Regional power grid power supply capability margin analysis method based on multi-source data
Through real-time monitoring and cluster analysis, the power consumption data of regional power grids is evaluated, the load correlation interval is locked, and the numerical monitoring signal is generated, which solves the problem of single and real-time power supply margin analysis methods in the existing technology, and achieves more accurate power consumption prediction and power supply capacity assessment.
Patent Information
- Application Number
- CN202411039496.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-30
- Publication Date
- 2024-11-19
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
In the prior art, the identification process of regional power supply margin analysis methods is relatively single, and is carried out in real time and cannot be determined in advance, making it difficult for operators to take response measures in advance to avoid insufficient power use.
Through the monitoring equipment, the power consumption parameters are monitored in real time, the load status is identified, and the load correlation interval is locked based on past data, a numerical monitoring and processing signal is generated, the power consumption inventory is evaluated, and the unit time inflow is adjusted to ensure power supply capacity.
More accurate numerical prediction and early warning are achieved to ensure the accuracy and effectiveness of power supply capacity margin analysis and avoid insufficient power supply.
Smart Images

Figure CN118983779A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of power grid monitoring, and in particular to a method for analyzing the power supply capacity margin of a regional power grid based on multi-source data. Background Art
[0002] Regional power grid supply refers to the provision of electricity services to users in a specific geographical area through a widely distributed power grid system; these power grid systems include all transmission and distribution facilities from power stations to end users. The power supply area is usually divided according to administrative divisions and power grid structures to ensure scientific management and efficient service.
[0003] The application with publication number CN105552906A discloses a method for analyzing the load margin of a regional power grid based on the primal-dual interior point method, including: refining and simplifying the physical model of the regional power grid; taking the maximum total margin of the load of the power supply main transformer of the regional power grid as the goal, and taking the N-1 safety of the power grid as the criterion, constructing a mathematical optimization model that meets the power grid operation constraints and equipment capacity constraints; solving the load margin optimization model based on the primal-dual interior point method, performing N-1 safety analysis on the regional power grid, and obtaining the load distribution when the total load margin is optimal; judging the key constraints that limit the load margin of the power grid by the evolution of the slack variables of the algorithm. The method for analyzing the load margin of a regional power grid provided by the present invention is simple and practical, has a fast solution speed, can accurately and quickly analyze the load margin of the regional power grid, and indicate the bottleneck information that limits the load capacity of the power grid. It has practical reference value for power grid planning and operation scheduling.
[0004] When the regional power grid is conducting power supply margin analysis, it generally assesses the specific power load through the power consumption generated per unit time, and then identifies whether the power supply margin of this power grid area is sufficient based on the assessed power load and the power consumption stock in this area. However, the original identification and processing method has a relatively simple identification process and is carried out in real time, and cannot be determined in advance for operators to prepare countermeasures in advance to avoid power shortages. Summary of the invention
[0005] In view of the shortcomings of the prior art, the present invention provides a regional power grid power supply capacity margin analysis method based on multi-source data, which solves the problem of the original identification and processing method, whose identification process is relatively simple and is carried out in real time, and cannot be determined in advance for operators to prepare countermeasures in advance.
