Winter concrete construction thermal insulation structure and construction method

By using a combined structure of heating devices and multi-layer insulation layers in winter concrete construction, the impact of low-temperature environment on concrete strength is solved, the quality and durability of concrete are ensured, and cracks and strength losses caused by frost damage are avoided.

CN118979647AInactive Publication Date: 2024-11-19CHINA 19TH METALLURGICAL CORP
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202410943375.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-15
Publication Date
2024-11-19
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The low-temperature environment in winter has a great impact on the development of the strength of newly poured concrete, resulting in insufficient tensile strength of concrete after condensation, prone to irrecoverable irregular cracks and strength losses, and frost damage will reduce the compactness and durability of concrete.

Method used

The concrete construction insulation structure is adopted in winter, including base plate, support column, cast-in-place concrete slab, scaffolding, support formwork, heating device and multi-layer insulation layer. The concrete is heated and insulated when the temperature is lower than the set temperature to ensure The curing temperature of concrete is above the set temperature.

Benefits of technology

It effectively avoids concrete cracking caused by low temperature, ensures the quality and compactness of concrete, and improves compressive strength and durability.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118979647A_ABST
    Figure CN118979647A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of building construction, in particular to a winter concrete construction heat preservation structure and a construction method, which are used for carrying out heating and heat preservation treatment on poured concrete when the temperature is lower than a set temperature and ensuring the quality of the concrete after curing is completed. The outer surface of the supporting formwork of the supporting column is coated with the first heat preservation layer, the outer side of the first heat preservation layer is coated with the first thin film layer, meanwhile, the second thin film layer is laid on the upper surface of the cast-in-place concrete slab, the second heat preservation layer is laid on the upper surface of the second thin film layer, and the third thin film layer is laid on the upper surface of the second heat preservation layer; the heating device is used for generating heat to enable the curing temperature of the cast-in-place concrete to be higher than the set temperature, the quality of the cast-in-place concrete is guaranteed, and concrete cracking caused by low temperature is avoided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building construction, in particular to a winter concrete construction insulation structure and a construction method. Background Art

[0002] The reason why concrete mixture can gradually solidify and harden after pouring and obtain the final strength is due to the cement hydration. The speed of cement hydration is related to the composition and mix ratio of concrete itself, and mainly changes with the temperature. When the temperature rises, the hydration speeds up and the strength increases faster; when the temperature drops to 0℃, part of the water in the concrete begins to freeze and gradually changes from liquid water to solid water. At this time, the water involved in cement hydration is reduced, so the hydration slows down and the strength growth is correspondingly slower.

[0003] In the construction of concrete for house frame buildings, the low temperature environment in winter has a great impact on the newly poured concrete, especially in high altitude or mountainous areas, where the temperature difference between day and night is large, and the ambient temperature is often below zero at night. Low temperature conditions will reduce the hydration rate of cement, thereby affecting the strength development of concrete. If the tensile strength of concrete has not yet reached the level that can resist the expansion force generated by ice after solidification, that is, it is affected by negative temperature, the concrete expansion cracking caused by ice will lead to irreversible irregular cracks and strength loss. When the ice melts, various voids will be formed inside the concrete, thereby reducing the compactness and durability of the concrete. If the fresh concrete suffers from frost damage within 24 hours, its compressive strength at 28 days will be reduced by about 50%, and it will also cause the concrete surface to peel off and reduce durability. For this reason, reliable measures must be taken to ensure the quality of concrete construction during winter construction. Summary of the invention

[0004] The technical problem to be solved by the present invention is to provide a winter concrete construction insulation structure and construction method, which are used to heat and insulate the poured concrete when the temperature is lower than the set temperature, so as to ensure the quality of the concrete after the curing is completed.

[0005] The technical solution adopted by the present invention to solve its technical problems is a winter concrete construction insulation structure, comprising a base plate, a plurality of support columns are evenly distributed on the base plate, a cast-in-place concrete slab is arranged above the support columns, a scaffold is arranged between the cast-in-place concrete slab and the base plate, a support formwork is arranged on the top of the scaffold, and the upper surface of the support formwork is in contact with the lower surface of the cast-in-place concrete slab; a heating device is arranged on the scaffold, the outer surface of the support column is provided with a support formwork, the outer side of the support formwork is provided with a first insulation layer, and the outer side of the first insulation layer is provided with a first film layer; the upper surface of the cast-in-place concrete slab is provided with a second film layer, the upper surface of the second film layer is provided with a second insulation layer, and the upper surface of the second insulation layer is provided with a third film layer.

