Suspension protection excavation method for existing pipeline

Through the suspension protection excavation method, the foundation pit support and retaining wall are used to layer construction, and the problems of existing pipelines being damaged and soil disturbed in underground structure construction are solved, and the stability and construction safety of the pipeline are improved. Suitable for a variety of pipe sizes and buried depths.

CN119021234APending Publication Date: 2024-11-26CCCC FOURTH HARBOR ENG CO LTD

Patent Information

Application Number
CN202411310342.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-19
Publication Date
2024-11-26

AI Technical Summary

Technical Problem

In underground structure construction, it is difficult to avoid damage to existing pipelines, suspension protection has stability problems, and soil disturbances during construction affect the stability and reliability of the pipelines.

Method used

A suspension protection excavation method is adopted, including construction preparation, foundation pit support, suspended beams and retaining walls, reducing soil disturbances through the overall structure of support piles and retaining walls, ensuring the stability of the pipeline. and reliability.

Benefits of technology

It effectively reduces soil deformation around the pipeline, improves the stability and construction safety of the pipeline, reduces construction costs and risks, and is suitable for large diameter and deep buried pipelines.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119021234A_ABST
    Figure CN119021234A_ABST
Patent Text Reader

Abstract

The invention discloses a suspension protection excavation method for an existing pipeline, which can effectively protect the pipeline, reduce the disturbance of soil around the pipeline in the underground structure construction process and ensure the stability of the pipeline in the underground structure construction process under the condition that the pipeline is not migrated. The suspension protection excavation method for the existing pipeline comprises the steps that construction preparation is conducted, and earth surface sundries in a construction area are removed; the current pipeline is searched, the position of the current pipeline is marked, and then support piles are constructed around the excavation construction area; crown beams are constructed, and the adjacent supporting piles are connected; a first foundation pit inner support is constructed, and the opposite supporting piles are connected; mounting a supporting beam and a suspension beam; earthwork is excavated layer by layer at the crown beams on the two sides of the pipeline, and retaining walls are constructed; and the pipelines are suspended, earthwork is excavated in a layered mode in an excavation construction area defined by the supporting piles, and a retaining wall is constructed till construction reaches the foundation elevation.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of construction engineering, and in particular to a suspension protection excavation method for an existing pipeline. Background Art

[0002] In the process of urban construction, it is common to encounter situations where underground structures such as pipe corridors and underground roads intersect with existing underground pipelines. When constructing underground structures under existing underground pipelines, it is necessary to protect the existing underground pipelines to prevent the construction of underground structures from damaging the existing underground pipelines and affecting the normal operation of urban infrastructure. In order to prevent the construction of underground structures from affecting existing underground pipelines, the existing underground pipelines are usually relocated before the construction of underground structures, and then the proposed underground structures are open-cut. The relocation of underground pipelines will have an impact on the surrounding environment and bring inconvenience to the lives of residents. The relocation and maintenance costs are high. In cases where it is inconvenient to relocate, there are also methods such as pipe jacking for dark excavation construction, which will increase construction costs and risks.

[0003] When it is not convenient to relocate the existing underground pipelines or to carry out dark excavation construction, the in-situ suspension protection of the existing underground pipelines can reduce the impact on the surrounding environment and the risk of construction. However, the in-situ suspension protection will have the following problems: the stability of the suspension structure itself will affect the stability of the pipeline suspension. When the large-diameter pipeline (diameter not less than 800mm) is suspended in situ for protection, the suspension structure is prone to deformation and damage due to concentrated force, which affects the reliability of the suspension protection of the large-diameter pipeline; the suspension usually adopts wire rope, and the contact between the wire rope and the pipeline is easy to cause the pipeline to be damaged by concentrated force; some pipelines are concrete socket pipes, and when they are suspended for protection, they are prone to pipeline damage and pipeline leakage; during the pipeline suspension protection and soil excavation construction after suspension protection, the disturbance of the soil around the pipeline will cause the pipeline to deform, affecting the stability and reliability of the pipeline suspension protection; during the foundation pit excavation construction under the existing pipeline, the foundation pit support structure needs to be constructed to ensure the safety of the foundation pit excavation construction, and the existing pipeline will interfere with the construction of the foundation pit support structure, resulting in difficulties in the construction of the foundation pit support structure. Summary of the invention

[0004] At least one of the purposes of the present invention is to provide a method for suspended protective excavation of existing pipelines in order to overcome the problems existing in the above-mentioned prior art, which can effectively protect the pipeline without relocating the pipeline, reduce the disturbance of the soil around the pipeline during the construction of the underground structure, and ensure the stability of the pipeline during the construction of the underground structure.

[0005] In order to achieve the above-mentioned purpose, the technical solution adopted by the present invention includes the following aspects.

[0006] A method for suspended protection excavation of an existing pipeline comprises the following steps: Step 1: Construction preparation, clearing the surface debris in the construction area; Step 2: Survey the existing pipelines, mark the locations of the existing pipelines and the edge lines of the foundation pit excavation, and then construct support piles along the edge lines of the foundation pit excavation; Step 3: construct the crown beam of the foundation pit support and connect the adjacent support piles; construct the first support in the foundation pit and connect the relative support piles; Step 4: Install support beams and suspension beams; Step 5: Excavate the earth in layers at the intersection of the pipeline and the foundation pit excavation construction line to the bottom elevation of the pipeline, and construct the retaining wall in layers between the top of the pipeline and the crown beam; Step 6: Suspend the pipeline; after the compressive strength of the retaining wall is not less than 30Mpa, perform pipeline suspension protection construction in sections along the length of the pipeline; Step 7: Excavate the earth in layers within the foundation pit excavation construction area surrounded by the support piles, and construct the retaining wall in layers; after excavating the earth downward by 1 to 1.8 m, construct the retaining wall in the same way as step 5; Step 8. Repeat step 7 until the construction reaches the base elevation.

