Construction method for erecting and installing large-span steel truss girder in segmented and fragmented mode

By segmenting the large-span steel trusses and erecting temporary supports, the safety risks and cost problems of the installation of underground steel trusses in steep terrain are solved, and efficient and safe construction results are achieved.

CN118979438APending Publication Date: 2024-11-19GANSU ROAD & BRIDGE CONSTR GROUP +1
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202410912299.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-09
Publication Date
2024-11-19

AI Technical Summary

Technical Problem

In construction sites with steep terrain and large drops, existing large-span steel truss installation methods such as the pushing method and the crane lifting method have problems of safety risks and increased costs, and it is impossible to set up a stable crane support point, which is suitable for steel Truss mount and installation.

Method used

The installation and construction method of large-span steel truss is adopted. By dividing the steel truss into two sections A and B, pre-assembled and on-site assembled, and a temporary steel bracket is erected between the guide bridge and the main bridge. The bridge stud and temporary bracket are accurately installed to reduce lifting load and improve installation safety and accuracy.

Benefits of technology

It reduces construction difficulty and accident risk, improves installation efficiency and construction quality, shortens the construction cycle, and maximizes economic benefits.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118979438A_ABST
    Figure CN118979438A_ABST
Patent Text Reader

Abstract

The invention relates to the field of large-span steel truss girder construction, in particular to a large-span steel truss girder segmented and fragmented erection and installation construction method, which comprises the following steps of: dividing a steel truss girder into segments according to the structure, the size and the field limiting conditions of the steel truss girder, specifically dividing the steel truss girder into a segment A and a segment B, manufacturing and pre-assembling; pre-assembled components are transported to the site, formal assembly is conducted on an assembling platform built on the site, and meanwhile a temporary steel structure support is built between the main bridge and the approach bridge; starting to erect and install the steel trusses, namely installing a bridge girder erection machine and moving forwards through holes, enabling front supporting legs to fall onto a temporary steel structure support, sequentially erecting a left section A steel truss and a right section A steel truss, and after the left section A steel truss and the right section A steel truss are in place; a secondary through hole of the bridge girder erection machine moves forwards, a front supporting leg falls to a main bridge cover beam, a middle supporting leg falls to a temporary support, and a B truss girder left piece and a B truss girder right piece are erected in sequence; and after the section A and the section B of the steel truss girder are in place, a jack is arranged on the temporary support to adjust the line type of the main girder, and two sections of truss girders are welded after the line type of the main girder meets the requirement.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of large-span steel truss girder construction, and in particular to a construction method for erecting and installing large-span steel truss girder in sections and pieces. Background Art

[0002] Large-span steel trusses are widely used in bridge projects in the fields of highways, railways and urban rail transit due to their advantages such as high strength, light weight and large span.

[0003] The mature methods for installing large-span steel trusses at home and abroad mainly include the top-pushing method and the crane hoisting method. The top-pushing method sets the starting support point and gradually pushes the prefabricated bridge components horizontally to the predetermined position on one side of the bridge through equipment such as hydraulic jacks; the crane hoisting method sets up special hoisting equipment on the bridge deck or on the ground to complete the hoisting and installation of the steel trusses; the above construction methods have good safety and stability during the bridge construction process, so they are widely used in the field of bridge engineering.

[0004] However, there are limitations when using the above methods in construction sites with steep terrain and large drop heights. The top-pushing method may face the problem of large height differences of dropped beams and high safety risks. If a leading beam is set up, the cost will increase. The crane hoisting method cannot set up a stable crane support point and is not suitable for the erection and installation of steel trusses. Therefore, it is necessary to conduct in-depth research and summary on the construction technology of large-span steel truss installation in such terrains. Summary of the invention

[0005] The purpose of the present invention is to solve the problems raised in the above-mentioned background technology and to propose a construction method for erecting and installing a large-span steel truss girder in sections and pieces.

[0006] In order to achieve the above object, the present invention adopts the following technical solutions:

[0007] A construction method for erecting and installing a large-span steel truss girder in sections and pieces, characterized by comprising the following steps:

[0008] Step 1: According to the steel truss structure, size and site constraints, the steel truss is divided into sections, specifically into sections A and B, and manufactured and pre-assembled;

[0009] Step 2: transport the pre-assembled components to the site and assemble them on the assembly platform built on site. At the same time, set up a temporary steel structure support between the main bridge and the approach bridge;

[0010] Step 3: Start to erect and install the steel trusses. The steps are as follows: first install the bridge erection machine and move forward through the hole, the front leg falls on the temporary steel structure support, and the left A and right A sections of the steel trusses are erected in turn, and the left and right sections of the A section of the steel trusses are in place; then, the bridge erection machine moves forward through the hole for the second time, the front leg falls to the main bridge cap beam, the middle leg falls to the temporary support, and the left and right sections of the B trusses are erected in turn; after the A and B sections of the steel trusses are in place, set the jack on the temporary support to adjust the main beam line shape, and weld the two segment trusses after the main beam linearity meets the requirements;

[0011] Step 4: Remove the bridge-building machine and temporary support.

