Aerial work platform and system

By designing a detachable aerial work platform, using adjustable wall connecting parts and fence structures, the problems of high cost and long cycle of setting up a high aerial work platform in the existing technology are solved, and rapid construction and flexible adjustment are achieved, suitable for a variety of purposes Construction scenario.

CN118958640APending Publication Date: 2024-11-15CHINA CONSTR THIRD BUREAU GRP (SHENZHEN) CO LTD
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202411318502.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-20
Publication Date
2024-11-15

AI Technical Summary

Technical Problem

During the construction process, when the floor-standing scaffolding or cantilever frame is set up in the prior art for supporting molds and peripheral protection, it is costly, long cycles and inconvenient for turnover, making it difficult to meet the flexible needs of the aerial working platform.

Method used

A high-altitude working platform is designed, including a detachable connecting frames and fences. By assembling the fences on the ground and adjusting the spacing of the connecting walls, a platform capable of air operations is formed without the need to set up additional floor-standing scaffolding or cantilever structures.

Benefits of technology

It realizes the rapid construction and flexible adjustment of the aerial working platform, reduces construction costs and time, improves operating efficiency and safety, and is suitable for exterior wall construction and air conditioning installation and other scenarios.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118958640A_ABST
    Figure CN118958640A_ABST
Patent Text Reader

Abstract

The invention discloses an aerial work platform and system, and relates to the technical field of aerial work platforms. The aerial work platform comprises a first connecting frame, a second connecting frame and a third connecting frame, the first connecting frame comprises a first wall connecting piece and a first fence, and the first fence is detachably connected to the first wall connecting piece; the second connecting frame comprises a second wall connecting piece and a second fence, the second fence is detachably connected to the second wall connecting piece, and the first wall connecting piece and the second wall connecting piece are arranged in a spaced mode in the first direction; and the third connecting frame is connected with the first wall connecting piece and the second wall connecting piece. The aerial work platform can be built without depending on a floor type scaffold or a cantilever structure, and the application range of the aerial work platform is widened.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of aerial work platforms, and in particular to an aerial work platform and system. Background Art

[0002] At present, when adding new structures outside the already constructed structures (gables, air-conditioning floating panels), it is necessary to set up ground-based scaffolding or cantilever frames for formwork support and peripheral protection. For construction, the cost of setting up the frame is high, the cycle is long, and it is inconvenient to turn around. Summary of the invention

[0003] In view of this, the present application provides an aerial work platform and system, the purpose of which is to solve one of the technical problems in the prior art.

[0004] To achieve the above objectives, the technical solutions adopted in this application are as follows:

[0005] In a first aspect, an embodiment of the present application provides an aerial work platform, comprising:

[0006] A first connecting frame, comprising a first wall connecting member and a first fence, wherein the first fence is detachably connected to the first wall connecting member;

[0007] A second connecting frame includes a second wall connecting member and a second fence, wherein the second fence is detachably connected to the second wall connecting member, and the first wall connecting member and the second wall connecting member are spaced apart along a first direction;

[0008] The third connecting frame connects the first wall connecting member and the second wall connecting member.

[0009] In one embodiment of the first aspect, the first wall connecting member comprises:

[0010] First vertical board;

[0011] A second vertical plate, wherein the first vertical plate and the second vertical plate are spaced apart along a second direction;

[0012] a first transverse plate connected to ends of the first vertical plate and the second vertical plate;

[0013] A second transverse plate is connected to an end of the second vertical plate away from the first transverse plate, the second transverse plate is arranged away from the first vertical plate, and the first direction is perpendicular to the second direction.

[0014] In one embodiment of the first aspect, the first fence comprises:

[0015] First crossbar;

[0016] a second crossbar, wherein the first crossbar and the second crossbar are spaced apart along a third direction, and the first direction, the second direction and the third direction are perpendicular to each other;

[0017] A first vertical rod, a second vertical rod and a third vertical rod are arranged in sequence along the second direction at intervals, the first vertical rod is detachably connected to the second vertical board, the second vertical rod and the third vertical rod are respectively detachably connected to the second horizontal board, the first vertical rod is respectively connected to the first horizontal rod and the second horizontal rod; the second vertical rod is respectively connected to the first horizontal rod and the second horizontal rod; the third vertical rod is respectively connected to the first horizontal rod and the second horizontal rod.