[0007] Preferably, in step three, during the construction of the crown beam, embedded parts are set at the designed installation position of the supporting beam on the crown beam, and the embedded parts include embedded steel plates and anchor bolts. When setting the embedded parts, the anchor bolts are welded to the steel frame of the crown beam, and the embedded parts are poured on the crown beam along with the crown beam concrete.

[0008] Preferably, in step 4, the installation process of the support beam includes: Measure and lay out on the embedded steel plate to locate the installation position of the support beam; Support the polytetrafluoroethylene plate on the embedded steel plate; Support members are respectively arranged on both sides of the polytetrafluoroethylene plate; The support beam is installed by a crane. After the support beam is hoisted onto the polytetrafluoroethylene plate, a connecting plate is used to connect the support beam and the support member.

[0009] Preferably, in step four, the installation process of the suspension beam includes: using a crane to install a suspension beam perpendicular to the support beam on the top of the support beam, multiple suspension beams are arranged along the length direction of the support beam, and the suspension beam is fixedly connected to the support beam.

[0010] Preferably, in step six, the pipeline suspension process includes: Within the boundary line of the foundation pit excavation, the soil around the first pipe section of the pipeline is manually excavated from one end of the pipeline at a distance of 1.5 to 2 meters from the crown beam; Placing a joist on the soil below the first pipe section, wherein the joist and the first pipe section are perpendicular to each other; After connecting the joist beam to the suspension rods on both sides of the first pipe section, adjust the height of the suspension rods so that the joist beam can support and drag the first pipe section; Along the length of the pipeline, other sections are constructed in the same way as the first section, with each section being 3 to 4 meters long, until the pipeline is suspended within the edge of the foundation pit excavation construction.

[0011] Preferably, before the joist supports the first pipe section, an encapsulation structure is constructed on the first pipe section, and the construction process of the encapsulation structure includes: Adjust the height of the hanger rod so that the distance between the joist and the first pipe section meets the construction requirements of the encapsulation structure; Installing a sealing bottom mold on the joist, the sealing bottom mold is coaxially arranged with the first pipe section, both sides of the sealing bottom mold are 200 mm wider than the edge of the pipeline, and the sealing bottom mold is supported by adjacent joists; Arranging a steel mesh on the encapsulation bottom mold so that the steel mesh wraps the first pipe section; Install the encapsulation side mold on the encapsulation bottom mold to enclose the casting space of the encapsulation structure; Pour concrete in the pouring space, and remove the encapsulating side formwork after the concrete reaches the demoulding strength; Adjust the height of the hanger rod to move the joist downward; Remove the bottom formwork of the envelope and adjust the height of the hanger so that the joist contacts the bottom of the envelope structure to support the envelope structure; Pre-tension the hanger.

[0012] Preferably, in step 5, the process of constructing the retaining wall includes: At the end of the pipeline, dig 1~1.8m downward to form a retaining wall construction area; Tie the retaining wall reinforcement within the retaining wall construction area; Support retaining wall formwork on both sides of the retaining wall reinforcement; C40 early-strength concrete is used to cast the retaining wall.

[0013] Preferably, in step eight, during the repeated retaining wall construction process, after the compressive strength of the constructed retaining wall is not less than 30 MPa, the retaining wall to be constructed is constructed under the retaining wall.

[0014] Preferably, in step eight, during the repeated retaining wall construction process, a waist beam is constructed at the designed position of the retaining wall, and the waist beam is integrally formed with the retaining wall. Before the construction of the retaining wall and the waist beam, anchor cables are constructed on the side walls of the soil according to the design requirements, and the anchor cables are embedded in the side walls of the soil. Then, the retaining wall steel bars and the waist beam steel bars are tied to construct the retaining wall and the waist beam.

[0015] Preferably, when the distance between the two pipelines is not greater than 2 m, in the process of installing the support beams in step 4, a group of support beams are installed between the two pipelines so that the two pipelines share a group of support beams.

[0016] In summary, due to the adoption of the above technical solution, the present invention has at least the following beneficial effects: By constructing support piles around the construction area, the influence of soil deformation on the pipeline can be reduced during the pipeline suspension protection and excavation construction after the suspension protection, thereby ensuring the stability and reliability of the pipeline suspension protection; before the pipeline suspension protection, retaining walls are constructed between adjacent support piles on both sides of the pipeline, and the retaining walls and support piles are connected into an integral structure, which can further avoid soil disturbance around the pipeline and cause pipeline deformation, thereby effectively protecting the pipeline and ensuring the normal use of the pipeline; after the pipeline is suspended and protected, retaining walls are constructed to the base during the subsequent excavation construction process, thereby avoiding the influence of soil disturbance on the pipeline during the excavation process.

[0017] During the pipeline suspension protection process, the protection effect of the pipeline is improved by cooperating with the construction of the encapsulation structure through the suspension protection structure, ensuring the reliability of pipeline operation, reducing the construction difficulty of the encapsulation structure, and improving the construction efficiency. Before the pipeline suspension protection, the embedded parts are installed at the preset installation position of the support beam during the crown beam construction process to ensure the effective connection between the support beam and the crown beam and improve the stability of the pipeline suspension; before the support beam is installed, a polytetrafluoroethylene plate is constructed on the embedded parts, which can play a shock-absorbing role on the pipeline during the pipeline suspension and subsequent excavation construction process, reducing the impact of soil and crown beam deformation on the stability of pipeline suspension.

