Method and device for determining blast furnace drill bit, electronic equipment and storage medium

By calculating the history and target molten iron flow rate of the blast furnace, generating a calibration table and correcting the drill bit size, the problem of experience reliance on blast furnace drill bit size selection is solved, and the blast furnace operation stability and net slag iron efficiency are improved.

CN118939935APending Publication Date: 2024-11-12SGIS SONGSHAN CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411072789.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-06
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

The size selection of existing blast furnace drill bits depends on the operator's experience, resulting in large differences in slag and iron output between shifts, affecting the operation stability of blast furnace.

Method used

By obtaining the historical operation data and current operation data of the blast furnace, calculate the historical iron flow rate and target iron flow rate, generate a calibration table, determine the target drill bit size, and correct it based on the current operation data, and scientifically select the drill bit size.

Benefits of technology

It effectively improves the stability of blast furnace operation, reduces slag iron residue, improves the efficiency of net slag iron, and avoids instability caused by empirical selection.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118939935A_ABST
    Figure CN118939935A_ABST
Patent Text Reader

Abstract

The invention discloses a blast furnace drill bit determination method and device, electronic equipment and a storage medium. The blast furnace drill bit determining method comprises the steps that historical operation data and current operation data of a blast furnace are obtained; according to the historical operation data and the current operation data, the historical molten iron flow rate of the blast furnace and the target molten iron flow rate of the blast furnace are calculated; generating a first calibration table according to the historical molten iron flow velocity and the historical operation data; and determining the target drill bit size of the blast furnace according to the current operation data, the target molten iron flow velocity and the first calibration table. According to the technical scheme provided by the embodiment of the invention, the technical problems that in the prior art, the size of the drill bit is selected according to experience, and due to the fact that personal experience levels are inconsistent, the iron slag tapping difference between shifts is large, and the blast furnace runs unstably are solved, and the running stability of the blast furnace is effectively improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of blast furnace smelting, and in particular to a method, device, electronic equipment and storage medium for determining a blast furnace drill bit. Background Art

[0002] When the blast furnace taps, the choice of drill bit specifications is directly related to whether the slag inside the blast furnace can be discharged smoothly and cleanly. If the drill bit specifications are too large, the slag inside the blast furnace cannot be discharged cleanly, which is easy to cause slag and iron to be trapped inside the blast furnace, resulting in fluctuations in the blast furnace condition; if the drill bit specifications are too small, the slag and iron in the blast furnace cannot be discharged in time, causing air blocking.

[0003] At present, the selection of drill bit size for each blast furnace is mainly based on the experience of the blast furnace operator, who directs the furnace operator to select the drill bit size when opening the iron hole. Due to the inconsistent personal experience level, the slag and iron output between shifts vary greatly, resulting in unstable blast furnace operation. Summary of the invention

[0004] The present invention provides a method, device, electronic device and storage medium for determining a blast furnace drill bit, so as to solve the technical problem that the existing technology selects the drill bit size based on experience, and due to inconsistent personal experience levels, there is a large difference in slag and iron output between shifts, resulting in unstable blast furnace operation.

[0005] According to one aspect of the present invention, a method for determining a blast furnace drill bit is provided, comprising:

[0006] Obtain the historical and current operation data of the blast furnace;

[0007] Calculating a historical molten iron flow rate of a blast furnace and a target molten iron flow rate of the blast furnace respectively according to the historical operation data and the current operation data;

[0008] generating a first calibration table according to the historical molten iron flow rate and the historical operation data;

[0009] A target drill bit size for the blast furnace is determined based on the current operating data, the target molten iron flow rate, and the first calibration table.

[0010] Optionally, the historical operation data include: the average daily output of the blast furnace in the previous month, the daily iron-tapping interval of the blast furnace in the previous month, and the daily iron-tapping furnace times of the blast furnace in the previous month; the current operation data include: the iron surplus or shortage of the blast furnace, the iron-tapping interval of the current furnace, the iron-tapping time of the current furnace, and the theoretical value of molten iron generation per minute;

[0011] The calculating, according to the historical operation data and the current operation data, respectively, the historical molten iron flow rate of the blast furnace and the target molten iron flow rate of the blast furnace comprises:

[0012] Calculate the historical molten iron flow rate of the blast furnace according to the average daily output of the blast furnace in the previous month, the daily iron-tapping interval of the blast furnace in the previous month, and the daily iron-tapping heats of the blast furnace in the previous month;

[0013] The target molten iron flow rate of the blast furnace is calculated according to the iron surplus or shortage, the tapping interval, the tapping time and the theoretical value of molten iron production per minute.

[0014] Optionally, the calculating the historical molten iron flow rate of the blast furnace according to the average daily output of the blast furnace in the previous month, the daily iron-tapping interval of the blast furnace in the previous month, and the daily iron-tapping heats of the blast furnace in the previous month comprises:

[0015] The historical molten iron flow rate of the blast furnace is calculated using the following formula:

[0016] V0=M0 / (1440-t0×N0);

[0017] Wherein, V0 is the historical molten iron flow rate, M0 is the average daily output of the blast furnace in the last month, t0 is the daily iron-tapping interval of the blast furnace in the last month, and N0 is the daily iron-tapping furnace times of the blast furnace in the last month.

