Heat supply method and system based on multivariate peak regulation
Through data analysis and dynamic adjustment of the heating demand and operating status of the power plant, the problem of the inability to accurately control the heating supply of the power plant is solved, and accurate prediction and cost optimization of the heating capacity of the power plant is achieved.
Patent Information
- Application Number
- CN202410801794.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-20
- Publication Date
- 2024-11-12
AI Technical Summary
The existing technology lacks the control and prediction capabilities for allocating thermal power plants, which leads to the inability to accurately control the heating of power plants and the inability to effectively deal with changes in thermal loads.
By analyzing historical data, filtering the original matching relationship data between heating demand parameters and power plant operating status, determining heating-related costs, dynamically adjusting the power plant operating status, generating reference matching relationship data, eliminating unstable data, sorting the best, and testing The optimal solution is to achieve accurate prediction and control of power plant heating.
Accurate prediction of the heating capacity of the power plant and more reasonable energy utilization have been achieved, reducing the overall heating cost.
Smart Images

Figure CN118940988A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of power plant heating, and in particular to a heating method and system based on multi-element peak regulation. Background Art
[0002] The multi-peak shaving heating method usually refers to the use of multiple means and strategies in the heating system to adapt to the changes in heat load in different time periods to ensure the efficient operation of the heating system and the rational use of energy. This includes cogeneration, which combines thermal power plants with heating systems and uses the waste heat generated during the power generation process for heating to improve energy efficiency. In the existing technology, due to the lack of control and prediction capabilities for the allocation of thermal power plant heating, the heating of power plants cannot be accurately controlled. Therefore, there is an urgent need for a multi-peak shaving heating method and system that can predict and control the heating of power plants. Summary of the invention
[0003] The object of the present invention is to provide a multi-element peak-shaving heating method and system capable of predicting and controlling the heating supply of a power plant.
[0004] The present invention discloses a heating method based on multi-element peak regulation, comprising:
[0005] Analyze historical data and filter out the original matching relationship data between heating demand parameters and power plant operating status;
[0006] Based on the time node to which the original matching relationship data belongs, determining the heating related cost corresponding to the original matching relationship data, and based on the heating related cost, determining the original heating total cost;
[0007] Based on the heat demand parameters, the power plant operation status in the original matching relationship data is dynamically adjusted to generate a number of reference matching relationship data;
[0008] Based on the heating-related costs corresponding to the original matching relationship data, the total reference heating cost of each reference matching relationship data is calculated;
[0009] Based on the stability requirements of the power plant operation status, the reference matching relationship data are eliminated, and based on the reference total heating cost and the stability characteristics of the power plant operation status, the remaining reference matching relationship data are prioritized;
[0010] Several reference matching relationship data with the highest ranking are tested, and based on the test results, the reference matching relationship data to be retained are determined.
[0011] In some embodiments disclosed in the present invention, the method for screening out the original matching relationship data between the heating demand parameter, the power plant operation status and the ambient temperature includes:
[0012] Taking each day as the analysis cycle, the heating demand parameters and power plant operation status data in the historical data are extracted in a manner corresponding to the time nodes, and the heating demand parameters and power plant operation status data are sorted according to the time series relationship.
[0013] In some embodiments disclosed in the present invention, the method for screening out the original matching relationship data between the heating demand parameter and the power plant operation status also includes:
[0014] Analyze the temporal correlation between heat demand parameter data and power plant operation status data;
[0015] Based on the relevant mapping relationship, several first focus time mapping sections are defined for the heat demand parameter data, several second focus time mapping sections are defined for the power plant operation status data, and the first focus time mapping sections are associated with the second focus time mapping sections.
[0016] In some embodiments disclosed in the present invention, a method for dynamically adjusting the power plant operating status in the original plant matching relationship data includes:
[0017] Scan and analyze the power plant operation status data of the second focus time mapping section to determine the power plant heat supply parameter curve and power generation curve, scan and analyze the heat demand parameter data to generate the heat demand parameter curve;
[0018] If the fluctuation amplitude of the power plant heating parameter curve is greater than the preset value, and the number of fluctuations is greater than the preset value, the power plant heating parameter curve is flattened and adjusted;
[0019] If the heating demand parameter curve and the power generation curve rise correspondingly at the same time, and the power generation curve is greater than or equal to the power generation standard line, the rising curvature of the power generation curve is adjusted upward or downward.