[0006] To achieve the above objectives, the present invention is implemented by the following technical scheme: a method for analyzing the power supply capacity margin of a regional power grid based on multi-source data comprises the following steps:
[0007] S1. Use relevant monitoring equipment to monitor the power consumption parameters of each regional power grid, and identify whether the power consumption state of the regional power grid is in a load state based on the power consumption generated per unit time. The specific sub-steps are:
[0008] S11, the power consumption generated per unit time by real-time monitoring is calibrated as YD, and each group of power consumption YD is compared with the preset threshold value Y1. When YD≤Y1, no calibration processing is performed and monitoring is continued. When YD>Y1, its duration St is recorded. If St≥3min, the power grid in this area is calibrated as a load power grid area;
[0009] If St < 3min, continue monitoring;
[0010] S2. Based on the determined load power consumption area, record the current time, and define a set of processing cycles. Based on different load power consumption data of this load power consumption area in the past time period, several sets of load power consumption data are correlated and processed, and the load correlation interval of this processing cycle is locked. The specific sub-steps are:
[0011] S21, record the current time and define a set of processing periods T, where T is a preset value, and the processing period T is a time period delayed from the current time. Based on the current time and the processing period T, define a set of processing time periods [Dt, Dt+T], where Dt represents the current time;
[0012] S22, based on the defined processing period, identify the total amount of load data generated in the processing period from the past power consumption data, and mark the total amount of load data generated in the identified different past processing periods as F i , where i represents different past periods;
[0013] S23, the total amount of several groups of total load data F i Perform data clustering: cluster several groups F i Sort the values from small to large to determine a sorted set. If the number of values in the sorted set is even, select the middle two sets F i The mean of the median value F iz If the number of values in the sorted set is odd, directly select the middle set F i As the intermediate value F iz ;
[0014] From the median value F iz First, identify whether the difference Cz between the values before and after the middle value and the middle value satisfies: Cz≤Y2, where Y2 is the preset value:
[0015] If Cz≤Y2 is satisfied, the values on both sides are calibrated as similar values, and then the previous and next values are confirmed starting from the similar values, and the relevant selection of similar values is completed in sequence until Cz>Y2 is stopped, and the selected groups of similar values are calibrated as similar characteristic value segments, and then the difference confirmation is started from the similar values on both sides of the similar characteristic value segment, and the subsequent similar characteristic value segments are confirmed one by one;
[0016] If Cz≤Y2 is not satisfied, the difference confirmation is started from the same values on both sides of the middle value, and the same processing method is performed to confirm the same characteristic value segments;
[0017] S24. From the confirmed similar characteristic value segments, select a value segment with the largest number of values as the standard segment, and select the corresponding value F from the standard segment. i The minimum value F imin and the maximum value F imax Determine the load correlation interval [F imin , F imax ];
[0018] If there are multiple groups of value segments with the largest number of values, all of them are marked as standard segments, and the corresponding value F is selected from the multiple groups of standard segments. i The minimum value F imin and the maximum value F imax Determine the load correlation interval [F imin , F imax ];
[0019] S3, based on the electricity consumption stock determined at the current moment and the load associated interval determined in the current processing cycle, identify whether the electricity consumption stock meets the load power consumption of the current processing cycle, and generate a corresponding numerical monitoring processing signal based on the identification result. The specific sub-steps are:
[0020] S31, the electricity consumption stock determined at the current moment is calibrated as YC, and then based on the determined load association interval [F imin , F imax ], if YC≤F imax When , a numerical monitoring processing signal is generated;
[0021] If YC>F imax When , no processing signal is generated, and the power consumption data of this load power consumption area is monitored in real time;
[0022] S4, based on the confirmed numerical monitoring processing signal, a group of monitoring cycles are locked from the processing cycle, and the unit time electricity inflow and power consumption of the load power consumption area in this monitoring cycle are numerically confirmed, and based on the confirmed specific values, the maximum abnormal amount generated in this monitoring cycle is determined, and then based on the electricity consumption inventory determined at the current moment, it is determined whether the unit time electricity inflow needs to be adjusted. The specific sub-steps are:
[0023] S41, based on the processing cycle T, use (T×1 / 3) to confirm a set of monitoring cycles, this monitoring cycle belongs to the front 1 / 3 period of this processing cycle T, and the unit time electricity inflow corresponding to different moments in this monitoring cycle is calibrated as HR k The power consumption corresponding to different times in this monitoring cycle is calibrated as YD k , where k represents different moments, and determines the abnormal amount YL generated at the corresponding moment k , among which YL k =HR k -YD k Determine the abnormal amount YL corresponding to the corresponding time k ;
[0024] S42, based on the electricity consumption YC confirmed at the current moment, the standard median Gc is determined by adopting YC÷T=Gc, and the different abnormal quantities YL corresponding to different moments in this monitoring cycle are determined based on the different abnormal quantities YL corresponding to different moments in this monitoring cycle. k , generate its abnormal quantity change curve, determine the position of the standard median Gc on the vertical coordinate axis of the two-dimensional coordinate system, and construct a set of related vertical lines, which are perpendicular to this position, determine the initial endpoint and the terminal endpoint of the abnormal quantity change curve, and construct two sets of vertical lines perpendicular to the related vertical lines based on the determined initial endpoint and terminal endpoint;
[0025] S43. After the two sets of vertical lines are constructed, the abnormal quantity change curve and the related vertical lines are divided into several range areas, and the area above the related vertical lines is marked as the upper area, and the area below the related vertical lines is marked as the lower area;
[0026] S44, identifying the total area Mz of the upper region, and then identifying the total area Mh of the lower region. If (Mz÷Mh)>1, executing step S45 to adjust the amount of inflow per unit time. If (Mz÷Mh)≤1, no processing signal is generated.
