Substation scene modeling method and system

Through the substation scenario modeling method, data parameterization generation templates and model mapping templates are constructed, wiring diagrams and CAD files are analyzed, and data acquisition problems in the existing technology of substation three-dimensional model construction are solved, achieving high accuracy 3D model construction of degree and flexibility.

CN118965520APending Publication Date: 2024-11-15NARI INFORMATION & COMM TECH
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411024274.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-29
Publication Date
2024-11-15

AI Technical Summary

Technical Problem

The prior art has problems such as unstable data acquisition, time-consuming, poor model accuracy and flexibility in the construction of three-dimensional models of substations, especially inadequate adaptability to different types of substations.

Method used

Using the substation scenario modeling method, the template and model mapping template are generated by building data parameterization, the wiring diagram and CAD files are analyzed, the equipment model data is obtained, and the model mapping and splicing is carried out according to the substation type and scene characteristics are supported, and manual adjustment and topological calibration are supported. to improve the accuracy and flexibility of the model.

Benefits of technology

It realizes the high accuracy and flexibility of the three-dimensional model of the substation, and is suitable for different types of substation scenarios, reducing data acquisition time and improving the practical application value of the model.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118965520A_ABST
    Figure CN118965520A_ABST
Patent Text Reader

Abstract

The invention provides a substation scene modeling method and system. The method comprises the following steps: step 1, constructing a substation scene modeling template; 2, generating a template according to data parameterization in the step 1, and analyzing an in-station wiring diagram and a CAD file; and 3, performing substation scene modeling by using the data obtained in the step 2 and the model mapping template in the step 1. According to the method, the transformer substation scene modeling template is constructed, so that the three-dimensional model of the transformer substation is obtained more orderly, and the constructed transformer substation scene modeling template is high in precision; by analyzing the in-station wiring diagram and the CAD file, the method can be used for different types of transformer substations and scenes, and the actual requirements are met; by modeling the transformer substation scene and manually adjusting the model, the constructed model is high in flexibility, and by checking connectivity topology in the model, the obtained transformer substation scene model can be more accurate and accord with an actual application scene.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of substation digitization, and more specifically, relates to a substation modeling method and system. Background Art

[0002] The grid map integrates massive data such as grid resources, assets, topology, and measurement, and is used for dynamic management of physical grids in digital space, realizing core production businesses such as equipment asset management, production business command, and grid engineering construction. The grid map needs to cover grid resource information in all links of "generation-transmission-transformation-distribution-use" horizontally, and vertically through the full voltage level electrical topology from 1100 kV to 0.4 kV. The rapid construction model of substations is the basic work of the grid map.

[0003] Prior art document 1 (CN117576322A) discloses a method and system for constructing a three-dimensional model of a substation based on scene adaptability. The disadvantage is that for different substations, it is necessary to scan and model multiple substation equipment in the target substation area through drone patrol, which requires a lot of manpower and time, and it is difficult to ensure the accuracy and real-time performance of the model.

[0004] Prior art document 2 (CN115937288A) discloses a method for constructing a three-dimensional scene model of a substation. Its shortcomings are that the laser three-dimensional scanning technology and the oblique photography technology require all-round photo information of the building to be obtained for different substation unit scenes. UAV photography is also affected by the on-site environment and weather, and the data acquisition effect is unstable and takes a lot of time.

[0005] Prior art document 3 (CN111898007A) discloses a system and method for constructing a three-dimensional scene model of a substation. The disadvantage is that the system uses ledger information to associate with the three-dimensional model of the equipment, and the model cannot be manually adjusted according to the actual situation, resulting in poor flexibility. Summary of the invention

[0006] In order to solve the deficiencies in the prior art, the present invention provides a substation scene modeling method and system.

[0007] The present invention adopts the following technical solution.

[0008] A first aspect of the present invention provides a substation scenario modeling method, comprising the following steps:

[0009] Step 1: Construct a substation scenario modeling template, including: data parameterization generation template and model mapping template;

[0010] Step 2: Generate a template according to the data parameters in step 1, parse the wiring diagram and CAD file in the substation, and obtain the type and quantity of bays and equipment model data in the substation;

[0011] Step 3: Based on the type and quantity of bays in the substation and the equipment model data obtained in step 2, perform substation scenario modeling according to the model mapping template in step 1.

[0012] Preferably, in step 1, the data parameterization generation template includes: parameterization generation scheme data, parameterization generation data attribute rules.

[0013] Preferably, the parameterized generation data attribute rules include substation classification and bay units.

