Offshore wind turbine foundation scouring depth monitoring device and installation method

By installing operation and maintenance platforms and monitoring components on the offshore fan, using water pressure sensors and depth sounding probes for real-time erosion depth monitoring, and combining three-dimensional imaging software, the cost and real-time erosion depth and morphology monitoring of the offshore fan foundation is solved. The problem has achieved accurate dynamic monitoring and data transmission.

CN118997239AActive Publication Date: 2024-11-22CHINA STATE CONSTR HARBOR CONSTR

Patent Information

Application Number
CN202411372206.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-29
Publication Date
2024-11-22
Estimated Expiration
2044-09-29

AI Technical Summary

Technical Problem

The existing basic erosion depth monitoring method of offshore fans has problems such as high cost, difficulty in real-time dynamic monitoring, complex installation process and inaccurate data, and cannot effectively evaluate the load capacity loss and three-dimensional pit morphology changes caused by erosion.

Method used

A basic erosion depth monitoring device for offshore fan including an operation and maintenance platform and monitoring components was designed. The erosion depth was monitored in real time by combining a water pressure sensor and a depth sounding probe, and morphological imaging was used to achieve dynamic monitoring of the entire process. and data transmission.

Benefits of technology

It realizes accurate monitoring of the foundation erosion depth and three-dimensional pit form of offshore fan, reduces monitoring costs, simplifies the installation process, improves the real-time and accuracy of monitoring, and supports the maintenance and recycling of monitoring devices.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118997239A_ABST
    Figure CN118997239A_ABST
Patent Text Reader

Abstract

The invention relates to an offshore wind turbine foundation scouring depth monitoring device which comprises an operation and maintenance platform and a monitoring assembly. The operation and maintenance platform and the monitoring assembly are both connected to the side wall of the fan foundation, the operation and maintenance platform is located above the monitoring assembly, the lower end of the fan foundation is inserted into the lower portion of a mud line, the monitoring assembly is located below the sea level, and the operation and maintenance platform is located above the sea level; the operation and maintenance platform is connected with the monitoring assembly through a lifting rope. The operation and maintenance platform is an annular hollowed-out net support, and the annular hollowed-out net support is fixedly connected to the side wall of the draught fan foundation. The monitoring assembly comprises an inflatable bag, an inner ring, an outer ring, a plurality of supports and a monitor; the device has the characteristics of simplicity, convenience, accuracy in monitoring, real-time dynamic monitoring in the whole process and recyclability, and the mounting method matched with the device improves the efficiency of monitoring the scouring depth and the three-dimensional shape of the scouring pit.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to an offshore wind turbine foundation scour depth monitoring device and an installation method. Background Art

[0002] Today, as we realize the modernization drive, although conventional energy still accounts for a large proportion of my country's energy structure, the proportion of new energy is increasing year by year with a rapid momentum. As a green, efficient and reusable new energy, offshore wind power is widely used in near and far seas.

[0003] The types of offshore wind turbine foundations are divided into fixed foundations and floating foundations. Both types of foundations directly or indirectly utilize marine soil to exert the bearing capacity of the wind turbine foundation. The existence of the wind turbine foundation will change the initial flow field of the neighborhood around the foundation. Under the action of waves and tides, the soil around the wind turbine foundation will be scoured and form scour pits. The existence of scour pits will affect the stability of the wind turbine foundation. With the increase of scour depth, the bearing capacity of the wind turbine foundation will be significantly reduced, which will affect the safety of the upper wind turbine. The existing monitoring of the scour depth of wind turbine foundations is mainly carried out by topographic exploration ships to image the three-dimensional scour pit morphology and monitor the scour depth. However, the depth and morphology of the scour pit will change dynamically with the change of the ocean flow field environment. This installation method will not only incur expensive monitoring costs, but also cannot perform long-term dynamic monitoring. Therefore, the use of low-cost, long-term, and high-precision wind turbine foundation scour depth monitoring methods to more accurately evaluate the bearing capacity loss and increased deformation caused by scour is an urgent problem to be solved in the safety status assessment of wind turbines.

[0004] At present, non-contact scouring installation methods are usually used to image the three-dimensional scouring pit morphology and monitor the scouring depth of offshore wind turbine foundations. Although the non-contact scouring installation method can accurately monitor the scouring depth and three-dimensional scouring pit morphology, it cannot monitor the entire service stage of the foundation and transmit data back in time; and its monitoring process mainly relies on renting a topographic survey ship and using the monitoring equipment on the ship to image the scouring depth and scouring pit morphology, which not only cannot achieve real-time dynamic monitoring, but also has high monitoring costs.

[0005] For the imaging of the three-dimensional scour pit morphology and monitoring of the scour depth of offshore wind turbine foundations, a contact scour installation method is also used. First, although contact monitoring can achieve periodic scour depth monitoring, it is achieved by installing components around the foundation. The installed components and the wind turbine foundation are welded together, which will increase the installation resistance of the foundation and make the installation process difficult; secondly, since it is fixed around the bottom of the foundation, it will be very difficult to repair when the monitoring component fails; thirdly, since it indirectly obtains the scour depth by monitoring the changes in soil pressure and water pressure, and does not obtain the scour depth by differentiating multiple sensors, it is easily affected by the complex marine environment, resulting in inaccurate measured data; finally, it uses limited sensors to monitor the scour depth of local feature points, and cannot monitor the morphology of three-dimensional scour pits.

[0006] Patent CN 106917420 A-A pile foundation scour monitoring device, the invention: proposes a pile foundation scour monitoring device, including an underwater measuring tube, a measuring component and a data acquisition instrument. By monitoring the real-time changes in the soil pressure on the pile side at different depths near the pile foundation and during the entire scour process, the influence of the scour depth on the stress of the pile foundation is obtained, and by analyzing the non-periodic changes in the soil pressure on the pile side under wave and current scour, the stress state between the pile and the soil and the safety margin of scour are obtained in real time. Although it is easy to operate, has high accuracy, good real-time performance, and effectively realizes remote monitoring of pile foundation scour monitoring, it can only obtain the scour depth during the service process of the foundation, and cannot obtain the three-dimensional dynamic scour pit morphology.

[0007] Patent 201810721314.9-Bridge pier scour monitoring platform, this invention: discloses a bridge pier scour monitoring platform, including a sleeve, a pulley, an adjusting hammer, an ultrasonic sensor, an ascending limit card and a descending limit card. The above components are all located inside the sleeve, and the sleeve is fixedly installed by a steel wire rope installed around the bridge pier. One end of the pulley is connected to the adjusting hammer, and the other end is connected to the ultrasonic sensor. The adjusting hammer rises accordingly with the rise of the tide level, and the ultrasonic sensor descends. When the adjusting hammer reaches the ascending limit card, the sensor is completely submerged in the water and begins to measure; conversely, when the tide level drops, the ultrasonic sensor rises and leaves the water surface. The complete set of devices of the present invention can be installed above the water surface, avoiding the need for underwater installation in traditional methods, and reducing the difficulty of sensor installation engineering; at the same time, the sensor is only submerged in the water at high tide, which reduces the immersion time, slows down the growth rate of organisms on the sensor surface, improves the accuracy of measurement data, and extends the maintenance time of the instrument. However, it can only measure the local scour depth in the scour pit through the sensor. The locally monitored scour depth cannot reflect the overall scour depth around the foundation, and cannot monitor the three-dimensional dynamic scour pit morphology.

[0008] Patent CN 113551829 A-scour monitoring device and offshore wind turbine foundation structure scour installation method, the invention: through the fixed shell set up, multiple groups of monitoring components can be installed in the seabed together with the offshore wind turbine pile foundation and contact the seabed. It is a contact scour monitoring device, which is not easily affected by the environment, the monitoring data is more accurate, and the monitoring stability is good, and measurement errors will not occur under strong scour. However, it is fixed around the foundation, which will increase the installation resistance of the foundation, making the installation process difficult, and damage will occur during the driving process.

[0009] Patent 202210597562.3-A lifting foundation scour monitoring device and method, the invention: discloses a lifting foundation scour monitoring device, including: a lifting screw installed on the side wall of the pier, a sliding seat is threadedly connected to the lifting screw, a sealing cover is installed on the sliding seat, a monitoring component and a lighting component are installed in the sealing cover, a transmission box is installed on the side wall of the pier, and the bottom of the transmission box is connected to the water wheel through the water wheel shaft. The transmission box is used to convert the rotation of the water wheel caused by the water flow into the lifting movement of the sealing cover. By comparing the original image with the image after scouring, and combining the number of rotations to analyze the foundation scour amount. It determines the scour amount according to the water flow velocity. There is currently no authoritative specification to refer to measure the feasibility of this method; secondly, the scour amount obtained is not accurate. Assuming that the number of rotations of the water wheel driven by the water flow in the forward direction and the scour amount 1 and the number of rotations of the water wheel driven by the water flow in the reverse direction and the scour amount 2 are not necessarily a simple superposition effect.

[0010] Patent CN 113373994 A-A bridge foundation scour monitoring component, the invention: discloses a bridge foundation scour monitoring component, including: an acquisition module, a transmission module and an analysis module; the acquisition module and the analysis module are both connected to the transmission module; the acquisition module is used to: transmit ultrasonic waves to the riverbed; receive echo ultrasonic waves reflected by the riverbed; convert the echo ultrasonic waves into voltage signals, and transmit the voltage signals to the transmission module; the transmission module is used to send the voltage signals to the analysis module; the analysis module is used to calculate the scour depth of the riverbed according to the voltage signal. The present invention uses ultrasonic waves to detect the scour depth of the riverbed, the propagation of ultrasonic waves is not affected by external factors, and the accuracy of measuring the scour depth is higher. However, there is a big difference between the scour monitoring of offshore wind turbine foundation structures and the scour monitoring of bridges or riverbeds. The scour of inland rivers is relatively gentle, while the marine environment is more severe than that of inland rivers. The scour situation at sea is much more serious, and the reliability of the device needs to be verified. Secondly, if the scour monitoring device is directly installed on the seabed near the offshore wind turbine, there will be a monitoring blind spot, and the overall three-dimensional morphology of the scour pit cannot be imaged. Finally, due to the remote location of offshore wind turbines, the offshore environment is difficult to predict, and the changes in its scour situation may occur in a short time, or may not occur for a long time after installation. This requires that the scour monitoring device for the offshore wind turbine foundation structure be maintenance-free.

[0011] Therefore, in order to solve the above problems, an offshore wind turbine foundation scour depth monitoring device and installation method are proposed. Summary of the invention

[0012] The purpose of the present invention is to overcome the existing defects and provide an offshore wind turbine foundation scour depth monitoring device and installation method, which has the characteristics of simplicity and convenience, accurate monitoring, real-time dynamic monitoring of the whole process and recyclability. The matching installation method improves the efficiency of scour depth and scour pit three-dimensional morphology monitoring.

[0013] The technical solution to achieve the above-mentioned purpose is: a device for monitoring the scour depth of an offshore wind turbine foundation, comprising an operation and maintenance platform and a monitoring component; the operation and maintenance platform and the monitoring component are both connected to the side wall of the wind turbine foundation, the operation and maintenance platform is located above the monitoring component, the lower end of the wind turbine foundation is inserted below the mud line, the monitoring component is located below the sea level, and the operation and maintenance platform is located above the sea level; the operation and maintenance platform is connected to the monitoring component via a suspension rope.

