Electric power dispatching plan calculation method and system based on wavelet transform measured data
Through wavelet transformation, the disconnection transmission distribution factor of the power system is calculated, and the power scheduling plan is formulated, which solves the problem of inaccurate calculations in the existing technology, and achieves the rapid adaptation and safe operation of the power system.
Patent Information
- Application Number
- CN202411033271.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-30
- Publication Date
- 2024-11-15
AI Technical Summary
The existing power scheduling plan calculation methods based on SCADA data and mathematical models cannot adapt to the rapid changes in network topology and generator sets or loads in a timely manner, resulting in inaccurate calculation results and ineffective handling of power system failures, especially in the rapid growth of new energy sources. It is more prominent when it is.
Using the actual measured data calculation method based on wavelet transformation, by obtaining real-time PMU data of the power system, discrete wavelet transformation and denoising reconstruction, establishing active power and current increment matrix, calculating the circuit-break transmission distribution factor, and formulating the N-1 safety The standard power scheduling plan is independent of the physical parameters of the power system.
It realizes the rapid and accurate calculation of the power scheduling plan under the N-1 safety standard of the power system, which can adapt to network topology and load changes, predict branch flow changes after failure, ensure safe operation of the power grid, and solves the problem of inaccurate calculations of traditional methods.
Smart Images

Figure CN118970911A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of power system dispatching and operation, and in particular relates to a method and system for calculating a power dispatching plan based on wavelet transform measured data. Background Art
[0002] Every day, power dispatchers need to make power dispatch plans that meet the N-1 safety criteria through a large number of calculations. The calculation method of the power dispatch plan under the traditional N-1 safety criteria is based on the real-time operating data required for the reliability of the entire power system provided by the monitoring and data acquisition system (SCADA) and the latest system simulation mathematical model, so as to ensure that the system can withstand various disturbances and failures, such as a sudden failure of a transmission branch and shutdown. The traditional SCADA system updates data every 2 to 4 seconds to provide power system operators with real-time status data of the power system. On the other hand, the existing power dispatch plan under the N-1 safety criteria calculated based on the mathematical simulation model relies on accurate and timely updated network topology parameters.
[0003] Therefore, these N-1 safety criteria based on SCADA data and mathematical models are not able to adapt to the rapid disturbances and changes from the network topology, generators or loads. These disturbances and changes will obviously change some topologies and parameters, so that the dispatch plans that meet the N-1 safety criteria calculated by the mathematical model without timely data update will be wrong or even unusable. Data errors and the inability to grasp the current state of the transmission branch in time, and the inability to deal with the fault in time and effectively when it occurs are the causes of many serious power outages. Therefore, the existing technology for monitoring and protecting the power system based on the system model no longer fully meets the recent development needs of the power industry, especially with the rapid growth of new energy, the intermittent and random characteristics of its output have exacerbated the impact of such characteristics on the power system. Therefore, a method and system that does not rely on power system parameters and can more quickly and accurately calculate the power dispatch plan under the N-1 safety criteria is more practical and urgent. Summary of the invention
[0004] In order to overcome the deficiencies in the prior art, the present invention aims to provide a method for calculating a power dispatch plan based on wavelet transform measured data, which can quickly and accurately calculate the power dispatch plan under the N-1 safety criterion of the power system without relying on changes in the physical parameters of the power system, analyze and predict whether other lines are overloaded when a line fails, and ensure the safe operation of the power grid.
[0005] In order to achieve the above object, the technical solution adopted by the present invention is:
[0006] The power dispatching plan calculation method based on wavelet transform measured data is implemented based on the following steps:
[0007] 1) Obtain the power system grid topology data and the real-time measurement data of PMU on the grid at each moment in a certain period of time;
[0008] 2) Perform discrete wavelet transform on PMU measured data to remove noise and reconstruct;
[0009] 3) Based on the denoising and reconstruction of PMU measured data, the bus static injected active power and branch active power flow increment matrix are established;
[0010] 4) calculating the power system disconnection transmission distribution factor according to the active power and branch active power flow increment matrix;
[0011] 5) Calculating a power dispatch plan that meets the N-1 safety criterion based on the power system disconnection transmission distribution factor.