[0014] Preferably, the substation classification data attribute rules are generated parameterized to determine the type of substation according to the type of main transformer;

[0015] When building the in-station model, the data source is obtained from the interval unit.

[0016] Preferably, the parameterized generation model mapping rules include above-ground outdoor stations, above-ground indoor stations, above-ground semi-indoor stations and basement stations.

[0017] Preferably, in step 2, the locations of various types of equipment are obtained by interpreting CAD files, and the corresponding equipment models are mapped. The specific CAD files include standard-named DWG files and non-standard-named DWG files.

[0018] Preferably, the specific mapping process of the standard named DWG file includes:

[0019] Parse the DWG file and verify whether the block data name in the DWG file complies with the rules;

[0020] Get the block data name and coordinates in the file;

[0021] Match model files by block data name;

[0022] Map the model file to the substation according to the coordinates.

[0023] Preferably, the specific mapping process of the non-standard named DWG file includes:

[0024] Parse the DWG file;

[0025] Match block data graphics in DWG files through AI;

[0026] Get the block data name and coordinates in the file;

[0027] Match model files by block data name;

[0028] Map the model file to the substation according to the coordinates.

[0029] Preferably, in step 3, for the substation rapid template building function, building the scene specifically includes: editing hanging points, selecting substations, splicing models, cable generation, manual adjustment, saving scenes, topology verification and publishing scenes.

[0030] Preferably, the splicing model specifically includes:

[0031] Obtain the type and number of bays in the substation by parsing the wiring diagram;

[0032] Obtain the installation location of the main transformer and divide the substation into above-ground outdoor station, above-ground indoor station, above-ground semi-indoor station and basement station;

[0033] According to the model mapping rules;

[0034] Get the interval type through the wiring diagram;

[0035] Obtain the voltage level of each bay through the wiring diagram;

[0036] Obtain the corresponding bay model according to bay type and voltage level;

[0037] Place the models according to the model mapping rules;

[0038] Determine the spatial location of the substation by obtaining the substation coordinates;

[0039] Get the lines that have been modeled;

[0040] Obtain the terminal tower information of the lines that have been modeled;

[0041] Determine the substation connection method based on the start and stop stations and start and stop switches of the terminal tower;

[0042] Determine the corresponding pole tower attachment based on the existing lines.

[0043] Preferably, the altitude and the coordinate position are combined to form the spatial position of the substation, the altitude represents the spatial height of the equipment, and the coordinate position represents the longitude and latitude coordinates of the equipment.

[0044] A second aspect of the present invention provides a substation scenario modeling system, which is used to run the substation scenario modeling method, including:

[0045] Substation scenario modeling template module: used to build data parameterization generation template and model mapping template model;

[0046] Data parsing module: used to generate templates for data parameterization, build wiring diagrams and CAD file models within the parsing station;

[0047] Substation scenario modeling module: The data obtained by parsing the wiring diagram and CAD files in the substation and the substation scenario modeling template are used to build the substation scenario model.

[0048] An electronic device comprises: a memory, a processor and a computer program stored in the memory and executable on the processor, wherein the computer program implements the above-mentioned substation scenario modeling method when loaded into the processor.

[0049] A computer-readable storage medium stores a computer program, and when the computer program is executed by a processor, the above-mentioned substation scenario modeling method is implemented.

[0050] Compared with the prior art, the beneficial effects of the present invention include at least: by constructing a substation scene modeling template, parameterizing and generating equipment data attributes and constructing a model mapping template for the acquired substation type, the acquisition of the three-dimensional model of the substation is more organized, and the constructed substation scene modeling template has high accuracy; according to the constructed substation scene modeling template, the wiring diagram and CAD file in the station are parsed, and the corresponding equipment model is mapped to the actual scene, which can be used for different types of substations and scenes, conforming to the equipment attribute rules in actual applications and the construction rules of the same type of substations, and meeting actual needs; in the substation scene modeling, the model is spliced, and the model can be manually adjusted after the cable is generated. The constructed model has high flexibility, and by performing topological verification on the connectivity in the model, the obtained substation scene model can be made more accurate and conform to the actual application scenario. BRIEF DESCRIPTION OF THE DRAWINGS

[0051] Figure 1 is a schematic diagram of an above-ground outdoor station provided according to an embodiment of the present invention;

[0052] Figure 2 is a schematic diagram of an above-ground indoor station provided according to an embodiment of the present invention;

[0053] Figure 3 is a schematic diagram of a ground semi-indoor station provided according to an embodiment of the present invention;