[0012] Preferably, in step one, after the steel trusses are divided, they are manufactured according to the design requirements; after the manufacturing is completed, they are pre-assembled in the factory, and during the pre-assembly process of the steel trusses, each component is clearly marked to ensure that they can be accurately identified and installed during on-site assembly; finally, the pre-assembly process is recorded in detail for reference in subsequent construction.

[0013] Preferably, in step 2, the steps of formal assembly are as follows:

[0014] (1) Construction preparation

[0015] When the components are transported to the site, the stand columns are first installed on the two-piece stand base. Then, the stand columns are fixed with expansion bolts, and the camber is adjusted according to the design drawing requirements.

[0016] (2) Assembly of Section A truss

[0017] Considering the linear requirements of the whole span steel truss, when assembling the A section truss, the main truss side section A and the main truss middle section B1 are hoisted on the No. 1 stand to adjust the camber and linearity according to the design requirements; then the two main trusses of section A and section B1 are spot welded and firmly connected by the stacking plate method; finally, the main truss diagonal web between the main truss side section A and the main truss middle section B1 is bolted, and the main truss upper chord and main truss lower chord are welded;

[0018] (3) Assembly of Section B Truss

[0019] First, hoist the main truss middle section B2, main truss middle section B3 and main truss side section A onto the No. 2 stand, and adjust the camber as per the design requirements; then, use the stacking plate method to spot weld the three main trusses, B2, B3 and A, to connect them firmly; finally, hoist and bolt the main truss diagonal web members between the main truss middle section B2, main truss middle section B3 and main truss side section A, and weld the main truss upper chord and main truss lower chord.

[0020] Preferably, in step 2, the erection of the temporary steel structure support comprises the following steps:

[0021] (1) Temporary support foundation

[0022] The bottom of the temporary support column adopts a reinforced concrete foundation, the top of the foundation is set with an embedded steel plate, and the support steel pipe column is welded and fixed to the embedded parts;

[0023] (2) Temporary support erection

[0024] A steel structure support is set up above the concrete foundation, and a support platform for the front legs of the bridge erecting machine is set up on the upper part of the steel structure platform to ensure that the front legs of the bridge erecting machine are supported stably. The temporary support uses Φ325×8 round tube columns and Steel pipes are used as diagonal braces; for the up and down passages of steel beams, 1-meter-wide up and down ramps are set up in some temporary supports. The ramp skeleton is 3-4 scaffolding steel pipes, and 0.8×1.2m bamboo lotuses are laid on top and fixed to the scaffolding steel pipes. At the same time, safety guardrails and safety enclosure measures are taken on both sides to ensure the safety of pedestrians and work.

[0025] Preferably, in step three, the specific steps of erecting and installing the steel truss are as follows:

[0026] (1) Bridge erection machine through hole

[0027] ① The front outriggers are lifted up with reverse supports, the rear outriggers are lowered, and the pins are inserted to raise the main beam away from the middle support and reverse supports; the middle support is moved forward with the 1# overhead crane, and the reverse support is moved forward with the 2# overhead crane; after the middle support and reverse supports are in place, the reverse supports support the main beam, and the rear outriggers are retracted;

[0028] ② The rear outriggers are retracted, the front outriggers are suspended, the main beam moves forward and the 1# and 2# overhead cranes move backward; at this time, the 1# and 2# overhead cranes are always above the middle support and the reverse support, and stop when the main beam moves forward about 15m;

[0029] ③ The rear outriggers are raised, the counter-supports are retracted, and the middle supports and rear outriggers support the main beam; the 2# overhead crane lifts the counter-supports and moves forward again. After it is in place, the counter-supports are lifted, the rear outriggers are retracted, and the beam transport vehicle is moved forward to the counter-supports for binding;

[0030] ④1# and 2# overhead cranes move backward and stop above the counter-support, and 2# overhead crane is tied with beam counterweight; the rear outriggers are retracted, and the middle support and counter-support are pushed forward;

[0031] ⑤ After the front legs of the bridge crane arrive at the temporary support position, anchor the front legs, stop the overhead crane above the rear legs, the bridge crane is in place and ready for lifting, adjust the longitudinal slope of the bridge crane and the transverse slope of the transverse track;

[0032] (2) Installation of the main truss of the left section A of the first span

[0033] ① Use the beam feeding rail car to transport the left A main truss of the first span to the beam feeding area of ​​the bridge erection machine;

[0034] ② The front and rear cranes of the bridge erector lift the left A main truss:

[0035] ③ The front and rear cranes hoist the main truss of the left piece A and move forward synchronously. After the main truss is in place, the crane stops moving;

[0036] ④The front and rear winches fall synchronously. When the winches are 100mm away from the support, the trolley moves left to the position to be erected;