[0014] Preferably, the operation and maintenance platform is an annular hollow mesh bracket, and the annular hollow mesh bracket is fixedly connected to the side wall of the wind turbine foundation.

[0015] Preferably, the monitoring assembly includes an inflatable bag, an inner ring, an outer ring, multiple supports and a monitor; the inflatable bag is connected to the inner wall of the inner ring, multiple supports are equidistantly connected to the outer wall of the inner ring, the outer ends of the multiple supports are connected to the inner wall of the outer ring, and the lower end of the outer ring is slidably connected to the monitor; the inflatable bag is connected to the outer wall of the fan foundation.

[0016] Preferably, each of the upper end surfaces of the supports is connected to a first water pressure sensor and a pull ring, the lower end of the suspension rope is connected to the pull ring, and the upper end is connected to the operation and maintenance platform.

[0017] Preferably, the monitor includes two depth sounding probes, which are respectively connected to the two ends of a rotating shaft, the rotating shaft is rotatably connected to the lower end of a vertical rod, the upper end of the vertical rod is connected to a groove slider, the lower end of the outer ring is provided with a groove slide, and the groove slider is slidably connected in the groove slide.

[0018] Preferably, a driving device is provided inside the outer ring for driving the groove slider to move in a circular motion along the groove slideway.

[0019] Preferably, a second water pressure sensor is provided at the mud line, and the second water pressure sensor is connected to the first water pressure sensor through an electrical signal.

[0020] A method for installing an offshore wind turbine foundation scour depth monitoring device comprises the following steps:

[0021] Step 1: Preparation before construction of the wind turbine foundation: Before installing the wind turbine foundation, take advantage of the fact that the inner diameter of the monitoring component is larger than the outer diameter of the wind turbine foundation, put the monitoring component on the wind turbine foundation, and adjust the monitoring component to a suitable position. Inflate the airbag to fix the monitoring component on the outer wall of the wind turbine foundation. The position of the monitoring component remains unchanged at this stage. Then hoist the wind turbine foundation to the guide hole of the positioning platform, and fix the monitoring component on the operation and maintenance platform with a hoisting rope.

[0022] Step 2: Monitoring the scouring depth during the construction of the wind turbine foundation: During the installation of the wind turbine foundation, the airbag is deflated to reduce its volume, making it loosely connected or disconnected from the wind turbine foundation, to prevent the monitoring component and the wind turbine foundation from sinking below the mud line together; at the same time, the suspension rope is loosened on the operation and maintenance platform to gradually reduce the depth of the monitoring component until the depth reaches the limit, and the operation is stopped. At this time, the installation of the wind turbine foundation is completed; at this stage, there is scouring in the area around the wind turbine foundation, and the scouring depth gradually increases with the installation depth, that is, the installation time, and the scouring depth varies from zero to one pile diameter;

[0023] When the wind turbine foundation is not installed in place: at this stage, the monitoring component is gradually lowered by loosening the suspension rope, that is, the distance from the monitoring component to the mud line gradually changes with the installation process of the wind turbine foundation; in order to facilitate the explanation of the monitoring principle, the scouring depth at a certain moment is used as an example to illustrate here; at this moment, the measurement value of the first water pressure sensor on the support of the monitoring component and the measurement value of the second water pressure sensor at the mud line are known, then the distance L between the first water pressure sensor and the second water pressure sensor can be obtained by calculating the difference between the two. Here, due to error considerations, the measurement value of the first water pressure sensor on the support is determined when the monitoring component is horizontal. If the measurement values ​​of the first water pressure sensors on the four supports are different, it means that the monitoring component is tilted, and the monitoring component is kept horizontal by adjusting the length of the suspension rope; since the distance between the first water pressure sensor on the support and the depth probe is fixed at L0, the measuring The distance from the deep probe to the mud line can be calculated as L1=L-L0 through the distance difference; the sounding probe monitors the scouring depth of the measured point by rotating a certain angle α1. The rotation angle α1 is known, and the distance from the sounding probe to the measured point is s1. The sounding probe has been measured, then the scouring depth of the measured point Δh1=s1cosα1-L1, wherein if the rotation angle α1 is less than 90°, the rotation angle α1 is used when calculating the scouring depth; if the rotation angle α1 is greater than 90°, the rotation angle α1-90° is used when calculating the scouring depth; due to the relationship between the scouring depth and time, the scouring depth of each point at a certain section measured by the sounding probe through the rotation angle cannot reflect the scouring depth of each point at the section at a certain moment measured in the actual process. Therefore, in order to make the measurement result more accurate, a sounding probe with a fixed position is set up to vertically monitor the relationship between the scouring depth of the point below it and time, and the relationship function S between the scouring depth and time is obtained. L =S L (t); Assuming that the time for the depth probe to rotate from the previous monitoring point to the next monitoring point is t, the relationship function S between the measured scour depth and time is L =S L (t), find the scour depth S1 corresponding to the time of the previous monitoring point and the scour depth S2 corresponding to the time of the next monitoring point, then β1=S2 / S1 is the rate of change of the scour depth with time, and the accurate scour depth can be calculated through the rate of change of the scour depth with time, that is, Δh′1=(s1 cosα1-L1) / β1; when the scour depths of all points at the section are fully monitored, the groove slideway at the bottom of the outer ring drives the monitor connected to it to realize circumferential movement, and the scour depth of each point within the circumferential range of the wind turbine foundation is monitored, and then the scour depth monitoring data is transmitted to the data receiving platform, and the scour pit morphology is imaged in three dimensions using three-dimensional imaging software;

[0024] When the installation of the wind turbine foundation is completed: at this stage, the lifting rope is completely relaxed, and the depth of the monitoring component's descent reaches the limit, that is, the distance from the monitoring component to the mud line is fixed, and the airbag is inflated to expand its volume. At this time, a close contact is formed between the airbag and the outer wall of the wind turbine foundation, that is, the monitoring component is fixed on the outer wall of the wind turbine foundation; in order to facilitate the explanation of the monitoring principle, the scouring depth at a certain moment is used as an example; at this moment, the measurement value of the first water pressure sensor on the support of the monitoring component and the measurement value of the first water pressure sensor at the mud line are known, and the distance L′ between the first water pressure sensor and the second water pressure sensor can be obtained by calculating the difference between the two. Here, due to the error Consider that the measurement value of the first water pressure sensor on the support is determined when the monitoring component is horizontal. If the measurement values ​​of the first water pressure sensors on the four supports are different, it means that the monitoring component is tilted. The monitoring component is kept horizontal by adjusting the length of the suspension rope. Since the distance between the first water pressure sensor on the support and the depth probe is fixed at L0, the distance from the depth probe to the mud line can be calculated by the distance difference as L2=L′-L0. The depth probe monitors the scouring depth of the measured point by rotating a certain angle α2. The rotation angle α2 is known, and the distance from the depth probe to the measured point is s2. The depth probe has measured it, so the scouring depth of the measured point Δh2=s2 cosα2-L2, where if the rotation angle α2 is less than 90°, the rotation angle α2 is used when calculating the scour depth; if the rotation angle α2 is greater than 90°, the rotation angle α2-90° is used when calculating the scour depth; due to the relationship between the scour depth and time, the scour depth of each point on a certain section measured by the depth sounding probe through the rotation angle cannot reflect the scour depth of each point on the section measured at a certain moment in the actual process. Therefore, in order to make the measurement result more accurate, a depth sounding probe with a fixed position is set up to vertically monitor the relationship between the scour depth of the point below it and time, and the relationship function S between the scour depth and time is obtained. L =S L (t); Assuming that the time for the depth probe to rotate from the previous monitoring point to the next monitoring point is t, the relationship function S between the measured scour depth and time is L =S L(t), find the scour depth S3 corresponding to the time of the previous monitoring point and the scour depth S4 corresponding to the time of the next monitoring point, then β2=S4 / S3 is the rate of change of the scour depth with time, and the accurate scour depth can be calculated through the rate of change of the scour depth with time, that is, Δh′2=(s2 cosα2-L2) / β2; when the scour depths of all points at the section are fully monitored, the groove slideway at the bottom of the outer ring drives the monitor connected to it to realize circumferential movement, and the scour depth of each point within the circumferential range of the wind turbine foundation is monitored, and then the scour depth monitoring data is transmitted to the data receiving platform, and the scour pit morphology is imaged in three dimensions using three-dimensional imaging software;

[0025] Step 3: Dynamic scouring depth monitoring during the service phase of the wind turbine foundation: The service process of the wind turbine foundation begins after installation. As the service time of the wind turbine foundation increases, the scouring around the foundation continues, and the scouring radius of the soil around the foundation and the shape of the scouring pit also change. The scouring depth changes from one pile diameter to two pile diameters.

[0026] At this stage, the suspension rope is completely relaxed, and the depth of the monitoring component descending reaches the limit, that is, the distance from the monitoring component to the mud line is fixed. In order to facilitate the explanation of the monitoring principle, the scouring depth at a certain moment is used as an example for explanation; at this moment, the measurement value of the first water pressure sensor on the support of the monitoring component and the measurement value of the second water pressure sensor at the mud line are known, and the distance L′ between the first water pressure sensor and the second water pressure sensor can be obtained by calculating the difference between the two. Here, due to error considerations, the measurement value of the first water pressure sensor on the support is determined when the monitoring component is horizontal. If the measured values ​​of the first water pressure sensors on the four supports are different, it means that the monitoring assembly is tilted. The monitoring assembly can be kept horizontal by adjusting the length of the suspension rope. Since the distance between the first water pressure sensor on the support and the depth probe is fixed at L0, the distance from the depth probe to the mud line can be calculated by the distance difference as L2=L′-L0. The depth probe monitors the scouring depth of the measured point by rotating a certain angle α3. The rotation angle α3 is known, and the distance from the depth probe to the measured point is s3. The depth probe has measured it, so the scouring depth of the measured point Δh3=s3. cosα3-L2, where if the rotation angle α3 is less than 90°, the rotation angle α3 is used when calculating the scour depth; if the rotation angle α3 is greater than 90°, the rotation angle α3-90° is used when calculating the scour depth; due to the relationship between the scour depth and time, the scour depth of each point on a certain section measured by the depth sounding probe through the rotation angle cannot reflect the scour depth of each point on the section measured at a certain moment in the actual process. Therefore, in order to make the measurement result more accurate, a depth sounding probe with a fixed position is set up to vertically monitor the relationship between the scour depth of the point below it and time, and the relationship function S between the scour depth and time is obtained.L =S L (t); Assuming that the time for the depth probe to rotate from the previous monitoring point to the next monitoring point is t, the relationship function S between the measured scour depth and time is L =S L (t), find the scour depth S5 corresponding to the time of the previous monitoring point and the scour depth S6 corresponding to the time of the next monitoring point, then β3=S6 / S5 is the rate of change of the scour depth with time, and the accurate scour depth can be calculated through the rate of change of the scour depth with time, that is, Δh′3=(s3 cosα3-L2) / β3; when the scour depths of all points at the section are fully monitored, the groove slideway at the bottom of the outer ring drives the monitor connected to it to realize circumferential movement, and the scour depth of each point within the circumferential range of the wind turbine foundation is monitored, and then the scour depth monitoring data is transmitted to the data receiving platform, and the scour pit morphology is imaged in three dimensions using three-dimensional imaging software;

