Load transfer tool and load transfer method for large-section wire of power transmission line

By designing a load transfer tool for large-section conductors of transmission lines using a parallel screw assembly and a turbine box drive structure, the problem that traditional tools cannot meet the conductor load requirements of LGJ-630 was solved, enabling efficient replacement of insulators and safe operation.

CN118970724APending Publication Date: 2024-11-15STATE GRID HUNAN ELECTRIC POWER COMPANY LIMITED +2
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202411351416.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-26
Publication Date
2024-11-15

AI Technical Summary

Technical Problem

Traditional maintenance tools are insufficient to meet the load requirements of LGJ-630 conductors, making insulator replacement time-consuming and labor-intensive. Furthermore, existing UHV tools are incompatible and cannot be used for live-line work.

Method used

A load transfer tool for large-section conductors of transmission lines was designed, comprising a parallel screw assembly, a pull plate, and a clamp. The tool generates stable tension through a three-parallel screw assembly and a turbine box drive structure, and is supplemented by a closed clamp for insulator replacement.

Benefits of technology

This technology enables efficient replacement of LGJ-630 double-split conductor insulators, reducing labor intensity, improving work efficiency, and ensuring safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118970724A_ABST
    Figure CN118970724A_ABST
Patent Text Reader

Abstract

The invention discloses a load transfer tool for a large-section wire of a power transmission line. The load transfer tool comprises a parallel lead screw assembly, and a pull plate and a clamp which are connected with two ends of the parallel lead screw assembly, the parallel lead screw assembly comprises lead screws arranged side by side, and bearing plates are fixed to the two ends of the lead screws. The pulling plate and the clamp are connected to the force bearing plate; the clamp can clamp and fix yoke plates at the two ends of the insulator; the screw rod comprises an inner screw rod and an outer screw rod which are sleeved inside and outside, a screw rod nut seat is fixedly arranged at the end part of the outer screw rod, and the inner screw rod is in threaded connection with the screw rod nut seat; the inner screw rod is screwed into the outer screw rod and the screw rod nut seat by rotating the outer screw rod, so that the bearing plate can be tightened, and the clamps at the two ends are driven to be close to each other. According to the invention, the novel screw rod assemblies connected in parallel are arranged, so that the pull force required for replacing the insulator of the power transmission line is generated enough to assist the replacement of the insulator; by using the tool, the insulator replacement difficulty is reduced, the safety of operators is effectively ensured, the labor intensity is reduced, and the operation efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of power transmission lines, and in particular relates to a load transfer tool and a load transfer method for a large-section conductor of a power transmission line. Background Art

[0002] With the rapid development of power grids, the transmission load is getting bigger and bigger, and the conductor diameter is required to be thicker. The number of lines using LGJ-630 double split conductors has increased accordingly. Due to the operating environment of the transmission line, the line insulators are susceptible to lightning strikes, bird damage, dirt, freezing and other factors. Deterioration, self-explosion and even flashover of the entire string of insulators in operation have become common defects in transmission lines. In order to ensure the safe and stable operation of the line, it is necessary to use insulator replacement tools to replace them in time.

[0003] At present, traditional maintenance tools cannot meet the load requirements of LGJ-630 conductor maintenance. The tension generated by hand chain hoists and ordinary screws is too small, so only large-tonnage capstans and other construction tools can be used for maintenance. This method is time-consuming and labor-intensive to replace insulators and insulator strings, and is limited by power outage time, making it impossible to perform live operations.

[0004] Although there are similar tools for UHV transmission line maintenance, they are too heavy and too large, which is time-consuming and labor-intensive to use. The load redundancy is too large, resulting in poor economic efficiency. In addition, they do not match the structural dimensions of the LGJ-630 double-split conductor and hardware of the 220kV line, as well as the dimensions of the original fixtures. At the same time, there is the problem that different tools are needed to replace the first piece at the end of the insulator, the middle piece, several pieces, or the entire string.

[0005] The load transfer problem of LGJ-630 double-split conductors for 220kV transmission lines needs to be solved urgently. A conductor load transfer tool suitable for replacing the entire tension string, single-piece insulators and single-piece and multi-piece insulators of the suspension string of the LGJ-630 double-split conductor is needed to effectively solve the demand for maintenance tools for the insulator string of the LGJ-630 double-split conductor. Summary of the invention

[0006] The object of the present invention is to provide a load transfer tool and a load transfer method for a large-section conductor of a power transmission line which can generate a large and stable pulling force.

