering machinery provided according to the technical solution of the present application includes a pumping device as in any one of the technical solutions in the second aspect of the present application and / or a pumping system as in any one of the technical solutions in the third aspect of the present application and / or a pumping system as in any one of the technical solutions in the fourth aspect of the present application and / or a readable storage medium as in any one of the technical solutions in the fifth aspect of the present application, and thus it has all the beneficial effects of the pumping device as in any one of the technical solutions in the second aspect of the present application and / or a pumping system as in any one of the technical solutions in the third aspect of the present application and / or a pumping system as in any one of the technical solutions in the fourth aspect of the present application and / or a readable storage medium as in any one of the technical solutions in the fifth aspect of the present application, which are not repeated here.

[0034] Additional aspects and advantages of the embodiments according to the present application will become apparent in the following description or will be understood through the practice of the embodiments according to the present application. BRIEF DESCRIPTION OF THE DRAWINGS

[0035] Figure 1 This is a partial front view structural diagram of a pumping device according to an embodiment of the present application;

[0036] Figure 2 This is a schematic diagram of the main structure of a pumping device according to an embodiment of the present application;

[0037] Figure 3 This is a schematic diagram of the main structure of a pumping device according to an embodiment of the present application;

[0038] Figure 4 This is a schematic diagram of the main structure of a pumping device according to an embodiment of the present application;

[0039] Figure 5 This is a schematic diagram of the main structure of an engineering machinery according to an embodiment of the present application;

[0040] Figure 6 A schematic flow chart of the steps of a pumping method according to an embodiment of the present application;

[0041] Figure 7 A schematic flow chart of the steps of a pumping method according to an embodiment of the present application;

[0042] Figure 8 A schematic flow chart of the steps of a pumping method according to an embodiment of the present application;

[0043] Fig. 9 This is a schematic structural block diagram of a pumping system according to an embodiment of the present application;

[0044] Fig.10 This is a schematic structural block diagram of a pumping system according to an embodiment of the present application;

[0045] Fig.11 This is a schematic block diagram of the structure of a pumping device according to an embodiment of the present application;

[0046] Fig.12 A schematic flow chart of the steps of a pumping method according to an embodiment of the present application;

[0047] Fig.13 A schematic flow chart of the steps of a pumping method according to an embodiment of the present application;

[0048] Fig.14 A schematic flow chart of the steps of a pumping method according to an embodiment of the present application;

[0049] Fig.15 A schematic flow chart of the steps of a pumping method according to an embodiment of the present application;

[0050] Fig.16 This is a schematic flow chart of the steps of a pumping method according to an embodiment of the present application.

[0051] in, Figures 1 to 16 The corresponding relationship between the reference numerals and component names in the figure is:

[0052] 10: Pumping device; 110: Hopper; 112: Stirring system; 114: Stirring blades; 116: Stirring shaft; 118: Stirring motor; 120: Conveying cylinder; 122: Piston; 130: Torque sensor; 140: Pressure sensor; 150: Control system; 160: Oil cylinder; 170: Water tank; 20: Pumping system; 220: Matching module; 230: Control module; 30: Pumping system; 300: Memory; 400: Processor; 50: Engineering machinery. DETAILED DESCRIPTION

[0053] In order to more clearly understand the above-mentioned purposes, features and advantages of the embodiments of the present application, the embodiments of the present application are further described in detail below in conjunction with the accompanying drawings and specific implementation methods. It should be noted that the features of the embodiments of the present application can be combined with each other without conflict.

[0054] In the following description, many specific details are set forth to facilitate a full understanding of the embodiments of the present application. However, the embodiments of the present application may also be implemented in other ways different from those described herein. Therefore, the scope of protection provided by the embodiments of the present application is not limited to the specific embodiments disclosed below.

[0055] Refer to the following Figures 1 to 16 Some embodiments provided according to the present application are described.