[0027] Step 4: Monitoring of stable scour depth during the service period of the wind turbine foundation: At this stage, the scour depth reaches a balanced state, and the scour depth is twice the pile diameter. Ignoring the change of scour depth with time, the scour pit shape tends to be stable. It is only necessary to measure the scour depth of each point at any cross section and obtain the stabilized scour pit shape. In order to facilitate the explanation of the monitoring principle, the scour depth at a point at a certain moment is used as an example. At this moment, the measurement value of the first water pressure sensor on the support of the monitoring component and the measurement value of the second water pressure sensor at the mud line are known. The distance L′ between the first water pressure sensor and the second water pressure sensor can be obtained by calculating the difference between the two. Here, due to error considerations, The measurement value of the water pressure sensor on the support is determined when the monitoring component is horizontal. If the measurement values ​​of the first water pressure sensors on the four supports are different, it means that the monitoring component is tilted. The monitoring component is kept horizontal by adjusting the length of the suspension rope. Since the distance between the first water pressure sensor on the support and the depth probe is fixed at L0, the distance from the depth probe to the mud line can be calculated by the distance difference as L2=L′-L0. The depth probe monitors the scouring depth of the measured point by rotating a certain angle α4. The rotation angle α4 is known, and the distance from the depth probe to the measured point is s4. The depth probe has measured it, so the scouring depth of the measured point Δh4=s4 cosα4-L2, where if the rotation angle α4 is less than 90°, the rotation angle α4 is used when calculating the scour depth; if the rotation angle α4 is greater than 90°, the rotation angle α4-90° is used when calculating the scour depth; after the scour depths of all points at the section are fully monitored, the groove slideway at the bottom of the outer ring drives the monitor connected thereto to realize circumferential movement, and the scour depths of all points within the circumferential range of the wind turbine foundation are monitored, and then the scour depth monitoring data is transmitted to the data receiving platform, and the scour pit morphology is imaged in three dimensions using three-dimensional imaging software;

[0028] Step 5: Determine the scour range of the area around the wind turbine foundation: As the scour depth changes, the range of the scour pit also gradually changes. How to determine the boundary of the scour pit is an extremely important step;

[0029] When the rotation angle of the depth sounding probe is less than 90°, the problem to be solved in the area between the depth sounding probe and the fan foundation is how to determine the intersection point of the fan foundation and any cross section of the scour pit, that is, the maximum scour depth point of the fan foundation; in the process of changing the rotation angle of the depth sounding probe from small to large, the measured distance is first the distance from the depth sounding probe to each point in the axial direction of the fan foundation, and this measured distance gradually increases with the increase of the rotation angle; secondly, the measured distance is the distance from the depth sounding probe to the point in the area belonging to the scour pit, and this measured distance gradually decreases with the increase of the rotation angle; therefore, at a certain cross section, when the rotation angle of the depth sounding probe is less than 90°, the point with the largest measured distance is the maximum scour depth point;

[0030] When the rotation angle of the depth sounding probe is greater than 90°, the area corresponding to the scour pit section and the mud line needs to be solved to determine the intersection of the mud line and any section of the scour pit, that is, the maximum scour radius of the fan foundation; when the rotation angle of the depth sounding probe changes from small to large, the distance to each point of the scour pit section in the area gradually increases with the increase of the rotation angle. To determine the maximum scour radius, it is necessary to analyze it in combination with geometric relationships; since the vertical distance from the depth sounding probe to the mud line is known and set to Z1, the distance between the depth sounding probe and the point to be measured is known and set to Z2, and the rotation angle of the depth sounding probe is known and set to β, if It is considered that the vertical distance from the monitoring point to the wind turbine foundation is the maximum impact radius of the wind turbine foundation;

[0031] Measurement of the accumulation height on the backflow side of the fan foundation when the depth probe moves circumferentially: During the scouring of the fan foundation, soil accumulation will occur on the backflow side. The problem to be solved is how to measure the height of the accumulated soil and determine the maximum boundary of the scouring pit; the shape of the soil accumulation can be seen as an axisymmetric structure according to literature search. When the depth probe moves to the accumulation area to measure the scouring depth, its distance to each point in the accumulation range is uncertain. To determine the height of the accumulated soil and the maximum boundary of the scouring pit, it is necessary to analyze it in combination with geometric relationships; combined with the maximum scouring depth radius of the fan foundation scouring, the vertical distance from this point to the depth probe is known and set to Z3, and the vertical distance from this point to the fan foundation is known and set to Z4. Continue to increase the rotation angle of the depth probe to start measuring the height of the accumulated soil; since the rotation angle of the depth probe is known and set to γ, the distance from the depth probe to each point in the accumulation range is known and set to Z5, then the vertical distance between each point in the accumulation range and the depth probe can be calculated and set to Z6=Z5 cosγ, where the corresponding monitoring point when the vertical distance Z6 between the measured point and the sounding probe is the smallest is the highest point of the accumulated soil, and the accumulation height is Z3-Z6 at this time; the horizontal distance from the maximum accumulation height point to the maximum scouring radius point is known through geometric relationship Z7=Z5 sinγ, so the maximum boundary of the scouring pit is Z4+2Z5 sinγ;

[0032] Step 6: Repair and recovery of the scour depth monitoring device: When the wind turbine foundation is decommissioned or the monitoring component fails, the monitoring component is lifted to the sea level by lifting the rope tied under the operation and maintenance platform to achieve the repair and reuse of the entire monitoring device.

[0033] The beneficial effects of the present invention are:

[0034] 1) The scour depth monitoring device and installation method for offshore wind turbine foundation can maintain the change of its own relative position as the installation depth of the wind turbine foundation increases during the installation process by setting up the monitoring component, and measure the scour depth of a certain monitoring point around the wind turbine foundation during the installation process by combining the difference of the water pressure sensor with the monitoring angle of the depth sounding probe; at the same time, the relationship between the scour depth of the wind turbine foundation and time is considered, and the relationship function of the scour depth changing with time is obtained, and the monitored scour depth is corrected by using this function; in addition, by analyzing the characteristic points of the scour boundary, the determination method of the characteristic points is obtained by using the geometric relationship, so as to realize the scour depth monitoring of each point of the entire cross section; at the same time, the depth sounding probe can also make circumferential motion on the slideway through the slider to realize the scour depth monitoring of the 360° area around the wind turbine foundation; finally, the monitoring data is transmitted to the data receiving platform, and the three-dimensional scour pit morphology is imaged by the computer, thereby realizing the scour depth detection and three-dimensional scour pit morphology imaging of the entire installation and service process.

[0035] 2) The monitoring component determines the height from the monitoring component to the mudline by analyzing the difference between the two water pressure sensors set at the monitoring component and the mudline, and determines the height from the depth probe to the mudline by combining the installation position of the depth probe; by comparing the values ​​of the four groups of water pressure sensors, it is determined whether the monitoring component is in a horizontal state, and the position of the component is monitored in time by pulling the rope to reduce the height calculation error from the depth probe to the mudline. According to the rotation angle of the depth probe and the distance from the depth probe to the monitoring point, combined with the known height from the depth probe to the mudline, the scour depth at the monitoring point is solved using geometric relationships, and the influence of the rotation time of the depth probe on the scour depth measurement result is considered. The relationship function of the scour depth changing with time is used to correct the measurement result. In this process, since the rotation angle of the depth probe can be accurately measured, the distance error from the depth probe to the monitoring point is controlled by the error accuracy of the depth probe itself, and the height error from the depth probe to the mudline is small, the error of the entire monitoring process is small. Then, the circumferential movement of the depth sounding probe is realized through the annular slide, and the monitoring process is repeated to complete the monitoring of the scour depth at any point in the area around the foundation and use a computer to draw the three-dimensional scour pit shape of the fan foundation based on the monitored scour depth data. This process is the result of repeating the above monitoring process. Since the error of the above monitoring process is low, the overall error can also be controlled within a lower range, thereby obtaining more accurate monitoring data.

[0036] 3) As traditional monitoring devices are difficult to repair when they fail, the monitoring component can be raised and lowered by the ropes arranged under the operation and maintenance platform. Since the location of the operation and maintenance platform is fixed and always above sea level, when the monitoring component fails, the operation and maintenance personnel can retract the ropes through a simple lifting device, thereby driving the monitoring component to rise to the sea level for easy maintenance of the fault; after the maintenance is completed, the ropes can be loosened through a simple lifting device, allowing the monitoring component to descend to the predetermined monitoring position.

[0037] 4) In view of the high monitoring cost of traditional monitoring devices, this monitoring component not only shortens the maintenance time when a fault occurs, thus saving a lot of maintenance costs, but also can be lifted to sea level by a simple lifting device arranged on the operation and maintenance platform after the wind turbine foundation is retired, so that the entire monitoring device can be recovered and reused, greatly reducing the monitoring cost. BRIEF DESCRIPTION OF THE DRAWINGS

[0038] Figure 1 It is a front view of the offshore wind turbine foundation scour depth monitoring device of the present invention;

[0039] Figure 2 is a top view of the offshore wind turbine foundation scour depth monitoring device of the present invention;

[0040] Figure 3 is a top view of the monitoring assembly of the present invention;

[0041] Figure 4 is a front view of the monitoring assembly of the present invention;

[0042] Figure 5 is a detailed diagram of the monitor of the present invention;

[0043] Figure 6 is a front view of the scouring depth monitoring during the installation process of step 1 of the installation method of the present invention;

[0044] Figure 7 is a front view of detailed scouring depth monitoring during the installation process of step 1 of the installation method of the present invention;

[0045] Figure 8 It is a front view of the scour depth monitoring after the installation of step 2 of the installation method of the present invention is completed;

[0046] Fig. 9 It is a front view of detailed scour depth monitoring after the installation of step 2 of the installation method of the present invention is completed;

[0047] Fig.10 It is a front view of the scouring depth monitoring in the dynamic scouring stage in step 3 of the installation method of the present invention;

[0048] Fig.11It is a front view of detailed scouring depth monitoring in the dynamic scouring stage of step 3 of the installation method of the present invention;

[0049] Fig.12 It is a front view of the scouring depth monitoring in the stable scouring stage in step 4 of the installation method of the present invention;

[0050] Fig.13 It is a front view of the flushing boundary determination process in step five of the installation method of the present invention.

[0051] In the figure: 1. Wind turbine foundation; 2. Operation and maintenance platform; 21. Annular hollow mesh bracket; 3. Monitoring component; 3-1. Inflatable bag; 3-2. Inner ring; 3-3. Outer ring; 3-31. Grooved slide; 3-4. Support; 3-41. First water pressure sensor; 3-42. Pull ring; 3-5. Monitor; 3-51. Grooved slider; 3-52. Vertical rod; 3-53. Rotating shaft; 3-54. Depth probe; 4. Sea level; 5. Mud line; 6. Lifting rope. DETAILED DESCRIPTION

[0052] The technical solution of the present invention will be described clearly and completely below in conjunction with the accompanying drawings. In the description of the present invention, it should be noted that the terms "center", "up", "down", "left", "right", "vertical", "horizontal", "inside", "outside" and the like indicate directions or positional relationships based on the directions or positional relationships shown in the accompanying drawings, which are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as a limitation on the present invention. In addition, the terms "first", "second", and "third" are used for descriptive purposes only and cannot be understood as indicating or implying relative importance.