[0018] The method for suspended protection excavation of existing pipelines of the present invention can effectively protect the pipelines without relocating the pipelines, realize open excavation construction under the pipelines, and at the same time, the deformation of the existing pipelines during the construction process is small, ensuring the normal use of the pipelines; it is not only suitable for existing pipelines with large diameters and / or deep burial depths (such as: burial depth of not less than 5m), but also suitable for existing pipelines with smaller diameters and shallower burial depths, ensuring the reliability of pipeline suspension protection. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Figure 1 It is a schematic diagram of a suspension protection structure of an existing pipeline according to an exemplary embodiment of the present invention.

[0020] Figure 2 It is a schematic diagram of a suspension protection structure of an existing pipeline according to another exemplary embodiment of the present invention.

[0021] Figure 3 4 is a top view of a suspension protection for an existing pipeline according to an exemplary embodiment of the present invention.

[0022] Figure 4It is a schematic diagram of the connection structure of the retaining wall and the supporting piles according to an exemplary embodiment of the present invention.

[0023] Figure 5 Schematic diagram of a pipeline encapsulation structure according to an exemplary embodiment of the present invention.

[0024] Figure 6 It is a schematic diagram of the suspension beam structure of an exemplary embodiment of the present invention.

[0025] Figure 7 It is a schematic diagram of the embedded parts structure of an exemplary embodiment of the present invention.

[0026] Figure 8 It is a partial schematic diagram of a connection structure between a support beam and embedded parts according to an exemplary embodiment of the present invention.

[0027] Fig. 9 Schematic diagram of the connecting plate structure of an exemplary embodiment of the present invention.

[0028] Fig.10 It is a schematic diagram of the retaining wall template setting of an exemplary embodiment of the present invention.

[0029] Fig.11 It is a partial schematic diagram of a connection structure between a support beam and embedded parts according to another exemplary embodiment of the present invention.

[0030] Fig.12 It is a flow chart of the suspended protection excavation of an existing pipeline according to an exemplary embodiment of the present invention.

[0031] Labels in the figure: 1-support beam, 2-suspension beam, 200-first cross beam, 201-first connecting plate, 202-second connecting plate, 203-rib plate, 3-suspender rod, 4-support beam, 5-support pile, 6-retaining wall, 600-retaining wall steel bar, 601-connecting bar, 7-pipeline, 8-encapsulation structure, 800-steel mesh, 9-waist beam, 10-anchor cable, 11-embedded parts, 110-embedded steel plate , 111-anchor bolts, 12-steel plate gaskets, 13-double nuts, 14-crown beams, 15-supports in foundation pits, 16-polytetrafluoroethylene plates, 17-lower chords, 18-vertical rods, 19-connecting plates, 20-connecting bosses, 21-supports, 22-connecting ribs, 23-slideways, 24-connecting grooves, 25-retaining wall formwork, 250-vertical back ribs, 251-horizontal back ribs, 252-diagonal braces. DETAILED DESCRIPTION

[0032] The present invention is further described in detail below in conjunction with the accompanying drawings and embodiments to make the purpose, technical solutions and advantages of the present invention more clearly understood. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not intended to limit the present invention.

[0033] like Figure 1-Figure 3As shown, the suspension protection structure of the existing pipeline of the exemplary embodiment of the present invention includes a support beam 1, a suspension beam 2, a hanger 3, a joist 4, a supporting pile 5 and a retaining wall 6, wherein a plurality of supporting piles 5 surround a construction area to be excavated in a foundation pit, the tops of adjacent supporting piles 5 are connected into an integral structure by a crown beam 14, the pipeline 7 passes between two adjacent supporting piles 5, support beams 1 are respectively arranged on both sides of the pipeline 7, the bottom of the support beam 1 is located above the crown beam 14, the top of the support beam 1 is connected by the suspension beam 2, the hanger 3 is arranged on the suspension beam 2, the hangers 3 are symmetrically distributed on both sides of the pipeline 7, the hangers 3 are connected by the joist 4, the joist 4 is used to support the joist 7, the retaining wall 6 is arranged between two adjacent supporting piles 5 on both sides of the pipeline 7, and the retaining wall 6 extends downward from the height direction of the supporting piles 5.

[0034] The pipeline 7 is suspended by the support beam 1, the suspension beam 2, the hanger 3 and the support beam 4, which can ensure the stability of the suspension protection structure and prevent the pipeline 7 from being damaged during the suspension process. The load generated during the suspension of the pipeline 7 is transmitted to the support piles on both sides of the pipeline 7 through the support beam 1, the suspension beam 2 and the crown beam 14. The two adjacent support piles 5 on both sides of the pipeline 7 are connected by the retaining wall 6 to ensure the stability of the soil around the pipeline 7. During the suspension of the pipeline 7 and the excavation of the foundation pit under the pipeline 7, the soil disturbance around the pipeline 7 can be avoided to prevent the pipeline 7 from being deformed, thereby effectively protecting the pipeline 7 and ensuring the normal use of the pipeline 7.

[0035] refer to Figure 5 , an encapsulation structure 8 is arranged along the length direction of the pipeline 7, which wraps the pipeline 7. In the process of suspending the pipeline 7, the pipeline 7 can be effectively protected, the rigidity of the pipeline 7 is increased, and the pipeline 7 is prevented from being damaged; the joist 4 is located at the bottom of the encapsulation structure, and the pipeline 7 is suspended through the joist 4 and the suspension rod 3. The joist 4 has a wide force-bearing area, which can avoid direct contact with the pipeline 7 and avoid damage to the pipeline 7 on the one hand, and can improve the force dispersion effect on the other hand, prevent damage to the contact part between the encapsulation structure and the joist 4, and improve the protection effect on the pipeline 7. The encapsulation structure 8 is a steel-concrete structure, in which a steel mesh 800 is arranged, and the steel mesh 800 wraps the pipeline 7 as a whole, which can further improve the protection effect on the pipeline 7; the cross-sectional shape of the encapsulation structure 8 is a rectangle as a whole, and the thickness of the encapsulation structure 8 on the surface of the pipeline 7 is 200~300mm (the vertical distance between the edge of the encapsulation structure and the edge of the pipeline).

