Closed-loop test method and device for power grid safety and stability control system

Through the closed-loop testing method, the fault status of the power grid is simulated and iteratively calculated, which solves the problem that the existing technology cannot simulate the trip characteristics of the actual power grid, and improves the testing accuracy of the grid safety and stability control system.

CN118940492APending Publication Date: 2024-11-12ELECTRIC POWER RESEARCH INSTITUTE OF STATE GRID NINGXIA ELECTRIC POWER COMPANY +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410981437.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-22
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

The testing method of the existing grid safety and stability control system cannot simulate the actual grid fault trip characteristics, and cannot truly examine the action characteristics and grid response characteristics of the device strategy after the fault.

Method used

The closed-loop testing method is adopted to obtain the strategy simulation data through simulation simulation, iterative calculation and verification until multiple rounds of closed-loop testing of action signals are completed, the actual grid fault status is simulated, and the action characteristics and response characteristics of the device strategy are verified.

Benefits of technology

It realizes the real investigation of the action characteristics and grid response characteristics of the device strategy after the failure, and improves the accuracy and effectiveness of the test.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118940492A_ABST
    Figure CN118940492A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of power system safety and stability control, in particular to a closed-loop test method and device for a power grid safety and stability control system. When the preset strategy comprises multiple rounds of action signals, obtaining strategy simulation data corresponding to the preset strategy obtained by carrying out analogue simulation on a preset power grid system; issuing the strategy simulation data to a power grid safety and stability control system for strategy simulation verification to obtain a strategy simulation result corresponding to the first round of action signal; according to a strategy simulation result corresponding to the first-round action signal, simulation software is controlled to carry out iterative calculation, and iterative simulation data is generated; and strategy simulation verification is carried out again according to the iteration simulation data, and the iteration calculation and strategy simulation verification process is repeated until closed-loop testing of multiple rounds of action signals in the preset strategy is completed. Therefore, the method can truly inspect whether the action characteristics of the stable device strategy after the fault and the response characteristics of the power grid after the action meet the design requirements or not.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of power system safety and stability control, and in particular to a closed-loop testing method and device for a power grid safety and stability control system. Background Art

[0002] The regional power grid safety and stability control system (hereinafter referred to as the stability control system) is to install safety and stability control devices in two or more power plants and stations, connect them by communication means, and execute and send stability control commands. The stability control system can not only prevent large-scale power outages and power grid collapse, but also serve as the second and third lines of defense to ensure the safe and stable operation of the power system. The control technology of the stability control system is a key technology to improve the level of safe and stable operation of the power grid, and it is also an important means to ensure the safe and economic operation of the power grid. Through testing and experimentation, problems with the stability control system equipment and secondary circuits can be discovered in a timely manner, and the correctness of the stability control system channels and control strategies can be studied, providing a solid safety foundation for the "three lines of defense" of the power grid.

[0003] At present, the mainstream test methods of stability control systems are divided into factory testing and on-site debugging. Since the traditional method is an open-loop test, the test environment is quite different from the actual grid conditions. For example, when testing the tripping logic, it can only simulate the characteristics of typical fault tripping and no-fault tripping, and cannot simulate the actual grid fault tripping characteristics. Therefore, it is impossible to truly examine the action characteristics of the stability device strategy after a fault occurs and whether the response characteristics of the grid after the action meet the design requirements. Summary of the invention

[0004] In view of this, the present invention provides a closed-loop testing method and device for a power grid safety and stability control system to solve the problem that the testing method of the temperature control system in the prior art cannot simulate the actual power grid fault tripping characteristics.

[0005] In a first aspect, the present invention provides a closed-loop testing method for a power grid safety and stability control system, the method comprising: obtaining strategy simulation data corresponding to a preset strategy by simulating a preset power grid system, the preset strategy including multiple rounds of action signals; sending the strategy simulation data to the power grid safety and stability control system for strategy simulation verification, and obtaining strategy simulation results corresponding to a first round of action signals; controlling simulation software to perform iterative calculations based on the strategy simulation results corresponding to the first round of action signals to generate iterative simulation data; performing strategy simulation verification again based on the iterative simulation data, and repeating the process of iterative calculation and strategy simulation verification until the closed-loop test of multiple rounds of action signals in the preset strategy is completed.