[0018] Optionally, calculating the target molten iron flow rate of the blast furnace according to the iron abundance or shortage, the tapping interval, the tapping time, and the theoretical value of molten iron production per minute includes:

[0019] Multiplying the tapping time and the theoretical value of molten iron production per minute to obtain a first product;

[0020] Multiplying the tapping interval time and the theoretical value of molten iron production per minute to obtain a second product;

[0021] Adding the first product, the second product and the iron abundance or deficit to obtain a first sum value;

[0022] The quotient obtained by dividing the first sum value by the iron tapping time is determined as the target molten iron flow rate of the blast furnace.

[0023] Optionally, the current operation data also includes: the wind pressure of the blast furnace at the current moment, the furnace temperature of the blast furnace at the current moment, and the iron mouth depth of the blast furnace;

[0024] Determining the target drill bit size of the blast furnace according to the current operation data, the target molten iron flow rate and the first calibration table includes:

[0025] According to the target molten iron flow rate, determining a first target drill bit size for the blast furnace by querying the first calibration table;

[0026] Determining a correction coefficient according to the wind pressure, the furnace temperature and the taphole depth;

[0027] A second target drill size is determined according to the correction coefficient and the first target drill size.

[0028] Optionally, the correction coefficient includes a first correction coefficient, a second correction coefficient and a third correction coefficient;

[0029] Determining the correction coefficient according to the wind pressure, the furnace temperature and the taphole depth includes:

[0030] When the wind pressure is greater than or equal to a preset standard wind pressure value, the first correction coefficient is less than or equal to a first preset threshold value;

[0031] When the wind pressure is less than a preset standard wind pressure value, the first correction coefficient is greater than a first preset threshold value;

[0032] When the furnace temperature is greater than or equal to a preset standard furnace temperature value, the second correction coefficient is greater than a first preset threshold value;

[0033] When the furnace temperature is lower than a preset standard furnace temperature value, the second correction coefficient is lower than or equal to a first preset threshold value;

[0034] When the iron mouth depth is greater than or equal to a preset standard iron mouth depth value, the third correction coefficient is greater than a first preset threshold value;

[0035] When the iron mouth depth is less than a preset standard iron mouth depth value, the third correction coefficient is less than or equal to a first preset threshold value.

[0036] According to another aspect of the present invention, there is provided a device for determining a blast furnace drill bit, comprising:

[0037] An acquisition module, the acquisition module is used to acquire historical operation data and current operation data of the blast furnace;

[0038] A calculation module, the calculation module is used to calculate the historical molten iron flow rate of the blast furnace and the target molten iron flow rate of the blast furnace according to the historical operation data and the current operation data;

[0039] A generating module, the generating module is used to generate a first calibration table according to the historical molten iron flow rate and the historical operation data;

[0040] A determination module is used to determine a target drill bit size for a blast furnace based on the current operating data, the target molten iron flow rate, the first calibration table, and a preset correction coefficient.

[0041] Optionally, the historical operation data include: the average daily output of the blast furnace in the previous month, the daily iron-tapping interval of the blast furnace in the previous month, and the daily iron-tapping furnace times of the blast furnace in the previous month; the current operation data include: the iron surplus or shortage of the blast furnace, the iron-tapping interval of the current furnace, the iron-tapping time of the current furnace, and the theoretical value of molten iron generation per minute;

[0042] The calculation module includes a first calculation submodule and a second calculation submodule;

[0043] The first calculation submodule is used to calculate the historical molten iron flow rate of the blast furnace according to the average daily output of the blast furnace in the last month, the daily iron-tapping interval of the blast furnace in the last month, and the daily iron-tapping heats of the blast furnace in the last month;

[0044] The second calculation submodule is used to calculate the target molten iron flow rate of the blast furnace according to the iron surplus or shortage, the tapping interval time, the tapping time and the theoretical value of the molten iron production per minute.

[0045] According to another aspect of the present invention, an electronic device is provided, the electronic device comprising:

[0046] at least one processor; and

[0047] a memory communicatively connected to the at least one processor; wherein,

[0048] The memory stores a computer program executable by the at least one processor, and the computer program is executed by the at least one processor so that the at least one processor can execute the method for determining a blast furnace drill bit described in any embodiment of the present invention.

[0049] According to another aspect of the present invention, a computer-readable storage medium is provided, wherein the computer-readable storage medium stores computer instructions, and the computer instructions are used to enable a processor to implement the method for determining a blast furnace drill bit described in any embodiment of the present invention when executed.

[0050] The embodiment of the present invention provides a method, device, electronic device and storage medium for determining a blast furnace drill bit. The method includes: obtaining historical operation data and current operation data of the blast furnace; calculating the historical molten iron flow rate of the blast furnace and the target molten iron flow rate of the blast furnace according to the historical operation data and the current operation data; generating a first calibration table according to the historical molten iron flow rate and the historical operation data; determining the target drill bit size of the blast furnace according to the current operation data, the target molten iron flow rate and the first calibration table. The technical solution provided by the embodiment of the present invention combines the factors that affect whether a blast furnace can produce clean slag and iron, obtains the historical operation data of the blast furnace, calculates the historical molten iron flow rate of the blast furnace according to the historical operation data, and obtains the first calibration table by collecting and sorting the historical operation data and the historical molten iron flow rate. The table can characterize the relationship between the historical molten iron flow rate, the historical operation data and the drill bit size specifications, calculates the target molten iron flow rate according to the current operation data, and preliminarily determines the drill bit size corresponding to the target molten iron flow rate according to the target molten iron flow rate and the first calibration table, and corrects the preliminarily determined drill bit size in combination with the current operation data to obtain the final target drill bit size of the blast furnace, which provides a scientific basis and construction standards for the size selection of the blast furnace drill bit, and does not need to rely on personal experience to select the size of the blast furnace drill bit, which solves the technical problem that the prior art selects the drill bit size based on experience, and due to inconsistent personal experience levels, there is a large difference in slag and iron output between shifts, resulting in unstable blast furnace operation. The technical solution provided by the embodiment of the present invention effectively improves the stability of blast furnace operation.