[0054] Figure 4 is a schematic diagram of a basement station provided according to an embodiment of the present invention;

[0055] Figure 5 is a schematic diagram of a single-body model hanging point provided according to an embodiment of the present invention;

[0056] Figure 6 is a schematic diagram of another single-body model hanging point provided according to an embodiment of the present invention;

[0057] Figure 7is a schematic diagram of a spacing model hanging point provided according to an embodiment of the present invention;

[0058] Figure 8 is a schematic diagram of another spacing model hanging point provided according to an embodiment of the present invention;

[0059] Fig. 9 It is a flow chart of a splicing model provided according to an embodiment of the present invention. DETAILED DESCRIPTION

[0060] In order to make the purpose, technical scheme and advantages of the present invention clearer, the technical scheme of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. The described embodiments are only embodiments of a part of the present invention, not all embodiments. Based on the spirit of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work belong to the protection scope of the present invention.

[0061] Embodiment 1 of the present invention provides a substation scenario modeling method, comprising the following steps:

[0062] Step 1: Construct a substation scenario modeling template, including: data parameterization generation template and model mapping template;

[0063] In order to ensure multi-platform rendering support, each model is divided into a fine model and a simple model. The fine model is used for platforms with high rendering capabilities and has no requirements for model geometry; the simple model is used for efficient loading of a grid map, and the geometry of the simple model must be less than 100,000. For example, but not limited to, for a flagpole, if a fine model is made, the cylindrical surface can generate 32 or 64 faces or even more. The more faces, the rounder the column appears, while the simple model only generates 8 faces, which is equivalent to replacing the cylinder with an 8-sided column.

[0064] Step 1.1: Data parameterization generates templates, including: parameterization generates scheme data, parameterization generates data attribute rules. The specific steps are as follows:

[0065] Step 1.1.1 Parameterize and generate solution data. The specific process is as follows:

[0066] The substation quick template function requires parsing the in-station wiring diagram, which represents the wiring diagram of the primary equipment. It can show the topological connection relationship and switch status of the main primary equipment. Currently, 41 categories are obtained, and they will be continuously improved based on the data source. The wiring diagram data classifies different equipment according to the equipment code. The corresponding relationship is shown in the following table:

[0067] Table 1 Equipment code correspondence table

[0068]

[0069]

[0070] Step 1.1.2 parameterizes and generates data attribute rules, including substation classification and bay units. The specific steps are as follows:

[0071] Step 1.1.2.1 Parameterize and generate substation classification data attribute rules. The specific process is as follows:

[0072] The type of substation is determined based on the type of main transformer. For example, "0301Z" represents the main transformer type. The main transformer installation location attribute "installationLocation" is obtained through the main transformer to distinguish whether the substation is an above-ground indoor station, an above-ground outdoor station, an above-ground semi-indoor station, or a basement station.

[0073] Step 1.1.2.2 Parameterize and generate interval unit data attribute rules. The specific process is as follows:

[0074] When building a station model, the data source is mainly obtained from the interval unit. The interval unit attribute fields are shown in the following table:

[0075] Table 2 Interval data attribute table

[0076]

[0077]

[0078] Use "jgZ" to obtain the bays in the substation wiring diagram, and then use "type" to distinguish bay types. The corresponding relationship between bay types is as follows:

[0079] Table 3 Interval type code correspondence table

[0080]

[0081]

[0082] The voltage level correspondence is distinguished according to "voltageLevel".

[0083] Table 4 Voltage level code correspondence table

[0084]

[0085]

[0086]

[0087] Step 1.2 parameterizes the model mapping rules, including ground outdoor stations, ground indoor stations, ground semi-indoor stations, and basement stations. The specific process is as follows:

[0088] The specific process of parameterizing and generating the mapping rules for the ground outdoor stations in step 1.2.1 is as follows:

[0089] The intervals are obtained through the wiring diagram, and the incoming line unit, busbar unit, busbar (section) switch unit, main transformer incoming line unit, transformer unit and outgoing line unit are extracted according to the interval type.

[0090] like Figure 1 As shown, select the incoming and outgoing line direction of the substation and the transformer location according to the preset layout.

[0091] The incoming line intervals are sorted according to the interval numbers of the incoming line units, and the incoming line interval models are generated according to the quantity. The models are mapped in a side-by-side order, and the models select the default interval model according to the voltage level.

