Rock and soil construction investigation management platform and method based on aerial photography of unmanned aerial vehicle
The geotechnical construction survey and management platform, which utilizes drone aerial photography, enables global image acquisition and risk assessment of the construction area, solving the problem of unmanageable construction cracks and improving construction safety and efficiency.
Patent Information
- Application Number
- CN202411052278.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-02
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2044-08-02
AI Technical Summary
During geotechnical construction, the large construction area makes it impossible to fully investigate and manage construction cracks, resulting in the inability to effectively assess and manage construction risks and affecting construction safety.
A geotechnical construction investigation and management platform based on drone aerial photography is adopted to dynamically identify risks and conduct safety assessments of the construction area through image acquisition, recognition, and evaluation layers, and to locate unsafe areas.
It enables global image acquisition and risk assessment of the construction area, allowing for timely detection and location of potential construction risks, improving construction safety, reducing the need for manual operations, and achieving energy efficiency.
Smart Images

Figure CN119007041A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of geotechnical construction, and in particular to a geotechnical construction investigation and management platform and method based on unmanned aerial vehicle aerial photography. Background Art
[0002] Geotechnical construction is an important engineering activity. It involves the treatment and transformation of rock and soil to meet the construction needs of various buildings and infrastructure. It includes foundation treatment, foundation pit support, slope reinforcement and other work. Ensuring the stability and safety of the project through drilling, grouting, anchoring and other technical means is a key link in the smooth development of construction projects.
[0003] The invention patent with application number 202010726628.5 discloses a geotechnical engineering survey system, including an information collection terminal, an information processing terminal, an information management terminal and a wireless terminal, wherein the information collection terminal is communicatively connected to the information processing terminal via a wireless terminal, and the information processing terminal is communicatively connected to the information management terminal via a wireless terminal.
[0004] The application aims to solve the problem that "at present, the geotechnical engineering investigation work in my country, except for railways, highways, bridges, etc., is mainly carried out in various urban areas and newly developed blocks. According to relevant national standards and regulations, each building must be investigated in accordance with the current standards. Moreover, the investigation methods recognized by national standards are limited to drilling, static exploration, dynamic exploration, water sampling and testing. This will inevitably lead to the phenomenon of repeated geotechnical engineering investigation in the same geological unit, the same stratigraphic structure, and the same block, which wastes a lot of manpower, material and financial resources."
[0005] However, during the geotechnical construction process, the construction risks caused by construction cracks on the geotechnical construction surface cannot be comprehensively surveyed and managed due to the large size of the geotechnical construction surface. The cracks on the geotechnical construction surface accumulate and deteriorate over a long period of time, triggering a chain reaction, causing safety problems such as collapse and subsidence of the geotechnical construction surface to varying degrees, resulting in the inability to guarantee the work safety of on-site workers during the geotechnical construction process.
[0006] To this end, we proposed a geotechnical construction investigation and management platform and method based on UAV aerial photography. Summary of the invention
[0007] In view of the above-mentioned shortcomings of the prior art, the present invention provides a geotechnical construction investigation and management platform and method based on drone aerial photography, which solves the technical problems raised in the above-mentioned background technology.
[0008] To achieve the above objectives, the present invention is implemented through the following technical solutions:
[0009] In the first aspect, a geotechnical construction survey management platform based on drone aerial photography includes: a collection layer, an identification layer and an evaluation layer;
[0010] The boundary information of the geotechnical construction area is uploaded through the collection layer. The collection layer constructs a geotechnical construction area model based on the uploaded boundary information, and simultaneously sets the model division logic. The geotechnical construction area model is divided based on the division logic to obtain several groups of sub-geotechnical construction area models. Each sub-geotechnical construction area model is used as an image acquisition target, and the surface image of the geotechnical construction area is collected. The surface image of the geotechnical construction area is synchronously sent to the recognition layer. The recognition layer receives the surface image of the geotechnical construction area and synchronously identifies the dynamic risk of the geotechnical construction area based on the surface images of each geotechnical construction area. The assessment layer receives the dynamic risk of the geotechnical construction area identified by the recognition layer in real time, assesses the safety of the geotechnical construction based on the dynamic risk of the geotechnical construction area, and simultaneously locates the unsafe area in the geotechnical construction area when the assessment result is that the geotechnical construction is unsafe.
[0011] The identification layer includes a receiving module, a processing module and an identification module. The receiving module is used to receive the surface image of the geotechnical construction area and store the surface image of the geotechnical construction area. The processing module is used to obtain the surface image of the geotechnical construction area stored in the receiving module and perform feature highlighting processing on the surface image of the geotechnical construction area. The identification module is used to traverse the surface image of the geotechnical construction area after the feature highlighting processing and identify the dynamic risk of the geotechnical construction area based on the image.
[0012] The dynamic risk identification logic of the geotechnical construction area is expressed as:
[0013]
[0014] Where: K is the dynamic risk performance value of the geotechnical construction area; u is the set of sub-geotechnical construction area models; k v is the dynamic risk performance value of the geotechnical construction area reflected by the sub-geotechnical construction area model of group v; d(b q ,b q+1 ) is the distance between the sub-image with the maximum feature judgment value in the set of all sub-images that have intersections with adjacent sub-geotechnical construction area models in the grayscale image corresponding to the vth group of sub-geotechnical construction area models divided into 3×3 groups of sub-images, and the sub-image with the maximum feature judgment value in the set of all sub-images that have intersections with adjacent sub-geotechnical construction area models in the grayscale image corresponding to the v+1th group of sub-geotechnical construction area models; d(a q ,p0) is the distance between the center of the grayscale image corresponding to the v-th group of sub-geotechnical construction area model and the sub-image with the maximum feature judgment value in the set of all sub-images that do not have an intersection area with the adjacent sub-geotechnical construction area model in the grayscale image corresponding to the v-th group of sub-geotechnical construction area model divided into 3×3 groups of sub-images;
[0015] Among them, the larger the dynamic risk performance value K of the geotechnical construction area is, the lower the risk of the geotechnical construction area is, and vice versa, the higher the risk of the geotechnical construction area is;
[0016] The receiving module is interactively connected to the processing module and the identification module through a wireless network, the identification module is interactively connected to the camera module through a wireless network, the camera module is interactively connected to the division module and the construction module through a wireless network, the receiving module is interactively connected to the evaluation module through a wireless network, and the evaluation module is interactively connected to the positioning module and the output module through a wireless network.
