Method and equipment for calculating uncertainty of wind flow model extrapolation of wind measurement data of wind power plant

By obtaining the location data of wind farm wind towers and wind turbines and the terrain rugged index, and using simple calculation methods to calculate the uncertainty of extrapolation of wind flow model, the problems of complex calculation and large amount of calculation in the existing technology are solved, and the problem of improvement is improved The scientificity and accuracy of the calculation of the extrapolation of the wind flow model of wind farm measurement data.

CN119021836APending Publication Date: 2024-11-26CHINA THREE GORGES INT CORP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411147469.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-20
Publication Date
2024-11-26

AI Technical Summary

Technical Problem

The uncertainty calculation method for extrapolation of wind flow model of wind farm wind measurement data in the prior art is complex and has a large amount of calculation, making it difficult to actually apply in engineering.

Method used

By obtaining the position data of wind farm wind measurement towers and wind turbine units and the terrain rugged index, the uncertainty of extrapolation of wind flow model is calculated using simple calculation methods, considering the impact between different wind measurement towers and generators, sub-item weights and Sub-item uncertainty, and then calculate the uncertainty of the extrapolation of the overall romantic flow model.

Benefits of technology

The calculation process is simplified, the calculation amount is reduced, the scientificity and accuracy of uncertainty calculation are improved, and the impact of wind farm terrain conditions on uncertainty can be effectively considered.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119021836A_ABST
    Figure CN119021836A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of wind power generation, and discloses an uncertainty calculation method and equipment for wind power plant wind measurement data wind flow model extrapolation. The uncertainty calculation method for wind power plant wind measurement data wind flow model extrapolation comprises the following steps: acquiring first position data of a wind speed sensor of a wind power plant anemometer tower and second position data of a hub of a wind generating set; obtaining a first terrain rugged index of the wind power plant anemometer tower and a second terrain rugged index of the wind generating set; and based on the first position data, the second position data, the first terrain rugged index and the second terrain rugged index, calculating uncertainty of wind flow model extrapolation, wherein the wind flow model is used for extrapolating wind measurement data of the hub height of the wind generating set according to the wind measurement data of the wind power plant anemometer tower. The method can solve the problems that the uncertainty calculation method of wind measurement data wind flow model extrapolation is complex and the calculation amount is large.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of wind power generation, and in particular to an uncertainty calculation method and device for extrapolating a wind flow model of wind farm wind measurement data. Background Art

[0002] Wind energy is one of the most abundant renewable energy sources. In the early development of a wind farm, it is necessary to set up a wind tower and collect wind data. Since the locations of the wind turbines to be selected in the wind farm are different from those of the wind towers, the wind energy resource conditions are also different. The wind speed data at the wind tower location needs to be extrapolated to the wind speed data at the hub height of each wind turbine to be selected in the wind farm using a wind flow model, in order to obtain the wind energy resource conditions of each wind turbine to be selected and calculate the power generation, which is then added together to obtain the power generation of the wind farm.

[0003] In the process of calculating power generation, it is necessary to calculate the uncertainty caused by the extrapolation of the wind flow model of the wind farm wind measurement data. At present, a new wind tower is set up at the location of the proposed wind turbine generator set, and then the error of the wind flow model extrapolation is calculated based on the results of the wind flow model extrapolation and the wind measurement data of the new wind tower. The Gaussian distribution model is used for fitting and the calculation of uncertainty is relatively complex and computationally intensive, which is not convenient for actual use in engineering. Summary of the invention

[0004] In view of this, the present invention provides a method and device for calculating uncertainty of extrapolating a wind flow model based on wind measurement data of a wind farm, so as to solve the problem that the method for calculating uncertainty of extrapolating a wind flow model based on wind measurement data is complex and has a large amount of calculation.

[0005] In a first aspect, the present invention provides a method for calculating the uncertainty of extrapolating a wind flow model based on wind measurement data of a wind farm. The method for calculating the uncertainty of extrapolating a wind flow model based on wind measurement data of a wind farm comprises: obtaining first position data of a wind speed sensor of a wind measurement tower of the wind farm and second position data of a hub of a wind turbine generator set; obtaining a first terrain ruggedness index of the wind measurement tower of the wind farm and a second terrain ruggedness index of the wind turbine generator set; calculating the uncertainty of extrapolating the wind flow model based on the first position data, the second position data, the first terrain ruggedness index and the second terrain ruggedness index, wherein the wind flow model is used to obtain wind measurement data of the hub height of the wind turbine generator set based on the wind measurement data of the wind measurement tower of the wind farm.

[0006] In this implementation, the uncertainty of wind flow model extrapolation is calculated by using the position data of the wind speed sensor and the hub of the wind turbine generator set and the nearby terrain data. The method of the present application is based on simple calculations and does not use complex calculation models. It can solve the problems of complex calculation methods and large amount of calculations. At the same time, it can consider the impact of wind farm terrain conditions on uncertainty and realize scientific calculation of uncertainty.