[0036] The retaining wall 6 extends downward from the bottom of the crown beam 14 to the base of the foundation pit excavation. A plurality of waist beams 9 are arranged in the height direction of the retaining wall 6. Each waist beam 9 is arranged along the length direction of the retaining wall 6. A plurality of anchor cables 10 are fixedly connected to each waist beam 9. Each anchor cable 10 passes through the retaining wall 6 and extends obliquely into the soil around the retaining wall 6. Under the joint action of the anchor cables 10 and the waist beams 9, the stability of the retaining wall 6 can be improved, and the protective effect of the retaining wall 6 can be improved, so that the disturbance of the soil between the supporting piles 5 on both sides of the pipeline 7 can be reduced during the excavation process, and the stability of the suspension protection structure of the existing pipeline can be improved. The waist beam 9 and the retaining wall 6 are both steel-concrete structures, and the two are cast into an integrated structure by concrete. The two ends of the retaining wall 6 are connected to the supporting piles 5 by the connecting bar 601 embedded bar method (refer to Figure 4 ), or the steel bars at both ends of the retaining wall 6 are welded to the main bars of the supporting piles 5.

[0037] The support beam 1 is made of Bailey beam or double I-beam. When the diameter of the pipeline is not less than 800mm, Bailey beam is preferably used. A group of support beams 1 is respectively arranged on both sides of the pipeline 7. Each group of support beams 1 includes two or more groups of Bailey plates. Adjacent groups of Bailey plates are connected by Bailey plate scissor braces to improve the stability of the support beam 1 structure. When the distance between the two pipelines 7 is close (such as when the distance between the two pipelines is not more than 2m), between the two pipelines 7, the two pipelines 7 can share a group of support beams 1. The support beam 1 and the crown beam 14 are connected by embedded parts 11 (refer to Figure 8 ), the support beam 1 and the embedded part 11 are connected by a limiter to prevent the support beam 1 from slipping and ensure the stability of the support beam 1; the limiter includes a connecting plate 19 and a support member 21, the two support members 21 are relatively arranged on the embedded steel plate 110, the support member 21 and the embedded steel plate 110 are welded, and the distance between the two support members 21 is not less than the width of the lower chord 17 of the Bailey plate of the support beam 1, the lower chord 17 adopts double-piece channel steel or double-piece I-beam, and the vertical rod 18 is arranged in the middle of the lower chord 17. When the lower chord 17 adopts double-piece channel steel, one or more connecting ribs 22 are arranged in the notch of the double-piece channel steel, and a slide groove 23 is arranged on the connecting rib 22. A connecting boss 20 is integrally provided at one end of the connecting plate 19, and the cross-sectional shape of the connecting boss 20 is rectangular, and a connecting groove running through the connecting boss 20 is arranged in the middle of the connecting boss 20 (reference Fig. 9), when the connecting rib 22 and the connecting plate 19 are connected, the connecting rib 22 is embedded in the connecting groove of the connecting boss 20, and the connecting rib 22 and the connecting plate 19 can be connected by bolts passing through the connecting holes on the connecting boss 20 and the sliding grooves 23 on the connecting rib 22 at the same time. After the connection, the nuts on the adjusting bolts can make the connecting plate 19 slide on the connecting rib 22. The support member 21 is made of channel steel or I-beam, and the support member 21 is provided with connecting holes, and the connecting plate 19 is provided with connecting grooves 24. When the connecting plate 19 slides to contact the top of the support member 21, the bolts are used to pass through the connecting grooves on the connecting plate 19 and the connecting holes on the support member 21 at the same time to connect and fix the connecting plate 19 and the support member 21. The limiter adopts a structure in which the connecting plate 19 and the supporting member 21 cooperate, which can stably install the support beam 1 on the embedded member 11, and also facilitate the later removal of the support beam 1. Figure 8 FIG. 2 shows the connection structure of the lower chord of one set of Bailey plates and the embedded parts when the support beam adopts Bailey beam. When the Bailey beam adopts multiple sets of Bailey plates, a limiter can be set on the lower chord of one or more sets of Bailey plates, or a limiter can be set on the lower chords on both sides of the Bailey beam (refer to FIG. 2 ). Fig.11 ), to ensure the stability of the connection between the Bailey beam and the embedded parts; when the supporting beam adopts double-piece I-beam, limiters can be set on both sides of the double-piece I-beam.

[0038] refer to Figure 6The suspension beam 2 includes two first beams 200 arranged opposite to each other, and there is a gap between the two first beams 200 for the suspension rod to pass through. The tops of the two first beams 200 are connected by a first connecting plate 201, and the bottoms are connected by a second connecting plate 202. The first connecting plate 201 and the second connecting plate 202 are coaxial, and the first beam 200 and the first connecting plate 201 are welded, and the first beam 200 and the second connecting plate 202 are welded. The first beam 200 is made of 25c channel steel, and a rib plate 203 is arranged in the notch of the first beam 200. A plurality of rib plates 203 are arranged along the length direction of the first beam 200, and a plurality of first connecting plates 201 and a plurality of second connecting plates 202 are arranged along the length direction of the first beam 200 to improve the overall structural strength of the suspension beam 2; at the suspension rod installation position, the number of rib plates 203 in the corresponding area can be increased to prevent the suspension beam 2 from deforming. The first crossbeam 200 is welded to the support beam 1 (or can be detachably connected) to prevent the suspension beam 2 from sliding on the support beam 1 and ensure the stability of the connection between the suspension beam 2 and the support beam 1. The structure of the joist beam 4 is the same as that of the suspension beam 2, including two second crossbeams arranged opposite to each other, with a gap between the two second crossbeams for the suspension rod to pass through, the tops of the two second crossbeams are connected by a first connecting plate, and the bottoms are connected by a second connecting plate, the first connecting plate and the second connecting plate are coaxial, the second crossbeam and the first connecting plate are welded, and the second crossbeam and the second connecting plate are welded. The second crossbeam is made of 25c channel steel, and a rib is arranged in the notch of the second crossbeam. Multiple ribs are arranged along the length direction of the second crossbeam, and multiple first connecting plates and multiple second connecting plates are arranged along the length direction of the second crossbeam; at the installation position of the suspension rod, the number of ribs in the corresponding area can be increased to prevent the joist beam from deforming.