[0056] like Figure 1 , Figure 2 , Fig.11 As shown, a pumping device 10 proposed according to an embodiment of the present application includes a hopper 110, a delivery cylinder 120, a torque sensor 130 and a control system 150. Specifically, a mixing system 112 is provided on the hopper 110, and the mixing system 112 includes a mixing blade 114. The delivery cylinder 120 is connected to the hopper 110, and a piston 122 is provided in the delivery cylinder 120. The torque sensor 130 is used to collect the torque value of the mixing blade 114 in real time during the rotation process. The control system 150 is used to grade the quality of concrete according to the torque value and the mixing pressure value, and control the speed and stroke of the piston 122 according to the concrete quality grade.

[0057] The pumping device 10 provided in this embodiment includes a hopper 110, a delivery cylinder 120, a torque sensor 130 and a control system 150. The torque sensor 130 is used to collect the torque value in the process of the rotation of the mixing blade 114 in real time. The control system 150 is used to judge the quality grade of the concrete in the hopper 110 according to the torque value. Different concrete quality grades correspond to different pumping control strategies, and the speed and stroke of the piston 122 are controlled according to the concrete quality grade. Under different concrete conditions, setting different piston 122 strokes can effectively avoid the problem of air in the pumping system of the pump truck. When the stroke becomes shorter, the displacement of the pump truck's pumping system can be ensured by increasing the movement speed of the piston 122. The control system 150 is self-adapted to ensure that there is no pumping air during the operation of the pump truck, causing the arm frame to shake and high fuel consumption, which can effectively increase the service life of the arm frame and the arm frame cylinder 160, and at the same time improve the discharge continuity of the pumping process, effectively reduce the energy consumption of the equipment, and achieve the effect of saving fuel.

[0058] In some embodiments, the pumping device 10 may further include a pressure sensor 140. The pressure sensor 140 is used to obtain a mixing pressure value. The control system 150 is used to grade the concrete quality according to the torque value and the mixing pressure value, and to control the speed and stroke of the piston 122 according to the concrete quality grade.

[0059] In some embodiments, the mixing system 112 may further include a mixing shaft 116 and a mixing motor 118. The mixing motor 118 mixes the concrete in the hopper 110 by driving the mixing shaft 116 to rotate and thereby driving the mixing blades 114 to rotate. The torque sensor 130 is disposed on the mixing shaft 116 and can collect the torque value in real time during the rotation of the mixing blades 114. The pressure sensor 140 is disposed on a hydraulic hose connected to the mixing motor 118 and is used to obtain the mixing pressure value.

[0060] In some embodiments, the pumping device 10 may further include an oil cylinder 160 and a water tank 170. The oil cylinder 160 is connected to the delivery cylinder 120 and is used to drive the piston 122. The water tank 170 is disposed between the oil cylinder 160 and the delivery cylinder 120. The movement stroke and movement speed of the piston 122 are adjusted by the action of the oil cylinder 160 driven by the hydraulic system.

[0061] In some embodiments, optionally, there are two stirring systems 112 , and the two stirring systems 112 are symmetrically arranged on both sides of the hopper 110 .

[0062] like Fig.16 As shown, an embodiment of the second aspect of the present application provides a pumping method, comprising the following steps:

[0063] Step S102: establishing a corresponding relationship between stirring data and pumping control strategy;

[0064] Step S104: Acquire stirring data during the rotation of the stirring blades in the hopper, and match a pumping control strategy corresponding to the stirring data according to the corresponding relationship to control the pumping system to perform pumping.

[0065] According to the pumping method provided in this embodiment, firstly, a correspondence between the mixing data and the pumping control strategy is established. Then, the mixing data during the rotation of the mixing blades in the hopper is obtained, and the pumping control strategy corresponding to the mixing data is matched according to the corresponding relationship, and the pumping system is controlled to perform pumping according to the corresponding pumping control strategy. The pumping logic is automatically adjusted according to the different quality states of the concrete, and the control system is adapted to ensure that there is no pumping of air during the operation of the pump truck, which causes the boom to shake and high fuel consumption. This can effectively increase the service life of the boom and the boom cylinder, while improving the discharge continuity of the pumping process, effectively reducing the energy consumption of the equipment, and achieving the effect of saving fuel.