[0006] Furthermore, a windshield is provided on the outer periphery of the scaffolding, the scaffolding is located inside the windshield, and the top of the windshield is in contact with the lower surface of the supporting formwork.

[0007] Furthermore, the heating device comprises a heating barrel, and smokeless carbon is arranged in the heating barrel.

[0008] The construction method of winter concrete construction insulation structure adopts winter concrete construction insulation structure, including the following steps:

[0009] Install the scaffolding and supporting formwork on the base plate, and install the supporting formwork on the top of the scaffolding;

[0010] The concrete mixture is transported to the construction site by means of conveying equipment, and the support column is cast inside the support formwork. After the support column is cast, a cast-in-place concrete slab is cast on the upper surface of the support formwork; after the support column is inspected and qualified, the first insulation layer is coated on the outer side of the support formwork, and the first film layer is coated on the outer side of the first insulation layer;

[0011] After the cast-in-place concrete slab is poured, a second film layer is laid on the upper surface of the cast-in-place concrete slab, a second thermal insulation layer is laid on the upper surface of the second film layer, and a third film layer is laid on the upper surface of the second thermal insulation layer;

[0012] When the air temperature is lower than the set temperature, a heating device is installed on the scaffolding, and the heat generated by the heating device makes the temperature of the cast-in-place concrete slab and the supporting column higher than the set temperature.

[0013] Furthermore, the raw materials for construction of concrete are prepared in advance; the mixing water and aggregate in the concrete raw materials are mixed, and the temperature of the mixing water is higher than 60° C.; cement is then added and mixed to obtain a concrete mixture; the concrete mixture is insulated so that the outlet temperature of the concrete mixture reaches a preset value.

[0014] Furthermore, a windshield is placed around the outer periphery of the scaffolding so that the scaffolding is located inside the windshield, and the top of the windshield abuts against the lower surface of the supporting formwork.

[0015] The beneficial effects of the present invention are as follows: by coating the outer surface of the supporting formwork of the supporting column with a first insulation layer, and coating the outer side of the first insulation layer with a first film layer, and at the same time laying a second film layer on the upper surface of the cast-in-place concrete slab, laying a second insulation layer on the upper surface of the second film layer, and laying a third film layer on the upper surface of the second insulation layer, a heating device is used to generate heat to achieve a curing temperature of the cast-in-place concrete above a set temperature, thereby ensuring the quality of the cast-in-place concrete and avoiding concrete cracking due to low temperature. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 It is a schematic diagram of the structure of the present invention;

[0017] Figure 2 is along Figure 1 Sectional view along line AA;

[0018] Figure 3 is a schematic diagram of the support column.

[0019] Figure numerals: 1-base plate; 2-support column; 201-support formwork; 202-first insulation layer; 203-first film layer; 3-cast-in-place concrete slab; 301-second film layer; 302-second insulation layer; 303-third film layer; 4-scaffolding; 5-support formwork; 7-heating device; 8-windshield. DETAILED DESCRIPTION

[0020] Embodiments of the present invention are described in detail below, examples of which are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are only used to explain the present invention, and cannot be understood as limiting the present invention.

[0021] like Figure 1-Figure 3As shown, the winter concrete construction insulation structure of the present invention comprises a base plate 1, a plurality of support columns 2 are evenly distributed on the base plate 1, a cast-in-place concrete slab 3 is arranged above the support columns 2, a scaffold 4 is arranged between the cast-in-place concrete slab 3 and the base plate 1, a support formwork 5 is arranged on the top of the scaffold 4, and the upper surface of the support formwork 5 is in contact with the lower surface of the cast-in-place concrete slab 3; a heating device 7 is arranged on the scaffold 4, the outer surface of the support column 2 is provided with a support formwork 201, the outer side of the support formwork 201 is provided with a first insulation layer 202, and the outer side of the first insulation layer 202 is provided with a first film layer 203; the upper surface of the cast-in-place concrete slab 3 is provided with a second film layer 301, the upper surface of the second film layer 301 is provided with a second insulation layer 302, and the upper surface of the second insulation layer 302 is provided with a third film layer 303.