[0018] In one embodiment of the first aspect, the first connecting frame further includes:

[0019] a first diagonal member, the first diagonal member connecting the first transverse plate and the second transverse plate;

[0020] A second diagonal member is provided, wherein the second diagonal member connects an end of the second transverse plate away from the second vertical plate and the building body.

[0021] In one embodiment of the first aspect, the second wall connecting member comprises:

[0022] a third vertical plate and a fourth vertical plate, wherein the third vertical plate and the fourth vertical plate are arranged at intervals along the second direction;

[0023] a third transverse plate connected to ends of the third vertical plate and the fourth vertical plate;

[0024] A fourth transverse plate is connected to an end of the third vertical plate away from the fourth transverse plate, and the second transverse plate is arranged away from the first vertical plate.

[0025] In one embodiment of the first aspect, the second fence is connected to the fourth horizontal board, and the second fence includes:

[0026] The third crossbar;

[0027] a fourth cross bar, wherein the third cross bar and the fourth cross bar are spaced apart along the third direction, and the third cross bar and the fourth cross bar are spaced apart from the fourth vertical plate;

[0028] The fourth vertical rod and the fifth vertical rod are arranged in sequence along the second direction at intervals, the fourth vertical rod is detachably connected to the fourth vertical board, the fifth vertical rod is detachably connected to the fourth horizontal board, the fourth vertical rod is respectively connected to the third horizontal rod and the end of the fourth horizontal rod away from the fourth vertical board; the fifth vertical rod is respectively connected to the third horizontal rod and the fourth horizontal rod.

[0029] In one embodiment of the first aspect, the aerial work platform also includes a fourth connecting frame, the fourth connecting frame connects the first fence and the second fence, the third connecting frame and the fourth connecting frame are both arranged along the second direction, and the third connecting frame and the fourth connecting frame are spaced apart along the third direction.

[0030] In one embodiment of the first aspect, the fourth connecting frame is detachably connected to the first fence and the second fence respectively.

[0031] In one embodiment of the first aspect, the third connecting frame connects the second transverse plate and the fourth transverse plate, and the fourth connecting frame is respectively connected to ends of the third vertical rod and the fifth vertical rod away from the third connecting frame.

[0032] In a second aspect, an embodiment of the present application further provides an aerial work platform system, comprising the aerial work platform in any of the above embodiments.

[0033] Compared with the prior art, the beneficial effects of the present application are as follows: the present application proposes an aerial work platform, including a first connecting frame, a second connecting frame and a third connecting frame, the first connecting frame including a first wall connecting member and a first fence, the first fence being detachably connected to the first wall connecting member; the second connecting frame including a second wall connecting member and a second fence, the second fence being detachably connected to the second wall connecting member, the first wall connecting member and the second wall connecting member being spaced apart along a first direction; and the third connecting frame connecting the first wall connecting member and the second wall connecting member. By setting up the first fence being detachably connected to the first wall connecting member and the second fence being detachably connected to the second wall connecting member, when building the aerial work platform, the first fence and the second fence are first assembled on the first wall connecting member and the second wall connecting member respectively on the ground, and then the first wall connecting member and the second wall connecting member are connected to the building cavity, the distance between the first wall connecting member and the second wall connecting member can be adjusted according to the actual main structure of the building, and finally the third connecting frame is set up on the first wall connecting member and the second wall connecting member, so as to form a work platform capable of aerial work, without the need to set up a ground-based scaffold or cantilever structure. BRIEF DESCRIPTION OF THE DRAWINGS

[0034] In order to more clearly illustrate the technical solutions of the embodiments of the present application, the drawings required for use in the embodiments will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present application and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without paying creative work.

[0035] Figure 1 A schematic diagram of the structure of an aerial work platform in some embodiments of the present application is shown;

[0036] Figure 2 A schematic diagram of the structure of a first connecting frame in some embodiments of the present application is shown;

[0037] Figure 3 A schematic diagram of the structure of the second connecting frame in some embodiments of the present application is shown;

[0038] Figure 4 A schematic diagram of the structure of a third connecting frame in some embodiments of the present application is shown;

[0039] Figure 5 A schematic structural diagram of a fourth connecting frame in some embodiments of the present application is shown.