[0017] Furthermore, the acquisition layer includes a construction module, a division module, and a camera module. The construction module is used to upload the boundary information of the geotechnical construction area, and use the boundary information of the geotechnical construction area to construct a geotechnical construction area model. The division module is used to receive the geotechnical construction area model constructed in the construction module, divide the geotechnical construction area model, and decompose the geotechnical construction area model into a plurality of sub-geotechnical construction area models. The camera module is used to pick up the model boundary coordinates of each sub-geotechnical construction area model, determine the acquisition area of the surface image of the geotechnical construction area based on the model boundary coordinates, and execute the acquisition of the surface image of the geotechnical construction area.
[0018] Among them, the boundary information of the geotechnical construction area uploaded during the operation stage of the construction module, that is, no less than three groups of boundary coordinates of the geotechnical construction area, are connected to each other based on the boundary coordinates of the geotechnical construction area to form a closed area, and the closed area is the geotechnical construction area model. The geotechnical construction area model is a two-dimensional model. The camera module is integrated by a panoramic camera. The camera module determines the boundary coordinates of the sub-geotechnical construction area model based on the boundary coordinates of the geotechnical construction area model and the division result of the sub-geotechnical construction area model. When the camera module collects the surface image of the geotechnical construction area, the image collection range is determined based on the boundary coordinates of the sub-geotechnical construction area model, and the panoramic image of the sub-geotechnical construction area model, that is, the surface image of the geotechnical construction area, is collected.
[0019] Furthermore, the division module is set with a model division logic, and the division module divides the geotechnical construction area model based on the model division logic;
[0020] The partitioning logic set in the partitioning module is expressed as:
[0021] Calculating the size of the geotechnical construction area model based on the boundary information of the geotechnical construction area, setting the number and size of the sub-geotechnical construction area model divisions, dividing the geotechnical construction area model according to the set number and size of the sub-geotechnical construction area model divisions, so that the geotechnical construction area model is divided into sub-geotechnical construction area models equal to the set number of divisions, and the sizes of the respective geotechnical construction area models are equal to each other;
[0022] Among them, adjacent sub-geotechnical construction area models overlap each other, and the model area of the overlapping sub-geotechnical construction area models is always smaller than half of the corresponding area of any group of models in the overlapping sub-geotechnical construction area models.
[0023] Furthermore, each sub-geotechnical construction area model obtained by dividing the geotechnical construction area model in the division module also obeys:
[0024]
[0025] Where: n is the set of sub-geotechnical construction area models; s(p i ∩p i+1 ) is the size of the intersection of the adjacent i-th group of sub-geotechnical construction area models and the i+1-th group of sub-geotechnical construction area models; s p0 is the size of the sub-geotechnical construction area model division set in the division logic; q is the number of sub-geotechnical construction area model divisions set in the division logic; S0 is the size of the geotechnical construction area model determined based on the geotechnical construction area boundary information.
[0026] Furthermore, each time the system runs, it only collects the surface image of the geotechnical construction area once for each sub-geotechnical construction area model, and all collected surface images of the geotechnical construction area cover the entire geotechnical construction area;
[0027] When receiving the surface image of the geotechnical construction area, the receiving module preferentially receives the surface image of the geotechnical construction area with a large intersection area with the surface image of the adjacent geotechnical construction area;
[0028] The processing module runs continuously in the recognition layer, and each time it runs in the receiving module, it obtains a group of surface images of the geotechnical construction area based on the time sequence. After the processing module obtains the surface images of the geotechnical construction area and processes the surface images of the geotechnical construction area, the recognition module runs synchronously with the processing module.
[0029] Furthermore, in the processing module, the feature highlighting processing operation for the surface image of the geotechnical construction area is:
[0030]
[0031] Where Gray(i,j) is the output gray value of pixel (i,j); R(i,j), G(i,j), B(i,j) are the color components of pixel (i,j) based on R, G, B channels; ω1, ω2, ω3 are weights; χ is a constant offset; C is the feature judgment value; N, M are the rows and columns of the gray image; G x,y is the gray value of the pixel at the xth row and yth column; F x,y is the weighting coefficient of the pixel corresponding to the xth row and yth column;
[0032] Among them, the weights ω1, ω2, and ω3 are set by the system end user, and the sum of the weights ω1, ω2, and ω3 is 1. The constant offset χ ≥ 0. Based on formula (1), each pixel in the surface image of the geotechnical construction area is processed to output a grayscale image of the surface image of the geotechnical construction area. x,y The value is subject to, F x,y ∈(0, 1], the closer the pixel point at the xth row and yth column is to the center of the image F x,y The larger the value, the smaller the F x,y The smaller the value;
[0033] The grayscale image output by formula (1) is further divided into 3×3 groups of sub-images, and each group of sub-images is used as the calculation target of formula (2). After the feature judgment value C is obtained for each sub-image, each group of sub-images is divided into two groups of sub-image sets. One group of sub-image sets is the set of all sub-images that do not have an intersection area with the adjacent sub-geotechnical construction area model, and the other group of sub-image sets is the set of all sub-images that have an intersection area with the adjacent sub-geotechnical construction area model. A group of sub-images with the largest feature judgment value C is picked up from the two groups respectively, and the corresponding regional image is determined in the surface image of the geotechnical construction area based on the picked sub-image. The regional image determined in the surface image of the geotechnical construction area is the feature highlighting processing result of the surface image of the geotechnical construction area in the processing module.
