Prefabricated pavement slab mounting structure and construction method

Through the use of prefabricated road panel installation structure and adjustment parts, the problems of long construction time and poor material performance of the airport road surface and steel bridge deck are solved, and rapid and safe construction and efficient bonding are achieved, and construction efficiency is improved. The structure's freeze-thaw resistance extends its service life.

CN118996940AInactive Publication Date: 2024-11-22NINGBO ROABY TECH INDAL GROUP

Patent Information

Application Number
CN202411487208.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-24
Publication Date
2024-11-22
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The existing airport road surface and steel bridge deck paving technology has problems such as long construction time, poor material performance, harsh construction conditions, and prone to diseases, making it difficult to achieve rapid, safe and effective construction and maintenance.

Method used

Adopt a prefabricated track panel installation structure, including leveling adhesive layer and prefabricated track panel, adjust the elevation and slope through the adjustment parts, reserve holes for slurry replenishment, combine the shear structure and the skeleton structure to improve adhesion and shear resistance. , adopts materials such as polyurethane concrete to achieve rapid construction and efficient bonding.

Benefits of technology

It has achieved rapid assembly and construction, meeting the needs of unstoppable airport road surfaces and rapid delivery of steel bridge decks, improving construction efficiency and structure anti-freeze-thaw performance, extending service life, and reducing maintenance probability.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118996940A_ABST
    Figure CN118996940A_ABST
Patent Text Reader

Abstract

According to the prefabricated pavement slab mounting structure and the construction method, the prefabricated pavement slab mounting structure comprises a leveling bonding layer laid on a foundation pavement and a prefabricated pavement slab arranged on the leveling bonding layer, a leveling hole of the prefabricated pavement slab is matched with an adjusting piece used for adjusting the elevation and gradient of the prefabricated pavement slab, and slurry before the leveling bonding layer is solidified is filled into a reserved hole; the slurry supplementing liquid flows into the leveling bonding layer through the reserved hole and is solidified with the unsolidified slurry of the leveling bonding layer to form an integrated structure. According to the prefabricated pavement slab mounting structure, the elevation and gradient of the prefabricated pavement slab are adjusted through the adjusting piece, the slurry supplementing liquid and the adjusting piece bonding layer are solidified into an integrated structure, the interlayer bonding force is good, the bearing capacity is high, splicing type and full-width rapid on-site assembly thickening construction of the prefabricated pavement slab can be achieved on different types of foundation pavements, and the construction efficiency is improved. When the device is applied to airfield pavement slab repair, non-stop fast delivery is achieved, and when the device is applied to a steel bridge deck, the requirements of multi-dimensional deformation and stress release of a bridge, especially an extra-large flexible steel bridge under the action of external force are met.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of pavement construction and maintenance technology, and in particular to a prefabricated pavement panel installation structure and construction method, which are used for the construction and maintenance of airport pavements, and are also suitable for various scenarios such as steel bridge decks, tracks, railways, and city squares. Background Art

[0002] With the development of transportation and civil aviation, the original airport design standard load requirements have increased, and the long-term use of the field road has caused damage, such as road slab fractures, broken joints, and potholes. In addition, the climate is warming and the temperature rises, which makes the structural bearing capacity decay and the performance of use decrease. The most common practice for large-scale maintenance of airport concrete pavement, especially to increase the load of the road slab, is to add a certain thickness of cement or asphalt concrete overlay layer on the surface of the old road slab, which is usually called "covering" or "overlay". When overlaying asphalt on the airport pavement, the surface layer is generally divided into three layers, from top to bottom, they are the upper layer, the middle layer, and the lower layer, and the total thickness is controlled at about 20 cm. One typical overlay structure is 5 cm thick SMA-13 ​​asphalt concrete + 6.5 cm thick AC-13 + 6.5 cm thick AC-13 from top to bottom, with a total thickness of 18 cm. Asphalt concrete overlay needs to be completed in three stages, with a long cycle and cumbersome methods. At the same time, due to the material properties of asphalt, after a period of operation at the airport, it is easy to loosen, water damage, wheel rutting and other diseases, and even serious peeling diseases, which pose certain safety hazards. For example, an airport in central China has a 3200m×45m runway, and a 21cm asphalt blanket is added. The total area is 144,000 square meters. The flight was suspended for 126 days. Soon after it was put into operation, it began to suffer from diseases such as bulging and shifting. Due to the superposition of high temperature, heavy rain and other reasons, many airports such as Brazil, Indonesia, and Shenyang have rolled up a large area of ​​the asphalt overlay under the negative pressure of the aircraft taking off, posing a serious threat to aircraft and aviation safety. If cement concrete blanket is used, due to the long hardening and condensation time of cement concrete, a 28-day curing cycle is required according to the specification, and it is impossible to achieve non-stop construction. The paving temperature of asphalt mixture is usually 160℃, the construction environment temperature is required to be above 5℃, and the construction temperature of cement concrete should be controlled above 5℃ and below 35℃. These conditions greatly limit the construction time in high-latitude areas, making the construction period in high-latitude areas shorter. In winter, when the temperature is low, cement concrete cannot be fully hydrated and asphalt cannot be constructed. When asphalt is overlaid, the adhesion is low, and the material strength and elastic modulus are far apart. When concrete is overlaid, the new and old layers cannot be superimposed. Therefore, neither of them can bond with the original road surface to form an overall performance that is combined into one.

[0003] In addition, with the development of transportation, the construction of bridges, especially super-large steel bridges, has advanced by leaps and bounds. The original design standards and technical quality are facing major challenges. Among them, the pavement of steel bridges is the core part of the traffic system. In the worst operating environment, the pavement structure will often suffer from various serious premature damages within the design service life, which will have a major impact on the safety and efficiency of normal transportation. Large steel bridges are mostly built on rivers, rivers, and valleys. Once damaged, arterial traffic will be tense or paralyzed. Therefore, it is very important to choose a steel bridge deck paving technology with excellent material performance, scientific and reasonable structure, and fast and efficient construction. At present, the traditional steel bridge deck paving system can be roughly divided into three types: cast asphalt concrete paving system (GA), modified asphalt paving system (SMA), and epoxy resin asphalt concrete paving system (EA). These systems have the following problems: First, they are prone to damage: bridge deck pavement will bend and deform under the action of vehicle load, shear, wind force, etc., especially the upper part of the U-rib on the bridge deck, which is subjected to the most repeated bending. The thin thickness of the top plate leads to unstable stress and large deformation of the pavement layer, which is prone to fatigue cracking and other diseases; in order to reduce the dead load of the bridge, the steel bridge deck pavement is thinner than the concrete bridge deck pavement, which has a greater cohesive force challenge and is prone to shear displacement and other diseases; the steel bridge deck has low roughness and the smooth surface poses a great challenge to the bonding performance of the interface, which is prone to delamination and other diseases; due to the excellent thermal conductivity of steel and the steamer effect inside the box girder, the steel bridge deck can reach more than 70 degrees Celsius in summer, which poses a great challenge to the high temperature performance of the pavement material and is prone to cracking, rutting and other diseases. The above diseases affect both vehicle traffic safety and the service life of the bridge. Secondly, the construction time is long and the construction conditions are harsh. Most steel bridges are located in important traffic sections. In order to quickly deliver them to traffic or reduce the impact on normal traffic, the paving or repair of steel bridge decks usually requires a long time. However, traditional paving is cast in layers, and each layer requires multiple rounds of interlayer bonding surface treatment, paving, and curing. Each process takes a long time, and it is difficult to build new ones or repair them in a short time. Moreover, the asphalt paving temperature is usually 160°C, which requires high-temperature mixing on site, high-temperature transportation, high-temperature paving and rolling, so it cannot be constructed under low temperature conditions in winter, which greatly limits the construction period of steel bridge deck paving.For example, the Chinese invention patent application with application number CN202410620199.1 (publication number CN 118326815 A) discloses a prefabricated steel-UHPC lightweight composite bridge deck structure and construction method, which provides a prefabricated steel-UHPC lightweight combination. The prefabricated steel-UHPC lightweight combination is a "combined bridge structure". It forms "segmental beams" by welding and casting UTPC (high-strength concrete), shear studs + steel mesh, steel components, etc., and then transports them to the construction site to assemble the segmental beams into a whole bridge by welding, bolting, etc., rather than the "bridge deck pavement structure" in the conventional concept. Its damage is also the damage of the "main body" of the bridge. Summary of the invention

[0004] The first technical problem to be solved by the present invention is to provide a prefabricated road panel installation structure that can achieve rapid assembly construction in view of the above-mentioned existing technical status.

