Multi-purpose efficient disaster prevention method for high-gas easy-spontaneous-combustion coal seam roof roadway
By setting up a roof lane in a high gas easy-to-fire coal seam for pressure-relieving gas extraction and grid-form fixed-point drip irrigation, the problems of high gas extraction cost and grouting blank zones are solved, effectively preventing and controlling coal spontaneous combustion, and ensuring the The mines are produced safely and efficiently.
Patent Information
- Application Number
- CN202411310593.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-20
- Publication Date
- 2024-11-26
AI Technical Summary
The cost of gas extraction in high-gas spontaneous combustion coal seams is high, and the grouting and fire prevention and extinguishing technology has problems such as grouting blank zones, making it difficult to effectively prevent and control coal spontaneous combustion disasters.
The top lane lane is set up in the high gas easy-to-fired coal seam, and the cave chamber is constructed through the downward drilling hole to carry out pressure relief gas extraction, and the gas is extracted at high and low-level large-diameter drilling holes in the top lane. At the same time, the net is used Format fixed-point drip irrigation grouting, cover the goaf area for drip irrigation to prevent and control coal spontaneous combustion.
It realizes the efficiency of gas extraction and effective prevention and control of coal spontaneous combustion, reduces disaster prevention costs, avoids the problem of grouting blanks, and ensures safe and efficient production of mines.
Smart Images

Figure CN119021745A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of prevention and control of gas and coal spontaneous combustion disasters in high-gas and self-igniting coal seams, and in particular to a high-efficiency disaster prevention method for a roof lane in a high-gas and self-igniting coal seam with multiple uses. Background Art
[0002] my country's energy structure is characterized by "rich in coal, poor in oil, and little gas", and coal has always played an important role in my country's primary energy supply process. However, my country's coal-bearing strata have complex geological conditions, poor coal seam permeability, and high gas content, which makes gas pre-extraction difficult in my country, and coal and gas outburst disasters occur frequently. At the same time, gas outbursts are serious during coal seam recovery, and gas over-limit phenomena also occur from time to time. At the same time, many coal seams in my country are prone to spontaneous combustion, and spontaneous combustion disasters of coal left in goafs occur from time to time. At present, my country faces considerable difficulties in disaster prevention and control of high-gas and self-igniting coal seams.
[0003] In terms of gas disaster prevention and control, gas extraction is an effective method proven by practice. After decades of efforts, my country has established a system of underground gas extraction methods in coal mines that runs through the three stages of pre-mining, mining and post-mining. Among them, the main purpose of pre-mining extraction (also known as gas pre-extraction) is to eliminate the danger of coal seam outbursts, the main purpose of mining extraction is to control gas outbursts during mining, and the main purpose of post-mining extraction is to utilize the high concentration of gas in the goaf. At present, underground gas extraction in my country's coal mines is mainly concentrated in the two stages of pre-mining extraction and mining extraction. In the pre-mining extraction stage, the bottom rock tunnel (bottom extraction tunnel) extraction method is highly favored due to its high safety; in the mining extraction stage, the high extraction tunnel extraction method has the highest efficiency. At the same time, in order to control the gas concentration of the working face during mining and avoid gas exceeding the limit in the upper corner, many mines have also arranged low-level extraction tunnels, referred to as low extraction tunnels. Therefore, many mines currently need to arrange up to three gas extraction rock tunnels (bottom extraction tunnel, high extraction tunnel and low extraction tunnel) at the mining faces, resulting in high gas extraction costs in the mines.
[0004] In the prevention and control of spontaneous combustion of coal in goaf, grouting fire prevention and extinguishing technology has been widely used. The main principle of this technology is: after the non-combustible solid raw materials such as gangue, clay, fly ash, etc. are granulated and mixed with water in a certain proportion to form a suspended slurry, after pressurization, it is injected into the goaf of the self-igniting coal seam through the conveying pipeline to wrap the coal body and isolate the contact between the coal in the goaf and oxygen, so as to prevent the spontaneous combustion of the coal in the goaf or extinguish the coal body that has spontaneously combusted. Practice has proved that grouting fire prevention and extinguishing is an effective technology for the prevention and control of spontaneous combustion of coal in goaf, and it is simple to operate and easy to use. At present, grouting fire prevention and extinguishing mainly adopts the buried pipe grouting process in goaf. This process has obvious shortcomings: the grouting process belongs to flooding grouting, the flow of slurry during the grouting process is greatly affected by gravity and is not easy to be artificially controlled, the high-point coal is not easy to be wrapped by the slurry, and there are problems such as grouting blank zone. The existence of these problems has caused great difficulties in the prevention and control of spontaneous combustion of coal in goaf in my country. Summary of the invention
[0005] In order to solve the problems of high gas extraction cost in coal seams prone to self-ignition and high gas content, and the existence of grouting blank zones in grouting fire prevention and extinguishing technology, the present invention provides a high-efficiency disaster prevention method for multi-purpose roof lanes in coal seams prone to self-ignition and high gas content.
