Automatic electric venetian blind system

By introducing drive units, communication circuits and memory into the venetian blind system, combined with electronic compass and user input, automated sunlight control is realized, solving the problem that the venetian blind system cannot optimize sunlight control in the existing technology, and improving the building's comfort and energy efficiency.

CN118997651APending Publication Date: 2024-11-22LUTRON TECHNOLOGY COMPANY LLC
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411259678.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Priority Date
2020-02-21
Filing Date
2020-12-11
Publication Date
2024-11-22

AI Technical Summary

Technical Problem

Existing electric venetian blind systems are difficult to optimize daylight control automatically, and the tilt position of the slats cannot be effectively adjusted according to clock schedules and sun positions to maximize entry of non-direct sunlight and block direct sunlight.

Method used

A venetian blind system is designed, including a driving unit, communication circuit and memory, which automatically adjusts the tilt position of the slat through a clock schedule and a sun predicted position, and uses electronic compass and mobile devices to determine the actual direction of the building facade, and combines the User input is compensated for automated daylight control.

Benefits of technology

Automatically adjust the inclination of the venetian blind slats according to the clock schedule and sun position, maximizing the entry of non-direct sunlight and blocking direct sunlight, improving comfort and energy efficiency within the building.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118997651A_ABST
    Figure CN118997651A_ABST
Patent Text Reader

Abstract

The invention relates to an automated electric venetian blind system. A venetian blind system can control (e.g., automatically) the amount of sunlight entering a window on a facade of a building to prevent direct sunlight from irradiating into the building while maximizing the amount of non-direct sunlight in the building. The venetian blind system may tilt one or more slats to a field of view tilt position in which the slats are horizontal, wherein the slats may block direct sunlight from irradiating into the building, and a privacy tilt position in which the slats are vertical. The drive unit may tilt the slat according to a clock having an event time determined from a predicted position of the sun such that the slat is tilted to the side-inclined tilt position when the predicted position of the sun indicates direct sunlight is incident on the facade. The facing direction of the facade may be configured using a mobile device.
Need to check novelty before this filing date? Find Prior Art

Description

[0001] This application is a divisional application of the invention patent application with application date of December 11, 2020, application number 202080081907.9, and invention name “Automated Electric Venetian Blind System”.

[0002] CROSS-REFERENCE TO RELATED APPLICATIONS

[0003] This application claims the benefit of U.S. Provisional Application Serial No. 62 / 947,872, filed on December 13, 2019, entitled AUTOMATED MOTORIZED BLIND SYSTEM, and U.S. Provisional Application Serial No. 62 / 979,860, filed on February 21, 2020, entitled AUTOMATED MOTORIZED BLIND SYSTEM, which are incorporated herein by reference in their entirety. Background Art

[0004] A load-controlled environment, such as a residence or office building, for example, may be configured with various types of load control systems. For example, a lighting control system may be used to control lighting loads in a user's environment. An electric window treatment control system may be used to control the natural light provided to a user's environment. A heating, ventilation, and air conditioning (HVAC) system may be used to control the temperature in a user's environment.

[0005] Each load control system may include various control devices, including a control source device and a control target device. The control target device may receive a message (e.g., a digital message) from one or more of the control source devices. The message may include a load control message for controlling an electric load. The control target device may be capable of directly controlling the electric load. The control source device may be capable of indirectly controlling the electric load via the control target device by sending a message including a control instruction for controlling the electric load controlled by the control target device to the control target device.

[0006] Window treatments (such as, for example, roller blinds, valances, Roman shades, and venetian blinds) are typically installed in front of windows to provide control over the amount of sunlight entering a space. A typical venetian blind system includes a plurality of elongated slats extending along the width of the window and spaced vertically between a top rail and a bottom rail. The venetian blind system typically includes a lift cord extending from the bottom rail through an opening in the slat to the top rail and allowing the bottom rail to be raised and lowered to raise and lower the slat. In a manual venetian blind system, the end of the lift cord that is not attached to the bottom rail is typically suspended from the top rail so that a user can pull the lift cord to raise and lower the slat. The venetian blind system typically also includes an inclined ladder extending between the top rail and the bottom rail and operating to support the slat and tilt it. A typical prior art manual venetian blind system includes a rod that is suspended from the top rail and can be rotated to adjust the tilt angle of the slat. The slat can be oriented substantially horizontally (i.e., perpendicular to the window) to allow sunlight to enter the space, and can be oriented substantially vertically (i.e., parallel to the window) to prevent sunlight from entering the space.

[0007] Some prior art venetian blind systems include a motor for allowing the slats to be raised and lowered and for tilting the slats. Some electric venetian blind systems typically include a single motor coupled to a drive shaft extending across the width of the top rail. The drive shaft may have at least two drums for winding up the lift cords when the shaft is rotated by the motor. The tilting ladder is typically coupled to the drive shaft by friction, so that when the slats are already fully tilted in one direction, the ends of the tilting ladder slide through the drive shaft as the drive shaft rotates. In order to adjust the tilt of the slats, the drive shaft may be rotated in the reverse direction so that the friction between the tilting ladder and the drive shaft causes the ends of the tilting ladder to rotate. Therefore, in a typical prior art electric venetian blind system that includes a single motor, the motor must be rotated in the reverse direction to adjust the tilt of the slats. Summary of the invention

[0008] As described herein, a venetian blind system may be configured to control (e.g., automatically control) the amount of daylight entering a building to prevent direct sunlight from entering the building while attempting to maximize the amount of indirect sunlight entering the building. The venetian blind system may be installed to cover a window, located on a facade of a building. The venetian blind system may include: a top rail; a bottom bar; a plurality of slats, the plurality of slats being vertically spaced between the top rail and the bottom bar; a lift cord extending from the top rail to the bottom bar to allow raising and lowering the bottom bar; a tilting ladder extending from the top rail to the bottom bar and operable to support and tilt the slats; and a drive unit operably coupled to the tilting ladder for tilting the slats. The drive unit may be configured to selectively tilt the slats into each of a plurality of tilt positions, the plurality of tilt positions including at least: a view tilt position in which the slats are substantially horizontal; a side tilt position in which the slats are positioned to block direct sunlight from impinging into the building; and a privacy tilt position in which the slats are substantially vertical. The drive unit may be configured to tilt the slats into one of the plurality of tilt positions at each of a plurality of event times according to a clock schedule. The plurality of event times may be determined from a predicted position of the sun, such that the drive unit is configured to tilt the slats into the side tilt position when the predicted position of the sun indicates direct sunlight is incident on the facade, tilt the slats into the view tilt position when the predicted position of the sun indicates no direct sunlight is incident on the facade, and tilt the slats into the privacy tilt position between sunset and sunrise.

[0009] In addition, a control device (e.g., system control) is configured to control a venetian blind system to control (e.g., automatically control) the amount of daylight entering a building to block direct sunlight from entering the building while attempting to maximize the amount of indirect sunlight entering the building. The control device may include: a communication circuit configured to transmit a message including a command for controlling the venetian blind system; and a memory configured to store a clock schedule with event times and associated commands for tilting slats of the venetian blind system to one of a plurality of tilt positions, the plurality of tilt positions including at least: a view tilt position in which the slats are substantially horizontal; a side tilt position in which the slats are positioned to block direct sunlight from entering the building; and a privacy tilt position in which the slats are substantially vertical. The control device may also include a control circuit, which is configured to: generate the clock schedule by determining the multiple event times based on the predicted position of the sun; and based on the clock schedule, transmit a message for controlling the blind system to perform the following operations via the communication circuit: tilt the slats to the side tilt position when the predicted position of the sun indicates direct sunlight is incident on the facade, tilt the slats to the field of view tilt position when the predicted position of the sun indicates no direct sunlight is incident on the facade, and tilt the slats to the privacy tilt position between sunset and sunrise.

[0010] In addition, a method for configuring a venetian blind system mounted on a facade of a building is described herein. The method may include: (1) determining a compass direction of the facade using an electronic compass of a mobile device, the mobile device being positioned facing an interior surface of the facade; (2) displaying a top-view image of the building on a visual display of the building; (3) displaying an indication of the compass direction determined from the electronic compass of the mobile device on the top-view image of the building; (4) receiving an indication of an actual direction of the facade in response to a user input at the mobile device; (5) determining a compensation factor between the compass direction determined from the electronic compass and the actual direction determined from the user input; and (6) transmitting the actual direction of the facade to a control device to configure the venetian blind system based on the actual direction of the facade. BRIEF DESCRIPTION OF THE DRAWINGS

[0011] Figure 1 is a system diagram illustrating an exemplary load control environment for controlling electrical loads.

[0012] Figure 2 is a perspective view of an exemplary motorized window treatment, such as a Venetian blind system.

[0013] FIG. 3A to FIG. 3Cyes Figure 2 A side view of a Venetian blind system showing slats of the Venetian blind system in different tilted positions.

[0014] Figure 4A is a perspective view of an exemplary building showing the solar altitude angle and solar azimuth angle with respect to the elevation angle of the building's facade.

[0015] Figure 4B is an exemplary time clock schedule for controlling motorized blinds installed in a building.

[0016] FIG. 5A to FIG. 5F is a screenshot of a configuration application running on a mobile device that can be used to configure electric blinds.

[0017] Figure 6 is used to configure the motorized blinds (e.g. using the operating display FIG. 5A to FIG. 5F A flowchart of an exemplary configuration procedure for a mobile device (with a configuration application for a screen shot shown).

[0018] Figure 7 is a flow chart of an exemplary orientation configuration procedure that may be executed to configure the orientation of a motorized venetian blind.

[0019] Figure 8 is a flow chart of another exemplary orientation configuration procedure that may be executed to configure the orientation of a motorized venetian blind.

[0020] Fig. 9 is a flow chart of an exemplary clock schedule configuration procedure that may be executed to configure a clock schedule for controlling (eg, automatically controlling) the tilt position of one or more motorized venetian blinds.

[0021] Fig.10 is a flow chart of an exemplary facade timeclock schedule configuration program that may be executed to configure a timeclock schedule for controlling the tilt position of one or more motorized venetian blinds on a particular facade of a building in which the motorized venetian blinds are located.

[0022] Fig.11 is a flow chart of another exemplary facade clock schedule configuration process.

[0023] Fig.12 is a flow chart of an exemplary clock event configuration procedure that may be executed to configure clock events of a clock schedule for controlling the tilt position of one or more motorized venetian blinds.

[0024] Fig.13 is a flow chart of an exemplary facade timeclock schedule configuration program that may be executed to configure a timeclock schedule for controlling the tilt position of one or more motorized venetian blinds on a particular facade of a building in which the motorized venetian blinds are located.

[0025] Fig.14 is a flow chart of an exemplary clock schedule execution for a control device including a control source device.

[0026] Fig.15 is a block diagram of an exemplary network device.

[0027] Fig.16 is a block diagram of an exemplary system controller.

[0028] Fig.17 is a block diagram of an exemplary control target device.

[0029] Fig.18 is a block diagram of an exemplary control source device.

[0030] Fig.19 is a simplified block diagram of a motor drive unit. DETAILED DESCRIPTION

[0031] Figure 1 The invention is a load control system 100 including a load control device for controlling an electric load. Figure 1 As shown, the load control system 100 may be a load control environment, for example, a room 102 in a building. The load control system 100 may include a control device that may be capable of controlling (e.g., automatically controlling) an electrical load. The control device may include a control source device that may transmit a message for controlling the electrical load and / or a control target device that may control the electrical load in response to an instruction received in a message. The control target device may include a load control device that may directly control the electrical load in response to an instruction received in a message from the control source device.

[0032] Lighting control devices, such as lighting control devices 112, 113, may be examples of control target devices in load control system 100. Lighting control device 112 may be a dimmer, an electronic switch, a ballast, a light emitting diode (LED) driver, etc. Lighting control device 112 may be able to directly control the amount of power provided to lighting load 114. Lighting control device 112 may be configured to wirelessly receive messages via RF signal 154 (e.g., from an associated control device) and control lighting load 114 in response to the received messages.