[0051] It should be understood that the contents described in this section are not intended to identify the key or important features of the embodiments of the present invention, nor are they intended to limit the scope of the present invention. Other features of the present invention will become easily understood through the following description. BRIEF DESCRIPTION OF THE DRAWINGS

[0052] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the following briefly introduces the drawings required for use in the description of the embodiments. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.

[0053] Figure 1 A flow chart of a method for determining a blast furnace drill bit provided by an embodiment of the present invention;

[0054] Figure 2 A flow chart of another method for determining a blast furnace drill bit provided by an embodiment of the present invention;

[0055] Figure 3 A flow chart of another method for determining a blast furnace drill bit provided by an embodiment of the present invention;

[0056] Figure 4A schematic structural diagram of a device for determining a blast furnace drill bit provided by an embodiment of the present invention;

[0057] Figure 5 A schematic structural diagram of an electronic device for a method for determining a blast furnace drill bit provided for the implementation of the present invention. DETAILED DESCRIPTION

[0058] In order to enable those skilled in the art to better understand the scheme of the present invention, the technical scheme in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present invention.

[0059] It should be noted that the terms "first", "second", etc. in the specification and claims of the present invention and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequence. It should be understood that the data used in this way can be interchanged where appropriate, so that the embodiments of the present invention described herein can be implemented in an order other than those illustrated or described herein. In addition, the terms "including" and "having" and any variations thereof are intended to cover non-exclusive inclusions, for example, a process, method, system, product or device that includes a series of steps or units is not necessarily limited to those steps or units that are clearly listed, but may include other steps or units that are not clearly listed or inherent to these processes, methods, products or devices.

[0060] Figure 1 This is a flow chart of a method for determining a blast furnace drill bit provided by an embodiment of the present invention. This embodiment can be applied to the selection of the drill bit size required for opening an iron hole in a blast furnace. The method can be executed by a blast furnace drill bit determination device, which can be implemented in the form of hardware and / or software, and can be configured in any electronic device with a communication function. Figure 1 , the determination method includes:

[0061] S110. Acquire historical operation data and current operation data of the blast furnace.

[0062] Among them, the historical operation data include the average daily output of the blast furnace in the previous month, the daily iron-tapping interval of the blast furnace in the previous month, and the daily iron-tapping furnaces in the previous month; the current operation data include: the blast furnace's iron surplus or shortage, the iron-tapping interval of the current furnace, and the iron-tapping time of the current furnace; the iron surplus or shortage refers to the fact that the actual amount of molten iron produced by the blast furnace during the production process is less than the expected or designed output; the iron-tapping time refers to the time period from the opening of the iron tapping port to the closing of the iron tapping port of the blast furnace.

[0063] Specifically, the historical and current operation data of the blast furnace are obtained by querying the stored record information; for example, the historical and current operation data of the blast furnace are obtained through the iron zone dynamic system. The iron zone dynamic system is an information management and control system applied to the ironmaking area, which can realize comprehensive monitoring and management of the iron zone production process. For example, the iron zone dynamic system can collect and analyze data such as production performance, operation performance, molten iron scale, molten iron quality, material coding and real-time inventory count, so as to realize lean management, dynamic management and centralized and consistent management of iron zone production. It can not only improve the level of centralized control, digitization and intelligence, but also provide strong support for the optimization and efficiency improvement of the ironmaking process.

[0064] S120. Calculate the historical molten iron flow rate of the blast furnace and the target molten iron flow rate of the blast furnace according to the historical operation data and the current operation data.

[0065] Specifically, the historical molten iron flow rate of the blast furnace is calculated according to the historical operation data, and the target molten iron flow rate of the blast furnace is calculated according to the current operation data; the purpose of calculating the molten iron flow rate first is that the size of the blast furnace drill bit will have a certain impact on the molten iron flow rate. If the blast furnace drill bit has an appropriate aperture size and a small degree of wear, it can provide a larger and unobstructed channel, which helps to reduce the resistance of the molten iron flow, thereby accelerating the molten iron flow rate. The fast flow rate helps to discharge the molten iron and slag more efficiently. If the molten iron flow rate is fast and stable, the slag iron in the furnace can be fully discharged within the specified iron-out time, and the slag iron residue in the furnace can be reduced, thereby improving the degree of clean slag iron. On the contrary, if the blast furnace drill bit aperture is too small and the degree of wear is serious, forming a narrow and unsmooth channel, it will increase the resistance of the molten iron flow, resulting in a slowdown in the molten iron flow rate. Too slow a flow rate may cause the iron-out time to be extended, and the slag iron cannot be completely discharged, resulting in more slag iron remaining in the furnace, affecting the normal operation of the blast furnace and the subsequent smelting effect. Therefore, the condition of the blast furnace drill bit affects the molten iron flow rate, which in turn affects the effect of the blast furnace in producing clean slag iron. Therefore, it is necessary to calculate the historical molten iron flow rate and obtain the corresponding drill bit size under the historical molten iron flow rate.