[0006] The closed-loop test method of the power grid safety and stability control system provided by the embodiment of the present invention, when the preset strategy includes multiple rounds of action signals, obtains the strategy simulation data corresponding to the preset strategy by simulating the preset power grid system; sends the strategy simulation data to the power grid safety and stability control system for strategy simulation verification, and obtains the strategy simulation results corresponding to the first round of action signals; controls the simulation software to perform iterative calculations according to the strategy simulation results corresponding to the first round of action signals, and generates iterative simulation data; performs strategy simulation verification again according to the iterative simulation data, and repeats the process of iterative calculation and strategy simulation verification until the closed-loop test of multiple rounds of action signals in the preset strategy is completed. Thus, the method realizes that when the preset strategy includes multiple rounds of action signals, the strategy simulation results are fed back to the simulation software, and iterative calculations are performed to form a closed-loop test, so that it can truly examine whether the action characteristics of the stability device strategy after a fault occurs and the response characteristics of the power grid after the action meet the design requirements.

[0007] In an optional embodiment, a preset power grid system is simulated to obtain strategy simulation data corresponding to a preset strategy, including: using simulation software to build a power grid model and perform simulation to obtain simulation result data; based on the power grid model, simulating the fault state of the preset power grid system according to the preset strategy, and using the simulation data of the fault state of the preset power grid system as strategy simulation data.

[0008] In this embodiment, by building a power grid model and simulating its fault state, a data basis is provided for testing the power grid safety and stability control system.

[0009] In an optional embodiment, the strategy simulation results include action control data of a fully stable control system of a power grid; the simulation software is controlled to perform iterative calculations based on the strategy simulation results corresponding to the first round of action signals to generate iterative simulation data, including: the simulation software is controlled to update the power grid model according to the action control data to obtain an updated power grid model; based on the updated power grid model, the fault state of a preset power grid system is simulated according to a preset strategy to generate iterative simulation data.

[0010] In this embodiment, by updating the power grid model, a true simulation of an actual power grid fault is achieved, thereby improving the accuracy of subsequent tests.

[0011] In an optional implementation, strategy simulation verification is performed again based on the iterative simulation data, and the process of iterative calculation and strategy simulation verification is repeated until the closed-loop test of multiple rounds of action signals in the preset strategy is completed, including: strategy simulation verification is performed again based on the iterative simulation data, and the process of iterative calculation and strategy simulation verification is repeated until the strategy simulation results corresponding to the last round of action signals are obtained; according to the strategy simulation results corresponding to the last round of action signals, the simulation software is controlled to perform iterative calculations to generate iterative simulation data; the strategy simulation data is sent down to the power grid safety and stability control system for strategy simulation verification, and the closed-loop test results of the preset strategy are obtained according to the verification results.

[0012] In this embodiment, the iterative simulation data generated after iterative calculation of the last round of strategy simulation results is further sent to the power grid security and stability control system for strategy simulation verification, which provides a basis for determining whether the test results meet the requirements.

[0013] In the second aspect, the present invention provides a closed-loop test system for a power grid safety and stability control system, the system comprising a detection platform and multiple power grid safety and stability control systems arranged in multiple plants and stations, the detection platform comprising a simulation software system and a detection platform management machine; the simulation software system is used to simulate a preset power grid system to obtain strategy simulation data corresponding to a preset strategy, the preset strategy comprising multiple rounds of action signals; the detection platform management machine is used to send the strategy simulation data to the power grid safety and stability control system for strategy simulation verification, and obtain the strategy simulation results corresponding to the first round of action signals; according to the strategy simulation results corresponding to the first round of action signals, the simulation software in the simulation software system is controlled to perform iterative calculations to generate iterative simulation data; according to the iterative simulation data, the strategy simulation verification is performed again, and the process of iterative calculation and strategy simulation verification is repeated until the closed-loop test of multiple rounds of action signals in the preset strategy is completed.

[0014] In an optional embodiment, the plant station also includes: a verification node machine, a signal conversion device and a power amplifier; the verification node machine is used to receive the strategy simulation data output by the detection platform management machine, and send the strategy simulation data to the signal conversion device; the signal conversion device is used to convert the strategy simulation data and output it to the power amplifier; the power amplifier is used to amplify the converted data and input it into the power grid safety and stability control system for strategy simulation verification; the signal conversion device is also used to receive the strategy simulation results after the strategy simulation verification by the power grid safety and stability control system and send them to the detection platform management machine through the verification node machine.

