Tower area ultra-long straddle type sling construction method based on steel wire rope traction anti-skid device

By using wire rope to pull anti-slip devices in the tower area construction, combined with power roller set and anti-slip device, the problems of low construction efficiency and high slip risk of ultra-long riding straddle slings in the tower area are solved, and efficient and safe slings are achieved Install.

CN118997013APending Publication Date: 2024-11-22CCCC SECOND HARBOR ENGINEERING CO LTD +1
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411380331.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-30
Publication Date
2024-11-22

AI Technical Summary

Technical Problem

The prior art has low construction efficiency and high slip risk in the construction of ultra-long straddle slings in the tower area, making it difficult to meet the demand for rapid construction.

Method used

The traction anti-slip device based on the wire rope is adopted, including the traction body and the anti-slip device. Through the combination of the power roller set and the anti-slip device, the traction and anti-slip of the sling are realized, the construction process is simplified, and the risk of slip is reduced.

Benefits of technology

It improves construction efficiency, reduces slip risk, reduces the use time of hand-pulled hoists and lifting equipment, simplifies construction processes, and reduces the economic cost of the project.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118997013A_ABST
    Figure CN118997013A_ABST
Patent Text Reader

Abstract

The invention discloses a tower area ultra-long straddle type sling construction method based on a steel wire rope traction anti-skid device. A hole is formed in a catwalk surface layer, a power roller set is arranged, a tower crane or a tower top winch is used for hoisting a cable head to penetrate through the catwalk surface layer, a traction body is installed at the position of a cable clamp, and a large arm or the tower top winch is transversely moved through the tower crane; one end of the sling is dragged to cross the main cable and the sling clamp and put into the sling penetrating area of the traction body, the anti-skid device is installed, then the ultra-long sling is conveyed through the power roller set and gradually conveyed in place, installation is completed, the overall construction procedure is simple, the construction difficulty is small, the slippage risk of the ultra-long sling is greatly reduced, and the construction efficiency is improved. The process of reversing the chain block back and forth and the occupied time of hoisting equipment are reduced, the traction main body is mounted by utilizing the structural form of the cable clamp, the disassembly is simple, the reversing is convenient, and the comprehensive economic cost of a project is greatly reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of sling construction, and more specifically, to a tower area super-long straddle-type sling construction method based on a steel wire rope traction anti-slip device. Background Art

[0002] As the main force transmission component of the suspension bridge, the cable structure is divided into straddle type and pin type to adapt to different bridge structures. For the straddle type, the steel wire rope is passed around the cable clamp and the lower end is connected to the steel box girder for force transmission. Therefore, the total length of the steel wire rope is twice the length of the cable. The short cable in the span is mostly transported and installed by the zenithal trolley on the catwalk gantry cable. The closer the cable is to the tower area, the longer it is. Therefore, the installation is also very difficult and the construction efficiency is extremely low. The existing construction methods generally include the following: For the installation of cables with navigation conditions, holes are usually opened in the catwalk surface layer and pulley blocks are set. Then, the cable tower is hoisted by lifting equipment, and the cable passes through the reserved holes and then passes over the cable clamp and the main cable. Without sending the hook, the cable is gradually lifted by a hand winch, and a rope clamp and a hand winch are installed on the other side to fix it before the hook can be sent. The construction efficiency is slow and the risk of cable slippage is high. It can no longer meet the needs of fast construction of super-long straddle cables in the tower area. Summary of the invention

[0003] An object of the present invention is to solve at least the above problems and to provide at least the advantages which will be described hereinafter.

[0004] Another object of the present invention is to provide a method for constructing an extra-long straddle-type sling in a tower area based on a wire rope traction anti-slip device, so as to solve the technical problem of the difficulty in traction construction of an extra-long straddle-type sling in a tower area in the prior art.