[0066] S130. Generate a first calibration table according to historical molten iron flow rate and historical operation data.

[0067] Specifically, in the iron zone dynamic system, by collecting and sorting the historical operation data and the historical molten iron flow rate, a first calibration table can be automatically generated. The first calibration table is a table containing the corresponding relationship between the historical molten iron flow rate, the historical operation data and the drill size specifications, which can characterize the relationship between the historical molten iron flow rate, the historical operation data and the drill size specifications.

[0068] S140, determining a target drill bit size of the blast furnace according to current operation data, target molten iron flow rate and a first calibration table.

[0069] Specifically, according to the target molten iron flow rate and the first calibration table, the drill bit size corresponding to the target molten iron flow rate is preliminarily determined, and the preliminarily determined drill bit size is corrected in combination with the current operating data to obtain the final target drill bit size of the blast furnace.

[0070] The technical solution provided by the embodiment of the present invention combines the factors that affect whether a blast furnace can produce clean slag and iron, obtains the historical operation data of the blast furnace, calculates the historical molten iron flow rate of the blast furnace according to the historical operation data, and obtains the first calibration table by collecting and sorting the historical operation data and the historical molten iron flow rate. The table can characterize the relationship between the historical molten iron flow rate, the historical operation data and the drill bit size specifications, calculates the target molten iron flow rate according to the current operation data, and preliminarily determines the drill bit size corresponding to the target molten iron flow rate according to the target molten iron flow rate and the first calibration table, and corrects the preliminarily determined drill bit size in combination with the current operation data to obtain the final target drill bit size of the blast furnace, which provides a scientific basis and construction standards for the size selection of the blast furnace drill bit, and does not need to rely on personal experience to select the size of the blast furnace drill bit, which solves the technical problem that the prior art selects the drill bit size based on experience, and due to inconsistent personal experience levels, there is a large difference in slag and iron output between shifts, resulting in unstable blast furnace operation. The technical solution provided by the embodiment of the present invention effectively improves the stability of blast furnace operation.

[0071] Figure 2 The flowchart of another method for determining a blast furnace drill bit provided by the embodiment of the present invention is a further refinement of the above embodiment based on the above embodiment. The historical operation data includes: the average daily output of the blast furnace in the past month, the daily iron-tapping interval of the blast furnace in the past month, and the daily iron-tapping furnace times of the blast furnace in the past month; the current operation data includes: the abundance or shortage of iron in the blast furnace, the iron-tapping interval of the current furnace, the iron-tapping time of the current furnace, and the theoretical value of the amount of molten iron generated per minute; see Figure 2 , the determination method includes:

[0072] S210. Obtain historical operation data and current operation data of the blast furnace.

[0073] This step is the same as the step in the above embodiment S110 and will not be described again here.

[0074] S220. Calculate the historical molten iron flow rate of the blast furnace based on the average daily output of the blast furnace in the previous month, the daily iron-tapping interval of the blast furnace in the previous month, and the daily iron-tapping times of the blast furnace in the previous month.

[0075] Specifically, the historical molten iron flow rate of the blast furnace is calculated using the following formula:

[0076] V0=M0 / (1440-t0×N0);

[0077] Where V0 is the historical molten iron flow rate, M0 is the average daily output of the blast furnace in the past month, t0 is the daily iron-tapping interval of the blast furnace in the past month, and N0 is the daily iron-tapping times of the blast furnace in the past month.

[0078] S230, calculating the target molten iron flow rate of the blast furnace according to the iron abundance, iron tapping interval, iron tapping time and theoretical value of molten iron production per minute.

[0079] Among them, the theoretical value of molten iron production per minute can be calculated based on the average daily output of the blast furnace in the past month, specifically using the following formula: V=M0 / 1440; wherein V is the theoretical value of molten iron production per minute, M0 is the average daily output of the blast furnace in the past month, and 1440 is the minute value converted from 24 hours a day.

[0080] Optionally, the target molten iron flow rate of the blast furnace is calculated based on the amount of iron in the furnace, the tapping interval, the tapping time, and the theoretical value of the amount of molten iron produced per minute, including:

[0081] Multiply the tapping time and the theoretical value of molten iron production per minute to obtain the first product; multiply the tapping interval time and the theoretical value of molten iron production per minute to obtain the second product; add the first product, the second product and the iron surplus or shortage to obtain the first sum; divide the first sum by the tapping time to obtain the quotient, which is determined as the target molten iron flow rate of the blast furnace.

[0082] For example, if the theoretical value of molten iron production per minute is 5.0t, the tapping time of the current furnace is 2 hours, the tapping interval of the current furnace is 10 minutes, the surplus or shortage of iron is 50t, and it is estimated that it will take 2 hours to tap clean slag iron in the next furnace, then the target molten iron flow rate = (5.0×120min+5.0×10min+50t) / 120min=5.83t / min.

[0083] S240: Generate a first calibration table according to historical molten iron flow rate and historical operation data.

[0084] Exemplarily, a first calibration table is generated based on historical molten iron flow rates and historical operation data, as shown in Table 1 below.

[0085] Table 1

[0086]

[0087] Among them, the iron output for historical operation data refers to the average daily output M0 of the previous month, and the iron output time refers to the value calculated by 1440-t0×N0.

[0088] S250, determining a target drill bit size of the blast furnace according to current operation data, target molten iron flow rate and a first calibration table.