[0027] S45, select the maximum abnormal amount YL from the partial line segments associated with the upper area kmax , using YL kmax×2 / 3T=XQ determines the relevant demand XQ of this processing cycle, and determines the power consumption stock DL corresponding to the end time of this monitoring cycle, and uses (XQ-DL)÷2 / 3T=XZ to determine the new amount XZ of the inflow per unit time, and simultaneously generates a regional surplus or shortage signal, and displays the generated regional surplus or shortage signal and the new amount XZ of the inflow per unit time through the corresponding display terminal.
[0028] The present invention provides a method for analyzing the power supply capacity margin of a regional power grid based on multi-source data. Compared with the prior art, it has the following beneficial effects:
[0029] The present invention monitors the power consumption data of power grids in different regions, and determines the load power grid area based on the monitoring results, and determines the load data volume from the same period in the past of this area based on the corresponding load period, and then performs cluster analysis on the determined groups of load data volume, and locks the most standard load correlation interval based on the corresponding specific distance analysis results. Subsequently, numerical analysis is performed based on this load correlation interval, which can ensure that the numerical analysis value is more accurate, and can be predicted in advance, so as to achieve a better numerical prediction analysis processing effect;
[0030] Subsequently, for such load power grid areas, to assess whether their power reserves are sufficient, it is necessary to conduct numerical monitoring based on the corresponding power consumption data, and then assess whether the power reserves in the power application area are sufficient based on the specific numerical performance within the monitoring period, so as to ensure a better power supply capacity margin analysis effect. BRIEF DESCRIPTION OF THE DRAWINGS
[0031] Figure 1 It is a schematic diagram of the process of the present invention. DETAILED DESCRIPTION
[0032] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0033] Example 1
[0034] See also Figure 1 The present application provides a method for analyzing the power supply capacity margin of a regional power grid based on multi-source data, comprising the following steps:
[0035] S1. Use relevant monitoring equipment to monitor the power consumption parameters of each power grid in different regions, and identify whether the power consumption state of the power grid in this region is in a load state based on the power consumption generated per unit time. Specifically, when the power grid in each different region uses electricity, there are specific power consumption parameters per unit time. When the power consumption parameters generated per unit time exceed the set threshold, the corresponding transmission line and related equipment are in the corresponding load state, and their power consumption state belongs to the corresponding load state. The monitoring equipment is a fixed monitoring sensor, which monitors the power consumption parameters in real time;
[0036] The specific sub-steps for identifying whether the regional power grid is in a load state are:
[0037] S11, the power consumption generated per unit time by real-time monitoring is calibrated as YD, and each group of power consumption YD is compared with the preset threshold value Y1, wherein the specific value of Y1 is prepared by the operator in advance based on experience, when YD≤Y1, no calibration processing is performed, and monitoring continues, when YD>Y1, its duration St is recorded (that is, the duration of YD>Y1, when YD fluctuates to YD≤Y1, the recording of the duration St is stopped), if St≥3min, the power grid in this area is calibrated as a load power grid area;
[0038] If St < 3min, continue monitoring. The reason for setting the time limit here is to avoid misjudgment due to fluctuations in power parameters.