[0015] In an optional implementation, a virtual private dial-up network is used for communication between the detection platform management machine and the verification node machine.

[0016] In this embodiment, by using a virtual private dial-up network for communication, the test efficiency of the closed-loop test system of the power grid security and stability control system is improved.

[0017] In an optional implementation, the system uses Beidou satellite synchronization technology for synchronization and time synchronization.

[0018] In this embodiment, synchronization is used to ensure synchronization of detection of a spatially large-span distributed system.

[0019] In a third aspect, the present invention provides a computer device comprising: a memory and a processor, the memory and the processor being communicatively connected to each other, the memory storing computer instructions, and the processor executing the closed-loop test method of the power grid security and stability control system of the first aspect or any corresponding embodiment thereof by executing the computer instructions.

[0020] In a fourth aspect, the present invention provides a computer-readable storage medium having computer instructions stored thereon, the computer instructions being used to enable a computer to execute the closed-loop testing method for a power grid security and stability control system according to the first aspect or any corresponding embodiment thereof.

[0021] In a fifth aspect, the present invention provides a computer program product, comprising computer instructions, wherein the computer instructions are used to enable a computer to execute the closed-loop testing method for a power grid security and stability control system according to the first aspect or any corresponding embodiment thereof. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] In order to more clearly illustrate the specific implementation methods of the present invention or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0023] Figure 1 is a flow chart of a closed-loop test method for a power grid security and stability control system according to an embodiment of the present invention;

[0024] Figure 2 is a structural block diagram of a closed-loop test system for a power grid security and stability control system according to an embodiment of the present invention;

[0025] Figure 3 It is a schematic diagram of the hardware structure of a computer device according to an embodiment of the present invention. DETAILED DESCRIPTION

[0026] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative work are within the scope of protection of the present invention.

[0027] According to an embodiment of the present invention, an embodiment of a closed-loop test method for a power grid security and stability control system is provided. It should be noted that the steps shown in the flowchart of the accompanying drawings can be executed in a computer system such as a set of computer executable instructions, and although a logical order is shown in the flowchart, in some cases, the steps shown or described can be executed in an order different from that shown here.

[0028] In this embodiment, a closed-loop test method for a power grid security and stability control system is provided, which can be used for electronic devices such as computers, mobile phones, tablet computers, etc. Figure 1 is a flow chart of a closed-loop test method of a power grid security and stability control system according to an embodiment of the present invention. Figure 1 As shown, the process includes the following steps:

[0029] Step S101, obtains the strategy simulation data corresponding to the preset strategy obtained by simulating the preset power grid system, and the preset strategy includes multiple rounds of action signals. The preset power grid system specifically includes an electric power system installed with a power grid safety and stability control system and controlled by the power grid safety and stability control system, and the electric power system includes specific power electronic devices, electric power equipment and the connection relationship between them. The power grid safety and stability control system can execute the preset control strategy according to the operating state of the power grid system, such as adjusting the output of the generator, cutting off non-critical loads and starting the backup power supply, etc. At the same time, it can also execute emergency control strategies when a serious fault occurs in the power grid, such as cutting the machine, and load, decoupling operations, etc. In order to ensure that the power grid safety and stability control system executes the above control strategy according to the actual situation during the operation of the power grid, it is necessary to test the power grid safety and stability control system first, that is, to test whether it can execute the relevant strategy in time when the relevant situation occurs. Therefore, during the test, it is necessary to first obtain the strategy simulation data, and the strategy simulation data includes the relevant state data of the power grid when executing different strategies, including electrical quantities such as current and voltage data. It can be obtained specifically by simulating the power grid.

[0030] Among them, the prediction strategy includes multiple rounds of action signals, which means that the power grid safety and stability control system will generate multiple rounds of control signals when executing a certain control strategy. For example, the first round of control signals is to control two switches to be disconnected, the second round of control signals is to control one switch to be closed, and so on.

[0031] In an optional implementation, the above step S101 includes:

[0032] Step S1011, using simulation software to build a power grid model and perform simulation to obtain simulation result data.

[0033] Step S1012: Based on the power grid model, a fault state of a preset power grid system is simulated according to a preset strategy, and simulation data of the fault state of the preset power grid system is used as strategy simulation data.

