Construction method of general-span tunnel non-full-height temporary support CD method

By dividing the tunnel section into seven construction areas and using non-full height temporary support CD method, the problems of low construction efficiency and long initial support deformation time in general span tunnel construction are solved, and more efficient and safe Construction effect.

CN119021716APending Publication Date: 2024-11-26CHINA COMM GUANGHANG BUREAU FIFTH ENG CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411221919.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-02
Publication Date
2024-11-26

AI Technical Summary

Technical Problem

In general span tunnel construction, the traditional CD method has low construction efficiency due to the large excavation and large interference, inconvenient mechanical operation, long deformation time of initial branch, and is not conducive to the safety of weak surrounding rock tunnels.

Method used

The tunnel section is divided into seven construction areas, and the non-full height temporary support CD method is adopted. By reasonably designing the excavation depth and support structure, the temporary support of the partition wall in the lower step is cancelled, the excavation segmentation and process are adjusted, and the trest bridge is set up to During the equipment passage and construction, the deformation is monitored in real time to determine the timing of the support and demolition.

Benefits of technology

It improves construction efficiency and safety, shortens the initial ring formation time, reduces construction costs, and ensures the stability of the tunnel structure and the convenience of construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119021716A_ABST
    Figure CN119021716A_ABST
Patent Text Reader

Abstract

The invention provides a construction method of a general-span tunnel non-full-height temporary support CD method. The construction method comprises the following steps that S1, the section of a tunnel is divided into seven construction areas; s2, a first pilot tunnel is excavated, and a first permanent primary support and a first temporary support are constructed; s3, a second pilot tunnel is excavated, and a second permanent primary support and a second temporary support are constructed; s4, a third pilot tunnel is excavated, and a third permanent primary support is constructed; s5, a fourth pilot tunnel is excavated, and a fourth permanent primary support is constructed; s6, a fifth pilot tunnel is excavated, and a fifth permanent primary support is constructed; s7, a middle partition wall formed by the first temporary support and the second temporary support is dismantled; s8, a sixth pilot tunnel is excavated, and a sixth permanent primary support is constructed; s9, a seventh pilot tunnel is excavated, and a seventh permanent primary support is constructed; s10, a trestle bridge is installed in a crossing mode; s11, a secondary lining, an inverted arch and inverted arch filling are constructed; and S12, the steps S2-S11 are repeated to complete tunnel construction. The method is stable in process and convenient to operate, and has good economic benefits.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of tunnel construction, in particular to a construction method of a CD method for temporary support of a general span tunnel with non-full height. Background Art

[0002] According to the surrounding rock level and span size, the excavation methods of mountain highway tunnels can be roughly divided into three methods: full-section method, step method and partial excavation method. The partial excavation method can be further divided into circular excavation with reserved core soil method, CD method, cross CD method, single side wall pilot method, double side wall pilot method, etc. The CD method is generally used when the geological conditions are poor. However, in actual engineering applications, due to the large number of excavation blocks, small cross-sections of each block, many processes and large interference, it seriously affects the efficiency of mechanical construction; and due to the slow advance of the face, the initial support deformation time is indirectly extended, which is not conducive to the construction safety of soft surrounding rock tunnels. At present, there are few summaries and studies on the applicability of tunnel design parameters and construction methods, and there are few improved methods. Especially in the face of general span tunnel construction, due to limited space, it is inconvenient for large equipment to enter the site for operation, and it is not conducive to the correction of the state. When the traditional method is used for construction, there is a partition of the inverted arch pilot pit, and the equipment on both sides cannot be flexibly adjusted, and the construction efficiency is low.

[0003] Chinese patent document CN 109594991 A records a rapid construction method for a shallow-buried soft rock extra-large cross-section tunnel combining the CD method and the step method, but this method is not applicable to tunnels of general spans; Chinese patent document CN 108131143A records a construction method for a super-large span tunnel using the step CD method, which also has the above-mentioned problems, has defects in use, and needs to be improved. Summary of the invention

[0004] The invention provides a construction method of a CD method for temporary support of a general span tunnel with non-full height, which solves the technical problems of inconvenient construction, large interference and slow looping speed.