[0006] The present invention is realized through the following technical scheme: a high-efficiency disaster prevention method for a roof tunnel with multiple uses in a high-gas and self-igniting coal seam. First, a roof tunnel is arranged at a certain layer above the protective coal pillar between the return air tunnel of the working face to be mined and the air intake tunnel of the adjacent working face, and the extension direction of the roof tunnel is adapted to the extension direction of the return air tunnel of the working face to be mined and the air intake tunnel of the adjacent working face; downward through-layer drilling is constructed from the roof tunnel toward the return air tunnel of the working face to be mined and the air intake tunnel of the adjacent working face and within a certain range on both sides, and the hole expansion and cave formation are carried out to construct a cave formation cavern, and pressure relief gas extraction is carried out to protect the excavation of the return air tunnel of the working face to be mined and the air intake tunnel of the adjacent working face; On this basis, high-position large-diameter boreholes and low-position large-diameter boreholes are respectively constructed in the rock layer above the working face in the roof tunnel to extract the gas gushing out from the coal seam and adjacent layers during the mining process of the working face to be mined; In addition, during the mining process of the working face to be mined and the adjacent working face, grouting holes are constructed in the rock strata above the working face to be mined and the adjacent working face from the roof tunnel, and grid-type fixed-point drip grouting is carried out on the goaf of the working face to be mined and the adjacent working face to effectively prevent and control the spontaneous combustion of coal in the goaf.
[0007] As a further improvement of the technical solution of the present invention, the roof tunnel is located above the coal seam, and the grouting boreholes constructed from the roof tunnel are downward boreholes; the grid-type fixed-point drip grouting refers to the drip irrigation method of slurry injection during the grouting process, the final hole positions of the grouting boreholes are distributed in a grid pattern, and the slurry can be injected into the designated positions in the goaf through the grouting boreholes.
[0008] As a further improvement of the technical solution of the present invention, grouting drilling can also be used to fill the goaf in a grid pattern, reduce surface subsidence and the development of mining-induced fissures during the mining process of the working face to be mined and the adjacent working face, reduce surface air leakage, and thus prevent spontaneous combustion of coal in the goaf of shallow coal seams caused by surface air leakage.
[0009] As a further improvement of the technical solution of the present invention, in order to further improve the grouting effect of the goaf area, the goaf area grid fixed-point drip grouting process can also be used in combination with the traditional goaf area buried pipe grouting process.
[0010] As a further improvement of the technical solution of the present invention, the roof tunnel is located in a stable rock stratum 15 to 25 m above the coal seam in the vertical direction, and is located in the center of the return air tunnel of the working face to be mined and the air intake tunnel of the adjacent working face in the horizontal direction.
[0011] As a further improvement of the technical solution of the present invention, the final hole position of the high-position large-diameter drill hole is located in the fracture zone on the right side of the return air channel of the working face to be mined, and the final hole position of the low-position large-diameter drill hole is located in the collapse zone on the right side of the return air channel of the working face to be mined.
[0012] As a further improvement of the technical solution of the present invention, in order to reduce the amount of drilling work, the grouting drilling adopts a cross-working face arrangement method, that is, the grouting drilling constructed in the top plate tunnel covers the left half of the working face to be mined and the right half of the adjacent working face; the final hole position of the grouting drilling is located in the collapse zone of the working face to be mined and the adjacent working face.
[0013] As a further improvement of the technical solution of the present invention, after the downward through-layer drilling is completed and the hole is expanded and formed, it is necessary to be able to carry out coal slurry return operation to discharge the coal slurry in the hole forming cavern, and use high-pressure air to blow dry the residual water in the downward through-layer drilling hole and the hole forming cavern to eliminate the influence of water locking effect on gas extraction.
[0014] As a further improvement of the technical solution of the present invention, the spacing between the high-position large-diameter drill holes and the low-position large-diameter drill holes is adjusted according to parameters such as the gas content of the coal seam, the position of the adjacent layer, and the borehole diameter; the spacing of the grouting drill holes and the grouting amount of a single hole can be adjusted according to parameters such as the coal seam mining height, the position of the adjacent layer, the burial depth of the coal seam, and the slurry fluidity.