[0037] ⑤Put the left A main truss beam on the support of the pier column. The height of the beam is adjusted by the weight of the sand in the sand tube at the tail to ensure the accuracy of the beam drop;

[0038] ⑥ Properly support and tie up the A main truss to prevent it from sliding and tipping over;

[0039] ⑦ The main truss of the left section A of the first span has been erected;

[0040] (3) Installation of the main truss of the first span right section A

[0041] ①The front and rear cranes move backward to the beam feeding area;

[0042] ② Install the right A main beam in the same way as the left A main truss beam of the first span;

[0043] (4) Installation of the main truss of the left section B of the second span

[0044] ① To facilitate the forward movement of the bridge erection machine and to provide a support plane for the middle outrigger, counter-support and rear outrigger on the bridge deck, a steel plate is laid on the A steel truss bridge deck that has been erected;

[0045] ② The beam transport rail vehicle transports the main truss beam of the left section B of the second span to the beam feeding area of ​​the bridge erection machine;

[0046] ③ The bridge erection machine passes through the hole. At this time, the front leg of the bridge erection machine falls to the main bridge cap beam, and the middle leg falls to the temporary support;

[0047] ④ The front and rear cranes of the bridge erection machine lift the left main truss B of the second span and start installation;

[0048] ⑤ The front and rear cranes hoist the main truss of the left piece B and move forward synchronously. After the main truss is in place, the crane stops moving;

[0049] ⑥The front and rear winches fall synchronously. When the winches are 100mm away from the support, the trolley moves left until it reaches the position to be erected;

[0050] ⑦ Place the main truss beam of the left section B of the second span on the support of the pier column. The height of the beam is adjusted by the weight of the sand in the sand tube at the tail to ensure the accuracy of the beam drop;

[0051] ⑧Temporarily connect with the erected first span left piece A steel truss through support and binding to prevent sliding and tipping;

[0052] ⑨ Weld and bolt the main truss, web members and diagonal web members to the erected left A main truss of the first span;

[0053] ⑩The main truss of the left section B of the second span has been erected;

[0054] (5) Installation of the main truss of the first span right section B

[0055] ①The front and rear cranes move backward to the beam feeding area;

[0056] ②Install the right section B main beam according to the installation method of the left section B main truss of the first span.

[0057] The beneficial effects of the present invention are:

[0058] 1. The present invention divides the steel truss into longitudinal sections and transverse slices, which reduces the hoisting load of the bridge erection machine during the construction process, reduces the construction difficulty, and improves the installation efficiency;

[0059] 2. The present invention is adapted to local conditions and sets a temporary bracket between the approach bridge and the main bridge. On the one hand, it provides stable support for the bridge erection machine and enhances the safety of the installation process. On the other hand, the temporary bracket, as the supporting point of the steel truss beam, can be used to adjust the position and posture of the steel truss beam, thereby improving the accuracy of the installation and ensuring the construction quality of the steel truss beam.

[0060] 3. The present invention improves installation efficiency, shortens construction period, reduces accident risks, makes the best use of existing resources and maximizes economic benefits by segmenting and prefabricating steel trusses and setting temporary supports. BRIEF DESCRIPTION OF THE DRAWINGS

[0061] Figure 1 This is a process flow chart of Embodiment 1 of the present invention;

[0062] Figure 2 The on-site topographic map in the first embodiment of the present invention;

[0063] Figure 3 This is a segmented structural diagram of a steel truss beam in Embodiment 1 of the present invention;

[0064] Figure 4 This is a section diagram of the steel truss A in the first embodiment of the present invention;

[0065] Figure 5 This is a segment diagram of the steel truss girder B in the first embodiment of the present invention;

[0066] Figure 6 This is a schematic diagram of the installation of the pedestal in the first embodiment of the present invention;

[0067] Figure 7 This is a schematic diagram of the splicing of section A in the first embodiment of the present invention;

[0068] Figure 8 This is a schematic diagram of splicing segment B in Embodiment 1 of the present invention;

[0069] Fig. 9 Schematic diagram of temporary support in Embodiment 1 of the present invention; in the figure: 1—reinforced concrete, 2—column, 3, 6—diagonal brace, 4—cross-joint, 5—flange, 7—main truss, 8—center line of truss, 9—cross beam on bridge erection machine;

[0070] Fig.10 This is a transverse schematic diagram of the temporary support steel structure in the first embodiment of the present invention; in the figure: 1—reinforced concrete, 2—column, 3, 6—diagonal brace, 4—cross-connection, 5—flange, 7—main truss, 8—center line of truss, 9—cross beam on bridge erection machine;

[0071] Fig.11 This is a schematic diagram of a bridge erection machine through hole in the first embodiment of the present invention;

[0072] Fig.12 This is a schematic diagram of the beam feeding stage of section A in the first embodiment of the present invention;

[0073] Fig.13 This is a schematic diagram of the installation of the main beam of section A in the first embodiment of the present invention;