[0040] Main component symbols: 100- aerial work platform; 110- first connecting frame; 111- first wall connecting member; 1111- first vertical plate; 1112- second vertical plate; 1113- first horizontal plate; 1114- second horizontal plate; 112- first fence; 1121- first horizontal bar; 1122- second horizontal bar; 1123- first vertical bar; 1124- second vertical bar; 1125- third vertical bar; 113- first inclined member; 114- second inclined member Pulling member; 120-second connecting frame; 121-second wall connecting member; 1211-third vertical plate; 1212-fourth vertical plate; 1213-third horizontal plate; 1214-fourth horizontal plate; 122-second fence; 1221-third horizontal bar; 1222-fourth horizontal bar; 1223-fourth vertical bar; 1224-fifth vertical bar; 130-third connecting frame; 140-fourth connecting frame; D1-first direction; D2-second direction; D3-third direction. DETAILED DESCRIPTION

[0041] The embodiments of the present application are described in detail below, and examples of the embodiments are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are only used to explain the present application, and cannot be understood as limiting the present application.

[0042] In the description of the present application, it should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise", "axial", "radial", "circumferential" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present application and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present application.

[0043] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of this application, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.

[0044] In this application, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.

[0045] In the present application, unless otherwise clearly specified and limited, a first feature being “above” or “below” a second feature may mean that the first and second features are in direct contact, or the first and second features are in indirect contact through an intermediate medium. Moreover, a first feature being “above”, “above”, and “above” a second feature may mean that the first feature is directly above or obliquely above the second feature, or simply means that the first feature is higher in level than the second feature. A first feature being “below”, “below”, and “below” a second feature may mean that the first feature is directly below or obliquely below the second feature, or simply means that the first feature is lower in level than the second feature.

[0046] like Figure 1 As shown, an embodiment of the present application provides an aerial work platform 100 , including a first connecting frame 110 , a second connecting frame 120 and a third connecting frame 130 .

[0047] Among them, the first connecting frame 110 includes a first wall connecting member 111 and a first fence 112, and the first fence 112 can be detachably connected to the first wall connecting member 111; the second connecting frame 120 includes a second wall connecting member 121 and a second fence 122, and the second fence 122 can be detachably connected to the second wall connecting member 121, and the first wall connecting member 111 and the second wall connecting member 121 are arranged at intervals along the first direction D1; the third connecting frame 130 connects the first wall connecting member 111 and the second wall connecting member 121.

[0048] By setting up the first fence 112 to be detachably connected to the first wall connecting member 111 and the second fence 122 to be detachably connected to the second wall connecting member 121, when building the aerial work platform 100, first assemble the first fence 112 and the second fence 122 on the ground respectively on the first wall connecting member 111 and the second wall connecting member 121, and then connect the first wall connecting member 111 and the second wall connecting member 121 to the building cavity, and the distance between the first wall connecting member 111 and the second wall connecting member 121 can be adjusted according to the actual main structure of the building, and finally, set the third connecting frame 130 on the first wall connecting member 111 and the second wall connecting member 121 to form a work platform capable of performing aerial operations.

[0049] The assembly process of the aerial work platform 100 does not require the construction of additional ground-based scaffolding or cantilever structures, making the aerial work platform 100 of the present application suitable for construction processes such as exterior wall construction and air-conditioning outdoor unit installation.

[0050] In some embodiments, the first wall connecting member 111 includes a first vertical plate 1111 , a second vertical plate 1112 , a first horizontal plate 1113 , and a second horizontal plate 1114 .

[0051] The first vertical plate 1111 and the second vertical plate 1112 are spaced apart along the second direction D2, and the first horizontal plate 1113 is connected to the ends of the first vertical plate 1111 and the second vertical plate 1112, so that the first vertical plate 1111, the second vertical plate 1112 and the first horizontal plate 1113 are connected to form an inverted U-shaped structure, which facilitates the first wall connecting member 111 to be quickly connected to the window sill of the building.