[0015] The high-efficiency disaster prevention method for a roof lane in a high-gas self-igniting coal seam provided by the present invention has the following advantages over the prior art: The present invention is aimed at the fact that many mining working faces of high-gas and self-igniting coal seams in my country need to arrange up to 3 gas extraction rock tunnels (bottom extraction tunnel, high extraction tunnel and low extraction tunnel), the gas extraction cost is high, and at the same time, in the process of buried pipe grouting for fire prevention and extinguishing in the goaf, the slurry flow is greatly affected by gravity and is not easy to be artificially controlled. The high-point coal is not easy to be wrapped by the slurry, and there are grouting blank zones and other problems. It provides a high-efficiency disaster prevention method for the roof tunnel of high-gas and self-igniting coal seams. After adopting the present invention, a roof tunnel can not only be used for pre-extraction of coal tunnel strip gas and protection of coal tunnel excavation, but also can be used for extraction of gas gushing from the coal seam and adjacent layers during mining of the working face, and can also be used for drip irrigation grouting for fire prevention and extinguishing in the goaf, realizing "one tunnel for multiple uses", which can greatly reduce the disaster prevention cost of high-gas and self-igniting coal seams and ensure safe and efficient production of mines. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] The accompanying drawings, which are incorporated in and constitute a part of this specification, illustrate embodiments consistent with the invention and, together with the description, serve to explain the principles of the invention.
[0017] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, for ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.
[0018] Figure 1 The invention discloses a highly efficient disaster prevention method for a multi-purpose roof lane of a high-gas self-igniting coal seam.
[0019] In the figure: 1-return air lane of the working face to be mined; 2-intake air lane adjacent to the working face; 3-protective coal pillar; 4-roof lane; 5-downward through-layer drilling; 6-hole-making chamber; 7-working face to be mined; 8-high-position large-diameter drilling hole; 9-low-position large-diameter drilling hole; 10-adjacent to the working face; 11-grouting drilling hole; 12-coal seam. DETAILED DESCRIPTION
[0020] In order to more clearly understand the above-mentioned objectives, features and advantages of the present invention, the scheme of the present invention will be further described below. It should be noted that the embodiments of the present invention and the features in the embodiments can be combined with each other without conflict.
[0021] In the following description, many specific details are set forth to facilitate a full understanding of the present invention, but the present invention may also be implemented in other ways different from those described herein; it is obvious that the embodiments in the specification are only part of the embodiments of the present invention, rather than all of the embodiments.
[0022] The specific embodiments of the present invention are described in detail below.
[0023] like Figure 1 As shown, the present invention provides a high-efficiency disaster prevention method for a roof tunnel with multiple uses in a high-gas self-igniting coal seam. First, a roof tunnel 4 is arranged at a certain layer above the protective coal pillar 3 between the return air tunnel 1 of the working face to be mined and the air intake tunnel 2 of the adjacent working face. The extension direction of the roof tunnel 4 is adapted to the extension direction of the return air tunnel 1 of the working face to be mined and the air intake tunnel 2 of the adjacent working face; downward through-layer drilling holes 5 are constructed from the roof tunnel 4 toward the return air tunnel 1 of the working face to be mined and the air intake tunnel 2 of the adjacent working face and within a certain range on both sides, and the hole expansion and cavitation are carried out to construct a cavitation cavern 6, and pressure relief gas extraction is carried out to protect the excavation of the return air tunnel 1 of the working face to be mined and the air intake tunnel 2 of the adjacent working face; On this basis, a high-position large-diameter borehole 8 and a low-position large-diameter borehole 9 are respectively constructed in the rock layer above the working face 7 from the roof tunnel 4 to extract the gas gushing out from the coal seam and the adjacent layers during the mining process of the working face 7; In addition, during the mining process of the working face 7 to be mined and the adjacent working face 10, grouting holes 11 are constructed in the rock strata above the working face 7 to be mined and the adjacent working face 10 from the roof tunnel 4, and grid-type fixed-point drip grouting is carried out on the goaf of the working face 7 to be mined and the adjacent working face 10, so as to effectively prevent and control the spontaneous combustion disaster of coal in the goaf.