[0074] Fig.14 This is a schematic diagram of the beam feeding stage of section B in the first embodiment of the present invention;

[0075] Fig.15 This is a schematic diagram of the installation of the section B main beam in the first embodiment of the present invention. DETAILED DESCRIPTION

[0076] To this end, based on the large-span steel truss erection and installation project of the Sangyuanzi Yellow River Bridge, the steel truss was divided into sections longitudinally and slices transversely according to the terrain restrictions and the tonnage restrictions of conventional bridge erection machines. At the same time, a temporary bracket was set between the approach bridge and the main bridge. On the one hand, it provided stable support for the bridge erection machine, and on the other hand, it served as a support point for the steel truss, so that one thing could be used for multiple purposes. After practical testing, this method has strong reliability and applicability, and has achieved good results.

[0077] Embodiment 1

[0078] The construction method of the present invention mainly includes the following construction steps: steel truss segment division, on-site segment manufacturing, in-plant segment pre-assembly, transportation to the construction site, on-site re-assembly, temporary support establishment (can be prepared in advance), bridge erection machine installation, segment hoisting and erection, segment and cross brace connection, bridge erection machine and temporary support removal. Its construction process is as follows Figure 1 As shown;

[0079] The specific construction steps are as follows:

[0080] 1. Segment division of steel trusses

[0081] There is a natural barrier between the No. 2 and No. 3 piers on the left side of the Sangyuanzi Yellow River Bridge. Figure 2 shown.

[0082] For this purpose, considering the structural characteristics of steel trusses, the construction site and the mileage restrictions of the bridge erection machine, the dimensions of the steel truss segments are divided as follows:

[0083] The 70-meter steel truss is divided into A and B sections. The total length of section A is 23,000 mm, and the total length of section B is 47,000 mm. On this basis, section A is further divided into manufacturing section A1 (12,500 mm) and manufacturing section A2 (10,500 mm), and section B (47,000 mm) is divided into manufacturing section B1 (19,500 mm), B2 (15,000 mm), and B3 (12,500 mm). Figure 3 , Figure 4 and Figure 5 As shown:

[0084] 2. On-site segmented manufacturing and pre-assembly

[0085] After the steel trusses are divided, they are manufactured according to the design requirements. After the manufacturing is completed, they are pre-assembled in the factory. During the pre-assembly process of the steel trusses, each component is clearly marked to ensure accurate identification and installation during on-site assembly. Finally, the pre-assembly process is recorded in detail for reference in subsequent construction.

[0086] 3. Assembly on site

[0087] (1) Construction preparation

[0088] like Figure 6 As shown, after the components are transported to the site, the stand columns are installed on the basis of the two-piece pedestal (the schematic diagram of the pedestal is as follows), and then the stand columns are fixed with expansion bolts, and the camber is adjusted according to the requirements of the design drawings.

[0089] (2) Assembly of Section A truss

[0090] like Figure 7 As shown in the figure, considering the linear requirements of the whole span steel truss, when assembling the A section truss, the main truss side section A and the main truss middle section B1 are hoisted on the No. 1 stand to adjust the camber and linearity according to the design requirements. Then, the two main trusses of section A and section B1 are spot welded and firmly connected by the stacking plate method. Finally, the main truss diagonal web between the main truss side section A and the main truss middle section B1 is bolted, and the main truss upper chord and main truss lower chord are welded.

[0091] (3) Assembly of Section B Truss

[0092] like Figure 8As shown, the middle section B2, the middle section B3 and the side section A of the main truss are hoisted on the No. 2 stand, and the camber is adjusted according to the design requirements. Then, the three main trusses of section B2, section B3 and section A are spot welded and firmly connected by stacking plates. Finally, the diagonal webs of the main truss between the middle section B2, the middle section B3 and the side section A of the main truss are hoisted and bolted, and the upper chord and lower chord of the main truss are welded.

[0093] 4. Temporary support installation

[0094] (1) Temporary support foundation

[0095] like Fig. 9 As shown, the bottom end of the temporary support column adopts a reinforced concrete foundation, an embedded steel plate is set on the top of the foundation, and the support steel pipe column is welded and fixed to the embedded parts, as shown in the figure below.

[0096] (2) Temporary support erection

[0097] like Fig.10 As shown in the figure, a steel structure support is set up above the concrete foundation. The height of the steel structure platform of the support is the same as that of the No. 2 and No. 3 piers on the left side of the Sangyuanzi Yellow River Bridge. A support platform for the front legs of the bridge erection machine is set up on the upper part of the steel structure platform to ensure the stability of the front legs of the bridge erection machine. The temporary support uses Φ325×8 round tube columns and Steel pipes are used as diagonal braces. For the upper and lower passages of the steel beams, a 1-meter-wide upper and lower ramp is set up in some temporary brackets. The ramp skeleton is 3-4 scaffolding steel pipes, and 0.8×1.2m bamboo lotus is laid on top and fixed to the scaffolding steel pipes. At the same time, safety guardrails and safety enclosure measures are built on both sides to ensure the safety of pedestrians and workers.