[0039] The hanger rod 3 is made of finely rolled threaded steel with a diameter of 32-40 mm. The hanger rod 3 and the suspension beam 2 as well as the hanger rod 3 and the supporting beam 4 are connected through steel plate washers 12 and double nuts 13 .

[0040] refer to Fig.12 The method for suspended protection excavation of an existing pipeline according to an exemplary embodiment of the present invention comprises the following steps: Step 1: Construction preparation: clear the surface debris in the construction area.

[0041] Step 2: Survey the existing pipeline 7, mark the position of the existing pipeline 7 and the boundary line of the foundation pit excavation construction, and then construct support piles 5 along the boundary line of the foundation pit excavation construction (no support piles are set at the intersection of the existing pipeline and the boundary line of the foundation pit excavation construction).

[0042] The boundary line of foundation pit excavation construction is marked on the surface. According to the technical data of the existing pipeline 7, a combination of mechanical excavation and manual excavation is used to explore the trench of pipeline 7. First, at the end of pipeline 7 in the construction area (the intersection of the pipeline and the boundary line of foundation pit excavation construction), the existing soil layer on the surface is excavated by mechanical excavation. When the excavation is about 1m away from the top of pipeline 7, manual excavation is used to expose pipeline 7 to prevent pipeline 7 from being disturbed or damaged during the excavation process; after the pipeline 7 is exposed, a sign is set at the position of pipeline 7 to mark the position of the emerging pipeline 7; then, support piles 5 (cast-in-place piles) are constructed along the marked boundary line of foundation pit excavation construction to protect the soil in the foundation pit excavation construction area.

[0043] Step 3: construct the crown beam 14 of the foundation pit support to connect the adjacent support piles 5; construct the first foundation pit support 15 to connect the relative support piles 5.

[0044] The bottom elevation of the crown beam 14 is higher than the elevation of the pipeline 7, that is, the crown beam 14 is located above the pipeline 7 and crosses the pipeline 7; the crown beam 14 is a steel-concrete structure. During the construction of the crown beam 14, an embedded part 11 is set at the designed installation position of the support beam 1 on the crown beam 14. The embedded part 11 includes an embedded steel plate 110 and an anchor bolt 111 (refer to Figure 7 , Figure 8 ), the anchor bolt 111 is integrally formed with the embedded steel plate 110. When the embedded part 11 is set, the anchor bolt 111 is welded to the steel frame of the crown beam 14, and the embedded part 11 is poured in the crown beam 14 along with the concrete of the crown beam 14, so that the embedded part 11 is stably connected to the crown beam 14; the support 15 in the foundation pit is a steel-concrete structure, and the support 15 in the foundation pit is connected to the relative crown beam 14 or the supporting pile 5 into an integral structure (the support 15 in the foundation pit can be constructed at the same time as the crown beam 14); when constructing the supporting pile 5, multiple supporting piles 5 are arranged at intervals, and the distance between adjacent supporting piles 5 is determined according to the design requirements.

[0045] Step 4: Install support beam 1 and suspension beam 2.

[0046] Measure and lay out on the embedded steel plate 110 on the crown beam 14 to locate the installation position of the support beam 1, and then support the polytetrafluoroethylene plate 16 on the embedded steel plate 110 (the polytetrafluoroethylene plate can be glued to the embedded steel plate). The setting width of the polytetrafluoroethylene plate 16 is not less than the width of the support beam 1. When the support beam adopts double-piece I-beams, the width of the polytetrafluoroethylene plate is not less than the width of the double-piece I-beams. When the support beam adopts Bailey beams, the width of the polytetrafluoroethylene plate is not less than the width of the lower chord of the Bailey plate. After the support beam 1 is installed, it can play a shock-absorbing role in the subsequent excavation process, reducing the influence of soil deformation on the stability of the suspended protection structure.

[0047] After supporting the polytetrafluoroethylene plate 16, support members 21 are respectively arranged on both sides of the polytetrafluoroethylene plate 16. After the support members 21 are welded to the embedded steel plate 110, a crane is used to erect the support beam 1. When the support beam 1 adopts a Bailey beam, two or more groups of Bailey plates are recorded as a group of Bailey beams, and the Bailey plates of adjacent groups are connected by Bailey plate scissors struts. During the erection of the support beam 1, after the first group of Bailey plates are hoisted to the installation position by a crane, the first group of Bailey plates are moved below to between the two support members 21, and the lower chord 17 of the Bailey plates is made to contact the polytetrafluoroethylene plate 16. After the lower chord 19 of the first group of Bailey plates is connected to the support member 21 through the connecting plate 19, the second group of Bailey plates is installed in the same way as the first group of Bailey plates, and then the first group of Bailey plates and the second group of Bailey plates are connected by Bailey plate scissors struts to form a Bailey beam. After the first group of Bailey beams are installed, other Bailey beams are installed in the same way as the first group of Bailey beams. When the support beam 1 uses double I-beams, a crane is used to lift one group of double I-beams onto the polytetrafluoroethylene plate 16 at a preset position. After the double I-beams and the embedded steel plate 110 are connected by a limiter, the other double I-beams are installed in the same way as the first group of double I-beams.