[0066] like Figure 6 As shown, according to a pumping method of an embodiment proposed in the present application, the stirring data during the rotation of the stirring blades in the hopper is obtained, and a pumping control strategy corresponding to the stirring data is matched according to the corresponding relationship to control the pumping system to pump, which specifically includes the following steps:

[0067] Step S202: obtaining the torque value of the stirring blade in the hopper during the rotation process;

[0068] Step S204: matching a preset torque value according to the torque value, and controlling the speed and stroke of the piston in the pumping system according to a pumping control strategy corresponding to the preset torque value.

[0069] In this embodiment, the torque value during the rotation of the mixing blades in the hopper is first obtained. Then, the preset torque value is matched according to the torque value, and the speed and stroke of the piston in the pumping system are controlled according to the pumping control strategy corresponding to the preset torque value. Under different concrete conditions, setting different piston strokes can effectively avoid the problem of air in the pump truck pumping system sucking materials. When the stroke becomes shorter, the displacement of the pump truck's pumping system can be guaranteed by increasing the piston movement speed. The control system is adaptive to ensure that there is no pumping of air during the operation of the pump truck, which causes the boom to shake and high fuel consumption. The service life of the boom and the boom cylinder can be effectively improved, while improving the discharge continuity of the pumping process, effectively reducing the energy consumption of the equipment, and achieving the effect of saving fuel.

[0070] like Fig.12 As shown, according to a pumping method of an embodiment proposed in the present application, a corresponding relationship between stirring data and a pumping control strategy is established, which specifically includes the following steps:

[0071] Step S302: Acquire stirring data and the optimal pumping control strategy corresponding to the stirring data;

[0072] Step S304: different concretes correspond to different mixing data, and different mixing data correspond to different optimal pumping control strategies.

[0073] In this embodiment, the mixing data and the optimal pumping control strategy corresponding to the mixing data are first obtained. Then different concretes are matched to different mixing data, and different mixing data are matched to different optimal pumping control strategies. It can be understood that under a mixing data condition, there are many pumping control strategies, and the best one needs to be found. Under different mixing data, there are corresponding different optimal pumping control strategies, that is, there is no air in the delivery pipe and the pumping efficiency is high.

[0074] like Fig.13 As shown, according to a pumping method of an embodiment proposed in the present application, different concretes correspond to different mixing data, and different mixing data correspond to different optimal pumping control strategies, which specifically includes the following steps:

[0075] Step S402: classifying the quality of concrete according to the torque values ​​in the mixing system corresponding to different concretes to obtain multiple concrete quality grades;

[0076] Step S404: Match different concrete quality grades with different piston speeds and strokes.

[0077] In this embodiment, different concretes are matched with different mixing data, and different mixing data are matched with different optimal pumping control strategies. Specifically, the concrete quality is graded according to the torque value in the mixing system corresponding to different concretes to obtain multiple concrete quality grades. Different concrete quality grades are matched with different piston speeds and strokes, so as to obtain pumping control strategies corresponding to different concrete quality grades.

[0078] like Fig.14 As shown, according to a pumping method of an embodiment proposed in the present application, matching a preset torque value according to a torque value specifically includes the following steps:

[0079] Step S502: determining whether the torque value is within a preset torque value range;

[0080] Step S504: If the torque value is within the preset torque value range, the torque value is matched to the preset torque value.

[0081] In this embodiment, the preset torque value is matched according to the torque value, specifically, it is determined whether the torque value is within the preset torque value range. If the torque value is within the preset torque value range, the torque value is matched with the preset torque value. By matching the torque value with the preset torque value, the speed and stroke of the piston in the pumping system can be controlled according to the pumping control strategy corresponding to the preset torque value.

[0082] like Fig.15 As shown, according to a pumping method of an embodiment proposed in the present application, the speed and stroke of the piston in the pumping system are controlled according to a pumping control strategy corresponding to a preset torque value, specifically comprising the following steps:

[0083] Step S602: When the preset torque value is a first torque value, the speed of the piston in the pumping system is controlled to be a first speed, and the stroke of the piston is controlled to be a first stroke; or when the preset torque value is a second torque value, the speed of the piston in the pumping system is controlled to be a second speed, and the stroke of the piston is controlled to be a second stroke; or when the preset torque value is a third torque value, the speed of the piston in the pumping system is controlled to be a third speed, and the stroke of the piston is controlled to be a third stroke.