[0098] 5. Lifting and erection of steel trusses

[0099] (1) Bridge machine through hole, such as Fig.11 As shown,

[0100] ① The front outriggers are lifted up with the reverse support, the rear outriggers are lowered, and the pins are inserted. The main beam is lifted away from the middle support and the reverse support. Use the 1# overhead crane to move the middle support forward, and the 2# overhead crane to move the reverse support forward. After the middle support and the reverse support are in place, the reverse support supports the main beam, and the rear outriggers are retracted.

[0101] ② The rear outriggers are retracted, the front outriggers are suspended, the main beam moves forward and the 1#2# overhead cranes move backward. At this time, the 1#2# overhead cranes are always above the middle support and the reverse support, and stop when the main beam moves forward about 15m.

[0102] ③ The rear outriggers are raised, the counter-supports are retracted, and the middle supports and rear outriggers support the main beam. The 2# overhead crane lifts the counter-supports and moves forward again. After it is in place, the counter-supports are raised, the rear outriggers are retracted, and the beam transport vehicle is moved forward to the counter-supports for binding.

[0103] ④1# and 2# overhead cranes move backward and stop above the counter-support, 2# overhead crane is tied with beam counterweight. The rear outriggers are retracted, and the middle support and counter-support are pushed forward.

[0104] ⑤ After the front legs of the bridge crane arrive at the temporary support position, anchor the front legs, and the overhead crane stops above the rear legs. The bridge crane is in place and ready for lifting. Adjust the longitudinal slope of the bridge crane and the transverse slope of the transverse track. The schematic diagram after the hole is completed is as follows:

[0105] (2) Installation of the main truss of the left section A of the first span

[0106] ① Use the beam feeding rail car to transport the left A main truss of the first span to the beam feeding area of ​​the bridge erection machine;

[0107] ② The front and rear cranes of the bridge erector lift the left A main truss; Fig.12 As shown:

[0108] ③ The front and rear cranes hoist the main truss of the left piece A and move forward synchronously. After the main truss is in place, the crane stops moving;

[0109] ④The front and rear winches fall synchronously. When the winches are 100mm away from the support, the trolley moves left to the position to be erected;

[0110] ⑤Put the left A main truss beam on the support of the pier column. The height of the beam is adjusted by the weight of the sand in the sand tube at the tail to ensure the accuracy of the beam drop;

[0111] ⑥ Properly support and tie up the A main truss to prevent it from sliding and tipping over;

[0112] ⑦ The main truss of the left section A of the first span has been erected. Fig.13 As shown:

[0113] (3) Installation of the main truss of the first span right section A

[0114] ①The front and rear cranes move backward to the beam feeding area;

[0115] ②Install the right section A main beam according to the installation method of the left section A main truss of the first span.

[0116] (4) Installation of the main truss of the left section B of the second span

[0117] ① To facilitate the forward movement of the bridge erection machine and to provide a support plane for the middle outrigger, counter-support and rear outrigger on the bridge deck, a steel plate is laid on the A steel truss bridge deck that has been erected;

[0118] ② The beam transport rail vehicle transports the main truss beam of the left section B of the second span to the beam feeding area of ​​the bridge erection machine;

[0119] ③ The bridge erection machine passes through the hole. At this time, the front leg of the bridge erection machine falls to the main bridge cap beam, and the middle leg falls to the temporary support;

[0120] ④ The front and rear cranes of the bridge erector lift the left main truss B of the second span and start installation; Fig.14 As shown:

[0121] ⑤ The front and rear cranes hoist the main truss of the left piece B and move forward synchronously. After the main truss is in place, the crane stops moving;

[0122] ⑥The front and rear winches fall synchronously. When the winches are 100mm away from the support, the trolley moves left until it reaches the position to be erected;

[0123] ⑦ Place the main truss beam of the left section B of the second span on the support of the pier column. The height of the beam is adjusted by the weight of the sand in the sand tube at the tail to ensure the accuracy of the beam drop;

[0124] ⑧Temporarily connect with the erected first span left piece A steel truss through support and binding to prevent sliding and tipping;

[0125] ⑨ Weld and bolt the main truss, web members and diagonal web members to the erected left A main truss of the first span;

[0126] ⑩The main truss of the left section B of the second span has been erected; Fig.15 As shown:

[0127] (5) Installation of the main truss of the first span right section B

[0128] ①The front and rear cranes move backward to the beam feeding area;

[0129] ②Install the right section B main beam according to the installation method of the left section B main truss of the first span.