[0048] After the support beam 1 is installed, a crane is used to install a suspension beam 2 perpendicular to the support beam 1 on the top of the support beam 1. Multiple suspension beams 2 are arranged along the length direction of the support beam 1, and the distance between adjacent suspension beams 2 is 1.2~1.8m (preferably 1.5m); the suspension beam 2 is welded to the support beam 1 to ensure the stability of the connection between the suspension beam 2 and the support beam 1; after the suspension beam 2 is installed, two or more suspension rods 3 are arranged on each suspension beam 2, and the number of suspension rods 3 is determined according to the number of pipelines 7 and the lifting requirements of pipelines 7; when two suspension rods 3 are arranged, the two suspension rods 3 are symmetrically arranged relative to the pipelines 7 to ensure the stability of the suspension of the pipelines 7; the suspension rod 3 and the suspension beam 2 are connected by a steel plate gasket 12 and a double nut 13, and the height of the suspension rod 3 is adjustable; the suspension rod 3 can be installed after the suspension beam 2, or it can be installed during the suspension of the pipeline 7.

[0049] Step 5: Excavate the earth in layers at the intersection of the pipeline 7 and the edge line of the foundation pit excavation construction to the bottom elevation of the pipeline 7, and construct the retaining wall 6 in layers between the top of the pipeline 7 and the crown beam 14.

[0050] Excavate 1~1.8m downward in the soil direction to form a retaining wall construction area, tie the retaining wall steel bars 600 in the retaining wall construction area, implant the connecting bars 601 into the supporting piles 5 at the connecting position of the retaining wall steel bars 600 and the supporting piles 5, and then weld the connecting bars 601 to the retaining wall steel bars 600 to connect the retaining wall steel bars 600 and the supporting piles 5 into an integral structure; when the retaining wall steel bars 600 and the supporting piles 5 are connected, the surface of the supporting piles 5 can also be chiseled off at the connecting position of the supporting piles 5 to expose the main bars of the supporting piles 5, and then the main bars of the supporting piles 5 can be welded to the retaining wall steel bars 600; at the connecting position of the retaining wall steel bars 400 and the crown beam 14, implant the connecting bars into the crown beam 14, weld the retaining wall steel bars 600 and the crown beam steel bars to connect the retaining wall steel bars 600 and the crown beam 14 into an integral structure. After the retaining wall reinforcement 600 is tied, the retaining wall formwork 25 is supported on both sides of the retaining wall reinforcement 600. The opposite retaining wall formwork 25 is connected by a tie rod. The retaining wall formwork 25 is reinforced by a vertical back rib 250 (using a 50mm×100mm wooden square) and a horizontal back rib 251 (using a double steel pipe of φ48×3.5mm). The formwork on the side away from the soil is also reinforced by a diagonal brace 252 (using a steel pipe) (refer to Fig.10 ), the vertical back rib 250 is arranged between the panel and the horizontal back rib 251; the retaining wall template 25 is 1-1.8m high, and multiple horizontal back ribs 251 are arranged along the height direction of the retaining wall template 25, and the diagonal braces 252 support the horizontal back rib 251. At the contact part between the support pile 5 and the retaining wall template 25, part of the surface of the support pile 5 is chiseled off so that the installation angle of the retaining wall template 25 meets the requirements and reduces the intrusion limit; after the retaining wall template 25 is installed, the gaps on both sides of the retaining wall template 25 are blocked to ensure the construction quality of the retaining wall 6.

[0051] After the retaining wall formwork 25 is set up, C40 early-strength concrete is used to cast the retaining wall 6 to reduce the exposure time of the soil after excavation and reduce soil deformation; after the concrete of the retaining wall 6 reaches the demoulding strength, the retaining wall formwork 25 is removed, and the flatness of the surface of the retaining wall 6 is checked. When the surface of the retaining wall 6 is convex, the intrusion is removed. When the surface of the retaining wall 6 is concave, a steel mesh is hung on the surface of the retaining wall 6 and sprayed with anchors for leveling; when water leakage occurs in the retaining wall 6, drainage and sealing treatment are carried out to ensure the waterproof construction quality of the retaining wall 6; the upper edge thickness of the retaining wall 6 is 150mm thicker than the lower edge thickness to facilitate the pouring of concrete.

[0052] Due to the interference of pipeline 7, the construction of supporting piles 5 needs to avoid pipeline 7, resulting in the inability to form a continuous supporting pile 5 enclosure structure on both sides of pipeline 7. The soil at the position of pipeline 7 is prone to deformation, and problems such as slippage, collapse and leakage are prone to occur during pipeline suspension protection and foundation pit excavation. Before the pipeline is suspended, a retaining wall is constructed to connect the supporting piles on both sides of the pipeline into a enclosure structure, which improves the deformation resistance. When the buried depth of the pipeline is deeper (such as: the buried depth is not less than 5m), it is more conducive to reducing the impact of soil deformation during the pipeline suspension process and avoiding pipeline damage.

[0053] Step six, suspend the pipeline 7; after the compressive strength of the retaining wall 6 is not less than 30Mpa, the pipeline 7 is suspended and protected in sections along the length direction of the pipeline 7.