[0012] Wherein, in step 1), it is assumed that the power system consists of a group of N+1 buses, wherein the N+1th bus is a reference bus; and V={0, 1, ..., N} represents the N+1 bus set, and E={1, ..., L} represents the L branch set; then the power system grid topology data includes N+1 buses, L branches and a corresponding grid topology association matrix;
[0013] In a certain time period, at the start time 0 and at each time kΔt thereafter, the real-time measurement data of the PMU includes the bus net injected active power and branch active power flow data, where k=0,1,…,M, Δt=1 / 50 second, that is, the sampling frequency is 50 Hz, M is an integer multiple of 2 / Δt=100 and M>N;
[0014] In the PMU measured data obtained, at time t = 0, the static injected active power of bus i∈V and the active power flow of branch l∈E are marked as P i (0) and P l (0); the bus static injected active power and branch active power flow at time kΔt are marked as P i (kΔt) and P l (kΔt); use P i represents the internal time sampling sequence signal of the bus i∈V, which is P i (kΔt); P l represents the time sampling sequence signal of the (m,n)∈E branch, which is P l (kΔt).
[0015] Step 2) specifically includes the following steps:
[0016] 2-1)P i and P lPerform discrete wavelet transform respectively to obtain the corresponding discrete wavelet transform component combination f(P i ) and f(P l ); each component combination contains s components;
[0017] 2-2) denoising and reconstructing the discrete wavelet transform component;
[0018] The PMU measured data is subjected to discrete wavelet transform denoising and reconstruction with 2 Hz as the threshold; the frequency of each discrete wavelet transform component is calculated, and the component containing the target frequency is subjected to frequency threshold denoising based on the threshold; that is, the discrete wavelet transform components with frequencies greater than the threshold are set to zero, and the discrete wavelet transform components with frequencies less than or equal to the threshold are kept unchanged, and then the processed components are reconstructed as the denoised reconstructed signal; the discrete wavelet transform component combination f(P i ) and f(P l ) The discrete signals after denoising and reconstruction are respectively identified as and
[0019] For k = 0, 1, ..., M, its and The corresponding sampling values are and
[0020] Step 3) specifically includes:
[0021] The net active power increment of the denoised and reconstructed bus corresponding to the time kΔt is:
[0022]
[0023] Logo is an M-dimensional vector, whose kth component is Logo Reconstruct bus active power increment matrix for denoising; is an M×N matrix, whose i-th column vector is
[0024] The denoised and reconstructed branch active power flow corresponding to time kΔt is identified as Then the denoised reconstructed power flow increment corresponding to time kΔt is:
[0025]
[0026] Logo is the branch power flow increment vector, is an L-dimensional vector, whose kth component is
[0027] Step 4) Calculate the disconnection transmission distribution factor, the specific steps are:
[0028] definition Identifies the injection transfer distribution factor of branch l with respect to bus i, that is, the sensitivity of the active power flow on branch l to the injected active power of bus i; Ψ l is an N-dimensional vector whose i-th component is Then calculate
[0029]
[0030] For each branch l, calculate N injection transfer distribution factors A total of LN injection transfer distribution factors were obtained;
[0031] use Identify the power transfer distribution factor of branch l with respect to the power transferred from bus i to bus j, then
[0032] use Identifies the branch disconnection distribution factor of branch l with respect to branch l', i.e., the sensitivity of the flow change on branch l after branch l' is disconnected; It is the current on the branch road l', is the increment of the power flow on branch l after branch l' is disconnected, then It is defined by the following equation:
[0033]
[0034] For branches l and l', assuming that l' is the branch from bus m to bus n, the solution is obtained based on the denoised and reconstructed PMU measurement data. The calculation formula is:
[0035]
[0036] Break transmission distribution factor is the increment of the flow on branch l when unit power is transferred from bus i to bus j, after branch l' is disconnected; that is, when power ΔF is transferred from bus i to bus j, the increment of the flow on branch l after branch l' is disconnected is ΔT, then The calculation formula of its circuit breaker transmission distribution factor is:
[0037]
[0038] Step 5) Formulate a power dispatch plan with a power transmission from bus i to bus j of no more than ΔF under the N-1 safety criterion; the maximum increment of the power flow on branch l after branch l' is disconnected is set up Assume the flow on branch l is P l , whose upper limit is The power dispatch plan under the N-1 safety criterion is: for l∈L, the inequality is satisfied:
[0039]
[0040] Among them, k l ≥0 and for all branches l, at least one of the two inequalities above is equal; take k = Min l∈L k l , then kΔF is the maximum transmission power from bus i to bus j that meets the N-1 safety criterion of the power system, and is the power dispatch plan of the power system that meets the N-1 safety criterion; that is, after any branch in the system fails and is disconnected, the power system can still maintain safe operation and implement the power dispatch plan of transmitting power kΔF from bus i to bus j.