[0034] Specifically, the simulation software can be an ADPSS (Advanced Digital Power System Simulator, a fully digital simulation device for power systems), BPA (Bonneville Power Administration, Bonneville Power Management), RTDS (real time digital simulation system, real-time digital simulation system) and other full-network electromechanical electromagnetic simulation systems to achieve full-network electromechanical electromagnetic simulation. Through these simulation software, the relevant power grid system can be simulated, that is, a power grid model similar to the actual power grid is constructed, and the power grid model includes the topological structure, equipment parameters and operating conditions of the power grid. At the same time, in order to realize the test of the power grid safety and stability control system, it is necessary to simulate the corresponding power grid fault state when the power grid model executes the relevant strategy, and generate corresponding simulation data, that is, strategy simulation data. Therefore, the simulation software can be used as a data source in the closed-loop test method to provide strategy simulation data, etc. In addition, before simulating the power grid fault state, the normal operating state of the power grid can be simulated to obtain simulation result data, which includes relevant parameter data such as current and voltage when the power grid model is running, so that the constructed power grid model can be guaranteed to operate normally through the simulation result data.

[0035] Step S102, the strategy simulation data is sent to the power grid security and stability control system for strategy simulation verification, and the strategy simulation results corresponding to the first round of action signals are obtained. Specifically, the closed-loop test method can be implemented based on a closed-loop test platform, which includes a detection platform management machine, and the detection platform management machine receives the strategy simulation data obtained by simulation software simulation, and parses the strategy simulation data. Among them, since the data types obtained by simulation with different simulation software may be different, the detection platform management machine (with compatibility for different data) is used to parse and process the data to obtain the required test data and test commands, etc. At the same time, the detection platform management machine also has a human-machine interface, and through the interaction of the human-machine interface, the control of the specific test process by the staff can be realized.

[0036] After the detection platform management machine analyzes the data, it sends the test data and test commands to the power grid safety and stability control system. After receiving the test data, the power grid safety and stability control system will execute the relevant strategy, that is, to achieve synchronous triggering of the corresponding fault state and generate corresponding action control data. The action control data can be a switch control signal, such as controlling a certain switch to disconnect, etc. Among them, the generated action control data is packaged and uploaded to the detection platform management machine for processing and analysis after generating strategy simulation results. It should be noted that since this embodiment is a test of a preset strategy containing multiple rounds of action signals, what is obtained here is the strategy simulation result corresponding to the first round of action signals.

[0037] Step S103, according to the strategy simulation result corresponding to the first round of action signal, the simulation software is controlled to perform iterative calculation to generate iterative simulation data. Specifically, after receiving the strategy simulation result, the detection platform management machine needs to parse it first to determine which device or device action needs to be controlled, that is, to determine the specific action control data, and then send the action control data to the simulation software, which further adjusts the power grid model based on the action control data to generate iterative simulation data.

[0038] In an optional implementation manner, the above step S103 includes:

[0039] Step S1031, controlling the simulation software to simulate the preset power grid system according to the action data to obtain an updated power grid model.

[0040] Step S1032, based on the updated power grid model, simulating the fault state of the preset power grid system according to the preset strategy to generate iterative simulation data.

[0041] Specifically, after receiving the strategy simulation results and parsing the action control data, the detection platform management machine sends the action control data to the simulation software. After receiving the action control data, the simulation software performs corresponding actions according to the action control data in the power grid model it constructs. For example, if the action control data is to control a certain switch to disconnect, the simulation software also controls the corresponding switch in its power grid model to disconnect and obtain an updated power grid model. Then, the simulation of the corresponding fault state continues in the updated power grid model to generate iterative simulation data. The iterative simulation data is similar to the strategy simulation data type and also contains relevant electrical quantity data, such as voltage and current.

[0042] Step S104, perform strategy simulation verification again according to the iterative simulation data, repeat the process of iterative calculation and strategy simulation verification, until the closed-loop test of multiple rounds of action signals in the preset strategy is completed. Specifically, after the iterative simulation data is generated by simulation, refer to the process of step S102, the detection platform management machine controls the power grid security and stability control system again to perform strategy simulation verification, and receives the strategy simulation results again. Among them, if a preset strategy includes three rounds of action signals, the strategy simulation results received again include the corresponding second round of action control signals generated by the power grid security and stability control system. At this time, the simulation software adjusts the power grid model again according to the second round of action signals to obtain an updated power grid model, and simulates and generates iterative simulation data again based on the updated power grid model, and performs strategy simulation verification again, and receives the strategy simulation results corresponding to the third round of action control signals generated by the power grid security and stability control system. That is, the test of the three rounds of action signals corresponding to the preset strategy is completed.

