Building engineering pile foundation construction punching equipment

By introducing servo motors and pressure sensors into the pile foundation construction drilling equipment for positioning, and using fixing frames and pumps for cleaning, the problems of difficulty and large errors after drilling are solved, and the accuracy of drilling is improved and efficiency.

CN118958860APending Publication Date: 2024-11-15CHINA CONSTR EIGHT ENG DIV CORP LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411248408.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-06
Publication Date
2024-11-15

AI Technical Summary

Technical Problem

The existing foundation pile drilling equipment cannot effectively clean the drilling body after drilling, and the error in the drilling position is large, which affects efficiency and quality.

Method used

A construction pile foundation drilling equipment for construction engineering including a positioning mechanism and a cleaning mechanism is designed, and the precise positioning of the spiral drilling device is achieved using servo motors and pressure sensors, and the cleaning of the drilling device is achieved through a fixture and a pump.

Benefits of technology

It improves the accuracy and cleaning efficiency of hole drilling, reduces the error of manual guidance by workers, and improves the efficiency and quality of engineering pile foundation construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118958860A_ABST
    Figure CN118958860A_ABST
Patent Text Reader

Abstract

The invention discloses constructional engineering pile foundation construction punching equipment, and relates to the technical field of constructional engineering, the constructional engineering pile foundation construction punching equipment comprises a punching equipment body, a water storage tank is fixedly installed on the surface of the punching equipment body, and a first supporting plate and a fixing block are fixedly installed on the back face of the water storage tank; a second supporting plate is fixedly installed on the side, close to the first supporting plate, of the punching equipment body, a water suction pump is fixedly installed on a fixing block, a water suction pipe is fixedly communicated between the input end of the water suction pump and the water storage tank, and the output end of the water suction pump is fixedly communicated with a water outlet pipe. The high-precision, high-efficiency and high-quality pile foundation construction punching effect is achieved, and the problems that a punching drill body cannot be cleaned after punching, a pile casing is installed at the punching position of existing foundation pile punching equipment in advance, a worker needs to command the pile casing, the error is large, and the working efficiency is high are solved. And meanwhile, the punching efficiency and quality can be influenced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building engineering, and in particular to a drilling device for pile foundation construction of building engineering. Background Art

[0002] A construction project refers to an engineering entity formed by the construction of various types of building structures and their ancillary facilities and the installation of supporting lines, pipelines and equipment. Among them, "building structures" refer to projects with roofs, beams, columns, walls and foundations, and can form internal spaces to meet people's needs for production, residence, study and public activities. Before construction, pile foundations need to be poured to ensure the stability of the building, and drilling is required before pouring the foundation piles, so drilling equipment is used.

[0003] The patent document with publication number CN214062849U discloses a pile foundation drilling equipment for green engineering construction, wherein an upper plate body is installed at the upper ends of two brackets, and ground-insertion rods are movably connected to the front and rear sides of the bottoms of the two brackets, and a foot pedal is connected to the upper end of the ground-insertion rod. A mounting rod is connected to the middle and upper end of the mounting plate body, and a rack is installed on the side wall of the mounting rod, and the rack is meshed with a gear. The gear is installed on the shaft of a driving motor, and the driving motor is installed on the upper plate body. Guide rods are installed on both upper ends of the mounting plate body, and the guide rods are movably connected in the guide holes of the upper plate body. A hydraulic motor is installed at the bottom of the mounting plate body, and the rotating shaft of the hydraulic motor is connected to the upper end of the drilling body through a connector, and a reinforcing frame is installed on the outer side of the two brackets.

[0004] However, the above invention has the following shortcomings: the drilling drill body cannot be cleaned after drilling, and the existing pile drilling equipment installs a casing in advance at the drilling position, and requires workers to direct next to the casing, which not only has a large error, but also affects the drilling efficiency and quality, so there are certain limitations. Summary of the invention

[0005] The object of the present invention is to provide a drilling device for pile foundation construction in a construction project to solve the problems raised in the above-mentioned background technology. The positioning mechanism provided can easily and accurately position the spiral punch and improve the accuracy of drilling. The cleaning mechanism provided can clean the soil in the spiral punch and improve the cleaning efficiency.