[0053] The present invention will be further described below in conjunction with the accompanying drawings.

[0054] The presence of foundations in the marine environment will change the initial flow field structure of the neighborhood around the foundation. The obstruction of the foundation will cause streamline contraction, causing the upper water surface in front of the foundation to rise slightly, and the lower water flow to flow downward, thus forming a horseshoe-shaped vortex in front of the foundation and a wake vortex behind the foundation. Under the action of vortices and turbulence, the near-bottom velocity of the foundation increases, resulting in a decrease in the upper pressure at the seabed mud water surface and an unchanged lower pressure. A pressure difference is generated between the upper and lower sides of the seabed soil, inducing soil liquefaction, and then the seabed soil is lost under the action of water flow, causing scouring. [Hazards of foundation scouring] Scouring will occur around the foundation under the action of vortices and turbulence, forming scouring pits, and the disasters caused by scouring will intensify over time. Under the action of scouring, the buried depth of the foundation is reduced, which greatly weakens the bearing capacity of the foundation; at the same time, the eccentricity of the bearing capacity load increases, which seriously threatens the safe operation of offshore wind farms. [Existing foundation scouring depth monitoring methods]: Existing foundation scouring depth monitoring methods are divided into contact monitoring and non-contact monitoring. Contact monitoring is to install some components around the foundation, on which soil pressure sensors, water pressure sensors or electrode probes are installed; non-contact monitoring is to use external terrain exploration equipment (ultrasound, sonar, light sensors, etc.) to regularly monitor the scouring conditions around the foundation. [Problems with existing foundation scouring depth monitoring]: First, although contact monitoring can realize periodic scouring depth monitoring, since it is achieved through components installed around the foundation, the installation resistance of the foundation increases and the installation process is difficult; secondly, since it is fixed around the bottom of the foundation, it will be very difficult to repair when the monitoring component fails; thirdly, since it indirectly obtains the scouring depth by monitoring soil pressure changes, water pressure changes, etc., and does not obtain the scouring depth by differentiating multiple sensors, it is easily affected by the complex marine environment, resulting in inaccurate measured data; finally, it uses limited sensors to monitor the scouring depth of local feature points, and cannot monitor the morphology of three-dimensional scouring pits. Although non-contact monitoring can monitor the scour depth and three-dimensional scour pit morphology more accurately, it cannot monitor the entire service period of the foundation and transmit data back in a timely manner; and its monitoring process mainly relies on renting a topographic survey ship and using the monitoring equipment on the ship to image the scour depth and scour pit morphology. Not only can it not achieve real-time dynamic monitoring, but the monitoring cost is also expensive.

[0055] like Figure 1-5 As shown, an offshore wind turbine foundation scour depth monitoring device includes an operation and maintenance platform 2 and a monitoring component 3; the operation and maintenance platform 2 and the monitoring component 3 are both connected to the side wall of the wind turbine foundation 1, the operation and maintenance platform 2 is located above the monitoring component 3, the lower end of the wind turbine foundation 1 is inserted below the mud line 5, the monitoring component 3 is located below the sea level 4, and the operation and maintenance platform 2 is located above the sea level 4; the operation and maintenance platform 2 is connected to the monitoring component 3 through a suspension rope 6. The operation and maintenance platform 2 is an annular hollow mesh bracket 21, and the annular hollow mesh bracket 21 is fixedly connected to the side wall of the wind turbine foundation 1.

[0056] Specifically, the operation and maintenance platform 2 is generally a square steel structure, and its main function is to anchor the monitoring component 3 and provide a workstation for maintenance personnel during fault inspection and repair. At least four anchor points are reserved at the bottom of the operation and maintenance platform 2 for the suspension rope 6 to pass through. When the wind turbine foundation 1 is installed, the staff on the operation and maintenance platform 2 loosens the suspension rope to increase its water depth to achieve dynamic scouring depth monitoring during the installation process. The height of the operation and maintenance platform 2 is higher than the height of the sea level 4, thereby reducing the corrosion of the operation and maintenance platform 2 by seawater and increasing the convenience during maintenance.

[0057] Specifically, the monitoring assembly 3 includes an inflatable bag 3-1, an inner ring 3-2, an outer ring 3-3, multiple supports 3-4 and a monitor 3-5; the inflatable bag 3-1 is connected to the inner wall of the inner ring 3-2, multiple supports 3-4 are connected to the outer wall of the inner ring 3-2 at equal distances, the outer ends of the multiple supports 3-4 are connected to the inner wall of the outer ring 3-3, and the lower end of the outer ring 3-3 is slidably connected to the monitor 3-5; the inflatable bag 3-1 is connected to the outer wall of the fan foundation 1. The upper end surface of each support 3-4 is connected to a first water pressure sensor 3-41 and a pull ring 3-42, the lower end of the suspension rope 6 is connected to the pull ring 3-42, and the upper end is connected to the operation and maintenance platform 2. The monitor 3-5 includes two depth sounding probes 3-54, which are respectively connected to the two ends of the rotating shaft 3-53, the rotating shaft 3-53 is rotatably connected to the lower end of the vertical rod 3-52, the upper end of the vertical rod 3-52 is connected to the groove slider 3-51, the lower end of the outer ring 3-3 is provided with a groove slide 3-31, and the groove slider 3-51 is slidably connected in the groove slide 3-31. A driving device is provided inside the outer ring 3-3 to drive the groove slider 3-51 to move in a circle along the groove slide 3-31.

[0058] Specifically, a second water pressure sensor is provided at the mud line 5, and the second water pressure sensor is connected to the first water pressure sensor 3-41 through an electrical signal.

[0059] Specifically, the monitoring component 3 is a double-circular hollow structure, and its main function is to monitor the scour depth of the fan foundation 1 during the installation and service process and transmit the monitoring data back to the data receiving platform. At the same time, the data is processed using three-dimensional imaging software to generate the three-dimensional shape of the scour pit during the entire installation and service cycle.

[0060] Specifically, the inflatable bag 3-1 is a flexible material of an annular structure, which is hollow inside and can change its volume by filling and releasing air. The surface of the inflatable bag 3-1 has a certain degree of roughness, which can provide greater friction. The inflatable bag 3-1 is connected to the inner side of the inner ring 3-2, and the connection between the two is a fixed connection. By inflating the inflatable bag 3-1 to expand its volume, the monitoring component 3 is closely attached to the side wall of the fan foundation 1, thereby fixing the monitoring component 3.

[0061] Specifically, the inner ring 3-2 is a circular ring with a certain thickness and height, an inner area of ​​which is fixedly connected to the inflatable bag 3-1, and the outer side is connected to the outer ring 3-3 through the support 3-4.

[0062] Specifically, the outer ring 3-3 is a circular ring with a certain thickness and height, the inner side of which is connected to the inner ring 3-2 through the support 3-4, and the bottom end is provided with an outward slide 3-31. The outward slide 3-31 is connected to the monitor 3-5, and the monitor 3-5 installed on the groove slide 3-31 can realize circumferential movement through the transmission system inside it.

[0063] Specifically, the support 3-4 is a rectangular steel material with a certain thickness and width. It serves as a connecting component and plays a connecting role. The first water pressure sensor 3-41 and the pull ring 3-42 are provided on the upper part. The two ends are respectively connected to the outer side of the inner ring 3-2 and the inner side of the outer ring 3-3. The support 3-4, the inner ring 3-2 and the outer ring 3-3 are fixed by welding. There are at least four supports 3-4, which are evenly arranged in the circumferential direction at a certain angle.

[0064] Specifically, the first water pressure sensor 3-41 can measure the water pressure at the height of the monitoring component 3. By calculating the difference between it and the second water pressure sensor installed at the mud line 5, the distance between the monitoring component 3 and the mud line 5 can be determined. Then, the fixed distance between the first water pressure sensor 3-41 on the support 3-4 and the depth probe 3-54 can be subtracted to obtain the distance between the depth probe 3-54 and the mud line 5. At the same time, by comparing the water pressure values ​​measured by the first water pressure sensors 3-41 on different supports 3-4, it can be determined whether the monitoring component 3 is horizontal and its inclination angle. There are at least four pull rings 3-42, with a lifting rope 6 passing through the middle, which is connected to the operation and maintenance platform 2 through the lifting rope 6. The operation and maintenance personnel can drive the monitoring component 3 to rise and fall by lifting and loosening the lifting rope, thereby realizing dynamic monitoring of the scouring depth and fault repair.

[0065] Specifically, the monitor 3-5 is connected to the groove slideway 3-31 at the lower end of the outer ring 3-3 through the groove slider 3-51, and the groove slider 3-51 connected thereto is driven internally by the groove slideway 3-31, so as to realize the circumferential scouring depth monitoring of the fan foundation 1. The groove slider 3-51 is a block with an inverted T-shaped groove on the top, one end of which is connected to the groove slideway 3-31, and the other end is connected to the depth probe 3-54 through the vertical rod 3-52 and the rotating shaft 3-53 at the end of the vertical rod 3-52. The vertical rod 3-52 mainly plays a connecting role, with its upper end connected to the groove slider 3-51 and the lower end being the rotating shaft 3-53, which is connected to the depth probe 3-54 through the rotating shaft 3-53. There are at least two sounding probes 3-54, one with a fixed angle and position, vertically downward monitoring the relationship function of the scouring depth changing with time, and the other adjusting the angle and moving in a circumferential direction to monitor the scouring depth at any point in any cross section within a 360° range. The sounding probe 3-54 can only emit one ray at a time to measure the distance between the measured point and the sounding probe 3-54, and the hinge point at the lower end of the connecting rod 3-52 can realize the rotation within the 180-degree angle range of the plane in which it is located, thereby monitoring the scouring depth of any point in the plane in which it is located.

[0066] Specifically, at least one second water pressure sensor is provided at the far end of the mud line 5. By measuring the water pressure at the mud line 5, the difference between it and the first water pressure sensor on the support 3-4 is determined. By using the geometric relationship and combining the rotation angle of the depth probe 3-54, the scouring depth at any point in the scouring range is obtained.