[0005] The second technical problem to be solved by the present invention is to provide a construction method for airport prefabricated road panels that can be assembled on-site in full width and achieve rapid construction without stopping flights, in view of the above-mentioned existing technical status.

[0006] The third technical problem to be solved by the present invention is to provide a construction method for prefabricated steel bridge deck panels with a rigid-flexible combined assembly structure, which meets the requirements of stress release and rapid construction, in response to the above-mentioned existing technical status.

[0007] The technical solution adopted by the present invention to solve the above-mentioned first technical problem is: a prefabricated road panel installation structure, characterized in that it includes a leveling adhesive layer laid on the basic road surface and a prefabricated road panel arranged on the leveling adhesive layer, the prefabricated road panel is formed with leveling holes and reserved holes, the leveling holes are equipped with adjusting parts for adjusting the elevation and slope of the prefabricated road panel, the slurry of the leveling adhesive layer before solidification can be filled into the reserved holes, and the slurry can flow into the leveling adhesive layer through the reserved holes and solidify into an integrated structure with the unsolidified slurry of the leveling adhesive layer.

[0008] In order to effectively increase the bonding force between the prefabricated road panel and the leveling bonding layer and improve the shear resistance between the layers, a shear resistance structure matching the leveling bonding layer is formed at the bottom of the prefabricated road panel.

[0009] The shear-resistant structure can have various forms. Preferably, the shear-resistant structure is an inner concave portion concave at the bottom of the prefabricated road panel, or an outer convex portion convex at the bottom of the prefabricated road panel, or a wavy structure formed at the bottom of the prefabricated road panel. In addition, other different forms of uneven structures can also be used as long as the contact area between the prefabricated road panel and the adjustable bonding layer is increased.

[0010] Prefabricated road panels can adopt a variety of different structures. Preferably, the prefabricated road panel includes a main structure layer and an anti-skid layer arranged above the main structure layer. The main structure layer is embedded with a skeleton structure for enhancing the bearing capacity of the prefabricated road panel. Thus, the anti-skid layer plays an anti-skid role on the surface of the road panel, and the skeleton structure plays a role in improving the structural strength of the prefabricated road panel, thereby enhancing its overall strength and anti-deformation performance.

[0011] There can be many kinds of skeleton structures, preferably, the skeleton structure is a steel mesh or a fiber mesh. According to actual needs, one or more layers of fiber mesh or steel mesh can be provided.

[0012] As a preferred solution, the basic pavement is a road panel to be repaired and the prefabricated road panel is a block structure. One road panel to be repaired corresponds to at least two spliced ​​prefabricated road panels, and the skeleton structure is exposed on the spliced ​​side of the prefabricated road panel. Usually, one road panel to be repaired corresponds to four prefabricated road panels of the same size. At this time, wet joint construction is performed between adjacent prefabricated road panels.

[0013] As another preferred solution, the base pavement is the airport pavement panel to be repaired and the prefabricated pavement panel adopts a whole plate structure, the size of the prefabricated pavement panel is consistent with the airport pavement panel to be repaired, elastic rubber plates are arranged around the prefabricated pavement panel, and the skeleton structure is hidden inside the prefabricated pavement panel. At this time, the gaps between adjacent prefabricated pavement panels are filled.

[0014] As another preferred solution, the base road surface is a steel bridge deck, and the skeleton structure extends outwards around the prefabricated road panels. In this case, the width of a prefabricated road panel is substantially the same as the width of a lane, and wet joint construction is performed between adjacent prefabricated road panels.

[0015] In order to adjust the elevation and slope of the prefabricated road panel, as an adjustment scheme, an embedded nut is welded and fixed at the bottom of the skeleton structure, and the embedded nut is arranged directly below the leveling hole. The adjustment member is a leveling bolt that passes through the leveling hole from top to bottom and is threadedly connected to the embedded nut. The lower end of the leveling bolt passes through the embedded nut and is used to resist the basic road surface.

[0016] In order to prevent the lower end of the leveling bolt from directly abutting against the base road surface and thus damaging the base road surface, a leveling pad is installed on the base road surface, and the lower end of the leveling bolt abuts against the leveling pad.

[0017] It is further preferred that the prefabricated road panel is cast after the embedded bolts are screwed into the embedded nuts, and the embedded bolts are removed after the prefabricated road panel is cured and demoulded, thereby forming the leveling holes on the prefabricated road panel. In this way, after the embedded bolts are removed, the leveling holes obtained are countersunk bolt holes. After the installation and vibration are completed, the countersunk bolt holes are filled with polymer adhesive to form an integral I-shaped structure with the lower leveling adhesive layer. The formed I-shaped structure serves to increase the bonding strength and shear strength between the prefabricated road panel and the base road surface.

[0018] Further preferably, the embedded bolts are plastic cylindrical head bolts.

[0019] As another adjustment scheme, the basic pavement is the airport road panel to be repaired, and an embedded steel plate is welded and fixed on the top of the skeleton structure. The embedded steel plate is provided with an upper through hole aligned with the leveling hole, and the top of the prefabricated road panel is provided with a countersunk hole connected to the upper through hole. Planting bolts are pre-planted on the airport road panel to be repaired, and an elastic adjustment pad is sleeved on the planting bolts. The elastic adjustment pad is clamped between the prefabricated road panel and the airport road panel to be repaired, and a lower through hole is provided on the elastic adjustment pad. The planting bolt passes through the lower through hole, the leveling hole and the upper through hole from bottom to top and extends into the countersunk hole. The adjustment member is an adjustment nut provided in the countersunk hole and threadedly connected to the planting bolt. When adjusting the height, it is only necessary to rotate the adjustment nut to achieve the up and down movement of the prefabricated road panel through the deformation of the elastic adjustment pad. When the rotating adjusting nut drives the embedded steel plate to press down, the deformation of the elastic adjusting pad increases, the prefabricated road panel moves downward, and the installation height decreases. When the adjusting nut is rotated in the opposite direction, the deformation of the elastic adjusting pad decreases, the prefabricated road panel moves upward, and the installation height increases.

[0020] As another adjustment scheme, the basic pavement is a steel bridge deck, and a supporting steel plate is welded and fixed on the top of the skeleton structure, and an upper through hole is opened on the supporting steel plate and aligned with the leveling hole, and a countersunk hole connected to the upper through hole is opened on the top of the prefabricated road panel, and fixing bolts are fixed on the steel bridge deck, and an elastic adjustment pad is sleeved on the fixing bolts, and the elastic adjustment pad is clamped between the fixing bolts and the prefabricated road panel, and a lower through hole is opened on the elastic adjustment pad, and the fixing bolt passes through the lower through hole, the leveling hole and the upper through hole from bottom to top in sequence and extends into the countersunk hole, and the adjustment member is an adjusting nut arranged in the countersunk hole and threadedly connected to the fixing bolt. When adjusting the height, you only need to rotate the adjusting nut to realize the up and down movement of the prefabricated road panel through the deformation of the elastic adjusting pad. When the rotating adjusting nut drives the supporting steel plate to press down, the deformation of the elastic adjusting pad increases, the prefabricated road panel moves downward, and the installation height decreases. When the adjusting nut is rotated in the opposite direction, the deformation of the elastic adjusting pad decreases, the prefabricated road panel moves upward, and the installation height increases.