[0006] The technical solution of the present invention is: a drilling equipment for pile foundation construction of a construction project, comprising a drilling equipment body, a water tank is fixedly installed on the surface of the drilling equipment body, a first support plate and a fixed block are respectively fixedly installed on the back of the water tank, a second support plate is fixedly installed on the side of the drilling equipment body close to the first support plate, a water pump is fixedly installed on the fixed block, a water pump is fixedly connected between the input end of the water pump and the water tank by a water pumping pipe, and the output end of the water pump is fixedly connected with a water outlet pipe, and the water outlet pipes are fixedly passed through the first support plate and the second support plate, and also include a positioning mechanism and a cleaning mechanism.

[0007] The positioning mechanism includes a servo motor 1 fixedly installed inside the punching device body.

[0008] The cleaning mechanism comprises a fixing frame.

[0009] Preferably, the output end of the servo motor is fixedly connected to a first threaded shaft, a rectangular block is fixedly installed inside the punching device body, the rectangular block is threadedly connected to the first threaded shaft, a moving block is fixedly installed on the upper surface of the rectangular block, and the moving block is slidably matched with the punching device body.

[0010] Preferably, a sliding groove is provided on the left side of the moving block, a sliding block is slidably installed inside the sliding groove, and a moving frame is fixedly connected to the left side of the sliding block.

[0011] Preferably, a limit frame is fixedly installed on one side of the movable frame, and a sliding plate is slidably installed on the limit frame. A second threaded shaft is threadedly connected between the sliding plate and the movable block, a rubber pad is arranged between the bottom end of the second threaded shaft and the upper surface of the movable block, and a rotating plate is fixedly installed on the top end of the second threaded shaft.

[0012] Preferably, a servo motor 2 is arranged above the moving frame, a fixing seat is fixedly connected to the outer surface of the servo motor 2, and a bottom surface of the fixing seat is fixedly connected to the upper surface of the moving frame.

[0013] Preferably, the inner wall of the movable frame is rotatably connected to a first rotating shaft, and one end of the first rotating shaft is fixedly connected to the output shaft of the second servo motor.

[0014] Preferably, a first connecting plate is fixedly installed on the outer surface of the first rotating shaft, a camera and a pressure sensor are fixedly installed on the inner wall of the first connecting plate, a pair of force springs are fixedly installed on the side of the first connecting plate close to the pressure sensor, and a force plate is fixedly installed on one end of the pair of force springs.

[0015] Preferably, the fixing frame is fixedly mounted on the surface of the first connecting plate, the inner wall of the fixing frame is rotatably connected to a second rotating shaft, the outer surface of the second rotating shaft is fixedly connected to a cleaning plate, a limiting plate is fixedly mounted on one side of the fixing frame, and the front side of the cleaning plate is in contact with the back side of the limiting plate.

[0016] Preferably, the back side of the water storage tank is fixedly connected with a water injection pipe, and the outer surface of the water injection pipe is clamped with a water retaining block.

[0017] The present invention provides a construction engineering pile foundation construction drilling equipment through improvement, which has the following improvements and advantages compared with the prior art:

[0018] First, the present invention is provided with a servo motor 1, which drives the first threaded shaft to rotate. The threaded connection is used to drive the rectangular block to move by rotating the first threaded shaft, thereby driving the moving block and the equipment above the moving block to move outward, and the sliding groove and the sliding block are used to move the moving frame, so as to facilitate adjustment according to the size of the casing. At this time, the servo motor 2 can be used to drive the first rotating shaft to rotate, thereby driving the first connecting plate and the pressure sensor fixed on the inner wall of the first connecting plate to rotate, so that the pressure sensor can face the casing, and then slowly reverse to allow the pressure sensor and the casing to contact each other. The data fed back by the pressure sensor can determine that the spiral hole puncher on the punching equipment body is directly above the center of the casing, thereby eliminating the problem of workers cooperating with guidance, improving the efficiency of the spiral hole puncher calibration, and thus improving the efficiency and quality of drilling in engineering pile foundation construction.