[0043] In an optional implementation, the above step S104 includes:

[0044] Step S1041, performing strategy simulation verification again according to the iterative simulation data, repeating the process of iterative calculation and strategy simulation verification until the strategy simulation result corresponding to the last round of action signal is obtained;

[0045] Step S1042, controlling the simulation software to perform iterative calculations according to the strategy simulation results corresponding to the last round of action signals to generate iterative simulation data;

[0046] Step S1043, sending the strategy simulation data to the power grid security and stability control system for strategy simulation verification, and obtaining a closed-loop test result of the preset strategy according to the verification result.

[0047] Specifically, by repeating the process of iterative calculation and simulation verification, the strategy simulation result corresponding to the last round of action signals is obtained, that is, the last round of action control data of the power grid safety and stability control system, and the action control data is sent to the simulation software. After receiving the action control data, the simulation software performs corresponding actions according to the action control data in the power grid model it constructs. For example, if the action control data is to control a certain switch to be disconnected, the simulation software also controls the corresponding switch in its power grid model to be disconnected, and obtains an updated power grid model. Then, the simulation of the corresponding fault state continues in the updated power grid model to generate iterative simulation data. The iterative simulation data is similar to the strategy simulation data type, and also contains relevant electrical quantity data, such as voltage and current. At the same time, the iterative simulation data is sent to the power grid safety and stability control system. If the power grid safety and stability control system has no other actions, it means that the electrical quantity data in the iterative simulation data obtained this time meets the power grid operation requirements, that is, the corresponding fault state can be eliminated by executing the preset strategy, and the preset strategy does not need to be adjusted again. If the power grid safety and stability control system executes a new action after receiving the iterative simulation data, it means that the electrical quantity data in the iterative simulation data obtained this time does not meet the power grid operation requirements, that is, the corresponding fault state cannot be eliminated by executing the preset strategy, and the preset strategy needs to be adjusted.

[0048] The closed-loop test method of the power grid safety and stability control system provided by the embodiment of the present invention, when the preset strategy includes multiple rounds of action signals, obtains the strategy simulation data corresponding to the preset strategy by simulating the preset power grid system; sends the strategy simulation data to the power grid safety and stability control system for strategy simulation verification, and obtains the strategy simulation results corresponding to the first round of action signals; controls the simulation software to perform iterative calculations according to the strategy simulation results corresponding to the first round of action signals, and generates iterative simulation data; performs strategy simulation verification again according to the iterative simulation data, and repeats the process of iterative calculation and strategy simulation verification until the closed-loop test of multiple rounds of action signals in the preset strategy is completed. Thus, the method realizes that when the preset strategy includes multiple rounds of action signals, the strategy simulation results are fed back to the simulation software, and iterative calculations are performed to form a closed-loop test, so that it can truly examine whether the action characteristics of the stability device strategy after a fault occurs and the response characteristics of the power grid after the action meet the design requirements.

[0049] In this embodiment, a closed-loop test system for a power grid safety and stability control system is provided. The system includes a detection platform and multiple power grid safety and stability control systems arranged in multiple plants and stations. The detection platform includes a simulation software system and a detection platform management machine; the simulation software system is used to simulate a preset power grid system to obtain strategy simulation data corresponding to a preset strategy, and the preset strategy includes multiple rounds of action signals; the detection platform management machine is used to send the strategy simulation data to the power grid safety and stability control system for strategy simulation verification, and obtain the strategy simulation results corresponding to the first round of action signals; according to the strategy simulation results corresponding to the first round of action signals, the simulation software in the simulation software system is controlled to perform iterative calculations to generate iterative simulation data; according to the iterative simulation data, the strategy simulation verification is performed again, and the process of iterative calculation and strategy simulation verification is repeated until the closed-loop test of multiple rounds of action signals in the preset strategy is completed.

[0050] It should be noted that the further working description of the above-mentioned simulation software system and detection platform management machine is the same as the above-mentioned closed-loop test method embodiment of the power grid safety and stability control system, and will not be repeated here.