[0007] The large-section conductor load transfer tool provided by the present invention comprises a parallel screw assembly and a pull plate and a clamp connected at both ends thereof; the parallel screw assembly comprises screws arranged in parallel, and load-bearing plates are fixed at both ends of the screws; the pull plate and the clamp are connected to the load-bearing plates; the clamp can clamp and fix the connecting plates at both ends of the insulator; the screw comprises an inner screw and an outer screw arranged inside and outside, a screw nut seat is fixedly arranged at the end of the outer screw, and the inner screw is threadedly connected with the screw nut seat; by rotating the outer screw so that the inner screw thread is screwed into the outer screw and the screw nut seat, the load-bearing plate can be tightened, and the clamps at both ends can be driven to approach.

[0008] In one embodiment of the above tool, the parallel screw assembly is a three-parallel screw assembly, including two sets of screw assemblies arranged opposite to each other, and the screw assembly includes a load-bearing plate, three inner screws and outer screws and screw nut seats arranged outside thereof.

[0009] In one embodiment of the above-mentioned tool, the inner screw is a slender solid straight rod with threads; the load-bearing plate is a triangular high-strength titanium alloy plate; three inner screws are fixed to the three corners of the load-bearing plate; the outer screw is a hollow long rod, and the screw nut seat is fixed to the end of the outer screw; the three outer screws are respectively sleeved on the outer ends of each inner screw, and the threads of the inner screws are engaged with the screw nut seats.

[0010] In one implementation of the above tool, a gear connecting rod is inserted and fixed between two opposing external screw rods to connect and fix the two external screw rods; a driven gear is fixed outside the gear connecting rod.

[0011] In one embodiment of the above tool, driven gears are fixed on the three sets of opposite external screw rods, and a driving gear is provided at the center of the three driven gears, and the driving gear is meshed with each driven gear.

[0012] In one embodiment of the above tool, the driving gear is connected to the driving structure of the turbine box, and the turbine box is simultaneously slidably connected to three sets of external screw rods.

[0013] In one embodiment of the above tool, the driving structure of the turbine box is a turbine worm structure, and the worm extends out of the turbine box.

[0014] In one embodiment of the above tool, the load-bearing plates at both ends of the parallel screw assembly are connected to the pull plate at one end, and an end clamp is provided at the end of the pull plate; and the other end is connected to the broadsword clamp.

[0015] In one embodiment of the above tool, the outer ends of the end clamp and the broadsword clamp are H-shaped clamping seats, and the clamping seats are provided with at least two fasteners connected to the connecting plates at both ends of the insulator.

[0016] A method for performing a transmission line load transfer method using one of the transmission line large-section conductor load transfer tools described above, the steps of which are as follows:

[0017] A. The method for transferring the load of a whole string of tension insulators is as follows:

[0018] 1) Connect and fix the end card with the wire side connecting plate, and then connect and fix the knife card with the cross arm side connecting plate;

[0019] 2) Connect the large knife clamp at the conductor end to the load transfer tool to keep the length of the three screw rods consistent, and then connect the insulating pull rod, which is then connected to the front clamp of the large knife clamp at the cross arm end to ensure consistent length and uniform force;

[0020] 3) Connect the lifting bracket to the top of the fixture and the bottle support rack to the bottom of the fixture;

[0021] 4) After the load transfer tool is stressed, the porcelain bottle on the conductor side unloads the force, the load is transferred, and the replacement operation is carried out;

[0022] B. The method for transferring the load of the insulator string on the conductor side is as follows:

[0023] 1) Connect and fix the wire end fixture to the wire side connecting plate;

[0024] 2) Install the closed card front card on the fifth and sixth porcelain bottles, so that the closed card front card and the porcelain bottle steel cap can only shake left and right, and cannot move forward and backward;

[0025] 3) Connect the wire end fixture to the load transfer tool, and then connect the insulating pull rod and the closed clamp front clamp;

[0026] 4) Connect the lifting bracket to the top of the fixture and the bottle support rack to the bottom of the fixture; after the load transfer tool is stressed, perform the replacement operation;

[0027] C. The method of replacing the insulator string with the middle large porcelain bottle string is as follows:

[0028] 1) Connect the front and rear cards of the closed card to the insulator string respectively, with 5-6 insulators in between;