[0019] Secondly, the present invention is provided with a fixing frame, and the second rotating shaft rotatably connected to the inner wall of the fixing frame can drive the cleaning plate to be perpendicular to the first connecting plate, thereby ensuring that the cleaning plate can extend into the inverted spiral punch. When the spiral punch rotates and rises, the soil in the spiral punch can be cleaned, thereby effectively avoiding the problem that the soil is easily dispersed to the surroundings during the cleaning process and is not easy to be processed centrally. In addition, the spiral punch can be cleaned through the water outlet pipe by utilizing the water storage tank and the water pump, thereby improving the cleaning effect. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] In order to more clearly illustrate the specific implementation methods of the present invention or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0021] Figure 1 A schematic diagram of the overall first-view structure provided by the present invention;

[0022] Figure 2 A schematic diagram of the positioning mechanism structure provided by the present invention;

[0023] Figure 3 A schematic diagram of the structure of a servo motor provided by the present invention;

[0024] Figure 4 A second structural diagram of a servo motor provided by the present invention;

[0025] Figure 5 A schematic diagram of a partial cross-section structure of the positioning mechanism provided by the present invention;

[0026] Figure 6 A schematic diagram of the structure of the pressure sensor provided by the present invention;

[0027] Figure 7 A schematic diagram of the structure of a second threaded shaft provided by the present invention;

[0028] Figure 8 This is a schematic diagram of the structure of the water pump provided by the present invention.

[0029] Reference numerals:

[0030] 1. Punching device body; 2. Positioning mechanism; 201. Moving block; 202. Second threaded shaft; 203. Moving frame; 204. First threaded shaft; 205. Rectangular block; 206. Servo motor 1; 207. Pressure sensor; 208. Servo motor 2; 209. First connecting plate; 210. Sliding groove; 211. First rotating shaft; 212. Sliding plate; 213. Limiting frame; 214. Sliding block; 215 , force spring; 216, force plate; 217, camera; 3, cleaning mechanism; 301, fixing bracket; 302, second rotating shaft; 303, cleaning plate; 304, limiting plate; 4, water storage tank; 5, fixing seat; 6, rotating plate; 7, rubber pad; 8, second supporting plate; 9, water retaining block; 10, water outlet pipe; 11, first supporting plate; 12, water pump; 13, water pumping pipe; 14, fixing block; 15, water injection pipe. DETAILED DESCRIPTION

[0031] The present invention is described in detail below, and the technical solutions in the embodiments of the present invention are clearly and completely described. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0032] The present invention provides a construction engineering pile foundation construction drilling equipment through improvement. The technical solution of the present invention is:

[0033] like Figures 1 to 8As shown, the embodiment of the present invention provides a drilling device for pile foundation construction of a construction project, including a drilling device body 1, a water storage tank 4 is fixedly installed on the surface of the drilling device body 1, a first support plate 11 and a fixed block 14 are fixedly installed on the back of the water storage tank 4, a second support plate 8 is fixedly installed on the side of the drilling device body 1 close to the first support plate 11, a water pump 12 is fixedly installed on the fixed block 14, a water pump 12 is fixedly connected between the input end of the water pump 12 and the water storage tank 4 by a water pumping pipe 13, and the output end of the water pump 12 is fixedly connected to the water outlet. The pipe 10 and the water outlet pipe 10 are fixedly passed through the first support plate 11 and the second support plate 8, and also include a positioning mechanism 2 and a cleaning mechanism 3. Through the water storage tank 4, the spiral puncher after punching can be cleaned by using the water pump 12. The first support plate 11 and the second support plate 8 and the fixing block 14 are convenient for fixing the water outlet pipe 10 and the water pump 12. In addition, the positioning mechanism 2 can improve the accuracy of punching, and the cleaning mechanism 3 is convenient for preliminary cleaning of the spiral puncher to improve the cleaning effect.