[0089] The technical solution provided by the embodiment of the present invention calculates the historical molten iron flow rate of the blast furnace based on the historical operating data, and obtains the first calibration table by collecting and sorting the historical operating data and the historical molten iron flow rate, so that the drill bit size corresponding to the target molten iron flow rate can be determined by querying the table later, and the preliminarily determined drill bit size is corrected in combination with the current operating data to obtain the final target drill bit size of the blast furnace, thereby effectively improving the stability of the blast furnace operation.

[0090] Figure 3 The present invention provides a flowchart of another method for determining a blast furnace drill bit. The present invention further refines the above embodiments based on the above embodiments. The current operation data also includes: the wind pressure of the blast furnace at the current moment, the furnace temperature of the blast furnace at the current moment, and the iron mouth depth of the blast furnace; see Figure 3 , the determination method includes:

[0091] S310. Obtain historical operation data and current operation data of the blast furnace.

[0092] S320. Calculate the historical molten iron flow rate of the blast furnace and the target molten iron flow rate of the blast furnace according to the historical operation data and the current operation data.

[0093] S330: Generate a first calibration table according to historical molten iron flow rate and historical operation data.

[0094] S340. Determine a first target drill bit size for the blast furnace by querying a first calibration table according to the target molten iron flow rate.

[0095] The first target drill bit size refers to the drill bit size corresponding to the target molten iron flow rate when not corrected by the correction coefficient, and is determined by querying the first calibration table.

[0096] S350, determine the correction coefficient according to the wind pressure, furnace temperature and taphole depth.

[0097] The correction coefficients include a first correction coefficient K1, a second correction coefficient K2 and a third correction coefficient K3.

[0098] Specifically, due to the selection of blast furnace drill bits, in addition to considering the slag and iron in the furnace, it is also necessary to consider the influence of the wind pressure, furnace temperature trend and iron mouth depth on the drill bit size. The higher the wind pressure, the smaller the drill bit size, and the lower the wind pressure, the larger the drill bit size; the higher the furnace temperature, the larger the drill bit size, and the lower the furnace temperature, the smaller the drill bit size; the deeper the iron mouth depth, the larger the drill bit size, and the shallower the iron mouth depth, the smaller the drill bit size; therefore, according to the wind pressure, furnace temperature and iron mouth depth, the correction coefficients K1, K2 and K3 are set based on empirical data. In other words, the drill bit size is not only related to the abundance and shortage of iron and the interval time of iron tapping, but also to the wind pressure, furnace temperature and iron mouth depth, as shown in Table 2 below. Therefore, after determining the first target drill bit size of the blast furnace, it is necessary to correct the first target drill bit size according to the correction coefficient to obtain the final target drill bit size of the blast furnace.

[0099] Table 2

[0100]

[0101] S360: Determine a second target drill bit size according to the correction coefficient and the first target drill bit size.

[0102] Among them, the second target drill bit size refers to the drill bit size after correction by the correction coefficient. Specifically, after determining the first target drill bit size, the correction coefficient is first determined according to the real-time wind pressure, furnace temperature and iron mouth depth, and then the second target drill bit size is determined according to the product obtained by multiplying the first target drill bit size by the correction coefficient. At this time, the multiplication is the first target drill bit size multiplied by K1, K2, and K3 in sequence, rather than multiplied by only one of the correction coefficients.

[0103] In addition, in order to avoid too many drill bit varieties and further control the flow rate of molten iron during tapping, a combination drill bit selection mode is adopted. When tapping iron, you can use a combination drill to open the tap hole according to the tap hole depth recorded in the operating policy. For example, if the tap hole depth is 3.2m, you can first use The drill bit drilled to 1m, then changed to The drill bit is then drilled 2.2 m to open the iron mouth, so as to control the iron flow rate and discharge clean slag iron.

[0104] Optionally, the correction factor is determined based on the wind pressure, furnace temperature and taphole depth, including:

[0105] When the wind pressure is greater than or equal to a preset standard wind pressure value, the first correction coefficient is less than or equal to a first preset threshold value.

[0106] When the wind pressure is less than a preset standard wind pressure value, the first correction coefficient is greater than a first preset threshold value.

[0107] When the furnace temperature is greater than or equal to a preset standard furnace temperature value, the second correction coefficient is greater than the first preset threshold value.

[0108] When the furnace temperature is lower than the preset standard furnace temperature value, the second correction coefficient is lower than or equal to the first preset threshold value.

[0109] When the iron mouth depth is greater than or equal to a preset standard iron mouth depth value, the third correction coefficient is greater than the first preset threshold value.

[0110] When the iron mouth depth is less than a preset standard iron mouth depth value, the third correction coefficient is less than or equal to a first preset threshold value.