[0007] In an optional embodiment, there are multiple wind farm wind towers and wind turbine hubs, and calculating the uncertainty of wind flow model extrapolation based on the first position data, the second position data, the first terrain ruggedness index and the second terrain ruggedness index includes: calculating the sub-item weights of each wind farm wind tower for each wind turbine based on the first position data and the second position data; calculating the sub-item uncertainty of each wind farm wind tower for each wind turbine based on the first position data, the second position data, the first terrain ruggedness index and the second terrain ruggedness index; calculating the uncertainty of wind flow model extrapolation based on the sub-item weights and the sub-item uncertainty.

[0008] In this implementation, by calculating the uncertainty of each wind farm wind tower for each wind turbine separately, and then obtaining the uncertainty of the overall wind flow model extrapolation based on the weight, the influence of different wind towers and generators on the extrapolation results can be considered, thereby improving the scientificity and accuracy of the uncertainty calculation.

[0009] In an optional implementation, calculating the uncertainty of wind flow model extrapolation based on the sub-item weights and sub-item uncertainties includes: Among them, U0 is the uncertainty of wind flow model extrapolation, W j,i is the sub-item weight of the j-th wind farm wind tower to the i-th wind turbine generator set, U j,i is the partial uncertainty of the j-th wind farm wind tower for the ith wind turbine generator set.

[0010] In an optional embodiment, the first position data includes a first geodetic horizontal coordinate, a first geodetic vertical coordinate and a first altitude of the wind farm wind tower, and the second position data includes a second geodetic horizontal coordinate, a second geodetic vertical coordinate and a second altitude of the hub of the wind turbine.

[0011] In an optional implementation, calculating the sub-item weights of each wind farm wind tower to each wind turbine generator set based on the first position data and the second position data includes: calculating the spatial distance between each wind farm wind tower and each wind turbine generator set based on the first position data and the second position data as follows: Among them, D j,i is the spatial distance between the wind tower of the jth wind farm and the ith wind turbine generator set, X j , Y j , Z j are the first geodetic horizontal coordinate, the first geodetic vertical coordinate and the first altitude, respectively. i , Y i , Z i They are the second geodetic horizontal coordinate, the second geodetic vertical coordinate and the second altitude respectively; the sub-item weights are determined based on the spatial distance as follows: Among them, Wj,i is the sub-item weight of the j-th wind farm wind tower to the ith wind turbine generator set, and n is the total number of wind farm wind towers.

[0012] In an optional implementation, calculating the sub-item uncertainty of each wind farm wind tower for each wind turbine generator set based on the first position data, the second position data, the first terrain ruggedness index, and the second terrain ruggedness index includes: Among them, U j,i is the partial uncertainty of the j-th wind farm wind tower for the i-th wind turbine generator set, R j is the first terrain roughness index, R i is the second terrain roughness index, X j , Y j , Z j are the first geodetic horizontal coordinate, the first geodetic vertical coordinate and the first altitude, respectively. i , Y i , Z i are the second geodetic horizontal coordinate, the second geodetic vertical coordinate and the second altitude respectively, and m is the total number of wind turbines.

[0013] In this implementation, the sub-item weights and sub-item uncertainties are calculated based on simple calculation methods, which can reduce the amount of calculation and improve calculation efficiency.

[0014] In an optional embodiment, obtaining a first terrain ruggedness index of a wind farm wind tower and a second terrain ruggedness index of a wind turbine generator set includes: taking the wind farm wind tower as the center of the circle, dividing a plurality of radius line segments according to a preset angle and a preset length, dividing the radius line segments into a plurality of small line segments using contour lines, and calculating the inclination of each small line segment, obtaining the number ratio of the small line segments corresponding to each radius line segment whose inclination is greater than the preset inclination, calculating the average number ratio of all radius line segments, and obtaining the first terrain ruggedness index; taking the wind turbine generator set as the center of the circle, dividing a plurality of radius line segments according to a preset angle and a preset length, dividing the radius line segments into a plurality of small line segments using contour lines, and calculating the inclination of each small line segment, obtaining the number ratio of the small line segments corresponding to each radius line segment whose inclination is greater than the preset inclination, calculating the average number ratio of all radius line segments, and obtaining the second terrain ruggedness index.

[0015] In a second aspect, the present invention provides a computer device, comprising: a memory and a processor, the memory and the processor being communicatively connected to each other, the memory storing computer instructions, and the processor executing the computer instructions to execute the uncertainty calculation method for extrapolating a wind flow model of wind farm wind measurement data of the first aspect or any corresponding embodiment thereof.

[0016] In a third aspect, the present invention provides a computer-readable storage medium having computer instructions stored thereon, the computer instructions being used to enable a computer to execute the uncertainty calculation method for extrapolating a wind flow model of wind farm wind measurement data according to the first aspect or any corresponding embodiment thereof.