[0067] like Figure 6-13 As shown, a method for installing an offshore wind turbine foundation scour depth monitoring device comprises the following steps:

[0068] Step 1, preparation before construction of the fan foundation 1: Before installing the fan foundation 1, take advantage of the fact that the inner diameter of the monitoring component 3 is larger than the outer diameter of the fan foundation 1, put the monitoring component 3 on the fan foundation 1, and adjust the monitoring component 3 to a suitable position, and inflate the inflatable bag 3-1 to fix the monitoring component 3 on the outer wall of the fan foundation 1. The position of the monitoring component 3 remains unchanged at this stage; then hoist the fan foundation 1 to the guide hole of the positioning platform, and fix the monitoring component 3 on the operation and maintenance platform 2 by a hoisting rope;

[0069] Step 2: Monitoring the scouring depth during the construction of the wind turbine foundation 1: During the installation of the wind turbine foundation 1, the airbag 3-1 is deflated to reduce its volume, so that it becomes loosely connected or disconnected from the wind turbine foundation 1, to prevent the monitoring component 3 and the wind turbine foundation 1 from sinking below the mud line 5 together; at the same time, the suspension rope 6 is loosened on the operation and maintenance platform 2 to gradually reduce the depth of the monitoring component 3 until the depth reaches the limit, and the operation is stopped. At this time, the installation of the wind turbine foundation 1 is completed; at this stage, there is scouring in the area around the wind turbine foundation 1, and the scouring depth gradually increases with the installation depth, that is, the installation time, and the scouring depth varies from zero to one pile diameter;

[0070] When the wind turbine foundation 1 is not installed in place: at this stage, the monitoring component 3 is gradually lowered by loosening the suspension rope 6, that is, the distance from the monitoring component 3 to the mud line 5 gradually changes with the installation process of the wind turbine foundation 1; in order to facilitate the explanation of the monitoring principle, the scouring depth at a certain moment is used as an example for explanation; at this moment, the measurement value of the first water pressure sensor 3-41 on the support 3-4 in the monitoring component 3 and the measurement value of the second water pressure sensor at the mud line 5 are known, and the distance L between the first water pressure sensor 3-41 and the second water pressure sensor can be obtained by calculating the difference between the two. Here, for error considerations, the measurement value of the first water pressure sensor 3-41 on the support 3-4 is determined when the monitoring component 3 is horizontal. It is concluded that if the measured values ​​of the first water pressure sensors 3-41 on the four supports 3-4 are different, it means that the monitoring component 3 is tilted, and the monitoring component 3 is kept in a horizontal state by adjusting the length of the suspension rope 6; since the distance between the first water pressure sensor 3-41 on the support 3-4 and the depth probe 3-54 is fixed at L0, the distance from the depth probe 3-54 to the mud line 5 can be calculated by the distance difference as L1=L-L0; the depth probe 3-54 monitors the scouring depth of the measured point by rotating a certain angle α1, and its rotation angle α1 is known, and the distance from the depth probe 3-54 to the measured point is s1. The depth probe 3-54 has been measured, so the scouring depth of the measured point Δh1=s1 cosα1-L1, where if the rotation angle α1 is less than 90°, the rotation angle α1 is used when calculating the scour depth; if the rotation angle α1 is greater than 90°, the rotation angle α1-90° is used when calculating the scour depth; due to the relationship between the scour depth and time, the scour depth of each point at a certain section measured by the depth sounding probe 3-54 through the rotation angle cannot reflect the scour depth of each point at the section at a certain moment measured in the actual process. Therefore, in order to make the measurement result more accurate, a depth sounding probe 3-54 with a fixed position is set to vertically monitor the relationship between the scour depth of the next point and time, and the relationship function S between the scour depth and time is obtained. L =S L(t); Assuming that the time for the depth probe 3-54 to rotate from the previous monitoring point to the next monitoring point is t, the relationship function S between the measured scour depth and time is L =S L (t), find the scour depth S1 corresponding to the time of the previous monitoring point and the scour depth S2 corresponding to the time of the next monitoring point, then β1=S2 / S1 is the rate of change of the scour depth with time, and the accurate scour depth Δh′1=(s1 cosα1-L1) / β1 can be calculated through the rate of change of the scour depth with time; when the scour depths of all points at the section are fully monitored, the groove slideway 3-31 at the lower part of the outer ring 3-3 drives the monitor 3-5 connected thereto to realize circumferential movement, and monitors the scour depths of all points within the circumferential range of the fan foundation 1, and then transmits the scour depth monitoring data to the data receiving platform, and uses the three-dimensional imaging software to perform three-dimensional imaging of the scour pit morphology;

[0071] When the installation of the wind turbine foundation is completed: at this stage, the suspension rope 6 is completely relaxed, and the depth of the monitoring component 3 descending reaches the limit, that is, the distance from the monitoring component 3 to the mud line 5 is fixed, and the air bag 3-1 is inflated to expand the volume of the air bag 3-1. At this time, the air bag 3-1 is in close contact with the outer wall of the wind turbine foundation 1, that is, the monitoring component 3 is fixed on the outer wall of the wind turbine foundation 1; in order to facilitate the explanation of the monitoring principle, the scouring depth at a certain moment is taken as an example; at this moment, the measurement value of the first water pressure sensor 3-41 on the support 3-4 in the monitoring component 3 and the measurement value of the first water pressure sensor 3-41 at the mud line 5 are known, and the distance L between the first water pressure sensor 3-41 and the second water pressure sensor can be obtained by calculating the difference between the two. Here, for error considerations, the support 3-4 The measurement value of the first water pressure sensor 3-41 on the support 3-4 is determined when the monitoring component 3 is horizontal. If the measurement values ​​of the first water pressure sensors 3-41 on the four supports 3-4 are different, it means that the monitoring component 3 is tilted. The monitoring component 3 is kept horizontal by adjusting the length of the suspension rope 6. Since the distance between the first water pressure sensor 3-41 on the support 3-4 and the depth probe 3-54 is fixed at L0, the distance from the depth probe 3-54 to the mud line 5 can be calculated by the distance difference as L2=L′-L0. The depth probe 3-54 monitors the scouring depth of the measured point by rotating a certain angle α2. The rotation angle α2 is known, and the distance from the depth probe 3-54 to the measured point is s2. The depth probe 3-54 has been measured, so the scouring depth of the measured point Δh2=s1 cosα2-L2, where if the rotation angle α2 is less than 90°, the rotation angle α2 is used when calculating the scour depth; if the rotation angle α2 is greater than 90°, the rotation angle α2-90° is used when calculating the scour depth; due to the relationship between the scour depth and time, the scour depth of each point at a certain section measured by the depth sounding probe 3-54 through the rotation angle cannot reflect the scour depth of each point at the section at a certain moment measured in the actual process. Therefore, in order to make the measurement result more accurate, a depth sounding probe 3-54 with a fixed position is set to vertically monitor the relationship between the scour depth of the next point and time, and the relationship function S between the scour depth and time is obtained. L =S L (t); Assuming that the time for the depth probe 3-54 to rotate from the previous monitoring point to the next monitoring point is t, the relationship function S between the measured scour depth and time is L =S L(t), find the scour depth S3 corresponding to the time of the previous monitoring point and the scour depth S4 corresponding to the time of the next monitoring point, then β2=S4 / S3 is the rate of change of the scour depth with time, and the accurate scour depth can be calculated through the rate of change of the scour depth with time, that is, Δh′2=(s2 cosα2-L2) / β2; when the scour depths of all points at the section are fully monitored, the groove slide 3-31 at the lower part of the outer ring 3-3 drives the monitor 3-5 connected thereto to realize circumferential movement, and monitors the scour depths of all points within the circumferential range of the fan foundation 1, and then transmits the scour depth monitoring data to the data receiving platform, and uses the three-dimensional imaging software to perform three-dimensional imaging of the scour pit morphology;

[0072] Step 3: Dynamic scouring depth monitoring of wind turbine foundation 1 during service: After the installation of wind turbine foundation 1 is completed, its service process begins. As the service time of wind turbine foundation 1 increases, the scouring around the foundation continues, the scouring radius of the soil around the foundation and the shape of the scouring pit also change, and the scouring depth changes from one pile diameter to two pile diameters;

[0073] At this stage, the suspension rope is completely relaxed, and the depth of the monitoring component 3 descending reaches the limit, that is, the distance from the monitoring component 3 to the mud line 5 is fixed. In order to facilitate the explanation of the monitoring principle, the scouring depth at a certain moment is taken as an example for explanation; at this moment, the measurement value of the first water pressure sensor 3-41 on the support 3-4 in the monitoring component 3 and the measurement value of the second water pressure sensor at the mud line 5 are known, and the distance L′ between the first water pressure sensor 3-41 and the second water pressure sensor can be obtained by calculating the difference between the two. Here, for error considerations, the measurement value of the first water pressure sensor 3-41 on the support 3-4 is determined when the monitoring component 3 is horizontal. If the four supports 3-4 are If the measured values ​​of the first water pressure sensors 3-41 on the support 3-4 are different, it means that the monitoring assembly 3 is tilted. The monitoring assembly 3 is kept in a horizontal state by adjusting the length of the suspension rope 6. Since the distance between the first water pressure sensor 3-41 on the support 3-4 and the depth probe 3-54 is fixed at L0, the distance from the depth probe 3-54 to the mud line 5 can be calculated by the distance difference as L2=L′-L0. The depth probe 3-54 monitors the scouring depth of the measured point by rotating a certain angle α3. The rotation angle α3 is known, and the distance from the depth probe 3-54 to the measured point is s3. The depth probe 3-54 has been measured, so the scouring depth of the measured point Δh3=s3. cosα3-L2, where if the rotation angle α3 is less than 90°, the rotation angle α3 is used when calculating the scour depth; if the rotation angle α3 is greater than 90°, the rotation angle α3-90° is used when calculating the scour depth; due to the relationship between the scour depth and time, the scour depth of each point at a certain section measured by the depth sounding probe 3-54 through the rotation angle cannot reflect the scour depth of each point at the section at a certain moment measured in the actual process. Therefore, in order to make the measurement result more accurate, a depth sounding probe 3-54 with a fixed position is set to vertically monitor the relationship between the scour depth of the next point and time, and the relationship function S between the scour depth and time is obtained. L =S L (t); Assuming that the time for the depth probe 3-54 to rotate from the previous monitoring point to the next monitoring point is t, the relationship function S between the measured scour depth and time is L =S L(t), find the scour depth S5 corresponding to the time of the previous monitoring point and the scour depth S6 corresponding to the time of the next monitoring point, then β3=S6 / S5 is the rate of change of the scour depth with time, and the accurate scour depth can be calculated through the rate of change of the scour depth with time, that is, Δh′3=(s3 cosα3-L2) / β3; when the scour depths of all points at the section are fully monitored, the groove slideway 3-31 at the lower part of the outer ring 3-3 drives the monitor 3-5 connected thereto to realize circumferential movement, and monitors the scour depths of all points within the circumferential range of the fan foundation 1, and then transmits the scour depth monitoring data to the data receiving platform, and uses the three-dimensional imaging software to perform three-dimensional imaging of the scour pit morphology;