[0054] Within the boundary line of foundation pit excavation construction, the soil around the first pipe section is manually excavated from one end of pipeline 7 at a distance of 1.5 to 2 m from the crown beam. The excavation length is 3 to 4 m, and the excavation depth is determined according to the suspension protection requirements of pipeline 7. After the excavation depth meets the requirements, a support beam 4 is placed on the soil under the first pipe section. The support beam 4 and the first pipe section are perpendicular to each other. After connecting the support beam 4 and the hangers 3 on both sides of the first pipe section, the height of the hanger 3 is adjusted so that the support beam 4 can support and drag the first pipe section. Before the joist 4 supports the first pipe section, an encapsulation structure 8 can also be constructed on the first pipe section to improve the protection effect of the first pipe section; the cross-sectional shape of the encapsulation structure 8 is generally rectangular, and the construction process of the encapsulation structure 8 includes: adjusting the height of the hanger 3 so that the distance between the joist 4 and the first pipe section meets the construction requirements of the encapsulation structure 8; installing an encapsulation bottom mold on the joist 4, the encapsulation bottom mold is coaxially arranged with the first pipe section, and both sides of the encapsulation bottom mold are 200mm wider than the edge of the first pipe section (that is, the width of the encapsulation bottom mold is 400mm larger than the diameter of the first pipe section), and the encapsulation bottom mold is supported by the adjacent joist 4; after the encapsulation bottom mold is installed, a steel mesh 800 of Ф8@200mm is arranged on the encapsulation bottom mold, and along the length direction of the first pipe section, the setting length of the steel mesh 800 is greater than the encapsulation structure 8 is designed to facilitate the effective overlap of adjacent sections of the encapsulation structure 8, ensure the integrity and continuity of the encapsulation structure 8, and ensure the overall strength of the encapsulation structure 8; the overlap length between the steel meshes 800 of adjacent sections of the encapsulation structure 8 is not less than 40 cm; after the steel mesh 800 wraps the first pipe section, the encapsulation side formwork is installed on the encapsulation bottom formwork to enclose a casting space for the encapsulation structure 8, and then concrete is poured in the casting space. After the concrete reaches the demolding strength, the encapsulation side formwork is removed, the height of the hanger 3 is adjusted to move the support beam 4 downward, and after the encapsulation bottom formwork is removed, the height of the hanger 3 is adjusted to make the support beam 4 contact with the bottom of the encapsulation structure 8 to support the encapsulation structure 8, and then the hanger 3 is pre-tensioned with a pre-tensioning force of 50 kN to ensure the stability of the suspension of the first pipe section. After the first pipe section is suspended, other pipe sections are constructed along the length direction of pipeline 7 in the same way as the first pipe section. The length of each pipe section is 3 to 4 meters, until the pipeline 7 within the edge of the foundation pit excavation construction is suspended.

[0055] Step seven, excavate the earth in layers within the foundation pit excavation construction area surrounded by the supporting piles 5, and construct the retaining wall 6 in layers; after excavating the earth downward by 1~1.8m, construct the retaining wall 6 in the same way as step five; during the construction of the retaining wall 6, when the retaining wall steel bars 600 are connected with the already constructed retaining wall steel bars 600, the longitudinal main bars of the retaining wall steel bars 600 are welded to the longitudinal steel bars of the already constructed retaining wall 6 or connected through sleeves to ensure the integrity and continuity of the retaining wall 6 structure; in the length direction of the retaining wall 6, the number of joints of the longitudinal steel bars shall not exceed 50%.

[0056] Step 8, repeat step 7 until the construction reaches the base elevation; repeat the construction process of retaining wall 6, after the compressive strength of the constructed retaining wall is not less than 30Mpa, then excavate and construct the retaining wall to be constructed under this section of retaining wall; repeat the construction process of retaining wall 6, construct waist beam 9 at the designed position of retaining wall 6 to further improve the stability of retaining wall 6; the distance between the first waist beam 9 and the bottom of pipeline 7 is 1.7~3m, and the distance between adjacent waist beams 9 is determined according to design and construction requirements; waist beam 9 is cast with C40 early-strength concrete, and waist beam 9 is integrally formed with retaining wall 6. Before the construction of retaining wall 6 and waist beam 9, anchor cable 10 is constructed on the side wall of the soil according to design requirements, so that the anchor cable 10 is embedded in the side wall of the soil, and then the retaining wall steel bars 600 and waist beam 9 steel bars are tied to construct retaining wall 6 and waist beam 9. During the downward excavation, in order to further reduce soil displacement, improve the supporting effect of the supporting piles 5, and improve the stability of the pipeline 7 suspension, after each downward excavation to a certain depth, a foundation pit support 15 is constructed, and the two ends of the foundation pit support 15 are respectively connected to the supporting piles 5.

[0057] The above is only a detailed description of the specific implementation of the present invention, rather than a limitation of the present invention. Various substitutions, modifications and improvements made by those skilled in the relevant art without departing from the principle and scope of the present invention should be included in the protection scope of the present invention.

Claims

1. A method for suspension protection excavation of an existing pipeline, characterized in that: The following steps are involved: Step 1: Construction preparation, clearing the surface debris in the construction area; Step 2: Survey the existing pipelines, mark the locations of the existing pipelines and the edge lines of the foundation pit excavation, and then construct support piles along the edge lines of the foundation pit excavation; Step 3: construct the crown beam of the foundation pit support and connect the adjacent support piles; construct the first support in the foundation pit and connect the relative support piles; Step 4: Install support beams and suspension beams; Step 5: Excavate the earth in layers at the intersection of the pipeline and the foundation pit excavation construction line to the bottom elevation of the pipeline, and construct the retaining wall in layers between the top of the pipeline and the crown beam; Step 6: Suspend the pipeline; after the compressive strength of the retaining wall is not less than 30Mpa, perform pipeline suspension protection construction in sections along the length of the pipeline; Step 7: Excavate the earth in layers within the foundation pit excavation construction area surrounded by the support piles, and construct the retaining wall in layers; after excavating the earth downward by 1 to 1.8 m, construct the retaining wall in the same way as step 5; Step 8. Repeat step 7 until the construction reaches the base elevation.