[0084] In this embodiment, when the preset torque value is a first torque value, the speed of the piston in the pumping system is controlled to be a first speed, and the stroke of the piston is controlled to be a first stroke. When the preset torque value is a second torque value, the speed of the piston in the pumping system is controlled to be a second speed, and the stroke of the piston is controlled to be a second stroke. When the preset torque value is a third torque value, the speed of the piston in the pumping system is controlled to be a third speed, and the stroke of the piston is controlled to be a third stroke.

[0085] like Figure 7 As shown, according to a pumping method of an embodiment proposed in the present application, obtaining the torque value during the rotation of the stirring blade in the hopper specifically includes the following steps:

[0086] Step S702: Obtain the torque value of the stirring blade in the hopper during rotation through the torque sensor.

[0087] In this embodiment, the torque value during the rotation of the mixing blades in the hopper is obtained, specifically, the torque value during the rotation of the mixing blades in the hopper is obtained by a torque sensor, so that the quality of concrete can be graded according to the torque value.

[0088] like Fig. 9 As shown, an embodiment of the third aspect of the present application provides a pumping system 20, including: a matching module 220, used to establish a correspondence between stirring data and a pumping control strategy; a control module 230, used to obtain stirring data during the rotation of stirring blades in the hopper, and match the pumping control strategy corresponding to the stirring data according to the corresponding relationship to control the pumping system to pump.

[0089] The pumping system 20 provided according to the present embodiment includes a matching module 220 and a control module 230. Among them, the matching module 220 is used to establish a corresponding relationship between the mixing data and the pumping control strategy. The control module 230 is used to obtain the mixing data during the rotation of the mixing blades in the hopper, and match the pumping control strategy corresponding to the mixing data according to the corresponding relationship to control the pumping system to pump. Under different concrete conditions, setting different piston strokes can effectively avoid the problem of air in the pump truck pumping system sucking materials. When the stroke becomes shorter, the displacement of the pump truck's pumping system can be guaranteed by increasing the piston movement speed. The control system is self-adapted to ensure that there is no pumping air during the operation of the pump truck, causing the boom to shake and high fuel consumption. The service life of the boom and the boom cylinder can be effectively improved, while improving the discharge continuity of the pumping process, effectively reducing the energy consumption of the equipment, and achieving the effect of saving fuel.

[0090] like Fig.10 As shown, an embodiment of the fourth aspect of the present application provides a pumping system 30, comprising: a memory 300 and a processor 400, wherein the memory 300 stores a program or instruction that can be run on the processor 400, and when the processor 400 executes the program or instruction, the steps of the pumping method of any one of the embodiments of the second aspect are implemented, so it has the technical effect of any one of the embodiments of the second aspect mentioned above, which will not be repeated here.

[0091] The embodiment of the fifth aspect of the present application provides a readable storage medium on which a program or instruction is stored. When the program or instruction is executed by a processor, the steps of the pumping method of any one of the embodiments of the first aspect are implemented, and thus the technical effects of any one of the embodiments of the first aspect mentioned above are not repeated here.

[0092] like Figure 5 As shown, an embodiment of the sixth aspect of the present application provides an engineering machine 50, comprising a pumping device 10 as in any of the above embodiments and / or a pumping system 20 as in any of the above embodiments and / or a readable storage medium as in any of the above embodiments.

[0093] The engineering machinery 50 provided according to the embodiment of the present application includes a pumping device 10 as in any of the above embodiments and / or a pumping system 20 as in any of the above embodiments and / or a pumping system 30 as in any of the above embodiments and / or a readable storage medium as in any of the above embodiments, so it has all the beneficial effects of the pumping device 10 as in any of the above embodiments and / or a pumping system 20 as in any of the above embodiments and / or a pumping system 30 as in any of the above embodiments and / or a readable storage medium as in any of the above embodiments, which will not be described in detail herein. Among them, the engineering machinery includes a concrete pump truck.

[0094] like Figure 1 , Figure 2 , Figure 3 , Figure 4 , Figure 5 , Figure 8 As shown, a pumping device 10 according to a specific embodiment of the present application includes a hopper 110, a delivery cylinder 120, a piston 122, a water tank 170, and an oil cylinder 160, wherein the movement stroke and movement speed of the piston 122 are adjusted by the action of the oil cylinder 160 driven by the hydraulic system.