[0034] Furthermore, the evaluation layer includes an evaluation module, a positioning module and an output module. The evaluation module is used to continuously receive the dynamic risks of the geotechnical construction area identified in the identification layer, and evaluate whether the geotechnical construction is safe based on the continuously received dynamic risks of the geotechnical construction area. The positioning module is used to obtain the evaluation result of whether the geotechnical construction is safe in the evaluation module, and when the evaluation result is no, locate the unsafe area in the geotechnical construction area. The output module is used to receive the unsafe area in the geotechnical construction area located in the positioning module, obtain the coordinates of the unsafe area and output them;
[0035] Among them, the evaluation logic of whether the geotechnical construction is safe in the evaluation module is expressed as:
[0036]
[0037] Where: K1, K2, K3, ... are the dynamic risk performance values of the geotechnical construction area continuously received by the assessment module; K O It is the dynamic risk determination value of geotechnical construction area;
[0038] Among them, K1, K2, K3, ... are sorted based on the identification time sequence, and K1, K2, K3, ... are not less than three groups. K1 is the dynamic risk performance value of the geotechnical construction area identified the earliest, and the dynamic risk judgment value of the geotechnical construction area K O Based on the user customization on the system side, if any one of the above formulas is true, it means that the current geotechnical construction status is unsafe; otherwise, it means that the current geotechnical construction status is safe.
[0039] Furthermore, the positioning logic of the unsafe area in the geotechnical construction area in the positioning module is expressed as:
[0040] K v1 >K v2 >K v3 >......;
[0041] Where: K v1 , K v2 , K v3 , ... are the dynamic risk performance values of the geotechnical construction area reflected by the sub-geotechnical construction area model of the vth group based on K1, K2, K3, ... when being obtained;
[0042] Among them, K v1 , K v2 , K v3 , ... sorting based on recognition time sequence, K v1 It is the dynamic risk performance value of the geotechnical construction area identified earliest. Based on the above formula, each sub-geotechnical construction area model is taken as the judgment target, and the area corresponding to the sub-geotechnical construction area model that meets the above formula is judged as an unsafe area in the geotechnical construction area.
[0043] Second, a geotechnical construction survey management method based on drone aerial photography, including:
[0044] S1: Upload the boundary information of the geotechnical construction area, build a geotechnical construction area model, divide the geotechnical construction area model, and obtain several groups of sub-geotechnical construction area models;
[0045] S2: according to the corresponding area of the sub-geotechnical construction area model, the surface image of the geotechnical construction area is collected, and feature highlighting processing is performed on the collected surface image of the geotechnical construction area;
[0046] S3: Obtain the feature highlighting processing results of the surface image of the geotechnical construction area, and use the feature highlighting processing results to identify the dynamic risks of the geotechnical construction area;
[0047] S4: Continuously record the dynamic risk identification results of the geotechnical construction area, and evaluate whether the current geotechnical construction is safe based on the continuously recorded identification results;
[0048] S5: When the assessment result shows that the current geotechnical construction is unsafe, the unsafe area in the geotechnical construction area is located and output.
[0049] Compared with the known public technology, the technical solution provided by the present invention has the following advantages:
[0050] Beneficial effects:
[0051] The present invention provides a geotechnical construction survey management platform based on drone aerial photography. During operation, the platform uses a set geotechnical construction area surface image acquisition logic to globally collect surface images of the geotechnical construction area, and then based on image analysis, captures locations where cracks may exist on the surface of the geotechnical construction area. Further, based on the captured surface locations of the geotechnical construction area where cracks may exist, joint analysis is performed to evaluate and determine the construction safety risks of the geotechnical construction area. When the evaluation result is unsafe, the platform can also locate and provide feedback on areas with high surface risks in the geotechnical construction area in a targeted manner, thereby providing construction safety survey management for geotechnical construction to the greatest extent and in a comprehensive manner. In addition, during the implementation phase of the solution, the demand for manual operation is low, and the overall solution is energy-saving, efficient, and intelligent.
[0052] In addition, based on the further configuration of a geotechnical construction investigation and management method based on drone aerial photography, auxiliary logic support is provided for the operation of the above-mentioned platform, ensuring that the technical solution composed of the above-mentioned platform and method is more stable and reliable during the specific implementation and application stage. BRIEF DESCRIPTION OF THE DRAWINGS
[0053] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the prior art descriptions are briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention, and for ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.
[0054] Figure 1 This is a structural schematic diagram of a geotechnical construction survey management platform based on drone aerial photography;
[0055] Figure 2 It is a flowchart of a geotechnical construction investigation management method based on UAV aerial photography;
[0056] Figure 3 It is a schematic diagram showing the logic of geotechnical construction area model division in the present invention;
[0057] Figure 4 It is a schematic diagram of the source of application parameters in the dynamic risk identification logic of geotechnical construction areas in the present invention;
[0058] The numbers in the figure represent: 1. Example 1 of sub-geotechnical construction area model; 2. Example 2 of sub-geotechnical construction area model. DETAILED DESCRIPTION
[0059] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0060] The present invention will be further described below in conjunction with the embodiments.