[0041] Correspondingly, the present invention also proposes a power dispatch plan calculation system based on wavelet transform measured data. The calculation system includes a data acquisition module, a discrete wavelet transform denoising and reconstruction module, an incremental matrix generation module, a first calculation module and a second calculation module.
[0042] The data acquisition module includes a first data acquisition module and a second data acquisition module, wherein the first data acquisition module is used to obtain the power system grid topology data, and the second data acquisition module is used to obtain the PMU measured data on the power grid at each moment during a certain period of time;
[0043] The discrete wavelet transform denoising and reconstruction module performs discrete wavelet transform on the acquired PMU measured data, performs frequency threshold denoising and reconstructs the data;
[0044] The incremental matrix generation module is used to establish a bus net injected active power incremental matrix and a branch active power flow incremental matrix based on discrete wavelet transform denoising and reconstruction data;
[0045] The first calculation module is used to calculate the disconnection transmission distribution factor;
[0046] The second calculation module is used to calculate a power dispatch plan that meets the N-1 safety criterion.
[0047] The beneficial effects of the present invention are:
[0048] The method for calculating the power dispatch plan based on the real-time measurement data of the PMU of the present invention is capable of adapting to the changes in the power grid parameters caused by the rapid disturbance and change of the network topology, the generator set or the load, and quickly and accurately calculating the power dispatch plan that meets the N-1 safety criterion, and solves the problem of inaccurate calculation of the power dispatch plan caused by the intermittent and random characteristics of the output of the existing power system, so that the changes in the power flow dispatch plan of each branch after a branch fails can be accurately and quickly predicted, and whether the branch is overloaded or exceeds the limit can be predicted, so as to ensure the safe operation of the power grid. BRIEF DESCRIPTION OF THE DRAWINGS
[0049] Figure 1 It is a schematic diagram of the calculation process of the present invention;
[0050] Figure 2 It is a schematic diagram of the system structure of the present invention. DETAILED DESCRIPTION
[0051] The principles and features of the present invention are described below in conjunction with the accompanying drawings. The examples given are only used to explain the present invention and are not intended to limit the scope of use of the present invention.
[0052] like Figure 1 As shown, the present invention proposes a method for calculating a power dispatch plan based on wavelet transform measured data, which is implemented based on the following steps:
[0053] 1) Obtain the power system grid topology data and the real-time measurement data of PMU on the grid at each moment in a certain time period.
[0054] Assume that the power system consists of a set of N+1 buses, where the N+1th bus is a reference bus; and V={0, 1, ..., N} represents the N+1 bus set, and E={1, ..., L} represents the L branch set; then the power system grid topology data includes N+1 buses, L branches and the corresponding grid topology association matrix.
[0055] In a certain time period, starting from time 0 and at each time kΔt thereafter, the real-time measurement data of the PMU includes the bus net injected active power and branch active power flow data, where k=0,1,…,M, Δt=1 / 50 second, that is, the sampling frequency is 50 Hz, M is an integer multiple of 2 / Δt=100 and M>N.
[0056] In the PMU measured data obtained, at time t = 0, the static injected active power of bus i∈V and the active power flow of branch l∈E are marked as P i (0) and P l (0); the bus static injected active power and branch active power flow at time kΔt are marked as P i (kΔt) and P l(kΔt); use P i represents the internal time sampling sequence signal of the bus i∈V, which is P i (kΔt)(k=0,…,M);P l (l∈E) represents the time sampling sequence signal of the (m,n)∈E branch, which is P l (kΔt)(k=0,…,M).