[0005] In order to achieve these purposes and other advantages according to the present invention, a tower area super-long straddle type sling construction method based on a wire rope traction anti-slip device is provided, comprising the following steps: S1. After the main cable and the cable clamp are installed, the cable clamp is provided with a screw hole and a saddle groove for installing the sling. A wire rope traction anti-skid device is installed on the cable clamp. The wire rope traction anti-skid device includes a traction body and an anti-skid device. The traction body includes a pair of relatively arranged main body parts, a gap with a spacing greater than the outer diameter of the sling is left between the pair of main body parts, and a mounting hole is arranged at the lower end. The mounting hole and the screw hole are inserted into a screw for fixed connection. A pair of main body parts are rotatably connected with a power roller group at the lower end of the gap. The power roller group is surrounded at the lower end of the gap for limiting to form a cable threading area for guiding the cable threading; S2. Drill a hole in the catwalk surface layer and set a pulley block, place the cable drum on the platform under the tower or the transport ship, use a tower crane or a tower top winch to pass through the catwalk surface layer and connect it to the cable head, and pull the cable head to the height of the corresponding cable clamp; S3, move the tower crane boom or the traction end of the tower top winch horizontally, move the sling head upward over the corresponding cable clamp and the traction body, and then move the sling down to the power roller group in the cable passing area; S4. An anti-skid device is coaxially arranged at the position corresponding to the cable-threading area. The anti-skid device is installed on the traction side of the sling of the main part and is sleeved on the outside of the sling at the corresponding position; S5, start the traction work, and transport the sling along the cable-threading area from the traction side to the other side through the power roller group. The anti-skid device does not work when the transmission direction is forward. When the reverse cable slip phenomenon occurs, the anti-skid device temporarily fixes the position of the sling; S6. When the lengths of the slings on both sides of the cable clamp are the same, use the tower crane to lift the sling to the center position as a whole, move it into the saddle groove, install the extra-long sling, and finally connect the ear plate at the end of the sling to the main beam to complete the system conversion.

[0006] Preferably, the anti-skid device is formed by detachably splicing two identical halves of a conical sleeve, a trapezoidal cavity is formed inside the anti-skid device, the inner diameters of the two axial ends of the anti-skid device are the same and larger than the outer diameter of the sling, the larger diameter surface of the conical sleeve is connected to the traction side of the sling of the main body, a wedge block is coaxially arranged in the trapezoidal cavity, the wedge block is an annular elastic structure, the inner diameter of the wedge block is slightly larger than the outer diameter of the sling, and the outer diameter of the smaller end of the wedge block is smaller than the minimum diameter of the trapezoidal cavity; In step S5, when the transmission direction is forward, there is a gap between the wedge block and the sling, and the wedge block does not hinder the forward movement of the sling. When the slipping phenomenon occurs, the wedge block slides in the direction of the smaller diameter of the trapezoidal cavity, and the position of the sling is fixed by the friction force generated by the extrusion.

[0007] Preferably, the power roller group includes a vertical power roller and a pair of transverse power rollers, the rotation direction of the vertical power roller is parallel to the radial cross-section of the main cable, the pair of transverse power rollers are relatively installed on a pair of the main body parts, and the space above the vertical power roller and between the pair of transverse power rollers forms the cable threading area. When the sling is transmitted in step S5, the vertical power roller supports and guides the movement of the sling upward, and the transverse power roller maintains the same linear speed as the vertical power roller to guide the movement of the sling.

[0008] Preferably, the middle parts of the outer ends of the vertical power roller and the transverse power roller are recessed inward to form arc-shaped limiting grooves respectively, and the diameter of the limiting grooves is slightly larger than the diameter of the sling, and the sling is limited and guided by multiple limiting grooves in the rope threading area.

[0009] Preferably, a traction motor is provided on the traction body, and the traction motor is used to drive the vertical power roller or the vertical power roller and the horizontal power roller to rotate toward the side of the sling to be towed. In step S5, the traction motor is started to tow and transport the sling in the limiting groove under the action of friction force.