[0020] In some embodiments disclosed in the present invention, based on the reference total heating cost and the stability characteristics of the power plant operation state, the method for preferentially sorting the remaining reference matching relationship data includes:
[0021] Based on the time length of each concerned mapping time segment and the total heating costs corresponding to different time nodes, the sub-reference total heating cost of each concerned mapping time segment is calculated;
[0022] Scan and analyze the power generation curve in the power plant operation state corresponding to each concerned mapping time segment, determine the abnormal fluctuation amplitude of the curve fluctuation amplitude greater than the preset value and the abnormal duration greater than the preset value, and calculate the corresponding sub-stability evaluation of each concerned mapping time segment based on the abnormal fluctuation amplitude and the abnormal duration;
[0023] Based on the sub-reference total heating cost corresponding to each concerned mapping section, the reference total heating cost is calculated, and based on the sub-stability evaluation corresponding to each concerned mapping section, the stability evaluation of the reference matching relationship data is calculated;
[0024] Based on the reference heating total cost and stability evaluation, the remaining reference matching relationship data are prioritized;
[0025] Among them, the expression for calculating the stability evaluation of the sub-component is:
[0026]
[0027] Among them, W is the corresponding value of the sub-stability evaluation, k1 is the stability evaluation conversion coefficient, h is the abnormal vibration amplitude, t is the abnormal duration, and c is the abnormal fluctuation adjustment constant.
[0028] In some embodiments disclosed in the present invention, the method for preferentially sorting the remaining reference matching relationship data includes:
[0029] Determine the preset total cost interval to which the reference heating total cost belongs, and determine the first priority weight value of the reference matching relationship data based on the corresponding relationship between the preset total cost interval and the priority weight value;
[0030] Determine the preset stability evaluation interval to which the stability evaluation belongs, and determine the second priority weight value of the reference matching relationship data based on the corresponding relationship between the preset stability evaluation interval and the priority weight value;
[0031] The first priority weight value and the second priority weight value are summed to obtain a comprehensive priority value of the reference matching relationship data, and the reference matching relationship data is preferentially sorted based on the size of the comprehensive priority weight value.
[0032] In some embodiments disclosed in the present invention, the method for preferentially sorting the remaining reference matching relationship data includes:
[0033] A first weight coefficient and a second weight coefficient are set for reference heating comprehensive cost and stability evaluation respectively;
[0034] Based on the first weight coefficient and the reference heating comprehensive cost, a first priority operator is constructed, and based on the second weight coefficient and the stability evaluation, a second priority operator is constructed;
[0035] Based on the first priority operator and the second priority operator, a comprehensive priority value is obtained, and based on the size of the comprehensive priority value, the reference matching relationship data is prioritized.
[0036] In some embodiments disclosed in the present invention, based on the heating-related costs, the method for determining the total heating cost includes:
[0037] Analyze the difference between the heat demand parameter and the first heat parameter in the power plant operation status data at the same time node, and define the difference as the second heat parameter;
[0038] Determine the source channel of the second heating parameter, obtain the unit quotation of heating from each source channel, and calculate the second total heating cost corresponding to the second heating parameter in combination with the third heating parameter of each source channel;
[0039] Obtain the additional power generation beyond the planned power generation in the power plant operation status data, and calculate the equivalent heating loss unit price corresponding to the additional power generation in combination with the power quotation at the same time node;
[0040] Calculate the basic heating unit price corresponding to the first heating parameter in the power plant operation status data, and combine it with the equivalent heating loss unit price to obtain the first total heating cost corresponding to the first heating parameter;
[0041] Based on the first total heating cost and the second total heating cost, obtaining the total heating cost;
[0042] The expression for calculating the total heating cost is:
[0043]
[0044] Among them, M is the corresponding value of the total heating cost per unit time, a n is the unit price of heat supply from the nth heat supply source, v 3~n is the third heating parameter of the nth heating source channel, g is the basic heating unit price of the power plant, v2 is the second heating parameter, p2 is the real-time power generation of the power plant, p1 is the planned power generation of the power plant, b is the power generation adjustment constant, and L is the equivalent heating loss unit price adjustment coefficient.