[0022] The bottom plate 1 is a concrete plate, the support column 2 is a cast-in-place concrete column, a support formwork 201 is built on the bottom plate 1, and cast-in-place concrete is formed inside the support formwork 201 to form a support column 2, and the support column 2 connects the bottom plate 1 and the cast-in-place concrete plate 3 above; a scaffold 4 is built above the bottom plate 1, and a support formwork 5 is provided on the top of the scaffold 4, and the support formwork 5 is a wooden board, which is used for supporting when pouring the cast-in-place concrete plate 3; when in use, the upper surface of the support formwork 5 is in contact with the lower surface of the cast-in-place concrete plate 3; The heating device 7 is used to heat the support column 2 and the cast-in-place concrete slab 3 to keep the support column 2 and the cast-in-place concrete slab 3 above 0°C. The heating device 7 can be a heater. One end of the rope can be tied at the lower part of the scaffolding 4, and the other end of the rope can be passed around the crossbar of the scaffolding 4 and downward. A wire ring is set on the heating device 7 to connect the rope with the wire ring. This setting can adjust the height of the heating device 7. Of course, a platform for placing the heating device 7 can also be set up in the scaffolding 4. No more details are given here. The first insulation layer 202 can be covered on the surface of the support formwork 201 with a quilt or straw mat, and tied tightly with iron wire to fully protect the support column 2; the first film layer 203 uses a plastic film, which is used to isolate the cold wind from penetrating and avoid taking away the heat of the support column 2. The second film layer 301 and the third film layer 303 are both made of plastic film. The second film layer 301 can effectively lock the moisture in the cast-in-place concrete slab 3, keep the surface of the cast-in-place concrete slab 3 moist and have a good cooling rate, so that the surface quality of the concrete can be guaranteed without watering and curing. The second thermal insulation layer 302 can be made of a 5cm thick quilt or straw mat, and finally a third film layer 303 is covered on the upper surface of the second thermal insulation layer 302. The second thermal insulation layer 302 should be tightly wrapped and firmly overlapped, especially in holes and joints, to ensure quality. In order to prevent the cold wind from blowing away the heat, further, the outer periphery of the scaffolding 4 is provided with a windshield 8, the scaffolding 4 is located inside the windshield 8, and the top of the windshield 8 is in contact with the lower surface of the support formwork 5. The windshield 8 can be surrounded by colored strips of cloth, which has the function of blocking wind and rain, and can prevent the wind from blowing away the heat generated by the heating device 7.

[0023] If a heater is used as the heating device 7, an external power supply is required, which is inconvenient to use. Further, the heating device 7 includes a heating barrel, and smokeless carbon is arranged in the heating barrel. When the smokeless carbon is ignited during use, the heat generated by the smokeless carbon will increase the temperature of the air, thereby increasing the temperature of the support column 2 and the cast-in-place concrete slab 3.

[0024] The construction method of winter concrete construction insulation structure adopts winter concrete construction insulation structure, including the following steps:

[0025] Install a scaffold 4 and a supporting formwork 201 on the base plate 1, and install a supporting formwork 5 on the top of the scaffold 4;

[0026] The concrete mixture is transported to the construction site by means of a conveying device, and a support column 2 is cast inside the support formwork 201. After the support column 2 is cast, a cast-in-place concrete slab 3 is cast on the upper surface of the support formwork 5. After the support column 2 is inspected and qualified, a first insulation layer 202 is coated on the outer side of the support formwork 201, and a first film layer 203 is coated on the outer side of the first insulation layer 202.

[0027] After the cast-in-place concrete slab 3 is cast, a second film layer 301 is laid on the upper surface of the cast-in-place concrete slab 3, a second thermal insulation layer 302 is laid on the upper surface of the second film layer 301, and a third film layer 303 is laid on the upper surface of the second thermal insulation layer 302;

[0028] When the air temperature is lower than the set temperature, the heating device 7 is set on the scaffolding, and the heating device 7 generates heat to make the temperature of the cast-in-place concrete slab 3 and the support column 2 higher than the set temperature. The set temperature is higher than 0°C, and the preferred set temperature is 5°C. One end of the rope can be tied at the lower part of the scaffolding 4, and the other end of the rope can be passed around the crossbar of the scaffolding 4 downward. A wire ring is set on the heating device 7, and the wire ring is connected to the wire ring to realize the installation of the heating device 7. This setting can adjust the height of the heating device 7.

[0029] Furthermore, prepare the raw materials for construction concrete in advance; mix the mixing water and aggregates in the concrete raw materials, and the temperature of the mixing water is higher than 60°C; then add cement for mixing to obtain a concrete mixture; keep the concrete mixture warm so that the outlet temperature of the concrete mixture reaches the preset value. Among them, the cement is selected from silicate cement or ordinary silicate cement, the cement grade is greater than or equal to 42.5, and the water-cement ratio is less than or equal to 0.5; the aggregates used must be clean; select admixtures, including early strength agents, antifreeze agents, water reducers, and antifreeze agents. Preheat and keep warm the mixing water and aggregates in the concrete raw materials, and the preheating temperature of the water is set to 60-80°C, and then add cement to avoid false setting. The outlet temperature of the concrete mixture is greater than 10°C.