[0021] The fixing bolts can be fixed on the steel bridge deck in a variety of different ways. The heads of the fixing bolts are fixed on the steel bridge deck by welding or by bonding with an adhesive. Preferably, the fixing bolts are fixed by bonding with an adhesive.

[0022] The main structure layer is preferably cast with polyurethane concrete. Polyurethane concrete has the characteristics of excellent waterproof, anti-corrosion performance, rapid curing, excellent followability, fatigue resistance, etc., and has incomparable advantages over ordinary concrete. In addition, the main structure layer can also be made of inorganic cement concrete or other organic composite materials other than polyurethane, such as epoxy resin, furan resin, polyester resin and other materials.

[0023] In order to allow the leveling adhesive material to fill the reserved hole, the bottom of the reserved hole is in an eight-shaped structure with a small top and a large bottom. The reserved hole is used as a grouting hole and a grouting hole.

[0024] The technical solution adopted by the present invention to solve the above second technical problem is: a construction method of a prefabricated road panel installation structure, characterized in that the base pavement used by the prefabricated road panel installation structure is the airport road panel to be repaired, and the construction method comprises the following steps: S101. Surface treatment of the airport runway panels to be repaired; S102, leveling the bonding layer, laying the leveling bonding layer on the airport runway panel to be repaired; S103, hoisting the prefabricated prefabricated road panels piece by piece to the designated position above the airport road panel to be repaired; S104, making the prefabricated road panel and the leveling adhesive layer fully and densely bonded by vibration; S105, adjusting the elevation and slope of the prefabricated road panel by means of an adjusting member; S106, performing grouting through the reserved holes, the grouting being completed before the leveling adhesive layer is cured, and the grouting liquid and the uncured leveling adhesive layer grout are cured and formed synchronously; S107. Processing the joints between adjacent prefabricated road panels.

[0025] Further preferably, in step S101, firstly, special repairs are carried out on the defects existing in the surface layer of the airport road panel, and then the surface of the airport road panel to be repaired is cleaned and dried, including by high-pressure water washing, shot blasting, milling and the like, to ensure that the foundation is intact and the surface paved slabs are firmly bonded.

[0026] Further preferably, in step S102, the treatment thickness of the leveling adhesive layer is 5-50 mm, the material solidification time is ≤60 minutes, and the compressive strength of the leveling adhesive layer after casting is ≥25 MPa. The leveling adhesive layer has the characteristics of high toughness, super strong adhesion, leveling, high temperature self-repairing function, no shrinkage, high early strength, and can be cast in place.

[0027] Further preferably, in step S103, the prefabricated road panel is accurately hoisted to a designated position by hoisting and positioning equipment.

[0028] Further preferably, in step S104, the leveling adhesive layer fills the shear structure at the bottom of the prefabricated road panel, the reserved holes and the joints of adjacent prefabricated road panels due to the pressure and vibration of the prefabricated road panel. After the prefabricated road panel is tightly bonded to the leveling adhesive layer, the elevation of the installed prefabricated road panel is remeasured to detect the misalignment and make corrections.

[0029] Further preferably, in step S105, if the adjusting member is a leveling bolt, the prefabricated road panel is driven to move up and down by rotating the leveling bolt; if the adjusting member is an adjusting nut, the prefabricated road panel is driven to move up and down by rotating the adjusting nut.

[0030] Further preferably, if the adjusting member adopts a leveling bolt, after the leveling action is completed, the leveling bolt is screwed out of the leveling hole, and then the leveling hole is post-grouted and sealed, or the leveling bolt is retained in the leveling hole and the leveling hole is post-grouted and sealed.

[0031] Further preferably, in step S106, grouting is performed using a leveling adhesive layer material to firmly bond the prefabricated road panel to the base pavement, thereby ensuring the compactness of the structure and preventing grouting and voids, so as to ensure the overall stability of the road panel. Grouting should be completed in time before the leveling adhesive layer solidifies to achieve synchronous solidification and molding.

[0032] Further preferably, in step S107, if the prefabricated road panel adopts a block plate structure, the wet joints between adjacent prefabricated road panels are filled with the material of the leveling adhesive layer, and prefabricated sand identical to the anti-slip layer on the surface of the prefabricated road panel is sprinkled on the surface of the wet joint filling layer, and the surface is ground.

[0033] Further preferably, in step S107, if the prefabricated road panel adopts the whole plate structure, the prefabricated road panel and the airport road panel to be repaired are completely overlapped and bonded and cured, then the elastic rubber sheet around the prefabricated road panel is removed and the seams between adjacent prefabricated road panels are cleaned, and the seams are sealed with caulking material to ensure that the joints are watertight.

[0034] There can be many kinds of caulking materials. Preferably, the caulking material is polyurethane, silicone or polysulfide sealant.

[0035] The technical solution adopted by the present invention to solve the third technical problem is: a construction method of a prefabricated road panel installation structure, characterized in that the base road surface used by the prefabricated road panel installation structure is a steel bridge deck, and the construction method comprises the following steps: S201. Survey the quality of steel bridge decks. Before construction, check and clean the oil, water, welding slag and welding nodules on the bridge decks, and check the flatness of the bridge decks; S202, Shot blasting and rust removal of steel bridge deck; S203, leveling the bonding layer, adding a self-repairing material capable of repairing cracks in a high temperature environment into the leveling bonding layer; S204, hoisting the prefabricated prefabricated road panels piece by piece to a designated position above the steel bridge deck by means of hoisting equipment; S205, making the prefabricated road panel fully contact with the leveling adhesive layer by vibration, re-measure the elevation of the installed prefabricated road panel, detect the misalignment and make corrections, and the leveling adhesive layer fills the shear structure at the bottom of the prefabricated road panel, the reserved holes and the joint positions of adjacent prefabricated road panels due to the pressure and vibration of the prefabricated road panel; S206, adjusting the elevation and slope of the prefabricated road panel by means of an adjusting member; S207, using the same material as the leveling adhesive layer to perform grouting through the reserved holes, the grouting is completed before the leveling adhesive layer is cured, and the grouting liquid and the uncured grout of the leveling adhesive layer are synchronously cured and formed; S208. Treat the joints between adjacent prefabricated road panels by filling the joints with the same material as the leveling adhesive layer to form a joint filling layer.

[0036] It is further preferred that the deformation performance of the leveling adhesive layer and the joint filling layer structure is greater than that of the prefabricated road panel, so that it forms a rigid-flexible group with the prefabricated road panel. A leveling adhesive material with flexibility, deformation performance greater than that of the prefabricated panel, stress release, high toughness, super strong adhesion, leveling and high-temperature self-repairing functions is used as the bottom leveling adhesive and filling material at the joints. A combination of rigid prefabricated road panels and flexible joints is used to improve the functional grading complementarity and stability of the steel bridge deck structure, meet the needs of multi-dimensional deformation and stress release generated by the bridge under the action of external forces, enable the pavement layer to adapt to the deformation and strain of the steel bridge, improve the driving comfort of the steel bridge deck, reduce or delay the occurrence of surface damage, significantly improve the reliability of the pavement, reduce the probability of maintenance, greatly shorten the construction time, and effectively extend the service life of the pavement in service.