[0074] Step 4, stable scour depth monitoring of wind turbine foundation 1 during service: At this stage, the scour depth reaches a balanced state, and the scour depth is twice the pile diameter. Ignoring the change of scour depth with time, the scour pit shape tends to be stable. It is only necessary to measure the scour depth of each point at any cross section and obtain the stabilized scour pit shape. In order to facilitate the explanation of the monitoring principle, the scour depth at a point at a certain moment is used as an example. At this moment, the measurement value of the first water pressure sensor 3-41 on the support 3-4 in the monitoring component 3 and the measurement value of the second water pressure sensor at the mud line 5 are known. The distance L′ between the first water pressure sensor 3-41 and the second water pressure sensor can be obtained by calculating the difference between the two. Here, for error considerations, the water pressure sensor 3-4 on the support 3-4 1 The determination of the measured value is obtained when the monitoring component 3 is horizontal. If the measured values ​​of the first water pressure sensors 3-41 on the four supports 3-4 are different, it means that the monitoring component 3 is tilted. The monitoring component 3 is kept horizontal by adjusting the length of the suspension rope 6. Since the distance between the first water pressure sensor 3-41 on the support 3-4 and the depth probe 3-54 is fixed at L0, the distance from the depth probe 3-54 to the mud line 5 can be calculated by the distance difference as L2=L′-L0. The depth probe 3-54 monitors the scouring depth of the measured point by rotating a certain angle α4. The rotation angle α4 is known, and the distance from the depth probe 3-54 to the measured point is s4. The depth probe 3-54 has been measured, so the scouring depth of the measured point Δh4=s4 cosα4-L2, wherein if the rotation angle α4 is less than 90°, the rotation angle α4 is used when calculating the scour depth, and if the rotation angle α4 is greater than 90°, the rotation angle α4-90° is used when calculating the scour depth; after all the scour depths at the cross section are monitored, the groove slideway 3-31 at the lower part of the outer ring 3-3 drives the monitor 3-5 connected thereto to realize circumferential movement, and the scour depths of each point within the circumferential range of the fan foundation 1 are monitored, and then the scour depth monitoring data is transmitted to the data receiving platform, and the scour pit morphology is imaged in three dimensions using three-dimensional imaging software;

[0075] Step 5: Determine the scour range of the area around the wind turbine foundation 1: As the scour depth changes, the range of the scour pit also gradually changes. How to determine the boundary of the scour pit is an extremely important step;

[0076] When the rotation angle of the depth sounding probe 3-54 is less than 90°, the problem to be solved in the area between the depth sounding probe 3-54 and the fan foundation 1 is how to determine the intersection of the fan foundation 1 and any cross section of the scour pit, that is, the maximum scour depth point of the fan foundation 1; in the process of changing the rotation angle of the depth sounding probe 3-54 from small to large, the measured distance is first the distance from the depth sounding probe 3-54 to each point in the axial direction of the fan foundation 1, and this measured distance gradually increases with the increase of the rotation angle; secondly, the measured distance is the distance from the depth sounding probe 3-54 to the point belonging to the scour pit in the area, and this measured distance gradually decreases with the increase of the rotation angle; therefore, at a certain cross section, when the rotation angle of the depth sounding probe 3-54 is less than 90°, the point with the largest measured distance is the maximum scour depth point;

[0077] When the rotation angle of the depth sounding probe 3-54 is greater than 90°, the area corresponding to the scour pit section and the mud line 5 needs to be solved to determine the intersection of the mud line 5 and any section of the scour pit, that is, the maximum scour radius of the fan foundation 1; when the rotation angle of the depth sounding probe 3-54 changes from small to large, the distance to each point of the scour pit section in the area gradually increases with the increase of the rotation angle. To determine the maximum scour radius, it is necessary to analyze it in combination with geometric relationships; since the vertical distance from the depth sounding probe 3-54 to the mud line 5 is known and set to Z1, the distance between the depth sounding probe 3-54 and the point to be measured is known and set to Z2, and the rotation angle of the depth sounding probe 3-54 is known and set to β, if It is considered that the vertical distance from the monitoring point to the wind turbine foundation 1 is the maximum impact radius of the wind turbine foundation;

[0078] Measurement of the accumulation height on the backflow side of the fan foundation 1 when the depth probe 3-54 moves circumferentially: During the scouring process of the fan foundation 1, soil accumulation will appear on the backflow side. The problem to be solved is how to measure the height of the accumulated soil and determine the maximum boundary of the scouring pit. The shape of the soil accumulation can be seen as an axisymmetric structure according to literature search. When the depth probe 3-54 moves to the accumulation area to measure the scouring depth, the distance to each point in the accumulation range is uncertain. To determine the height of the accumulated soil and the maximum boundary of the scouring pit, it is necessary to combine the geometric relationship to perform Analysis; Combined with the maximum scour radius of the fan foundation, the vertical distance from this point to the depth probe 3-54 is known and set to Z3, and the vertical distance from this point to the fan foundation 1 is known and set to Z4. Continue to increase the rotation angle of the depth probe 3-54 to start measuring the height of the accumulated soil; Since the rotation angle of the depth probe 3-54 is known and set to γ, the distance from the depth probe 3-54 to each point in the accumulation range is known and set to Z5, then the vertical distance between each point in the accumulation range and the depth probe 3-54 can be calculated and set to Z6=Z5 cosγ, where the corresponding monitoring point when the vertical distance Z6 between the measured point and the depth probe 3-54 is the smallest is the highest point of the accumulated soil, and the accumulation height is Z3-Z6 at this time; the horizontal distance from the maximum accumulation height point to the maximum scour radius point is known to be Z7=Z5 sinγ through geometric relationships, so the maximum boundary of the scour pit is Z4+2Z5 sinγ;

[0079] Step six, maintenance and recycling of the scour depth monitoring device: When the wind turbine foundation 1 is retired or the monitoring component 3 fails, the monitoring component 3 is lifted to the sea level by lifting the rope 6 tied under the operation and maintenance platform 2, so as to achieve maintenance and reuse of the entire monitoring device.

[0080] The installation method of the offshore wind turbine foundation scour depth monitoring device solves the problem that the scour depth and scour pit morphology during the installation and service of the wind turbine foundation cannot be dynamically monitored in real time and the scour data is inaccurate. It can accurately monitor the scour status of the wind turbine foundation during the installation and service, and evaluate the safety status of the wind turbine and remedy the possible insufficient foundation bearing capacity in combination with the scour data. The wind turbine foundation scour depth monitoring device of the present invention can not only monitor the scour pit morphology and scour depth around the wind turbine foundation in real time during the service stage, but also monitor the scour depth of the area around the foundation during the installation process, realizing the monitoring of the scour pit morphology and scour depth during the installation and service process; at the same time, at least two water pressure sensors are used to determine the distance between the monitoring device and the mud line, and the relationship function of the scour depth changing with time is obtained in combination with the installation position and rotation angle of the two depth sounding probes, and the scour depth of each point to be measured at a certain cross section is determined by geometric relationship calculation; finally, the monitoring device is recovered or repaired in the fault stage by lifting the pull rope under the operation and maintenance platform. It has the characteristics of simplicity and convenience, accurate monitoring, real-time dynamic monitoring of the whole process and recyclability. The matching construction method improves the efficiency of monitoring the scouring depth and three-dimensional shape of the scouring pit.

[0081] (Scooting depth monitoring and three-dimensional scour pit morphology imaging during the entire installation and service process) The monitoring component can maintain the change of its own relative position as the installation depth of the fan foundation increases during the installation process. The scour depth of a certain monitoring point around the fan foundation during the installation process can be measured by combining the difference of the water pressure sensor with the monitoring angle of the depth sounding probe. At the same time, the relationship between the scouring depth of the fan foundation and time is taken into account to obtain a relationship function of the scouring depth changing with time, and this function is used to correct the monitored scouring depth. In addition, by analyzing the characteristic points of the scouring boundary, the determination method of the characteristic points is obtained using geometric relationships, thereby realizing scour depth monitoring of each point in the entire cross-section. At the same time, the depth sounding probe can also make circumferential motion on the slideway through the slider to realize scour depth monitoring of the 360° area around the fan foundation. Finally, the monitoring data is transmitted to the data receiving platform, and the three-dimensional scour pit morphology is imaged by the computer, thereby realizing scour depth detection and three-dimensional scour pit morphology imaging during the entire installation and service process.

[0082] (The scour depth at each location is measured using geometric relationships, and the measurement data is accurate and reliable) The monitoring component determines the height from the monitoring component to the mud line by analyzing the difference between the two water pressure sensors set at the monitoring component and the mud line, and determines the height from the depth probe to the mud line by combining the installation position of the depth probe; by comparing the values ​​of the four groups of water pressure sensors, it is determined whether the monitoring component is in a horizontal state, and the position of the component is monitored in time by pulling the rope to reduce the height calculation error from the depth probe to the mud line. According to the rotation angle of the depth probe and the distance from the depth probe to the monitoring point, and combined with the known height from the depth probe to the mud line, the scour depth at the monitoring point is solved using geometric relationships, and the influence of the rotation time of the depth probe on the scour depth measurement result is considered. The relationship function of the scour depth changing with time is used to correct the measurement result. In this process, since the rotation angle of the depth probe can be accurately measured, the distance error from the depth probe to the monitoring point is controlled by the error accuracy of the depth probe itself, and the height error from the depth probe to the mud line is small, therefore, the error of the entire monitoring process is small. Then, the circumferential movement of the depth sounding probe is realized through the annular slide, and the monitoring process is repeated to complete the monitoring of the scour depth at any point in the area around the foundation and use a computer to draw the three-dimensional scour pit shape of the fan foundation based on the monitored scour depth data. This process is the result of repeating the above monitoring process. Since the error of the above monitoring process is low, the overall error can also be controlled within a lower range, thereby obtaining more accurate monitoring data.

[0083] (The height of the monitoring component can be adjusted, which is convenient for monitoring adjustment and fault repair) Since traditional monitoring devices are difficult to repair when they fail, this monitoring component can be raised and lowered through the ropes arranged under the operation and maintenance platform. Since the position of the operation and maintenance platform is fixed and always above sea level, when the monitoring component fails, the operation and maintenance personnel can retract the rope through a simple lifting device, thereby driving the monitoring component to rise to the sea level, which is convenient for fault inspection and repair; after the inspection is completed, the rope can be loosened through a simple lifting device, so that the monitoring component can be lowered to the predetermined monitoring position.

[0084] (The monitoring device is recyclable, saving costs) As the monitoring cost of traditional monitoring devices is too high, this monitoring component not only shortens the maintenance time when a fault occurs, saving a lot of maintenance costs, but also can be recycled and reused by lifting the monitoring component to sea level through a simple lifting device arranged on the operation and maintenance platform after the wind turbine foundation is retired, greatly reducing the monitoring cost.

[0085] Compared with the shortcomings of traditional wind turbine foundation scour depth monitoring, such as inaccurate monitoring, inability to image the three-dimensional scour pit morphology, high monitoring cost, and difficult maintenance in case of failure, the installation method of the scour depth monitoring device of the present invention can maintain the change of its own relative position as the installation depth of the wind turbine foundation increases during the installation process. The scour depth of a certain monitoring point around the wind turbine foundation during the installation process can be measured by combining the difference of the water pressure sensor with the monitoring angle of the depth sounding probe. At the same time, the relationship between the scour depth of the wind turbine foundation and time is taken into account to obtain the scour depth. A relationship function that changes with time is obtained, and this function is used to correct the monitored scour depth. In addition, by analyzing the characteristic points of the scour boundary, the method of determining the characteristic points is obtained using geometric relationships, thereby realizing the scour depth monitoring of each point in the entire cross-section. At the same time, the depth probe can also make circumferential motion on the groove slide through the groove slider to realize the scour depth monitoring of the 360° area around the wind turbine foundation. Finally, the monitoring data is transmitted to the data receiving platform, and the three-dimensional scour pit morphology is imaged by computer, thereby realizing the scour depth detection and three-dimensional scour pit morphology imaging throughout the installation and service process. The monitoring component first determines the height of the monitoring component to the mud line through the difference of the water pressure sensor, and determines the height of the monitoring component to the mud line, combined with the installation position of the depth probe, so as to determine the height of the depth probe to the mud line. According to the rotation angle of the depth probe and the distance from the depth probe to the monitoring point, and combined with the known height of the depth probe to the mud line, the scour depth at the monitoring point is solved by geometric relationship; then the scour depth of any point around the foundation is monitored through the annular slide; finally, the three-dimensional scour pit shape of the fan foundation is drawn by computer based on the monitored scour depth data. The entire monitoring process uses geometric relationships to obtain relevant monitoring data, with relatively low data errors, and can image the three-dimensional scour pit shape of the entire process, which is convenient for real-time assessment of the safety status of the fan foundation and timely remediation before the bearing capacity of the fan foundation is damaged due to scour. In addition, in view of the difficulties in repairing traditional monitoring devices when they fail and the high monitoring costs, the present invention achieves the rising and lowering of the monitoring components through a recommended lifting device arranged on the operation and maintenance platform, which is convenient for the maintenance of the monitoring components when they fail. At the same time, the monitoring components can be lifted to sea level through the lifting device after the wind turbine foundation is retired, and the monitoring devices can be recovered and reused through hoisting, which greatly reduces the monitoring costs.