[0057] 2) Perform discrete wavelet transform on the PMU measured data to remove noise and reconstruct. The specific steps include:
[0058] 2-1)P i (i∈V) and P l (l∈E) respectively perform discrete wavelet transform (DWT) to obtain the corresponding discrete wavelet transform component combination f(P i ) and f(P l ); each component combination contains s components;
[0059] 2-2) denoising and reconstructing the discrete wavelet transform component;
[0060] The discrete wavelet transform (DWT) components are denoised and reconstructed. The frequency of changes in the power system bus power and branch power flow is low, concentrated below 2 Hz; while the noise frequency is high, concentrated above 10 Hz. The present invention uses 2 Hz as a threshold to perform discrete wavelet transform (DWT) denoising and reconstruction on the PMU measured data; calculates the frequency of each component of the discrete wavelet transform (DWT), and performs frequency threshold denoising on the components containing the target frequency based on the threshold; that is, sets the discrete wavelet transform (DWT) components with a frequency greater than the threshold to zero, keeps the discrete wavelet transform (DWT) components with a frequency less than or equal to the threshold unchanged, and then reconstructs the processed components as the denoised reconstructed signal; the discrete wavelet transform (DWT) component combination f(P i )(i∈V) and f(P l The discrete signals after denoising and reconstruction are respectively identified as and
[0061] For k = 0, 1, ..., M, and The corresponding sampling values are and
[0062] 3) According to the denoising and reconstruction of PMU measured data, the bus static injection active power and branch active power flow increment matrix are established; specifically including:
[0063] The net active power increment of the denoised and reconstructed bus corresponding to the time kΔt is:
[0064]
[0065] Logo is an M-dimensional vector, whose kth component is Logo Reconstruct the bus active power increment matrix for denoising; is an M×N matrix, whose i-th column vector is
[0066] The denoised and reconstructed branch active power flow corresponding to time kΔt is identified as Then the denoised reconstructed power flow increment corresponding to time kΔt is:
[0067]
[0068] Logo is the branch power flow increment vector, is an L-dimensional vector, whose kth component is
[0069] 4) Calculate the power system disconnection transmission distribution factor according to the active power and branch active power flow increment matrix. The specific steps are:
[0070] definition Identifies the injection transfer distribution factor of branch l with respect to bus i, that is, the sensitivity of the active power flow on branch l to the injected active power of bus i; Ψ l is an N-dimensional vector whose i-th component is Then calculate
[0071]
[0072] For each branch l, calculate N injection transfer distribution factors A total of LN injection transfer distribution factors were obtained;
[0073] use Identify the power transfer distribution factor of branch l with respect to the power transferred from bus i to bus j, then
[0074] use Identifies the branch disconnection distribution factor of branch l with respect to branch l', i.e., the sensitivity of the flow change on branch l after branch l' is disconnected; It is the current on the branch road l', is the increment of the power flow on branch l after branch l' is disconnected, then It is defined by the following equation:
[0075]
[0076] For branches l and l', assuming that l' is the branch from bus m to bus n, the solution is obtained based on the denoised and reconstructed PMU measurement data. The calculation formula is:
[0077]
[0078] Break transmission distribution factor is the increment of the flow on branch l when unit power is transferred from bus i to bus j, after branch l' is disconnected; that is, when power ΔF is transferred from bus i to bus j, the increment of the flow on branch l after branch l' is disconnected is ΔT, then The calculation formula of the disconnection transmission distribution factor is:
[0079]
[0080] 5) Calculating a power dispatch plan that meets the N-1 safety criterion based on the power system disconnection transmission distribution factor.
[0081] Formulate a power dispatch plan with the power transmission from bus i to bus j not greater than ΔF under the N-1 safety criterion; the maximum increment of the power flow on branch l after branch l' is disconnected is set up Assume the flow on branch l is P l , whose upper limit is The power dispatch plan under the N-1 safety criterion is: for l∈L, the inequality is satisfied:
[0082]
[0083] Among them, k l ≥0 and for all branches l, at least one of the two inequalities above is equal; take k=Min l∈L k l , then kΔF is the maximum transmission power from bus i to bus j that meets the N-1 safety criterion of the power system, and is the power dispatch plan of the power system that meets the N-1 safety criterion; that is, after any branch in the system fails and is disconnected, the power system can still maintain safe operation and implement the power dispatch plan of transmitting power kΔF from bus i to bus j.
[0084] Traditional technologies for monitoring and protecting power systems based on power system parameters and mathematical models will not be applicable when power system disturbances occur due to changes in system parameters, and therefore no longer fully meet the recent development needs of the power industry, especially the rapid growth of new energy sources, whose intermittent and random output characteristics have exacerbated the impact of such characteristics on the power system.
[0085] Compared with the prior art, the present invention is different from the traditional method and system that completely relies on power system parameters to solve the power flow model to calculate the power dispatch plan. The present invention calculates the power dispatch plan under the N-1 safety criterion through PMU real-time measurement data, so that the power dispatch plan can be calculated quickly and accurately when the power system parameters change, so as to quickly and accurately predict the changes in the power flow of each branch after a branch fails, predict whether the branch is overloaded and exceeds the limit, and ensure the safe operation of the power grid.