[0037] Further preferably, in step S203, the self-repairing material is Class III original fly ash or graphene / polymer composite material, the treatment thickness of the leveling adhesive layer is preferably 5-50 mm, the material solidification time is ≤ 60 minutes, and the compressive strength of the leveling adhesive layer after casting is ≥ 25 MPa, and the flexural tensile strength is ≥ 5 MPa. When exposed to a high temperature environment, the self-repairing material can self-repair microcracks and improve the mechanical properties and high temperature resistance of the structure.

[0038] Compared with the prior art, the advantages of the present invention are: the prefabricated road panel installation structure lays a leveling adhesive layer on the basic road surface, installs the prefabricated road panel on the leveling adhesive layer, adjusts the elevation and slope of the prefabricated road panel by adjusting parts, and the reserved holes are used as grouting holes and grouting holes. The grouting liquid and the adjusting sheet adhesive layer are solidified into an integrated structure, and the interlayer bonding force is good, the bearing capacity is sufficient, the anti-freezing and thawing performance is good, the flatness is good, and the molding time is fast. The prefabricated road panel can realize splicing, full-width rapid on-site assembly and thickening construction on different types of basic road surfaces. For example, when it is used to repair the airport road panel, it can not affect the normal operation of the airport, realize rapid large-area delivery, and meet the high quality requirements of the airport road surface. When it is applied to the steel bridge deck, it can form a rigid-flexible assembled structure, which can greatly meet the bridge, especially the extra-large flexible steel bridge, and produce multi-dimensional deformation and stress release under the action of external force. Whether it is used for new construction or maintenance, it will not cause any change or impact on the original bridge structure and function. At the same time, it greatly improves the quality and construction efficiency of the bridge deck structure layer, and realizes rapid large-area delivery. BRIEF DESCRIPTION OF THE DRAWINGS

[0039] Figure 1 This is a structural schematic diagram of a prefabricated road panel installation structure according to Embodiment 1 of the invention; Figure 2 A cross-sectional view of a pavement surface of a prefabricated pavement panel installation structure according to Embodiment 1 of the present invention; Figure 3 This is a schematic diagram of the structure of the block board according to the first embodiment of the present invention; Figure 4 for Figure 3 A structural cross-sectional view of the block plate shown; Figure 5 for Figure 3 Another structural cross-sectional view of the block plate shown; Figure 6 for Figure 5 An enlarged schematic diagram of part I; Figure 7 This is a structural cross-sectional view of a prefabricated road panel in a formed state according to Embodiment 1 of the present invention; Figure 8 This is a structural cross-sectional view of a prefabricated road panel in a demoulding state according to Embodiment 1 of the present invention; Fig. 9This is a structural cross-sectional view of a prefabricated road panel in an installed state according to Embodiment 1 of the present invention; Fig.10 This is a schematic diagram of a leveling structure of a prefabricated road panel according to Embodiment 1 of the present invention; Fig.11 This is a schematic diagram of another leveling structure of the prefabricated road panel according to the first embodiment of the present invention; Fig.12 This is a structural schematic diagram of a grouting joint installed on a prefabricated road panel according to the first embodiment of the present invention; Fig.13 This is a schematic diagram of the installation structure of the block board according to the first embodiment of the present invention; Fig.14 This is a schematic diagram of the wet joint structure of the block panels according to the first embodiment of the present invention; Fig.15 This is a schematic structural diagram of the entire board according to the first embodiment of the present invention; Fig.16 for Fig.15 A structural cross-sectional view of the precast road panel shown; Fig.17 for Fig.15 Schematic diagram of vibration filling of precast road panel shown; Fig.18 for Fig.14 The schematic diagram of the installation structure of the prefabricated road panel is shown; Fig.19 for Fig.15 The full-width structural diagram of the prefabricated road panel after installation is shown; Fig. 20 This is a schematic structural diagram of the shear-resistant structure of the first embodiment of the present invention in a molded state of an outer convex portion; Fig.21 This is a schematic diagram of the structure of the first embodiment of the present invention in which the shear-resistant structure is an outer convex part in a demoulding state; Fig. 22 This is a schematic diagram of the structure of the first embodiment of the present invention when the shear-resistant structure is in an installed state with the outer convex part; Fig.23 A cross-sectional view of a pavement surface of a prefabricated pavement panel in which the shear-resistant structure is an outer convex portion according to the first embodiment of the present invention; Fig.24 This is a structural schematic diagram of a prefabricated road panel installation structure according to a second embodiment of the present invention; Fig.25 A cross-sectional view of the pavement surface of the prefabricated pavement panel installation structure according to the second embodiment of the present invention Fig.26 This is a schematic structural diagram of a prefabricated road panel according to a second embodiment of the present invention; Fig. 27 for Fig.26 A structural cross-sectional view of the precast road panel shown; Fig.28 for Fig.26 Schematic diagram of vibration filling of precast road panel shown; Fig.29 This is a schematic diagram of the installation structure of the prefabricated road panel according to the second embodiment of the present invention; Fig.30 This is a schematic diagram of the leveling structure of the second embodiment of the present invention. DETAILED DESCRIPTION

[0040] The present invention is further described in detail below with reference to the accompanying drawings. Embodiment 1:

[0041] like Figures 1 to 6 As shown, the prefabricated road panel installation structure of this embodiment includes a leveling adhesive layer 2 laid on the base road surface 1 and a prefabricated road panel 3 arranged on the leveling adhesive layer 2. The base road surface 1 is the airport road panel to be repaired. The bottom of the prefabricated road panel 3 is formed with a shear-resistant structure that matches the leveling adhesive layer 2. The shear-resistant structure can effectively increase the bonding force between the prefabricated road panel 3 and the leveling adhesive layer 2, and improve the shear resistance between the layers. The shear-resistant structure of this embodiment is an inner concave portion 35 that is concave at the bottom of the prefabricated road panel 3 and is semicircular. Figures 20 to 23 As shown, the shear structure is a convex portion 36 protruding from the bottom of the prefabricated road panel 3, and the convex portion is also semicircular. In addition, the shear structure can also be in other different forms such as wave shape, trapezoidal shape, etc., as long as the contact area between the prefabricated road panel and the adjustable bonding layer is increased.

[0042] The prefabricated road panel 3 can be standardized and batch-produced by an intelligent flow-type device, which effectively ensures that the prefabricated road panel 3 is flat, uniform, high-quality and stable. Specifically, the prefabricated road panel 3 is divided into two layers, the lower layer is the main structure layer 31, and the upper layer is the anti-skid layer 32. The main structure layer 31 is embedded with a skeleton structure 37 for enhancing the bearing capacity of the prefabricated road panel 3. In this embodiment, the main structure layer 31 is cast with a polymer mixture with excellent corrosion resistance, good weather resistance and rapid curing. Inorganic cement concrete or organic composite materials such as polyurethane, epoxy resin, furan resin, polyester resin and other materials can be used. Polyurethane concrete is preferably used for casting. Polyurethane concrete has the characteristics of excellent waterproof, anti-corrosion performance, rapid curing, excellent follow-up, fatigue resistance and the like, and has incomparable advantages compared with ordinary concrete.

[0043] The skeleton structure 37 is made of steel mesh, which can be one layer or two layers. In addition, the skeleton structure 37 can also be made of fiber mesh. The skeleton structure 37 plays a role in improving the structural strength of the prefabricated road panel 3, and enhancing its overall strength and anti-deformation performance. When manufacturing the prefabricated road panel 3, the top surface of the prefabricated road panel 3 is provided with a non-slip layer 32 formed by spreading high-wear-resistant sand particles in the vibrated and extracted surface mortar and leveling it by grinding or other methods. The non-slip layer 32 plays a role in preventing the surface of the road panel from slipping, so that its friction system can meet the design standards of various road surfaces.