[0005] In order to solve the above technical problems, the technical solution adopted by the present invention is: a construction method of a general span tunnel non-full height temporary support CD method, comprising the following steps: S1. Divide the tunnel section into seven construction areas from top to bottom and rationally design the excavation depth of different areas; S2, excavate the first pilot pit and implement the first permanent initial support and the first temporary support; S3, excavate the second pilot pit and implement the second permanent initial support and the second temporary support; S4, excavate the third pilot pit and implement the third permanent initial support; S5. Excavate the fourth pilot pit and construct the fourth permanent primary support; S6. Excavate the fifth pilot pit and construct the fifth permanent primary support; S7, removing the middle partition formed by the first temporary support and the second temporary support beyond the design distance of the fourth pilot pit end face, ensuring that the end face of the middle partition and the invert are staggered to form a transverse temporary working face; S8, excavate the sixth pilot pit and construct the sixth permanent primary support; S9, excavate the seventh pilot pit and construct the seventh permanent primary support; S10, the seventh pilot pit and the middle partition are kept at a distance, and a trestle is installed across the upper side of the seventh pilot pit; S11, construct secondary lining, invert and invert filling, and complete the pouring of tunnel top and bottom; S12. Repeat S2 to S11 until the overall tunnel construction is completed.

[0006] In the preferred scheme, during the construction process of the first pilot pit, the second pilot pit, the third pilot pit, the fourth pilot pit, the fifth pilot pit, the sixth pilot pit and the seventh pilot pit, it is necessary to install locking anchor pipes, lay steel mesh, and carry out initial support spraying and anchor rods at the same time. The width of the fifth guide pit and the sixth guide pit is less than two meters, and the width of the first guide pit is greater than seven meters.

[0007] In the preferred solution, in S7, the timing of dismantling the middle partition wall support is determined based on the monitoring and measurement data. The support can be dismantled only after the tunnel deformation is stable, and the stability of the initial support structure of the tunnel should be ensured during the dismantling process. Starting from the end face of the fourth pilot pit, the temporary support of the middle partition wall should be retained for at least five meters.

[0008] In the preferred solution, in S3, reinforced concrete is used for temporary support at the bottom of the second temporary support to reduce settlement. In S9, in order to prevent deformation and settlement, the excavation footage is not more than three meters at a time, and the excavation process reduces the vibration impact of the mechanical operation process.

[0009] In the preferred solution, in S1, the construction process is controlled by combining the excavation section depth with the designed reserved deformation according to the geological conditions of the surrounding rock, and the designed reserved deformation is adjusted in real time according to the monitoring results, and the weak points are reinforced.

[0010] In the preferred solution, for construction of extremely unstable gravel soil surrounding rock, spraying concrete before the construction of steel and steel mesh will cause great disturbance to it, and the initial spraying concrete cannot play a supporting role, so the initial spraying can be omitted; The manufacturing dimensions of the steel arch frame are controlled according to the actual deformation reserve, and the frame is trial-assembled and numbered at the reinforcement yard, with the installation position noted to ensure the installation accuracy in the hole.

[0011] In the preferred scheme, in order to reduce the disturbance of the advance support drilling operation and avoid serious block falling or even local collapse, the advance support process is adjusted from "erecting the steel arch frame first, then laying out the advance support and finally spraying concrete" to "erecting the steel arch frame first, then spraying concrete (reserving the arch guide holes but not spraying) and finally laying out the advance support".

[0012] In the preferred scheme, the spraying concrete operation should be carried out in layers from the arch feet on both sides to the arch top. When spraying, the low-lying areas should be roughly sprayed flat first, and then sprayed in a spiral reciprocating manner. When spraying, the nozzle should be as perpendicular to the sprayed surface as possible, the angle should not be less than 70°, and the distance should be kept at 0.6~1.5 meters; The angle and length of the advance support are strictly constructed according to the design requirements. When the angle is restricted by the steel arch frame and cannot be constructed according to the design, the angle is easier to be smaller than larger to ensure the effective support length.