[0052] It should be understood that the spacing between the first vertical plate 1111 and the second vertical plate 1112 is adjustable, so that the first wall connecting member 111 can be connected to walls of different thicknesses.

[0053] Exemplarily, a waist-shaped hole is opened on the first horizontal plate 1113, and the waist-shaped hole is arranged along the first direction D1. The first vertical plate 1111 is connected to the first horizontal plate 1113 by bolts, and the bolts are arranged in the waist-shaped hole. The second vertical plate 1112 is welded and fixed to the first horizontal plate 1113. In this way, the efficiency of installing the first wall connecting member 111 and the wall is accelerated by only moving the first vertical plate 1111 to change the distance between the first vertical plate 1111 and the second vertical plate 1112.

[0054] The second transverse plate 1114 is connected to the end of the second vertical plate 1112 away from the first transverse plate 1113. The second transverse plate 1114 is set away from the first vertical plate 1111, so that the first wall connecting member 111 is stepped as a whole. In this way, after the first wall connecting member 111 is fixed to the wall, the second transverse plate 1114 extends to the side away from the wall, which is convenient for the staff to step down from the wall onto the second transverse plate 1114 to assemble the subsequent third connecting frame 130 and the fourth connecting frame 140.

[0055] It should be understood that when the first wall connecting member 111 is connected to the wall, the first vertical plate 1111 and the first horizontal plate 1113 are both stably connected to the building wall through the fixed connection structure.

[0056] The first wall connecting member 111 is a steel member, and thus has sufficient strength to achieve a stable connection with the wall. In addition, the strong rigidity of the steel member is utilized to enable the staff to move safely on the second cross plate 1114 .

[0057] like Figure 1 and Figure 2 The first vertical plate 1111, the second vertical plate 1112, the first horizontal plate 1113 and the second horizontal plate 1114 are all rectangular plates. The second horizontal plate 1114 is for workers to walk and move, so the area of ​​the second horizontal plate 1114 is relatively large, and the second horizontal plate 1114 is also a steel structure.

[0058] In some embodiments, the second horizontal plate 1114 includes a rectangular frame and a plurality of steel rods arranged at intervals in the rectangular frame. Such a structure enables the second horizontal plate 1114 to retain rigidity for workers to walk and move, is not easily deformed, and can also reduce the deadweight of the second horizontal plate 1114, making the connection between the first wall connecting member 111 and the wall more stable.

[0059] It should be noted that the first direction D1 is the length direction of the aerial work platform 100, the second direction D2 is the width direction of the aerial work platform 100, and the third direction D3 is the height direction of the aerial work platform 100. The first direction D1, the second direction D2 and the third direction D3 are perpendicular to each other.

[0060] In some embodiments, Figure 2 As shown, the first fence 112 includes a first horizontal bar 1121, a second horizontal bar 1122, and a first vertical bar 1123, a second vertical bar 1124 and a third vertical bar 1125 which are sequentially arranged at intervals along the second direction D2.

[0061] The first cross bar 1121 and the second cross bar 1122 are arranged at intervals along the third direction D3, the first vertical bar 1123 is detachably connected to the second vertical plate 1112, the second vertical bar 1124 and the third vertical bar 1125 are detachably connected to the second cross plate 1114, the first vertical bar 1123 is respectively connected to the first cross bar 1121 and the second cross bar 1122; the second vertical bar 1124 is respectively connected to the first cross bar 1121 and the second cross bar 1122; the third vertical bar 1125 is respectively connected to the first cross bar 1121 and the second cross bar 1122.

[0062] The second horizontal plate 1114 is provided with three connection parts on one side away from the second wall connecting member 121 , which are respectively connected to the first vertical rod 1123 , the second vertical rod 1124 and the third vertical rod 1125 .

[0063] For example, Figure 2 As shown, a through hole is provided on the connection part, and an elastic protrusion is provided at the bottom of the first vertical rod 1123. By connecting the elastic protrusion and the through hole, the first fence 112 and the second horizontal plate 1114 can be detachably connected. In this way, the first horizontal rod 1121, the second horizontal rod 1122 and the first vertical rod 1123 can be welded to speed up the assembly efficiency of the first fence 112 and the first wall connecting member 111.