[0034] The positioning mechanism 2 includes a servo motor 206 fixedly installed inside the punching device body 1. The servo motor 206 is used to provide a stable power source for the positioning mechanism 2, thereby ensuring the normal operation of the positioning mechanism 2.

[0035] The cleaning mechanism 3 includes a fixing frame 301 . The fixing frame 301 is provided to provide a stable supporting foundation for the cleaning mechanism 3 .

[0036] Furthermore, the output end of the servo motor 206 is fixedly connected to the first threaded shaft 204, and a rectangular block 205 is fixedly installed inside the punching device body 1. The rectangular block 205 and the first threaded shaft 204 are threadedly connected. A moving block 201 is fixedly installed on the upper surface of the rectangular block 205. The moving block 201 and the punching device body 1 are slidingly matched. The servo motor 206 is used to drive the first threaded shaft 204 to rotate, and the rectangular block 205 and the moving block 201 are moved through the threaded connection. The moving block 201 and the punching device body 1 are slidingly matched, so as to assist the movement of the moving block 201.

[0037] Furthermore, a sliding groove 210 is provided on the left side of the moving block 201, and a sliding block 214 is slidably installed inside the sliding groove 210. The left side of the sliding block 214 is fixedly connected to the moving frame 203. The sliding groove 210 is provided to facilitate the sliding of the sliding block 214, thereby moving with the moving frame 203, so as to facilitate adjustment according to the size of the casing diameter, and the sliding groove 210 can also support the sliding block 214, ensuring that the sliding block 214 can be stably fixed with the moving frame 203 in the sliding or fixed state.

[0038] Furthermore, a limit frame 213 is fixedly installed on one side of the moving frame 203, and a sliding plate 212 is slidably installed on the limit frame 213. The sliding plate 212 and the moving block 201 are commonly connected with a second threaded shaft 202 through a thread, and a rubber pad 7 is arranged between the bottom end of the second threaded shaft 202 and the upper surface of the moving block 201, and a rotating plate 6 is fixedly installed on the top of the second threaded shaft 202. The fixedly installed limit frame 213 and the sliding plate 212 facilitate the moving frame 203 to slide to the specified position, and then the second threaded shaft 202 is driven to rotate by the rotating plate 6, so that the sliding plate 212 fixes the limit frame 213, thereby fixing the moving frame 203, and the rubber pad 7 can form a strong adhesion force with other objects. Due to the flexibility of the rubber, the actual contact area is increased, and it is not easy to slide even under a certain external force, thereby improving the stability after fixation.

[0039] As a further solution of the present invention, a servo motor 208 is arranged above the moving frame 203, and the outer surface of the servo motor 208 is fixedly connected with a fixing seat 5, and the bottom surface of the fixing seat 5 is fixedly connected to the upper surface of the moving frame 203. The setting of the fixing seat 5 can support the servo motor 208, thereby ensuring that the servo motor 208 can be more stable when in use.

[0040] Furthermore, the inner wall of the movable frame 203 is rotatably connected to a first rotating shaft 211, one end of the first rotating shaft 211 is fixedly connected to the output shaft of the servo motor 208, and a first connecting plate 209 is fixedly installed on the outer surface of the first rotating shaft 211. The first rotating shaft 211 is driven to rotate by the set servo motor 208, thereby driving the first connecting plate 209 to rotate.