[0017] In a fourth aspect, the present invention provides a computer program product, comprising computer instructions for causing a computer to execute the uncertainty calculation method for extrapolating a wind flow model of wind farm wind measurement data according to the first aspect or any corresponding embodiment thereof. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] In order to more clearly illustrate the specific implementation methods of the present invention or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0019] Figure 1 It is a flow chart of a method for calculating uncertainty of wind flow model extrapolation of wind farm wind measurement data according to an embodiment of the present invention;

[0020] Figure 2 It is a flow chart of another uncertainty calculation method for extrapolating a wind flow model of wind farm wind measurement data according to an embodiment of the present invention;

[0021] Figure 3 Schematic diagram of a flow chart of a method for calculating uncertainty of wind flow model extrapolation of wind farm wind measurement data according to an embodiment of the present invention.

[0022] Figure 4 is a structural block diagram of an uncertainty calculation device for extrapolating a wind flow model of wind farm wind measurement data according to an embodiment of the present invention;

[0023] Figure 5 It is a schematic diagram of the hardware structure of a computer device according to an embodiment of the present invention. DETAILED DESCRIPTION

[0024] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative work are within the scope of protection of the present invention.

[0025] The wind flow model is used to obtain the wind data at the hub height of the wind turbine generator set based on the wind data measured by the wind tower in the wind farm.

[0026] Specifically, when using the wind flow model, the surveying and mapping topographic map, the wind speed data and wind direction data of each wind farm wind tower, the first position data of the wind speed sensor of each wind farm wind tower, and the second position data of the hub height of each wind turbine generator set to be selected are input, so that the wind speed and wind direction data of the wind farm wind tower are extrapolated by the wind flow model to obtain the wind speed and wind direction data of the hub height of each wind turbine generator set to be selected, so as to obtain the wind energy resource status of each wind turbine generator set to be selected and calculate the power generation, and then add them to obtain the power generation of the wind farm. However, due to the differences in the location and environmental terrain of the wind tower and the generator, the wind energy resource status is also different, and there are errors in the extrapolation results of the wind flow model. According to an embodiment of the present invention, an embodiment of an uncertainty calculation method for extrapolating a wind flow model of wind farm wind measurement data is provided. It should be noted that the steps shown in the flowchart of the accompanying drawings can be executed in a computer system such as a set of computer executable instructions, and although the logical order is shown in the flowchart, in some cases, the steps shown or described can be executed in a different order than here.

[0027] In this embodiment, a method for calculating the uncertainty of wind flow model extrapolation of wind farm wind measurement data is provided. Figure 1 FIG. 1 is a flow chart of a method for calculating uncertainty of wind flow model extrapolation of wind farm wind measurement data according to an embodiment of the present invention. It should be noted that if there are substantially the same results, this embodiment does not use Figure 1 The process sequence shown is limited. Figure 1 As shown, the process includes the following steps:

[0028] Step S101, obtaining first position data of a wind speed sensor of a wind farm wind tower and second position data of a hub of a wind turbine generator set.

[0029] The wind farm wind towers are multiple wind towers in the wind farm, and the first position data are three-dimensional coordinate data of wind speed sensors of the wind farm wind towers.

[0030] The hub of the wind turbine generator set is the hub of a plurality of wind turbine generator sets to be selected, and the second position data is the three-dimensional coordinate data of the hub of the wind turbine generator set.

[0031] In one implementation, the first position data includes a first geodetic horizontal coordinate, a first geodetic vertical coordinate and a first altitude of a wind farm wind tower, and the second position data includes a second geodetic horizontal coordinate, a second geodetic vertical coordinate and a second altitude of a hub of the wind turbine.

[0032] Step S102: obtaining a first terrain ruggedness index of a wind farm wind tower and a second terrain ruggedness index of a wind turbine generator set.

[0033] A surveying and mapping topographic map near the wind farm is obtained, and a corresponding first terrain ruggedness index and a second terrain ruggedness index are calculated according to the positions of each wind farm wind tower and each wind turbine.

[0034] Step S103, calculating the uncertainty of wind flow model extrapolation based on the first position data, the second position data, the first terrain ruggedness index and the second terrain ruggedness index.

[0035] The uncertainty calculation method for wind flow model extrapolation of wind farm wind measurement data provided in this embodiment calculates the uncertainty of wind flow model extrapolation by using the position data of the wind speed sensor and the hub of the wind turbine generator set and the nearby terrain data. The method of the present application is based on simple calculations and does not use complex calculation models, which can solve the problems of complex calculation methods and large calculation amount. At the same time, it can consider the influence of wind farm terrain conditions on uncertainty and realize scientific calculation of uncertainty.

[0036] In this embodiment, a method for calculating the uncertainty of wind flow model extrapolation of wind farm wind measurement data is provided. Figure 2 FIG. 1 is a flowchart of another uncertainty calculation method for extrapolating a wind flow model of wind farm wind measurement data according to an embodiment of the present invention. It should be noted that if there are substantially the same results, this embodiment does not use Figure 2 The process sequence shown is limited. Figure 2 As shown, the process includes the following steps:

[0037] Step S201, obtaining first position data of a wind speed sensor of a wind farm wind tower and second position data of a hub of a wind turbine generator set.