[0045] In some embodiments disclosed in the present invention, a method for determining reference matching relationship data of an application based on a test result includes:
[0046] Obtain real-time heating demand parameters, and based on the corresponding relationship, determine the reference matching relationship data to be called for data;
[0047] The operating status of the power plant is collected in real time. If the operating status of the power plant collected in real time is consistent with the operating status of the power plant expressed in the reference matching relationship data, the reference matching relationship data is retained.
[0048] In some embodiments disclosed in the present invention, there is also disclosed a heating system based on multi-element peak load regulation, comprising:
[0049] The first module is used to analyze historical data and filter out the original matching relationship data between heating demand parameters and power plant operation status;
[0050] The second module is used to determine the heating related costs corresponding to the original matching relationship data based on the time node to which the original matching relationship data belongs, and determine the original heating total cost based on the heating related costs;
[0051] The third module is used to dynamically adjust the power plant operation status in the original matching relationship data based on the heating demand parameter, generate a number of reference matching relationship data, and calculate the total reference heating cost of each reference matching relationship data based on the heating-related cost corresponding to the original matching relationship data;
[0052] The fourth module is used to eliminate reference matching relationship data based on the stability requirements of the power plant's operating status, and to prioritize the remaining reference matching relationship data based on the reference total heating cost and the stability characteristics of the power plant's operating status, to test several reference matching relationship data with the highest ranking, and to determine the reference matching relationship data to be retained based on the test results.
[0053] The present invention discloses a heating method and system based on multi-element peak regulation, and relates to the technical field of power plant heating. The specifically disclosed technical scheme is to screen out the original matching relationship data between the heating demand parameters and the operating status of the power plant, determine the original total heating cost, calculate the reference total heating cost of each reference matching relationship data based on the heating-related costs corresponding to the original matching relationship data, and preferentially sort the remaining reference matching relationship data based on the reference total heating cost and the stability characteristics of the power plant operating status, test several reference matching relationship data with top rankings, and determine the retained reference matching relationship data based on the test results. Through the above technical scheme, the present invention realizes the gradual optimization of the original matching relationship data, can realize more accurate prediction of the heating capacity of the power plant, and more reasonably call the heating capacity of the power plant, thereby reducing the overall heating cost.
[0054] The technical solution of the present invention is further described in detail below through the accompanying drawings and embodiments. BRIEF DESCRIPTION OF THE DRAWINGS
[0055] Figure 1 This is a method step diagram of a heating method based on multi-element peak regulation disclosed in an embodiment of the present invention. DETAILED DESCRIPTION
[0056] The technical solution of the present invention is further described below through the accompanying drawings and embodiments.
[0057] The following will be combined with the accompanying drawings and specific embodiments to clearly and completely describe the technical solution of the present invention. It should be understood that the preferred embodiments described herein are only used to illustrate and explain the present invention and cannot be understood as limiting the scope of protection of the present invention. Those skilled in the art in this field can make some non-essential improvements and adjustments based on the content of the present invention described below. In the present invention, unless otherwise clearly specified and limited, the technical terms used in the present invention should be the common meanings understood by the technical personnel described in the present invention.
[0058] The present invention discloses a heating method based on multi-element peak regulation, see Figure 1 ,include:
[0059] Step S100, analyzing historical data to filter out original matching relationship data between heating demand parameters and power plant operating status.
[0060] In this step, historical data needs to be analyzed, among which the heat demand parameters can be the heat demand index parameters required at different time nodes, that is, the total heat demand, and the power plant operation status can be the power generation at different time nodes. Under normal conditions, the higher the power generation of the power plant, the greater the heating capacity. The significance of establishing a correlation between the heat demand parameters and the power plant operation status data is that under normal conditions, when certain characteristics can be expressed according to the heat demand parameters, the power plant operation status can be determined, and then the power plant heating capacity can be predicted when heating is needed in the later stage.
[0061] Step S200, based on the time node to which the original matching relationship data belongs, determine the heating related costs corresponding to the original matching relationship data, and based on the heating related costs, determine the original heating total cost.