[0095] Specifically, a torque sensor 130 is installed on the stirring shaft 116 in the stirring system 112 in the hopper 110 of the pump truck, which can collect the torque value of the stirring blade 114 during the rotation process and the hydraulic system pressure value of the hydraulic motor in real time to determine the quality grade of the concrete in the hopper 110.

[0096] In the early stage, through factory tests, the quality of different concretes is changed to collect the corresponding values ​​of the mixing torque sensor 130 and the pressure of the mixing hydraulic system, and the concrete is divided into N grades, namely A1, A2...An and other different grades. Different concrete quality grades correspond to different pumping control strategies.

[0097] like Figure 3 and Figure 5 As shown, during the pumping process, it is found that when the quality of concrete in the hopper 110 is poor, the pumping system of the concrete pump truck has a certain inclination angle.

[0098] At this time, according to the conventional pumping mode, no matter what the concrete condition is, the piston 122 in the delivery cylinder 120 will return to the end of the delivery cylinder 120 to suck the material. When the concrete is poor, a phenomenon will occur, that is, the part at the end of the delivery cylinder 120 will not be able to suck up the material, and there will be a phenomenon that some air exists. This part of the air is pushed outward by the piston 122, that is, during the pumping process, the concrete in the pipeline system of the pump truck will be discontinuous, which will cause a series of problems such as the shaking of the concrete pump truck arm and discontinuous discharge, resulting in increased fuel consumption of the equipment.

[0099] like Figure 4 As shown, in order to solve the above problem, it is found that by controlling the movement stroke of the piston 122, setting different piston strokes under different concrete conditions can effectively avoid the problem of air being present in the material suction of the pump truck pumping system.

[0100] like Figure 8As shown, the technical solution of this embodiment is as follows. First, the quality of the concrete pumped this time is judged by the torque value in the mixing system 112 and the mixing pressure value of the hydraulic system. It can be calibrated as A1, A2...An and other different levels in advance, and then the speed and stroke of the piston 122 in the pumping system are set by the control system 150. When the stroke becomes shorter, the displacement of the pump system of the pump truck can be guaranteed by increasing the piston movement speed. The control system 150 is adapted to ensure that there is no pumping of air during the operation of the pump truck, which will cause the boom to shake and the fuel consumption to be high.

[0101] In summary, the beneficial effects of the embodiments of the present application are:

[0102] 1. It can effectively reduce the vibration of the boom during pumping and reduce a series of problems caused by the vibration of the boom. At the same time, it can effectively increase the service life of the boom and the boom cylinder.

[0103] 2. It can improve the discharge continuity of the pumping process, effectively reduce the energy consumption of the equipment and achieve the effect of fuel saving.

[0104] In the embodiments according to the present application, the terms "first", "second", and "third" are used for descriptive purposes only and are not to be understood as indicating or implying relative importance; the term "plurality" refers to two or more, unless otherwise expressly defined. Terms such as "installed", "connected", "connected", and "fixed" should be understood in a broad sense. For example, "connected" can be a fixed connection, a detachable connection, or an integral connection; "connected" can be a direct connection or an indirect connection through an intermediate medium. For those of ordinary skill in the art, the specific meanings of the above terms in the embodiments according to the present application can be understood according to the specific circumstances.

[0105] In the description of the embodiments of the present application, it needs to be understood that the directions or positional relationships indicated by the terms "up", "down", "left", "right", "front", "back", etc. are based on the directions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the embodiments of the present application and simplifying the description, rather than indicating or implying that the referred device or unit must have a specific direction, be constructed and operated in a specific orientation, and therefore, cannot be understood as a limitation on the embodiments of the present application.

[0106] In the description of this specification, the description of the terms "one embodiment", "some embodiments", "specific embodiments", etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example according to the present application. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described can be combined in any one or more embodiments or examples in a suitable manner.

[0107] The above are only preferred embodiments of the present application and are not intended to limit the embodiments of the present application. For those skilled in the art, various modifications and changes may be made to the embodiments of the present application. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the embodiments of the present application shall be included in the protection scope of the embodiments of the present application.