[0033] The lighting control device 113 may be a wall mounted dimmer, a wall mounted switch, or other keypad device for controlling the lighting load 115. The lighting control device 113 may be adapted to be mounted in a standard electrical wall box. The lighting control device 113 may include a desktop or plug-in load control device. The lighting control device 113 may include one or more buttons for controlling the lighting load 115. The lighting control device 113 may include a toggle actuator. Actuation (e.g., continuous actuation) of the toggle actuator may switch (e.g., turn off and on) the lighting load 115. The lighting control device 113 may include an intensity adjustment actuator (e.g., a rocker switch or an intensity adjustment button). Actuating the upper or lower portion of the intensity adjustment actuator may increase or decrease the amount of power delivered to the lighting load 115, respectively, and thus increase or decrease the intensity of the receiving lighting load within a range of minimum intensity (e.g., approximately 1%) to maximum intensity (e.g., approximately 100%). The lighting control device 113 may include a plurality of visual indicators (e.g., light emitting diodes (LEDs)) that may be arranged in a linear array and may illuminate to provide feedback on the intensity of the lighting load 115. Examples of wall mounted dimmers are described in more detail in U.S. Patent No. 5,248,919, entitled LIGHTING CONTROL DEVICE, issued on September 29, 1993, and U.S. Patent Application Publication No. 2014 / 0132475, entitled WIRELESS LOAD CONTROL DEVICE, published on May 15, 2014, the entire disclosures of which are incorporated herein by reference.

[0034] Lighting control device 113 may be configured to wirelessly receive messages (e.g., from an associated control device) via wireless signals such as radio frequency (RF) signals 154 using a first wireless protocol (e.g., a proprietary protocol such as a CLEARCONNECT protocol (e.g., CLEAR CONNECT A protocol and / or CLEAR CONNECT X protocol)). Lighting control device 113 may be configured to control lighting load 115 in response to the received message. Examples of dimmer switches operable to transmit and receive messages are described in greater detail in commonly assigned U.S. Patent Application No. 12 / 033,223, filed on February 19, 2008, entitled COMMUNICATION PROTOCOL FOR A RADIOFREQUENCY LOAD CONTROL SYSTEM, which is incorporated herein by reference in its entirety.

[0035] The load control system 100 may include a daylight control device, such as a motorized window treatment 116. The motorized window treatment 116 may include a motor drive unit (not shown) configured to control the position of a covering material 118 to control the amount of daylight entering the load control environment 102. For example, the covering material 118 may include a shade fabric wrapped around a roller tube, and the motor drive unit may be configured to rotate the roller tube to raise and lower the shade fabric. Additionally, the motorized window treatment 116 may include a venetian blind and the covering material 118 may include one or more slats. The motor drive unit of the venetian blind may be configured to raise and lower a bottom rod of the venetian blind to raise and lower the slats, and / or tilt the slats to adjust the amount of daylight entering the load control environment 102.

[0036] The load control system 100 may include one or more other control target devices, such as a plug-in load control device 126 for directly controlling a floor lamp 128, a table lamp, and / or other electrical loads that may be plugged into the plug-in load control device 126, and / or a temperature control device 124 (e.g., a thermostat) for directly controlling a heating, ventilation, and air conditioning (HVAC) system. The load control system 100 may also or alternatively include an audio control device (e.g., a speaker system) and / or a video control device (e.g., a device capable of streaming video content).

[0037] The control source devices in the load control system 100 may include a remote control device 122, an occupancy sensor 110, a daylight sensor 108, and / or a window sensor 120. The control source device may transmit a message to an associated control target device for directly controlling an electrical load by transmitting a message (such as a load control message) to the control target device. The remote control device 122 may send a message for controlling the control target device after actuating one or more buttons on the remote control device 122. The one or more buttons may correspond to a preset (e.g., scene) for controlling the lighting load 114, the lighting load 115, the lighting load 128, or any combination thereof. The occupancy sensor 110 may send a message to the control target device in response to an occupancy or vacancy condition (e.g., movement or no movement) sensed within its observable area. The daylight sensor 108 may send a message to the control target device in response to the detection of the amount of light within its observable area. The window sensor 120 may send a message to the control target device in response to a measured light level received from outside the load control system 100. For example, the window sensor 120 may detect when sunlight is directly shining into the window sensor 120, is reflected onto the window sensor 120, and / or is blocked by external items (such as clouds or buildings). The window sensor 120 may send a message indicating the detected light level and / or a condition indicating that the detected light level exceeds a threshold (e.g., exceeds a threshold or falls below a threshold).

[0038] The control source device and the control target device may communicate with the system controller 150. The system controller 150 may be capable of transmitting messages to and / or receiving messages from the control devices (e.g., the control source device and / or the control target device). The message may include association information for associating the control source device with the control target device. The system controller 150 may use the association information to facilitate the transmission of control information from the control source device to the associated control target device. For example, the system controller 150 may use a radio frequency (RF) signal 154 to communicate with one or more control devices (e.g., the control source device and / or the control target device). When the system controller 150 receives a message from the control device, the system controller may use the association information to facilitate the transmission of control instructions and / or other information to the associated device. The system controller 150 may also receive programming data (e.g., settings) for the control device and transmit messages for performing control according to the programming data. In addition, the system controller 150 may be configured to control messages of the control target device in response to a clock schedule. The system controller 150 may be configured to execute a clock (eg, an astronomical clock) for determining the current time in order to determine when to transmit a message for controlling the control target device according to the event time of the clock schedule.

[0039] The system controller 150 may also or alternatively communicate via wireless signals, such as RF signals 152, using a second wireless protocol (e.g., a standard protocol such as WI-FI, BLUETOOTH, etc.). For example, the system controller 150 may communicate with one or more network devices, such as a network device 144 (e.g., a mobile device). The network device 144 may include a personal computer (PC), a laptop computer, a tablet computer, a smart phone, or an equivalent device via RF signals 152. The system controller 150 may be a gateway device, a bridge device, an access point, etc. Examples of load control systems having a system controller 150 are described in more detail in commonly assigned U.S. Patent Application Publication No. 2014 / 0001977, published on January 2, 2014, entitled LOAD CONTROL SYSTEM HAVING INDEPENDENTLY-CONTROLLED UNITSRESPONSIVE TO A BROADCAST CONTROL SYSTEM, and U.S. Patent Application Publication No. 2015 / 0185752, published on July 2, 2015, entitled WIRELESS LOAD CONTROL SYSTEM, the entire disclosures of which are incorporated herein by reference.

[0040] The control source device in the load control system 100 can be associated with the control target device using various association techniques. For example, in the association procedure, the control source device can be associated with the control target device by the user 142 actuating a button on the control source device and / or the control target device. Actuating a button on the control source device and / or the control target device can place the control source device and / or the control target device in an association mode, for example, for associating with each other. In the association mode, the control source device can transmit an association message to the control target device. The association message from the control source device may include a unique identifier of the control source device. The control target device may store the unique identifier of the control source locally so that the control target device may be able to identify a message (e.g., a subsequent message) from the control source device that may include a load control instruction. The control target device may be able to respond to a message from the associated control source device by controlling the corresponding electrical load according to the load control instruction received in the message. Examples of load control systems are described in more detail in commonly assigned U.S. Patent No. 5,905,442, issued on May 18, 1999, entitled METHOD AND APPARATUS FOR CONTROLLING AND DETERMINING THE STATUS OF ELECTRICAL DEVICES FROM REMOTE LOCATIONS, and U.S. Patent No. 8,417,388, issued on April 9, 2013, entitled LOAD CON TROL SYSTEM HAVING AN ENERGY SAVINGS MODE, the entire disclosures of which are incorporated herein by reference.

[0041] The load control system 100 can be designed and / or configured using design software (e.g., graphical user interface (GUI) software and / or configuration applications) running on a network device 144 (e.g., such as a personal computer (PC), laptop computer, tablet computer, smart phone, or equivalent device with a visual display). Using the design software, a user 142 can select control devices (e.g., control devices of the load control system, such as control source devices and / or control target devices) and / or adjust programming data for configuring the system. For example, the user 142 can be a homeowner who can use the network device 144 to design and / or configure the load control system 100 in a house where the homeowner lives. In addition, the user 142 can be a worker, such as an electrical contractor, who can be hired by the homeowner to design and / or configure the load control system 100 in a house where the homeowner lives. The design software running on the network device 144 can be used to configure the electric window treatment 116 (e.g., as will be described in more detail below). Examples of configuration programs for load control systems are described in more detail in commonly assigned U.S. Patent No. 8,228,163, entitled HANDHELD PROGRAMMER FORLIGHTING CONTROL SYSTEM, issued on July 24, 2012, and U.S. Patent Application Publication No. 2014 / 0265568, entitled COMMISSIONING LOAD CONTROL SYSTEMS, published on September 18, 2014, the entire disclosures of which are incorporated herein by reference.

[0042] The functionality of the load control system 100 may be automatically configured by the design software in response to the type of control devices (e.g., lighting control devices, remote control devices, etc.) added to the load control system during a configuration procedure. The design software may automatically generate programming data (e.g., including one or more control features) that defines the operation of the load control system 100 based on the location and / or load type of the control devices that have been added to the load control system. After the control devices have been added to the load control system 100, the design software may be configured to review the details of the automatically programmed control features with the user of the design software. The user may confirm that the automatically programmed functionality is desired and / or manually edit the control features. Once the functionality of the control features is confirmed and / or edited, portions of the programming database may be transmitted to the control devices of the load control system 100 for use during normal operation of the load control system. For example, the complete programming database may be transmitted from the network device 144 to the system controller 150, and the system controller 150 may transmit portions of the programming database to each of the control devices. Once the system controller 150 begins transmitting portions of the programming database to the control devices, the user may be able to use the network device 144 to control the operation of the load control system 100. For example, since the entire programming database is stored on the system controller 150, a user can select a command using the network device 144 and the network device 144 can transmit a message including the command to the system controller 150, which in turn can transmit the command to the appropriate control device of the load control system 100 (e.g., based on the programming database stored on the system controller). When the control device transmits the command directly to the load control device, the programming data transmitted to the control device can be used. Once the load control device has its portion of the database, the load control device can be controlled by the control device (e.g., remote control device and other control devices in the system).

[0043] After the programming data has been transferred to the control devices and the load control system 100 is fully functional (e.g., during normal operation), the design software executed at the system controller 150 may automatically update the programming data. When one or more control devices (e.g., lighting control devices and / or remote control devices) are added to the load control system 100, the design software executed at the system controller 150 may automatically update the control features associated with the added control devices and / or add control features. For example, if a user adds a lighting control device to the load control system 100 via the network device 144 using the design software, the design software executed at the system controller 150 may automatically add the lighting control device to various scenes and / or schedules. When automatically updating the control features after the programming data has been transferred to the control devices, the design software may not overwrite manual changes previously made to the control features by the user. This may ensure that the user's manual changes are maintained after subsequent automatic updates.

[0044] Figure 2 is a perspective view of an exemplary powered window treatment (eg, a venetian blind system 210 ) that may be deployed as the powered window treatment 116 of the load control system 100 . FIG. 3A to FIG. 3C yes Figure 2 300 . The venetian blind system 210 is shown as being installed in front of a window 300 on a facade 310 of a building. The venetian blind system 210 may include a covering material, such as a plurality of flat slats 212, disposed between a top rail 214 and a bottom bar 216 (e.g., a bottom rail). The venetian blind system 210 may be configured to be installed in front of a window 300. The venetian blind system 210 may include a mounting bracket (not shown) coupled to a top of the top rail 214 for mounting the venetian blind system 210 to a ceiling above the window 300 and a side panel (not shown) that may allow the venetian blind system 210 to be alternatively mounted to a wall surrounding the window 300. The venetian blind system 210 may also include a curtain head 215 located in front of the top rail 214.

[0045] The venetian blind system 210 may also include a drive unit 230 (e.g., a motor drive unit or a venetian blind drive unit) located in the top rail 214 for adjusting the covering material of the venetian blind system 210 to control the amount of daylight entering the space. For example, the drive unit 230 may include a motor (not shown) configured to operate to raise and lower the bottom bar 216 and / or tilt the slats 212 to control the amount of daylight entering the space, as will be described in more detail below. In one embodiment, the drive unit 230 may be configured to independently control the position of the bottom bar 216 and the tilt angle of the slats 212 to control the amount of daylight entering the space in which the venetian blind system 210 is installed. In other embodiments, the drive unit 230 may be configured to control only one or the other of the position of the bottom bar 216 and the tilt angle of the slats 212. For example, in various embodiments, the drive unit 230 may be configured to control only the tilt angle of the slats 212. In such embodiments, the position of the bottom bar 216 may be manually adjustable by a user. The drive unit 230 may be configured to receive a supply voltage, for example, a direct current (DC) supply voltage from a DC power supply such as, for example, a battery (e.g., an alkaline battery, a nickel-cadmium battery, a nickel-metal hydride battery, a lithium-ion battery, etc.). The drive unit 230 may include wireless communication circuitry for receiving wireless signals (e.g., a radio frequency (RF) signal), such as, for example, an RF receiver or transceiver. The drive unit 230 may be configured to raise and lower the bottom bar 116 and / or tilt the slats 212 in response to commands received via the wireless signal to control the amount of daylight entering the space. The venetian blind system 210 may also include one or more batteries (e.g., alkaline batteries, nickel-cadmium batteries, nickel-metal hydride batteries, lithium-ion batteries, etc.) located within or at least partially within the top rail 214 for powering the drive unit 230. The battery may be, for example, a D-cell battery or an AA battery.