[0024] Further, in the present invention, the roof tunnel 4 is located above the coal seam 12, and the grouting borehole 11 constructed from the roof tunnel 4 is a downward borehole, so its grouting process belongs to drip grouting. At the same time, the terminal hole positions of the grouting boreholes 11 are distributed in a grid pattern, so the grid-type fixed-point drip grouting in the goaf can be achieved through the grouting boreholes 11. The diameter of the grouting boreholes 11 of this embodiment is preferably 75~113 mm, and can also be adjusted according to actual conditions. The grid-type fixed-point drip grouting of the goaf through the grouting boreholes 11 can achieve a relatively uniform wrapping of the goaf coal by the slurry, cut off the contact between the coal and oxygen, and help solve the problems of the traditional goaf buried pipe grouting (flood grouting), such as the slurry flow being greatly affected by gravity, not easy to be artificially controlled, the high-point coal being not easily wrapped by the slurry, and the existence of a grouting blank zone. At the same time, the grouting borehole 11 can also be used to fill the goaf in a grid-like fixed-point manner, reduce surface settlement and mining crack development during the working face mining process, reduce surface air leakage, and thus prevent spontaneous combustion of coal in the goaf caused by surface air leakage in shallow coal seams.
[0025] Further preferably, in order to further improve the grouting effect of the goaf area, the goaf area grid fixed-point drip grouting process of the present invention can also be used in combination with the traditional goaf area buried pipe grouting process.
[0026] Specifically, the roof tunnel 4 is located in a stable rock layer 15 to 25 m above the coal seam 12 in the vertical direction, and is located in the center of the return air tunnel 1 of the working face to be mined and the air intake tunnel 2 of the adjacent working face in the horizontal direction. After the roof tunnel 4 is designed in such a position, it can simultaneously cover the excavation of two coal tunnels (i.e., the return air tunnel 1 of the working face to be mined and the air intake tunnel 2 of the adjacent working face), and the coal tunnel excavation cost can be significantly reduced and the excavation speed can be significantly accelerated.
[0027] Preferably, the final hole position of the high-position large-diameter drill hole 8 is located in the fracture zone on the right side of the return air channel 1 of the working face to be mined, and the final hole position of the low-position large-diameter drill hole 9 is located in the collapse zone on the right side of the return air channel 1 of the working face to be mined.
[0028] Further, such as Figure 1 As shown, in order to reduce the amount of drilling work, the grouting boreholes 11 are arranged across the working face, that is, the grouting boreholes 11 constructed in the roof tunnel 4 cover the left half of the working face 7 to be mined and the right half of the adjacent working face 10; the final hole position of the grouting boreholes 11 is located in the collapse zone of the working face 7 to be mined and the adjacent working face 10.
[0029] Furthermore, after the downward through-layer drilling hole 5 is completed by expanding the hole and making a cave, it is necessary to be able to carry out the coal slurry return operation, discharge the coal slurry in the cavern 6, and use high-pressure air to blow dry the residual water in the downward through-layer drilling hole 5 and the cavern 6 to eliminate the influence of the water lock effect on gas extraction. Furthermore, the spacing between the high-position large-diameter drilling hole 8 and the low-position large-diameter drilling hole 9 is adjusted according to the parameters such as the gas content of the coal seam, the position of the adjacent layer, and the borehole diameter. The spacing of the grouting drilling hole 11 and the grouting amount of each hole can be adjusted according to the parameters such as the coal seam mining height, the position of the adjacent layer, the buried depth of the coal seam, and the fluidity of the slurry. The diameter of the high-position large-diameter drilling hole 8 and the low-position large-diameter drilling hole 9 is preferably above 200 mm.
[0030] The roof tunnel of the present invention can not only be used for pre-extraction of coal tunnel strip gas and protection of coal tunnel excavation, but also can be used for extraction of gushing gas from the coal seam and adjacent layers during mining of the working face, and can also be used for drip grouting fire prevention and extinguishing in the goaf, realizing "one tunnel for multiple uses", which can greatly reduce the disaster prevention cost of high-gas and self-igniting coal seams and ensure safe and efficient production in mines.
[0031] The above is only a specific implementation of the present invention, which enables those skilled in the art to understand or implement the present invention. Although detailed descriptions are given with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions recorded in the aforementioned embodiments, or replace some or all of the technical features therein by equivalents; and these modifications or replacements do not make the essence of the corresponding technical solutions deviate from the scope of the technical solutions of the embodiments, and they should all be covered by the protection scope of the claims.