[0010] Preferably, the traction body is provided with a scaffold at one end of the traction body located at a lower height in the extension direction of the main cable, the scaffold extends outwardly along the main cable direction at one end away from the main body section beyond the cable clamp and a pair of arc rings are symmetrically hinged on both sides of the extension end along the circumference of the main cable, the lower ends of the arc rings extend radially outward to form connecting ears, the connecting ears of the pair of arc rings are connected by bolts, the inner sides of the pair of arc rings are covered with a rubber layer, the inner side of the rubber layer is arranged with the same size as the outer diameter of the main cable, the scaffold is rotatably connected to the corresponding main body section, and the mounting hole is provided on the main body section away from the scaffold; When installing the traction body in step S1, the main body section on one side is overlapped with the frame, and the main body section on the other side is fixed to the end of the cable clamp by screwing the screw into the installation hole and the screw hole to leave at least one saddle groove. The arc ring on the frame is rotated to embrace the corresponding position of the main cable, and then bolts are screwed into a pair of connecting ears to fix the traction body to temporarily fix one end of the cable clamp. In step S6, the sling is lifted in the direction of the higher main cable height and moved into the saddle groove.

[0011] Preferably, the scaffolding and the corresponding traction body are connected in a horizontal radial rotation along the main cable. In step S6, after lifting the sling, the screw is unscrewed to release the fixed state of the traction body connected to the cable clamp, and the entire traction body is rotated toward the scaffolding to vacate the remaining saddle groove, and the sling is moved into the saddle groove. Then, the traction body and the cable clamp are temporarily fixed again by the screw for pulling the next sling through.

[0012] Preferably, the upper ends of a pair of the main body sections are arranged to be inclined upward relative to one side of the gap to form a guiding transition slope, and the minimum spacing between the guiding transition slopes on both sides is larger than the size of the lifting end of the tower crane, so as to guide the traction end of the tower crane boom or the tower top winch when lifting or moving the sling into the saddle groove.

[0013] The present invention includes at least the following beneficial effects: the tower area extra-long straddling sling construction method based on the wire rope traction anti-skid device of the present invention, opens a hole in the catwalk surface layer and sets a power roller group, uses a tower crane or a tower top winch to hoist the rope head through the catwalk surface layer, installs the traction body at the rope clamp position, uses the tower crane to move the boom or the tower top winch horizontally, pulls one end of the sling over the main cable and the rope clamp, and puts it into the rope threading area of ​​the traction body, installs the anti-skid device, and then transmits the extra-long sling through the power roller group and gradually transmits it to the position to complete the installation. The overall construction process is simple and the construction difficulty is small, which greatly reduces the slip risk of the extra-long sling, reduces the process of turning the hand winch back and forth and the time occupied by the lifting and hoisting equipment, and the traction body is installed using the structural form of the rope clamp itself, which is simple to disassemble and convenient to turn over, greatly reducing the comprehensive economic cost of the project.

[0014] Other advantages, objectives and features of the present invention will be embodied in part through the following description, and in part will be understood by those skilled in the art through study and practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] Figure 1 It is a front structural diagram of the steel wire rope traction anti-skid device of the present invention; Figure 2 It is a side structural diagram of the steel wire rope traction anti-skid device of the present invention; Figure 3 This is a schematic diagram of the structure of the present invention corresponding to step S2 when pulling the sling; Figure 4 It is a front view structural diagram of a steel wire rope traction anti-skid device according to an embodiment of the present invention when a frame is provided; Figure 5 It is a structural schematic diagram of the anti-skid device of the present invention in the state of transporting the sling; Figure 6 It is a structural schematic diagram of the anti-skid device of the present invention in the anti-skid state of the sling; Figure markings in the specification: 1. main cable, 2. cable clamp, 3. power roller group, 4. horizontal power roller, 5. vertical power roller, 6. sling, 7. screw, 8. saddle groove, 9. traction body, 10. anti-skid device, 11. gap, 12. conical sleeve, 13. trapezoidal platform cavity, 14. limiting groove, 15. frame, 16. arc ring, 17. connecting ear, 18. rotating shaft, 19. guide transition slope, 20. wedge block. DETAILED DESCRIPTION

[0016] The present invention is further described in detail below in conjunction with the accompanying drawings so that those skilled in the art can implement the invention with reference to the description.