[0046] The venetian blind system 210 may include two lift cords 218 positioned at the left and right ends of the slats 112 to allow the bottom bar 216 to be raised and lowered. The venetian blind system 210 may also include two tilting ladders 220 positioned at the left and right ends of the slats 112 to allow the slats 212 to be tilted. The motor of the drive unit 230 may be operably coupled to the tilting ladders for tilting the slats. The slats 212 may extend across the width of the window 300 so that the venetian blind system 210 (e.g., so that the venetian blind system 210 may be able to cover the window) and the slats 212 may be equally spaced between the top rail 214 and the bottom bar 216. Alternatively, the slats 212 may include curved slats instead of flat slats. The lift cords 218 may each extend from the top rail 214 through a corresponding lift cord opening 222 in each of the slats 212 to the bottom bar 216. In an embodiment that includes powered raising and lowering of the bottom bar 216, the drive unit 230 can be configured to wind and unwind the lift cord 218 to respectively raise and lower the bottom bar 116 between the fully raised position and the fully lowered position. In such an embodiment, as the drive unit 230 raises the bottom bar 216, the slats 212 can each contact the bottom bar one by one and can be raised with the bottom bar. In addition, the drive unit 230 can control the bottom bar 216 to a specific intermediate position between the fully raised position and the fully lowered position.

[0047] The inclined ladders 220 may each have a front band 224 (e.g., front strip) and a rear band 226 (e.g., rear strip) extending parallel to each other from the top rail 214 to the bottom bar 216 adjacent to the lift cord 218. The front band 224 of the inclined ladder 220 may be generally positioned in front of the lift cord 218. Each inclined ladder 220 may also include a plurality of rungs (not shown) (e.g., bands or strips) extending from the front band 224 to the rear band 226 between each pair of adjacent slats 212 of the venetian blind system 210 to form the ladder. Thus, each of the slats 212 may rest on one of the rungs in each of the inclined ladders 220 so that the slats may be vertically equidistantly spaced apart when the bottom bar 216 is in the fully lowered position. In an embodiment in which the position of the bottom bar 216 is controlled by a drive unit 230, the front band 224 and the rear band 226 may be coupled to the drive unit 230 in the top rail 214. As the drive unit 230 winds the lift cord 218 to raise the bottom bar 216, the portion of the inclined ladder 220 between adjacent rungs may become slack as the bottom bar is raised and the stacked slats 212 contact the next slat. The drive unit 230 may be configured to tilt the slats 212 by vertically moving the front belt 224 and the rear belt 226 relative to each other, so that the rungs and, therefore, the slats 212 are tilted at a certain angle (e.g., a tilt angle θ) relative to the front belt and the rear belt. 百叶帘 ). Alternatively, the front and rear straps 224, 226 and the crosspieces of the inclined ladder 220 may include ropes.

[0048] like FIG. 3A to FIG. 3C As shown, the drive unit 230 can tilt the slats 212 of the blind system 210 into different tilted positions. For example, the drive unit 230 can be configured to tilt the slats 212 into different tilted positions. Figure 3A The tilted position of the field of view shown, such as Figure 3B sideways tilt position (e.g., direct sunlight blocking position or "fade-fighter" tilt position) and / or as shown Figure 3C The drive unit 230 may be configured to control the slats 212 to be in a horizontal orientation (e.g., in a horizontal plane) in the view tilt position to allow daylight (e.g., indirect sunlight) to enter the space where the blind system 210 is located and / or allow the space occupant to have a view outside the window. For example, the view tilt position may be considered to be a 50% tilt position of the blind system 210. The drive unit 230 may be configured to tilt the slats 212 toward the rear of the blind system 210 (e.g., toward the window) by approximately 45° to a side tilt position to block direct sunlight from entering the space while still allowing indirect sunlight to enter the space, but it should be understood that the drive unit 230 may be configured to tilt the slats 212 (e.g., continuously, variably, and reversely) to any angle between 0° and 90°, such as, for example, 30°, 45°, 60°, etc. The side-slant tilt position can be in the range of about 1% tilt position to 49% tilt position of the blind system 210, where, for example, a 45° tilt angle can be considered a 25% tilt position. For example, the side-slant tilt position can be configured and / or adjusted using design software running on a mobile device (e.g., network device 144). In addition, the drive unit 230 can be configured to tilt the slats 212 from the horizontal plane toward the rear of the blind system 210 by about 90° to reach a position such as Figure 3C The slats 230 may be positioned in the privacy tilt position shown to block direct and indirect sunlight from entering the space and / or to block views through the windows to provide privacy to occupants of the space. For example, the privacy tilt position may be considered a 0% tilt position of the venetian blind system 210. In addition, the drive unit 230 may be configured to tilt the slats approximately 90° from a horizontal plane toward the front of the venetian blind system 210 when in the privacy tilt position (e.g., a 100% tilt position of the venetian blind system 210).

[0049] The drive unit 230 of the blind system 210 may be configured to control (e.g., automatically control) the tilt position of the blind system 210 (e.g., slats 212). For example, when direct sunlight is incident on the facade 310 where the window 300 is located, the drive unit 230 of the blind system 210 may be configured to automatically control the tilt position of the slats 212 to a side tilt position to block direct sunlight from irradiating into the space. When direct sunlight is not incident on the facade 310, the drive unit 230 of the blind system 210 may be configured to control (e.g., automatically control) the tilt position of the slats 212 to a view tilt position to allow indirect sunlight to enter the space and / or allow users of the space to have a view outside the window. For example, the drive unit 230 may be configured to delay the automatic adjustment of the tilt position for a predetermined amount of time (e.g., one hour) after the tilt position is adjusted in response to a command received via a wireless signal. In addition, the drive unit 230 of the venetian blind system 210 may be configured to control the tilt position of the slats 212 at various times relative to the sunrise and sunset times of an upcoming day. For example, the drive unit 230 of the venetian blind system 210 may be configured to control the tilt position of the slats 212 to the privacy tilt position between sunset and sunrise. In addition, the drive unit 230 of the venetian blind system 210 may be configured to control the tilt position of the slats 212 to the privacy tilt position at predetermined times of the day that may be specified by a user of the space (e.g., during nighttime hours).

[0050] The drive unit 230 of the blind system 210 may be configured to control (e.g., automatically control) the tilt position of the slats 212 according to a predetermined clock schedule. The clock schedule may be generated by a system controller (e.g., system controller 150) of the load control system of the blind system 210. The system controller may be configured to generate the clock schedule daily (e.g., during the night time when the slats 212 are in the privacy tilt position). The system controller may be configured to store the clock schedule and transmit commands to the drive unit 230 of the blind system 210 for tilting the slats 212 to the appropriate tilt position according to the clock schedule. In addition, the system controller may transmit the clock schedule to the drive unit 230 of the blind system 210 for use the next day. The drive unit 230 of the blind system 210 may be configured to store the clock schedule in a memory (e.g., a new clock schedule every day) and tilt the slats 212 to multiple tilt positions at corresponding event times of the clock schedule during the day (e.g., the drive unit 230 may be configured to execute a clock). Furthermore, the drive unit 230 of the blind system 210 may be configured to generate a clock schedule itself daily. Additionally and / or alternatively, the drive unit 230 of the blind system 210 may be configured to generate a clock schedule for a plurality of upcoming days and store the clock schedule in a memory.

[0051] The system controller and / or drive unit 230 of the blind system 210 may be configured to calculate the predetermined positions of the sun at multiple discrete times of the day in order to determine when and how to generate clock events for the clock-of-day schedule. The position of the sun in the sky may be determined by the sun altitude angle a t and the solar azimuth a s limited. Figure 4A is a perspective view of an exemplary building 400 where a window 300 of a facade 310 may be located. t It may be the angle between a line 410 pointing toward the sun and a line 420 from the facade 310 to the sun projected on the ground (eg, a line pointing toward the horizon at the location of the building 400). t It can also be regarded as the incident angle of the sun's rays on the horizontal plane. s It may be the angle formed by a line 430 from the facade 310 to the south and a line 420 from the observer to the sun projected on the ground.

[0052] The system controller and / or drive unit 230 of the blind system 210 may be configured to generate a time signal based on a date (eg, a Julian date) and a time (eg, a standard time t s ) and the location of the building 400 where the window 300 is located (eg, longitude λ and latitude Φ) to calculate the solar altitude angle a t and the solar azimuth a s For example, the system controller and / or the drive unit 230 of the venetian blind system 210 may be configured to calculate the sun altitude angle a using the following equation: t and the solar azimuth a s . Solar time 太阳 (for example, the time given by a sundial) and the standard time t s The difference between the times given by a clock (e.g., the time given by a clock) due to the ecliptic angle of the Earth's rotation axis can be defined by the equation of time ET. The equation of time ET can be determined as a function of the current Julian date J using, for example, the following equation:

[0053] ET = 0.1644 sin(A) - 0.1273 cos(B), (Equation 1)

[0054] Where A = [4π·(J-81.6)] / 365.25 and B = [2π·(J-2.5)] / 365.25. The Julian date J may be a decimal number representing the day of the year. For example, the Julian date J may be equal to one for January 1, two for January 2, three for January 3, and so on. Solar time t 太阳 The standard time t can be calculated, for example, using the following equation s, the equation of time ET, the standard meridian SM of the time zone of the building's location, and the longitude λ:

[0055] t 太阳 =t s +ET+[12·(SM-λ)] / π. (Equation 2)

[0056] The standard meridian SM may be determined from the time zone of the location of the building 400. Each time zone may have a unique standard meridian that may define a particular line of latitude within the time zone. There may be approximately 15° between the standard meridians of adjacent time zones.

[0057] Sun altitude angle a s and the solar azimuth a z It can be determined from the solar declination δ. The solar declination δ can define the angle of incidence of the sun's rays on the Earth's equatorial plane. The solar declination δ can be determined using, for example, the following equation:

[0058] δ = 0.4093·sin[2π·(J-81) / 368]. (Equation 3)

[0059] Standard time t s The solar altitude angle a t The solar time t can be calculated using, for example, the following equation 太阳 , solar declination δ, and local latitude Φ:

[0060] a t =arcsin[sin(Φ)·sin(δ)-cos(Φ)·cos(δ)·cos(π·t 太阳 / 12)]. (Equation 4) Standard time t s The solar azimuth at a s The solar time t can be calculated using, for example, the following equation 太阳 , solar declination δ, and local latitude Φ:

[0061] a s =arctan[-cos(δ)·sin(π·t 太阳 / 12) / C], (Equation 5)

[0062] Where C=-[cos(φ)·sin(δ)+sin(φ)·cos(δ)·cos(π·t 太阳 / 12)].

[0063] The system controller and / or drive unit 230 of the blind system 210 may be configured to determine whether the sun is in a position such that the sun is directly incident on the facade 310 by calculating a measure of the sun's position. For example, the system controller and / or drive unit 230 of the blind system 210 may be configured to determine whether the sun is in a position such that the sun is directly incident on the facade 310 by calculating a measure of the sun's position. p To determine whether the sun is directly shining on the facade 310. The sun's profile angle a p The solar altitude angle a of the sun can be used t and the solar azimuth a s and the elevation angle a of the facade 310 where the window 300 is located e (e.g., elevation angle). e It can be the angle between the line 440 normal to the facade 310 and the line 430 pointing to the south. p The apparent height of the sun relative to the facade 310 can be defined. p It may be the angle between the line 440 normal to the facade 310 and the line 450 which is the projection of the line 410 pointing toward the sun onto a vertical plane passing through the line 440 normal to the facade 310. p The solar altitude angle a can be calculated using, for example, the following equation t and the solar elevation angle a z Function:

[0064] a p =arctan[sin(a t ) / cos(a z )], (Equation 6)

[0065] The solar elevation angle a z is the solar azimuth angle a of the facade 310 s With elevation angle a e The difference (for example, a z =a s -a e ). When the profile angle a p Between 0° and 90°, the sun may be in a position to shine on the facade 310 (e.g., on a sunny day). p When the angle a is less than 0°, the sun may be above the horizon (e.g., before sunrise and / or after sunset). p When it is greater than 90°, the sun may have passed over the top of the building 400.