[0029] 2) Install the front and rear cards of the closed card so that the rear card of the closed card and the steel cap of the porcelain bottle can only shake left and right, but cannot move forward and backward;

[0030] 3) Connect the front clamp of the closed card to the load transfer tool, and then connect the insulating pull rod to the rear clamp of the closed card;

[0031] 4) Connect the lifting bracket to the top of the fixture and the bottle support rack to the bottom of the fixture;

[0032] 5) After the load transfer tool is stressed, the porcelain bottle on the cross arm unloads the force, the load is transferred, and the replacement operation is carried out;

[0033] D. The method for replacing the insulator string on the crossarm side is as follows:

[0034] 1) Connect and fix the cross arm side end fixture with the cross arm side connecting plate;

[0035] 2) Install the closed card back card on the fifth and sixth porcelain bottles, so that the closed card back card and the porcelain bottle steel cap can only shake left and right, and cannot move forward and backward;

[0036] 3) Connect the cross arm end clamp to the load transfer tool, and then connect the insulating pull rod and the closed clamp front clamp;

[0037] 4) Then connect the lifting bracket to the top of the fixture and the bottle support rack to the bottom of the fixture;

[0038] 5) After the load transfer tool is subjected to force, the porcelain bottle on the cross arm side unloads the force, the load is transferred, and the replacement operation is carried out.

[0039] The beneficial effects of the present invention are:

[0040] 1. A new type of parallel lead screw assembly is set up to generate the pulling force required for replacing the transmission line insulators, and assist the insulators in completing the replacement;

[0041] 2. This tool can be used to perform various insulator string maintenance and replacement projects such as the replacement of the entire tension string, single-piece insulators and single and multi-piece insulators of the suspension string of the LGJ-630 double-split conductor, which reduces the difficulty of insulator replacement, effectively ensures the safety of operators, reduces labor intensity, and improves work efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0042] Figure 1 This is a schematic diagram of the axonometric structure of an embodiment of the present invention.

[0043] Figure 2 for Figure 1 Schematic diagram of the axonometric structure of the three-way parallel screw assembly.

[0044] Figure 3 for Figure 2 Schematic diagram of the axonometric structure without the turbine box.

[0045] Figure 4 for Figure 2 Schematic diagram of the axonometric structure of the inner screw, outer screw, screw nut seat and gear connecting rod.

[0046] Figure 5 for Figure 4 Axonometric diagram of the structure without the external screw and gear connecting rod. (The external thread of the internal screw is not shown)

[0047] Figure 6 for Figure 4 Schematic diagram of the axonometric structure of the middle gear connecting rod.

[0048] Figure 7 This is a schematic diagram of a usage scenario of the power transmission line insulator replacement tool of this embodiment. DETAILED DESCRIPTION

[0049] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the relevant technical solutions. Obviously, the described embodiments are only part of the embodiments, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0050] like Figure 1 As shown, the large-section conductor load transfer tool for power transmission lines disclosed in this embodiment includes a three-parallel screw assembly 1, a pull plate 2, a large knife clamp 3 and an end clamp 4.

[0051] like Figure 2 and Figure 3 As shown, the three-parallel screw assembly 1 includes an inner screw 11, an outer screw 12, a screw nut seat 13, a load-bearing plate 14, a gear connecting rod 15, a driven gear 16, a driving gear 17 and a turbine box 18.

[0052] like Figure 4 As shown, the inner screw rod 11 is a slender solid straight rod with external threads. The load-bearing plate 14 is a triangular high-strength plate. Three inner screw rods are fixed to the three corners of the load-bearing plate.

[0053] like Figure 5 As shown, the outer screw rod 12 is a hollow rod. The screw nut seat 13 is fixedly connected to one end of the outer screw rod by thread. The three outer screw rods are respectively sleeved on the outer ends of the inner screw rods 11, and the threads of the inner screw rods are engaged with the screw nut seat. The other end of the outer screw rod extends outward.

[0054] A bearing plate, three inner screw rods and outer screw rods wrapped therein form a screw rod assembly. Two sets of screw rod assemblies are arranged opposite to each other, with the bearing plates located at both ends and the outer screw rods facing each other.

[0055] like Figure 6 As shown, a gear connecting rod 15 is inserted and fixed between two opposite outer screw rods 12 to connect and fix the two outer screw rods. A driven gear 16 is fixed outside the gear connecting rod.