[0061] Embodiment 1:
[0062] A geotechnical construction survey management platform based on drone aerial photography in this embodiment, such as Figure 1 As shown, it includes: a collection layer, an identification layer and an evaluation layer;
[0063] The boundary information of the geotechnical construction area is uploaded through the collection layer. The collection layer constructs a geotechnical construction area model based on the uploaded boundary information, and simultaneously sets the model division logic. The geotechnical construction area model is divided based on the division logic to obtain several groups of sub-geotechnical construction area models. Each sub-geotechnical construction area model is used as an image acquisition target, and the surface image of the geotechnical construction area is collected. The surface image of the geotechnical construction area is synchronously sent to the recognition layer. The recognition layer receives the surface image of the geotechnical construction area and synchronously identifies the dynamic risk of the geotechnical construction area based on the surface images of each geotechnical construction area. The assessment layer receives the dynamic risk of the geotechnical construction area identified by the recognition layer in real time, assesses the safety of the geotechnical construction based on the dynamic risk of the geotechnical construction area, and simultaneously locates the unsafe area in the geotechnical construction area when the assessment result is that the geotechnical construction is unsafe.
[0064] The acquisition layer includes a construction module, a division module, and a camera module. The construction module is used to upload the boundary information of the geotechnical construction area, and use the boundary information of the geotechnical construction area to build a geotechnical construction area model. The division module is used to receive the geotechnical construction area model constructed in the construction module, divide the geotechnical construction area model, and decompose the geotechnical construction area model into a plurality of sub-geotechnical construction area models. The camera module is used to pick up the model boundary coordinates of each sub-geotechnical construction area model, determine the acquisition area of the surface image of the geotechnical construction area based on the model boundary coordinates, and execute the acquisition of the surface image of the geotechnical construction area.
[0065] Among them, the geotechnical construction area boundary information uploaded during the operation phase of the construction module, that is, no less than three groups of geotechnical construction area boundary coordinates, the construction module is connected to each other based on the geotechnical construction area boundary coordinates to form a closed area, the closed area is the geotechnical construction area model, the geotechnical construction area model is a two-dimensional model, the camera module is integrated by a panoramic camera, the camera module determines the boundary coordinates of the sub-geotechnical construction area model based on the boundary coordinates of the geotechnical construction area model and the result of the division of the sub-geotechnical construction area model, when the camera module collects the surface image of the geotechnical construction area, the image collection range is determined based on the boundary coordinates of the sub-geotechnical construction area model, and the panoramic image of the sub-geotechnical construction area model is collected, that is, the surface image of the geotechnical construction area;
[0066] The recognition layer includes a receiving module, a processing module and a recognition module. The receiving module is used to receive the surface image of the geotechnical construction area and store the surface image of the geotechnical construction area. The processing module is used to obtain the surface image of the geotechnical construction area stored in the receiving module and perform feature highlighting processing on the surface image of the geotechnical construction area. The recognition module is used to traverse the surface image of the geotechnical construction area after feature highlighting processing and identify the dynamic risk of the geotechnical construction area based on the image.
[0067] The logic of dynamic risk identification in geotechnical construction area is expressed as:
[0068]
[0069] Where: K is the dynamic risk performance value of the geotechnical construction area; u is the set of sub-geotechnical construction area models; k v is the dynamic risk performance value of the geotechnical construction area reflected by the sub-geotechnical construction area model of group v; d(b q ,b q+1 ) is the distance between the sub-image with the maximum feature judgment value in the set of all sub-images that have intersections with adjacent sub-geotechnical construction area models in the grayscale image corresponding to the vth group of sub-geotechnical construction area models divided into 3×3 groups of sub-images, and the sub-image with the maximum feature judgment value in the set of all sub-images that have intersections with adjacent sub-geotechnical construction area models in the grayscale image corresponding to the v+1th group of sub-geotechnical construction area models; d(a q ,p0) is the distance between the center of the grayscale image corresponding to the v-th group of sub-geotechnical construction area model and the sub-image with the maximum feature judgment value in the set of all sub-images that do not have an intersection area with the adjacent sub-geotechnical construction area model in the grayscale image corresponding to the v-th group of sub-geotechnical construction area model divided into 3×3 groups of sub-images;
[0070] Among them, the larger the dynamic risk performance value K of the geotechnical construction area is, the lower the risk of the geotechnical construction area is, and vice versa, the higher the risk of the geotechnical construction area is;
[0071] The evaluation layer includes an evaluation module, a positioning module and an output module. The evaluation module is used to continuously receive the dynamic risks of the geotechnical construction area identified in the identification layer, and evaluate whether the geotechnical construction is safe based on the continuously received dynamic risks of the geotechnical construction area. The positioning module is used to obtain the evaluation result of whether the geotechnical construction is safe in the evaluation module, and when the evaluation result is no, locate the unsafe area in the geotechnical construction area. The output module is used to receive the unsafe area in the geotechnical construction area located in the positioning module, obtain the coordinates of the unsafe area and output them;
[0072] Among them, the evaluation logic of whether the geotechnical construction is safe in the evaluation module is expressed as:
[0073]
[0074] Where: K1, K2, K3, ... are the dynamic risk performance values of the geotechnical construction area continuously received by the assessment module; K O It is the dynamic risk determination value of geotechnical construction area;
[0075] Among them, K1, K2, K3, ... are sorted based on the identification time sequence, and K1, K2, K3, ... are not less than three groups. K1 is the dynamic risk performance value of the geotechnical construction area identified the earliest, and the dynamic risk judgment value of the geotechnical construction area K O Based on the user customization of the system end, in the above formula, if any one of the above formulas is true, it means that the current geotechnical construction state is unsafe, otherwise, it means that the current geotechnical construction state is safe;
[0076] The positioning logic of the unsafe area in the geotechnical construction area in the positioning module is expressed as:
[0077] K v1 >K v2 >K v3 >......;
[0078] Where: K v1 , K v2 , K v3 , ... are the dynamic risk performance values of the geotechnical construction area reflected by the sub-geotechnical construction area model of the vth group based on K1, K2, K3, ... when being obtained;
[0079] Among them, K v1 , K v2 , K v3 , ... sorting based on recognition time sequence, K v1 is the dynamic risk performance value of the geotechnical construction area identified earliest. Based on the above formula, each sub-geotechnical construction area model is used as the judgment target, and the area corresponding to the sub-geotechnical construction area model that meets the above formula is judged as an unsafe area in the geotechnical construction area;
[0080] The receiving module is interactively connected to the processing module and the recognition module through a wireless network, the recognition module is interactively connected to the camera module through a wireless network, the camera module is interactively connected to the division module and the construction module through a wireless network, the receiving module is interactively connected to the evaluation module through a wireless network, and the evaluation module is interactively connected to the positioning module and the output module through a wireless network.