[0066] In addition, the system controller and / or the driving unit 230 of the blind system 210 may be configured to calculate the solar azimuth angle a of the sun. s To determine whether the sun is directly shining on the facade 310. The solar azimuth angle as The solar time t can be calculated using, for example, Equation 5 as shown above 太阳 , solar declination δ, and local latitude Φ. The system controller and / or drive unit 230 of the blind system 210 may be configured to adjust the elevation angle a of the facade 310 based on the elevation angle a of the facade 310. e To determine the solar azimuth limit a of the facade 310 s1 、a s2 When the solar azimuth angle a s The solar azimuth limit a between the facade 310 s1 、a s2 During this time, the sun may be in a position to shine on facade 310 (eg, on a sunny day).

[0067] The system controller and / or drive unit 230 of the blind system 210 may be configured to calculate a measure of the sun's position on the facade 310 (eg, the profile angle a p and / or solar azimuth a s ) to determine a time when direct sunlight may begin to be incident on the facade 310 during an upcoming day and / or a time when direct sunlight may cease to be incident on the facade 310. The system controller and / or the drive unit 230 of the venetian blind system 210 may be configured to generate a clock event of a clock schedule to tilt the venetian blind system 210 to the side tilt tilt position when the sun is directly shining on the facade 310 during the upcoming day, and to tilt the venetian blind system 210 to the view tilt position when the sun is not directly shining on the facade 310. For example, the system controller and / or the drive unit 230 of the venetian blind system 210 may be configured to determine one or more anti-fade tilt times t during the upcoming day to control the venetian blind system 210 to the side tilt tilt position (e.g., anti-fade tilt times) FF , and one or more view tilting times t for controlling the blind system 210 to the view tilting position 视野 The system controller and / or drive unit 230 of the blind system 210 may be configured to generate a clock event of a clock schedule to tilt the blind system 210 to a privacy tilt position that begins at or shortly after sunset and ends at sunrise. For example, the system controller and / or drive unit 230 of the blind system 210 may be configured to generate a clock event of a clock schedule to tilt the blind system 210 to a privacy tilt position that begins at or shortly after sunset and ends at sunrise. 日落 To determine the privacy tilt position time t for controlling the electric blinds to the privacy tilt position 隐私Additionally, the system controller and / or drive unit 230 of the blind system 210 may be configured to generate clock events of a clock schedule to cause the blind system 210 to tilt to the privacy tilt position between predetermined times that may be preconfigured by a user of the blind system 210. For example, a user may override one or more preconfigured tilt positions of the blind system 210 (e.g., tilt positions based on sunlight measurements).

[0068] The system controller and / or the drive unit 230 of the blind system 210 may be configured to determine, during a configuration procedure of the blind system 210, the elevation angle a of the facade 310 on which the blind system 210 is installed. e During the configuration procedure, the blind system 210 may be associated with one of four different cardinal directions (e.g., north, east, south, and west) or four different sequential directions (e.g., northeast, southeast, southwest, and northwest). For example, the blind system 210 may be associated with the actual elevation angle a that is closest to the facade 310 in the eight different cardinal or sequential directions. e The elevation angle a of the facade 310 is e The electronic compass of the mobile device (eg, network device 144) may be used to estimate the value during the configuration process, as will be described below with reference to Figure 6 Describe in more detail.

[0069] Because the blind system 210 can be associated with (e.g., only associated with) one of eight different cardinal or ordinal directions, the system controller and / or drive unit 230 of the blind system 210 can take into account the possible elevation angle a of the facade 310 when determining the event times of the clock schedule. e For example, for each of the eight different cardinal or ordinal directions, the elevation angle a of the facade 310 is e The range can be about 45°. Each of the eight different cardinal or sequential directions can be determined by a central elevation angle a e0 and the two end elevation angles a e1 、a e2 To characterize, as shown in Table 1.

[0070] Table 1

[0071]

[0072] The system controller and / or the driving unit 230 of the blind system 210 may call the first end point elevation angle a e1 and the second endpoint elevation angle a e2 And can be based on the first endpoint elevation angle a e1 and the second endpoint elevation angle a e2 Determine the event time of the clock schedule for the upcoming day. Although the example embodiment of Table 1 includes the endpoint elevation angle a e1 、ae2 However, it should be understood that the first endpoint elevation angle a may be selected to be e1 and the second endpoint elevation angle a e2 so that the adjacent cardinal and sequential directions include the first end elevation angle a e1 and the second endpoint elevation angle a e2 There is some overlap in the elevation range between them.

[0073] The system controller may be configured to generate a clock schedule for a plurality of (e.g., all) venetian blind systems (e.g., electric venetian blinds) installed in the building 400. For example, the system controller may be configured to generate a clock schedule (e.g., a separate clock schedule) with different event times depending on which facade of the building 400 each of the plurality of venetian blind systems is located. The system controller may be configured to combine the clock schedules together to generate a system clock schedule for the entire building 400. The system controller may be configured to transmit the separate clock schedules to the venetian blind systems on the respective facades of the building and / or to transmit the system clock schedule to all venetian blind systems in the building. Additionally and / or alternatively, the system controller may be configured to transmit a command for tilting the slats (e.g., based on the separate clock schedule) to each of the venetian blind systems on the respective facades of the building. Furthermore, as previously mentioned, the drive unit of each of the venetian blind systems in the building may be configured to generate a respective separate clock schedule for controlling itself during the upcoming day.

[0074] The system controller and / or the drive unit 230 of the blind system 210 may be configured to associate one of the four different cardinal directions or the four different ordinal directions with a geographic area to determine different event times of a clock schedule. For example, a first facade located at a first set of geographic coordinates (e.g., a global positioning system (GPS)) and facing one of the four different cardinal directions or the four different ordinal directions (e.g., a facade may be associated with it) may determine a time period during which the sun may shine directly on the first facade. The system controller and / or the drive unit 230 of the blind system 210 may generate a clock schedule for each blind system on the first facade and facing the same direction of the four different cardinal directions or the four different ordinal directions.

[0075] Figure 4BAn exemplary system clock schedule 490 for a building located at a particular location for a particular day of the year is shown. The building's blind systems may be located on the north, east, south, and west facades of the building. Event times may be calculated based on the time of direct sunlight striking the different facades. The blinds on the different facades may be controlled to a side tilt position, a view tilt position, and a privacy tilt position at different event times. Each column under a different facade may represent a separate clock schedule that may be transmitted only to the blind systems located on that facade.

[0076] FIG. 5A to FIG. 5F 5 are screen shots 510 through 560 of a configuration application running on a mobile device (eg, network device 144 ) that may be used to configure a motorized blind (eg, blind system 210 ). Figure 6 is used to configure the motorized blinds (e.g. using the operating display FIG. 5A to FIG. 5F 560 ). For example, the configuration procedure 600 may be completed by an installer of electric venetian blinds using a mobile device. The mobile device may be configured to communicate with a system controller (e.g., the system controller 150 of the load control system 100) and / or directly with the electric venetian blinds. The configuration procedure 600 may begin at 610. At 612, the installer may open the configuration application running on the mobile device. At 614, the installer may select a control device (e.g., electric venetian blinds) to configure and / or assign to the load control system and / or other control devices. For example, the installer may Figure 5A A specific control device (e.g., a wood blind) is selected on the configuration application as shown in screen shot 510 in FIG. If an electric blind is selected at 616, the configuration application may prompt the installer to actuate (e.g., press and hold) a button on the motor drive unit of the electric blind at 618, such as Figure 5A 510. In response to actuation of a button on the motorized blind, the system controller may be configured to assign the motorized blind to the load control system and / or another control device (eg, input device) of the load control system.

[0077] At 620, the installer may use a configuration application running on the mobile device to configure the facing direction of the facade where the electric Venetian blind is located (e.g., a line normal to the facade, such as line 430 normal to the facade 310 shown in FIG. 4 ). For example, the configuration application may prompt the installer to orient (e.g., point) the mobile device (e.g., a smartphone) toward the electric Venetian blind being configured, such as Figure 5BThe configuration application may display (e.g., in response to orienting the mobile device toward the electric blinds) an overhead view image 532 of a building (e.g., a house) in which the electric blinds are installed and in which the installer is standing, such as Figure 5C 530 is shown. The configuration application may also display a location indicator 534 (e.g., a small dot) over the image 532 of the building. The location indicator 534 may indicate the location of the installer. The location indicator 534 may be surrounded by a compass indicator 536, which may also be overlaid on the image 532 of the building. The compass indicator 536 may be divided into eight different sections to indicate four different cardinal directions (e.g., north, east, south, and west) and four different sequential directions (e.g., northeast, southeast, southwest, and northwest) from the location of the building. The compass indicator 536 may indicate the direction that the mobile device is facing (e.g., pointing to), as determined by the internal electronic compass of the mobile device. The mobile device may be configured to set the orientation of the electric blinds in response to the direction indicated by the electronic compass.

[0078] Because the electronic compass of the mobile device may not be accurate (e.g., particularly when located inside a building), the installer may be able to actuate one of the segments of the compass indicator 536 to indicate the actual direction the mobile device is facing. For example, the installer may press one of the segments of the compass indicator 536 to select the direction corresponding to the segment. The mobile device may update the orientation of the electric blinds in response to the selected segment of the compass indicator 536. The orientation of the electric blinds (e.g., the facing direction of the facade) may be stored in the mobile device and / or the system controller for use in controlling (e.g., automatically controlling) the electric blinds.

[0079] At 622, the installer may use the configuration application to assign the location (eg, room) of the motorized blinds being configured, such as Figure 5D As shown in the screenshot 540 of FIG. At 624, the installer can use the configuration application to enter the name of the electric blinds being configured, such as Figure 5E If there are more control devices to configure at 626, the installer can select the "Add Another Device" button on the configuration application, such as Fig. 5F, and the configuration program 600 may loop to allow another control device to be selected for configuration at 614. When a control device other than a motorized blind (e.g., a dimmer switch, an electronic switch, a temperature control device, a remote control device, an occupancy sensor, a daylight sensor, etc.) is selected at 616, the installer may configure the other control device in an appropriate manner at 628. For example, the installer may actuate a button on the other control device to assign the control device to a load control system (e.g., as in 618), assign a location for the control device (e.g., as in 622), and / or enter a name for the control device (e.g., as in 624). When there are no more control devices to configure at 626, the mobile device and / or system controller may store the configuration data established by the configuration program 600 at 630 and close the configuration application before exiting the configuration program 600.

[0080] Figure 7 7 is a flow chart of an exemplary orientation configuration procedure 700 that may be executed to configure the orientation of a motorized venetian blind (e.g., the venetian blind system 210). For example, the orientation configuration procedure 700 may be executed by a mobile device (e.g., the network device 144) as part of a configuration procedure for the motorized venetian blind (e.g., at 614 of the configuration procedure 600). The orientation configuration procedure 700 may be executed to configure the orientation of all motorized venetian blinds on a single facade (e.g., to configure the facing direction of the facade). At 710, the orientation configuration procedure 700 may be executed by the mobile device. At 712, the mobile device may determine the orientation of the mobile device using an electronic compass of the mobile device. For example, at 712, the mobile device may determine the orientation in degrees from true north. At 714, the mobile device may display an overhead view image of the building in which the mobile device is located, with a compass indicator overlaid on top of the image (e.g., as in FIG. 1 ). Figure 5C ). The overhead view image of the building allows the mobile device to receive a selection of a particular facade of the building, and may allow the user to manually select or correct a direction associated with the facade. If the direction determined at 716 is incorrect, the mobile device may receive an updated direction (e.g., set by the installer via a configuration application) at 718. At 720, the mobile device may determine a compass compensation factor based on the updated direction. For example, the compass compensation factor may be the difference between the updated direction and the direction determined by the electronic compass. The mobile device may use the compass compensation factor when using the electronic compass to determine the direction of the mobile device for other facades of the building. At 722, the mobile device may update the compass indicator on the image of the building to indicate the updated direction.

[0081] When the direction is correct at 716, the mobile device may assign the facade to one of a plurality of predetermined directions based on the measured or corrected compass direction. For example, the predetermined directions may include cardinal directions and ordinal directions, and the mobile device may determine the cardinal direction or ordinal direction that is closest to the determined orientation of the electric blinds (e.g., the facing direction of the facade) at 724. As another example, the predetermined directions may include cardinal directions, ordinal directions, half winds (NNE, ENE, ESE, SSE, SSW, WSW, WNW, and NNW), quarter winds, and / or custom directions. At 726, the mobile device may assign additional blind systems 210 to the facade and assign the same direction of the plurality of predetermined directions to each blind system on the facade. At 728, the mobile device may then store the determined direction in a memory as the orientation of one or the electric blinds on the current facade, and may exit the orientation configuration procedure 700.