[0111] Among them, the preset standard wind pressure value, the preset standard furnace temperature value and the preset standard iron mouth depth value can all be preset based on business guidelines. The first preset threshold value can be preset according to engineering requirements, and the present invention does not limit this. For example, when the wind pressure is greater than or equal to the preset standard wind pressure value, it means that the wind pressure is high. If the wind pressure is high, the drill bit size should be reduced, so the value of the first correction coefficient K1 should be ≤1. When the wind pressure is less than the preset standard wind pressure value, it means that the wind pressure is low. If the wind pressure is low, the drill bit size should be increased, so the value of the first correction coefficient K1 should be >1; when the furnace temperature is greater than or equal to the preset standard furnace temperature value, it means that the furnace temperature trend is constantly increasing. The furnace temperature trend is in an increasing state, then the drill bit size needs to be increased, so the value of the second correction coefficient K2 should be >1. When the furnace temperature is less than the preset standard furnace temperature value, it means that the furnace temperature trend is increasing. The furnace temperature trend is in an increasing state, then the drill bit size needs to be increased, so the value of the second correction coefficient K2 should be >1. When the furnace temperature reaches the standard value, it means that the furnace temperature trend is constantly decreasing. If the furnace temperature trend is in a decreasing state, the drill bit size needs to be reduced, so the value of the second correction coefficient K2 should be ≤1; when the iron mouth depth is greater than or equal to the preset standard iron mouth depth value, it means that the iron mouth depth is deeper. If the iron mouth depth is deep, the drill bit size needs to be increased, so the value of the third correction coefficient K3 should be >1. When the iron mouth depth is less than the preset standard iron mouth depth value, it means that the iron mouth depth is insufficient. If the iron mouth depth is insufficient, the drill bit size needs to be reduced, so the value of the third correction coefficient K3 should be ≤1.

[0112] The technical solution provided by the embodiment of the present invention not only takes into account the slag and iron storage situation inside the blast furnace, but also takes into account the influence of the wind pressure, furnace temperature trend and iron mouth depth on the drill bit when selecting the drill bit size. The wind pressure, furnace temperature and iron mouth depth determine the correction coefficient that affects the selection of the drill bit size, so as to determine the best solution for timely discharge of clean slag and iron in different situations.

[0113] Figure 4 A structural diagram of a blast furnace drill bit determination device provided by an embodiment of the present invention, see Figure 4 The determination device includes an acquisition module 410, a calculation module 420, a generation module 430 and a determination module 440.

[0114] The acquisition module 410 is used to acquire the historical operation data and current operation data of the blast furnace.

[0115] The calculation module 420 is used to calculate the historical molten iron flow rate of the blast furnace and the target molten iron flow rate of the blast furnace according to the historical operation data and the current operation data.

[0116] The generation module 430 is used to generate a first calibration table according to historical molten iron flow rate and historical operation data.

[0117] The determination module 440 is used to determine the target drill bit size of the blast furnace according to the current operation data, the target molten iron flow rate, the first calibration table and the preset correction coefficient.

[0118] Optionally, the historical operation data includes: the average daily output of the blast furnace in the previous month, the daily iron-tapping interval of the blast furnace in the previous month, and the daily iron-tapping furnace times of the blast furnace in the previous month; the current operation data includes: the iron surplus or shortage of the blast furnace, the iron-tapping interval of the current furnace, the iron-tapping time of the current furnace, and the theoretical value of the amount of molten iron generated per minute;

[0119] The calculation module 420 includes a first calculation submodule and a second calculation submodule.

[0120] The first calculation submodule is used to calculate the historical molten iron flow rate of the blast furnace according to the average daily output of the blast furnace in the past month, the daily iron-tapping interval of the blast furnace in the past month, and the daily iron-tapping furnace times of the blast furnace in the past month.

[0121] The second calculation submodule is used to calculate the target molten iron flow rate of the blast furnace according to the abundance or shortage of iron, the tapping interval time, the tapping time and the theoretical value of the molten iron production per minute.

[0122] A blast furnace drill bit determination device provided in an embodiment of the present invention can execute a blast furnace drill bit determination method provided in any embodiment of the present invention, and has corresponding functional modules and beneficial effects of the execution method.

[0123] Figure 5 A schematic diagram of the structure of an electronic device for a method for determining a blast furnace drill bit provided for the implementation of the present invention. The electronic device is intended to represent various forms of digital computers, such as laptop computers, desktop computers, workbenches, personal digital assistants, servers, blade servers, mainframe computers, and other suitable computers. The electronic device may also represent various forms of mobile devices, such as personal digital processing, cellular phones, smart phones, wearable devices (such as helmets, glasses, watches, etc.) and other similar computing devices. The components shown herein, their connections and relationships, and their functions are merely examples and are not intended to limit the implementation of the present invention described and / or claimed herein.

[0124] like Figure 5As shown, the electronic device 10 includes at least one processor 11, and a memory connected to the at least one processor 11, such as a read-only memory (ROM) 12, a random access memory (RAM) 13, etc., wherein the memory stores a computer program that can be executed by at least one processor, and the processor 11 can perform various appropriate actions and processes according to the computer program stored in the read-only memory (ROM) 12 or the computer program loaded from the storage unit 18 to the random access memory (RAM) 13. In the RAM 13, various programs and data required for the operation of the electronic device 10 can also be stored. The processor 11, the ROM 12, and the RAM 13 are connected to each other through a bus 14. An input / output (I / O) interface 15 is also connected to the bus 14.

[0125] A number of components in the electronic device 10 are connected to the I / O interface 15, including: an input unit 16, such as a keyboard, a mouse, etc.; an output unit 17, such as various types of displays, speakers, etc.; a storage unit 18, such as a disk, an optical disk, etc.; and a communication unit 19, such as a network card, a modem, a wireless communication transceiver, etc. The communication unit 19 allows the electronic device 10 to exchange information / data with other devices through a computer network such as the Internet and / or various telecommunication networks.