[0013] In the preferred solution, the timing of demolition of the middle partition wall is strictly controlled. When the initial support construction of the fifth pilot pit is completed and the distance to the fourth pilot pit is greater than five meters, it can be demolished one by one. The length of demolition at one time shall not be greater than three meters. When dismantling the temporary support, the initial support of the pilot pit under the same pile number shall be sprayed and mixed first.

[0014] In the preferred solution, after the temporary support of the middle partition wall is removed, the construction time of the sixth and seventh pilot pits is strictly controlled, and the position of the trestle is moved and adjusted according to the excavation position to improve the convenience of construction and ensure that the construction of the invert is completed within the design time.

[0015] The beneficial effects of the present invention are as follows: by distinguishing the cross-section of the tunnel, the safety and stability of the overall construction are guaranteed, the supports between different guide pits cooperate with each other, one side of the middle partition wall and the formed ring structure form a stable support foundation, and then a trestle is set up. The trestle is convenient for the passage of construction equipment and manpower, thereby facilitating the operation. The middle partition wall ensures that the construction has sufficient operating space while playing a supporting role, which greatly alleviates the problem of different forces on the upper side of the tunnel. The present invention has high construction efficiency, ensures the safety of construction and has good economic benefits. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] The present invention will be further described below in conjunction with the accompanying drawings and embodiments: Figure 1 This is a schematic diagram of the construction section of the present invention. Figure 1 ; Figure 2 This is a schematic diagram of the construction section of the present invention. Figure 2 ; Figure 3 This is a schematic diagram of the construction section of the present invention. Figure 3 ; Figure 4 This is a schematic diagram of the construction section of the present invention. Figure 4 ; Figure 5 This is a schematic diagram of the construction section of the present invention. Figure 5 ; Figure 6 This is a schematic diagram of the construction section of the present invention. Figure 6 ; Figure 7 It is a front view schematic diagram of the construction of the present invention; Figure 8 The internal structure of the present invention is shown in FIG. Figure 1 ; Fig. 9 The internal structure of the present invention is shown in FIG. Figure 2 ; Fig.10 The internal structure of the present invention is shown in FIG. Figure 3 ; Fig.11 It is a process flow chart of the construction of the present invention; Fig.12 It is a monitoring data diagram of the construction of the present invention.

[0017] In the figure: first pilot pit 1; first permanent initial support 101; first temporary support 102; second pilot pit 2; second permanent initial support 201; second temporary support 202; third pilot pit 3; third permanent initial support 301; fourth pilot pit 4; fourth permanent initial support 401; fifth pilot pit 5; fifth permanent initial support 501; sixth pilot pit 6; sixth permanent initial support 601; seventh pilot pit 7; seventh permanent initial support 701; initial support injection 8; secondary lining 9; invert 10; invert filling 11; trestle 12; quick-setting concrete hole 13. DETAILED DESCRIPTION

[0018] like Figure 1-11 A construction method of a CD method for temporary support of a general span tunnel with non-full height includes the following steps: S1. Divide the tunnel section into seven construction areas from top to bottom and rationally design the excavation depth of different areas; S2, excavating the first pilot pit 1 and implementing the first permanent initial support 101 and the first temporary support 102; during excavation, the step length is not more than 3m; S3, excavating the second pilot pit 2 and implementing the second permanent initial support 201 and the second temporary support 202; S4, excavate the third pilot tunnel 3 and implement the third permanent initial support 301; the step length is not more than 3m, and the distance from the current pilot tunnel is not more than 13m; S5, excavating the fourth pilot pit 4 and constructing the fourth permanent initial support 401; S6, excavating the fifth pilot pit 5 and constructing the fifth permanent initial support 501; S7. Remove the intermediate partition formed by the first temporary support 102 and the second temporary support 202 beyond the design distance of the end face of the fourth pilot pit 4 to ensure that the end face of the intermediate partition and the invert are offset to form a temporary transverse working surface; according to the monitoring and measurement data, remove the temporary support of the intermediate partition after the deformation of the tunnel is stable, and retain at least 5m (starting from the fourth pilot pit 4) during the removal process to ensure the stability of the tunnel primary support structure S8, excavating the sixth pilot pit 6 and constructing the sixth permanent primary support 601; S9, excavating the seventh pilot pit 7 and constructing the seventh permanent primary support 701; S10, the seventh pilot pit 7 and the middle partition wall are kept at a distance, and a trestle 12 is installed across the upper side of the seventh pilot pit 7; S11, constructing secondary lining 9, invert 10 and invert filling 11, and completing the pouring of the top and bottom of the tunnel; S12. Repeat S2 to S11 until the overall tunnel construction is completed.