[0130] Embodiment 2

[0131] The method of the present invention not only improves the installation efficiency, but also significantly shortens the construction period, reduces the risk of accidents, maximizes the use of existing resources, and achieves economic benefits by making use of the longitudinal segmentation, transverse segmentation and temporary support of the steel truss beam for multiple purposes. To this end, the economic indicators of this method are compared with those of the top-pushing method and the crane hoisting method, as follows:

[0132] (1) Pushing method

[0133] The top-pushing method requires the setting of a front guide beam (the structure adopts a lattice steel truss). After checking the height difference of the dropped beam, the calculated size of the front guide beam is:

[0134] ① Length estimation

[0135] The length of the front beam should generally be greater than the length of the cantilever span to ensure that the front beam can cross to the other side first during the jacking process and provide sufficient support and stability. Usually, the length of the front beam is about 1.2 to 1.5 times the span.

[0136] Estimated length: 70 meters × (1.2 to 1.5) = 84 meters to 105 meters

[0137] ②Height estimation:

[0138] According to general engineering experience, the height of the front guide beam is usually about 1 / 30 to 1 / 20 of the span, which is about 2.33 meters to 3.5 meters according to calculations.

[0139] ③Width estimation:

[0140] The width of the steel truss is 4 meters, and the width of the front guide beam should be 4 to 5 meters.

[0141] After calculation, the front guide beam requires 130 tons of steel, and the cost of steel is about 130 tons × 6,000 yuan / ton = 780,000 yuan; the design and manufacturing cost is 300,000 yuan; the transportation and installation cost is 600,000 yuan; other costs and unforeseen costs are 100,000 yuan. The total cost is about 1.28 million yuan.

[0142] Push hydraulic jack: 12 sets, rental 10,000 yuan / day

[0143] Control system and auxiliary equipment: 500,000 yuan.

[0144] Total: 128+50+12×1×15=3.78 million yuan

[0145] (2) Crane hoisting method

[0146] Crawler crane 650t: two

[0147] Entry fee: 300,000 x 2 = 600,000

[0148] Monthly rent: 300,000 yuan / month × 2 = 600,000 yuan

[0149] In addition, in order for the crane to work properly, the foundation must be pre-processed. The local slope foundation needs to be piled up to meet the normal working conditions of the crane. The foundation treatment and design costs are about 800,000 yuan, and the total cost is: 80+120+120=3.2 million yuan

[0150] (3) Use segmented installation method:

[0151] Temporary support cost: 2 tons of steel, the cost of steel is about 5 tons × 6,000 yuan / ton = 30,000 yuan;

[0152] Installation and demolition costs 90,000 yuan + 50,000 yuan = 140,000 yuan

[0153] Bridge crane rental:

[0154] Factory entry and exit fees: 560,000

[0155] Monthly rent: 308,000 yuan / month × 2 = 616,000 yuan

[0156] Driver: 50,000 / month x 2 = 100,000

[0157] Total cost: 1.446 million

[0158] From the above data, it can be seen that this method saves 2.34 million yuan and 1.76 million yuan respectively compared with the jacking method and crane lifting method, with significant economic effects.

[0159] Example 3: Sangyuanzi Yellow River Bridge Project of G312 Line Qingshuiyi to Fujiayao Highway Project

[0160] (1) Project location: Laizibao Township, Yuzhong County, Gansu Province

[0161] (2) Construction period: February 2020 to August 2024

[0162] (3) Project cost: RMB 861 million.

[0163] (4) Project Overview: Sangyuanzi Yellow River Bridge is located in Sangyuanzi Gorge. The bridge axis intersects the Yellow River at an angle of about 60 degrees. It crosses the Yellow River, Longhai Railway, provincial highway, and Sangyuanzi Natural Danger Cultural Relics Protection Area. The left span of the bridge is 949m long, and the right span is 959m long. The main bridge adopts a (151+328+151)m double-tower three-span semi-floating system combined beam cable-stayed bridge. The steel truss is the third span of the left span that crosses the Sangyuanzi Mountain Danger, with a span of 70m. It adopts a simply supported steel truss-UHPC light composite beam. The steel truss consists of a main truss, a cross-link, and upper and lower cross-links. The upper chord and lower chord of the main truss and the lower chord of the cross beam are welded "Ⅱ" section members, and the remaining members are all standard H-shaped steel.

[0164] The main truss is a double main truss structure, consisting of an upper chord, a lower chord, a vertical web and an oblique web. It adopts the form of "Ⅱ" section and "H" steel connection. The truss center height is 5.5m, the full width between the outer edges of the steel frame is 17.25m, and the length of the section is 5m.

[0165] The project adopts this construction method. First, the steel truss beams are processed and assembled in sections, which reduces the difficulty of transporting the steel truss beams, improves transportation efficiency, and reduces transportation costs. At the same time, the steel truss beams are processed and assembled in sections, which reduces the weight of the beam body, reduces the difficulty of top-pushing construction, and improves construction efficiency. The process scheme of segmented processing and assembly can reduce the splicing process on site and improve construction efficiency.