[0017] It should be noted that the experimental methods described in the following embodiments are conventional methods unless otherwise specified, and the reagents and materials are commercially available unless otherwise specified; in the description of the present invention, the terms "lateral", "longitudinal", "upper", "lower", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.

[0018] like Figure 1-6 As shown, the present invention provides a tower area super-long straddle type sling construction method based on a wire rope traction anti-skid device, comprising the following steps: After the installation of S1, main cable 1 and cable clamp 2 is completed, the cable clamp 2 is provided with a screw hole and a saddle groove 8 for installing the sling 6, and a wire rope traction anti-skid device is installed on the cable clamp 2. The wire rope traction anti-skid device includes a traction body 9 and an anti-skid device 10. The traction body 9 includes a pair of relatively arranged main body parts, and a gap 11 with a spacing greater than the outer diameter of the sling 6 is reserved between the pair of main body parts, and a mounting hole is provided at the lower end. A screw 7 is inserted between the mounting hole and the screw hole for fixed connection. A pair of main body parts are rotatably connected with a power roller group 3 at the lower end of the gap 11. The power roller group 3 is surrounded by the lower end of the gap 11 for limiting to form a rope threading area for guiding the rope 6 to thread.

[0019] For the convenience of explanation, Figure 3 From left to right is used as the traction movement direction of the sling 6. First, a traction body 9 is installed on the cable clamp 2 using a row of screw holes and screws 7 on the top of the cable clamp 2 as a guiding structure for the cable 6 to bypass the cable clamp 2 upward. The rollers of the power roller group 3 can rotate freely relative to the traction body 9 and rotate synchronously with the movement of the sling 6. At the same time, the traction body 9 and the power roller group 3 form a lateral limit and a bottom support limit for the sling 6 during the movement. It is only necessary to put the position of the sling 6 near the cable head end into the cable threading area to basically ensure the safety and guidance of the traction construction of the sling 6 straddling the cable clamp 2, thereby improving the traction speed. The two main body parts can be detachably connected as a whole, or they can be fixed separately by screws 7.

[0020] S2. Drill a hole in the catwalk surface layer and set a pulley block, place the cable drum of the sling 6 on the platform under the tower or at the position of the transport ship, use a tower crane or a tower top winch to pass through the catwalk surface layer and connect it to the cable head of the sling 6, pull the cable head of the sling 6 to the height of the corresponding cable clamp 2, and complete the upward vertical movement of the sling 6.

[0021] S3, move the tower crane boom or the traction end of the tower top winch horizontally, move the cable head of the sling 6 upward over the corresponding cable clamp 2 and the traction body 9, and then move the sling 6 down to the power roller group 3 in the cable threading area. At this time, the turning and reversing movement of the sling 6 is completed, and the sling 6 is mainly supported in the vertical direction.

[0022] S4. An anti-skid device 10 is coaxially arranged at the position corresponding to the cable-threading area. The anti-skid device 10 is installed at the traction side of the sling 6 of the main body section and is sleeved on the outside of the sling 6 at the corresponding position.

[0023] S5, start the traction work, and transport the sling 6 from the traction side to the other side along the rope-threading area through the power roller group 3. The anti-skid device 10 does not work when the transmission direction is forward. When the reverse rope slip phenomenon occurs, the position of the sling 6 is temporarily fixed by the anti-skid device 10.

[0024] S6. Continue to transport the sling 6 through the power roller group 3. When the lengths of the slings 6 on both sides of the cable clamp 2 are the same, use the tower crane to lift the sling 6 to the middle position, that is, the highest position in the middle of the basic sling 6, and transfer it into the saddle groove 8 to complete the traction construction of the sling 6. Then install the extra-long sling 6, and finally connect the ear plate at the end of the sling 6 to the main beam to complete the system conversion.