[0056] The three sets of relative outer screw rods are all fixed with driven gears 16. At the center of the three driven gears, there is a driving gear 17. The driving gear is meshed with each driven gear to drive each gear to rotate.

[0057] The drive structure of the turbine box 18 is connected to the driving gear, and can drive the driving gear to rotate. The turbine box is also slidably connected to three sets of external screw rods to further limit the external screw rods.

[0058] The drive structure of the turbine box is a worm gear structure, and the worm extends out of the turbine box. The worm can be driven to rotate by applying external force, and the worm and worm wheel cooperate to rotate the driving gear, thereby driving the driven gear and the screw. This external force can be applied to the worm by a person swinging a rocker up and down, or by using an electric wrench.

[0059] When the turbine box drives the active gear, the active gear drives the three driven gears to rotate, and the driven gear drives the corresponding outer screw to rotate; the outer screw is fixedly connected to the screw nut seat, and when the outer screw rotates, it drives the screw nut seat to rotate in the same direction, drives the inner screw engaged with the screw nut seat to lift or retract, and drives the load-bearing plates at both ends of the inner screw to move.

[0060] The load-bearing plates at both ends of the three-parallel screw assembly 1 have one end connected to the pull plate 2, and an end clamp 4 is provided at the end of the pull plate; the other end is connected to the broadsword clamp 3.

[0061] The pull plate 2 is a long straight solid plate, and the length of the pull plate can be adjusted according to the length of the tension insulator.

[0062] One side of the large knife clamp 3 is hinged to the bearing plate at one end of the three-parallel screw assembly 1; the other end is H-shaped, which can clamp the connecting plate on one side of the tension insulator and is fastened by two bolts.

[0063] The structure of the end card 4 is similar to that of the broadsword card 3, except that the front view shapes of the two are different: the end card is in the shape of a straight plate, while the broadsword card is in the shape of a curved knife.

[0064] like Figure 7 As shown, when the load transfer tool is used, the large knife clamp and the end clamp respectively connect and fix the connecting plates at both ends of the tension insulator. At this time, the tension insulator is stretched outward by the wires at both ends; through the contraction of the three parallel lead screws, the insulator string is unloaded and the load is transferred to the tool, so that the insulator string can be replaced.

[0065] When performing load transfer operations, closed clamps are also required for assistance. Closed clamps are existing technologies. Closed clamps include front clamps, rear clamps, and screw rods. The front clamp is located at the front end of the closed clamp and is responsible for connecting with the insulator steel cap and clamping the circular clamp on the steel cap. The rear clamp is located at the rear end of the closed clamp, corresponding to the front clamp, and has a similar structure.

[0066] When using this load transfer tool to replace an entire string of tension insulators, the steps are as follows:

[0067] 1) First connect and fix the end card to the wire side connecting plate, and then connect and fix the large knife card to the cross arm side connecting plate.

[0068] 2) First connect the large knife clamp at the conductor end to the load transfer tool to keep the length of the three screw rods consistent, then connect the insulating pull rod, and then connect the insulating pull rod to the front clamp of the large knife clamp at the cross arm end to ensure consistent length and uniform force.

[0069] 3) Then connect the lifting bracket to the top of the fixture and the bottle support rack to the bottom of the fixture.

[0070] 4) After the load transfer tool is subjected to force, the porcelain bottle on the conductor side is unloaded and the replacement operation is carried out.

[0071] 5) The whole string of new insulators is transferred to the work site through the lifting bracket via the capstan, and then lifted by the bottle support rack, placed at the replacement site, and installed with force.

[0072] When using this load transfer tool to replace the conductor side insulator string, the steps are as follows:

[0073] 1) Connect and fix the wire end fixture to the wire side connecting plate.

[0074] 2) Install the closed card front card on the fifth and sixth porcelain bottles so that the closed card front card and the porcelain bottle steel cap can only shake left and right but cannot move forward and backward.

[0075] 3) First connect the wire end clamp to the load transfer tool to keep the length of the three screw rods consistent, then connect the insulating pull rod, and then connect the insulating pull rod to the front clamp of the closed clamp to ensure consistent length and uniform force.

[0076] 4) Then connect the lifting bracket to the top of the fixture and the bottle support rack to the bottom of the fixture.

[0077] 5) After the load transfer tool is subjected to force, the porcelain bottle on the conductor side is unloaded and the replacement operation is carried out.