[0062] In this step, the corresponding heating-related costs are determined according to the time points of the original matching relationship data, and the total heating costs corresponding to each set of original matching relationship data are calculated to obtain the original heating cost data, providing a basis for subsequent optimization.
[0063] Step S300: Based on the heat demand parameter, the power plant operation status in the original matching relationship data is dynamically adjusted to generate a number of reference matching relationship data.
[0064] In this step, the operating status of the power plant is dynamically adjusted according to the heating demand parameters, and multiple sets of possible operating plans are generated (refer to the matching relationship data) to explore different power plant operating states to better meet the heating demand.
[0065] Step S400, based on the heating-related costs corresponding to the original matching relationship data, the reference total heating cost of each reference matching relationship data is calculated.
[0066] In this step, for each set of reference matching relationship data, the corresponding reference total heating cost is calculated based on the original heating cost data to evaluate the cost-effectiveness of different operation schemes.
[0067] Step S500, based on the stability requirement of the power plant operation state, the reference matching relationship data is eliminated, and based on the reference total heating cost and the stability characteristics of the power plant operation state, the remaining reference matching relationship data is preferentially sorted.
[0068] In this step, according to the stability requirements of the power plant's operating status, those reference matching relationship data that may cause unstable operation of the power plant are eliminated. Combined with the reference total heating cost and stability characteristics, the remaining data are sorted to find the operating plan with the best cost-effectiveness and stability, ensure the stability of the power plant's operation, and find the operating plan with the best economic benefits.
[0069] Step S600 , testing a number of reference matching relationship data that are ranked high, and determining the reference matching relationship data to be retained based on the test results.
[0070] In this step, field tests or simulation tests are conducted on several reference matching relationship data that are ranked high to verify their actual effects. Based on the test results, the reference matching relationship data that are finally retained, i.e., the optimal power plant operation plan, is determined.
[0071] In some embodiments disclosed in the present invention, the method for screening out the original matching relationship data between the heating demand parameter, the power plant operation status and the ambient temperature includes:
[0072] Step S101, taking each day as the analysis cycle, extracting the heat demand parameters and power plant operation status data in the historical data in a manner corresponding to the time nodes, and sorting the heat demand parameters and power plant operation status data according to the time series relationship.
[0073] In some embodiments disclosed in the present invention, the method for screening out the original matching relationship data between the heating demand parameter and the power plant operation status also includes:
[0074] Step S201, analyzing the temporal correlation mapping relationship between the heat demand parameter data and the power plant operation status data.
[0075] Step S202, based on the relevant mapping relationship, define a number of first focus time mapping sections for the heat demand parameter data, define a number of second focus time mapping sections for the power plant operation status data, and associate the first focus time mapping sections with the second focus time mapping sections.
[0076] In some embodiments disclosed in the present invention, a method for dynamically adjusting the power plant operating status in the original plant matching relationship data includes:
[0077] Step S2021, scan and analyze the power plant operation status data of the second focus time mapping section, determine the power plant heating parameter curve and power generation curve, scan and analyze the heating demand parameter data, and generate the heating demand parameter curve.
[0078] In this step, the power plant operating status data of a specific time period (the second focus time mapping period) is analyzed to determine the power plant's heating parameter curve and power generation curve. At the same time, the heating demand parameter data is analyzed to generate a heating demand parameter curve and obtain the key performance indicator curves of the power plant's heating and power generation.
[0079] Step S2022: If the fluctuation amplitude of the power plant heating parameter curve is greater than the preset value, and the number of fluctuations is greater than the preset value, the power plant heating parameter curve is leveled and adjusted.
[0080] In this step, if the fluctuation amplitude and fluctuation frequency of the power plant's heating parameter curve exceed the preset threshold, it indicates that the heating output is unstable and may need to be adjusted to level it, that is, to reduce fluctuations and make the heating parameter curve more stable, thereby ensuring the stability of the heating output and avoiding the impact of excessive fluctuations on the quality of heating services.
[0081] Step S2023, if the heating demand parameter curve and the power generation curve rise correspondingly at the same time, and the power generation curve is greater than or equal to the power generation standard line, the rising curvature of the power generation curve is adjusted upward or downward.