[0126] The processor 11 may be a variety of general and / or special processing components with processing and computing capabilities. Some examples of the processor 11 include, but are not limited to, a central processing unit (CPU), a graphics processing unit (GPU), various special artificial intelligence (AI) computing chips, various processors running machine learning model algorithms, a digital signal processor (DSP), and any appropriate processor, controller, microcontroller, etc. The processor 11 executes the various methods and processes described above, such as a method for determining a blast furnace drill bit.

[0127] In some embodiments, a method for determining a blast furnace drill bit may be implemented as a computer program, which is tangibly contained in a computer-readable storage medium, such as a storage unit 18. In some embodiments, part or all of the computer program may be loaded and / or installed on the electronic device 10 via the ROM 12 and / or the communication unit 19. When the computer program is loaded into the RAM 13 and executed by the processor 11, one or more steps of the method for determining a blast furnace drill bit described above may be performed. Alternatively, in other embodiments, the processor 11 may be configured to perform a method for determining a blast furnace drill bit in any other appropriate manner (e.g., by means of firmware).

[0128] Various implementations of the systems and techniques described above herein can be implemented in digital electronic circuit systems, integrated circuit systems, field programmable gate arrays (FPGAs), application specific integrated circuits (ASICs), application specific standard products (ASSPs), systems on chips (SOCs), load programmable logic devices (CPLDs), computer hardware, firmware, software, and / or combinations thereof. These various implementations can include: being implemented in one or more computer programs that can be executed and / or interpreted on a programmable system including at least one programmable processor, which can be a special purpose or general purpose programmable processor that can receive data and instructions from a storage system, at least one input device, and at least one output device, and transmit data and instructions to the storage system, the at least one input device, and the at least one output device.

[0129] Computer programs for implementing the methods of the present invention may be written in any combination of one or more programming languages. These computer programs may be provided to a processor of a general-purpose computer, a special-purpose computer, or other programmable data processing device, so that when the computer program is executed by the processor, the functions / operations specified in the flow chart and / or block diagram are implemented. The computer program may be executed entirely on the machine, partially on the machine, partially on the machine and partially on a remote machine as a stand-alone software package, or entirely on a remote machine or server.

[0130] In the context of the present invention, a computer-readable storage medium may be a tangible medium that may contain or store a computer program for use by or in combination with an instruction execution system, device or equipment. A computer-readable storage medium may include, but is not limited to, electronic, magnetic, optical, electromagnetic, infrared, or semiconductor systems, devices or equipment, or any suitable combination of the foregoing. Alternatively, a computer-readable storage medium may be a machine-readable signal medium. A more specific example of a machine-readable storage medium may include an electrical connection based on one or more lines, a portable computer disk, a hard disk, a random access memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), an optical fiber, a portable compact disk read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination of the foregoing.

[0131] To provide interaction with a user, the systems and techniques described herein may be implemented on an electronic device having: a display device (e.g., a CRT (cathode ray tube) or LCD (liquid crystal display) monitor) for displaying information to the user; and a keyboard and a pointing device (e.g., a mouse or trackball) through which the user can provide input to the electronic device. Other types of devices may also be used to provide interaction with the user; for example, the feedback provided to the user may be any form of sensory feedback (e.g., visual feedback, auditory feedback, or tactile feedback); and input from the user may be received in any form (including acoustic input, voice input, or tactile input).

[0132] The systems and techniques described herein may be implemented in a computing system that includes backend components (e.g., as a data server), or a computing system that includes middleware components (e.g., an application server), or a computing system that includes frontend components (e.g., a user computer with a graphical user interface or a web browser through which a user can interact with implementations of the systems and techniques described herein), or a computing system that includes any combination of such backend components, middleware components, or frontend components. The components of the system may be interconnected by any form or medium of digital data communication (e.g., a communication network). Examples of communication networks include: a local area network (LAN), a wide area network (WAN), a blockchain network, and the Internet.

[0133] A computing system may include a client and a server. The client and the server are generally remote from each other and usually interact through a communication network. The client and server relationship is generated by computer programs running on the corresponding computers and having a client-server relationship with each other. The server may be a cloud server, also known as a cloud computing server or cloud host, which is a host product in the cloud computing service system to solve the defects of difficult management and weak business scalability in traditional physical hosts and VPS services.

[0134] It should be understood that the various forms of processes shown above can be used to reorder, add or delete steps. For example, the steps described in the present invention can be executed in parallel, sequentially or in different orders, as long as the desired results of the technical solution of the present invention can be achieved, and this document does not limit this.

[0135] The above specific implementations do not constitute a limitation on the protection scope of the present invention. It should be understood by those skilled in the art that various modifications, combinations, sub-combinations and substitutions can be made according to design requirements and other factors. Any modification, equivalent substitution and improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims

1. A method for determining a blast furnace drill bit, It is characterized in that include: Obtain the historical and current operation data of the blast furnace; Calculating a historical molten iron flow rate of a blast furnace and a target molten iron flow rate of the blast furnace respectively according to the historical operation data and the current operation data; generating a first calibration table according to the historical molten iron flow rate and the historical operation data; A target drill bit size for the blast furnace is determined based on the current operating data, the target molten iron flow rate, and the first calibration table.