[0166] Example 4: Lanlin Reconstruction Section 1: Xigou Extra-Large Bridge

[0167] (1) Project location: Xigou Valley, Xiguoyuan Town, Qilihe District, Lanzhou City, Gansu Province

[0168] (2) Construction period: December 2019 to December 2021

[0169] (3) Project cost: RMB 528 million

[0170] (4) Project Overview: Xigou Bridge is located in the valley of Xigou. The bridge goes down the platform along the bank of the gully and crosses the gully. The bridge crosses the original G75 Lanlin Expressway twice and crosses the Caojiazui Cultural Relics Protection Area. The upper structure of the bridge is a prestressed concrete continuous steel structure + corrugated web steel box + steel truss composite beam. The lower structure is a column pier / hollow thin-walled pier and column platform. The foundation is a bored pile foundation. The deepest pile foundation is 70 meters and the highest bridge pier is 62 meters. The 5th and 7th joints of the upper structure adopt 50m+90m+50m prestressed concrete continuous rigid frame. The cast-in-place section of the side span at the transition bridge piers 15#, 18# and 23# of the continuous rigid frame section adopts the bracket balanced weight cast-in-place method. The cast-in-place section of the side span at the transition bridge pier 26# of the continuous rigid frame section adopts the bracket cast-in-place method. The steel truss of the approach bridge adopts this method. The steel truss is installed in sections and pieces, which improves transportation efficiency, reduces transportation costs, reduces the difficulty of top-pushing construction, and improves construction efficiency. Moreover, the process of segmented processing and prefabricated assembly can reduce the number of splicing steps on site and improve construction efficiency.

[0171] Finally, it should be noted that: Obviously, the above embodiments are only examples for clearly explaining the present invention, and are not intended to limit the implementation methods. For ordinary technicians in the relevant field, other different forms of changes or modifications can be made based on the above description. It is not necessary and impossible to list all the implementation methods here. The obvious changes or modifications derived from this are still within the scope of protection of the present invention.

Claims

1. A construction method for erecting and installing a large-span steel truss girder in sections and pieces, characterized in that: The steps include: Step 1: According to the steel truss structure, size and site constraints, the steel truss is divided into sections, specifically into sections A and B, and manufactured and pre-assembled; Step 2: transport the pre-assembled components to the site and assemble them on the assembly platform built on site. At the same time, set up a temporary steel structure support between the main bridge and the approach bridge; Step 3: Start to erect and install the steel trusses. The steps are as follows: first install the bridge erection machine and move forward through the hole, the front leg falls on the temporary steel structure support, and the left A and right A sections of the steel trusses are erected in turn, and the left and right sections of the A section of the steel trusses are in place; then, the bridge erection machine moves forward through the hole for the second time, the front leg falls to the main bridge cover beam, and the middle leg falls to the temporary support, and the left and right sections of the B trusses are erected in turn; after the A and B sections of the steel trusses are in place, set a jack on the temporary support to adjust the main beam line shape, and weld the two segment trusses after the main beam linearity meets the requirements; Step 4: Remove the bridge-building machine and temporary support.

2. According to claim 1, a construction method for erecting and installing a large-span steel truss beam in sections and pieces, characterized in that: In step 1, after the steel trusses are divided, the steel trusses are manufactured according to the design requirements; After manufacturing is completed, pre-assembly is carried out in the factory. During the pre-assembly process of the steel trusses, each component is clearly marked to ensure that it can be accurately identified and installed during on-site assembly; finally, the pre-assembly process is recorded in detail for reference in subsequent construction.

3. The method for installing a large-span steel truss girder in sections and pieces according to claim 1 is characterized by: In step 2, the steps for formal assembly are as follows: (1) Construction preparation When the components are transported to the site, the stand columns are first installed on the two-piece stand base. Then, the stand columns are fixed with expansion bolts, and the camber is adjusted according to the design drawing requirements. (2) Assembly of Section A truss Considering the linear requirements of the whole span steel truss, when assembling the A section truss, the main truss side section A and the main truss middle section B1 are hoisted on the No. 1 stand to adjust the camber and linearity according to the design requirements; then the two main trusses of section A and section B1 are spot welded and firmly connected by the stacking plate method; finally, the main truss diagonal web between the main truss side section A and the main truss middle section B1 is bolted, and the main truss upper chord and main truss lower chord are welded; (3) Assembly of Section B Truss First, hoist the main truss middle section B2, main truss middle section B3 and main truss side section A onto the No. 2 stand, and adjust the camber as per the design requirements; then, use the stacking plate method to spot weld the three main trusses, B2, B3 and A, to connect them firmly; finally, hoist and bolt the main truss diagonal web members between the main truss middle section B2, main truss middle section B3 and main truss side section A, and weld the main truss upper chord and main truss lower chord.