[0086] like Figure 2 As shown, accordingly, the present invention also proposes a power dispatch plan calculation system based on wavelet transform measured data, which includes a data acquisition module, a discrete wavelet transform denoising and reconstruction module, an incremental matrix generation module, a first calculation module and a second calculation module.
[0087] The data acquisition module includes a first data acquisition module and a second data acquisition module, wherein the first data acquisition module is used to obtain the power system grid topology data, and the second data acquisition module is used to obtain the PMU measured data on the power grid at each moment during a certain period of time;
[0088] The discrete wavelet transform denoising and reconstruction module performs discrete wavelet transform on the acquired PMU measured data, performs frequency threshold denoising and reconstructs the data;
[0089] The incremental matrix generation module is used to establish a bus net injected active power incremental matrix and a branch active power flow incremental matrix based on discrete wavelet transform denoising and reconstruction data;
[0090] The first calculation module is used to calculate the disconnection transmission distribution factor;
[0091] The second calculation module is used to calculate a power dispatch plan that meets the N-1 safety criterion.
[0092] The method for calculating the power dispatch plan based on the real-time measurement data of the PMU of the present invention is capable of adapting to the changes in the grid parameters caused by the rapid disturbance and changes from the network topology, the generator set or the load, and quickly and accurately calculating the power dispatch plan that meets the N-1 safety criterion, thereby solving the problem of inaccurate calculation of the power dispatch plan caused by the intermittent and random characteristics of the output of the existing power system.
[0093] Obviously, the embodiments described above are only some embodiments of the present application, rather than all embodiments. The preferred embodiments of the present application are given in the accompanying drawings, but they do not limit the patent scope of the present application. The present application can be implemented in many different forms. On the contrary, the purpose of providing these embodiments is to make the understanding of the disclosure of the present application more thorough and comprehensive. Although the present application is described in detail with reference to the aforementioned embodiments, for those skilled in the art, it is still possible to modify the technical solutions recorded in the aforementioned specific implementation methods, or to perform equivalent replacement of some of the technical features therein. Any equivalent structure made using the contents of the specification and drawings of this application, directly or indirectly used in other related technical fields, is similarly within the scope of patent protection of this application.
Claims
1. A method for calculating a power dispatch plan based on wavelet transform measured data, characterized in that: The method is implemented based on the following steps: 1) Obtain the power system grid topology data and the real-time measurement data of PMU on the grid at each moment in a certain period of time; 2) Perform discrete wavelet transform on PMU measured data to remove noise and reconstruct; 3) Based on the denoising and reconstruction of PMU measured data, the bus static injected active power and branch active power flow increment matrix are established; 4) calculating the power system disconnection transmission distribution factor according to the active power and branch active power flow increment matrix; 5) Calculating a power dispatch plan that meets the N-1 safety criterion based on the power system disconnection transmission distribution factor.
2. The method for calculating electric power dispatching plan based on wavelet transform measured data according to claim 1 is characterized in that: In step 1), it is assumed that the power system consists of a group of N+1 buses, wherein the N+1th bus is a reference bus; and V={0, 1, ..., N} represents the N+1 bus set, and E={1, ..., L} represents the L branch set; then the power system grid topology data includes N+1 buses, L branches and a corresponding grid topology association matrix; In a certain time period, at the start time 0 and at each time kΔt thereafter, the real-time measurement data of the PMU includes the bus net injected active power and branch active power flow data, where k=0,1,…,M, Δt=1 / 50 second, that is, the sampling frequency is 50 Hz, M is an integer multiple of 2 / Δt=100 and M>N; In the PMU measured data obtained, at time t = 0, the static injected active power and The branch active power flows are marked as P i (0) and The busbar static active power injection and branch active power flow at time kΔt are marked as P i (kΔt) and Use P i Represents the internal time sampling sequence signal of the bus i∈V, which is P i (kΔt); Represents the time sampling sequence signal of the (m,n)∈E branch, which is 3. The method for calculating electric power dispatching plan based on wavelet transform measured data according to claim 2 is characterized in that: Step 2) specifically includes the following steps: 2-1)P i and Perform discrete wavelet transform respectively to obtain the corresponding discrete wavelet transform component combination f(P i )and Each component combination contains s components; 2-2) denoising and reconstructing the discrete wavelet transform component; The PMU measured data is subjected