[0082] In this step, when the heat demand parameter curve and the power generation curve rise at the same time, and the power generation curve is greater than or equal to the power generation standard line, it indicates that the power plant may be able to provide more thermal energy. Depending on the specific situation, the rising curvature of the power generation curve is adjusted up or down to better meet the heat demand while maintaining the efficiency of the power plant operation, optimizing the power generation efficiency and heating capacity of the power plant, and achieving a balance between energy output and demand.
[0083] In some embodiments disclosed in the present invention, based on the reference total heating cost and the stability characteristics of the power plant operation state, the method for preferentially sorting the remaining reference matching relationship data includes:
[0084] Step S501 : calculating the sub-reference total heating cost of each focused mapping time segment based on the time length of each focused mapping time segment and the total heating cost corresponding to different time nodes.
[0085] Step S502, scan and analyze the power generation curve in the power plant operating state corresponding to each concerned mapping time segment, determine the abnormal fluctuation amplitude of the curve fluctuation amplitude greater than the preset value and the abnormal duration greater than the preset value, and based on the abnormal fluctuation amplitude and the abnormal duration, calculate the corresponding sub-stability evaluation of each concerned mapping time segment.
[0086] Step S503, based on the sub-reference total heating cost corresponding to each concerned mapping section, a reference total heating cost is calculated, and based on the sub-stability evaluation corresponding to each concerned mapping section, a stability evaluation of the reference matching relationship data is calculated.
[0087] Step S504: based on the reference total heating cost and stability evaluation, the remaining reference matching relationship data are prioritized.
[0088] Among them, the expression for calculating the stability evaluation of the sub-component is:
[0089]
[0090] Among them, W is the corresponding value of the sub-stability evaluation, k1 is the stability evaluation conversion coefficient, h is the abnormal vibration amplitude, t is the abnormal duration, and c is the abnormal fluctuation adjustment constant.
[0091] In some embodiments disclosed in the present invention, the method for preferentially sorting the remaining reference matching relationship data includes:
[0092] Step S5041, determine the preset total cost interval to which the reference heating total cost belongs, and determine the first priority weight value of the reference matching relationship data based on the corresponding relationship between the preset total cost interval and the priority weight value.
[0093] In this step, the stability of each reference matching relationship data is evaluated and classified into the corresponding preset stability evaluation interval. Using the correspondence between the preset stability evaluation interval and the priority weight value, a second priority weight value is assigned to each reference matching relationship data. Ensuring the stability of power plant operation is also an important factor in selecting the optimal matching relationship.
[0094] Step S5042, determining the preset stability evaluation interval to which the stability evaluation belongs, and determining the second priority weight value of the reference matching relationship data based on the corresponding relationship between the preset stability evaluation interval and the priority weight value.
[0095] In this step, the stability of each reference matching relationship data is evaluated and classified into the corresponding preset stability evaluation interval. Using the correspondence between the preset stability evaluation interval and the priority weight value, a second priority weight value is assigned to each reference matching relationship data. Ensuring the stability of power plant operation is also an important factor in selecting the optimal matching relationship.
[0096] Step S5043, summing the first priority weight value and the second priority weight value to obtain a comprehensive priority value of the reference matching relationship data, and prioritizing the reference matching relationship data based on the size of the comprehensive priority weight value.
[0097] The above steps can provide a comprehensive score for each reference matching relationship data, which reflects the dual considerations of cost and stability. Finally, all reference matching relationship data can be sorted according to this comprehensive score to determine which solutions are the best. This multi-factor decision-making method helps to strike a balance between multiple goals and ensure that the selected solution is both economical and stable.
[0098] In some embodiments disclosed in the present invention, the method for preferentially sorting the remaining reference matching relationship data includes:
[0099] Step S5044, setting a first weight coefficient and a second weight coefficient respectively for the reference heating comprehensive cost and stability evaluation.
[0100] Step S5045, constructing a first priority operator based on the first weight coefficient and the reference heating comprehensive cost, and constructing a second priority operator based on the second weight coefficient and the stability evaluation.
[0101] Step S5046, based on the first priority operator and the second priority operator, a comprehensive priority value is obtained, and based on the size of the comprehensive priority value, the reference matching relationship data is prioritized.