[0064] Exemplarily, the bottom of the first vertical rod 1123 and the connecting portion are socketed to speed up the assembly efficiency of the first fence 112 and the first wall connecting member 111.

[0065] Exemplarily, a threaded hole is provided on the connection part, and a threaded joint is provided at the bottom of the first vertical rod 1123, and a detachable connection is achieved by threading the first vertical rod 1123 and the connection part. In this way, the connection between the first fence 112 and the second horizontal board 1114 is more stable.

[0066] By providing the first crossbar 1121, the second crossbar 1122, the first vertical bar 1123, the second vertical bar 1124 and the third vertical bar 1125, the second fence 122 has sufficient strength to play a protective role, and can also reduce the deadweight of the first fence 112, so that the connection between the first connecting frame 110 and the wall is more stable. It can also reduce the weight of the overall structure of the first connecting frame 110, so that one or two workers can easily assemble the aerial work platform 100.

[0067] In some embodiments, Figure 1 and Figure 2 As shown, the first connecting frame 110 further includes a first diagonal brace 113 and a second diagonal brace 114 .

[0068] The first inclined brace 113 connects the first transverse plate 1113 and the second transverse plate 1114 , so that the pressure on the second transverse plate 1114 is transferred to the wall through the first transverse plate 1113 , thereby improving the stability of the first connecting frame 110 .

[0069] Exemplarily, the first diagonal member 113 is a steel cable, or the first diagonal member 113 is a steel plate.

[0070] The second inclined brace 114 connects the end of the second transverse plate 1114 away from the second vertical plate 1112 and the building body. Exemplarily, the first inclined brace 113 is a steel cable, which can be more flexibly set to a fixed point according to the wall structure.

[0071] In some embodiments, Figure 1 and Figure 3As shown, the second wall connecting member 121 includes a third vertical plate 1211 , a fourth vertical plate 1212 , a third horizontal plate 1213 and a fourth horizontal plate 1214 .

[0072] The third vertical plate 1211 and the fourth vertical plate 1212 are spaced apart along the second direction D2, and the third horizontal plate 1213 is connected to the ends of the third vertical plate 1211 and the fourth vertical plate 1212, so that the third vertical plate 1211, the fourth vertical plate 1212 and the third horizontal plate 1213 are connected to form an inverted U-shaped structure, which facilitates the second wall connecting member 121 to be quickly connected to the window sill of the building.

[0073] It should be understood that the spacing between the third vertical plate 1211 and the fourth vertical plate 1212 is adjustable, so that the second wall connecting member 121 can be connected to walls of different thicknesses.

[0074] Exemplarily, a waist-shaped hole is opened on the third horizontal plate 1213, and the waist-shaped hole is arranged along the first direction D1. The third vertical plate 1211 is connected to the third horizontal plate 1213 by bolts, and the bolts are arranged in the waist-shaped hole. The fourth vertical plate 1212 is welded and fixed to the second horizontal plate 1114. In this way, the efficiency of installing the second wall connecting member 121 and the wall is accelerated by only moving the third vertical plate 1211 to change the distance between the third vertical plate 1211 and the fourth vertical plate 1212.

[0075] The fourth horizontal plate 1214 is connected to the end of the third vertical plate 1211 away from the fourth horizontal plate 1214, the second horizontal plate 1114 is set away from the first vertical plate 1111, the fourth horizontal plate 1214 is connected to the end of the fourth vertical plate 1212 away from the first horizontal plate 1113, and the second horizontal plate 1114 is set away from the first vertical plate 1111, so that the second wall connecting member 121 is stepped as a whole, and the second horizontal plate 1114 and the fourth horizontal plate 1214 are used as fulcrums for setting up the third connecting frame 130.

[0076] In this way, when the first wall connecting member 111 and the second wall connecting member 121 are respectively installed and connected to the wall, by adjusting the distance between the second cross plate 1114 and the second cross plate 1114 according to the actual wall structure, the length of the aerial work platform 100 can be set as needed, thereby improving the applicable scenarios of the aerial work platform 100.