[0025] The method for constructing an extra-long straddling sling 6 in a tower area based on a steel wire rope traction anti-skid device of the present invention comprises the following steps: opening a hole in the catwalk surface layer and setting a power roller group 3; utilizing a tower crane or a tower top hoist to hoist the rope head through the catwalk surface layer; installing a traction body 9 at the position of the rope clamp 2; utilizing a tower crane to move the boom or a tower top hoist horizontally to pull one end of the sling 6 over the main cable 1 and the rope clamp 2, and placing it in the rope threading area of ​​the traction body 9; installing an anti-skid device 10; and then transmitting the extra-long sling 6 through the power roller group 3 and gradually transmitting it to the position to complete the installation. The overall construction process is simple and the construction difficulty is low, which greatly reduces the slip risk of the extra-long sling 6, reduces the process of turning the hand winch back and forth and the time occupied by the lifting and hoisting equipment, and the traction body 9 is installed using the structural form of the rope clamp 2 itself, which is simple to disassemble and convenient to turn over, greatly reducing the comprehensive economic cost of the project.

[0026] In another technical solution, Figure 2 , 5 -6, the anti-skid device 10 is formed by detachably splicing two identical halves of a conical sleeve 12, a trapezoidal cavity 13 is formed inside the anti-skid device 10, the inner diameters of the two axial ends of the anti-skid device 10 are the same and larger than the outer diameter of the sling 6, the larger diameter surface of the conical sleeve 12 is connected to the traction side of the sling 6 of the main body, a wedge block 20 is coaxially arranged in the trapezoidal cavity 13, the wedge block 20 is an annular elastic structure, the inner diameter of the wedge block 20 is slightly larger than the outer diameter of the sling 6, and the outer diameter of the smaller end of the wedge block 20 is smaller than the minimum diameter of the trapezoidal cavity 13; In step S5, when the transmission direction is forward, there is a gap between the wedge block 20 and the sling 6, and the wedge block 20 does not hinder the forward movement of the sling 6. When the slipping phenomenon occurs, the wedge block 20 slides in the direction of the smaller diameter of the trapezoidal cavity 13, and the position of the sling 6 is fixed by the friction force generated by the extrusion.

[0027] The two semi-conical sleeve 12 structures are arranged to facilitate installation on the sling 6 after being placed in the rope threading area. The two semi-conical sleeves 12 extend radially outward at the ends to form mounting ear plates. Screw holes are provided between the opposite mounting ear plates and are connected with high-strength bolts. The inlet and outlet of the anti-skid device 10 at both ends of the trapezoidal platform cavity 13 are slightly larger than the outer diameter of the sling 6 and do not hinder the movement of the sling 6. A wedge block 20 is arranged in the trapezoidal platform cavity 13, which can flexibly play the role of squeezing limit or smooth passage according to the moving direction of the sling 6, thereby improving the safety of towing and moving the sling 6.

[0028] In another technical solution, Figure 1-2 As shown in Figure 4, the power roller group 3 includes a vertical power roller 5 and a pair of transverse power rollers 4. The rotation direction of the vertical power roller 5 is parallel to the radial section of the main cable 1. The pair of transverse power rollers 4 are relatively installed on a pair of the main body parts. The space above the vertical power roller 5 and between the pair of transverse power rollers 4 forms the cable threading area. When the sling 6 is transmitted in step S5, the vertical power roller 5 supports and guides the movement of the sling 6 upward, and the transverse power roller 4 maintains the same linear speed as the vertical power roller 5 to guide the movement of the sling 6.

[0029] The transverse power roller 4 and the vertical power roller 5 can rotate freely relative to the traction body 9 and rotate synchronously with the movement of the sling 6. At the same time, the traction body 9 and the transverse power roller 4 form a lateral limit for the sling 6 during the movement. It is only necessary to put the position of the sling 6 close to the end of the rope head into the rope threading area to basically ensure the safety and guidance of the traction construction of the sling 6 riding on the rope clamp 2, thereby improving the traction speed.