[0082] Figure 8 800 is a flow chart of an exemplary orientation configuration procedure 800 that can be executed to configure the orientation of an electric blind (e.g., a blind system 210). For example, the orientation configuration procedure 800 can be executed by a mobile device (e.g., a network device 144) as part of a configuration procedure for the electric blind (e.g., at 614 of the configuration procedure 600). The orientation configuration procedure 800 can be executed to configure the orientation of all electric blinds on a single facade (e.g., to configure the facing direction of the facade). The orientation configuration procedure 800 is similar to the orientation procedure 700 discussed above, and similar descriptions are not repeated herein. At 812, the mobile device can use an electronic compass and / or a global positioning system (GPS) receiver of the mobile device to determine the location and / or direction of the mobile device. For example, at 812, the mobile device can determine the direction in degrees from true north. At 814, the mobile device can record movement from a first point along the facade (e.g., a first corner of the facade) to a second point along the facade (e.g., a second corner of the facade). For example, a mobile device may be transported by a user from a first point along a facade to a second point along the facade. At 816, the direction of the facade may be determined based on the position and / or direction determined by the mobile device before and during the movement of the mobile device on the facade. As discussed above, if the determined direction is incorrect, the mobile device may receive an updated direction at 818, determine a compass compensation factor based on the updated direction at 820, and update the direction of the facade at 822. The mobile device may use the compass compensation factor when using an electronic compass to determine the direction of the mobile device for other facades of the building. Similarly, as discussed above, the orientation configuration program 800 determines the closest one of the predetermined directions at 824, may assign additional blind systems to the facade at 826, and store a direction selected from a plurality of directions for each blind system on the facade.

[0083] Fig. 9 1 is a flow chart of an exemplary clock schedule configuration procedure 900 that may be executed to configure a clock schedule for controlling (e.g., automatically controlling) the tilt position of one or more motorized blinds (e.g., motorized window treatments 116 and / or blind system 210). The clock schedule configuration procedure 900 may be executed by a control device (e.g., system controller 150) of a load control system that includes motorized blinds. For example, the clock schedule configuration procedure 900 may be executed periodically (e.g., once a day) at 910 to configure a clock schedule for the motorized blinds for an upcoming day. At 912, the control device may configure a clock schedule for the motorized blinds starting with the north facade, which motorized blinds may be located on the north facade of a building on which the load control system is installed. If there are blinds located on the current facade (e.g., the north facade) at 914, the control device may configure a clock schedule for the blinds on the current facade at 916. For example, the control device can set the clock schedule event to control the tilt position of the motorized blinds to maximize indirect sunlight entering the space while preventing direct sunlight from entering the space (e.g., as will be described below with reference to Fig.10 and Fig.11 ). If there are no blinds on the current facade at 914, the control device may not configure the clock schedule. If there are more facades on the building at 918, the control device may move to the next facade at 920. At 914, the control device may again determine whether the next facade has blinds. If the next facade has blinds, in the case where there are electric blinds on the next facade at 914, the control device may configure the clock schedule for the next facade at 916. When there are no more facades on the building at 918, the control device may transmit (e.g., wirelessly) the clock schedule to each of the corresponding electric blinds (e.g., corresponding to the corresponding facade) at 920, and then exit the clock schedule configuration program 900. The electric blinds may each store the corresponding clock schedule and execute the corresponding event of the corresponding clock schedule at the preconfigured time on the upcoming day.

[0084] Fig.10is a flow chart of an exemplary facade clock schedule configuration procedure 1000. The exemplary facade clock schedule configuration procedure 1000 may be executed to configure a clock schedule for controlling (e.g., automatically controlling) the tilt position of one or more motorized blinds (e.g., motorized window treatments 116 and / or blind system 210) on a particular facade of a building where the motorized blinds are located. The facade clock schedule configuration procedure 1000 may be executed by a control device (e.g., system controller 150) of a load control system that includes the motorized blinds. The facade clock schedule configuration procedure 1000 may be executed by the motorized blinds for which the clock schedule is being configured. For example, the facade clock schedule configuration procedure 1000 may be executed periodically (e.g., once a day) at 1010 to configure a clock schedule for the motorized blinds for an upcoming day. For example, the facade clock schedule configuration procedure 1000 may be executed at 1010 at a predetermined time. Fig. 9 The clock configuration process 900 is shown as being executed at 916. At 1012, the control device may determine the end elevation angle a of the current facade. e1 、a e2 For example, the control device may call the endpoint elevation angle a from the memory according to one of the cardinal directions or ordinal directions associated with the current elevation. e1 、a e2 (For example, as shown in Table 1 above).

[0085] Next, the control device may, for example, take into account the first end elevation angle a e1 and the second endpoint elevation angle a e2 To determine the event time for controlling the electric blinds on the current facade. For example, at 1014, assuming that the elevation angle a of the current facade e Equal to the first endpoint elevation angle a e1 , the control device can determine the event time for controlling the electric blinds to prevent direct sunlight from shining into the space. At 1016, assuming that the elevation angle a of the current facade e Equal to the second endpoint elevation angle a e2 , the control device can determine the event time for controlling the electric blinds to prevent direct sunlight from shining into the space. e1 and the second endpoint elevation angle a e2 In both cases, the control device may determine at 1014 and 1016 an event time for controlling the electric blind to the side tilt position and / or the field tilt position according to the predicted position of the sun in the upcoming day. For example, at 1014 and 1016, the control device may calculate the event time when the sun is at the first end elevation angle a and the first end elevation angle b respectively. e1 and the second endpoint elevation angle a e2 The lower profile angle a p , then determine the profile angle a pWhether it is between 0° and 90°, determines whether the sun is shining directly on the facade.

[0086] At 1018, the control device can compare the elevation angle α at the first end point. e1 The event time determined (e.g., at 1014) and the elevation angle α at the second endpoint e2 The event time of the final clock schedule is determined by comparing the event time determined at the next (e.g., at 1016). For example, when comparing the event time at which the electric blinds can be controlled to a sideways tilted position (e.g., at the first end elevation angle a e1 Anti-fading tilt time t FF and the elevation angle a at the first end point e2 Anti-fading tilt time t FF ), the control device may select the earlier of the two anti-fading tilt times as the anti-fading tilt time in the final clock schedule. In addition, the control device may subtract the buffer time t from the earlier of the two anti-fading tilt times before storing the fade filter tilt time in the clock schedule. 缓冲 (e.g., three minutes). For example, the stored anti-fading tilt time may include a buffer time. The buffer time t 缓冲 This can help ensure that the sun will not shine directly into the space during the upcoming day. When comparing the event time that the electric blinds can be controlled to the viewing angle tilt position (for example, at the first end elevation angle a e1 The visual field tilt time t FF and the elevation angle a at the first end point e2 The visual field tilt time t FF ), the control device may select the later of the two visual field tilt times as the visual field tilt time in the final clock schedule. In addition, the control device may store the visual field tilt time in the clock schedule before storing the buffer time t 缓冲 (e.g., three minutes) is added to the later of the two view tilt times. For example, the stored view tilt time may include a buffer time. e1 and the second endpoint elevation angle a e2 If there are two fade filter tilt times and / or two field of view tilt times in each event time determined below, the control device can compare the event times at the corresponding clock events to determine which event times to use in the final clock schedule.

[0087] At 1020, the control device may determine an event time (eg, privacy tilt time t ) at which the motorized blind may be controlled to the privacy tilt position. 隐私 ). Privacy tilt time t 隐私 Can be based on the sunset time of the upcoming day 日落 For example, the control device sets the privacy tilt time t隐私 Set to sunset time t 日落 After the offset time t 偏移 (e.g., 30 minutes). At 1022, the control device may calculate the time of sunrise of the upcoming day based on the time of sunrise t 日出 To determine the event time at which the electric blind can be controlled to leave the privacy tilt position. For example, if the first anti-fading tilt time t FF1 For the current facade (for example, the facade faces east and the sun can directly shine on the facade at sunrise) it is equal to the sunrise time t 日出 , then the control device does not need to be at sunrise time t 日出 Create another clock event at t to cause the electric blinds to move from the privacy position (for example, the electric blinds will move at sunrise time t 日出 However, if the first anti-fading tilt time t FF1 For the current facade (for example, the sun may not be shining directly on the facade at sunrise) it is equal to the sunrise time t 日出 , the control device can determine the time for sunrise at t 日出 Event time to control the motorized blinds to the viewing angle tilt position.

[0088] At 1024, the control device may generate a clock schedule for controlling the electric blinds on the current facade to the side tilt position, the view tilt position, and the privacy tilt position at the determined event times (e.g., as determined at 1018 and 1020) for the upcoming day. For example, the control device may generate a clock schedule for controlling the electric blinds to the side tilt position, the view tilt position, and the privacy tilt position at one or more determined anti-fading tilt times t FF A clock event for controlling the electric blind to a side tilt position at one or more determined viewing angle tilt times t 视野 A clock event at which the electric blind is controlled to a viewing tilt position and / or at a privacy time t 隐私 A clock event that controls the electric blind to the privacy tilt position (e.g., Figure 4B ). At 1026, the control device may store the clock schedule for the motorized blinds on the current facade (e.g., a separate clock schedule), and then exit the facade clock schedule configuration procedure 1000. The facade clock schedule configuration procedure 1000 may be repeated (e.g., continuously) for one or more other facades of the building that include motorized blinds. Alternatively, the facade clock schedule configuration procedure 1000 for the building facade may be performed simultaneously for each facade of the building.

[0089] Fig.11is a flow chart of another exemplary facade clock schedule configuration procedure 1100. The exemplary facade clock schedule configuration procedure 1100 may be executed to configure a clock schedule for controlling (e.g., automatically controlling) the tilt position of one or more motorized blinds (e.g., motorized window treatments 116 and / or blind system 210) on a particular facade of a building where the motorized blinds are located. The facade clock schedule configuration procedure 1100 may be executed by a control device (e.g., system controller 150) of a load control system that includes the motorized blinds. The facade clock schedule configuration procedure 1100 may also be executed by the motorized blinds for which a clock schedule is being configured, e.g., when the motorized blinds are configured to execute a clock. For example, the facade clock schedule configuration procedure 1100 may be executed periodically (e.g., once a day) at 1110 to configure a clock schedule for the motorized blinds for an upcoming day. For example, the facade clock schedule configuration procedure 1100 may be executed, e.g., at 1110. Figure 8 The clock configuration procedure 800 is shown as being executed at 816 .

[0090] At 1112, the control device can adjust the elevation angle a of the facade based on the elevation angle a of the facade. e Determine the solar azimuth limit a of the facade 310 s1 、a s2 To set the solar azimuth range. The control device can be based on the total elevation angle a 总 (e.g., approximately 180°) to set the solar azimuth limit a s1 、a s2 For example, the first solar azimuth limit a s1 Can be set equal to the first endpoint elevation angle a e1 Subtract the total elevation angle a 总 half (e.g., a s1 =a e1 –[a 总 / 2]), and the second solar azimuth limit a s2 Can be set equal to the second endpoint elevation angle a e2 Add the total elevation angle a 总 half (e.g., a s2 =a e2 +[a 总 / 2]). The control device may call the endpoint elevation angle a from the memory according to one of the cardinal directions or sequential directions associated with the current elevation. e1 、a e2 (For example, as shown in Table 1 above). In addition, the buffer angle a 缓冲 (e.g., approximately 5°) may be added to the solar azimuth limit a s1 、a s2 (For example, a s1 =a e1 –[a总 / 2]–a 缓冲 , a s2 =a e2 +[a 总 / 2]+a 缓冲 ).

[0091] At 1114, the control device may determine an event time for controlling the electric blinds on the current facade to block direct sunlight from shining into the space. The control device may determine an event time for controlling the electric blinds to a side tilt position and / or a view tilt position based on the predicted position of the sun throughout the upcoming day. For example, at 1114, the control device may calculate the sun's solar azimuth angle a s , then determine the profile angle a p Is the solar azimuth limit a on the facade? s1 、a s2 to determine whether the sun is directly shining on the facade.

[0092] At 1116, the control device may determine an event time at which the motorized blind may be controlled to the privacy tilt position (eg, privacy tilt time t 隐私 ). Privacy tilt time t 隐私 Can be based on the sunset time of the upcoming day 日落 For example, the control device sets the privacy tilt time t 隐私 Set to sunset time t 日落 After the offset time t 偏移 (e.g., 30 minutes).