[0039] S2. Based on the determined load power consumption area, record the current time, and define a set of processing cycles. Based on different load power consumption data of this load power consumption area in the past time period, several sets of load power consumption data are correlated and processed, and the load correlation interval of this processing cycle is locked. Specifically, in order to make better numerical predictions to analyze whether the margin of its power consumption is up to standard, it is necessary to lock the corresponding load correlation interval. Among them, the specific sub-steps of locking this load correlation interval are:
[0040] S21, record the current time and define a set of processing periods T, where T is a preset value, and its specific value is determined by the operator based on experience, and its processing period T is a time period delayed from the current time. Based on the current time and the processing period T, define a set of processing time periods [Dt, Dt+T], where Dt represents the current time;
[0041] S22, based on the defined processing period, identify the total amount of load data generated in this processing period from the past power consumption data, where the total amount of load data is the sum of the difference between the power consumption exceeding the preset threshold value Y1 and Y1 per unit time, and mark the total amount of load data generated by the identified different past processing periods as F i, where i represents different past time periods, and the specific values of several groups are formulated by the operator based on experience;
[0042] S23, the total amount of several groups of total load data F i Perform data clustering: cluster several groups F i Sort the values from small to large to determine a sorted set. If the number of values in the sorted set is even, select the middle two sets F i The mean of the median value F iz If the number of values in the sorted set is odd, directly select the middle set F i As the intermediate value F iz ;
[0043] From the median value F iz First, identify whether the difference Cz between the values before and after the middle value and the middle value satisfies: Cz≤Y2, where Y2 is a preset value, and its specific value is determined by the operator based on experience:
[0044] If Cz≤Y2 is satisfied, the values on both sides are calibrated as similar values, and then the previous and next values are confirmed starting from the similar values (the similar value in front of the middle value is confirmed by difference with the previous value, and the similar value behind the middle value is confirmed by difference with the later value), and the relevant selection of similar values is completed in sequence until Cz>Y2 is stopped, and the selected groups of similar values are calibrated as similar characteristic value segments, and then the difference confirmation is started from the similar values on both sides of the similar characteristic value segment, and the subsequent similar characteristic value segments are confirmed one by one;
[0045] If Cz≤Y2 is not satisfied, the difference confirmation is started from the same values on both sides of the middle value, and the same processing method is performed to confirm the same characteristic value segments;
[0046] Here we combine examples to understand: several groups of F i After the corresponding sorting process, the confirmed sorting set is expressed as {1, 2, 3, 4, 5, 8, 8.5, 8.7, 9, 9.3, 9.6, 11, 12, 13}, so the middle value is confirmed first, the middle is the average between 8.5 and 8.7, that is, 8.6, and the proposed value of Y2 is 1. Then, after the difference analysis process, the corresponding similar feature value segment {8, 8.5, 8.7, 9, 9.3, 9.6} and the similar feature value segments before and after {1, 2, 3, 4, 5} and {11, 12, 13} can be locked, thereby completing the specific confirmation of the corresponding similar feature value segment. The confirmed similar feature value segments are relatively clustered in terms of numerical attributes.