[0078] 6) Use the lifting bracket to transfer the new 5-6 porcelain bottles to the work site through the capstan, then lift them through the bottle support rack, place them in the replacement location, and install them under stress.

[0079] When using this load transfer tool to replace an insulator string with an intermediate large porcelain bottle string, the steps are as follows:

[0080] 1) Connect the front and rear closed card to the insulator string respectively, with 5-6 insulators in between.

[0081] 2) Install the front and rear cards of the closed card so that the rear card of the closed card and the steel cap of the porcelain bottle can only shake left and right but cannot move forward and backward.

[0082] 3) Connect the front clamp of the closed card to the load transfer tool to keep the length of the three screw rods consistent, then connect the insulating pull rod, and then connect the insulating pull rod to the rear clamp of the closed card to ensure consistent length and uniform force.

[0083] 4) Then connect the lifting bracket to the top of the fixture and the bottle support rack to the bottom of the fixture.

[0084] 5) After the load transfer tool is subjected to force, the porcelain bottle on the cross arm side is unloaded and the replacement operation is carried out.

[0085] 6) Use the lifting bracket to transfer the new 5-6 porcelain bottles to the work site through the capstan, then lift them through the bottle support rack, place them in the replacement location, and install them under stress.

[0086] When using this load transfer tool to replace the insulator string on the crossarm side, the steps are as follows:

[0087] 1) Connect and fix the crossarm side end clamps to the crossarm side connecting plates.

[0088] 2) Install the closed rear clamp on the fifth and sixth porcelain bottles so that the closed rear clamp and the porcelain bottle steel cap can only shake left and right but cannot move forward and backward.

[0089] 3) First connect the cross arm end clamp to the load transfer tool to keep the length of the three screw rods consistent, then connect the insulating pull rod, and then connect the insulating pull rod to the front clamp of the closed clamp to ensure consistent length and uniform force.

[0090] 4) Then connect the lifting bracket to the top of the fixture and the bottle support rack to the bottom of the fixture.

[0091] 5) After the load transfer tool is subjected to force, the porcelain bottle on the cross arm side is unloaded and the replacement operation is carried out.

[0092] 6) Use the lifting bracket to transfer the new 5-6 porcelain bottles to the work site through the capstan, then lift them through the bottle support rack, place them in the replacement location, and install them under stress.

[0093] Finally, it should be noted that the above is only a preferred embodiment of the present invention and is not intended to limit the present invention. Although detailed descriptions have been made with reference to the aforementioned embodiments, those skilled in the art can still modify the technical solutions described in the aforementioned embodiments or replace some of the technical features therein with equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

Claims

1. A load transfer tool for large-section conductors of power transmission lines, characterized in that: It includes a parallel screw rod assembly and a pull plate and a clamp connected at both ends thereof; The parallel screw rod assembly includes screw rods arranged in parallel, and the two ends of the screw rods are fixed with load-bearing plates; the pull plate and the clamp are connected to the load-bearing plate; the clamp can clamp and fix the connecting plates at the two ends of the insulator; The screw rod comprises an inner screw rod and an outer screw rod which are arranged inside and outside. A screw rod nut seat is fixedly arranged at the end of the outer screw rod, and the inner screw rod is threadedly connected with the screw rod nut seat. By rotating the outer screw rod so that the inner screw rod thread is screwed into the outer screw rod and the screw rod nut seat, the load-bearing plate can be tightened and the clamps at both ends can be driven closer.

2. The large-section conductor load transfer tool for power transmission lines according to claim 1, characterized in that: The parallel screw rod assembly is a three-parallel screw rod assembly, including two groups of screw rod assemblies arranged opposite to each other. The screw rod assembly includes a load-bearing plate, three inner screw rods and outer screw rods and screw rod nut seats arranged outside the inner screw rods.

3. The large-section conductor load transfer tool for power transmission lines according to claim 2, characterized in that: The inner screw is a slender solid straight rod with threads; the load-bearing plate is a triangular high-strength titanium alloy plate; three inner screws are fixed to the three corners of the load-bearing plate; the outer screw is a hollow long rod, and the screw nut seat is fixed to the end of the outer screw; the three outer screws are respectively sleeved on the outer ends of each inner screw, and the threads of the inner screw are engaged with the screw nut seats.

4. The large-section conductor load transfer tool for power transmission lines according to claim 2, characterized in that: A gear connecting rod is inserted and fixed between two opposite external screw rods to connect and fix the two external screw rods; a driven gear is fixed outside the gear connecting rod.