Claims
1. An efficient disaster prevention method for a multi-purpose roof lane in a high-gas self-igniting coal seam, characterized by: First, a roof tunnel (4) is arranged at a certain layer position above the protective coal pillar (3) between the return air tunnel (1) of the working face to be mined and the air intake tunnel (2) of the adjacent working face, and the extension direction of the roof tunnel (4) is compatible with the extension direction of the return air tunnel (1) of the working face to be mined and the air intake tunnel (2) of the adjacent working face; downward through-layer drilling (5) is constructed from the roof tunnel (4) toward the return air tunnel (1) of the working face to be mined and the air intake tunnel (2) of the adjacent working face and within a certain range on both sides, and the hole is expanded to form a cavern (6), and pressure-relief gas extraction is carried out to protect the excavation of the return air tunnel (1) of the working face to be mined and the air intake tunnel (2) of the adjacent working face; On this basis, a high-position large-diameter borehole (8) and a low-position large-diameter borehole (9) are respectively constructed in the rock layer above the working face to be mined (7) from the roof tunnel (4) to extract the gas gushing out from the coal seam and the adjacent layers during the mining process of the working face to be mined (7); In addition, during the mining process of the working face to be mined (7) and the adjacent working face (10), grouting holes (11) are constructed in the rock strata above the working face to be mined (7) and the adjacent working face (10) from the roof tunnel (4), and grid-type fixed-point drip grouting is performed on the goaf of the working face to be mined (7) and the adjacent working face (10), so as to effectively prevent and control the spontaneous combustion of coal in the goaf.
2. The high-efficiency disaster prevention method for a roof lane in a high-gas and self-igniting coal seam according to claim 1, characterized in that: The roof tunnel (4) is located above the coal seam (12), and the grouting boreholes (11) constructed from the roof tunnel (4) are downward boreholes; the grid-type fixed-point drip grouting means that the slurry injection method during the grouting process is drip irrigation, the terminal hole positions of the grouting boreholes (11) are distributed in a grid pattern, and the slurry can be injected into the designated positions in the goaf through the grouting boreholes (11).
3. The high-efficiency disaster prevention method for a roof lane in a high-gas and self-igniting coal seam according to claim 1, characterized in that: The grouting boreholes (11) can also be used to fill the goaf in a grid-like manner, thereby reducing the surface settlement and development of mining-induced fissures during the mining process of the working face to be mined (7) and the adjacent working face (10), reducing surface air leakage, and thus preventing spontaneous combustion of coal in the goaf of shallow coal seams caused by surface air leakage.
4. The high-efficiency disaster prevention method for a roof lane in a high-gas and self-igniting coal seam according to claim 1 is characterized by: In order to further improve the grouting effect of the goaf, the goaf grid fixed-point drip grouting process can also be used in combination with the traditional goaf buried pipe grouting process.
5. The high-efficiency disaster prevention method for a roof lane in a high-gas and self-igniting coal seam according to claim 1 is characterized by: The roof tunnel (4) is located in a stable rock layer 15 to 25 m above the coal seam (12) in the vertical direction, and is located in the center of the return air tunnel (1) of the working face to be mined and the intake air tunnel (2) of the adjacent working face in the horizontal direction.
6. The high-efficiency disaster prevention method for a roof lane in a high-gas and self-igniting coal seam according to claim 1 is characterized by: The final hole position of the high-position large-diameter borehole (8) is located in the fracture zone on the right side of the return air tunnel (1) of the working face to be mined, and the final hole position of the low-position large-diameter borehole (9) is located in the collapse zone on the right side of the return air tunnel (1) of the working face to be mined.
7. The high-efficiency disaster prevention method for a roof lane in a high-gas self-igniting coal seam according to claim 1 is characterized by: In order to reduce the amount of drilling work, the grouting boreholes (11) are arranged across the working face, that is, the grouting boreholes (11) constructed in the top slab tunnel (4) cover the left half of the working face to be mined (7) and the right half of the adjacent working face (10); the final hole position of the grouting boreholes (11) is located in the collapse zone of the working face to be mined (7) and the adjacent working face (10).
8. The high-efficiency disaster prevention method for a roof lane in a high-gas and self-igniting coal seam according to claim 1 is characterized by: After the downward through-layer drilling hole (5) is completed to expand the hole and form a cave, a coal slurry return operation must be carried out to discharge the coal slurry in the cave chamber (6) and use high-pressure air to blow out the residual water in the downward through-layer drilling hole (5) and the cave chamber (6) to eliminate the influence of the water lock effect on gas extraction.
9. The high-efficiency disaster prevention method for a roof lane in a high-gas and self-igniting coal seam according to claim 1, characterized in that: The spacing between the high-position large-diameter borehole (8) and the low-position large-diameter borehole (9) is adjusted according to parameters such as coal seam gas content, the position of adjacent layers, and borehole diameter. The spacing between grouting boreholes (11) and the grouting volume per hole can be adjusted according to coal seam mining height, adjacent layer position, coal seam burial depth, and slurry fluidity parameters.