[0019] The general span tunnel is a single-hole two-lane highway tunnel or a highway tunnel with an excavation width of less than 14m and greater than or equal to 9m. During the CD method construction of the tunnel, the temporary support height is shortened, the horizontal excavation section of the lower step and the excavation timing of the middle section are adjusted, and other process optimizations are carried out to solve the problems of limited working space, low construction efficiency, slow closure and ring formation in the application of the traditional CD method in general span tunnels. The problem is avoided that the initial support deformation time is extended due to slow closure and ring formation, and the arch foot and the temporary support arch foot are suspended in the air at the same time when the lower step and invert arch of the pilot tunnel are excavated.

[0020] By canceling the temporary support of the middle partition of the lower step, and adjusting the two-section excavation of the lower step to three sections of excavation: left, middle and right, with the width of the left and right sections less than 2mm and the width of the middle section greater than 7m, the horizontal construction space for machinery is guaranteed; Do not pursue the temporary support of the middle partition wall closely following the invert arch. The middle partition wall can be more than 5m away from the middle step of the subsequent pilot tunnel. The middle section of the lower step should be reserved and excavated together with the subsequent invert arch. Before that, it will serve as a construction passage between the tunnel face and the tunnel face. The traditional CD method is generally used when the geological conditions are poor. However, in actual engineering applications, due to the large number of excavation blocks, small cross-sections of each block, many processes and large interference, it seriously affects the efficiency of mechanical construction. In addition, due to the slow advance of the face, the initial support deformation time is indirectly prolonged, which is not conducive to the construction safety of soft surrounding rock tunnels. The traditional CD method excavates the lower step of the existing pilot tunnel at one time, which will cause the temporary support of the middle partition wall to be suspended at the same time. This problem is avoided by canceling the temporary support of the middle partition wall of the lower step and reserving the middle span of the step and the subsequent invert for one excavation. The temporary support of the middle partition wall plays the role of cantilever beam support, which is conducive to the stability of the initial support. Improve the efficiency of mechanized construction, shorten the time for initial support ring formation, and the second lining can be followed up in time when the progress of the face is fast, thus reducing the deformation time of the initial support.

[0021] The total length of the project is nearly 4 kilometers. It is a special-length highway tunnel with a maximum buried depth of nearly 900 meters. The exit passes through a shallow gravel soil layer of more than 100 meters, with a buried depth of about 0 to 50 meters. The geology of this section is slope alluvial gravel soil, with a slightly dense structure, weak cementation, strong permeability and poor self-stability. Because the shallow buried section at the exit of the tunnel is long, surface water quickly penetrates into the tunnel excavation surface under the influence of rainfall, which further reduces its cementation and increases its natural bulk density, which will greatly reduce its self-stability; and the area is a strong active fault zone transitioning from basin to plateau, with strong fault activity and seismic activity. It is very easy to collapse under the disturbance of tunnel excavation and drilling, and it is difficult to form a hole. This is the section with the worst tunnel geology and the most difficult excavation in this project.