[0077] In some embodiments, Figure 1 and Figure 3 As shown, the second fence 122 is connected to the fourth horizontal board 1214, and the second fence 122 includes a third horizontal bar 1221, a fourth horizontal bar 1222, a fourth vertical bar 1223 and a fifth vertical bar 1224 which are sequentially arranged in the second direction D2.

[0078] The third cross bar 1221 and the fourth cross bar 1222 are spaced apart along the third direction D3, and the third cross bar 1221 and the fourth cross bar 1222 are spaced apart from the fourth vertical plate 1212; the fourth vertical bar 1223 is detachably connected to the fourth vertical plate 1212, the fifth vertical bar 1224 is detachably connected to the fourth cross bar 1214, the fourth vertical bar 1223 is respectively connected to the ends of the third cross bar 1221 and the fourth cross bar 1222 away from the fourth vertical plate 1212; the second vertical bar 1124 is respectively connected to the third cross bar 1221 and the fourth cross bar 1222.

[0079] In this way, the staff can assemble the second fence 122 on the second wall connecting member 121 on the ground. At the same time, the second fence 122 is formed by splicing a plurality of rod-like structures, which plays a protective role while reducing its own weight, so that one or two staff members can complete the assembly of the second connecting frame 120 and the wall, thereby improving the assembly efficiency of the aerial work platform 100 and the safety of the assembly operation.

[0080] In some embodiments, the second connecting frame 120 further includes a third diagonal member (not shown).

[0081] The third inclined brace connects the end of the fourth horizontal plate 1214 away from the fourth vertical plate 1212 and the building body. Exemplarily, the third inclined brace is a steel cable, which can be more flexibly set with a fixing point according to the wall structure.

[0082] In some embodiments, Figure 1 , Figure 4 and Figure 5 As shown, the aerial work platform 100 also includes a fourth connecting frame 140, which connects the first fence 112 and the second fence 122. The third connecting frame 130 and the fourth connecting frame 140 are both arranged along the second direction D2, and the third connecting frame 130 and the fourth connecting frame 140 are spaced apart along the third direction D3.

[0083] In some embodiments, the third connecting frame 130 includes a rectangular frame and a plurality of steel rods arranged at intervals in the rectangular frame. Such a structure enables the third connecting frame 130 to retain rigidity for workers to walk and move, is not easy to deform, and can also reduce the weight of the third connecting frame 130 and reduce the difficulty of assembly.

[0084] In some embodiments, the rectangular frame and steel rods in the third connecting frame 130 are a telescopic sleeve rod structure, so that the length of the third connecting frame 130 in the first direction D1 can be adjusted, which is convenient for storage and makes the length of the aerial work platform 100 adjustable, thereby adjusting the applicable scenarios of the aerial work platform 100.

[0085] In some embodiments, the fourth connecting frame 140 is detachably connected to the first fence 112 and the second fence 122. Further, the third connecting frame 130 connects the second horizontal board 1114 and the fourth horizontal board 1214, and the fourth connecting frame 140 is respectively connected to the ends of the third vertical rod 1125 and the fifth vertical rod 1224 away from the third connecting frame.

[0086] The fourth connecting frame 140 is arranged above the third connecting frame 130 to play a protective role. The fourth fence is formed by splicing a plurality of rod-shaped structures, which plays a protective role while reducing the deadweight, so that one or two workers can complete the assembly of the second connecting frame 120 and the wall, thereby improving the assembly efficiency of the aerial work platform 100 and the safety of the assembly operation.

[0087] The present application also provides an aerial work platform 100 system, including the aerial work platform 100 in any of the above embodiments. Therefore, it has all the beneficial effects of the aerial work platform 100 in any of the above embodiments, which will not be described one by one here.

[0088] In some embodiments, the aerial work platform 100 system includes a suspension mechanism and an aerial work platform 100. The suspension mechanism is used to be fixedly installed on the top of a building, and the aerial work platform 100 is connected to the suspension mechanism through a sling, and the suspension mechanism is responsible for suspending the aerial work platform 100.

[0089] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "example", "specific example", or "some examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present application. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, without contradiction.

[0090] Although the embodiments of the present application have been shown and described above, it can be understood that the above embodiments are exemplary and cannot be understood as limitations on the present application. Ordinary technicians in the field can change, modify, replace and modify the above embodiments within the scope of the present application.