[0044] like Figure 7 As shown, before pouring the prefabricated road panel 3, the embedded bolt 410 is screwed into the embedded nut 41, and the embedded bolt adopts a plastic cylindrical head bolt. Figure 8 As shown, after the prefabricated road panel 3 is cured and demoulded, the embedded bolts 410 are removed. After the embedded bolts are removed, the countersunk bolt holes obtained are the leveling holes 33. Fig. 9 As shown, after the installation and vibration are completed, the countersunk bolt holes are filled with the same polymer adhesive as the leveling adhesive layer 2, so that it forms an integral I-shaped structure 21 with the lower leveling adhesive layer 2. The I-shaped structure 21 serves to increase the bonding strength and shear strength between the prefabricated road panel 3 and the base road surface 1. In addition, the leveling hole 33 can also be used as a hoisting hole, and the hoisting equipment hoists the prefabricated prefabricated road panel 3 to the designated position above the airport road panel to be repaired through the hoisting hole. The hoisting hole can be used as a connection hole with the lifting equipment during the hoisting and transportation of the prefabricated road panel 3. The connection of multiple connection holes can control the deformation of the product during the hoisting process, protect the transportation of the product, and reduce the problem of cracking and damage of the product during the hoisting process.

[0045] like Fig.10As shown, an embedded nut 41 is welded and fixed at the bottom of the skeleton structure 37, and the embedded nut 41 is arranged just below the leveling hole 33. A leveling pad 43 is installed on the base pavement 1, and the leveling pad 43 is located just below the embedded nut 41. When the prefabricated road panel 3 is installed, due to the flatness height difference of the base pavement 1 and the plasticity of the leveling adhesive before curing, the prefabricated road panel 3 will sink and be uneven, resulting in the flatness of the prefabricated road panel 3 not meeting the requirements during installation. Therefore, a leveling hole 33 is set and a bolt adjustment assembly is configured, and a leveling point is set at an appropriate position of the prefabricated panel. Specifically, the bolt adjustment assembly adopts a leveling bolt 42, which passes through the leveling hole 33 from top to bottom and is threadedly connected to the embedded nut 41, and the lower end of the leveling bolt 42 passes through the embedded nut 41 and abuts against the leveling pad 43. The contact area between the leveling bolts 42 and the airport road panel 1 to be repaired is increased by the leveling pad 43 to ensure that the original road surface is not damaged during the height adjustment process. When the elevation and slope of the prefabricated road panel 3 need to be adjusted, it is only necessary to rotate the leveling bolts to drive the prefabricated road panel to move up and down. The adjustment is very convenient, and the adjustment process is automatically completed by the height adjustment equipment. After the height adjustment action is completed, after the leveling adhesive layer is solidified or reaches the weight that can bear the weight of the road panel, it is preferred to screw the leveling bolts 42 out of the leveling holes 33, and then perform post-grouting and plugging on the leveling holes 33. It is also possible not to screw out the leveling bolts 42, and also perform post-grouting and plugging on the leveling holes 33.

[0046] like Fig.11 As shown, when the basic pavement 1 adopts a concrete structure such as an airport road panel, the following height adjustment structure can also be used to adjust the height of the prefabricated road panel 2. The specific structure is: a pre-embedded steel plate 44 is welded and fixed on the top of the skeleton structure 37, and an upper through hole aligned with the leveling hole 33 is opened on the pre-embedded steel plate 44. A countersunk hole 38 connected to the upper through hole is opened on the top of the prefabricated road panel 3. A planting bolt 45 is pre-planted on the airport road panel to be repaired, and an elastic adjustment pad 46 is sleeved on the planting bolt 45. The elastic adjustment pad 46 is clamped between the prefabricated road panel 3 and the airport road panel to be repaired. A lower through hole is opened on the elastic adjustment pad 46. The planting bolt 45 passes through the lower through hole, the leveling hole 33 and the upper through hole from bottom to top in sequence and extends into the countersunk hole 38. The adjusting nut 47 is arranged in the countersunk hole 38 and is threadedly connected to the planting bolt 45. When adjusting the height, it is only necessary to rotate the adjustment nut 47 to achieve the up and down movement of the prefabricated road panel 3 through the deformation of the elastic adjustment pad 46. When the rotation of the adjustment nut 47 drives the embedded steel plate 44 to press down, the deformation of the elastic adjustment pad 46 increases, the prefabricated road panel 3 moves downward, and the installation height decreases. When the adjustment nut 47 is rotated in the opposite direction, the deformation of the elastic adjustment pad 46 decreases, the prefabricated road panel 3 moves upward, and the installation height increases. Generally, this height adjustment structure is suitable for occasions where the basic road surface 1 is relatively flat and the planting bolts 45 can be implanted.

[0047] like Fig.12 As shown, in addition, the prefabricated road panel 3 is also formed with a reserved hole 34, which is used as a grouting hole and a grouting hole. After the prefabricated road panel 3 is installed on the uncured leveling adhesive layer 2, during vibration leveling, the uncured slurry of the leveling adhesive layer 2 fills the grouting hole. The grouting hole can monitor and grasp the vibration state at any time during the installation process. The grouting hole can be used as a grouting hole after the product is installed, which can effectively grout the area where the product adhesive is insufficient.

[0048] The functions of the grouting holes and the grouting holes are to exhaust and grouting. The grouting uses the material of the leveling adhesive layer. The grouting holes are equipped with grouting joints 7. The grouting liquid flows into the leveling adhesive layer 2 through the grouting joints 7. The grouting should be completed in time before the leveling adhesive layer 2 solidifies, so as to achieve synchronous solidification and form an integrated structure, so that the prefabricated road panel 3 and the base road surface 1 are firmly combined, the density of the structure is ensured, and the lack of grout and voiding phenomenon is prevented to ensure the overall stability of the road panel. In order to help the leveling adhesive material fill the grouting holes and the grouting holes, the bottom of the reserved hole 34 is an eight-shaped structure 341 with a small top and a large bottom.

[0049] The distribution positions of the leveling holes 33 and the reserved holes 34 are not limited to Figure 3 The position shown can be adjusted according to the actual situation on site.

[0050] like Fig.13 and Fig.14 As shown, the prefabricated road panel 3 adopts a block panel structure. Assuming that the width of the airport road panel to be repaired is 4.5 meters, the size of each prefabricated road panel 3 is preferably 2.17m×2.42m, that is, one airport road panel requires four prefabricated road panels 3 to be spliced ​​and repaired. Figure 3 As shown, the skeleton structure 37 is exposed at the joint side of the prefabricated road panel 3. A wet joint 5 is formed between adjacent prefabricated road panels 3. After the prefabricated road panels 3 are installed, the wet joint 5 is filled with the material of the leveling adhesive layer 2, and the surface of the filling layer of the wet joint 5 is sprinkled with prefabricated sand that is the same as the anti-slip layer 32 on the surface of the prefabricated road panel 3, and the surface is ground.

[0051] like Figures 15 to 19As shown, the prefabricated road panel 3 adopts a whole plate structure, and the size of each prefabricated road panel 3 is 4.5m×5m, that is, the prefabricated road panel 3 is made according to the specifications of the airport road panel to be repaired, and the widths of the two are consistent. Pre-set elastic rubber plates (not shown in the figure) are pasted around the prefabricated road panel 3, and the skeleton structure 37 is hidden inside the prefabricated road panel 3. After the prefabricated road panel 3 and the original road panel are completely overlapped and bonded and cured, the elastic rubber plate is removed and the seams 6 between the adjacent prefabricated road panels 3 are cleaned, and the seams 6 are filled with caulking materials such as polyurethane, silicone or polysulfide sealant to ensure that the joints are water-proof. The installation structure and leveling structure of the prefabricated road panel 3 of the whole plate are the same as those of the prefabricated road panel 3 of the block plate, and will not be described in detail here.