4. The method for installing a large-span steel truss girder in sections and pieces according to claim 1 is characterized by: In step 2, the erection of the temporary steel structure support includes the following steps: (1) Temporary support foundation The bottom of the temporary support column adopts a reinforced concrete foundation, the top of the foundation is set with an embedded steel plate, and the support steel pipe column is welded and fixed to the embedded parts; (2) Temporary support erection A steel structure support is set up above the concrete foundation, and a support platform for the front legs of the bridge erecting machine is set up on the upper part of the steel structure platform to ensure that the front legs of the bridge erecting machine are supported stably. The temporary support uses Φ325×8 round tube columns and φ152×8 steel pipes as diagonal braces; for the up and down passages of the steel beams, a 1-meter-wide up and down ramp is set in some temporary supports. The ramp skeleton is 3-4 scaffolding steel pipes, and 0.8×1.2m bamboo lotus is laid on it and fixed to the scaffolding steel pipes. At the same time, safety guardrails and safety enclosure measures are put in place on both sides to ensure the safety of pedestrians and work.

5. The method for installing a large-span steel truss girder in sections and pieces according to claim 1 is characterized by: In step three, the specific steps for erecting and installing the steel truss are as follows: (1) Bridge erection machine through hole ① The front outriggers are lifted up with reverse supports, the rear outriggers are lowered, and the pins are inserted to raise the main beam away from the middle support and reverse supports; the middle support is moved forward with the 1# overhead crane, and the reverse support is moved forward with the 2# overhead crane; after the middle support and reverse supports are in place, the reverse supports support the main beam, and the rear outriggers are retracted; ② The rear outriggers are retracted, the front outriggers are suspended in the air, the main beam moves forward and the 1#2# overhead cranes move backward at the same time; at this time, the 1#2# overhead cranes are always above the middle support and the reverse support, and stop when the main beam moves forward about 15m; ③ The rear outriggers are raised, the counter-supports are retracted, and the middle supports and rear outriggers support the main beam; the 2# overhead crane lifts the counter-supports and moves forward again. After it is in place, the counter-supports are lifted, the rear outriggers are retracted, and the beam transport vehicle is moved forward to the counter-supports for binding; ④1# and 2# overhead cranes move backward and stop above the counter-support, and 2# overhead crane is tied with beam counterweight; the rear outriggers are retracted, and the middle support and counter-support are pushed forward; ⑤ After the front legs of the bridge crane arrive at the temporary support position, anchor the front legs, stop the overhead crane above the rear legs, the bridge crane is in place and ready for lifting, adjust the longitudinal slope of the bridge crane and the transverse slope of the transverse track; (2) Installation of the main truss of the left section A of the first span ① Use the beam feeding rail car to transport the main truss of the left section A of the first span to the beam feeding area of ​​the bridge erection machine; ② The front and rear cranes of the bridge erector lift the left A main truss: ③ The front and rear cranes hoist the main truss of the left piece A and move forward synchronously. After the main truss is in place, the crane stops moving; ④The front and rear winches fall synchronously. When the winches are 100mm away from the support, the trolley moves left to the position to be erected; ⑤Put the left A main truss beam on the support of the pier column. The height of the beam is adjusted by the weight of the sand in the sand tube at the tail to ensure the accuracy of the beam drop; ⑥ Appropriately support and tie up the A main truss to prevent it from sliding and tipping over; ⑦ The main truss of the left section A of the first span has been erected; (3) Installation of the main truss of the first span right section A ①The front and rear cranes move backward to the beam feeding area; ② Install the right A main beam in the same way as the left A main truss of the first span; (4) Installation of the main truss of the left section B of the second span ① To facilitate the forward movement of the bridge erection machine and to provide a support plane for the middle outrigger, back support and rear outrigger on the bridge deck, a steel plate is laid on the A steel truss bridge deck that has been erected; ② The beam transport rail vehicle transports the main truss beam of the left section B of the second span to the beam feeding area of ​​the bridge erection machine; ③ The bridge erection machine passes through the hole. At this time, the front leg of the bridge erection machine falls to the main bridge cap beam, and the middle leg falls to the temporary support; ④ The front and rear cranes of the bridge erection machine lift the left main truss B of the second span and start installation; ⑤ The front and rear cranes hoist the main truss of the left piece B and move forward synchronously. After the main truss is in place, the crane stops moving; ⑥The front and rear winches fall synchronously. When the winches are 100mm away from the support, the trolley moves left until it reaches the position to be erected; ⑦ Place the main truss beam of the left section B of the second span on the support of the pier column. The height of the beam is adjusted by the weight of the sand in the sand tube at the tail to ensure the accuracy of the beam drop; ⑧Temporarily connect with the erected first span left piece A steel truss through support and binding to prevent sliding and tipping; ⑨ Weld and bolt the main truss, web members and diagonal web members to the erected left A main truss of the first span; ⑩The main truss of the left section B of the second span has been erected; (5) Installation of the main truss of the first span right section B ①The front and rear cranes move backward to the beam feeding area; ②Install the right section B main beam according to the installation method of the left section B main truss of the first span.