[0047] S24. From the confirmed numerical segments of the same type, select the numerical segment with the largest number of values as the standard segment. If there are multiple groups of numerical segments with the largest number of values, all the multiple groups of numerical segments are marked as standard segments, and the corresponding value F is selected from the single group of standard segments or multiple groups of standard segments. i The minimum value F imin and the maximum value F imax Determine the load correlation interval [F imin , F imax ];
[0048] Specifically, the numerical segment is the relevant load value with relatively clustered corresponding numerical characteristics. Such load values can lock the relevant load power consumption that may be generated in this processing cycle. Based on the determined load correlation interval, the relevant analysis of load power is performed to execute different processing methods, identify whether an intervention signal needs to be generated, and intervene and respond by external personnel;
[0049] S3, based on the electricity consumption stock determined at the current moment and the load associated interval determined in the current processing cycle, identifying whether the electricity consumption stock meets the load power consumption of the current processing cycle, and generating a corresponding processing signal based on the identification result, wherein the specific sub-steps of the identification are:
[0050] S31, the electricity consumption stock determined at the current moment is calibrated as YC, and then based on the determined load association interval [F imin , F imax ], if YC>F imax When , no processing signal is generated, and the power consumption data of this load power consumption area is monitored in real time;
[0051] If YC≤F imax When the power consumption data is generated, a numerical monitoring processing signal is generated to monitor and analyze the power consumption data generated in real time during this processing cycle, and to assess whether additional power consumption is required during this processing cycle;
[0052] S4, based on the confirmed numerical monitoring processing signal, a group of monitoring cycles are locked from the processing cycle, and the unit time electricity inflow and electricity consumption of the load power consumption area in this monitoring cycle are numerically confirmed, and based on the confirmed specific values, the maximum abnormal amount generated in this monitoring cycle is determined, and then based on the electricity consumption inventory determined at the current moment, it is determined whether the unit time electricity inflow needs to be adjusted, wherein the specific sub-steps of determining are:
[0053] S41, based on the processing cycle T, use (T×1 / 3) to confirm a set of monitoring cycles, this monitoring cycle belongs to the front 1 / 3 period of this processing cycle T, and the unit time electricity inflow corresponding to different moments in this monitoring cycle is calibrated as HR kThe power consumption corresponding to different times in this monitoring cycle is calibrated as YD k , where k represents different moments, and determines the abnormal amount YL generated at the corresponding moment k , among which YL k =HR k -YD k Determine the abnormal amount YL corresponding to the corresponding time k ;
[0054] S42, based on the electricity consumption YC confirmed at the current moment, the standard median Gc is determined by adopting YC÷T=Gc, and the different abnormal quantities YL corresponding to different moments in this monitoring cycle are determined based on the different abnormal quantities YL corresponding to different moments in this monitoring cycle. k , generate its abnormal quantity change curve, the horizontal coordinate axis of the change curve is the time line, and the vertical coordinate axis is the abnormal quantity value, determine the position of the standard median Gc on the vertical coordinate axis of the two-dimensional coordinate system, and construct a set of related vertical lines, which are perpendicular to this position, determine the initial endpoint and the terminal endpoint of the abnormal quantity change curve, and construct two sets of vertical lines perpendicular to the related vertical lines based on the determined initial endpoint and terminal endpoint, and one set of vertical lines passes through the initial endpoint and the other set of vertical lines passes through the terminal endpoint;
[0055] S43. After the two sets of vertical lines are constructed, the abnormal quantity change curve and the related vertical lines are divided into several range areas, and the area above the related vertical lines is marked as the upper area, and the area below the related vertical lines is marked as the lower area. Specifically, after the abnormal quantity change curve and the related vertical lines are constructed, the two end points of the change curve can construct a specific vertical line perpendicular to the related vertical line, and then the two constructed vertical lines and the related vertical lines can determine several range areas within the range of the abnormal quantity change curve. Then the range area includes the corresponding upper area and lower area, and the lower area belongs to the area with normal power consumption, and the upper area belongs to the area with insufficient power supply, which will seriously consume the corresponding power stock;
[0056] S44, identifying the total area Mz of the upper area, and then identifying the total area Mh of the lower area. If (Mz÷Mh)>1, executing step S45 to adjust the amount of inflow per unit time. If (Mz÷Mh)≤1, no processing signal is generated, and the power consumption data of this load power consumption area is monitored in real time.