[0022] According to the traditional CD method in the Technical Specifications for Highway Tunnel Construction, the construction is divided into the left half and the right half, and a middle partition is set between the left and right halves. At the same time, since the tunnel of this project belongs to the general span tunnel (9 meters ≤ excavation width < 14 meters) specified in the Technical Specifications for Highway Tunnel Construction, the internal construction space is very limited and needs to be used reasonably. At the same time, the limited space restricts the space for movement, displacement and turning of the on-site equipment, making excavation very inconvenient. The traditional middle partition is flush with the end face of the seventh pilot pit 7, so the left and right spaces are completely independent. At this time, the width of the left and right spaces is only 4.5 meters ≤ half width < 7 meters, which does not meet the passing conditions for equipment excavation construction. This scheme is to offset the middle partition and the end face of the seventh pilot pit 7, exceeding the end face of the middle partition. The partial and left and right supporting structures provide sufficient construction channels for the equipment and facilitate the equipment to move left and right and turn around. In addition, it needs to be constructed simultaneously with the initial support of the invert (half-width). The closing time of the initial support of the half-width is relatively long, which is not conducive to construction safety. After the middle partition wall divides the excavation surface into two, its half-width is small, and the vertical excavation is divided into three parts, which lengthens the depth of the pilot tunnel and increases the problem of limited rotation range of the excavator, seriously affecting its work efficiency. The invert follows the middle partition wall, and the pre-construction is carried out before the pilot tunnel heading construction. The position of the invert trestle must be frequently adjusted to the left and rear to achieve this. In addition, due to space limitations, the interference between the invert and the heading construction is relatively large, and flow operation cannot be achieved. This construction method has low work efficiency and slow progress, resulting in late construction of the secondary lining, which prolongs the settlement and deformation time of the initial support, which is not conducive to construction safety.

[0023] In the preferred solution, during the construction of the first pilot pit 1, the second pilot pit 2, the third pilot pit 3, the fourth pilot pit 4, the fifth pilot pit 5, the sixth pilot pit 6 and the seventh pilot pit 7, it is necessary to install locking anchor pipes, lay steel mesh, and simultaneously carry out initial support spraying 8 and install anchor rods. The width of the fifth pilot pit 5 and the sixth pilot pit 6 is less than two meters, and the width of the first pilot pit (7) is greater than seven meters.

[0024] This plan divides the excavation surface into 7 blocks, namely, the upper and middle parts of the left advance guide tunnel, the upper and middle parts of the right rear guide tunnel, and the non-full high school next door into left, middle and right parts. The left and right are not divided into lower steps, the excavation section is smaller, the middle part is the invert, the entire excavation, and the initial support, invert and its filling are constructed.

[0025] It has the following features: (1) The temporary initial support (support) of the middle wall of the lower step is cancelled, the excavation width of the left and right lower guide pits is reduced, and a reserved construction channel in the middle is excavated together with the subsequent invert. This solves the problem of the steel arch frame of the lower step of the left pilot tunnel and the temporary support steel arch frame being suspended in the air at the same time (due to the small space, they cannot be staggered front and back). This meets the requirements of the standard for the excavation of the entire invert, and at the same time, the invert and the heading face are constructed simultaneously without interfering with each other.

[0026] (2) The pilot tunnel is excavated vertically in two parts. The pilot tunnel is shallow, and after the lower step is excavated, the middle part is reserved for excavation together with the invert arch, which greatly reduces the rotation range of the excavator and improves work efficiency. At the same time, because the temporary support of the middle partition wall does not fall to the bottom of the invert arch, the temporary support of the middle partition wall plays the role of a cantilever beam support when the steps on both sides are constructed, which ensures safety.

[0027] (3) Compared with the traditional CD method, it does not pursue the temporary support of the invert closely following the middle partition wall, thereby solving the problem of limited space from the invert to the left and right guide pits for large equipment (excavators, muck trucks, loaders, wet spraying machines) to pass through the invert trestle, thus realizing streamlined operation.