[0081] In this embodiment, the construction module runs to upload the boundary information of the geotechnical construction area, and uses the boundary information of the geotechnical construction area to construct the geotechnical construction area model. The division module synchronously receives the geotechnical construction area model constructed in the construction module, divides the geotechnical construction area model, and decomposes the geotechnical construction area model into a plurality of sub-geotechnical construction area models. The camera module further picks up the model boundary coordinates of each sub-geotechnical construction area model, determines the acquisition area of the surface image of the geotechnical construction area based on the model boundary coordinates, and executes the acquisition of the surface image of the geotechnical construction area. The receiving module post-operates to receive the surface image of the geotechnical construction area, stores the surface image of the geotechnical construction area, and then obtains the surface image of the geotechnical construction area in the receiving module by the processing module. The stored surface images of the geotechnical construction area are subjected to feature highlighting processing. The recognition module further traverses the surface images of the geotechnical construction area after feature highlighting processing, and identifies the dynamic risks of the geotechnical construction area based on the images. Finally, the dynamic risks of the geotechnical construction area identified in the recognition layer are continuously received by the evaluation module. Whether the geotechnical construction is safe is evaluated based on the continuously received dynamic risks of the geotechnical construction area. The positioning module obtains the evaluation result of whether the geotechnical construction is safe in the evaluation module in real time. When the evaluation result is no, the unsafe area in the geotechnical construction area is located, and the output module receives the unsafe area in the geotechnical construction area located in the positioning module, obtains the coordinates of the unsafe area and outputs them.
[0082] Through the above-mentioned embodiments, the system brings about the implementation of survey and management of the risk hazards of geotechnical cracks in geotechnical construction, brings more effective safety maintenance to geotechnical construction, and provides guarantee for the safety of on-site workers during geotechnical construction.
[0083] See also Figure 3 As shown, based on the sub-geotechnical construction area model example 1, sub-geotechnical construction area model example 2 and arrow indications in the figure, the dotted line in the sub-geotechnical construction area model example 1 represents the area, that is, the intersection area of the sub-geotechnical construction area model example 1 and the sub-geotechnical construction area model example 2, which is used as an example for the following embodiments s(p i ∩p i+1 ) to show examples.
[0084] See also Figure 4As shown in the figure, the segmentation operation of the grayscale image corresponding to the sub-geotechnical construction area model is further demonstrated. The a marked in the figure represents the a applied in the dynamic risk identification logic of the geotechnical construction area in the following embodiment. q , b represents p0 applied in the dynamic risk identification logic of geotechnical construction area in the following embodiment, and c represents b applied in the dynamic risk identification logic of geotechnical construction area in the following embodiment. q , d represents the dynamic risk identification logic of geotechnical construction area in the following embodiment. v+1 ;
[0085] ab represents the line between markers a and b, and cd represents the line between markers c and d, that is, the feature highlighting processing result obtained when the system is running (ab is d (a q ,p0),cd,i.e.d(b q ,b v+1 )), in other words, the rock and soil cracks and fissures in the sub-rock and soil construction area model predicted by the system operation;
[0086] It should be noted that the camera module is a panoramic camera integrated on the surface of the drone, and the drone is carried and flown to realize the collection of surface images of the geotechnical construction area.
[0087] Embodiment 2:
[0088] In terms of specific implementation, based on the first embodiment, this embodiment refers to Figure 1 A geotechnical construction survey management platform based on drone aerial photography in Example 1 is further described in detail:
[0089] The division module is provided with a model division logic, and the division module divides the geotechnical construction area model based on the model division logic;
[0090] The partitioning logic set in the partitioning module is expressed as:
[0091] Calculating the size of the geotechnical construction area model based on the boundary information of the geotechnical construction area, setting the number and size of the sub-geotechnical construction area model divisions, dividing the geotechnical construction area model according to the set number and size of the sub-geotechnical construction area model divisions, so that the geotechnical construction area model is divided into sub-geotechnical construction area models equal to the set number of divisions, and the sizes of the respective geotechnical construction area models are equal to each other;
[0092] Among them, adjacent sub-geotechnical construction area models overlap each other, and the model area of the overlapping sub-geotechnical construction area models is always smaller than half of the corresponding area of any group of models in the overlapping sub-geotechnical construction area models;
[0093] In the division module, each sub-geotechnical construction area model obtained by dividing the geotechnical construction area model also obeys:
[0094]
[0095] Where: n is the set of sub-geotechnical construction area models; s(p i ∩p i+1 ) is the size of the intersection of the adjacent i-th group of sub-geotechnical construction area models and the i+1-th group of sub-geotechnical construction area models; s p0 is the size of the sub-geotechnical construction area model division set in the division logic; q is the number of sub-geotechnical construction area model divisions set in the division logic; S0 is the size of the geotechnical construction area model determined based on the geotechnical construction area boundary information.
[0096] In this embodiment, through the above-mentioned settings, further operation data support is provided for the operation of the system in Example 1, and the division logic of the division module when dividing the geotechnical construction area model is limited to ensure that the geotechnical construction area model is stably divided to obtain several groups of sub-geotechnical construction area models for further operation of the system in Example 1.