[0052] The construction method of the prefabricated road panel installation structure of this embodiment is applied to the repair of airport road panels, and the construction method comprises the following steps: S101. Surface treatment of the airport runway panels to be repaired; S102, leveling the adhesive layer 2, laying the leveling adhesive layer 2 on the airport runway panel to be repaired; S103, hoisting the prefabricated prefabricated road panels 3 piece by piece to the designated position above the airport road panel to be repaired; S104, making the prefabricated road panel 3 and the leveling adhesive layer 2 fully and densely bonded by vibration; S105, adjusting the elevation and slope of the prefabricated road panel 3 by adjusting the adjusting member; S106, grouting is performed through the reserved hole 34, and the grouting is completed before the leveling adhesive layer 2 is cured, and the grouting liquid and the uncured grout of the leveling adhesive layer 2 are synchronously cured and formed; S107 , processing the joints between adjacent prefabricated road panels 3 .

[0053] Among them, in step S101, firstly, special repairs are carried out on the defects existing in the surface layer of the airport road panel, and then the surface of the airport road panel to be repaired is cleaned and dried, including high-pressure water washing, shot blasting, milling and other methods to ensure that the foundation is intact and the surface paved road panel is firmly bonded. In step S102, the treatment thickness of the leveling adhesive layer 2 is 5-50mm, the material solidification time is ≤60 minutes, and the compressive strength of the leveling adhesive layer 2 after casting is ≥25MPa. The leveling adhesive layer 2 has the characteristics of high toughness, high fluidity, no shrinkage, high early strength, super strong adhesion, leveling, cast-in-place, high temperature self-repairing function, etc., which can effectively guarantee the bonding strength with the original road surface, and can penetrate into the pores and cracks of the airport road panel concrete, and play a role in penetration repair and strong bonding on the original road surface. In step S103, hoisting equipment and measurement measures are used to ensure the accuracy of the positioning of the prefabricated road panel 3. The hoisting process should avoid safety hazards or collisions with related objects and road panels to cause damage, so as to realize intelligent installation. In step S104, the leveling adhesive layer 2 fills the shear structure, grouting holes and joints of adjacent prefabricated road panels 3 at the bottom of the prefabricated road panel 3 due to the pressure and vibration of the prefabricated road panel 3. After the prefabricated road panel 3 and the leveling adhesive layer 2 are tightly bonded, the elevation of the installed prefabricated road panel 3 is re-measured to detect the misalignment and make corrections. In step S105, after the leveling is completed, the upper end of the leveling bolt 42 is ensured to be within the height range of the countersunk hole 38. On the day of construction, the leveling bolt 42 is left in the prefabricated road panel 3 to ensure the normal use of the prefabricated road panel 3. In the subsequent construction process, the leveling bolt 42 is screwed out of the leveling hole 33, and then the leveling hole 33 is post-grouted and sealed.

[0054] The above construction method can be used for full-width rapid on-site assembly and thickening construction, with good interlayer bonding, sufficient bearing capacity, good freeze-thaw resistance, good flatness, fast molding time, wear resistance, corrosion resistance, and is suitable for various civil and military airports. It can realize large-scale precise installation and replacement maintenance of airport pavements in a short period of time, achieving the purpose of non-stop construction at the airport. In addition, it can also be used in bridges and squares where large-scale on-site assembled prefabricated pavement panel structures are used.

[0055] Embodiment 2: like Figures 24 to 30 As shown, the base pavement 1 of the prefabricated road panel installation structure of this embodiment is a steel bridge deck, and the skeleton structure 37 extends outwardly around the prefabricated road panel 3. The width of the prefabricated road panel 3 is substantially consistent with the width of the lane, and the size of the prefabricated road panel 3 of the large plate-like structure is preferably a whole plate structure of 3.75m×3m.

[0056] In addition to the leveling bolts 42 of the first embodiment, the height adjustment structure of the prefabricated road panel installation structure can also adopt the following height adjustment structure: A support steel plate 49 is welded and fixed on the top of the skeleton structure 37. An upper through hole aligned with the leveling hole 33 is formed on the support steel plate 49. A countersunk hole 38 connected with the upper through hole is formed on the top of the prefabricated road panel 3. A fixing bolt 48 is fixed on the steel bridge deck. An elastic adjustment pad 46 is sleeved on the fixing bolt 48. The elastic adjustment pad 46 is clamped between the fixing bolt 48 and the prefabricated road panel 3. The thickness of the elastic adjustment pad 46 can be used as the preset height for the installation of the prefabricated road panel 3. A lower through hole is formed on the elastic adjustment pad 46. The fixing bolt 48 passes through the lower through hole, the leveling hole 33 and the upper through hole from bottom to top and extends into the countersunk hole 38. The lower part of the fixing bolt 48 is welded and fixed on the steel bridge deck or fixed on the steel bridge deck by bonding with an adhesive. The adhesive preferably uses high-strength epoxy glue. The adjustment member is an adjustment nut 47 arranged in the countersunk hole 38 and threadedly connected to the fixing bolt 48. During adjustment, the adjusting nut 47 is rotated, and the adjusting nut 47 drives the supporting steel plate 49 to press downward, causing the elastic adjusting pad 46 to deform, thereby causing the prefabricated road panel 3 to move downward and the installation height to decrease. When the adjusting nut 47 is rotated in the opposite direction, the deformation of the elastic adjusting pad 46 decreases, the prefabricated road panel 3 moves upward, and the installation height increases.

[0057] When the construction method of the prefabricated road panel installation structure is applied to the repair of a steel bridge deck, the construction method comprises the following steps: S201. Survey the quality of the steel bridge deck. Before construction, check and clean the oil, water, welding slag and welding nodules on the bridge deck, and check the flatness of the bridge deck; arrange personnel to cut and polish the parts of the local steel box girder with poor flatness in advance; S202, Steel bridge deck shot blasting and rust removal: After the steel bridge deck is shot blasted and rust removed, the cleanliness and roughness should be inspected. The cleanliness can be checked visually by comparing with the standard sample, and the roughness grade marked on the sample that is closest to the surface to be tested is used as the evaluation result. The humidity of the steel bridge deck should be ≤85%, and the cleanliness should reach Sa2.5 level; S203, treatment of the leveling adhesive layer 2; before the construction of the leveling adhesive layer, the construction area is inspected to ensure that there is no pollution such as oil and water stains and to ensure the cleanliness of the steel bridge deck. A leveling adhesive layer 2 is laid that has flexibility, deformation performance greater than that of the prefabricated board, stress release, high toughness, super strong adhesion, leveling and high-temperature self-repairing functions, and a self-repairing material that can repair cracks in a high temperature environment is added to the leveling adhesive layer 2; the self-repairing material can be Class III original fly ash or a graphene / polymer composite material. When exposed to a high temperature environment, the self-repairing material can self-repair microcracks and improve the mechanical properties and high temperature resistance of the structure. The leveling adhesive material used can effectively improve the bonding strength with the steel bridge deck and fill the bottom of the prefabricated road panel 3 and the joints between the panels. The treatment thickness of the leveling adhesive layer 2 is 5-50mm, the material solidification time is ≤60 minutes, and the compressive strength of the leveling adhesive layer 2 after casting is ≥25MPa, and the flexural tensile strength is ≥5MPa; S204, hoisting the prefabricated prefabricated road panels 3 piece by piece to the designated position above the steel bridge deck by hoisting equipment; ensuring the accuracy of the road panel positioning by measuring measures to achieve intelligent installation; S205, the prefabricated road panel 3 is fully contacted with the leveling adhesive layer 2 by vibration, and the elevation of the installed prefabricated road panel 3 is re-measured to detect the misalignment and make corrections. Due to the pressure and vibration of the prefabricated road panel 3, the leveling adhesive layer 2 fills the shear structure at the bottom of the prefabricated road panel 3, the reserved hole 34 and the joint position of the adjacent prefabricated road panel 3; S206, adjusting the elevation and slope of the prefabricated road panel 3 by means of an adjusting member; preferably, leveling is performed by means of a leveling bolt 42, and the leveling method is consistent with that of the first embodiment; S207, using the same material as the leveling adhesive layer 2 to perform grouting through the reserved hole 34, the grouting is completed before the leveling adhesive layer 2 is cured, and the grouting liquid and the uncured grout of the leveling adhesive layer 2 are simultaneously cured and formed to ensure the compactness of the structure, prevent the lack of grout and the void phenomenon, and ensure the overall stability of the road panel; S208, processing the joints between adjacent prefabricated road panels 3, using the same material as the leveling adhesive layer 2 to fill the joints to form a joint filling layer 8. Sprinkle the same prefabricated sand as the anti-slip layer 32 on the joint filling layer 8.