[0028] (4) The deformation convergence time of weak surrounding rock suitable for CD method is long and the deformation is large. Timely construction of secondary lining is one of the effective methods to suppress the deformation of primary support. Improving the progress of face excavation creates necessary conditions for the construction of secondary lining.

[0029] In the preferred scheme, in S7, the timing of dismantling the middle partition wall support is determined based on the monitoring and measurement data. The support can be dismantled only after the tunnel deformation is stable, and the stability of the initial support structure of the tunnel should be ensured during the dismantling process. Starting from the end face of the fourth pilot pit 4, the temporary support of the middle partition wall should be retained for at least five meters.

[0030] In the preferred solution, in S3, reinforced concrete is used for temporary support at the bottom of the second temporary support 202 to reduce settlement. In S9, in order to prevent deformation and settlement, the excavation footage is not more than three meters at a time, and the excavation process reduces the vibration and impact of the mechanical operation process.

[0031] In the preferred solution, in S1, the construction process is controlled by combining the excavation section depth with the designed reserved deformation according to the geological conditions of the surrounding rock, and the designed reserved deformation is adjusted in real time according to the monitoring results, and the weak points are reinforced.

[0032] In the preferred solution, for construction of extremely unstable gravel soil surrounding rock, spraying concrete before the construction of steel and steel mesh will cause great disturbance to it, and the initial spraying concrete cannot play a supporting role, so the initial spraying can be omitted; The manufacturing dimensions of the steel arch frame are controlled according to the actual deformation reserve, and the frame is trial-assembled and numbered at the reinforcement yard, with the installation position noted to ensure the installation accuracy in the hole.

[0033] In the preferred scheme, in order to reduce the disturbance of the advance support drilling operation and avoid serious block falling or even local collapse, the advance support process is adjusted from "first erecting the steel arch frame, then laying out the advance support and finally spraying concrete" to "first erecting the steel arch frame, then spraying concrete, reserving the arch frame guide holes without spraying, and finally laying out the advance support".

[0034] In the preferred scheme, the spraying concrete operation should be carried out in layers from the arch feet on both sides to the arch top. When spraying, the low-lying areas should be roughly sprayed flat first, and then sprayed in a spiral reciprocating manner. When spraying, the nozzle should be as perpendicular to the sprayed surface as possible, the angle should not be less than 70°, and the distance should be kept at 0.6~1.5 meters; The angle and length of the advance support are strictly constructed according to the design requirements. When the angle is restricted by the steel arch frame and cannot be constructed according to the design, the angle is easier to be smaller than larger to ensure the effective support length.

[0035] In the preferred scheme, the timing of demolition of the middle partition wall is strictly controlled. When the initial support construction of the fifth pilot pit 5 is completed and the distance from the fourth pilot pit 4 is greater than five meters, it can be demolished one by one. The length of demolition at one time shall not be greater than three meters. When dismantling the temporary support, the initial support of the pilot pit under the same pile number shall be sprayed and mixed first.

[0036] During the construction process, a good construction channel is formed by removing the middle partition wall and the lower soil. In order to further increase the overall structural strength, holes are inserted obliquely at a position of 20 cm on both sides close to the middle partition wall, and quick-setting concrete holes 13 are applied. Then, quick-setting concrete is poured in the holes to form a stable construction foundation. When the seventh pilot pit 7 is excavated, excavation and demolition are carried out according to the surrounding geology, which will not bring additional workload to the excavation process; and the number and position of the holes are adjusted according to the monitoring data. In order to further improve the efficiency of the construction, the mobile trestle 1 2 is provided with a follow-up lifting rotating disk in the middle, and is provided with outriggers, which can be lowered into the seventh guide pit 7 for support through the outriggers, and then the rotating disk is rotated to adjust the original trestle 12 from a straight state to an "L-shaped rotation state". At this time, it is convenient for the equipment to excavate the part blocked by the trestle 12 in the seventh guide pit 7. The two trestles 12 are fixed by a connecting rod. After the two trestles 12 are adjusted to two symmetrical "L-shaped rotation states", the connecting rod is locked. The follow-up lifting rotating disk can adjust the front and rear positions of the construction equipment, thereby ensuring stable and efficient construction.