[0041] Furthermore, a camera 217 and a pressure sensor 207 are fixedly installed on the inner wall of the first connecting plate 209, and a pair of force springs 215 are fixedly installed on the side of the first connecting plate 209 close to the pressure sensor 207. A force plate 216 is fixedly installed on one end of the pair of force springs 215. The camera 217 is arranged to facilitate the staff to observe the positions of the pressure sensor 207 and the casing in real time. By using the pressure sensor 207 and the values ​​received from various parts of the pressure sensor 207, it can be determined that the spiral punch on the punching equipment body 1 is directly above the center of the casing. Since the casing is circular, the maximum value of the received pressure is directly above the center of the casing, which avoids the need for workers to cooperate with guidance, thereby reducing errors and improving accuracy.

[0042] Furthermore, the fixing frame 301 is fixedly installed on the surface of the first connecting plate 209, the inner wall of the fixing frame 301 is rotatably connected to the second rotating shaft 302, the outer surface of the second rotating shaft 302 is fixedly connected to the cleaning plate 303, and a limiting plate 304 is fixedly installed on one side of the fixing frame 301, and the front side of the cleaning plate 303 contacts the back side of the limiting plate 304. The setting of the fixing frame 301 can provide stable support for the second rotating shaft 302 and the cleaning plate 303, and the second rotating shaft 302 can rotate with the cleaning plate 303 so that the cleaning plate 303 can be rotated onto the spiral punch, so as to clean the soil in the spiral punch, thereby effectively avoiding the problem that the soil is easily scattered around during the cleaning process and is not easy to be processed centrally.

[0043] Furthermore, a water injection pipe 15 is fixedly connected to the back of the water tank 4, and a water retaining block 9 is clamped on the outer surface of the water injection pipe 15. The water injection pipe 15 can be used to easily add water to the water tank 4. The water retaining block 9 can not only prevent the water in the water tank 4 from splashing out during movement, but also prevent external impurities from entering the water tank 4, thereby clogging the pumping pipe 13 and the outlet pipe 10.

[0044] Specific working principle: After the staff drives the pile driver to the designated position, the servo motor 206 drives the first threaded shaft 204 to rotate, thereby driving the rectangular block 205 and the moving block 201 to move, so that the positioning mechanism 2 moves out, and then slides the moving frame 203 to the designated position through the sliding groove 210 and the sliding block 214, which is convenient for adjustment according to the size of the casing, and improves the practicality of the positioning mechanism 2. After sliding to the appropriate position, the rotating plate 6 drives the second threaded shaft 202 to rotate, so that the sliding plate 212 and the limit frame 213 are fixed, and the moving frame 203 is fixed. Then, the servo motor 208 drives the first rotating shaft 211 to rotate, so that the camera 217 and the pressure sensor 207 are driven through the first connecting plate 209. The screw punch 217 is rotated, and the staff can observe the position of the screw punch and the casing in real time by using the camera 217. By using the values ​​received from various parts of the pressure sensor 207, it can be determined that the screw punch on the punching equipment body 1 is directly above the center of the casing. Since the casing is circular, the maximum value of the received pressure is directly above the center of the casing, which avoids the need for workers to cooperate with the guidance, thereby reducing errors and improving accuracy. After the drilling is completed, the cleaning plate 303 is rotated into the screw punch. The screw punch is rotated and raised, and the cleaning plate 303 can effectively clean the mud attached to the screw punch. The water in the water storage tank 4 is flushed to the screw punch through the water pump 13 and the water outlet pipe 10 by using the water pump 12, thereby improving the cleaning effect of the screw punch.

[0045] The above description enables those skilled in the art to implement or use the present invention. Various modifications to these embodiments will be apparent to those skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present invention. Therefore, the present invention will not be limited to the embodiments shown herein, but will conform to the widest scope consistent with the principles and novel features disclosed herein.