[0058] The prefabricated road panel 3 is rigid, the leveling adhesive layer 2 and the joint filling layer 8 are flexible, and their deformation performance is greater than that of the prefabricated road panel 3. The combination of rigid prefabricated road panels and flexible joints improves the functional grading complementarity and stability of the steel bridge deck structure. The deformation of the wet joints at the marking line meets the requirements of multi-dimensional deformation and stress release of bridges, especially large flexible steel bridges, under the action of external forces, and plays the role of a bridge deck expansion device, improving the functional grading complementarity and stability of the steel bridge deck structure, so that the pavement layer can adapt to the deformation and strain of the steel bridge, improve the driving comfort of the steel bridge deck, reduce or delay the occurrence of surface damage, significantly improve the reliability of the road surface, reduce the probability of maintenance, greatly shorten the construction time, and effectively extend the service life of the service road surface. Whether used for new construction or maintenance, it will not cause any changes or impacts on the original bridge structure and function.

[0059] After the prefabrication of the prefabricated road panels is completed, they can be combined with the steel bridge panels before they are hoisted and connected, or they can be quickly, intelligently and accurately installed through intelligent hoisting equipment after the steel bridge panels are hoisted and connected, and then their joints can be processed to achieve rapid opening of traffic, greatly improve the quality and construction efficiency of the bridge deck structure layer, and achieve the goal of rapid and large-scale delivery.

[0060] In the specification and claims of the present invention, terms indicating directions, such as "front", "rear", "up", "down", "left", "right", "side", "top", "bottom", etc., are used to describe various exemplary structural parts and elements of the present invention, but these terms are used here only for the purpose of convenience of description and are determined based on the exemplary orientations shown in the accompanying drawings. Since the embodiments disclosed in the present invention can be arranged in different directions, these terms indicating directions are only used as explanations and should not be regarded as limitations. For example, "up" and "down" are not necessarily limited to directions opposite to or consistent with the direction of gravity.

Claims

1. A prefabricated road panel installation structure, Features: The invention comprises a leveling adhesive layer (2) laid on a basic road surface (1) and a prefabricated road panel (3) arranged on the leveling adhesive layer (2), wherein the prefabricated road panel (3) is formed with a leveling hole (33) and a reserved hole (34), wherein the leveling hole (33) is equipped with an adjusting member for adjusting the elevation and slope of the prefabricated road panel (3), wherein the slurry of the leveling adhesive layer (2) before solidification can be filled into the reserved hole (34), and the slurry can flow into the leveling adhesive layer (2) through the reserved hole (34) and solidify with the unsolidified slurry of the leveling adhesive layer (2) to form an integrated structure.

2. The prefabricated road panel installation structure according to claim 1, Features: The bottom of the prefabricated road panel (3) is formed with a shear-resistant structure that matches the leveling adhesive layer (2).

3. The prefabricated road panel installation structure according to claim 2, Features: The shear-resistant structure is an inner concave portion (35) recessed at the bottom of the prefabricated road panel (3), or an outer convex portion (36) protruding at the bottom of the prefabricated road panel (3), or a wavy structure formed at the bottom of the prefabricated road panel (3).

4. The prefabricated road panel installation structure according to claim 1, Features: The prefabricated road panel (3) comprises a main structural layer (31) and an anti-slip layer (32) arranged above the main structural layer (31), and a skeleton structure (37) for enhancing the bearing capacity of the prefabricated road panel (3) is embedded in the main structural layer (31).

5. The prefabricated road panel installation structure according to claim 4, Features: The skeleton structure (37) is a steel mesh or a fiber mesh.

6. The prefabricated road panel installation structure according to claim 4, Features: The basic pavement (1) is a road panel to be repaired and the prefabricated road panel (3) is a block panel structure. One road panel to be repaired corresponds to at least two spliced ​​prefabricated road panels (3), and the skeleton structure (37) is exposed on the spliced ​​side of the prefabricated road panel (3).

7. The prefabricated road panel installation structure according to claim 4, Features: The basic pavement (1) is a road panel for an airport to be repaired and the prefabricated road panel (3) adopts a whole plate structure. The size of the prefabricated road panel (3) is consistent with that of the road panel for an airport to be repaired. Elastic rubber plates are provided around the prefabricated road panel (3), and the skeleton structure (37) is hidden inside the prefabricated road panel (3).

8. The prefabricated road panel installation structure according to claim 4, Features: The basic road surface (1) is a steel bridge deck, and the skeleton structure (37) extends outwards around the prefabricated road surface panel (3).

9. The prefabricated road panel installation structure according to claim 4, Features: An embedded nut (41) is welded and fixed at the bottom of the skeleton structure (37); the embedded nut (41) is arranged directly below the leveling hole (33); the adjustment member is a leveling bolt (42) that passes through the leveling hole (33) from top to bottom and is threadedly connected to the embedded nut (41); the lower end of the leveling bolt (42) passes through the embedded nut (41) and is used to abut against the base pavement (1).

10. The prefabricated road panel installation structure according to claim 9, Features: A leveling pad (43) is installed on the basic road surface (1), and the lower end of the leveling bolt (42) abuts against the leveling pad (43).

11. The prefabricated road panel installation structure according to claim 9, Features: After the embedded bolts (410) are screwed into the embedded nuts (41), the prefabricated road panel (3) is cast, and after the prefabricated road panel (3) is cured and demoulded, the embedded bolts (410) are removed, thereby forming the leveling holes (33) on the prefabricated road panel (3).

12. The prefabricated road panel installation structure according to claim 4, Features: The basic pavement (1) is a road panel for an airport to be repaired. A pre-buried steel plate (44) is welded and fixed on the top of the skeleton structure (37). The pre-buried steel plate (44) is provided with an upper through hole aligned with the leveling hole (33). The top of the prefabricated road panel (3) is provided with a countersunk hole (38) connected with the upper through hole. A planting bolt (45) is pre-planted on the road panel for an airport to be repaired. An elastic adjustment pad (46) is sleeved on the planting bolt (45). The elastic adjustment pad (46) is clamped between the prefabricated road panel (3) and the road panel for an airport to be repaired. A lower through hole is provided on the elastic adjustment pad (46). The planting bolt (45) passes through the lower through hole, the leveling hole (33) and the upper through hole in sequence from bottom to top and extends into the countersunk hole (38). The adjustment member is an adjustment nut (47) provided in the countersunk hole (38) and threadedly connected to the planting bolt (45).