[0092] Generate an incoming line interval model according to the quantity, for example but not limited to, each interval in the substation incoming line unit has 3 incoming lines corresponding to the three phases A, B, and C. If there are two incoming line units, the corresponding conductors entering the substation should be 6.

[0093] Mapping the model in a side-by-side order means placing the model in one direction and setting the three-dimensional model of the incoming lines side by side.

[0094] The number of high-voltage busbar units and the number of low-voltage busbar units are determined according to the voltage level, and the busbar bay model is mapped in a parallel manner. The model selects the default bay model according to the voltage level.

[0095] The busbar bays are mapped according to the busbar (section) switch units, and the model selects the default bay model according to the voltage level.

[0096] The outgoing line intervals are sorted according to the interval numbers of the outgoing line units, and models are generated according to the quantity. The models are mapped in a side-by-side order, and the models select the default interval model according to the voltage level.

[0097] The incoming lines obtained from the drawings are of one type, without distinguishing between high and low voltage. A substation may have more than three voltage levels, so the incoming line data must be screened and counted by voltage level, and a model is generated based on the counted number.

[0098] The specific process of parameterizing and generating the mapping rules of ground and indoor stations in step 1.2.2 is as follows:

[0099] The bays are obtained through the wiring diagram, and the incoming line unit, busbar unit, busbar (section) switch unit, transformer unit and outgoing line unit are extracted according to the bay type.

[0100] like Figure 2 As shown, the ground indoor station divides the substation into 3 floors by default: underground, first floor, and second floor

[0101] The model first generates one layer, the specific contents are as follows:

[0102] GIS equipment is generated from high-voltage incoming line bay, bus bay, busbar bay, and main transformer bay. They are spliced ​​from bottom to top. A control cabinet is reserved on the right side of the GIS, 1.8 meters are reserved on the left and right, 2.5 meters are reserved on the top and bottom, and 1.5 meters is reserved between the GIS and the control cabinet. The default GIS room width is 10 meters and the length is 20 meters. GIS equipment is generated from bottom to top. When the reserved space is insufficient after the GIS equipment model is spliced, the room length is stretched to accommodate the equipment placement.

[0103] The transformer is generated in the form of two rooms, and the wall bushing is set according to the modeling standard. The left room is 6.5 meters wide and 5 meters long, where the transformer body is placed; the right room is 6 meters wide and 5 meters long, where the radiator is placed

[0104] The switch cabinets are divided into two rows and placed face to face. The transformer incoming line is used as the benchmark. The discharge capacitor cabinets are placed on the left side of the incoming line, and the switch cabinets are arranged in the order of switch numbers on the right side. If there are other cabinets, they are arranged along the switch cabinets. When the transformer side cabinets are full of 11 cabinets, they are arranged in the opposite direction. The default number of switch cabinets allocated to a transformer shall not exceed 22. The distance between the transformer side cabinet and the transformer room is 1.75 meters, and the distance between the transformer opposite cabinet and the transformer opposite wall (virtual wall, no wall model, only used to determine the placement of the cabinet) is 1.75 meters. The transformer opposite wall is in a straight line with the front of the GIS, and the width of the distribution room is consistent with the total width of all transformers.

[0105] For other equipment, an independent space is generated on one side of the room where the GIS is located (on the side of the wall facing the transformer). The wall facing the transformer in this space is a virtual wall without a wall model. Visually, it is the same room as the switch cabinet. The length of this space is 3 meters, which is the sum of the GIS equipment space and the transformer space. Stairs are set on both sides of this space (the position of the stairs is consistent throughout the three floors), and the grounding transformer is set in the middle.

[0106] The underground space has an overall area consistent with the first floor, and a main transformer oil pit is generated under the transformer body.

[0107] On the second floor, the station transformer is placed in the center of the two stairs; the capacitor bank is placed on the transformer side above the switch cabinet room, and the distance between the capacitor banks is kept at 1.6 meters, starting from the GIS equipment side; an 8-meter-wide secondary equipment room is set up on the side opposite to the GIS equipment, with 28 cabinets placed by default, in 4 rows, 7 in each row, and the distance between the cabinet and the opposite wall of the GIS is 0.7 meters.

[0108] The specific process of parameterizing and generating the mapping rules of ground and indoor stations in step 1.2.3 is as follows:

[0109] The intervals are obtained through the wiring diagram, and the incoming line unit, busbar unit, busbar (section) switch unit, main transformer incoming line unit, transformer unit and outgoing line unit are extracted according to the interval type.