2. The determination method according to claim 1, It is characterized in that The historical operation data include: the average daily output of the blast furnace in the previous month, the daily tapping interval of the blast furnace in the previous month, and the daily tapping times of the blast furnace in the previous month; the current operation data include: the abundance or shortage of iron in the blast furnace, the tapping interval of the current time, the tapping time of the current time, and the theoretical value of molten iron production per minute; The calculating, according to the historical operation data and the current operation data, respectively, the historical molten iron flow rate of the blast furnace and the target molten iron flow rate of the blast furnace comprises: Calculate the historical molten iron flow rate of the blast furnace according to the average daily output of the blast furnace in the previous month, the daily iron-tapping interval of the blast furnace in the previous month, and the daily iron-tapping heats of the blast furnace in the previous month; The target molten iron flow rate of the blast furnace is calculated according to the iron surplus or shortage, the tapping interval, the tapping time and the theoretical value of molten iron production per minute.

3. The determination method according to claim 2, It is characterized in that Calculating the historical molten iron flow rate of the blast furnace according to the average daily output of the blast furnace in the previous month, the daily iron-tapping interval of the blast furnace in the previous month, and the daily iron-tapping heats of the blast furnace in the previous month comprises: The historical molten iron flow rate of the blast furnace is calculated using the following formula: V 0 =M 0 / (1440-t 0 ×N 0 ); Where V 0 is the historical molten iron flow rate, M 0 is the average daily output of the blast furnace in the previous month, t 0 is the daily tapping interval of the blast furnace in the previous month, N 0 It is the daily iron tapping times of the blast furnace in the last month.

4. The determination method according to claim 2, It is characterized in that The calculating the target molten iron flow rate of the blast furnace according to the iron abundance or shortage, the tapping interval, the tapping time and the theoretical value of the molten iron production per minute comprises: Multiplying the tapping time and the theoretical value of molten iron production per minute to obtain a first product; Multiplying the tapping interval time and the theoretical value of molten iron production per minute to obtain a second product; Adding the first product, the second product and the iron abundance or deficit to obtain a first sum value; The quotient obtained by dividing the first sum value by the iron tapping time is determined as the target molten iron flow rate of the blast furnace.

5. The determination method according to claim 1, It is characterized in that The current operation data also includes: the wind pressure of the blast furnace at the current moment, the furnace temperature of the blast furnace at the current moment, and the iron mouth depth of the blast furnace; Determining the target drill bit size of the blast furnace according to the current operation data, the target molten iron flow rate and the first calibration table includes: According to the target molten iron flow rate, determining a first target drill bit size for the blast furnace by querying the first calibration table; Determining a correction coefficient according to the wind pressure, the furnace temperature and the taphole depth; A second target drill size is determined according to the correction coefficient and the first target drill size.

6. The determination method according to claim 5, It is characterized in that The correction coefficients include a first correction coefficient, a second correction coefficient and a third correction coefficient; Determining the correction coefficient according to the wind pressure, the furnace temperature and the taphole depth includes: When the wind pressure is greater than or equal to a preset standard wind pressure value, the first correction coefficient is less than or equal to a first preset threshold value; When the wind pressure is less than a preset standard wind pressure value, the first correction coefficient is greater than a first preset threshold value; When the furnace temperature is greater than or equal to a preset standard furnace temperature value, the second correction coefficient is greater than a first preset threshold value; When the furnace temperature is lower than a preset standard furnace temperature value, the second correction coefficient is lower than or equal to a first preset threshold value; When the iron mouth depth is greater than or equal to a preset standard iron mouth depth value, the third correction coefficient is greater than a first preset threshold value; When the iron mouth depth is less than a preset standard iron mouth depth value, the third correction coefficient is less than or equal to a first preset threshold value.

7. A device for determining a blast furnace drill bit, It is characterized in that include: An acquisition module, the acquisition module is used to acquire historical operation data and current operation data of the blast furnace; A calculation module, the calculation module is used to calculate the historical molten iron flow rate of the blast furnace and the target molten iron flow rate of the blast furnace according to the historical operation data and the current operation data; A generating module, the generating module is used to generate a first calibration table according to the historical molten iron flow rate and the historical operation data; A determination module is used to determine a target drill bit size for a blast furnace based on the current operating data, the target molten iron flow rate, the first calibration table, and a preset correction coefficient.

8. The determination device according to claim 7, It is characterized in that The historical operation data include: the average daily output of the blast furnace in the previous month, the daily tapping interval of the blast furnace in the previous month, and the daily tapping times of the blast furnace in the previous month; the current operation data include: the abundance or shortage of iron in the blast furnace, the tapping interval of the current time, the tapping time of the current time, and the theoretical value of molten iron production per minute; The calculation module includes a first calculation submodule and a second calculation submodule; The first calculation submodule is used to calculate the historical molten iron flow rate of the blast furnace according to the average daily output of the blast furnace in the last month, the daily iron-tapping interval of the blast furnace in the last month, and the daily iron-tapping heats of the blast furnace in the last month; The second calculation submodule is used to calculate the target molten iron flow rate of the blast furnace according to the iron surplus or shortage, the tapping interval time, the tapping time and the theoretical value of the molten iron production per minute.

9. An electronic device, It is characterized in that The electronic device comprises: at least one processor; and a memory communicatively connected to the at least one processor; wherein, The memory stores a computer program executable by the at least one processor, and the computer program is executed by the at least one processor so that the at least one processor can perform the method for determining a blast furnace drill bit according to any one of claims 1 to 6.

10. A computer-readable storage medium, It is characterized in that The computer-readable storage medium stores computer instructions, and the computer instructions are used to enable a processor to implement the method for determining a blast furnace drill bit according to any one of claims 1 to 6 when executed.