13. The prefabricated road panel installation structure according to claim 4, Features: The basic pavement (1) is a steel bridge deck. A supporting steel plate (49) is welded and fixed on the top of the skeleton structure (37). An upper through hole aligned with the leveling hole (33) is formed on the supporting steel plate (49). A countersunk hole (38) connected to the upper through hole is formed on the top of the prefabricated road panel (3). A fixing bolt (48) is fixed on the steel bridge deck. An elastic adjustment pad (46) is sleeved on the fixing bolt (48). The elastic adjustment pad (46) is clamped between the fixing bolt (48) and the prefabricated road panel (3). A lower through hole is formed on the elastic adjustment pad (46). The fixing bolt (48) passes through the lower through hole, the leveling hole (33) and the upper through hole from bottom to top in sequence and extends into the countersunk hole (38). The adjusting member is an adjusting nut (47) arranged in the countersunk hole (38) and threadedly connected to the fixing bolt (48).

14. The prefabricated road panel installation structure according to claim 13, Features: The heads of the fixing bolts (48) are fixed on the steel bridge deck by welding or by bonding with an adhesive.

15. The prefabricated road panel installation structure according to claim 4, Features: The main structural layer (31) is cast using polyurethane concrete.

16. The prefabricated road panel installation structure according to claim 1, Features: The bottom of the reserved hole (34) is in an eight-shaped structure (341) that is smaller at the top and larger at the bottom.

17. A construction method for a prefabricated road panel installation structure, Features The construction method is applied to the prefabricated road panel installation structure according to any one of claims 1 to 16, wherein the basic road panel is an airport road panel to be repaired, and the construction method comprises the following steps: S101. Surface treatment of the airport runway panels to be repaired; S102, treating the leveling adhesive layer (2), laying the leveling adhesive layer (2) on the airport runway panel to be repaired; S103, hoisting the prefabricated prefabricated road panels (3) piece by piece to a designated position above the airport road panel to be repaired; S104, making the prefabricated road panel (3) and the leveling adhesive layer (2) fully and densely bonded by vibration; S105, adjusting the elevation and slope of the prefabricated road panel (3) by means of an adjusting member; S106, performing grouting through the reserved hole (34), the grouting being completed before the leveling adhesive layer (2) is cured, and the grouting liquid and the uncured grout of the leveling adhesive layer (2) are cured and formed synchronously; S107, processing the joints between adjacent prefabricated road panels (3).

18. The construction method of the prefabricated road panel installation structure according to claim 17, Features: In step S101, the surface layer of the airport runway panel to be repaired is firstly deep milled, and special treatment is performed on the existing defects, and then the surface is cleaned and dried.

19. The construction method of the prefabricated road panel installation structure according to claim 17, Features: In the step S102, the treatment thickness of the leveling adhesive layer (2) is 5-50 mm, the material solidification time is ≤60 minutes, and the compressive strength of the leveling adhesive layer (2) after casting is ≥25 MPa, and the flexural tensile strength is ≥5 MPa.

20. The construction method of the prefabricated road panel installation structure according to claim 17, Features: In the step S104, the leveling adhesive layer (2) fills the shear structure at the bottom of the prefabricated road panel (3), the reserved hole (34) and the joint position of the adjacent prefabricated road panel (3) due to the pressure and vibration of the prefabricated road panel (3). After the prefabricated road panel (3) and the leveling adhesive layer (2) are tightly bonded, the elevation of the installed prefabricated road panel (3) is re-measured to detect the misalignment and make corrections.

21. The construction method of the prefabricated road panel installation structure according to claim 17, Features: The adjusting member adopts a leveling bolt (42). After the leveling bolt (42) completes the leveling action, the leveling bolt (42) is screwed out of the leveling hole (33), and then the leveling hole (33) is subjected to a post-grouting and plugging treatment, or the leveling bolt (42) is retained in the leveling hole (33) and the leveling hole (33) is subjected to a post-grouting and plugging treatment.

22. The construction method of the prefabricated road panel installation structure according to claim 17, Features: In step S107, if the prefabricated road panel (3) adopts a block panel structure, the wet joints (5) between adjacent prefabricated road panels (3) are filled with the material of the leveling adhesive layer (2), and prefabricated sand that is the same as the anti-slip layer (32) on the surface of the prefabricated road panel (3) is sprinkled on the surface of the filling layer of the wet joints (5), and the surface is ground.

23. The construction method of the prefabricated road panel installation structure according to claim 17, Features: In step S107, if the prefabricated road panel (3) adopts a whole plate structure, the prefabricated road panel (3) is completely overlapped with the airport road panel to be repaired and bonded and cured, then the elastic rubber sheet around the prefabricated road panel (3) is removed, the seams (6) between adjacent prefabricated road panels (3) are cleaned, and the seams (6) are sealed with a caulking material.

24. The construction method of the prefabricated road panel installation structure according to claim 23, Features: The caulking material is polyurethane, silicone or polysulfide sealant.

25. A construction method for a prefabricated road panel installation structure, Features The construction method is applied to the prefabricated road panel installation structure described in any one of claims 1 to 16, wherein the base road surface is a steel bridge deck, and the construction method comprises the following steps: S201. Survey the quality of steel bridge decks. Before construction, check and clean the oil, water, welding slag and welding nodules on the bridge decks, and check the flatness of the bridge decks; S202, Shot blasting and rust removal of steel bridge deck; S203, treating the leveling adhesive layer (2), adding a self-repairing material capable of repairing cracks into the leveling adhesive layer (2); S204, hoisting the prefabricated prefabricated road panels (3) piece by piece to a designated position above the steel bridge deck by means of hoisting equipment; S205, by vibrating, the prefabricated road panel (3) is brought into full contact with the leveling adhesive layer (2), and the elevation of the installed prefabricated road panel (3) is re-measured to detect the misalignment and make corrections. Due to the pressure and vibration of the prefabricated road panel (3), the leveling adhesive layer (2) fills the shear structure at the bottom of the prefabricated road panel (3), the reserved hole (34) and the joint position of the adjacent prefabricated road panel (3); S206, adjusting the elevation and slope of the prefabricated road panel (3) by means of an adjusting member; S207, using the same material as the leveling adhesive layer (2) to perform grouting through the reserved hole (34), the grouting is completed before the leveling adhesive layer (2) is cured, and the grouting liquid and the uncured grout of the leveling adhesive layer (2) are synchronously cured and formed; S208, treating the joints between adjacent prefabricated road panels (3), using the same material as the leveling adhesive layer (2) to fill the joints to form a joint filling layer (8).

26. The construction method of the prefabricated road panel installation structure according to claim 25, Features: The deformation performance of the leveling adhesive layer (2) and the joint filling layer (8) is greater than that of the prefabricated road panel (3), so that the leveling adhesive layer (2), the joint filling layer (8) and the prefabricated road panel (3) form a rigid-flexible grouping structure.

27. The construction method of the prefabricated road panel installation structure according to claim 25, Features: In step S203, the self-healing material is Class III original fly ash or a graphene / polymer composite material, the treatment thickness of the leveling adhesive layer (2) is 5-50 mm, the material solidification time is ≤60 minutes, and the compressive strength of the leveling adhesive layer (2) after casting is ≥25 MPa, and the flexural tensile strength is ≥5 MPa.

Citation Information

Patent Citations

  • Fabricated road construction method

    CN107542017A

  • Rapid repair construction method of airport cement concrete road surface

    CN110644337A

  • Assembly type pavement structure and construction method

    CN112626962A

  • Bridge deck structure and expressway maintenance construction process

    CN114411551A

  • Fabricated pavement for airport and construction method thereof

    CN114922021A

Cited By

  • Display module and display equipment

    CN119600891A