[0057] S45, select the maximum abnormal amount YL from the partial line segments associated with the upper area kmax , using YL kmax×2 / 3T=XQ determines the relevant demand XQ of this processing cycle, and determines the power inventory DL corresponding to the end time of this monitoring cycle, and adopts (XQ-DL)÷2 / 3T=XZ to determine the new amount XZ of the inflow per unit time, and simultaneously generates the regional abundance or shortage signal, and displays the generated regional abundance or shortage signal and the new amount XZ of the inflow per unit time through the corresponding display terminal for external personnel to view. When external personnel take relevant measures based on this regional abundance or shortage signal, they make corresponding adjustments to the inflow per unit time, and the minimum value of the adjustment is (original inflow + XZ) to ensure the normal power consumption of this load power consumption area, avoid power shortage, and achieve better power supply processing effect.
[0058] Some of the data in the above formulas are dimensionless and numerically calculated. Meanwhile, the contents not described in detail in this specification belong to the prior art known to those skilled in the art.
[0059] The above embodiments are only used to illustrate the technical method of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that the technical method of the present invention may be modified or replaced by equivalents without departing from the spirit and scope of the technical method of the present invention.
Claims
1. A method for analyzing regional power grid power supply capacity margin based on multi-source data, characterized in that: The following steps are involved: S1. Use relevant monitoring equipment to monitor the power consumption parameters of the power grid in each different region, and identify whether the power consumption state of the power grid in this region is in a load state based on the power consumption generated per unit time; S2. Based on the determined load power consumption area, record the current time, and define a set of processing cycles. Based on different load power consumption data of this load power consumption area in the past time period, perform correlation processing on several sets of load power consumption data, and lock the load correlation interval of this processing cycle; S3, based on the electricity consumption stock determined at the current moment and the load associated interval determined in the current processing cycle, identifying whether the electricity consumption stock meets the load power consumption of the current processing cycle, and generating a corresponding numerical monitoring processing signal based on the identification result; S4. Based on the confirmed numerical monitoring processing signal, a group of monitoring cycles are locked from the processing cycle, and the unit time electricity inflow and electricity consumption of the load power consumption area within this monitoring cycle are numerically confirmed. Based on the confirmed specific values, the maximum abnormal amount generated in this monitoring cycle is determined, and then based on the electricity inventory determined at the current moment, it is determined whether the unit time electricity inflow needs to be adjusted.
2. The method for analyzing regional power grid power supply capacity margin based on multi-source data according to claim 1 is characterized in that: In step S1, the specific sub-steps for identifying whether the regional power grid is in a load state are: S11. The power consumption per unit time generated by real-time monitoring is calibrated as YD, and each group of power consumption YD is compared with the preset threshold value Y1. When YD≤Y1, no calibration processing is performed and monitoring continues. When YD>Y1, its duration St is recorded. If St≥3min, the power grid in this area is calibrated as a load power grid area.
3. The method for analyzing regional power grid power supply capacity margin based on multi-source data according to claim 2 is characterized in that: In the step S11, if St<3 min, the monitoring continues.
4. The method for analyzing regional power grid power supply capacity margin based on multi-source data according to claim 1 is characterized in that: In step S2, the specific sub-steps of locking the load associated interval are: S21, record the current time and define a set of processing periods T, where T is a preset value, and the processing period T is a time period delayed from the current time. Based on the current time and the processing period T, define a set of processing time periods [Dt, Dt+T], where Dt represents the current time; S22, based on the defined processing period, identify the total amount of load data generated in the processing period from the past power consumption data, and mark the total amount of load data generated in the identified different past processing periods as F i , where i represents different past periods; S23, the total amount of several groups of total load data F i Perform data clustering: cluster several groups F i Sort the values from small to large to determine a sorted set. If the number of values in the sorted set is even, select the middle two sets F i The mean of the median value F iz If the number of values in the sorted set is odd, directly select the middle set F i As the intermediate value F iz ; From the median value F iz First, identify whether the difference Cz between the values before and after the middle value and the middle value satisfies: Cz≤Y2, where Y2 is the preset value: If Cz≤Y2 is satisfied, the values on both sides are calibrated as similar values, and then the previous and next values are confirmed starting from the similar values, and the relevant selection of similar values is completed in sequence until Cz>Y2 is stopped, and the selected groups of similar values are calibrated as similar characteristic value segments, and then the difference confirmation is started from the similar values on both sides of the similar characteristic value segment, and the subsequent similar characteristic value segments are confirmed one by one; If Cz≤Y2 is not satisfied, the difference confirmation is started from the same values on both sides of the middle value, and the same processing method is performed to confirm the same characteristic value segments; S24. From the confirmed similar characteristic value segments, select a value segment with the largest number of values as the standard segment, and select the corresponding value F from the standard segment. i The minimum value F imin and the maximum value F imax Determine the load correlation interval [F imin , F imax ].