[0097] Embodiment three:
[0098] In terms of specific implementation, based on the first embodiment, this embodiment refers to Figure 1 A geotechnical construction survey management platform based on drone aerial photography in Example 1 is further described in detail:
[0099] Each time the system runs, the surface image of the geotechnical construction area is collected only once for each sub-geotechnical construction area model, and all collected surface images of the geotechnical construction area cover the entire geotechnical construction area;
[0100] When receiving the surface image of the geotechnical construction area, the receiving module preferentially receives the surface image of the geotechnical construction area having a large intersection area with the surface image of the adjacent geotechnical construction area;
[0101] The processing module runs continuously in the recognition layer, and each time it runs in the receiving module, it obtains a set of surface images of the geotechnical construction area based on the time sequence. After the processing module obtains the surface images of the geotechnical construction area, and processes the surface images of the geotechnical construction area, the recognition module runs synchronously with the processing module;
[0102] In the processing module, the feature highlighting processing operation for the surface image of the geotechnical construction area is as follows:
[0103]
[0104] Where Gray(i,j) is the output gray value of pixel (i,j); R(i,j), G(i,j), B(i,j) are the color components of pixel (i,j) based on R, G, B channels; ω1, ω2, ω3 are weights; χ is a constant offset; C is the feature judgment value; N, M are the rows and columns of the gray image; G x,y is the gray value of the pixel at the xth row and yth column; F x,y is the weighting coefficient of the pixel corresponding to the xth row and yth column;
[0105] Among them, the weights ω1, ω2, and ω3 are set by the system end user, and the sum of the weights ω1, ω2, and ω3 is 1. The constant offset χ ≥ 0. Based on formula (1), each pixel in the surface image of the geotechnical construction area is processed to output a grayscale image of the surface image of the geotechnical construction area. x,y The value is subject to, F x,y ∈(0, 1], the closer the pixel point at the xth row and yth column is to the center of the image F x,y The larger the value, the smaller the F x,y The smaller the value;
[0106] The grayscale image output by formula (1) is further divided into 3×3 groups of sub-images, and each group of sub-images is used as the calculation target of formula (2). After the feature judgment value C is obtained for each sub-image, each group of sub-images is divided into two groups of sub-image sets. One group of sub-image sets is the set of all sub-images that do not have an intersection area with the adjacent sub-geotechnical construction area model, and the other group of sub-image sets is the set of all sub-images that have an intersection area with the adjacent sub-geotechnical construction area model. A group of sub-images with the largest feature judgment value C is picked up from the two groups respectively, and the corresponding regional image is determined in the surface image of the geotechnical construction area based on the picked sub-image. The regional image determined in the surface image of the geotechnical construction area is the feature highlighting processing result of the surface image of the geotechnical construction area in the processing module.
[0107] In this embodiment, by setting the above-mentioned logical formula, the operational logic of the feature highlighting processing in the processing module is further limited, so that the recognition layer can stably operate the output image, providing an evaluation basis for the geotechnical construction safety evaluation in the evaluation layer.
[0108] Embodiment 4:
[0109] In terms of specific implementation, based on the first embodiment, this embodiment refers to Figure 2 A geotechnical construction survey management platform based on drone aerial photography in Example 1 is further described in detail:
[0110] A geotechnical construction survey management method based on drone aerial photography, comprising:
[0111] S1: Upload the boundary information of the geotechnical construction area, build a geotechnical construction area model, divide the geotechnical construction area model, and obtain several groups of sub-geotechnical construction area models;
[0112] S2: according to the corresponding area of the sub-geotechnical construction area model, the surface image of the geotechnical construction area is collected, and feature highlighting processing is performed on the collected surface image of the geotechnical construction area;
[0113] S3: Obtain the feature highlighting processing results of the surface image of the geotechnical construction area, and use the feature highlighting processing results to identify the dynamic risks of the geotechnical construction area;
[0114] S4: Continuously record the dynamic risk identification results of the geotechnical construction area, and evaluate whether the current geotechnical construction is safe based on the continuously recorded identification results;
[0115] S5: When the assessment result shows that the current geotechnical construction is unsafe, the unsafe area in the geotechnical construction area is located and output.
[0116] In summary, during the operation of the platform in the above embodiment, the surface image of the geotechnical construction area is globally collected according to the set surface image collection logic of the geotechnical construction area, and then based on image analysis, the location of possible cracks on the surface of the geotechnical construction area is captured, and further joint analysis is performed based on the captured surface locations of the geotechnical construction area where cracks may exist, and the construction safety risks of the geotechnical construction area are evaluated and determined. When the evaluation result is unsafe, the area with higher surface risk in the geotechnical construction area can be targeted and feedback can be given, thereby providing construction safety survey and management for geotechnical construction to the greatest extent and in a comprehensive manner. In addition, during the implementation stage of the scheme, the demand for manual operation is low, and the overall scheme is energy-saving, efficient, and intelligent. In addition, based on the further configuration of a geotechnical construction survey and management method based on drone aerial photography, auxiliary logic support is provided for the operation of the above platform, ensuring that the technical scheme composed of the above platform and method is more stable and reliable in the specific implementation and application stage.
[0117] The above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit the same. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that the technical solutions described in the aforementioned embodiments may still be modified, or some of the technical features may be replaced by equivalents. Such modifications or replacements will not cause the essence of the corresponding technical solutions to deviate from the spirit and scope of the technical solutions of the embodiments of the present invention.