Claims

1. An aerial work platform, characterized in that: include: A first connecting frame, comprising a first wall connecting member and a first fence, wherein the first fence is detachably connected to the first wall connecting member; A second connecting frame includes a second wall connecting member and a second fence, wherein the second fence is detachably connected to the second wall connecting member, and the first wall connecting member and the second wall connecting member are spaced apart along a first direction; The third connecting frame connects the first wall connecting member and the second wall connecting member.

2. The aerial work platform according to claim 1, characterized in that: The first wall connecting member comprises: First vertical board; A second vertical plate, wherein the first vertical plate and the second vertical plate are spaced apart along a second direction; a first transverse plate connected to ends of the first vertical plate and the second vertical plate; A second transverse plate is connected to an end of the second vertical plate away from the first transverse plate, the second transverse plate is arranged away from the first vertical plate, and the first direction is perpendicular to the second direction.

3. The aerial work platform according to claim 2, characterized in that: The first fence comprises: First crossbar; a second crossbar, wherein the first crossbar and the second crossbar are spaced apart along a third direction, and the first direction, the second direction and the third direction are perpendicular to each other; A first vertical rod, a second vertical rod and a third vertical rod are arranged in sequence along the second direction at intervals, the first vertical rod is detachably connected to the second vertical board, the second vertical rod and the third vertical rod are respectively detachably connected to the second horizontal board, the first vertical rod is respectively connected to the first horizontal rod and the second horizontal rod; the second vertical rod is respectively connected to the first horizontal rod and the second horizontal rod; the third vertical rod is respectively connected to the first horizontal rod and the second horizontal rod.

4. The aerial work platform according to claim 2, characterized in that: The first connecting frame also includes: a first diagonal member, the first diagonal member connecting the first transverse plate and the second transverse plate; A second diagonal member is provided, wherein the second diagonal member connects an end of the second transverse plate away from the second vertical plate and the building body.

5. The aerial work platform according to claim 3, characterized in that: The second wall connecting member comprises: a third vertical plate and a fourth vertical plate, wherein the third vertical plate and the fourth vertical plate are arranged at intervals along the second direction; a third transverse plate connected to ends of the third vertical plate and the fourth vertical plate; A fourth transverse plate is connected to an end of the third vertical plate away from the fourth transverse plate, and the second transverse plate is arranged away from the first vertical plate.

6. The aerial work platform according to claim 5, characterized in that: The second fence is connected to the fourth horizontal board, and the second fence includes: The third crossbar; a fourth crossbar, wherein the third crossbar and the fourth crossbar are spaced apart along the third direction, and the third crossbar and the fourth crossbar are spaced apart from the fourth vertical plate; The fourth vertical rod and the fifth vertical rod are arranged in sequence along the second direction at intervals, the fourth vertical rod is detachably connected to the fourth vertical board, the fifth vertical rod is detachably connected to the fourth horizontal board, the fourth vertical rod is respectively connected to the third horizontal rod and the end of the fourth horizontal rod away from the fourth vertical board; the fifth vertical rod is respectively connected to the third horizontal rod and the fourth horizontal rod.

7. The aerial work platform according to claim 6, characterized in that: The aerial work platform also includes a fourth connecting frame, which connects the first fence and the second fence. The third connecting frame and the fourth connecting frame are both arranged along the second direction, and the third connecting frame and the fourth connecting frame are spaced apart along the third direction.

8. The aerial work platform according to claim 7, characterized in that: The fourth connecting frame is detachably connected to the first fence and the second fence respectively.

9. The aerial work platform according to claim 7, characterized in that: The third connecting frame connects the second transverse plate and the fourth transverse plate, and the fourth connecting frame is respectively connected to the ends of the third vertical rod and the fifth vertical rod away from the third connecting frame.

10. An aerial work platform system, characterized in that: An aerial work platform comprising any one of claims 1 to 9.

Citation Information

Patent Citations

  • Mobilizable overhanging type operation platform and building construction system

    CN206308990U

  • Hang basket and bridge construction protection and hang basket

    CN208586516U

  • Movable bearing device for high-altitude construction based on steel structure

    CN217151155U

  • Hanging device for rope working

    JP2001227154A