[0102] In some embodiments disclosed in the present invention, based on the heating-related costs, the method for determining the total heating cost includes:
[0103] Step S201, analyzing the difference between the heat demand parameter and the first heat parameter in the power plant operation status data at the same time node, and defining the difference as the second heat parameter.
[0104] Step S202, determining the source channel of the second heating parameter, and obtaining the unit quotation of heating from each source channel, combining the third heating parameter of each source channel, and calculating the second total heating cost corresponding to the second heating parameter.
[0105] Step S203, obtaining the additional power generation power other than the planned power generation power in the power plant operation status data, and calculating the equivalent heating loss unit price corresponding to the additional power generation power in combination with the power quotation at the same time node;
[0106] Step S204, calculating the basic heating unit price corresponding to the first heating parameter in the power plant operation status data, and combining it with the equivalent heating loss unit price to obtain the first total heating cost corresponding to the first heating parameter.
[0107] Step S205, obtaining the total heating cost based on the first total heating cost and the second total heating cost.
[0108] The expression for calculating the total heating cost is:
[0109]
[0110] Among them, M is the corresponding value of the total heating cost per unit time, a n is the unit price of heat supply from the nth heat supply source, v 3~n is the third heating parameter of the nth heating source channel, g is the basic heating unit price of the power plant, v2 is the second heating parameter, p2 is the real-time power generation of the power plant, p1 is the planned power generation of the power plant, b is the power generation adjustment constant, and L is the equivalent heating loss unit price adjustment coefficient.
[0111] In some embodiments disclosed in the present invention, a method for determining reference matching relationship data of an application based on a test result includes:
[0112] Step S601, obtain real-time heating demand parameters, and based on the corresponding relationship, determine the reference matching relationship data to be called for data.
[0113] Step S602, collecting the operating status of the power plant in real time, if the operating status of the power plant collected in real time is consistent with the operating status of the power plant expressed in the reference matching relationship data, then retaining the reference matching relationship data.
[0114] The above steps ensure that the selected reference matching relationship data is not only optimal in theory, but also feasible in practice. Through real-time monitoring and comparison, it can be verified whether these data are truly applicable to the current heating demand and power plant operating conditions. If the verification is successful, these data will be finally determined as the reference matching relationship data for application, which will be used to guide the operation strategy of the power plant.
[0115] In some embodiments disclosed in the present invention, there is also disclosed a heating system based on multi-element peak regulation, including: a first module, a second module, a third module and a fourth module.
[0116] The first module is used to analyze historical data and filter out original matching relationship data between heating demand parameters and power plant operating status.
[0117] The second module is used to determine the heating-related costs corresponding to the original matching relationship data based on the time node to which the original matching relationship data belongs, and to determine the original total heating cost based on the heating-related costs.
[0118] The third module is used to dynamically adjust the power plant operating status in the original matching relationship data based on the heating demand parameters, generate a number of reference matching relationship data, and calculate the total reference heating cost of each reference matching relationship data based on the heating-related costs corresponding to the original matching relationship data.
[0119] The fourth module is used to eliminate reference matching relationship data based on the stability requirements of the power plant's operating status, and to prioritize the remaining reference matching relationship data based on the reference total heating cost and the stability characteristics of the power plant's operating status, to test several reference matching relationship data with the highest ranking, and to determine the reference matching relationship data to be retained based on the test results.
[0120] Through the description of the above implementation methods, those skilled in the art can clearly understand that the present invention can be implemented by hardware, or by means of software plus a necessary general hardware platform. Based on such an understanding, the technical solution of the present invention can be embodied in the form of a software product, which can be stored in a non-volatile storage medium (which can be a CD-ROM, a USB flash drive, a mobile hard disk, etc.), including a number of instructions for a computer device (which can be a personal computer, a server, or a network device, etc.) to execute the methods described in each implementation scenario of the present invention.