5. The method for analyzing regional power grid power supply capacity margin based on multi-source data according to claim 4 is characterized in that: In step S24, if there are multiple groups of value segments with the largest number of values, all of the multiple groups of value segments are marked as standard segments, and the corresponding value F is selected from the multiple groups of standard segments. i The minimum value F imin and the maximum value F imax Determine the load correlation interval [F imin , F imax ].
6. The method for analyzing regional power grid power supply capacity margin based on multi-source data according to claim 5 is characterized in that: In step S3, the specific sub-steps of generating the numerical monitoring processing signal are: S31, the electricity consumption stock determined at the current moment is calibrated as YC, and then based on the determined load association interval [F imin , F imax ], if YC≤F imax When , a numerical monitoring processing signal is generated.
7. The method for analyzing regional power grid power supply capacity margin based on multi-source data according to claim 6 is characterized in that: In step S31, if YC>F imax When , no processing signal is generated, and the power consumption data of this load power consumption area can be monitored in real time.
8. The method for analyzing regional power grid power supply capacity margin based on multi-source data according to claim 6 is characterized in that: In step S4, the specific sub-steps for determining whether it is necessary to adjust the amount of electricity remitted per unit time are: S41, based on the processing cycle T, using (T× 1 / 3) Confirm a set of monitoring cycles, which belong to the front end of this processing cycle T 1 / 3 period, the unit time electricity inflow corresponding to different moments in this monitoring cycle is calibrated as HR k The power consumption corresponding to different times in this monitoring cycle is calibrated as YD k , where k represents different moments, and determines the abnormal amount YL generated at the corresponding moment k , among which YL k =HR k -YD k Determine the abnormal amount YL corresponding to the corresponding time k ; S42, based on the electricity consumption YC confirmed at the current moment, the standard median Gc is determined by adopting YC÷T=Gc, and the different abnormal quantities YL corresponding to different moments in this monitoring cycle are determined based on the different abnormal quantities YL corresponding to different moments in this monitoring cycle. k , generate its abnormal quantity change curve, determine the position of the standard median Gc on the vertical coordinate axis of the two-dimensional coordinate system, and construct a set of related vertical lines, which are perpendicular to this position, determine the initial endpoint and the terminal endpoint of the abnormal quantity change curve, and construct two sets of vertical lines perpendicular to the related vertical lines based on the determined initial endpoint and terminal endpoint; S43. After the two sets of vertical lines are constructed, the abnormal quantity change curve and the related vertical lines are divided into several range areas, and the area above the related vertical lines is marked as the upper area, and the area below the related vertical lines is marked as the lower area; S44, identifying the total area Mz of the upper region, and then identifying the total area Mh of the lower region. If (Mz÷Mh)>1, executing step S45 to adjust the amount of inflow per unit time. If (Mz÷Mh)≤1, no processing signal is generated. S45, select the maximum abnormal amount YL from the partial line segments associated with the upper area kmax , using YL kmax × 2 / 3T=XQ Determine the relevant demand XQ of this processing cycle, and determine the power consumption inventory DL corresponding to the end of this monitoring cycle, using (XQ-DL)÷ 2 / 3T=XZ determines the new amount XZ of the inflow per unit time, and simultaneously generates a regional sufficiency or insufficiency signal, and displays the generated regional sufficiency or insufficiency signal and the new amount XZ of the inflow per unit time through a corresponding display terminal.