[0110] like Figure 3 As shown, the transformer winding type "windingType" is used to determine whether the substation has medium voltage, and the "voltageLevel" is used to distinguish the high voltage side, medium voltage side, and low voltage side.

[0111] Select the direction of incoming and outgoing lines and transformer location of the substation according to the preset layout

[0112] The incoming line intervals are sorted according to the interval numbers of the incoming line units, and models are generated according to the quantity. The models are mapped in a side-by-side order, and the models select the default interval model according to the voltage level.

[0113] The number of high-voltage busbar units and the number of low-voltage busbar units are determined according to the voltage level, and the busbar bay model is mapped in a parallel manner. The model selects the default bay model according to the voltage level.

[0114] The busbar bays are mapped according to the busbar (section) switch units, and the model selects the default bay model according to the voltage level.

[0115] Differentiate the medium voltage outgoing line interval and the low voltage outgoing line interval in the outgoing line unit according to the voltage level

[0116] The medium voltage outgoing line intervals are sorted according to the interval numbers of the outgoing line units, and a model is generated according to the quantity. The models are mapped in a side-by-side order, and the model selects a default interval model according to the voltage level.

[0117] Get the number of switch cabinets in the substation wiring diagram according to the switch cabinet "0322Z" and map the switch cabinets in the distribution room.

[0118] The switch cabinets are divided into two rows and placed face to face. The switch cabinets are arranged in the order of switch numbers. If there are other cabinets, they will continue to be arranged along the switch cabinets. When there are 11 cabinets on the transformer side, they will continue to be arranged in the opposite direction. The default number of switch cabinets allocated to a transformer shall not exceed 22. The distance between the cabinet and the wall of the distribution room behind is 1.75 meters, and the distance from the walls on both sides is 1 meter. The width of the distribution room is 10 meters and the length is 12.5 meters * the number of transformers.

[0119] The grounding transformer room is mapped according to the number of grounding transformers "0304Z" (used transformers "0303Z"), and the grounding transformer room (station transformer) is placed along the back of the distribution room. The room width is 10 meters and the length is 7 meters.

[0120] The specific process of parameterizing and generating basement station mapping rules in step 1.2.4 is as follows:

[0121] The bays are obtained through the wiring diagram, and the incoming line unit, busbar unit, busbar (section) switch unit, transformer unit and outgoing line unit are extracted according to the bay type.

[0122] The ground indoor station is divided into 3 floors by default, underground 1st floor, underground 2nd floor, underground 3rd floor

[0123] The model gives priority to generating the second underground floor, the specific contents are as follows:

[0124] GIS equipment is generated from high-voltage incoming line bay, bus bay, busbar bay, and main transformer bay. They are spliced ​​from bottom to top. A control cabinet is reserved on the right side of the GIS, 1.8 meters are reserved on the left and right, 2.5 meters are reserved on the top and bottom, and 1.5 meters is reserved between the GIS and the control cabinet. The default GIS room width is 10 meters and the length is 20 meters. GIS equipment is generated from bottom to top. When the reserved space is insufficient after the GIS equipment model is spliced, the room length is stretched to accommodate the equipment placement.

[0125] The transformer is generated in the form of two rooms, and the wall bushing is set according to the modeling standard. The left room is 6.5 meters wide and 5 meters long, where the transformer body is placed; the right room is 6 meters wide and 5 meters long, where the radiator is placed.

[0126] The switch cabinets are divided into two rows and placed face to face. The transformer incoming line is used as the benchmark. The discharge capacitor cabinets are placed on the left side of the incoming line, and the switch cabinets are arranged in the order of switch numbers on the right side. If there are other cabinets, they are arranged along the switch cabinets. When the transformer side cabinets are full of 11 cabinets, they are arranged in the opposite direction. The default number of switch cabinets allocated to a transformer shall not exceed 22. The distance between the transformer side cabinet and the transformer room is 1.75 meters, and the distance between the transformer opposite cabinet and the transformer opposite wall (virtual wall, no wall model, only used to determine the placement of the cabinet) is 1.75 meters. The transformer opposite wall is in a straight line with the front of the GIS, and the width of the distribution room is consistent with the total width of all transformers.

[0127] For other equipment, an independent space is generated on one side of the room where the GIS is located (on the side of the wall facing the transformer). The wall facing the transformer in this space is a virtual wall without a wall model. Visually, it is the same room as the switch cabinet. The length of this space is 3 meters, which is the sum of the GIS equipment space and the transformer space. Stairs are set on both sides of this space (the position of the stairs is consistent throughout the three floors), and the grounding transformer is set in the middle.