[0121] The present invention discloses a heating method and system based on multi-element peak regulation, and relates to the technical field of power plant heating. The specifically disclosed technical scheme is to screen out the original matching relationship data between the heating demand parameters and the operating status of the power plant, determine the original total heating cost, calculate the reference total heating cost of each reference matching relationship data based on the heating-related costs corresponding to the original matching relationship data, and preferentially sort the remaining reference matching relationship data based on the reference total heating cost and the stability characteristics of the power plant operating status, test several reference matching relationship data with top rankings, and determine the retained reference matching relationship data based on the test results. Through the above technical scheme, the present invention realizes the gradual optimization of the original matching relationship data, can realize more accurate prediction of the heating capacity of the power plant, and more reasonably call the heating capacity of the power plant, thereby reducing the overall heating cost.
[0122] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that they can still modify or replace the technical solution of the present invention with equivalents, and these modifications or equivalent replacements cannot cause the modified technical solution to deviate from the spirit and scope of the technical solution of the present invention.
Claims
1. A heating method based on multi-element peak load regulation, characterized in that: include: Analyze historical data and filter out the original matching relationship data between heating demand parameters and power plant operating status; Based on the time node to which the original matching relationship data belongs, determining the heating related cost corresponding to the original matching relationship data, and based on the heating related cost, determining the original heating total cost; Based on the heat demand parameters, the power plant operation status in the original matching relationship data is dynamically adjusted to generate a number of reference matching relationship data; Based on the heating-related costs corresponding to the original matching relationship data, the total reference heating cost of each reference matching relationship data is calculated; Based on the stability requirements of the power plant operation status, the reference matching relationship data are eliminated, and based on the reference total heating cost and the stability characteristics of the power plant operation status, the remaining reference matching relationship data are prioritized; Several reference matching relationship data with the highest ranking are tested, and based on the test results, the reference matching relationship data to be retained are determined.
2. A heating method based on multi-element peak load regulation according to claim 1, characterized in that: Methods for screening out original matching relationship data between heating demand parameters, power plant operation status and ambient temperature include: Taking each day as the analysis cycle, the heating demand parameters and power plant operation status data in the historical data are extracted in a manner corresponding to the time nodes, and the heating demand parameters and power plant operation status data are sorted according to the time series relationship.
3. A heating method based on multi-element peak load regulation according to claim 2, characterized in that: The method of screening out the original matching relationship data between the heat demand parameter and the power plant operation status also includes: Analyze the temporal correlation between heat demand parameter data and power plant operation status data; Based on the relevant mapping relationship, several first focus time mapping sections are defined for the heat demand parameter data, several second focus time mapping sections are defined for the power plant operation status data, and the first focus time mapping sections are associated with the second focus time mapping sections.
4. A heating method based on multi-element peak load regulation according to claim 3, characterized in that: The method for dynamically adjusting the power plant operation status in the original plant matching relationship data includes: Scan and analyze the power plant operation status data of the second focus time mapping section to determine the power plant heat supply parameter curve and power generation curve, scan and analyze the heat demand parameter data to generate the heat demand parameter curve; If the fluctuation amplitude of the power plant heating parameter curve is greater than the preset value, and the number of fluctuations is greater than the preset value, the power plant heating parameter curve is flattened and adjusted; If the heating demand parameter curve and the power generation curve rise correspondingly at the same time, and the power generation curve is greater than or equal to the power generation standard line, the rising curvature of the power generation curve is adjusted upward or downward.
5. The heating method based on multi-element peak load regulation according to claim 3, characterized in that: Based on the reference total heating cost and the stability characteristics of the power plant operation status, the method for preferentially sorting the remaining reference matching relationship data includes: Based on the time length of each concerned mapping time segment and the total heating costs corresponding to different time nodes, the sub-reference total heating cost of each concerned mapping time segment is calculated; Scan and analyze the power generation curve in the power plant operation state corresponding to each concerned mapping time segment, determine the abnormal fluctuation amplitude of the curve fluctuation amplitude greater than the preset value and the abnormal duration greater than the preset value, and calculate the corresponding sub-stability evaluation of each concerned mapping time segment based on the abnormal fluctuation amplitude and the abnormal duration; Based on the sub-reference total heating cost corresponding to each concerned mapping section, the reference total heating cost is calculated, and based on the sub-stability evaluation corresponding to each concerned mapping section, the stability evaluation of the reference matching relationship data is calculated; Based on the reference heating total cost and stability evaluation, the remaining reference matching relationship data are prioritized; Among them, the expression for calculating the stability evaluation of the sub-component is: ; Among them, W is the corresponding value of the sub-stability evaluation, k1 is the stability evaluation conversion coefficient, h is the abnormal vibration amplitude, t is the abnormal duration, and c is the abnormal fluctuation adjustment constant.