[0038] A surveying and mapping topographic map of the wind farm is obtained, and based on the surveying and mapping topographic map of the wind farm, first position data of wind speed sensors of wind towers of each wind farm and second position data of hubs of each wind turbine generator set to be selected are obtained.

[0039] Specifically, the first position data includes a first geodetic horizontal coordinate, a first geodetic vertical coordinate and a first altitude of the wind farm wind tower, and the second position data includes a second geodetic horizontal coordinate, a second geodetic vertical coordinate and a second altitude of the hub of the wind turbine generator set.

[0040] In one implementation, the topographic map is surveyed with an accuracy of 1:2000 or above.

[0041] In one implementation, the extended width from the wind tower and each of the proposed wind turbine generator sets is 5 km or more.

[0042] Step S202: obtaining a first terrain ruggedness index of a wind farm wind tower and a second terrain ruggedness index of a wind turbine generator set.

[0043] A surveying and mapping topographic map near the wind farm is obtained, and a plurality of radius line segments are divided according to a preset angle and a preset length with the wind farm wind tower as the center of the circle, and the radius line segments are divided into a plurality of small line segments using contour lines, and the inclination of each small line segment is calculated, and the number ratio of the small line segments corresponding to each radius line segment with an inclination angle greater than the preset inclination angle is obtained, and the number ratio of all radius line segments is calculated to obtain a first terrain ruggedness index. A plurality of radius line segments are divided according to a preset angle and a preset length with the wind turbine generator set as the center of the circle, and the radius line segments are divided into a plurality of small line segments using contour lines, and the inclination of each small line segment is calculated, and the number ratio of the small line segments corresponding to each radius line segment with an inclination angle greater than the preset inclination angle is obtained, and the number ratio of all radius line segments is calculated to obtain a second terrain ruggedness index.

[0044] In one implementation, the preset angle is 5 degrees, the preset length is 5 km, and the preset inclination is 30 degrees.

[0045] Specifically, with the location of the wind farm wind tower as the center, a radius of every 5 degrees is taken, and the length of the radius is 5km. Each radius is divided into several line segments using the contour lines of the surveying and mapping topographic map, and the inclination of each line segment is calculated. The arithmetic mean of the ratio of the number of line segments with an inclination angle greater than 30 degrees in all radii to the number of total line segments divided by the contour lines in the radius is calculated as the first terrain ruggedness index. With the location of the wind turbine generator set as the center, a radius of every 5 degrees is taken, and the length of the radius is 5km. With the contour lines of the surveying and mapping topographic map, each radius is divided into several line segments, and the inclination of each line segment is calculated. The arithmetic mean of the ratio of the number of line segments with an inclination angle greater than 30 degrees in all radii to the number of total line segments divided by the contour lines in the radius is calculated as the second terrain ruggedness index.

[0046] The above method is used to obtain a plurality of first terrain ruggedness indexes and second terrain ruggedness indexes.

[0047] Step S203, calculating the uncertainty of wind flow model extrapolation based on the first position data, the second position data, the first terrain ruggedness index and the second terrain ruggedness index.

[0048] When extrapolating the wind flow model of wind measurement data, the uncertainty of a wind farm wind tower for a wind turbine is first calculated using the first position data, the second position data, the first terrain ruggedness index and the second terrain ruggedness index, and then the uncertainty of multiple wind farm wind towers for multiple wind turbines is combined.

[0049] Specifically, the above step S203 includes:

[0050] Step S2031: Calculate the sub-item weights of each wind farm wind tower for each wind turbine generator set based on the first position data and the second position data.

[0051] The positions of wind farm wind towers and wind turbines are used to determine the influence of each wind farm wind tower and each wind turbine on the extrapolation results when the wind flow model is extrapolated, that is, to determine the sub-item weights of each wind farm wind tower on each wind turbine.

[0052] In some optional implementations, the above step 2031 includes:

[0053] Step a1: Calculate the spatial distance between each wind farm wind tower and each wind turbine generator set based on the first position data and the second position data.

[0054] The spatial distance is calculated using the distance calculation formula:

[0055]

[0056] Among them, D j,i is the spatial distance between the wind tower of the jth wind farm and the ith wind turbine generator set, X j , Y j , Z j are the first geodetic horizontal coordinate, the first geodetic vertical coordinate and the first altitude, respectively. i , Y i , Z i They are the second geodetic horizontal coordinate, the second geodetic vertical coordinate and the second altitude respectively.

[0057] Step a2, determining the sub-item weights based on the spatial distance.

[0058] The calculation formula for the sub-item weight is:

[0059]

[0060] Among them, W j,i is the sub-item weight of the j-th wind farm wind tower to the ith wind turbine generator set, and n is the total number of wind farm wind towers.