[0093] At 1118, the control device may determine the sunrise time t of the upcoming day based on the sunrise time t 日出 To determine the event time at which the electric blind can be controlled to leave the privacy tilt position. For example, if the first anti-fading tilt time t FF1 For the current facade (for example, the facade faces east and the sun can directly shine on the facade at sunrise) it is equal to the sunrise time t 日出 , then the control device does not need to be at sunrise time t 日出 Create another clock event at t to cause the electric blinds to move from the privacy position (for example, the electric blinds will move at sunrise time t 日出 However, if the first anti-fading tilt time t FF1 For the current facade (for example, the sun may not be shining directly on the facade at sunrise) it is equal to the sunrise time t 日出 , the control device can determine the time for sunrise at t 日出 Event time to control the motorized blinds to the viewing angle tilt position.

[0094] At 1120, the control device may generate a clock schedule for controlling the electric blinds on the current facade to the side tilt position, the view tilt position, and the privacy tilt position at the determined event times (e.g., as determined at 1114 and 1116) for the upcoming day. For example, the control device may generate a clock schedule for controlling the electric blinds to the side tilt position, the view tilt position, and the privacy tilt position at one or more determined anti-fading tilt times t FF A clock event for controlling the electric blind to a side tilt position at one or more determined viewing angle tilt times t 视野 A clock event at which the electric blind is controlled to a viewing tilt position and / or at a privacy time t 隐私 A clock event that controls the electric blind to the privacy tilt position (e.g., Figure 4B shown).

[0095] At 1122, the control device may store the clock schedule for the motorized blinds on the current facade (e.g., a separate clock schedule) and then exit the facade clock schedule configuration procedure 1100. The facade clock schedule configuration procedure 1100 may be repeated (e.g., continuously) for one or more other facades of the building that include motorized blinds. Alternatively, the facade clock schedule configuration procedure 1100 for the building facade may be performed simultaneously for each facade of the building.

[0096] Fig.12 1 is a flow chart of an exemplary clock event configuration procedure 1200 that may be executed to configure event times for a clock schedule for controlling (e.g., automatically controlling) a tilt position of one or more motorized venetian blinds (e.g., motorized window treatments 116 and / or a venetian blind system 210). The clock event configuration procedure 1200 may be executed by a control device (e.g., system controller 150) of a load control system that includes the motorized venetian blinds. The clock event configuration procedure 1200 may be executed by the motorized venetian blinds for which a clock schedule is being configured. For example, the clock event configuration procedure 1200 may be executed at 1210 to configure a clock event for a clock schedule of the motorized venetian blinds for an upcoming day. The clock event configuration procedure 1200 may, for example, be executed at 1210 to configure a clock event for a clock schedule of the motorized venetian blinds for an upcoming day. Fig.10 1014 and 1016 of the facade clock schedule configuration procedure 1000 and / or Fig.11 The facade clock schedule configuration procedure 1100 is shown as being executed at 1114.

[0097] During the facade clock event configuration procedure 1200, the control device may step through each minute of the day and calculate a measure of the sun's position each minute (e.g., the sun's profile angle a). p and / or solar azimuth a s) to determine whether the electric blind should be controlled to a side tilt position and / or a view tilt position. At 1212, the control device may determine a solar position measurement (e.g., a solar profile angle a) of the sun at the current facade at the current time t. p and / or solar azimuth a s ). For example, at 1212, the control device may execute Fig.10 The facade clock schedule configuration program 1000 shown calculates the sun's profile angle α p , and can be executed Fig.11 The facade clock schedule configuration program 1100 shown calculates the solar azimuth angle a of the sun s When the clock event configuration procedure 1200 begins, the current time t may be initialized to zero (eg, midnight). For example, the control device may calculate the profile angle a at 1212 using equations 1 to 6 shown above. p and / or solar azimuth a s The control device can calculate the profile angle a according to the longitude λ and latitude Φ of the building in which the electric blind can be installed. p and / or solar azimuth a s The control device can calculate the elevation angle a of the current facade e The clock event configuration procedure 1200 may be executed multiple times, wherein the elevation angle a e Set to the first endpoint elevation angle a e1 and the second endpoint elevation angle a e2 (For example, as shown at 1014 and 1016 of the facade clock schedule configuration procedure 1000). The standard time t of equations 1 to 6 is s Can be set to the current time t.

[0098] At 1214, the control device may determine whether the current time t is at sunrise on the upcoming day. The control device may calculate the elevation angle a pointing to due east. e (For example, for an elevation angle of -90° e )'s profile angle a p-东 To determine that the current time t is at sunrise. If the elevation angle a pointing to the east e The profile angle a p-东 If the current time t is just above 0° (e.g., indicating that the sun may have just passed the horizon and is incident on the facade), the control device may conclude that the current time t is at sunrise. If the current time t is at sunrise at 1214, the control device may set the sunrise time t to 1216. 日出 Set equal to the current time t.

[0099] At 1218, the control device may determine whether the determined solar position measurement indicates that the sun has just left the current facade (e.g., stopped shining directly on the facade) at the current time t. For example, the control device may determine whether the calculated silhouette angle a at the previous time p The profile angle a calculated at the current time t is in the range of 0° to 90° p Now it is determined that the sun has just left the current facade at the current time t outside the range of 0° to 90°. In addition, the control device can determine whether the sun azimuth angle a calculated at the previous time is s At the azimuth limit a s1 、a s2 The solar azimuth angle a is calculated at the current time t. s Now at the azimuth limit a s1 、a s2 The control device determines at 1218 that the sun has just left the current facade at the current time t and at 1220 the first field of view tilt time t is outside the range between t and t. The previous time may be one minute before the current time. The previous time may be represented as t-1. 视野1 does not exist, the control device may tilt the first field of view by a time t at 1222. 视野1 Set to the current time t. If at 1220 the first field of view is tilted at time t 视野1 If it already exists, the control device may tilt the second field of view by time t at 1224. 视野2 Set to the current time t.

[0100] If the control device determines at 1218 that the sun has not just left (e.g., sunlight is still incident on) the current facade, the control device may determine at 1226 whether the determined position measurement of the sun indicates that the sun has just come upon the current facade (e.g., recently incident on and / or began to shine directly on the facade) at the current time t. For example, the control device may determine whether the calculated silhouette angle a at the previous time p The calculated profile angle a is outside the range of 0° to 90° and at the current time t p Now it is determined that the sun has just come to the current facade at the current time t within the range of 0° to 90°. In addition, the control device can determine whether the sun azimuth angle a calculated at the previous time is s At the azimuth limit a s1 、a s2 The solar azimuth angle a is calculated at the current time t. s Now at the azimuth limit a s1 、a s2The control device can determine the first anti-fading time t FF1 Is it defined (eg, already exists). If the control device determines at 1226 that the sun has just come onto the current facade at the current time t and at 1228 the first anti-fading tilt time t FF1 If it does not exist yet, the control device may adjust the first anti-fading tilt time t at 1230 FF1 Set to current time t. If the first anti-fading tilt time t at 1228 FF1 If it already exists, the control device can adjust the second anti-fading tilt time t at 1230 FF2 Set to the current time t.

[0101] At 1234, the control device may determine whether the current time t is at sunset on the upcoming day. The control device may calculate the elevation angle a pointing to due west. e (For example, for an elevation angle of 90° e )'s profile angle a p-西 To determine that the current time t is at sunset. If the elevation angle a pointing due west e The profile angle a p-西 If the current time t is just less than 0° (e.g., indicating that the sun may have just passed the horizon and is no longer incident on the facade), the control device may conclude that the current time t is at sunset. If the current time t is at sunset at 1234, the control device may calculate the sunrise time t at 1236. 日落 is set equal to the current time t. If the current time t is not equal to the end of the upcoming day (e.g., midnight) at 1238, then at 1240, the control device may increase the current time t by the step value t 步长 (e.g., one minute), and at 1212, the clock event configuration program 1200 may loop to calculate the sun's silhouette angle α at the updated current time t. p When the current time t equals the end of the upcoming day at 1238, the clock event configuration presentation 1200 may exit.

[0102] Fig.13is a flow chart of an exemplary facade clock schedule configuration procedure 1300. The exemplary facade clock schedule configuration procedure 1300 may be executed to configure a clock schedule for controlling (e.g., automatically controlling) the tilt position of one or more motorized blinds (e.g., motorized window treatments 116 and / or blind system 210) on a particular facade of a building where the motorized blinds are located. The facade clock schedule configuration procedure 1300 may be executed by a control device (e.g., system controller 150 and / or mobile device 114) of a load control system that includes the motorized blinds. The facade clock schedule configuration procedure 1300 may also be executed by the motorized blinds for which a clock schedule is being configured, such as when the motorized blinds are configured to execute a clock. For example, the facade clock schedule configuration procedure 1300 may be executed periodically (e.g., once a day, once a week, once a month, once a year, etc.) at 1310 to configure a clock schedule for the motorized blinds for an upcoming day. For example, the facade clock schedule configuration procedure 1300 may be executed, such as at Figure 8 The clock configuration procedure 800 is shown as being executed at 816 .

[0103] At 1312, the control device may associate the current facade with one of a set of predetermined directions. For example, the control device may associate the current facade with one of a cardinal direction or a sequential direction, one of a cardinal direction, a sequential direction, or a half-wind direction, one of a cardinal direction, a sequential direction, a half-wind direction, or a quarter-wind direction, one of a user-defined set of directions, and the like. At 1314, the control device may select a set of predetermined event times for controlling the motorized blinds on the current facade, for example, based on a set of predetermined event times for associated directions in the set of predetermined directions. For example, the control device may include a set of predetermined events for each of the potential directions of the facade. The set of predetermined events may be calculated using any suitable method, such as, for example, as described above with respect to Fig.10 The set of predetermined clock events may include a timer for performing a predetermined timer at one or more determined anti-fading tilt times t FF A clock event for controlling the electric blind to a side tilt position at one or more determined viewing angle tilt times t 视野 A clock event for controlling the electric blind to a viewing tilt position at a certain time and / or for controlling the electric blind to a viewing tilt position at a certain time during the privacy time t 隐私 A clock event that controls the electric blind to the privacy tilt position (e.g., Figure 4B shown).

[0104] The set of predetermined event times may include an event time at which the electric blind may be controlled to a privacy tilt position (eg, a privacy tilt time t 隐私 ). Privacy tilt time t 隐私 Can be based on the sunset time of the upcoming day日落 For example, the control device sets the privacy tilt time t 隐私 Set to sunset time t 日落 After the offset time t 偏移 (e.g., 30 minutes). Similarly, the set of scheduled event times may be based on the sunrise time t 日出 To determine the event time at which the electric blind can be controlled to leave the privacy tilt position. For example, if the first anti-fading tilt time t FF1 For the current facade (for example, the facade faces east and the sun may shine directly on the facade at sunrise) it is equal to the sunrise time t 日出 , then the scheduled event time of the group does not need to be at sunrise time t 日出 The additional clock event is included to cause the motorized blinds to move from the privacy position (eg, the motorized blinds will move at sunrise time t 日出 However, if the first anti-fading tilt time t FF1 For the current facade (for example, the sun may not be shining directly on the facade at sunrise) it is equal to the sunrise time t 日出 , the set of predetermined events may include a time for sunrise at t 日出 Event time to control the motorized blinds to the viewing angle tilt position.

[0105] At 1316, the control device may generate one or more custom events to be included in the set of predetermined events obtained at 1312. For example, the user may set additional t 隐私 For converting the blind system to a privacy tilt angle. Similarly, the user can remove one or more events, such as the anti-fading tilt time t FF , to maintain the blind system 210 in a previous configuration (eg, a view tilt position or a privacy tilt position). At 1316, the user may set one or more custom settings for one or more tilt positions, such as a custom anti-fade tilt percentage greater than or less than 25%.

[0106] At 1318, the control device may store the clock schedule for the motorized blinds on the current facade (e.g., a separate clock schedule) and then exit the facade clock schedule configuration procedure 1300. The facade clock schedule configuration procedure 1300 may be repeated (e.g., continuously) for one or more other facades of the building that include motorized blinds. Alternatively, the facade clock schedule configuration procedure 1300 for the building facade may be performed simultaneously for each facade of the building.

[0107] Fig.1414 is a flow chart of an exemplary clock schedule execution 1400 for a control device including a control source device. At 1412, the control device or the venetian blind system detects a time that matches an event time contained in the facade clock schedule. The event may include a transition to an anti-fading tilted position, a view tilted position, or a privacy tilted position. At 1414, the control device determines whether the event is a transition to an anti-fading tilted position. If the event is not a transition to an anti-fading tilted position, the control device executes the event and, at 1418, transitions the venetian blind system 210 to the tilted position indicated by the event in the clock schedule.