Claims
1. A geotechnical construction survey management platform based on drone aerial photography, characterized in that: include: Collection layer, identification layer and evaluation layer; The boundary information of the geotechnical construction area is uploaded through the collection layer. The collection layer constructs a geotechnical construction area model based on the uploaded boundary information, and simultaneously sets the model division logic. The geotechnical construction area model is divided based on the division logic to obtain several groups of sub-geotechnical construction area models. Each sub-geotechnical construction area model is used as an image acquisition target, and the surface image of the geotechnical construction area is collected. The surface image of the geotechnical construction area is synchronously sent to the recognition layer. The recognition layer receives the surface image of the geotechnical construction area and synchronously identifies the dynamic risk of the geotechnical construction area based on the surface images of each geotechnical construction area. The assessment layer receives the dynamic risk of the geotechnical construction area identified by the recognition layer in real time, assesses the safety of the geotechnical construction based on the dynamic risk of the geotechnical construction area, and simultaneously locates the unsafe area in the geotechnical construction area when the assessment result is that the geotechnical construction is unsafe. The identification layer includes a receiving module, a processing module and an identification module. The receiving module is used to receive the surface image of the geotechnical construction area and store the surface image of the geotechnical construction area. The processing module is used to obtain the surface image of the geotechnical construction area stored in the receiving module and perform feature highlighting processing on the surface image of the geotechnical construction area. The identification module is used to traverse the surface image of the geotechnical construction area after the feature highlighting processing and identify the dynamic risk of the geotechnical construction area based on the image. The dynamic risk identification logic of the geotechnical construction area is expressed as: Where: K is the dynamic risk performance value of the geotechnical construction area; u is the set of sub-geotechnical construction area models; k v is the dynamic risk performance value of the geotechnical construction area reflected by the sub-geotechnical construction area model of group v; d(b q ,b q+1 ) is the distance between the sub-image with the maximum feature judgment value in the set of all sub-images that have intersections with adjacent sub-geotechnical construction area models in the grayscale image corresponding to the vth group of sub-geotechnical construction area models divided into 3×3 groups of sub-images, and the sub-image with the maximum feature judgment value in the set of all sub-images that have intersections with adjacent sub-geotechnical construction area models in the grayscale image corresponding to the v+1th group of sub-geotechnical construction area models; d(a q ,p0) is the distance between the center of the grayscale image corresponding to the v-th group of sub-geotechnical construction area model and the sub-image with the maximum feature judgment value in the set of all sub-images that do not have an intersection area with the adjacent sub-geotechnical construction area model in the grayscale image corresponding to the v-th group of sub-geotechnical construction area model divided into 3×3 groups of sub-images; Among them, the larger the dynamic risk performance value K of the geotechnical construction area is, the lower the risk of the geotechnical construction area is, and vice versa, the higher the risk of the geotechnical construction area is.
2. According to the geotechnical construction survey management platform based on drone aerial photography according to claim 1, it is characterized in that: The acquisition layer includes a construction module, a division module, and a camera module. The construction module is used to upload the boundary information of the geotechnical construction area, and use the boundary information of the geotechnical construction area to build a geotechnical construction area model. The division module is used to receive the geotechnical construction area model built in the construction module, divide the geotechnical construction area model, and decompose the geotechnical construction area model into a plurality of sub-geotechnical construction area models. The camera module is used to pick up the model boundary coordinates of each sub-geotechnical construction area model, determine the acquisition area of the surface image of the geotechnical construction area based on the model boundary coordinates, and execute the acquisition of the surface image of the geotechnical construction area. Among them, the boundary information of the geotechnical construction area uploaded during the operation stage of the construction module, that is, no less than three groups of boundary coordinates of the geotechnical construction area, are connected to each other based on the boundary coordinates of the geotechnical construction area to form a closed area, and the closed area is the geotechnical construction area model. The geotechnical construction area model is a two-dimensional model. The camera module is integrated by a panoramic camera. The camera module determines the boundary coordinates of the sub-geotechnical construction area model based on the boundary coordinates of the geotechnical construction area model and the division result of the sub-geotechnical construction area model. When the camera module collects the surface image of the geotechnical construction area, the image collection range is determined based on the boundary coordinates of the sub-geotechnical construction area model, and the panoramic image of the sub-geotechnical construction area model, that is, the surface image of the geotechnical construction area, is collected.
3. The geotechnical construction survey management platform based on drone aerial photography according to claim 1 is characterized in that: The division module is provided with a model division logic, and the division module divides the geotechnical construction area model based on the model division logic; The partitioning logic set in the partitioning module is expressed as: Calculating the size of the geotechnical construction area model based on the boundary information of the geotechnical construction area, setting the number and size of the sub-geotechnical construction area model divisions, dividing the geotechnical construction area model according to the set number and size of the sub-geotechnical construction area model divisions, so that the geotechnical construction area model is divided into sub-geotechnical construction area models equal to the set number of divisions, and the sizes of the respective geotechnical construction area models are equal to each other; Among them, adjacent sub-geotechnical construction area models overlap each other, and the model area of the overlapping sub-geotechnical construction area models is always smaller than half of the corresponding area of any group of models in the overlapping sub-geotechnical construction area models.
4. The geotechnical construction survey management platform based on drone aerial photography according to claim 3 is characterized in that: Each sub-geotechnical construction area model obtained by dividing the geotechnical construction area model in the division module also obeys: Where: n is the set of sub-geotechnical construction area models; s(p i ∩p i+1 ) is the size of the intersection of the adjacent i-th group of sub-geotechnical construction area models and the i+1-th group of sub-geotechnical construction area models; is the size of the sub-geotechnical construction area model division set in the division logic; q is the number of sub-geotechnical construction area model divisions set in the division logic; S0 is the size of the geotechnical construction area model determined based on the geotechnical construction area boundary information.
5. The geotechnical construction survey management platform based on drone aerial photography according to claim 1 is characterized in that: Each time the system runs, the surface image of the geotechnical construction area is collected only once for each sub-geotechnical construction area model, and all collected surface images of the geotechnical construction area cover the entire geotechnical construction area; When receiving the surface image of the geotechnical construction area, the receiving module preferentially receives the surface image of the geotechnical construction area with a large intersection area with the surface image of the adjacent geotechnical construction area; The processing module runs continuously in the recognition layer, and each time it runs in the receiving module, it obtains a group of surface images of the geotechnical construction area based on the time sequence. After the processing module obtains the surface images of the geotechnical construction area and processes the surface images of the geotechnical construction area, the recognition module runs synchronously with the processing module.