[0086] The above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit the same. Although the present invention has been described in detail with reference to the above embodiments, those skilled in the art should understand that the technical solutions described in the above embodiments may still be modified, or some or all of the technical features may be replaced by equivalents. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the scope of the technical solutions of the embodiments of the present invention.

Claims

1. An offshore wind turbine foundation scour depth monitoring device, characterized in that: The invention comprises an operation and maintenance platform (2) and a monitoring component (3); the operation and maintenance platform (2) and the monitoring component (3) are both connected to the side wall of a wind turbine foundation (1); the operation and maintenance platform (2) is located above the monitoring component (3); the lower end of the wind turbine foundation (1) is inserted below a mud line (5); the monitoring component (3) is located below a sea level (4); and the operation and maintenance platform (2) is located above the sea level (4); the operation and maintenance platform (2) is connected to the monitoring component (3) via a suspension rope (6).

2. The offshore wind turbine foundation scour depth monitoring device according to claim 1 is characterized in that: The operation and maintenance platform (2) is an annular hollow mesh support (21), and the annular hollow mesh support (21) is fixedly connected to the side wall of the wind turbine foundation (1).

3. The offshore wind turbine foundation scour depth monitoring device according to claim 1 is characterized in that: The monitoring component (3) comprises an inflatable bag (3-1), an inner ring (3-2), an outer ring (3-3), a plurality of supports (3-4) and a monitor (3-5); the inflatable bag (3-1) is connected to the inner wall of the inner ring (3-2), a plurality of supports (3-4) are connected to the outer wall of the inner ring (3-2) at equal distances, the outer ends of the plurality of supports (3-4) are connected to the inner wall of the outer ring (3-3), and the lower end of the outer ring (3-3) is slidably connected to the monitor (3-5); the inflatable bag (3-1) is connected to the outer wall of the wind turbine foundation (1).

4. The offshore wind turbine foundation scour depth monitoring device according to claim 3 is characterized in that: The upper end surface of each support (3-4) is connected to a first water pressure sensor (3-41) and a pull ring (3-42); the lower end of the suspension rope (6) is connected to the pull ring (3-42), and the upper end is connected to the operation and maintenance platform (2).

5. The offshore wind turbine foundation scour depth monitoring device according to claim 3 is characterized in that: The monitor (3-5) comprises two depth sounding probes (3-54), the two depth sounding probes (3-54) are respectively connected to the two ends of a rotating shaft (3-53), the rotating shaft (3-53) is rotatably connected to the lower end of a vertical rod (3-52), the upper end of the vertical rod (3-52) is connected to a groove slider (3-51), the lower end of the outer ring (3-3) is provided with a groove slideway (3-31), and the groove slider (3-51) is slidably connected in the groove slideway (3-31).

6. The offshore wind turbine foundation scour depth monitoring device according to claim 5 is characterized in that: A driving device is arranged inside the outer ring (3-3) for driving the groove sliding block (3-51) to move in a circular motion along the groove slideway (3-31).

7. The offshore wind turbine foundation scour depth monitoring device according to claim 4 is characterized in that: A second water pressure sensor is provided at the mud line (5), and the second water pressure sensor is connected to the first water pressure sensor (3-41) via an electrical signal.