Claims

1. A pumping method, characterized in that: include: Establish the correspondence between mixing data and pumping control strategy; The stirring data during the rotation of the stirring blades in the hopper is obtained, and a pumping control strategy corresponding to the stirring data is matched according to the corresponding relationship to control the pumping system to perform pumping.

2. The pumping method according to claim 1, characterized in that: The step of acquiring stirring data during the rotation of the stirring blades in the hopper and matching a pumping control strategy corresponding to the stirring data according to the corresponding relationship to control the pumping system to perform pumping includes: Obtain the torque value during the rotation of the stirring blade in the hopper; A preset torque value is matched according to the torque value, and a speed and a stroke of a piston in a pumping system are controlled according to a pumping control strategy corresponding to the preset torque value.

3. The pumping method according to claim 2, characterized in that: The establishing of the corresponding relationship between the stirring data and the pumping control strategy includes: Acquire stirring data and an optimal pumping control strategy corresponding to the stirring data; Different concretes correspond to different mixing data, and different mixing data correspond to different optimal pumping control strategies.

4. The pumping method according to claim 3, characterized in that: The method of corresponding different mixing data to different concretes and corresponding different mixing data to different optimal pumping control strategies includes: The concrete quality is graded according to the torque value in the mixing system corresponding to different concretes, and multiple concrete quality grades are obtained; Different concrete quality grades are matched with different piston speeds and strokes.

5. The pumping method according to claim 2, characterized in that: The matching of the preset torque value according to the torque value comprises: Determining whether the torque value is within a preset torque value range; If the torque value is within the preset torque value range, the torque value is matched with the preset torque value.

6. The pumping method according to claim 5, characterized in that: The method of controlling the speed and stroke of the piston in the pumping system according to the pumping control strategy corresponding to the preset torque value includes: When the preset torque value is a first torque value, controlling the speed of the piston in the pumping system to be a first speed, and controlling the stroke of the piston to be a first stroke; or When the preset torque value is a second torque value, controlling the speed of the piston in the pumping system to be a second speed, and controlling the stroke of the piston to be a second stroke; or When the preset torque value is the third torque value, the speed of the piston in the pumping system is controlled to be the third speed, and the stroke of the piston is controlled to be the third stroke.

7. The pumping method according to any one of claims 2 to 6, characterized in that: The step of obtaining the torque value during the rotation of the stirring blade in the hopper includes: The torque value during the rotation of the stirring blade in the hopper is obtained through the torque sensor.

8. A pumping device, characterized in that: include: A hopper (110), wherein the hopper (110) is provided with a stirring system (112), and the stirring system (112) includes a stirring blade (114); A conveying cylinder (120) connected to the hopper (110), wherein a piston (122) is provided in the conveying cylinder (120); A torque sensor (130) for collecting the torque value of the stirring blade (114) in real time during its rotation; A control system (150) is used to grade the quality of the concrete according to the torque value, and to control the speed and stroke of the piston (122) according to the concrete quality grade.

9. A pumping system, characterized in that: include: A matching module (220) is used to establish a corresponding relationship between the stirring data and the pumping control strategy; The control module (230) is used to obtain stirring data during the rotation of the stirring blades in the hopper, and to match a pumping control strategy corresponding to the stirring data according to the corresponding relationship to control the pumping system to perform pumping.

10. A pumping system, characterized in that: include: A memory (300) and a processor (400), wherein the memory (300) stores a program or instruction that can be run on the processor (400), and when the processor (400) executes the program or the instruction, the steps of the pumping method according to any one of claims 1 to 7 are implemented.

11. A readable storage medium having a program or instruction stored thereon, characterized in that: When the program or the instructions are executed by a processor, the steps of the pumping method according to any one of claims 1 to 7 are implemented.

12. An engineering machine, characterized in that: include: The pumping device as claimed in claim 8; and / or The pumping system of claim 9; and / or The pumping system of claim 10; and / or The readable storage medium as claimed in claim 11.

Citation Information

Cited By

  • Pumping method, apparatus and system, readable storage medium, and construction machine

    WO2026036896A1