[0108] If the event is a transition to the anti-fading tilted position, then at 1416, the control device determines whether a transition to the anti-fading tilted position is necessary. For example, the control device may receive a signal from a control source device (such as control source device 1400 described in more detail below). The control source device may include a sensor configured to detect one or more environmental parameters indicating whether a transition to the anti-fading tilted position is necessary, such as, for example, an occupancy sensor, a sunlight sensor, a window sensor, etc. For example, if the control source device is configured to detect direct sunlight (e.g., a daylight sensor, etc.), the control source device may prevent the transition to the anti-fading tilted position when a minimum amount of sunlight (e.g., no sunlight) is detected. As another example, the control device may receive weather data for a geographic area that includes the facade. If the weather stream indicates that there is no direct sunlight, such as, for example, cloudy, rainy, etc., the control device may not transition to the anti-fading tilted position (because there is no direct sunlight on the facade).

[0109] Fig.151 is a block diagram illustrating an exemplary computing device 1500. As described herein, the computing device may include a network device or a server device (e.g., an authorization server, a resource server, and / or a third-party server). The computing device 1500 may include a control circuit 1502 for controlling the functions of the computing device 1500. The control circuit 1502 may include one or more general-purpose processors, special-purpose processors, conventional processors, digital signal processors (DSPs), microprocessors, integrated circuits, programmable logic devices (PLDs), application-specific integrated circuits (ASICs), etc. The control circuit 1502 may perform signal encoding, data processing, power control, input / output processing, or any other function that enables the computing device 1500 to perform as described herein. The control circuit 1502 may store information in and / or retrieve information from the memory 1504. The memory 1504 may include non-removable memory and / or removable memory. The non-removable memory may include a random access memory (RAM), a read-only memory (ROM), a hard disk, or any other type of non-removable memory. The removable memory may include a Subscriber Identity Module (SIM) card, a memory stick, a memory card, or any other type of removable memory.

[0110] The computing device 1500 may include a communication circuit 1508 for transmitting and / or receiving information. The communication circuit 1508 may perform wireless and / or wired communication. The communication circuit 1508 may include an RF transceiver or other circuitry capable of performing wireless communication via an antenna. The communication circuit 1508 may communicate with the control circuit 1502 for transmitting and / or receiving information.

[0111] The control circuit 1502 may communicate with an output device 1506, such as a visual output device (e.g., a display) and / or an auditory output device (e.g., a speaker), for providing information to a user. The control circuit 1502 and / or the output device 1506 may generate a user interface, such as a graphical user interface (GUI), for display on the computing device 1500. The output device 1506 and the control circuit 1502 may be in two-way communication, as the display 1506 may include a touch screen module capable of receiving user input and providing such user input to the control circuit 1502. The computing device 1500 may include an actuator 1512 (e.g., one or more buttons) that may be actuated by a user to communicate a user selection to the control circuit 1502.

[0112] Each of the modules within computing device 1500 may be powered by power supply 1510. Power supply 1510 may include, for example, an AC power supply or a DC power supply. Power supply 1510 may generate a supply voltage V CC To provide power to modules within the computing device 1500 .

[0113] Fig.16 1 is a block diagram illustrating an exemplary system controller 1600, such as the system controller 150 described herein. The system controller 1600 may include a control circuit 1602 for controlling the functions of the system controller 1600. The control circuit 1602 may include one or more general purpose processors, special purpose processors, conventional processors, digital signal processors (DSPs), microprocessors, integrated circuits, programmable logic devices (PLDs), application specific integrated circuits (ASICs), etc. The control circuit 1602 may perform signal encoding, data processing, power control, input / output processing, or any other function that enables the system controller 1600 to perform as described herein. The control circuit 1602 may be configured to execute a clock. The control circuit 1602 may store information in and / or retrieve information from a memory 1604. The memory 1604 may include non-removable memory and / or removable memory. The non-removable memory may include a random access memory (RAM), a read-only memory (ROM), a hard disk, or any other type of non-removable memory. The removable memory may include a subscriber identity module (SIM) card, a memory stick, a memory card, or any other type of removable memory. The memory 1604 may be configured to store a clock schedule defining event times and associated commands for controlling a control target device.

[0114] The system controller 1600 may include a communication circuit 1606 for transmitting and / or receiving information. The communication circuit 1606 may perform wireless and / or wired communication. The system controller 1600 may also or alternatively include a communication circuit 1608 for transmitting and / or receiving information. The communication circuit 1606 may perform wireless and / or wired communication. The communication circuits 1606 and 1608 may communicate with the control circuit 1602. The control circuit 1602 may be configured to transmit a message including a command for controlling a control target device via the communication circuit 1606. The control circuit 1602 may be configured to transmit a message including a command for controlling a control target device at an event time of a clock schedule. The communication circuits 1606 and 1608 may include an RF transceiver or other communication module capable of performing wireless communication via an antenna. The communication circuit 1606 and the communication circuit 1608 may be capable of performing communication via the same communication channel or different communication channels. For example, communication circuit 1606 may be capable of communicating via a first wireless communication link, such as with a network device over a network, etc., and communication circuit 1608 may be capable of communicating via a second wireless communication link, such as with a control device and / or other devices in a load control system.

[0115] The control circuit 1602 may communicate with an LED indicator 1612 to provide an indication to the user. The control circuit 1602 may communicate with an actuator 1614 (e.g., one or more buttons) that may be actuated by the user to communicate the user selection to the control circuit 1602. For example, the actuator 1614 may be actuated to place the control circuit 1602 in an association mode and / or to communicate an association message from the system controller 1600.

[0116] Each of the modules within the system controller 1600 may be powered by a power supply 1610. The power supply 1610 may include, for example, an AC power supply or a DC power supply. The power supply 1610 may generate a supply voltage V CC To provide power to the modules in the system controller 1600.

[0117] Fig.17 1700 is a block diagram illustrating an exemplary control target device (e.g., load control device 1700) as described herein. Load control device 1700 may be a dimmer switch, an electronic switch, an electronic ballast for a lamp, an LED driver for an LED light source, an AC plug-in load control device, a temperature control device (e.g., a thermostat), a motor drive unit for electric window treatments, or other load control devices. Load control device 1700 may include communication circuit 1702. Communication circuit 1702 may include a receiver, an RF transceiver, or other communication module capable of performing wired and / or wireless communication via communication link 1710. Communication circuit 1702 may communicate with control circuit 1704. Control circuit 1704 may include one or more general-purpose processors, special-purpose processors, conventional processors, digital signal processors (DSPs), microprocessors, integrated circuits, programmable logic devices (PLDs), application-specific integrated circuits (ASICs), etc. Control circuit 1704 may perform signal encoding, data processing, power control, input / output processing, or any other function that enables load control device 1700 to perform as described herein.

[0118] The control circuit 1704 may store information in and / or retrieve information from the memory 1706. For example, the memory 1706 may maintain a registry of associated control devices and / or control instructions. The memory 1706 may include non-removable memory and / or removable memory. The load control circuit 1708 may receive instructions from the control circuit 1704 and may control the electrical load 1716 based on the received instructions. The load control circuit 1708 may send state feedback about the state of the electrical load 1716 to the control circuit 1704. The load control circuit 1708 may receive power via the hot connection 1712 and the neutral connection 1714, and may provide a certain amount of power to the electrical load 1716. The electrical load 1716 may include any type of electrical load.

[0119] The control circuit 1704 can communicate with an actuator 1718 (e.g., one or more buttons) that can be actuated by a user to communicate a user selection to the control circuit 1704. For example, the actuator 1718 can be actuated to place the control circuit 1704 in an association mode and / or to communicate an association message from the load control device 1700.

[0120] Fig.18 1 is a block diagram illustrating an exemplary control source device 1800 as described herein. The control source device 1800 may be a remote control device, an occupancy sensor, a daylight sensor, a window sensor, a temperature sensor, etc. The control source device 1800 may include a control circuit 1802 for controlling the functions of the control source device 1800. The control circuit 1802 may include one or more general purpose processors, special purpose processors, conventional processors, digital signal processors (DSPs), microprocessors, integrated circuits, programmable logic devices (PLDs), application specific integrated circuits (ASICs), etc. The control circuit 1802 may perform signal encoding, data processing, power control, input / output processing, or any other function that enables the control source device 1800 to perform as described herein.

[0121] The control circuit 1802 may communicate with an actuator 1814 (e.g., one or more buttons) that may be actuated by a user to communicate a user selection to the control circuit 1802. For example, the actuator 1814 may be actuated to place the control circuit 1802 in an association mode and / or to communicate an association message from the control source device 1800. The control circuit 1802 may store information in and / or retrieve information from the memory 1804. The memory 1804 may include non-removable memory and / or removable memory, as described herein.

[0122] The control source device 1800 may include a communication circuit 1808 for transmitting and / or receiving information. The communication circuit 1808 may transmit and / or receive information via wired and / or wireless communication. The communication circuit 1808 may include a transmitter, an RF transceiver, or other circuitry capable of performing wired and / or wireless communication. The communication circuit 1808 may communicate with the control circuit 1802 for transmitting and / or receiving information.

[0123] The control circuit 1802 may communicate with the input circuit 1806. The input circuit 1806 may include an actuator (e.g., one or more buttons) or a sensor circuit (e.g., an occupancy sensor circuit, a daylight sensor circuit, or a temperature sensor circuit) for receiving inputs that may be sent to a device for controlling an electrical load. For example, the control source device may receive inputs from the input circuit 1806 to place the control circuit 1802 in an association mode and / or transmit an association message from the control source device. The control circuit 1802 may receive information from the input circuit 1806 (e.g., an indication that a button has been actuated or information has been sensed). Each of the modules within the control source device 1800 may be powered by a power supply 1810.

[0124] Fig.19 is a simplified block diagram of an exemplary motor drive unit 1900 (e.g., a motor drive unit of the motorized window treatment 116 and / or a drive unit 230 of the blind system 210) according to some embodiments. The motor drive unit 1900 may include a motor 1902 (e.g., a DC motor) that may be operated to raise and lower a covering material and / or tilt a slat (e.g., slat 212) to control the amount of daylight entering a space. The motor 1902 may be controlled by a pulse width modulation (PWM) signal, and the speed of the motor may be adjusted by adjusting the duty cycle of the PWM signal applied to the DC motor 1902. For example, the motor 1902 may be operably coupled to raise and lower a bottom bar and / or tilt a slat of a motorized blind (e.g., bottom bar 216 and / or slat 212 of the blind system 210). Changing the magnitude of the DC voltage applied to the motor 1902 or the duty cycle of the PWM signal may change the rotational speed of the motor. Furthermore, the motor 1902 may be configured to change direction of rotation in response to a change in polarity of a DC voltage or PWM signal applied to the motor 1902 .

[0125] To achieve this level of control over the motor 1902, the motor 1902 may be coupled to an H-bridge motor drive circuit 1904 that may be driven by the control circuit 1906. The H-bridge motor drive circuit 1904 may include four transistors, such as, for example, four field effect transistors (not shown). The transistors may be coupled so that when two of the transistors are turned on, a positive DC voltage is applied to the motor 1902 to cause the motor to rotate in a forward direction. When the other two transistors of the H-bridge circuit 1904 are turned on, a negative DC voltage may be applied to the motor 1902 to cause the motor 1902 to rotate in a reverse direction. To control the speed of the motor 1902, the control circuit 1906 may drive at least one transistor of the H-bridge circuit 1904 with a PWM signal. The control circuit 1906 may include any suitable processing circuit (such as, for example, a microprocessor, such as a complex instruction set computer (CISC) microprocessor, a reduced instruction set computing (RISC) microprocessor, and / or a very long instruction word (VLIW) microprocessor), a programmable logic device (PLD), a microcontroller, an application specific integrated circuit (ASIC), a field programmable gate array (FPGA), a chip multiprocessor (CMP), or any suitable processing device or control circuit. The control circuit 1906 may be configured to execute a clock. The control circuit 1906 may be configured to control the motor 1902 (e.g., tilt the slats) at event times of a clock schedule.