[0030] Furthermore, the wind shield 8 is surrounded on the outer periphery of the scaffold 4 so that the scaffold 4 is located inside the wind shield 8 , and the top of the wind shield 8 abuts against the lower surface of the supporting formwork 5 .

[0031] The embodiments of this specific implementation method are all preferred embodiments of the present invention, and are not intended to limit the protection scope of the present invention. Therefore, any equivalent changes made based on the structure, shape, and principle of the present invention should be included in the protection scope of the present invention.

Claims

1. A winter concrete construction insulation structure, comprising a base plate (1), a plurality of support columns (2) evenly distributed on the base plate (1), a cast-in-place concrete slab (3) arranged above the support columns (2), a scaffold (4) arranged between the cast-in-place concrete slab (3) and the base plate (1), a support formwork (5) arranged on the top of the scaffold (4), the upper surface of the support formwork (5) being in contact with the lower surface of the cast-in-place concrete slab (3); characterized in that: The scaffold (4) is provided with a heating device (7); the outer surface of the support column (2) is provided with a support formwork (201); the outer side of the support formwork (201) is provided with a first thermal insulation layer (202); the outer side of the first thermal insulation layer (202) is provided with a first film layer (203); the upper surface of the cast-in-place concrete slab (3) is provided with a second film layer (301); the upper surface of the second film layer (301) is provided with a second thermal insulation layer (302); and the upper surface of the second thermal insulation layer (302) is provided with a third film layer (303).

2. The winter concrete construction insulation structure as claimed in claim 1, characterized in that: A windshield (8) is provided on the outer periphery of the scaffold (4), the scaffold (4) is located inside the windshield (8), and the top of the windshield (8) abuts against the lower surface of the supporting formwork (5).

3. The winter concrete construction insulation structure as claimed in claim 1, characterized in that: The heating device (7) comprises a heating barrel, in which smokeless carbon is arranged.

4. A construction method for a winter concrete construction insulation structure, using the winter concrete construction insulation structure as claimed in any one of claims 1 to 3, characterized in that: The following steps are included: Installing a scaffold (4) and a supporting formwork (201) on the base plate (1), and installing a supporting formwork (5) on the top of the scaffold (4); The concrete mixture is transported to the construction site by means of a conveying device, and a support column (2) is cast inside the support formwork (201). After the support column (2) is cast, a cast-in-place concrete slab (3) is cast on the upper surface of the support formwork (5); after the support column (2) is inspected and found to be qualified, a first thermal insulation layer (202) is coated on the outer side of the support formwork (201), and a first film layer (203) is coated on the outer side of the first thermal insulation layer (202); After the cast-in-place concrete slab (3) is cast, a second film layer (301) is laid on the upper surface of the cast-in-place concrete slab (3), a second thermal insulation layer (302) is laid on the upper surface of the second film layer (301), and a third film layer (303) is laid on the upper surface of the second thermal insulation layer (302); When the air temperature is lower than the set temperature, the heating device (7) is arranged on the scaffold (4), and the heating device (7) generates heat so that the temperature of the cast-in-place concrete slab (3) and the supporting column (2) is higher than the set temperature.

5. The construction method of the winter concrete construction insulation structure as claimed in claim 4, characterized in that: Prepare the raw materials for construction concrete in advance; mix the mixing water and aggregate in the concrete raw materials, with the temperature of the mixing water being higher than 60°C; then add cement and mix to obtain a concrete mixture; keep the concrete mixture warm so that the outlet temperature of the concrete mixture reaches the preset value.

6. The construction method of the winter concrete construction insulation structure as claimed in claim 4, characterized in that: The windshield (8) is surrounded on the outer periphery of the scaffold (4), so that the scaffold (4) is located inside the windshield (8), and the top of the windshield (8) is in contact with the lower surface of the supporting formwork (5).

Citation Information

Patent Citations

  • Winter construction method of bridge pier stud in extremely cold region

    CN103225268A

  • Frost damage prevention method for cast-in-place concrete beams and slabs

    CN104790666A

  • Integrally poured building house construction system and construction method

    CN117090383A

  • Winter mass concrete pouring greenhouse device

    CN219509239U