[0061] Step S2032: Calculate the sub-item uncertainty of each wind farm wind tower for each wind turbine generator set based on the first position data, the second position data, the first terrain ruggedness index and the second terrain ruggedness index.

[0062] When the wind flow model is used to extrapolate the wind speed and direction data at the hub height of each proposed wind turbine, the extrapolation results of different wind turbines for different wind farm wind towers are different, and the uncertainties are also different.

[0063] This step proposes a method to calculate the uncertainty of each wind farm wind tower for each wind turbine generator set. The calculation formula is:

[0064]

[0065] Among them, U j,i is the partial uncertainty of the j-th wind farm wind tower for the i-th wind turbine generator set, R j is the first terrain roughness index, R i is the second terrain roughness index, X j , Y j , Z j are the first geodetic horizontal coordinate, the first geodetic vertical coordinate and the first altitude, respectively. i , Y i , Z i They are the second geodetic horizontal coordinate, the second geodetic vertical coordinate and the second altitude respectively.

[0066] Step S2033, calculating the uncertainty of wind flow model extrapolation based on the sub-item weights and sub-item uncertainties.

[0067] The sub-item weight is used as the weight of the corresponding sub-item uncertainty to calculate the uncertainty of the overall wind flow model extrapolation. The calculation formula is:

[0068]

[0069] Among them, U0 is the uncertainty of wind flow model extrapolation, W j,i is the sub-item weight of the j-th wind farm wind tower to the i-th wind turbine generator set, U j,i is the partial uncertainty of the j-th wind farm wind tower for the ith wind turbine generator set, and m is the total number of wind turbine generator sets.

[0070] The uncertainty calculation method for wind flow model extrapolation of wind farm wind measurement data provided in this embodiment calculates the uncertainty of wind flow model extrapolation by using the position data of the wind speed sensor and the hub of the wind turbine generator set and the nearby terrain data. The influence of each wind farm wind tower on the extrapolation result between each wind turbine is fully considered, while the influence of the environmental terrain of the wind tower and the generator on the uncertainty is considered, and the uncertainty of the overall wind flow model extrapolation is calculated based on the uncertainty of each wind farm wind tower on each wind turbine and the corresponding weight, thereby improving the scientificity and accuracy of the uncertainty calculation. Based on this, the uncertainty of wind flow model extrapolation is calculated using the calculation method proposed in this application. The calculation method is simple and can achieve scientific calculation of the uncertainty of wind flow model extrapolation while reducing the amount of uncertainty calculation.

[0071] In this embodiment, a method for calculating uncertainty of wind flow model extrapolation of wind farm wind measurement data is provided, which is applied to a wind farm with hilly terrain. The wind farm has three wind measurement towers and 10 wind turbines to be selected. Figure 3 FIG. 1 is a flowchart of a method for calculating uncertainty of wind flow model extrapolation of wind farm wind measurement data according to an embodiment of the present invention. It should be noted that if there are substantially the same results, this embodiment does not use Figure 3 The process sequence shown is limited. Figure 3 As shown, the process includes the following steps:

[0072] Step S301, data collection.

[0073] The wind speed and wind direction data are acquired based on the wind speed sensor and wind direction sensor of each wind farm wind tower, and the average wind speed and average wind direction in a set time period are calculated respectively. In one implementation, the acquisition frequency is above 1 Hz, and the set time period is 10 minutes.

[0074] According to the surveying and mapping topographic map of the wind farm, the geodetic horizontal axis coordinates, geodetic vertical axis coordinates and altitude data of the wind speed sensor of the wind measuring tower are obtained, and the geodetic horizontal axis coordinates, geodetic vertical axis coordinates and altitude data of the hub height of each selected wind turbine generator set are obtained.

[0075] Among them, the surveyed topographic map has an accuracy of 1:2000 or above, and the extended width from the wind measurement tower and each proposed wind turbine generator set is 5km or above.

[0076] Please refer to Table 1 and Table 2. Table 1 is a position data table of a wind tower according to an embodiment of the present invention, and Table 2 is a position data table of a proposed wind turbine hub height according to an embodiment of the present invention.

[0077] Table 1: Position data table of a wind tower according to an embodiment of the present invention

[0078] Wind tower number j <![CDATA[Geodetic transverse coordinate X j > Earth's vertical axis coordinate Yj <![CDATA[Altitude Z j > 1 38541759 4397697 1765.7 2 38539549 4395979 1684.8 3 38539069 4398689 1569.4

[0079] Table 2: Position data table of the proposed wind turbine hub height according to an embodiment of the present invention

[0080]

[0081] Step S302, calculating the terrain roughness index.

[0082] Taking the location of the wind tower or the location of each proposed wind turbine as the center of the circle, take a radius of every 5°, and the radius length is 5km. Use the contour lines of the surveying and mapping topographic map to divide each radius into several line segments, and calculate the inclination of each line segment; calculate the arithmetic mean of the ratio of the number of line segments with an inclination angle greater than 30° in all radii to the number of total line segments divided by the contour lines in the radius, which is the terrain ruggedness index of the wind tower location or the terrain ruggedness index of each proposed wind turbine location.