[0030] In another technical solution, Figure 1-2 As shown in Figures 4 and 5, the middle parts of the outer ends of the vertical power roller 5 and the horizontal power roller 4 are recessed inwards to form arc-shaped limiting grooves 14, respectively. The diameter of the limiting grooves 14 is slightly larger than the diameter of the sling 6. The sling 6 is limited and guided by a plurality of limiting grooves 14 in the cable-threading area. The setting of the limiting grooves 14 can also increase the contact area between the power roller and the sling 6, and improve the traction capacity under the action of friction.

[0031] In another technical solution, Figure 2As shown, a traction motor is provided on the traction body 9, and the traction motor is used to drive the vertical power roller 5 or the vertical power roller 5 and the horizontal power roller 4 to rotate toward the side of the sling 6 to be towed. In step S5, the traction motor is started to traction and transport the sling 6 in the limiting groove 14 under the action of friction. The drive device such as the traction motor is provided, so that the power roller group 3 can automatically transport the sling 6, and realize the efficient and automated traction construction of the sling 6.

[0032] In another technical solution, Figure 4 As shown, the traction body 9 is located at a lower end at a height in the extension direction of the main cable 1 and is provided with a bracket 15 outwardly along the direction of the main cable 1. The end of the bracket 15 away from the main body section extends beyond the cable clamp 2 and a pair of arc rings 16 are symmetrically hinged on both sides of the extension end along the circumference of the main cable 1. The lower ends of the arc rings 16 extend radially outward to form connecting ears 17. The connecting ears 17 of the pair of arc rings 16 are connected by bolts. The inner sides of the pair of arc rings 16 are covered with a rubber layer. The inner side of the rubber layer is circumferentially arranged with the same size as the outer diameter of the main cable 1. The bracket 15 is rotatably connected to the corresponding main body section, and the mounting hole is provided on the main body section away from the bracket 15. When installing the traction body 9 in step S1, the main body section on one side is overlapped with the frame 15, and the main body section on the other side is fixed to the end of the cable clamp 2 by screwing the screw 7 into the installation hole and the screw hole to leave at least one saddle groove 8. The arc ring 16 on the frame 15 is rotated to embrace the corresponding position of the main cable 1, and then bolts are screwed into a pair of connecting ears 17 to fix the traction body 9 temporarily to one end of the cable clamp 2. In step S6, the sling 6 is lifted in the direction of the higher height of the main cable 1 and moved into the saddle groove 8.

[0033] exist Figure 3 A traction body 9 is arranged on the left side of the cable clamp 2, and a frame 15 is supported on the main cable 1 through a pair of arc rings 16. A rubber layer is arranged on the arc ring 16 to avoid scratching the main cable 1. One end of the traction body 9 is held at the upper limit of the main cable 1 through the arc ring 16, and the other end is fixed to the cable clamp 2 through a screw 7. The number of installation holes between the traction body 9 and the cable clamp 2 and the number of screw holes occupied can be reduced, thereby improving the installation efficiency. At the same time, the obstruction of the saddle groove 8 by the traction body 9 can be reduced, and there is no need to frequently disassemble the traction body 9 to place the sling 6 in the remaining saddle groove 8.

[0034] In another technical solution, Figure 4As shown, the frame 15 and the corresponding traction body 9 are connected to each other in a horizontal radial rotation along the main cable 1. In step S6, after lifting the sling 6, the screw 7 is unscrewed to release the fixed state of the traction body 9 connected to the cable clamp 2, and the entire traction body 9 is rotated toward the frame 15 to vacate the remaining saddle groove 8, and the sling 6 is moved into the saddle groove 8. Then, the traction body 9 and the cable clamp 2 are temporarily fixed again by the screw 7 for pulling the next sling 6 to pass through.