[0051] In an optional embodiment, the plant station also includes: a verification node machine, a signal conversion device and a power amplifier; the verification node machine is used to receive the strategy simulation data output by the detection platform management machine, and send the strategy simulation data to the signal conversion device; the signal conversion device is used to convert the strategy simulation data and output it to the power amplifier; the power amplifier is used to amplify the converted data and input it into the power grid safety and stability control system for strategy simulation verification; the signal conversion device is also used to receive the strategy simulation results after the strategy simulation verification by the power grid safety and stability control system and send them to the detection platform management machine through the verification node machine.

[0052] Specifically, the signal conversion device is used to process the electrical quantity data in the strategy simulation data, such as analog-to-digital conversion, and then input it into the power grid safety and stability control system for strategy simulation verification after power amplification by the power amplifier; at the same time, the signal conversion device can also receive the strategy simulation results such as switch quantity and other data after the strategy simulation verification by the power grid safety and stability control system, process them, and then send them to the verification node machine.

[0053] In an optional implementation, the detection platform management machine and the verification node machine use a virtual private dial-up network for communication. The system uses Beidou satellite synchronization technology for synchronization, such as Figure 2As shown, the B code timing scheme can be adopted. Specifically, when the detection platform and the plant station are far apart, such as when the detection platform is set up in a laboratory, a virtual private dial-up network can be used for wireless communication between the detection platform management machine and the verification node machine to improve the test efficiency. In addition, the synchronization problem of spatially large-span distributed system detection is guaranteed by synchronous timing. Among them, when a virtual private dial-up network is used, an AR7088H gateway and a 5G dedicated card can be configured for each verification node machine in the plant station. The detection platform management machine can access any of the gateways, or a gateway can be configured for the management machine separately. Thus, a virtual private dial-up network dedicated 5G card and an industrial-grade 5G gateway AR7088H are used to realize self-organizing networking. Each SIM card has a fixed IP, realizing flexible point-to-point and point-to-multi wireless communication applications.

[0054] In addition, it should be noted that when there are many power grid safety and stability control systems to be tested, the system can use parallel and distributed computing technologies to improve computing efficiency and simulation scale.

[0055] In an optional embodiment, if Figure 2 As shown, the working principle of the power grid security and stability control device is explained with a preset strategy including two rounds of action signals:

[0056] The simulation software in the simulation software system set up in the laboratory, such as ADPSS, simulates the preset power grid system to obtain a power grid model, simulates the fault state of the preset power grid system according to the preset strategy based on the power grid model, and sends the simulation data of the simulated fault state of the preset power grid system as the strategy simulation data, i.e., the simulation result file, to the detection platform management machine.

[0057] After receiving the strategy simulation data, the detection platform management machine parses it to generate test data such as electrical quantity data under relevant fault conditions, and sends the parsed data to the corresponding power grid safety and stability control system (i.e., stability control equipment) through the verification node machines, signal conversion devices and power amplifiers in each plant station. The power grid safety and stability control system performs the strategy simulation verification of the first round of action signals based on the received data to obtain the corresponding action control data, and converts the action control data through the signal conversion device and sends it to the detection platform management machine by the verification node machine.

[0058] The detection platform management machine sends the action events in the received data to ADPSS, and ADPSS updates the power grid model according to the action events (such as closing a switch) and simulates and generates iterative simulation data. The detection platform management machine sends the electrical quantity data in the iterative simulation data to the corresponding power grid safety and stability control system (i.e., stabilization control equipment) through the verification node machines, signal conversion devices, and power amplifiers in each plant station, performs a second round of action signal strategy simulation verification, obtains the corresponding action control data, and converts the action control data through the signal conversion device and sends it to the detection platform management machine from the verification node machine.

[0059] The detection platform management machine sends the action events in the received data to ADPSS. ADPSS updates the power grid model according to the action events (such as disconnecting a switch) and simulates and generates iterative simulation data. The detection platform management machine sends the electrical quantity data in the iterative simulation data to the corresponding power grid safety and stability control system (i.e., stabilization control equipment) through the verification node machines, signal conversion devices, and power amplifiers in each plant station. If the power grid safety and stability control system has no other actions, it means that the electrical quantity data in the iterative simulation data obtained this time meets the power grid operation requirements, that is, the corresponding fault state can be eliminated by executing the preset strategy, and the preset strategy does not need to be adjusted again. If the power grid safety and stability control system receives the iterative simulation data and executes a new action, it means that the electrical quantity data in the iterative simulation data obtained this time does not meet the power grid operation requirements, that is, the corresponding fault state cannot be eliminated by executing the preset strategy, and the preset strategy needs to be adjusted.