[0083] Step S303, calculating weights.

[0084] According to the wind speed and wind direction data of the wind farm wind tower obtained in step S301, the surveying and mapping topographic map, the geodetic horizontal axis coordinates, the geodetic vertical axis coordinates and the altitude data of the wind speed sensor, the geodetic horizontal axis coordinates, the geodetic vertical axis coordinates and the altitude data of the hub height of each proposed wind turbine generator set. Using the wind flow model, the surveying and mapping topographic map, the geodetic horizontal axis coordinates, the geodetic vertical axis coordinates and the altitude data of the wind speed sensor, the geodetic horizontal axis coordinates, the geodetic vertical axis coordinates and the altitude data of the hub height of each proposed wind turbine generator set are input, so as to use the wind flow model to extrapolate the wind speed and wind direction data of the wind farm wind tower to obtain the wind speed and wind direction data of the hub height of each proposed wind turbine generator set. The weights of each wind tower extrapolated by the wind flow model for each proposed wind turbine generator set are calculated, and the formula is as follows:

[0085]

[0086] Where n is the total number of wind towers3.

[0087] Step S304, calculating the uncertainty of each item.

[0088] According to the geodetic horizontal axis coordinates, geodetic vertical axis coordinates and altitude data of the wind speed sensor of the wind farm wind tower obtained in step S301, the geodetic horizontal axis coordinates, geodetic vertical axis coordinates and altitude data of the hub height of each selected wind turbine generator set, and the terrain ruggedness index R of the j-th wind tower position obtained in step S302 j and the terrain ruggedness index R of the i-th proposed wind turbine location i , calculate the partial uncertainty U caused by the jth wind tower to the i-th selected wind turbine generator set j,i , the formula is as follows:

[0089]

[0090] Step S305, calculating the uncertainty caused by the extrapolation of the wind flow model of the wind farm wind measurement data.

[0091] The weight W of the wind turbine generator set to be selected based on the wind flow model extrapolated from the wind tower obtained in step S303 j,iThe uncertainty component U caused by the j-th wind tower to the i-th selected wind turbine generator set obtained in step S304 is j,i , calculate the uncertainty U0 caused by the extrapolation of the wind flow model of the wind farm wind measurement data, the formula is as follows:

[0092]

[0093] Wherein, m is the total number of wind turbines to be selected 10.

[0094] In this embodiment, a device for calculating uncertainty of wind flow model extrapolation of wind farm wind measurement data is also provided, which is used to implement the above-mentioned embodiments and preferred implementation modes, and the descriptions that have been made will not be repeated. As used below, the term "module" can be a combination of software and / or hardware that implements a predetermined function. Although the devices described in the following embodiments are preferably implemented in software, the implementation of hardware, or a combination of software and hardware, is also possible and conceivable.

[0095] This embodiment provides a device for calculating the uncertainty of wind flow model extrapolation of wind farm wind measurement data, such as Figure 4 As shown, including:

[0096] The first acquisition module 401 is used to acquire first position data of a wind speed sensor of a wind farm wind tower and second position data of a hub of a wind turbine generator set.

[0097] The second acquisition module 402 is used to acquire a first terrain ruggedness index of a wind farm wind tower and a second terrain ruggedness index of a wind turbine generator set.

[0098] The calculation module 403 is used to calculate the uncertainty of the wind flow model extrapolation based on the first position data, the second position data, the first terrain ruggedness index and the second terrain ruggedness index. The wind flow model is used to obtain the wind measurement data of the hub height of the wind turbine generator set based on the wind measurement data of the wind farm wind tower.

[0099] The further functional description of each of the above modules is the same as that of the above corresponding embodiments and will not be repeated here.

[0100] The uncertainty calculation device for extrapolating the wind flow model of the wind farm wind measurement data in this embodiment is presented in the form of a functional unit, where the unit refers to an ASIC (Application Specific Integrated Circuit) circuit, a processor and memory that executes one or more software or fixed programs, and / or other devices that can provide the above functions.

[0101] The embodiment of the present invention also provides a computer device having the above Figure 4The uncertainty calculation device for extrapolating the wind flow model of the wind farm wind measurement data is shown.

[0102] See also Figure 5 , Figure 5 is a schematic diagram of the structure of a computer device provided by an optional embodiment of the present invention, such as Figure 5 As shown, the computer device includes: one or more processors 10, a memory 20, and interfaces for connecting various components, including high-speed interfaces and low-speed interfaces. Various components are connected to each other using different buses for communication, and can be installed on a common mainboard or installed in other ways as needed. The processor can process the instructions executed in the computer device, including instructions stored in or on the memory to display the graphical information of the GUI on an external input / output device (such as, a display device coupled to the interface). In some optional embodiments, if necessary, multiple processors and / or multiple buses can be used together with multiple memories and multiple memories. Similarly, multiple computer devices can be connected, and each device provides some necessary operations (for example, as a server array, a group of blade servers, or a multi-processor system). Figure 5 A processor 10 is taken as an example.