[0035] When the space on both sides of the saddle groove 8 on the cable clamp 2 is limited, by setting a frame 15 and a traction body 9 rotatably connected to the frame 15, a rotating shaft 18 can be set together. When the main body portion blocks part of the saddle groove 8, the screw 7 can be released, the traction body 9 can be rotated upward to expose the saddle groove 8, and then the sling 6 can be placed in the remaining saddle groove 8. When it needs to be used again, the traction body 9 can be rotated again and fixed with the locking clamp through the screw 7, thereby improving the flexibility of the traction body 9 structure when used.

[0036] In another technical solution, Figure 4 As shown, the upper ends of a pair of the main body parts are arranged to be inclined upwards relatively close to one side of the gap 11 to form a guiding transition slope 19. The minimum spacing of the guiding transition slopes 19 on both sides is greater than the size of the lifting end of the tower crane, so as to guide the traction end of the tower crane boom or the tower top winch when the sling 6 is lifted or moved into the saddle groove 8. When the traction end moves, it can also slide along the guiding transition slope 19 to support the bottom and reduce shaking during the movement.

[0037] Although the embodiments of the present invention have been disclosed as above, they are not limited to the applications listed in the specification and the implementation modes, and they can be fully applied to various fields suitable for the present invention. For those familiar with the art, additional modifications can be easily implemented. Therefore, without departing from the general concept defined by the claims and the scope of equivalents, the present invention is not limited to the specific details and the illustrations shown and described herein.

Claims

1. The tower area super-long straddle-type sling construction method based on the wire rope traction anti-slip device, It is characterized in that The steps include: S1. After the main cable and the cable clamp are installed, the cable clamp is provided with a screw hole and a saddle groove for installing the sling. A wire rope traction anti-skid device is installed on the cable clamp. The wire rope traction anti-skid device includes a traction body and an anti-skid device. The traction body includes a pair of relatively arranged main body parts, a gap with a spacing greater than the outer diameter of the sling is left between the pair of main body parts, and a mounting hole is arranged at the lower end. The mounting hole and the screw hole are inserted into a screw for fixed connection. A pair of main body parts are rotatably connected with a power roller group at the lower end of the gap. The power roller group is surrounded at the lower end of the gap for limiting to form a cable threading area for guiding the cable threading; S2. Drill a hole in the catwalk surface layer and set a pulley block, place the cable drum on the platform under the tower or the transport ship, use a tower crane or a tower top winch to pass through the catwalk surface layer and connect it to the cable head, and pull the cable head to the height of the corresponding cable clamp; S3, move the tower crane boom or the traction end of the tower top winch horizontally, move the sling head upward over the corresponding cable clamp and the traction body, and then move the sling down to the power roller group in the cable passing area; S4. An anti-skid device is coaxially arranged at the position corresponding to the cable-threading area. The anti-skid device is installed on the traction side of the sling of the main part and is sleeved on the outside of the sling at the corresponding position; S5, start the traction work, and transport the sling along the cable-threading area from the traction side to the other side through the power roller group. The anti-skid device does not work when the transmission direction is forward. When the reverse cable slip phenomenon occurs, the anti-skid device temporarily fixes the position of the sling; S6. When the lengths of the slings on both sides of the cable clamp are the same, use the tower crane to lift the sling to the center position as a whole, move it into the saddle groove, install the extra-long sling, and finally connect the ear plate at the end of the sling to the main beam to complete the system conversion.

2. The tower area super-long straddle-type sling construction method based on the wire rope traction anti-slip device according to claim 1, It is characterized in that The anti-skid device is formed by detachably splicing two identical halves of a conical sleeve, and a trapezoidal cavity is formed inside the anti-skid device. The inner diameters of the two axial ends of the anti-skid device are the same and larger than the outer diameter of the sling. The larger diameter surface of the conical sleeve is connected to the traction side of the sling of the main body. A wedge block is coaxially arranged in the trapezoidal cavity. The wedge block is an annular elastic structure. The inner diameter of the wedge block is slightly larger than the outer diameter of the sling, and the outer diameter of the smaller end of the wedge block is smaller than the minimum diameter of the trapezoidal cavity. In step S5, when the transmission direction is forward, there is a gap between the wedge block and the sling, and the wedge block does not hinder the forward movement of the sling. When the slipping phenomenon occurs, the wedge block slides in the direction of the smaller diameter of the trapezoidal cavity, and the position of the sling is fixed by the friction force generated by the extrusion.