[0126] The motor drive unit 1900 may include a rotational position sensor, such as, for example, a Hall Effect Sensor (HES) circuit 1908, which may be configured to provide information about the rotational speed and direction of the motor 1902 to the control circuit 1906. The rotational position sensor may also include other suitable position sensors, such as, for example, optical sensors and resistive sensors. The control circuit 1906 may be configured to determine the rotational position of the motor 1902 in response to the Hall Effect Sensor circuit 1908. The control circuit 1906 may use the rotational position of the motor 1902 to determine the current position of the covering material (e.g., the covering material 118 such as the electric window treatment 116 and / or the bottom bar 216 of the drive system 210). The control circuit 1906 may be coupled to a non-volatile memory 1910 for storing the current position of the covering material, the fully open position, and the fully closed position. In addition, the memory 1910 may be configured to store a clock schedule including the event times of controlling the motor 1902 (e.g., tilting the slats). The memory 1910 may include an electrically erasable programmable read-only memory (EEPROM), but it will be appreciated that any suitable memory may be used.

[0127] The motor drive unit 1900 may include a communication circuit 1914 that allows the control circuit 1906 to transmit and receive communication signals to and from a keyboard and / or other motor drive units 1900. The motor drive unit 1900 may also include a plurality of buttons 1912 that allow a user to provide input to the control circuit 1906 during setup and configuration of the electric window treatment. The control circuit 1906 may drive the motor 1902 in a first direction at a constant rotational speed when a first button of the plurality of buttons 1912 is pressed and held, and may drive the motor 1902 in a second direction at a constant rotational speed when a second button of the plurality of buttons 1912 is pressed. In addition, the control circuit 1906 may be configured to tilt the slats of the electric blind in a first direction when the first button of the plurality of buttons 1912 is pressed, and tilt the slats of the electric blind in a second direction when the second button of the plurality of buttons 1912 is pressed.

[0128] The control circuit 1906 can be configured to control the movement of the covering material in response to a covering movement command (e.g., from a communication signal received through the communication circuit 1914 or a user input from the button 1912). The covering movement command can consist of a command type (e.g., "move to a desired position" or "tilt to a desired tilted position") and / or a desired position (e.g., the control circuit 1906 can be configured to control the position to which the covering material reaches and / or the position to which the slats of the electric blind are tilted). The desired position can be a preset position, a fully open position, or a fully closed position. In addition, the desired position can be a tilted position of the electric blind.

[0129] The motor drive unit 1900 can be powered by an alternating current (AC) supply voltage V AC (e.g., 24VAC) to receive power. AC supply voltage V AC can be provided to the full-wave rectifier bridge 1920 to generate a bus voltage V 总线 (e.g., 30 VDC), which can be filtered by storage capacitor 1918. The bus voltage V 总线 The power supply 1916 can receive the bus voltage V 总线 And generate DC supply voltage V CC (e.g., 5 VDC) is used to power the low-voltage circuits of the motor drive unit 1900 (e.g., the control circuit 1906, the memory 1910, and the communication circuit 1914).

[0130] Although features and elements are described herein in particular combinations, each feature or element may be used alone or in any combination with other features and elements. The methods described herein may be implemented in a computer program, software, or firmware incorporated into a computer-readable medium for execution by a computer or processor. Examples of computer-readable storage media include, but are not limited to, read-only memory (ROM), random access memory (RAM), removable disks, and optical media such as CD-ROM disks and digital versatile disks (DVDs).

Claims

1. A controller for adjusting the position of slats of a Venetian blind system, the controller include: A control circuit configured to generate a clock schedule to adjust a slat position of a Venetian blind system at each of a plurality of event times, wherein the plurality of event times comprises: a first event time at which direct sunlight is incident on a facade of the building, the first event time corresponding to a first endpoint elevation angle determined using one selected from a cardinal direction of the facade or an ordinal direction of the facade; and a second event time at which direct sunlight is no longer incident on the facade of the building, the second event time corresponding to a second endpoint elevation angle determined using one selected from a cardinal direction of the facade or an ordinal direction of the facade, wherein the first endpoint elevation angle and the second endpoint elevation angle are different; and The control circuit is configured as follows: tilting the slats to a privacy tilt position during which the slats are vertical between a determined sunset time and a determined sunrise time; tilting the slats to a field of view tilt position during which the slats are horizontal between the determined sunrise time and the first event time; Detect the occurrence of an interruption event; In response to not detecting an interruption event, tilting the slats at a first event time to a sideways tilted position during which the slats are tilted at an angle between horizontal and vertical; and The slats are tilted to the field of view tilt position between a second event time and a determined sunset time.

2. The controller of claim 1, wherein the control circuit is further configured to: In response to detecting the interruption event, the slats are maintained in the field of view tilt position at a first event time.

3. The curtain controller according to claim 2, in, In order to detect the occurrence of an interrupt event, the control circuit is further configured as follows: At least one sensor input is received indicating an absence of direct sunlight on the facade.

4. The controller according to claim 2, in, In order to detect the occurrence of an interrupt event, the control circuit is further configured as follows: At least one input signal indicative of a weather condition that prevents direct sunlight from reaching the facade is received.

5. The controller of claim 1, wherein the control circuit is further configured to: Calculate the sun's position relative to the facade's orientation; The plurality of event times are determined based on the orientation of the facade using the calculated position of the sun, the geographic location of the building, and the first endpoint elevation angle and the second endpoint elevation angle.

6. The controller of claim 1, wherein the control circuit is further configured to: The determined plurality of event times are stored as a clock time table in an operatively coupled memory circuit.

7. A control method for adjusting the position of slats of a Venetian blind system, the method include: A clock schedule is generated by the control circuit to adjust the slat position of the Venetian blind system at each of a plurality of event times, wherein the plurality of event times comprises: a first event time at which direct sunlight is incident on a facade of the building, the first event time corresponding to a first endpoint elevation angle determined using one selected from a cardinal direction of the facade or an ordinal direction of the facade; and a second event time at which direct sunlight is no longer incident on the facade of the building, the second event time corresponding to a second endpoint elevation angle determined using one selected from a cardinal direction of the facade or an ordinal direction of the facade, wherein the first endpoint elevation angle and the second endpoint elevation angle are different; and tilting the slats to a privacy tilt position, during which the slats are vertical, via a control circuit, between a determined sunset time and a determined sunrise time; tilting the slats by the control circuit between the determined sunrise time and the first event time to a field of view tilt position during which the slats are horizontal; Detect the occurrence of an interruption event; In response to not detecting an interruption event, at a first event time, tilting, by the control circuit, the slats to a sideways tilted position during which the slats are tilted at an angle between horizontal and vertical; and The slats are tilted to the field of view tilt position by the control circuit between the second event time and the determined sunset time.

8. The method according to claim 7, further comprising: include: In response to detecting the interruption event, the slats are maintained in the field of view tilt position by the control circuit at the first event time.

9. The method of claim 8, wherein detecting the occurrence of an interrupt event further comprises: include: At least one sensor input is received by the control circuitry indicating an absence of direct sunlight on the facade.

10. The method of claim 8, wherein detecting the occurrence of an interrupt event further comprises: include: At least one input signal indicative of a weather condition that prevents direct sunlight from striking the facade is received by the control circuit.

11. The method according to claim 7, further comprising: include: The position of the sun relative to the orientation of the facade is calculated by the control circuit; as well as The plurality of event times are determined by the control circuit based on the orientation of the facade using the calculated position of the sun, the geographic location of the building, and the first endpoint elevation angle and the second endpoint elevation angle.

12. The method according to claim 11, further comprising: include: The determined plurality of event times are stored as a clock schedule in an operatively coupled memory circuit by the control circuit.

13. A venetian blind system configured to be installed to cover a window located on a facade of a building, the venetian blind system include: Top rail; Bottom bar; a plurality of slats vertically spaced between the top rail and the bottom rail; a lift cord extending from the top rail to the bottom rail to allow raising and lowering of the bottom rail; a tilting step extending from the top rail to the bottom rail and operable to support and tilt the slats; as well as a drive unit operably coupled to the tilting ladder for tilting the slats; as well as A control circuit configured to generate a clock schedule to adjust a slat position of a Venetian blind system at each of a plurality of event times, wherein the plurality of event times comprises: a first event time at which direct sunlight is incident on a facade of the building, the first event time corresponding to a first endpoint elevation angle determined using one selected from a cardinal direction of the facade or an ordinal direction of the facade; and a second event time at which direct sunlight is no longer incident on the facade of the building, the second event time corresponding to a second endpoint elevation angle determined using one selected from a cardinal direction of the facade or an ordinal direction of the facade, wherein the first endpoint elevation angle and the second endpoint elevation angle are different; and The control circuit is configured as follows: tilting the slats to a privacy tilt position during which the slats are vertical between a determined sunset time and a determined sunrise time; tilting the slats to a field of view tilt position during which the slats are horizontal between the determined sunrise time and the first event time; Detect the occurrence of an interruption event; In response to not detecting an interruption event, tilting the slats to a sideways tilted position at a first event time during which the slats are tilted at an angle between horizontal and vertical; and The slats are tilted to the field of view tilt position between a second event time and a determined sunset time.

14. The venetian blind system of claim 13, wherein the drive unit comprises a motor operably coupled to the tilting step.

15. The blind system of claim 14, further comprising: include: wireless communication circuitry configured to receive wireless signals; Wherein the control circuit is configured to receive a message including a command to tilt the slats via the wireless communication circuit.

16. The blind system of claim 15, further comprising: include: a memory circuit for storing a clock schedule; The control circuit includes a clock for determining the times of the plurality of events of tilting the slats according to a clock schedule.

17. The blind system of claim 16, wherein the control circuit further comprises: A clock schedule is received via the wireless communication circuit.

18. The blind system of claim 15, wherein the control circuit further: Respective commands to tilt the slats are received at a plurality of event times of the clock schedule.

19. The blind system of claim 13, wherein the control circuit is further configured to: The plurality of event times of the clock schedule are determined based on the orientation of the facade according to the calculated position of the sun, the geographic location of the building, and the first and second endpoint elevation angles, and the clock schedule is stored in a memory.

20. The venetian blind system of claim 19, wherein the calculated position of the sun indicates direct sunlight incident on the facade when the sun's profile angle is between 0° and 90°.

21. The venetian blind system of claim 20, wherein the solar profile angle is calculated using a first end elevation angle and a second end elevation angle of the facade.

22. The venetian blind system of claim 19, wherein the calculated position of the sun indicates direct sunlight is incident on the facade when the sun's solar azimuth is between the solar azimuth limits of the facade.

23. The venetian blind system of claim 21, wherein the solar azimuth limit of the facade is based on a first end point elevation angle and a second end point elevation angle of the facade and a total facade angle.

24. A machine-readable medium comprising instructions which, when executed by a window shade control circuit, cause the window shade control circuit to: Generate a clock schedule to adjust the slat position of the Venetian blind system at each of a plurality of event times, wherein the plurality of event times include: a first event time at which direct sunlight is incident on a facade of the building, the first event time corresponding to a first endpoint elevation angle determined using one selected from a cardinal direction of the facade or an ordinal direction of the facade; as well as a second event time at which direct sunlight is no longer incident on the facade of the building, the second event time corresponding to a second endpoint elevation angle determined using one selected from a cardinal direction of the facade or an ordinal direction of the facade, wherein the first endpoint elevation angle and the second endpoint elevation angle are different; and tilting the slats to a privacy tilt position during which the slats are vertical between a determined sunset time and a determined sunrise time; tilting the slats to a field of view tilt position during which the slats are horizontal between the determined sunrise time and the first event time; Detect the occurrence of an interruption event; In response to not detecting an interruption event, tilting the slats at a first event time to a sideways tilted position during which the slats are tilted at an angle between horizontal and vertical; and The slats are tilted to the field of view tilt position between a second event time and a determined sunset time.

25. The machine-readable medium of claim 24, wherein when the instructions are executed, further cause the window shade control circuit to: In response to detecting the interruption event, the slats are maintained in the field of view tilt position at a first event time.

26. The machine-readable medium of claim 25, wherein the instructions that cause the window shade control circuit to detect the occurrence of an interrupt event further cause the window shade control circuit to: At least one sensor input is received indicating an absence of direct sunlight on the facade.

27. The machine-readable medium of claim 25, wherein the instructions that cause the window shade control circuit to detect the occurrence of an interrupt event further cause the window shade control circuit to: At least one input signal indicative of a weather condition that prevents direct sunlight from striking the facade is received.

28. The machine-readable medium of claim 25, wherein when the instructions are executed, further cause the window shade control circuit to: Calculate the position of the sun relative to the orientation of the facade; and The plurality of event times are determined based on the orientation of the facade using the calculated position of the sun, the geographic location of the building, and the first endpoint elevation angle and the second endpoint elevation angle.

29. The machine-readable medium of claim 28, wherein when the instructions are executed, further cause the window shade control circuit to: The determined plurality of event times are stored as a clock time table in an operatively coupled memory circuit.