[0103] The processor 10 may be a central processing unit, a network processor or a combination thereof. The processor 10 may further include a hardware chip. The hardware chip may be a dedicated integrated circuit, a programmable logic device or a combination thereof. The programmable logic device may be a complex programmable logic device, a field programmable gate array, a general purpose array logic or any combination thereof.

[0104] The memory 20 stores instructions executable by at least one processor 10, so that the at least one processor 10 executes the method shown in the above embodiment.

[0105] The memory 20 may include a program storage area and a data storage area, wherein the program storage area may store an operating system, an application required for at least one function; the data storage area may store data created according to the use of the computer device, etc. In addition, the memory 20 may include a high-speed random access memory, and may also include a non-transient memory, such as at least one disk storage device, a flash memory device, or other non-transient solid-state storage device. In some optional embodiments, the memory 20 may optionally include a memory remotely arranged relative to the processor 10, and these remote memories may be connected to the computer device via a network. Examples of the above-mentioned network include, but are not limited to, the Internet, an intranet, a local area network, a mobile communication network, and combinations thereof.

[0106] The memory 20 may include a volatile memory, such as a random access memory; the memory may also include a non-volatile memory, such as a flash memory, a hard disk or a solid state drive; the memory 20 may also include a combination of the above types of memory.

[0107] The computer device also includes an input device 30 and an output device 40. The processor 10, the memory 20, the input device 30 and the output device 40 may be connected via a bus or other means. Figure 5 The example of connecting through bus is taken in the following.

[0108] The input device 30 can receive input digital or character information, and generate key signal input related to the user settings and function control of the computer device, such as a touch screen, a keypad, a mouse, a track pad, a touch pad, an indicator bar, one or more mouse buttons, a trackball, a joystick, etc. The output device 40 may include a display device, an auxiliary lighting device (e.g., an LED) and a tactile feedback device (e.g., a vibration motor), etc. The above-mentioned display device includes but is not limited to a liquid crystal display, a light emitting diode, a display and a plasma display. In some optional embodiments, the display device can be a touch screen.

[0109] The embodiment of the present invention also provides a computer-readable storage medium. The method according to the embodiment of the present invention can be implemented in hardware, firmware, or can be implemented as a computer code that can be recorded in a storage medium, or can be implemented as a computer code that is originally stored in a remote storage medium or a non-temporary machine-readable storage medium and will be stored in a local storage medium through a network download, so that the method described herein can be stored in such software processing on a storage medium using a general-purpose computer, a dedicated processor, or programmable or dedicated hardware. Among them, the storage medium can be a magnetic disk, an optical disk, a read-only storage memory, a random access memory, a flash memory, a hard disk or a solid-state hard disk, etc.; further, the storage medium can also include a combination of the above types of memories. It can be understood that a computer, a processor, a microprocessor controller, or programmable hardware includes a storage component that can store or receive software or computer code. When the software or computer code is accessed and executed by a computer, a processor, or hardware, the method shown in the above embodiment is implemented.

[0110] A part of the present invention may be applied as a computer program product, such as a computer program instruction, which, when executed by a computer, can call or provide the method and / or technical solution according to the present invention through the operation of the computer. Those skilled in the art should understand that the existence of the computer program instruction in a computer-readable medium includes, but is not limited to, a source file, an executable file, an installation package file, etc., and accordingly, the way in which the computer program instruction is executed by the computer includes, but is not limited to: the computer directly executes the instruction, or the computer compiles the instruction and then executes the corresponding compiled program, or the computer reads and executes the instruction, or the computer reads and installs the instruction and then executes the corresponding installed program. Here, the computer-readable medium may be any available computer-readable storage medium or communication medium accessible to the computer.

[0111] Although the embodiments of the present invention have been described in conjunction with the accompanying drawings, those skilled in the art may make various modifications and variations without departing from the spirit and scope of the present invention, and such modifications and variations are all within the scope defined by the appended claims.

Claims

1. A method for calculating uncertainty in wind flow model extrapolation of wind farm wind measurement data, characterized in that: The method comprises: Acquire first position data of a wind speed sensor of a wind farm wind tower and second position data of a hub of a wind turbine generator set; Acquire a first terrain ruggedness index of the wind farm wind tower and a second terrain ruggedness index of the wind turbine generator set; The uncertainty of wind flow model extrapolation is calculated based on the first position data, the second position data, the first terrain ruggedness index and the second terrain ruggedness index. The wind flow model is used to obtain wind measurement data of the hub height of the wind turbine generator set based on the wind measurement data of the wind farm wind tower.