[0128] The overall area of ​​the bottom three layers is consistent with that of the first layer, and the main transformer oil pit is generated under the transformer body.

[0129] like Figure 4As shown, on the underground floor, the station transformer is placed in the center of the two stairs; the capacitor bank is placed on the transformer side above the switch cabinet room, with a distance of 1.6 meters between the capacitor banks, starting from the GIS equipment side; an 8-meter-wide secondary equipment room is set up on the side opposite to the GIS equipment, with 28 cabinets placed by default, in 4 rows, 7 cabinets in each row, and the distance between the cabinet and the opposite wall of the GIS is 0.7 meters.

[0130] Underground substations are built below ground level, unlike semi-indoor ones above ground.

[0131] Step 2: Generate a template according to the data parameters in step 1, parse the wiring diagram and CAD file in the substation, and obtain the type and quantity of bays and equipment model data in the substation;

[0132] In order to accurately obtain the location of various types of equipment, the corresponding equipment models are mapped by interpreting CAD files.

[0133] The specific mapping process of standard named DWG files includes:

[0134] Parse the DWG file and verify whether the block data name in the DWG file complies with the rules;

[0135] Get the block data name and coordinates in the file;

[0136] Match model files by block data name;

[0137] Map the model file to the substation according to the coordinates.

[0138] The specific mapping process of non-standard named DWG files includes:

[0139] Parse the DWG file;

[0140] Match block data graphics in DWG files through AI;

[0141] Get the block data name and coordinates in the file;

[0142] Match model files by block data name;

[0143] Map the model file to the substation according to the coordinates.

[0144] Step 3: Based on the equipment model data obtained in step 2, perform substation scenario modeling according to the model mapping template in step 1.

[0145] For the substation quick template building function, building the scene requires several steps, including: editing hanging points, selecting substations, splicing models, cable generation, manual adjustment, saving scenes, topology verification, publishing scenes, etc.

[0146] In view of the current situation of the power grid map, substations can be generated in batches by combining existing data, providing three-dimensional support capabilities for the power grid map.

[0147] The specific steps include:

[0148] Step 3.1: Edit the hanging point. Editing the hanging point is to mark the connection position between the wire and the equipment. The hanging point is used to generate the connection line, which is set on the high-voltage side and low-voltage side of the outdoor equipment respectively.

[0149] Editing hanging points includes: single model hanging points and interval model hanging points. The specific steps are as follows:

[0150] Step 3.1.1: Single model hanging point.

[0151] like Figure 5 and Figure 6 As shown, the single-body model hanging points are divided into two types: incoming line hanging points and outgoing line hanging points.

[0152] Incoming line hanging point: The incoming line hanging point is set on the high-voltage side of the single-body model and is used to hang the upper-level equipment.

[0153] Outgoing line hanging point: The outgoing line hanging point is set on the low-voltage side of the single-body model and is used to hang the next-level equipment.

[0154] Step 3.1.2: Space the model hanging points.

[0155] like Figure 7 and Figure 8 As shown, the interval model is composed of monomer models, the cables between the monomer models have been generated, and the hanging points of the interval model are divided into interval incoming line hanging points and interval outgoing line hanging points.

[0156] Incoming line hanging point: The incoming line hanging point is set on the high-voltage side of the single-body model and is used to hang the upper-level equipment.

[0157] Outgoing line hanging point: The outgoing line hanging point is set on the low-voltage side of the single-body model and is used to hang the next-level equipment.

[0158] Step 3.2: Select the substation.

[0159] First, substations are filtered by asset unit and voltage level;

[0160] In addition, during the first deployment, all substation data under the asset unit must be obtained to prepare for modeling.

[0161] Step 4.4: Assemble the model.

[0162] After obtaining the wiring diagram, set different substation models according to the main transformer installation location "installationLocation". The specific process is as follows Fig. 9 shown.

[0163] The substation creation process is as follows:

[0164] First, the type and number of bays in the substation are obtained by parsing the wiring diagram;

[0165] Obtain the installation location of the main transformer and divide the substation into above-ground outdoor station, above-ground indoor station, above-ground semi-indoor station, and basement station;

[0166] According to the model mapping rules;

[0167] Get the interval type through the wiring diagram;

[0168] Obtain the voltage level of each bay through the wiring diagram;

[0169] Obtain the corresponding bay model according to bay type and voltage level;

[0170] Place the models according to the model mapping rules;

[0171] Determine the spatial location of the substation by obtaining the substation coordinates;

[0172] Determine whether there is a completed modeling line;

[0173] Determine whether the line that has been modeled has a terminal tower;

[0174] Determine the start and end stations of the terminal tower and the start and stop switches to determine how to connect the substation.