5. The large-section conductor load transfer tool for power transmission lines according to claim 4, characterized in that: The three groups of opposite external screw rods are all fixed with driven gears, and the central position of the three driven gears is provided with a driving gear, and the driving gear is meshed with each driven gear.

6. The large-section conductor load transfer tool for power transmission lines according to claim 5, characterized in that: The driving gear is connected to the driving structure of the turbine box, and the turbine box is slidably connected to three sets of external screw rods at the same time.

7. The large-section conductor load transfer tool for power transmission lines according to claim 6, characterized in that: The driving structure of the turbine box is a turbine worm structure, and the worm extends out of the turbine box.

8. The large-section conductor load transfer tool for power transmission lines according to claim 1, characterized in that: The load-bearing plates at both ends of the parallel screw rod assembly have one end connected to the pull plate, and an end clamp is arranged at the end of the pull plate; and the other end is connected to the broadsword clamp.

9. The large-section conductor load transfer tool for power transmission lines according to claim 8, characterized in that: The outer ends of the end clamp and the broadsword clamp are H-shaped clamping seats, and the clamping seats are provided with at least two fasteners connected with the connecting plates at both ends of the insulator.

10. A method for transferring load on a power transmission line using the load transfer tool for large-section conductors of a power transmission line according to any one of claims 1 to 9, wherein the steps are as follows: A. The method for transferring the load of a whole string of tension insulators is as follows: 1) Connect and fix the end card with the wire side connecting plate, and then connect and fix the knife card with the cross arm side connecting plate; 2) Connect the large knife clamp at the conductor end to the load transfer tool to keep the length of the three screw rods consistent, and then connect the insulating pull rod, which is then connected to the front clamp of the large knife clamp at the cross arm end to ensure consistent length and uniform force; 3) Connect the lifting bracket to the top of the fixture and the bottle support rack to the bottom of the fixture; 4) After the load transfer tool is stressed, the porcelain bottle on the conductor side unloads the force, the load is transferred, and the replacement operation is carried out; B. The method for transferring the load of the insulator string on the conductor side is as follows: 1) Connect and fix the wire end fixture to the wire side connecting plate; 2) Install the closed card front card on the fifth and sixth porcelain bottles, so that the closed card front card and the porcelain bottle steel cap can only shake left and right, and cannot move forward and backward; 3) Connect the wire end fixture to the load transfer tool, and then connect the insulating pull rod and the closed clamp front clamp; 4) Connect the lifting bracket to the top of the fixture and the bottle support rack to the bottom of the fixture; after the load transfer tool is stressed, perform the replacement operation; C. The method of replacing the insulator string with the middle large porcelain bottle string is as follows: 1) Connect the front and rear cards of the closed card to the insulator string respectively, with 5-6 insulators in between; 2) Install the front and rear cards of the closed card so that the rear card of the closed card and the steel cap of the porcelain bottle can only shake left and right, but cannot move forward and backward; 3) Connect the front clamp of the closed card to the load transfer tool, and then connect the insulating pull rod to the rear clamp of the closed card; 4) Connect the lifting bracket to the top of the fixture and the bottle support rack to the bottom of the fixture; 5) After the load transfer tool is stressed, the porcelain bottle on the cross arm unloads the force, the load is transferred, and the replacement operation is carried out; D. The method for replacing the insulator string on the crossarm side is as follows: 1) Connect and fix the cross arm side end fixture with the cross arm side connecting plate; 2) Install the closed card back card on the fifth and sixth porcelain bottles, so that the closed card back card and the porcelain bottle steel cap can only shake left and right, and cannot move forward and backward; 3) Connect the cross arm end clamp to the load transfer tool, and then connect the insulating pull rod and the closed clamp front clamp; 4) Then connect the lifting bracket to the top of the fixture and the bottle support rack to the bottom of the fixture; 5) After the load transfer tool is subjected to force, the porcelain bottle on the cross arm side unloads the force, the load is transferred, and the replacement operation is carried out.

Citation Information

Patent Citations

  • Operating method for replacing 220 kV U210B / 170 type strain insulator string in live mode

    CN103219671A

  • Multi-lead-screw parallel drive device

    CN103939555A

  • Motor-driven lead screw nut pair lifting mechanism

    CN108087518A

  • Worm and gear speed reducer

    CN214118883U

  • Load transfer tool for large-section wire of power transmission line

    CN223156586U