[0060] The embodiment of the present invention also provides a computer device having the above Figure 2 The closed-loop test system of the power grid security and stability control system is shown.

[0061] See also Figure 3 , Figure 3 is a schematic diagram of the structure of a computer device provided by an optional embodiment of the present invention, such as Figure 3As shown, the computer device includes: one or more processors 10, a memory 20, and interfaces for connecting various components, including high-speed interfaces and low-speed interfaces. Various components are connected to each other using different buses for communication, and can be installed on a common mainboard or installed in other ways as needed. The processor can process the instructions executed in the computer device, including instructions stored in or on the memory to display the graphical information of the GUI on an external input / output device (such as, a display device coupled to the interface). In some optional embodiments, if necessary, multiple processors and / or multiple buses can be used together with multiple memories and multiple memories. Similarly, multiple computer devices can be connected, and each device provides some necessary operations (for example, as a server array, a group of blade servers, or a multi-processor system). Figure 3 A processor 10 is taken as an example.

[0062] The processor 10 may be a central processing unit, a network processor or a combination thereof. The processor 10 may further include a hardware chip. The hardware chip may be a dedicated integrated circuit, a programmable logic device or a combination thereof. The programmable logic device may be a complex programmable logic device, a field programmable gate array, a general purpose array logic or any combination thereof.

[0063] The memory 20 stores instructions executable by at least one processor 10, so that at least one processor 10 executes the method shown in the above embodiment.

[0064] The memory 20 may include a program storage area and a data storage area, wherein the program storage area may store an operating system, an application required for at least one function; the data storage area may store data created by the use of a computer device based on the presentation of a small program landing page, etc. In addition, the memory 20 may include a high-speed random access memory, and may also include a non-transient memory, such as at least one disk storage device, a flash memory device, or other non-transient solid-state storage device. In some optional embodiments, the memory 20 may optionally include a memory remotely arranged relative to the processor 10, and these remote memories may be connected to the computer device via a network. Examples of the above-mentioned network include, but are not limited to, the Internet, an intranet, a local area network, a mobile communication network, and combinations thereof.

[0065] The memory 20 may include a volatile memory, such as a random access memory; the memory may also include a non-volatile memory, such as a flash memory, a hard disk or a solid state drive; the memory 20 may also include a combination of the above types of memory.

[0066] The computer device further comprises a communication interface 30 for the computer device to communicate with other devices or a communication network.

[0067] The embodiment of the present invention also provides a computer-readable storage medium. The method according to the embodiment of the present invention can be implemented in hardware, firmware, or can be implemented as a computer code that can be recorded in a storage medium, or can be implemented as a computer code that is originally stored in a remote storage medium or a non-temporary machine-readable storage medium and will be stored in a local storage medium through a network download, so that the method described herein can be stored in such software processing on a storage medium using a general-purpose computer, a dedicated processor, or programmable or dedicated hardware. Among them, the storage medium can be a magnetic disk, an optical disk, a read-only storage memory, a random access memory, a flash memory, a hard disk or a solid-state hard disk, etc.; further, the storage medium can also include a combination of the above types of memories. It can be understood that a computer, a processor, a microprocessor controller, or programmable hardware includes a storage component that can store or receive software or computer code. When the software or computer code is accessed and executed by a computer, a processor, or hardware, the method shown in the above embodiment is implemented.

[0068] A part of the present invention may be applied as a computer program product, such as a computer program instruction, which, when executed by a computer, can call or provide the method and / or technical solution according to the present invention through the operation of the computer. Those skilled in the art should understand that the existence of the computer program instruction in a computer-readable medium includes, but is not limited to, a source file, an executable file, an installation package file, etc., and accordingly, the way in which the computer program instruction is executed by the computer includes, but is not limited to: the computer directly executes the instruction, or the computer compiles the instruction and then executes the corresponding compiled program, or the computer reads and executes the instruction, or the computer reads and installs the instruction and then executes the corresponding installed program. Here, the computer-readable medium may be any available computer-readable storage medium or communication medium accessible to the computer.

[0069] Although the embodiments of the present invention have been described in conjunction with the accompanying drawings, those skilled in the art may make various modifications and variations without departing from the spirit and scope of the present invention, and such modifications and variations are all within the scope defined by the appended claims.