6. A multi-element peak-shaving heating method according to claim 5, characterized in that: Methods for preferentially sorting the remaining reference matching relationship data include: Determine the preset total cost interval to which the reference heating total cost belongs, and determine the first priority weight value of the reference matching relationship data based on the corresponding relationship between the preset total cost interval and the priority weight value; Determine the preset stability evaluation interval to which the stability evaluation belongs, and determine the second priority weight value of the reference matching relationship data based on the corresponding relationship between the preset stability evaluation interval and the priority weight value; The first priority weight value and the second priority weight value are summed to obtain a comprehensive priority value of the reference matching relationship data, and the reference matching relationship data is preferentially sorted based on the size of the comprehensive priority weight value.
7. A multi-element peak-shaving heating method according to claim 5, characterized in that: Methods for preferentially sorting the remaining reference matching relationship data include: A first weight coefficient and a second weight coefficient are set for reference heating comprehensive cost and stability evaluation respectively; Based on the first weight coefficient and the reference heating comprehensive cost, a first priority operator is constructed, and based on the second weight coefficient and the stability evaluation, a second priority operator is constructed; Based on the first priority operator and the second priority operator, a comprehensive priority value is obtained, and based on the size of the comprehensive priority value, the reference matching relationship data is prioritized.
8. The heating method based on multi-element peak load regulation according to claim 1, characterized in that: Methods for determining the total cost of heating based on the costs associated with heating include: Analyze the difference between the heat demand parameter and the first heat parameter in the power plant operation status data at the same time node, and define the difference as the second heat parameter; Determine the source channel of the second heating parameter, obtain the unit quotation of heating from each source channel, and calculate the second total heating cost corresponding to the second heating parameter in combination with the third heating parameter of each source channel; Obtain the additional power generation beyond the planned power generation in the power plant operation status data, and calculate the equivalent heating loss unit price corresponding to the additional power generation in combination with the power quotation at the same time node; Calculate the basic heating unit price corresponding to the first heating parameter in the power plant operation status data, and combine it with the equivalent heating loss unit price to obtain the first total heating cost corresponding to the first heating parameter; Based on the first total heating cost and the second total heating cost, obtaining the total heating cost; The expression for calculating the total heating cost is: Among them, M is the corresponding value of the total heating cost per unit time, a n is the unit price of heat supply from the nth heat supply source, v 3~n is the third heating parameter of the nth heating source channel, g is the basic heating unit price of the power plant, v2 is the second heating parameter, p2 is the real-time power generation of the power plant, p1 is the planned power generation of the power plant, b is the power generation adjustment constant, and L is the equivalent heating loss unit price adjustment coefficient.
9. The heating method based on multi-element peak load regulation according to claim 1, characterized in that: Based on the test results, the method for determining the reference matching relationship data of the application includes: Obtain real-time heating demand parameters, and based on the corresponding relationship, determine the reference matching relationship data to be called for data; The operating status of the power plant is collected in real time. If the operating status of the power plant collected in real time is consistent with the operating status of the power plant expressed in the reference matching relationship data, the reference matching relationship data is retained.
10. A heating system based on multi-element peak load regulation, characterized in that: include: The first module is used to analyze historical data and filter out the original matching relationship data between heating demand parameters and power plant operation status; The second module is used to determine the heating related costs corresponding to the original matching relationship data based on the time node to which the original matching relationship data belongs, and determine the original heating total cost based on the heating related costs; The third module is used to dynamically adjust the power plant operation status in the original matching relationship data based on the heating demand parameter, generate a number of reference matching relationship data, and calculate the total reference heating cost of each reference matching relationship data based on the heating-related cost corresponding to the original matching relationship data; The fourth module is used to eliminate reference matching relationship data based on the stability requirements of the power plant's operating status, and to prioritize the remaining reference matching relationship data based on the reference total heating cost and the stability characteristics of the power plant's operating status, to test several reference matching relationship data with the highest ranking, and to determine the reference matching relationship data to be retained based on the test results.