2. The uncertainty calculation method for wind flow model extrapolation of wind farm wind measurement data according to claim 1 is characterized in that: There are multiple wind farm wind towers and multiple hubs of the wind turbine generator set, and the uncertainty of wind flow model extrapolation calculated based on the first position data, the second position data, the first terrain ruggedness index, and the second terrain ruggedness index includes: Calculate the sub-item weights of each wind farm wind tower for each wind turbine generator set based on the first position data and the second position data; Calculate the partial uncertainty of each wind farm wind tower for each wind turbine generator set based on the first position data, the second position data, the first terrain ruggedness index, and the second terrain ruggedness index; The uncertainty of the wind flow model extrapolation is calculated based on the sub-item weights and the sub-item uncertainties.

3. The uncertainty calculation method for wind flow model extrapolation of wind farm wind measurement data according to claim 2 is characterized in that: The calculating the uncertainty of the wind flow model extrapolation based on the sub-item weights and the sub-item uncertainties includes: Wherein, U0 is the uncertainty of the wind flow model extrapolation, and W j,i is the sub-item weight of the j-th wind farm wind tower to the i-th wind turbine generator set, and the U j,i is the partial uncertainty of the j-th wind farm wind tower for the ith wind turbine generator set.

4. The uncertainty calculation method for wind flow model extrapolation of wind farm wind measurement data according to claim 2 is characterized in that: The first position data includes a first geodetic horizontal coordinate, a first geodetic vertical coordinate and a first altitude of the wind farm wind tower, and the second position data includes a second geodetic horizontal coordinate, a second geodetic vertical coordinate and a second altitude of the hub of the wind turbine generator set.

5. The uncertainty calculation method for wind flow model extrapolation of wind farm wind measurement data according to claim 4 is characterized in that: The calculating, based on the first position data and the second position data, the sub-item weights of each wind farm wind tower for each wind turbine generator set comprises: The spatial distance between each wind farm wind tower and each wind turbine generator set is calculated based on the first position data and the second position data as follows: Among them, the D j,i is the spatial distance between the jth wind farm wind tower and the ith wind turbine generator set, and the X j , Y j , Z j are the first geodetic horizontal coordinate, the first geodetic vertical coordinate and the first altitude, respectively, the X i , Y i , Z i are the second geodetic horizontal coordinate, the second geodetic vertical coordinate and the second altitude respectively; The sub-item weights are determined based on the spatial distance as follows: Among them, the W j,i is the sub-item weight of the j-th wind farm wind tower to the ith wind turbine generator set, and n is the total number of wind farm wind towers.

6. The uncertainty calculation method for wind flow model extrapolation of wind farm wind measurement data according to claim 4 is characterized in that: The calculating of the sub-item uncertainty of each wind farm wind tower for each wind turbine generator set based on the first position data, the second position data, the first terrain ruggedness index and the second terrain ruggedness index comprises: Among them, the U j,i is the partial uncertainty of the j-th wind farm wind tower for the i-th wind turbine generator set, the R j is the first terrain ruggedness index, the R i is the second terrain ruggedness index, the X j , Y j , Z j are the first geodetic horizontal coordinate, the first geodetic vertical coordinate and the first altitude, respectively, the X i , Y i , Z i are respectively the second geodetic horizontal coordinate, the second geodetic vertical coordinate and the second altitude, and m is the total number of the wind turbine generator sets.

7. The uncertainty calculation method for wind flow model extrapolation of wind farm wind measurement data according to any one of claims 1 to 6, characterized in that: The step of obtaining a first terrain ruggedness index of the wind farm wind tower and a second terrain ruggedness index of the wind turbine generator set comprises: Taking the wind farm wind measurement tower as the center of the circle, dividing a plurality of radius line segments according to a preset angle and a preset length, dividing the radius line segment into a plurality of small line segments using contour lines, and calculating the inclination of each small line segment, obtaining the number ratio of the small line segments with an inclination angle greater than the preset inclination angle corresponding to each radius line segment, calculating the average number ratio of all radius line segments, and obtaining the first terrain ruggedness index; Taking the wind turbine generator set as the center of the circle, a plurality of radius line segments are divided according to a preset angle and a preset length, the radius line segment is divided into a plurality of small line segments using contour lines, and the inclination of each small line segment is calculated, the proportion of the number of small line segments corresponding to each radius line segment and having an inclination angle greater than the preset inclination angle is obtained, the average proportion of the number of all radius line segments is calculated, and the second terrain ruggedness index is obtained.

8. A computer device, characterized in that: include: A memory and a processor, wherein the memory and the processor are communicatively connected to each other, the memory stores computer instructions, and the processor executes the uncertainty calculation method for extrapolating a wind flow model of wind farm wind measurement data according to any one of claims 1 to 7 by executing the computer instructions.

9. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores computer instructions, and the computer instructions are used to enable a computer to execute the uncertainty calculation method for extrapolating a wind flow model of wind farm wind measurement data according to any one of claims 1 to 7.

10. A computer program product, characterized in that The method comprises computer instructions, wherein the computer instructions are used to enable a computer to execute the uncertainty calculation method for extrapolating a wind flow model of wind farm wind measurement data according to any one of claims 1 to 7.