Claims

1. A closed-loop test method for a power grid security and stability control system, characterized in that: The method comprises: Acquire strategy simulation data corresponding to a preset strategy obtained by simulating a preset power grid system, wherein the preset strategy includes multiple rounds of action signals; Sending the strategy simulation data to the power grid security and stability control system for strategy simulation verification to obtain the strategy simulation results corresponding to the first round of action signals; According to the strategy simulation results corresponding to the first round of action signals, the simulation software is controlled to perform iterative calculations to generate iterative simulation data; The strategy simulation verification is performed again based on the iterative simulation data, and the process of iterative calculation and strategy simulation verification is repeated until the closed-loop test of multiple rounds of action signals in the preset strategy is completed.

2. The method according to claim 1, characterized in that Acquire the strategy simulation data corresponding to the preset strategy obtained by simulating the preset power grid system, including: Use simulation software to build a power grid model and perform simulation to obtain simulation result data; Based on the power grid model, the fault state of the preset power grid system is simulated according to the preset strategy, and the simulation data of the simulated fault state of the preset power grid system is used as the strategy simulation data.

3. The method according to claim 2, characterized in that The strategy simulation result includes the action control data of the fully stable control system of the power grid; the simulation software is controlled to perform iterative calculation according to the strategy simulation result corresponding to the first round of action signals to generate iterative simulation data, including: The control simulation software updates the power grid model according to the action control data to obtain an updated power grid model; Based on the updated power grid model, the fault state of the preset power grid system is simulated according to the preset strategy to generate iterative simulation data.

4. The method according to claim 2, characterized in that: The strategy simulation verification is performed again based on the iterative simulation data, and the process of iterative calculation and strategy simulation verification is repeated until the closed-loop test of multiple rounds of action signals in the preset strategy is completed, including: Perform strategy simulation verification again based on iterative simulation data, repeat the process of iterative calculation and strategy simulation verification until the strategy simulation result corresponding to the last round of action signal is obtained; According to the strategy simulation result corresponding to the last round of action signals, the simulation software is controlled to perform iterative calculations to generate iterative simulation data; The strategy simulation data is sent to the power grid security and stability control system for strategy simulation verification, and a closed-loop test result of the preset strategy is obtained based on the verification result.

5. A closed-loop test system for a power grid security and stability control system, characterized in that: The system includes a detection platform and multiple power grid safety and stability control systems set up in multiple plants and stations, and the detection platform includes a simulation software system and a detection platform management machine; The simulation software system is used to simulate a preset power grid system to obtain strategy simulation data corresponding to a preset strategy, wherein the preset strategy includes multiple rounds of action signals; The detection platform management machine is used to send the strategy simulation data to the power grid security and stability control system for strategy simulation verification, and obtain the strategy simulation results corresponding to the first round of action signals; According to the strategy simulation result corresponding to the first round of action signals, the simulation software in the simulation software system is controlled to perform iterative calculations to generate iterative simulation data; The strategy simulation verification is performed again based on the iterative simulation data, and the process of iterative calculation and strategy simulation verification is repeated until the closed-loop test of multiple rounds of action signals in the preset strategy is completed.

6. The system according to claim 5, characterized in that The plant station also includes: a verification node machine, a signal conversion device and a power amplifier; The verification node machine is used to receive the strategy simulation data output by the detection platform management machine, and send the strategy simulation data to the signal conversion device; The signal conversion device is used to convert the strategy simulation data and then output it to the power amplifier; The power amplifier is used to amplify the converted data and then input it into the power grid security and stability control system for strategy simulation verification; The signal conversion device is also used to receive the strategy simulation results after the power grid security and stability control system performs strategy simulation verification and send them to the detection platform management machine through the verification node machine.

7. The system according to claim 6, characterized in that The detection platform management machine and the verification node machine communicate with each other using a virtual private dial-up network.

8. The system according to claim 5, characterized in that The system adopts Beidou satellite synchronization technology for synchronization and time synchronization.

9. A computer device, characterized in that: include: A memory and a processor, wherein the memory and the processor are communicatively connected to each other, the memory stores computer instructions, and the processor executes the closed-loop test method for the power grid security and stability control system according to any one of claims 1 to 4 by executing the computer instructions.

10. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores computer instructions, and the computer instructions are used to enable a computer to execute the closed-loop testing method for a power grid security and stability control system according to any one of claims 1 to 4.