8. A method for installing an offshore wind turbine foundation scour depth monitoring device, characterized in that: The following steps are involved: Step 1, preparation before construction of the fan foundation (1): Before installing the fan foundation (1), take advantage of the fact that the inner diameter of the monitoring component (3) is larger than the outer diameter of the fan foundation (1), so that the monitoring component (3) is placed on the fan foundation (1), and the monitoring component (3) is adjusted to a suitable position, and the monitoring component (3) is fixed to the outer wall of the fan foundation (1) by inflating the inflatable bag (3-1). The position of the monitoring component (3) remains unchanged at this stage; then the fan foundation (1) is hoisted to the guide hole of the positioning platform, and the monitoring component (3) is fixed to the operation and maintenance platform (2) by a hoisting rope; Step 2: Monitoring the scouring depth during the construction of the wind turbine foundation (1): During the installation of the wind turbine foundation (1), the air bag (3-1) is deflated to reduce the volume of the air bag (3-1) so that it becomes loosely connected or disconnected from the wind turbine foundation (1) to prevent the monitoring component (3) and the wind turbine foundation (1) from sinking below the mud line (5) together; at the same time, the suspension rope (6) is loosened on the operation and maintenance platform (2) to gradually reduce the depth of the monitoring component (3) until the depth reaches the limit and the operation is stopped. At this time, the installation of the wind turbine foundation (1) is completed; at this stage, there is scouring in the area around the wind turbine foundation (1), and the scouring depth gradually increases with the installation depth, i.e., the installation time, and the scouring depth varies from zero to one pile diameter; When the wind turbine foundation (1) is not installed in place: at this stage, the monitoring component (3) is gradually lowered by loosening the suspension rope (6), that is, the distance from the monitoring component (3) to the mud line (5) gradually changes with the installation process of the wind turbine foundation (1); in order to facilitate the explanation of the monitoring principle, the scouring depth at a certain moment is used as an example; at this moment, the measurement value of the first water pressure sensor (3-41) on the support (3-4) in the monitoring component (3) and the measurement value of the second water pressure sensor at the mud line (5) are known, and the difference between the two can be calculated to obtain the first The distance L between the first water pressure sensor (3-41) and the second water pressure sensor is determined. Here, for error considerations, the measurement value of the first water pressure sensor (3-41) on the support (3-4) is determined when the monitoring component (3) is horizontal. If the measurement values ​​of the first water pressure sensors (3-41) on the four supports (3-4) are different, it means that the monitoring component (3) is tilted. The monitoring component (3) is kept in a horizontal state by adjusting the length of the suspension rope (6); since the first water pressure sensor (3-41) on the support (3-4) is connected to the monitoring component (3), the monitoring component (3) is tilted. The distance between the depth probes (3-54) is fixed at L0, and the distance from the depth probe (3-54) to the mud line (5) can be calculated by the distance difference as L1=L-L0; the depth probe (3-54) monitors the scouring depth of the measured point by rotating a certain angle α1, and the rotation angle α1 is known, and the distance from the depth probe (3-54) to the measured point is s1. The depth probe (3-54) has been measured, and the scouring depth of the measured point Δh1=s1cosα1-L1, wherein if the rotation angle α1 is less than 90°, the rotation angle is used to calculate the scouring depth. The rotation angle is α1. If the rotation angle α1 is greater than 90°, the rotation angle is α1-90° when calculating the scouring depth. Due to the relationship between the scouring depth and time, the scouring depth of each point on a certain section measured by the depth sounding probe (3-54) through the rotation angle cannot reflect the scouring depth of each point on the section at a certain moment measured in the actual process. Therefore, in order to make the measurement result more accurate, a depth sounding probe (3-54) with a fixed position is set up to vertically monitor the relationship between the scouring depth of the point below it and time, and the relationship function S between the scouring depth and time is obtained. L =S L (t); Assuming that the time for the depth probe (3-54) to rotate from the previous monitoring point to the next monitoring point is t, the relationship function S between the measured scour depth and time is L =S L (t), find the scour depth S1 corresponding to the time of the previous monitoring point and the scour depth S2 corresponding to the time of the next monitoring point, then β1=S2 / S1 is the rate of change of the scour depth with time, and the accurate scour depth Δh′1=(s1 cosα1-L1) / β1 can be calculated through the rate of change of the scour depth with time; when the scour depths of all points at the section are fully monitored, the groove slideway (3-31) at the lower part of the outer ring (3-3) drives the monitor (3-5) connected thereto to realize circumferential movement, and monitors the scour depths of all points within the circumferential range of the wind turbine foundation (1), and then transmits the scour depth monitoring data to the data receiving platform, and uses three-dimensional imaging software to perform three-dimensional imaging of the scour pit morphology; When the installation of the wind turbine foundation is completed: at this stage, the suspension rope (6) is completely relaxed, and the depth of the monitoring component (3) reaches the limit, that is, the distance from the monitoring component (3) to the mud line (5) is fixed, and the volume of the inflatable bag (3-1) is expanded by inflating the inflatable bag (3-1). At this time, the inflatable bag (3-1) and the outer wall of the wind turbine foundation (1) form a close contact, that is, the monitoring component (3) is fixed on the outer wall of the wind turbine foundation (1); in order to facilitate the explanation of the monitoring principle, the scouring depth at a certain point at a certain moment is used as an example for explanation; at this moment, the first water pressure sensor on the support (3-4) in the monitoring component (3) The measured value of the first water pressure sensor (3-41) and the measured value of the first water pressure sensor (3-41) at the mud line (5) are known, and the distance L′ between the first water pressure sensor (3-41) and the second water pressure sensor can be obtained by calculating the difference between the two. Here, due to error considerations, the measured value of the first water pressure sensor (3-41) on the support (3-4) is determined when the monitoring component (3) is horizontal. If the measured values ​​of the first water pressure sensors (3-41) on the four supports (3-4) are different, it means that the monitoring component (3) is tilted. The monitoring component can be tilted by adjusting the length of the suspension rope (6). (3) is in a horizontal state; since the distance between the first water pressure sensor (3-41) on the support (3-4) and the depth probe (3-54) is fixed at L0, the distance from the depth probe (3-54) to the mud line (5) can be calculated by the distance difference as L2=L′-L0; the depth probe (3-54) monitors the scouring depth of the measured point by rotating a certain angle α2, and the rotation angle α2 is known, and the distance from the depth probe (3-54) to the measured point is S2. The depth probe (3-54) has been measured, and the scouring depth of the measured point Δh2=s2cosα2-L2, wherein if the rotation angle α2 is known, the distance from the depth probe (3-54) to the measured point is S2. If the rotation angle α2 is less than 90°, the rotation angle α2 is used when calculating the scouring depth. If the rotation angle α2 is greater than 90°, the rotation angle α2-90° is used when calculating the scouring depth. Due to the relationship between the scouring depth and time, the scouring depth of each point on a certain section measured by the depth sounding probe (3-54) through the rotation angle cannot reflect the scouring depth of each point on the section at a certain moment measured in the actual process. Therefore, in order to make the measurement result more accurate, a depth sounding probe (3-54) with a fixed position is set up to vertically monitor the relationship between the scouring depth of the point below it and time, and the relationship function S between the scouring depth and time is obtained. L =S L (t); Assuming that the time for the depth probe (3-54) to rotate from the previous monitoring point to the next monitoring point is t, the relationship function S between the measured scour depth and time is L =S L (t); find the scour depth S3 corresponding to the time of the previous monitoring point and the scour depth S4 corresponding to the time of the next monitoring point, then β2=S4 / S3 is the rate of change of the scour depth with time, and the accurate scour depth can be calculated through the rate of change of the scour depth with time, that is, Δh′2=(s2cosα2-L2) / β2; when the scour depths of all points at the cross section are fully monitored, the groove slideway (3-31) at the lower part of the outer ring (3-3) drives the monitor (3-5) connected thereto to realize circumferential movement, and monitors the scour depths of all points within the circumferential range of the wind turbine foundation (1), and then transmits the scour depth monitoring data to the data receiving platform, and uses three-dimensional imaging software to perform three-dimensional imaging of the scour pit morphology; Step 3: Dynamic scouring depth monitoring of the wind turbine foundation (1) during its service period: The wind turbine foundation (1) begins its service period after installation. As the service time of the wind turbine foundation (1) increases, the scouring around the foundation continues, and the scouring radius of the soil around the foundation and the shape of the scouring pit also change. The scouring depth changes from one pile diameter to two pile diameters. At this stage, the suspension rope is completely relaxed, and the depth of the monitoring component (3) descends to the limit, that is, the distance from the monitoring component (3) to the mud line (5) is fixed. In order to facilitate the explanation of the monitoring principle, the scouring depth at a certain point at a certain moment is used as an example for explanation; at this moment, the measurement value of the first water pressure sensor (3-41) on the support (3-4) in the monitoring component (3) and the measurement value of the second water pressure sensor at the mud line (5) are known, and the difference between the two can be calculated to obtain the first water pressure sensor (3-41) and the second water pressure sensor The distance L′ between the first water pressure sensor (3-41) on the support (3-4) is determined for error considerations when the monitoring component (3) is horizontal. If the measured values ​​of the first water pressure sensors (3-41) on the four supports (3-4) are different, it means that the monitoring component (3) is tilted. The monitoring component (3) is kept horizontal by adjusting the length of the suspension rope (6). Since the distance between the first water pressure sensor (3-41) on the support (3-4) and the depth probe (3-54) is The fixed value is L0, and the distance from the sounding probe (3-54) to the mud line (5) can be calculated as L2=L′-L0 through the distance difference; the sounding probe (3-54) monitors the scouring depth of the measured point by rotating a certain angle α3, and the rotation angle α3 is known. The distance from the sounding probe (3-54) to the measured point is s3. The sounding probe (3-54) has been measured, and the scouring depth of the measured point is Δh3=s3cosα3-L2, wherein if the rotation angle α3 is less than 90°, the rotation angle α3 is used when calculating the scouring depth. , if the rotation angle α3 is greater than 90°, the rotation angle α3-90° is used when calculating the scour depth; due to the relationship between the scour depth and time, the scour depth of each point on a certain section measured by the depth sounding probe (3-54) through the rotation angle cannot reflect the scour depth of each point on the section at a certain moment measured in the actual process. Therefore, in order to make the measurement result more accurate, a depth sounding probe (3-54) with a fixed position is set to vertically monitor the relationship between the scour depth of the point below it and time, and the relationship function S between the scour depth and time is obtained. L =S L (t); Assuming that the time for the depth probe (3-54) to rotate from the previous monitoring point to the next monitoring point is t, the relationship function S between the measured scour depth and time is L =S L (t), find the scour depth S5 corresponding to the time of the previous monitoring point and the scour depth S6 corresponding to the time of the next monitoring point, then β3=S6 / S5 is the rate of change of the scour depth with time, and the accurate scour depth Δh′3=(s3cosα3-L2) / β3 can be calculated through the rate of change of the scour depth with time; when the scour depths of all points at the section are fully monitored, the groove slideway (3-31) at the lower part of the outer ring (3-3) drives the monitor (3-5) connected thereto to realize circumferential movement, and monitors the scour depths of all points within the circumferential range of the wind turbine foundation (1), and then transmits the scour depth monitoring data to the data receiving platform, and uses three-dimensional imaging software to perform three-dimensional imaging of the scour pit morphology; Step 4, monitoring of stable scour depth of wind turbine foundation (1) during service period: At this stage, the scour depth reaches a balanced state, and the scour depth is twice the pile diameter. Ignoring the change of scour depth with time, the scour pit shape tends to be stable. It is only necessary to measure the scour depth of each point at any cross section and obtain the stable scour pit shape. In order to facilitate the explanation of the monitoring principle, the scour depth at a point at a certain moment is used as an example. At this moment, the measurement value of the first water pressure sensor (3-41) on the support (3-4) in the monitoring component (3) and the second water pressure sensor at the mud line (5) are If the measured value of the sensor is known, the distance L′ between the first water pressure sensor (3-41) and the second water pressure sensor can be obtained by calculating the difference between the two. Here, due to error considerations, the measured value of the water pressure sensor (3-41) on the support (3-4) is determined when the monitoring component (3) is horizontal. If the measured values ​​of the first water pressure sensors (3-41) on the four supports (3-4) are different, it means that the monitoring component (3) is tilted. The monitoring component (3) is kept in a horizontal state by adjusting the length of the suspension rope (6). The distance between the first water pressure sensor (3-41) on (3-4) and the depth probe (3-54) is fixed at L0, and the distance between the depth probe (3-54) and the mud line (5) can be calculated by the distance difference as L2=L′-L0; the depth probe (3-54) monitors the scouring depth of the measured point by rotating a certain angle α4, and the rotation angle α4 is known. The distance between the depth probe (3-54) and the measured point is s4. The depth probe (3-54) has been measured, and the scouring depth of the measured point Δh4=s4cosα4-L2, and the depth probe (3-54) is fixed at L0, and the distance between the depth probe (3-54) and the measured point is L0. If the rotation angle α4 is less than 90°, the rotation angle α4 is used when calculating the scour depth; if the rotation angle α4 is greater than 90°, the rotation angle α4-90° is used when calculating the scour depth; after the scour depths of all points at the cross section are fully monitored, the groove slideway (3-31) at the lower part of the outer ring (3-3) drives the monitor (3-5) connected thereto to realize circumferential movement, and the scour depths of all points within the circumferential range of the fan foundation (1) are monitored, and then the scour depth monitoring data is transmitted to the data receiving platform, and three-dimensional imaging software is used to perform three-dimensional imaging of the scour pit shape; Step 5: Determine the scour range of the area around the wind turbine foundation (1): As the scour depth changes, the range of the scour pit also gradually changes. How to determine the boundary of the scour pit is an extremely important step; When the rotation angle of the depth sounding probe (3-54) is less than 90°, the problem to be solved in the area between the depth sounding probe (3-54) and the fan foundation (1) is how to determine the intersection of the fan foundation (1) and any cross section of the scour pit, that is, the maximum scour point of the fan foundation (1); in the process of the depth sounding probe (3-54) rotating from small to large, the measured distance is first the distance from the depth sounding probe (3-54) to each point in the axial direction of the fan foundation (1), and this measured distance gradually increases with the increase of the rotation angle; secondly, the measured distance is the distance from the depth sounding probe (3-54) to the point in the area belonging to the scour pit, and this measured distance gradually decreases with the increase of the rotation angle; therefore, at a certain cross section, when the rotation angle of the depth sounding probe (3-54) is less than 90°, the point with the largest measured distance is the maximum scour point; When the rotation angle of the depth sounding probe (3-54) is greater than 90°, the area corresponding to the scour pit section and the mud line (5) needs to be solved to determine the intersection of the mud line (5) and any section of the scour pit, that is, the maximum scour radius of the fan foundation (1); when the rotation angle of the depth sounding probe (3-54) changes from small to large, the distance to each point of the scour pit section in the area gradually increases with the increase of the rotation angle. To determine the maximum scour radius, it is necessary to analyze in combination with geometric relationships; since the vertical distance from the depth sounding probe (3-54) to the mud line (5) is known and set to Z1, the distance between the depth sounding probe (3-54) and the point to be measured is known and set to Z2, and the rotation angle of the depth sounding probe (3-54) is known and set to β, if It is considered that the vertical distance from the monitoring point to the wind turbine foundation (1) is the maximum impact radius of the wind turbine foundation; When the sounding probe (3-54) moves in a circumferential direction, the height of the accumulation on the back side of the fan foundation (1) is measured: During the scouring process of the fan foundation (1), soil accumulation will appear on the back side. The problem to be solved is how to measure the height of the accumulated soil and determine the maximum boundary of the scouring pit. According to literature research, the shape of the soil accumulation can be seen as an axisymmetric structure. When the sounding probe (3-54) moves to the accumulation area to measure the scouring depth, its distance to each point in the accumulation range is uncertain. To determine the height of the accumulated soil and the maximum boundary of the scouring pit, it is necessary to analyze it in combination with geometric relationships. Combined with the maximum scouring depth radius of the fan foundation scouring, the vertical distance from this point to the sounding probe (3-54) is known and is set to Z3. The vertical distance from this point to the fan foundation (1) is The vertical distance is known and set to Z4, and the rotation angle of the depth sounding probe (3-54) is continuously increased to start measuring the height of the accumulated soil body; since the rotation angle of the depth sounding probe (3-54) is known and set to γ, the distance from the depth sounding probe (3-54) to each point in the accumulation range is known and set to Z5, then the vertical distance between each point in the accumulation range and the depth sounding probe (3-54) can be calculated and set to Z6=Z5cosγ, wherein the corresponding monitoring point when the vertical distance Z6 between the measured point and the depth sounding probe (3-54) is the smallest is the highest point of the accumulated soil body, and the accumulation height at this time is Z3-Z6; the horizontal distance from the maximum accumulation height point to the maximum scouring radius point can be known from the geometric relationship that Z7=Z5sinγ, and the maximum boundary of the scouring pit is Z4+2Z5sinγ; Step 6: Maintenance and recycling of the scouring depth monitoring device: When the wind turbine foundation (1) is decommissioned or the monitoring component (3) fails, the monitoring component (3) is lifted to the sea level by lifting the suspension rope (6) tied to the operation and maintenance platform (2), so as to achieve maintenance and reuse of the entire monitoring device.

Citation Information

Patent Citations

  • Auxiliary tooling and demolition process for integral demolition of single pile foundation of sea fan on soft soil seabed

    CN108797588A

  • Monitoring device and monitoring method for scouring state of offshore wind power pile foundation

    CN112729201A

  • Ocean wind power foundation safety monitoring platform and monitoring method

    CN113431108A

  • Device and method for monitoring scouring of offshore wind power pile foundation in real time

    CN114705338A

Cited By

  • Method for identifying underwater terrain erosion and deposition state in real time

    CN120467283A

  • Pile foundation detection equipment and detection method for civil engineering construction

    CN121877611A