to discrete wavelet transform denoising and reconstruction with 2 Hz as the threshold; the frequency of each discrete wavelet transform component is calculated, and the component containing the target frequency is subjected to frequency threshold denoising based on the threshold; that is, the discrete wavelet transform components with frequencies greater than the threshold are set to zero, and the discrete wavelet transform components with frequencies less than or equal to the threshold are kept unchanged, and then the processed components are reconstructed as the denoised reconstructed signal; the discrete wavelet transform component combination f(P i )and The discrete signals after denoising and reconstruction are respectively identified as and For k = 0, 1, ..., M, its and The corresponding sampling values are and 4. The method for calculating electric power dispatching plan based on wavelet transform measured data according to claim 3 is characterized in that: Step 3) specifically includes: The net active power increment of the denoised and reconstructed bus corresponding to the time kΔt is: Logo is an M-dimensional vector, whose kth component is Logo Reconstruct bus active power increment matrix for denoising; is an M×N matrix, whose i-th column vector is The denoised and reconstructed branch active power flow corresponding to time kΔt is identified as Then the denoised reconstructed power flow increment corresponding to time kΔt is: Logo is the branch power flow increment vector, is an L-dimensional vector, whose kth component is 5. The method for calculating electric power dispatching plan based on wavelet transform measured data according to claim 4 is characterized in that: Step 4) Calculate the disconnection transmission distribution factor, the specific steps are: definition Identify branch Regarding the injection transfer distribution factor on bus i, that is, the branch The active power flow on bus i corresponds to the sensitivity of the injected active power; is an N-dimensional vector whose i-th component is Then calculate For each branch Calculate the N injection transfer distribution factors A total of LN injection transfer distribution factors were obtained; use Identify branch Regarding the power transfer distribution factor of power from bus i to bus j, use Identify branch About Zhilu The branch disconnection distribution factor is After disconnection, the branch sensitivity to changes in upstream tidal currents; It is a branch road The trend on It is a branch road Disconnect the rear branch The increment of the upstream flow is It is defined by the following equation: For branch road and set up is the branch from bus m to bus n, and is solved based on denoising and reconstructing PMU measurement data The calculation formula is: Break transmission distribution factor is the unit power transmitted from bus i to bus j when the branch After disconnection, the branch The increment of the upstream flow; that is, when the power ΔF is transferred from bus i to bus j, the branch Disconnect the rear branch The increment of the upflow is ΔT, then ΔT / ΔF; the calculation formula of its disconnection transmission distribution factor is:
6. The method for calculating electric power dispatching plan based on wavelet transform measured data according to claim 5 is characterized in that: Step 5) Formulate a power dispatch plan that ensures that the power transmitted from bus i to bus j is no more than ΔF under the N-1 safety criterion; Disconnect the rear branch The maximum increment of the upflow is set up Set up branch road The trend is Its upper limit is The power dispatch plan under the N-1 safety criterion is: Satisfies the inequality: in, And make all branches At least one of the two inequalities in the above formula takes an equal sign; Then kΔF is the maximum transmission power from bus i to bus j that meets the N-1 safety criterion of the power system, and is the power dispatch plan for the power system that meets the N-1 safety criterion; that is, after any branch in the system fails and is disconnected, the power system can still maintain safe operation and implement the power dispatch plan to transfer power kΔF from bus i to bus j.
7. The method for calculating electric power dispatching plan based on wavelet transform measured data according to claim 6 is implemented by a system for calculating electric power dispatching plan based on wavelet transform measured data, and is characterized in that: The computing system comprises a data acquisition module, a discrete wavelet transform denoising and reconstruction module, an incremental matrix generation module, a first computing module and a second computing module. The data acquisition module includes a first data acquisition module and a second data acquisition module, wherein the first data acquisition module is used to obtain the power system grid topology data, and the second data acquisition module is used to obtain the PMU measured data on the power grid at each moment during a certain period of time; The discrete wavelet transform denoising and reconstruction module performs discrete wavelet transform on the acquired PMU measured data, performs frequency threshold denoising and reconstructs the data; The incremental matrix generation module is used to establish a bus net injected active power incremental matrix and a branch active power flow incremental matrix based on discrete wavelet transform denoising and reconstruction data; The first calculation module is used to calculate the disconnection transmission distribution factor; The second calculation module is used to calculate a power dispatch plan that meets the N-1 safety criterion.