2. The method for suspended protection excavation of an existing pipeline according to claim 1, characterized in that: In the step three, during the construction of the crown beam, embedded parts are set at the designed installation position of the support beam on the crown beam. The embedded parts include embedded steel plates and anchor bolts. When setting the embedded parts, the anchor bolts are welded to the steel frame of the crown beam, and the embedded parts are poured on the crown beam along with the crown beam concrete.

3. The method for suspended protection excavation of an existing pipeline according to claim 2, characterized in that: In step 4, the installation process of the support beam includes: Measure and lay out on the embedded steel plate to locate the installation position of the support beam; Support the polytetrafluoroethylene plate on the embedded steel plate; Support members are respectively arranged on both sides of the polytetrafluoroethylene plate; The support beam is installed by a crane. After the support beam is hoisted onto the polytetrafluoroethylene plate, a connecting plate is used to connect the support beam and the support member.

4. The method for suspended protection excavation of an existing pipeline according to claim 1, characterized in that: In step four, the installation process of the suspension beam includes: using a crane to install a suspension beam perpendicular to the support beam on the top of the support beam, multiple suspension beams are arranged along the length direction of the support beam, and the suspension beam is fixedly connected to the support beam.

5. The method for suspended protection excavation of an existing pipeline according to claim 1, characterized in that: In step 6, the pipeline suspension process includes: Within the boundary line of the foundation pit excavation, the soil around the first pipe section of the pipeline is manually excavated from one end of the pipeline at a distance of 1.5 to 2 meters from the crown beam; Placing a joist on the soil below the first pipe section, wherein the joist and the first pipe section are perpendicular to each other; After connecting the joist beam to the suspension rods on both sides of the first pipe section, adjust the height of the suspension rods so that the joist beam can support and drag the first pipe section; Along the length of the pipeline, other sections are constructed in the same way as the first section, with each section being 3 to 4 meters long, until the pipeline is suspended within the edge of the foundation pit excavation construction.

6. The method for suspended protection excavation of an existing pipeline according to claim 5, characterized in that: Before the joist supports the first pipe section, an encapsulation structure is constructed on the first pipe section. The construction process of the encapsulation structure includes: Adjust the height of the hanger rod so that the distance between the joist and the first pipe section meets the construction requirements of the encapsulation structure; Installing a sealing bottom mold on the joist, the sealing bottom mold is coaxially arranged with the first pipe section, both sides of the sealing bottom mold are 200 mm wider than the edge of the pipeline, and the sealing bottom mold is supported by adjacent joists; Arranging a steel mesh on the encapsulation bottom mold so that the steel mesh wraps the first pipe section; Install the encapsulation side mold on the encapsulation bottom mold to enclose the casting space of the encapsulation structure; Pour concrete in the pouring space, and remove the encapsulating side formwork after the concrete reaches the demoulding strength; Adjust the height of the hanger rod to move the joist downward; Remove the bottom formwork of the envelope and adjust the height of the hanger so that the joist contacts the bottom of the envelope structure to support the envelope structure; Pre-tension the hanger.

7. The method for suspended protection excavation of an existing pipeline according to claim 1, characterized in that: In step 5, the process of constructing the retaining wall includes: At the end of the pipeline, dig 1~1.8m downward to form a retaining wall construction area; Tie the retaining wall reinforcement within the retaining wall construction area; Support the retaining wall formwork on both sides of the retaining wall reinforcement; C40 early-strength concrete is used to cast the retaining wall.

8. The method for suspended protection excavation of an existing pipeline according to claim 1, characterized in that: In the step eight, during the repeated retaining wall construction process, after the compressive strength of the constructed retaining wall is not less than 30Mpa, the retaining wall to be constructed is constructed under the retaining wall.

9. The method for suspended protection excavation of an existing pipeline according to claim 1, characterized in that: In step eight, during the repeated retaining wall construction process, a waist beam is constructed at the designed position of the retaining wall, and the waist beam is formed integrally with the retaining wall. Before the construction of the retaining wall and the waist beam, anchor cables are constructed on the side walls of the soil according to the design requirements, so that the anchor cables are embedded in the side walls of the soil. Then, the retaining wall steel bars and the waist beam steel bars are tied to construct the retaining wall and the waist beam.

10. The method for suspended protection excavation of an existing pipeline according to any one of claims 1 to 9, characterized in that: When the distance between the two pipelines is not greater than 2m, in the process of installing the support beams in step 4, a set of support beams is installed between the two pipelines so that the two pipelines share a set of support beams.

Citation Information

Patent Citations

  • Large-diameter bell and spigot water supply concrete pipe hanging protection system and construction method thereof

    CN109296825A

  • Suspending protecting structure and method for high-voltage electricity pipeline on top of deep foundation pit

    CN110578343A

  • Foundation pit supporting structure capable of avoiding relocation and reformation of existing pipeline and construction method of foundation pit supporting structure

    CN115506366A

  • Supporting construction of petroleum pipeline line

    CN207213329U

  • Support device for pipeline in comprehensive pipe rack

    CN214222215U

Cited By

  • Discharging hole working pipe suspension supporting structure

    CN119777887A

  • Deep foundation pit engineering suspension protection deeply-buried pipeline and construction method

    CN120331304A

  • F-beam prefabricating method

    CN121200199A

  • Construction method and device for replacing underground drainage pipeline crossing deep foundation pit with steel pipeline

    CN121451670A