Claims

1. A drilling device for pile foundation construction in a construction project, comprising a drilling device body (1), a water storage tank (4) being fixedly mounted on the surface of the drilling device body (1), characterized in that: A first support plate (11) and a fixing block (14) are fixedly mounted on the back of the water storage tank (4), a second support plate (8) is fixedly mounted on the side of the punching device body (1) close to the first support plate (11), a water pump (12) is fixedly mounted on the fixing block (14), a water pump (13) is fixedly connected between the input end of the water pump (12) and the water storage tank (4), a water outlet pipe (10) is fixedly connected to the output end of the water pump (12), and the water outlet pipe (10) is fixedly passed through the first support plate (11) and the second support plate (8), and further comprising: A positioning mechanism (2), the positioning mechanism (2) comprising a servo motor (206) fixedly mounted inside the punching device body (1); A cleaning mechanism (3), wherein the cleaning mechanism (3) comprises a fixing frame (301).

2. The drilling equipment for pile foundation construction of a construction project according to claim 1, characterized in that: The output end of the servo motor 1 (206) is fixedly connected to a first threaded shaft (204); a rectangular block (205) is fixedly installed inside the punching device body (1); the rectangular block (205) and the first threaded shaft (204) are threadedly connected; a moving block (201) is fixedly installed on the upper surface of the rectangular block (205); and the moving block (201) and the punching device body (1) are slidably matched.

3. The drilling equipment for pile foundation construction of a construction project according to claim 2, characterized in that: The left side of the moving block (201) is provided with a sliding groove (210), a sliding block (214) is slidably installed inside the sliding groove (210), and the left side of the sliding block (214) is fixedly connected to the moving frame (203).

4. The drilling equipment for pile foundation construction of a construction project according to claim 3, characterized in that: A limit frame (213) is fixedly mounted on one side of the moving frame (203); a sliding plate (212) is slidably mounted on the limit frame (213); a second threaded shaft (202) is threadedly connected between the sliding plate (212) and the moving block (201); a rubber pad (7) is arranged between the bottom end of the second threaded shaft (202) and the upper surface of the moving block (201); and a rotating plate (6) is fixedly mounted on the top end of the second threaded shaft (202).

5. The drilling equipment for pile foundation construction of construction engineering according to claim 3, characterized in that: A servo motor 2 (208) is arranged above the moving frame (203), the outer surface of the servo motor 2 (208) is fixedly connected to a fixing seat (5), and the bottom surface of the fixing seat (5) is fixedly connected to the upper surface of the moving frame (203).

6. The drilling equipment for pile foundation construction of construction engineering according to claim 3, characterized in that: The inner wall of the movable frame (203) is rotatably connected to a first rotating shaft (211), one end of the first rotating shaft (211) is fixedly connected to an output shaft of a second servo motor (208), and a first connecting plate (209) is fixedly mounted on an outer surface of the first rotating shaft (211).

7. The drilling equipment for pile foundation construction of construction engineering according to claim 6, characterized in that: A camera (217) and a pressure sensor (207) are fixedly mounted on the inner wall of the first connecting plate (209), and a pair of force springs (215) are fixedly mounted on one side of the first connecting plate (209) close to the pressure sensor (207), and a force plate (216) is fixedly mounted on one end of the pair of force springs (215).

8. The drilling equipment for pile foundation construction of construction engineering according to claim 1, characterized in that: The fixing frame (301) is fixedly mounted on the surface of the first connecting plate (209); the inner wall of the fixing frame (301) is rotatably connected to a second rotating shaft (302); the outer surface of the second rotating shaft (302) is fixedly connected to a cleaning plate (303); a limiting plate (304) is fixedly mounted on one side of the fixing frame (301); the front side of the cleaning plate (303) is in contact with the back side of the limiting plate (304).

9. The drilling equipment for pile foundation construction of construction engineering according to claim 8, characterized in that: The back side of the water storage tank (4) is fixedly connected to a water injection pipe (15), and the outer surface of the water injection pipe (15) is clamped with a water retaining block (9).