[0037] In the preferred solution, after the temporary support of the middle partition wall is removed, the construction time of the sixth pilot pit 6 and the seventh pilot pit 7 is strictly controlled, and the position of the trestle 12 is adjusted according to the excavation position to improve the convenience of construction and ensure that the invert arch is completed within the design time.

[0038] After applying this solution on the project site, it has obvious economic benefits: (1) The defects of the invert arch excavation were solved, and the problem of the pilot tunnel and the primary arch frame of the middle partition being suspended in the air at the same time was avoided. At the same time, the time for the primary support to form a closed loop was shortened, reducing the construction safety risk.

[0039] (2) The deformation of the initial support can be effectively controlled. This process complies with the principle of reducing the primary excavation area and temporary support of the arch by the traditional CD method. In extremely broken gravel soil surrounding rock, the cumulative deformation can be controlled within 1 / 3 of the design deformation reserve, laying a solid foundation for safely and quickly passing through the gravel soil layer. The safety risk is controllable, such as Fig.12 There is specific monitoring data of the construction site.

[0040] (3) The CD method of temporary support with non-full height is adopted. The face and the invert are constructed simultaneously without interfering with each other, which can realize the CD method flow operation, which is conducive to quality control and improves construction efficiency. Under normal circumstances, three cycles of progress can be made per day, and each cycle is one arch frame spacing. The construction progress is twice as fast as that of the traditional CD method, and the work efficiency is significantly improved.

[0041] (4) The temporary primary support of the middle partition wall does not need to be set up at the full height, that is, from the arch top to the bottom of the second step, which can save the temporary primary support structure from the bottom of the second step to the bottom of the invert arch in the traditional CD method. For the construction of the Shanmuling Tunnel in this project, about 100 kg of steel arch frame can be saved per linear meter, nearly cubic meters of shotcrete can be saved, and the cost can be saved by about RMB 1,500 / m, totaling more than RMB 1 million, greatly reducing the construction cost.

[0042] The above embodiments are only preferred technical solutions of the present invention and should not be regarded as limiting the present invention. The protection scope of the present invention shall be the technical solutions recorded in the claims, including equivalent replacement solutions of the technical features in the technical solutions recorded in the claims. That is, equivalent replacement improvements within this scope are also within the protection scope of the present invention.

Claims

1. A construction method of a CD method for temporary support of a general span tunnel with non-full height, characterized by: The following steps are involved: S1. Divide the tunnel section into seven construction areas from top to bottom and rationally design the excavation depth of different areas; S2, excavating a first pilot pit (1) and implementing a first permanent initial support (101) and a first temporary support (102); S3, excavating a second pilot pit (2) and implementing a second permanent initial support (201) and a second temporary support (202); S4, excavating the third pilot pit (3) and applying the third permanent primary support (301); S5, excavating a fourth pilot pit (4) and applying a fourth permanent primary support (401); S6, excavating the fifth pilot pit (5) and implementing the fifth permanent primary support (501); S7, removing the intermediate partition formed by the first temporary support (102) and the second temporary support (202) beyond the design distance of the end face of the fourth pilot pit (4), ensuring that the end face of the intermediate partition and the invert are offset to form a temporary transverse working surface; S8, excavating the sixth pilot pit (6) and implementing the sixth permanent primary support (601); S9, excavating the seventh pilot pit (7) and implementing the seventh permanent primary support (701); S10, the seventh pilot pit (7) and the middle partition wall are kept at a distance, and a trestle (12) is installed across the upper side of the seventh pilot pit (7); S11, constructing secondary lining (9), invert (10) and invert filling (11), and completing the pouring of the tunnel top and bottom; S12. Repeat S2 to S11 until the overall tunnel construction is completed.