[0175] When deploying for the first time, it is recommended to generate batches by acquiring overall data, which can be used as a supplement to the three-dimensional display part of a power grid map. Determine whether to connect the corresponding tower based on whether there is a line.

[0176] The altitude indicates the spatial height of the device, and the coordinate position indicates the latitude and longitude coordinates of the device. The altitude and the coordinate position are combined to form the spatial location information of the device.

[0177] The switch number indicates the name of the switch in the substation and is unique in the substation.

[0178] Step 3.3: Cable generation.

[0179] When generating the cable, the inlet and outlet hanging points are connected at intervals according to the three phases A, B, and C of AC (two phases of DC poles Ⅰ and Ⅱ).

[0180] The connection order between the bays is: incoming line bay, high-voltage bus bay, main transformer bay, low-voltage bus bay, and outgoing line bay.

[0181] When creating a busbar bay, the cable between the busbar bay and the busbar is automatically generated based on whether a busbar exists.

[0182] If medium voltage exists, when the main transformer bay is connected to the next level bay, the corresponding bus bay is automatically determined according to the voltage level.

[0183] Step 3.4: Manual adjustment.

[0184] After the substation scene model is spliced, the model position can be adjusted manually. When moving, the cable can be moved with it, and the platform will automatically generate cables in real time.

[0185] Step 3.5: Save the scene.

[0186] After configuring the scene, the logical relationships, topological relationships, and spatial positions of various models in the scene are saved, and the saved binary files are stored on the server side.

[0187] Step 3.6: Topology verification.

[0188] Verify the connectivity topology of power transmission and transformation scenarios.

[0189] Step 3.7: Publish the scene.

[0190] Retrieve the scene description file, obtain the model from the library, form an overall model for slicing and publishing. The published results are two sets. One set of simple models is used for the power grid map. The model geometry is not more than 100,000 and the cables are published in the form of single cables. The other set of fine models is used by other engines. There is no requirement for the model geometry. The cables are generated according to the voltage level and published in the form of split cables. Different engines call different models. According to the front-end rendering engine, the power grid map gives priority to the simple model.

[0191] When publishing a scene, different layers are generated according to different asset units, and data permissions are controlled through layers.

[0192] Example 2

[0193] Embodiment 2 of the present invention provides a substation scenario modeling system, which is used to run a substation scenario modeling method described in embodiment 1, including:

[0194] Substation scenario modeling template module: used to build data parameterization generation template and model mapping template model;

[0195] Data parsing module: used to build the wiring diagram and CAD file model in the parsing station according to the data collection template;

[0196] Substation scenario modeling module: The data obtained by parsing the wiring diagram and CAD files in the substation and the substation scenario modeling template are used to build the substation scenario model.

[0197] Example 3

[0198] Embodiment 3 of the present invention provides an electronic device, comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein when the computer program is loaded into the processor, a substation scenario modeling method according to embodiment 1 is implemented.

[0199] Example 4

[0200] Embodiment 4 of the present invention provides a computer-readable storage medium, wherein the computer-readable storage medium stores a computer program, and when the computer program is executed by a processor, a substation scenario modeling method according to embodiment 1 is implemented.

[0201] Compared with the prior art, the beneficial effects of the present invention include at least: by constructing a substation scene modeling template, parameterizing and generating equipment data attributes and constructing a model mapping template for the acquired substation type, the acquisition of the three-dimensional model of the substation is more organized, and the constructed substation scene modeling template has high accuracy; according to the constructed substation scene modeling template, the wiring diagram and CAD file in the station are parsed, and the corresponding equipment model is mapped to the actual scene, which can be used for different types of substations and scenes, conforming to the equipment attribute rules in actual applications and the construction rules of the same type of substations, and meeting actual needs; in the substation scene modeling, the model is spliced, and the model can be manually adjusted after the cable is generated. The constructed model has high flexibility, and by performing topological verification on the connectivity in the model, the obtained substation scene model can be made more accurate and conform to the actual application scenario.

[0202] The present disclosure may be a system, a method and / or a computer program product. The computer program product may include a computer-readable storage medium carrying computer-readable program instructions for causing a processor to implement various aspects of the present disclosure.