6. The geotechnical construction survey management platform based on drone aerial photography according to claim 1 is characterized in that: In the processing module, the feature highlighting processing operation for the surface image of the geotechnical construction area is as follows: Where Gray(i,j) is the output gray value of pixel (i,j); R(i,j), G(i,j), B(i,j) are the color components of pixel (i,j) based on R, G, B channels; ω1, ω2, ω3 are weights; χ is a constant offset; C is the feature judgment value; N, M are the rows and columns of the gray image; G x,y is the gray value of the pixel at the xth row and yth column; F x,y is the weighting coefficient of the pixel corresponding to the xth row and yth column; Among them, the weights ω1, ω2, and ω3 are set by the system end user, and the sum of the weights ω1, ω2, and ω3 is 1. The constant offset χ ≥ 0. Based on formula (1), each pixel in the surface image of the geotechnical construction area is processed to output a grayscale image of the surface image of the geotechnical construction area. x,y The value is subject to, F x,y ∈(0, 1], the closer the pixel point at the xth row and yth column is to the center of the image F x,y The larger the value, the smaller the F x,y The smaller the value; The grayscale image output by formula (1) is further divided into 3×3 groups of sub-images, and each group of sub-images is used as the calculation target of formula (2). After the feature judgment value C is obtained for each sub-image, each group of sub-images is divided into two groups of sub-image sets. One group of sub-image sets is the set of all sub-images that do not have an intersection area with the adjacent sub-geotechnical construction area model, and the other group of sub-image sets is the set of all sub-images that have an intersection area with the adjacent sub-geotechnical construction area model. A group of sub-images with the largest feature judgment value C is picked up from the two groups respectively, and the corresponding regional image is determined in the surface image of the geotechnical construction area based on the picked sub-image. The regional image determined in the surface image of the geotechnical construction area is the feature highlighting processing result of the surface image of the geotechnical construction area in the processing module.
7. The geotechnical construction survey management platform based on drone aerial photography according to claim 1 is characterized in that: The evaluation layer includes an evaluation module, a positioning module and an output module. The evaluation module is used to continuously receive the dynamic risks of the geotechnical construction area identified in the identification layer, and evaluate whether the geotechnical construction is safe based on the continuously received dynamic risks of the geotechnical construction area. The positioning module is used to obtain the evaluation result of whether the geotechnical construction is safe in the evaluation module, and when the evaluation result is no, locate the unsafe area in the geotechnical construction area. The output module is used to receive the unsafe area in the geotechnical construction area located in the positioning module, obtain the coordinates of the unsafe area and output them; Among them, the evaluation logic of whether the geotechnical construction is safe in the evaluation module is expressed as: Where: K1, K2, K3, ... are the dynamic risk performance values of the geotechnical construction area continuously received by the assessment module; K O It is the dynamic risk determination value of geotechnical construction area; Among them, K1, K2, K3, ... are sorted based on the identification time sequence, and K1, K2, K3, ... are not less than three groups. K1 is the dynamic risk performance value of the geotechnical construction area identified the earliest, and the dynamic risk judgment value of the geotechnical construction area K O Based on the user customization on the system side, if any one of the above formulas is true, it means that the current geotechnical construction status is unsafe; otherwise, it means that the current geotechnical construction status is safe.
8. The geotechnical construction survey management platform based on drone aerial photography according to claim 7 is characterized in that: The positioning logic of the unsafe area in the geotechnical construction area in the positioning module is expressed as: K v1 >K v2 >K v3 >......; Where: K v1 , K v2 , K v3 , ... are the dynamic risk performance values of the geotechnical construction area reflected by the sub-geotechnical construction area model of the vth group based on K1, K2, K3, ... when being obtained; Among them, K v1 , K v2 , K v3 , ... sorting based on recognition time sequence, K v1 It is the dynamic risk performance value of the geotechnical construction area identified earliest. Based on the above formula, each sub-geotechnical construction area model is taken as the judgment target, and the area corresponding to the sub-geotechnical construction area model that meets the above formula is judged as an unsafe area in the geotechnical construction area.
9. The geotechnical construction survey management platform based on drone aerial photography according to claim 1 is characterized in that: The receiving module is interactively connected to the processing module and the identification module through a wireless network, the identification module is interactively connected to the camera module through a wireless network, the camera module is interactively connected to the division module and the construction module through a wireless network, the receiving module is interactively connected to the evaluation module through a wireless network, and the evaluation module is interactively connected to the positioning module and the output module through a wireless network.
10. A geotechnical construction survey management method based on drone aerial photography, the method is an implementation method of a geotechnical construction survey management platform based on drone aerial photography as claimed in any one of claims 1 to 9, characterized in that: include: S1: Upload the boundary information of the geotechnical construction area, build a geotechnical construction area model, divide the geotechnical construction area model, and obtain several groups of sub-geotechnical construction area models; S2: according to the corresponding area of the sub-geotechnical construction area model, the surface image of the geotechnical construction area is collected, and feature highlighting processing is performed on the collected surface image of the geotechnical construction area; S3: Obtain the feature highlighting processing results of the surface image of the geotechnical construction area, and use the feature highlighting processing results to identify the dynamic risks of the geotechnical construction area; S4: Continuously record the dynamic risk identification results of the geotechnical construction area, and evaluate whether the current geotechnical construction is safe based on the continuously recorded identification results; S5: When the assessment result shows that the current geotechnical construction is unsafe, the unsafe area in the geotechnical construction area is located and output.
Citation Information
Patent Citations
Bridge concrete crack detection method based on YOLOv5 improved algorithm
CN116485709A
Satellite remote sensing intelligent monitoring method and system for external damage construction of power transmission line
CN116630821A
Concrete member quality control method and system based on visual monitoring
CN117808356A