2. The construction method of the CD method for temporary support of a general span tunnel according to claim 1 is characterized by: During the construction of the first pilot pit (1), the second pilot pit (2), the third pilot pit (3), the fourth pilot pit (4), the fifth pilot pit (5), the sixth pilot pit (6) and the seventh pilot pit (7), it is necessary to install locking anchor pipes, lay steel mesh, and simultaneously carry out initial support spraying (8) and install anchor rods. The width of the fifth pilot pit (5) and the sixth pilot pit (6) is less than two meters, and the width of the first pilot pit (7) is greater than seven meters.

3. The construction method of the CD method for temporary support of a general span tunnel according to claim 1 is characterized by: In S7, the timing of dismantling the middle partition wall support is determined based on the monitoring and measurement data. The support can only be dismantled after the tunnel deformation is stable. During the dismantling process, the stability of the tunnel primary support structure should be ensured. Starting from the end face of the fourth pilot pit (4), the temporary support of the middle partition wall should be retained for at least five meters.

4. The construction method of the CD method for temporary support of a general span tunnel with non-full height according to claim 1 is characterized by: In S3, reinforced concrete is used to temporarily support the bottom of the second temporary support (202) to reduce settlement. In S9, in order to prevent deformation and settlement, the excavation depth at one time does not exceed three meters, and the excavation process reduces the vibration impact of the mechanical operation process.

5. The construction method of the CD method for temporary support of a general span tunnel according to claim 1 is characterized by: In S1, the construction process is controlled by combining the excavation section depth with the designed reserved deformation according to the geological conditions of the surrounding rock. At the same time, the designed reserved deformation is adjusted in real time according to the monitoring results, and the weak points are reinforced.

6. The construction method of the CD method for temporary support of a general span tunnel with non-full height according to claim 5 is characterized by: For construction of extremely unstable gravel soil surrounding rock, spraying concrete before the construction of steel and steel mesh will cause great disturbance to it, and the initial spraying concrete cannot play a supporting role, so it is not necessary to carry out the initial spraying; The manufacturing dimensions of the steel arch frame are controlled according to the actual deformation reserve, and the frame is trial-assembled and numbered at the reinforcement yard, with the installation position noted to ensure the installation accuracy in the hole.

7. The construction method of the CD method for temporary support of a general span tunnel with non-full height according to claim 6 is characterized by: In order to reduce the disturbance of advance support drilling operation and avoid serious block falling or even local collapse, the advance support process is adjusted from "erecting steel arch frame first, then setting up advance support and finally spraying concrete" to "erecting steel arch frame first, then spraying concrete (reserving arch frame guide holes but not spraying) and finally setting up advance support".

8. The construction method of the CD method for temporary support of a general span tunnel with non-full height according to claim 7 is characterized by: The spraying concrete operation should be carried out in layers from the arch feet on both sides to the arch top. When spraying, first spray the low-lying areas roughly flat, and spray in a spiral reciprocating manner. When spraying, the nozzle should be as perpendicular to the sprayed surface as possible, the angle should not be less than 70°, and the distance should be kept at 0.6~1.5 meters; The angle and length of the advance support are strictly constructed according to the design requirements. When the angle is restricted by the steel arch frame and cannot be constructed according to the design, the angle is easier to be smaller than larger to ensure the effective support length.

9. The construction method of the CD method for temporary support of a general span tunnel with non-full height according to claim 3 is characterized by: The timing of dismantling the middle partition wall shall be strictly controlled. When the primary support of the fifth pilot pit (5) is completed and the distance from the fourth pilot pit (4) is greater than five meters, it can be dismantled one by one. The length of dismantling at one time shall not exceed three meters. When dismantling the temporary support, the primary support of the pilot pit under the same pile number shall be sprayed with concrete first.

10. The construction method of the CD method for temporary support of a general span tunnel with non-full height according to claim 9 is characterized by: After the temporary support of the middle partition wall is removed, the construction time of the sixth pilot pit (6) and the seventh pilot pit (7) is strictly controlled, and the position of the trestle (12) is moved and adjusted according to the excavation position to improve the convenience of construction and ensure that the invert arch is completed within the design time.