[0203] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the above embodiments, ordinary technicians in the relevant field should understand that the specific implementation methods of the present invention can still be modified or replaced by equivalents, and any modifications or equivalent replacements that do not depart from the spirit and scope of the present invention should be covered within the scope of protection of the claims of the present invention.

Claims

1. A substation scenario modeling method, characterized in that: The following steps are involved: Step 1: Construct a substation scenario modeling template, including: data parameterization generation template and model mapping template; Step 2: Generate a template according to the data parameters in step 1, parse the wiring diagram and CAD file in the substation, and obtain the type and quantity of bays and equipment model data in the substation; Step 3: Based on the type and quantity of bays in the substation and the equipment model data obtained in step 2, perform substation scenario modeling according to the model mapping template in step 1.

2. A method for building a power transmission line scenario model according to claim 1, characterized in that: include: In step 1, the data parameterization generation template includes: parameterization generation scheme data and parameterization generation data attribute rules.

3. A method for building a power transmission line scenario model according to claim 2, characterized in that: include: Parameterized generation of data attribute rules, including substation classification and bay units.

4. A method for building a power transmission line scenario model according to claim 3, characterized in that: include: Parametrically generate substation classification data attribute rules, and determine the type of substation based on the type of main transformer; When building the in-station model, the data source is obtained from the interval unit.

5. A method for building a power transmission line scenario model according to claim 2, characterized in that: include: The model mapping rules are generated parametrically, including above-ground outdoor stations, above-ground indoor stations, above-ground semi-indoor stations, and basement stations.

6. A method for constructing a power transmission line scenario model according to claim 1, characterized in that: include: In step 2, the locations of various types of equipment are obtained by interpreting the CAD files, and the corresponding equipment models are mapped. The specific CAD files include standard-named DWG files and non-standard-named DWG files.

7. A method for constructing a power transmission line scenario model according to claim 6, characterized in that: include: The specific mapping process of standard named DWG files includes: Parse the DWG file and verify whether the block data name in the DWG file complies with the rules; Get the block data name and coordinates in the file; Match model files by block data name; Map the model file to the substation according to the coordinates.

8. A method for constructing a power transmission line scenario model according to claim 6, characterized in that: include: The specific mapping process of non-standard named DWG files includes: Parse the DWG file; Match block data graphics in DWG files through AI; Get the block data name and coordinates in the file; Match model files by block data name; Map the model file to the substation according to the coordinates.

9. A method for constructing a power transmission line scenario model according to claim 1, characterized in that: include: In step 3, for the substation quick template building function, the scene building specifically includes: editing hanging points, selecting substations, splicing models, cable generation, manual adjustment, saving scenes, topology verification and publishing scenes.

10. A method for constructing a power transmission line scenario model according to claim 9, characterized in that: include: Splicing model, including: Obtain the type and number of bays in the substation by parsing the wiring diagram; Obtain the installation location of the main transformer and divide the substation into above-ground outdoor station, above-ground indoor station, above-ground semi-indoor station and basement station; According to the model mapping rules; Get the interval type through the wiring diagram; Obtain the voltage level of each bay through the wiring diagram; Obtain the corresponding bay model according to bay type and voltage level; Place the models according to the model mapping rules; Determine the spatial location of the substation by obtaining the substation coordinates; Get the lines that have been modeled; Obtain the terminal tower information of the lines that have been modeled; Determine the substation connection method based on the start and stop stations and start and stop switches of the terminal tower; Determine the corresponding pole tower attachment based on the existing lines.

11. A method for constructing a power transmission line scenario model according to claim 10, characterized in that: include: The altitude and the coordinate position are combined to form the spatial position of the substation. The altitude indicates the spatial height of the equipment, and the coordinate position indicates the latitude and longitude coordinates of the equipment.

12. A substation scenario modeling system, running the substation scenario modeling method according to any one of claims 1 to 11, characterized in that: include: Substation scenario modeling template module: used to build data parameterization generation template and model mapping template model; Data parsing module: used to generate templates for data parameterization, build wiring diagrams and CAD file models within the parsing station; Substation scenario modeling module: The data obtained by parsing the wiring diagram and CAD files in the substation and the substation scenario modeling template are used to build the substation scenario model.

13. An electronic device, characterized in that: include: A memory, a processor, and a computer program stored in the memory and executable on the processor, wherein when the computer program is loaded into the processor, a substation scenario modeling method according to any one of claims 1 to 11 is implemented.

14. A computer-readable storage medium storing a computer program, characterized in that: When the computer program is executed by a processor, a substation scenario modeling method according to any one of claims 1 to 11 is implemented.