3. The tower area super-long straddle-type sling construction method based on the wire rope traction anti-skid device according to claim 1, It is characterized in that The power roller group includes a vertical power roller and a pair of transverse power rollers. The rotation direction of the vertical power roller is parallel to the radial cross-section of the main cable. The pair of transverse power rollers are relatively installed on a pair of the main body parts. The space above the vertical power roller and between the pair of transverse power rollers forms the cable threading area. When the sling is transmitted in step S5, the vertical power roller supports and guides the movement of the sling upward, and the transverse power roller maintains the same linear speed as the vertical power roller to guide the movement of the sling.

4. The tower area super-long straddle-type sling construction method based on the wire rope traction anti-skid device as claimed in claim 3, It is characterized in that The middle parts of the outer ends of the vertical power roller and the transverse power roller are recessed inwards to form arc-shaped limiting grooves respectively. The diameter of the limiting grooves is slightly larger than the diameter of the sling. The sling is limited and guided by multiple limiting grooves in the cable threading area.

5. The tower area super-long straddle-type sling construction method based on the steel wire rope traction anti-skid device according to claim 4, It is characterized in that The traction body is provided with a traction motor, which is used to drive the vertical power roller or the vertical power roller and the horizontal power roller to rotate toward the side of the sling to be towed. In step S5, the traction motor is started to tow and transport the sling in the limiting groove under the action of friction.

6. The tower area super-long straddle-type sling construction method based on the wire rope traction anti-skid device according to claim 4, It is characterized in that The traction body is located at a lower end at a height in the extension direction of the main cable and is provided with a scaffold outwardly along the main cable direction. One end of the scaffold away from the main body section extends beyond the cable clamp and a pair of arc rings are symmetrically hinged on both sides of the extension end along the circumference of the main cable. The lower ends of the arc rings extend radially outward to form connecting ears. The connecting ears of the pair of arc rings are connected by bolts. The inner sides of the pair of arc rings are covered with a rubber layer. The inner side of the rubber layer is circumferentially arranged with the same size as the outer diameter of the main cable. The scaffold is rotatably connected to the corresponding main body section, and the mounting hole is provided on the main body section away from the scaffold. When installing the traction body in step S1, the main body section on one side is overlapped with the frame, and the main body section on the other side is fixed to the end of the cable clamp by screwing the screw into the installation hole and the screw hole to leave at least one saddle groove. The arc ring on the frame is rotated to embrace the corresponding position of the main cable, and then bolts are screwed into a pair of connecting ears to fix the traction body to temporarily fix one end of the cable clamp. In step S6, the sling is lifted in the direction of the higher main cable height and moved into the saddle groove.

7. The tower area super-long straddle-type sling construction method based on the wire rope traction anti-skid device according to claim 6, It is characterized in that The scaffolding is connected to the corresponding traction body along the horizontal radial direction of the main cable. In step S6, after lifting the sling, the screw is unscrewed to release the fixed state of the traction body connected to the cable clamp, and the entire traction body is rotated toward the scaffolding to vacate the remaining saddle groove, and the sling is moved into the saddle groove. Then, the traction body and the cable clamp are temporarily fixed again by the screw for pulling the next sling through.

8. The tower area super-long straddle-type sling construction method based on the wire rope traction anti-skid device according to claim 6, It is characterized in that The upper ends of a pair of the main body sections are arranged to be inclined upward relative to one side of the gap to form a guiding transition slope, and the minimum spacing of the guiding transition slopes on both sides is larger than the size of the lifting end of the tower crane, so as to guide the traction end of the tower crane boom or the tower top winch when lifting or moving the sling into the saddle groove.