Wastewater discharge risk assessment method for plateau highway construction

Through the recurrent neural network model combined with geographic survey data to evaluate the wastewater discharge risks of plateau road construction, scientific plans were formulated, and the problems of low efficiency of wastewater treatment facilities in low temperature environments and large fluctuations in wastewater volume were solved, achieving efficient wastewater treatment and environmental protection.

CN119026929APending Publication Date: 2024-11-26SICHUAN HIGHWAY PLANNING SURVEY DESIGN AND RESEARCH INSTITUTE LTD
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202411523948.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-30
Publication Date
2024-11-26

AI Technical Summary

Technical Problem

During the construction of plateau roads, wastewater treatment facilities are affected by low temperatures, resulting in a decrease in microbial activity, and the wastewater discharge fluctuates greatly, which easily exceeds the purification and treatment capacity, causing environmental pollution risks. The existing technology lacks effective treatment methods for fragile plateau environments.

Method used

The recurrent neural network (RNN) model is used to combine ground exploration data and wastewater discharge historical data to conduct wastewater discharge risk assessment. Through GPS and ground exploration data matching, a wastewater discharge risk assessment model is established, and a wastewater treatment plan is determined, including preparing flocculants and medium-sized and modular wastewater treatment equipment is installed to deal with different wastewater volumes.

Benefits of technology

It has achieved reliable assessment of wastewater discharge risks in plateau road construction and scientific plan formulation, improved the accuracy and efficiency of wastewater treatment, avoided environmental pollution, and effectively responded to water influx incidents in tunnel construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119026929A_ABST
    Figure CN119026929A_ABST
Patent Text Reader

Abstract

The invention belongs to the technical field of ecological environmental protection, and relates to a plateau highway construction wastewater discharge risk assessment method, which comprises the following steps: S1, obtaining plateau highway construction tunnel wastewater discharge historical data; performing cleaning and standardization treatment on the wastewater discharge historical data; s2, acquiring road line geological exploration data; the road construction line position GPS data and the road line geological exploration data are fused; s3, according to the GPS data of the road construction line position, matching the discharge historical data with the road line geological exploration data to serve as a waste water discharge training set; s4, training a wastewater discharge risk assessment model by using the wastewater discharge training set; s5, in the tunnel construction process, inputting the GPS information of the current construction position of the road construction line tunnel and the road line geological exploration data into the wastewater discharge risk assessment model to obtain a wastewater discharge risk score of the current construction position of the tunnel; and S6, determining a wastewater treatment plan according to the wastewater discharge risk score.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the field of ecological environmental protection technology, in particular to a method for risk assessment of wastewater discharge in plateau highway construction, and is an innovative achievement in ecological environmental protection technology for highway construction in plateau areas. Background Art

[0002] Plateau refers to areas with an altitude of more than 1,000 meters and a relative height of more than 500 meters, and a relatively flat or undulating terrain. The climate in the western Sichuan Plateau is highly variable, with significant temperature differences between day and night and between seasons, which leads to the operating efficiency of wastewater treatment facilities, especially wastewater treatment facilities containing microbial purification, during the construction of plateau roads. The most important thing is that low temperature may reduce the activity of microorganisms and affect the effect of microbial purification treatment. The influence of low temperature and temperature difference between day and night on the activity of microorganisms is not easy to overcome by simple measures, and the discharge of construction wastewater is usually characterized by large sporadic nature and fluctuations in the composition of wastewater pollutants.

[0003] In addition, the temporal and spatial distribution of water resources in the plateau highway construction area is uneven, and there is usually a large difference in rainfall between the rainy season and the dry season. In the dry season, the environment's self-purification ability is weak, and occasional wastewater exceeds the purification capacity, which may cause greater pollution risks to the water resources of the surrounding natural environment.

[0004] At the same time, during the construction of plateau highways, the complex terrain and landforms of the region make both surface water circulation and groundwater flow different from those in plains. Once wastewater discharge exceeds the controllable range, it may cause rapid migration and diffusion of wastewater in mountainous / canyon environments, making subsequent treatment very difficult. After these wastewaters flow into the natural environment, they will cause serious damage to the fragile local ecosystem, and the ecological recovery cycle in the plateau area may take several years.

[0005] The existing technology for wastewater purification during plateau highway construction mainly uses fixed sedimentation, flocculation, filtration and other process methods. However, different wastewaters contain different pollutants, and the treatment methods required are also different.

[0006] The significant characteristics of the construction wastewater from the bridge pile foundation impact drilling process are high turbidity, chromaticity, and total dissolved solids concentration. The main reason is that the bridge impact drilling process mainly uses clay to make slurry for balancing the well wall pressure, cooling the drill bit, protecting the hole wall, and suspending the drilling cuttings. Therefore, the mud concentration in the mud wastewater is high, and the turbidity, chromaticity, and total dissolved solids concentration of the supernatant of the mud wastewater are high. In addition, since the impact drill wire rope is often coated with lubricating oil, petroleum substances are found in the water body detection.

[0007] The notable characteristics of the mixing station wastewater are high turbidity, color, total dissolved solids concentration and pH value. The main reasons are that the vehicle transportation process causes too much concrete sludge on the site, which flows into the sedimentation tank through site flushing, and the tank truck washing wastewater contains a large amount of residual concrete. Therefore, the sludge concentration in the wastewater is high, and the turbidity, color and total dissolved solids concentration of the wastewater supernatant are high.

[0008] During the construction of plateau highways, wastewater pollutants discharged at different locations are different, and the total amount of emissions fluctuates differently, resulting in different risks of environmental pollution. Traditional wastewater treatment processes in plain areas are mainly for wastewater treatment processes with relatively stable emissions and large buffer conditions, but lack experience in treating wastewater with large fluctuations under fragile plateau environmental conditions. Summary of the invention

[0009] The purpose of the present invention is to overcome the problems existing in the prior art of plateau highway construction, such as fragile plateau geological environment, large fluctuations in wastewater discharge, and great impact of wastewater on environmental pollution, and to provide a wastewater discharge risk assessment method for plateau highway construction. By predicting the wastewater discharge risk in advance, better guidance can be provided for the formulation of preventive measures to avoid environmental risks caused by direct wastewater discharge.

[0010] In order to achieve the above-mentioned object of the invention, the present invention provides the following technical solutions: A method for risk assessment of wastewater discharge in plateau highway construction comprises the following steps: S1. Obtain the historical data of wastewater discharge from plateau highway construction tunnels, wherein the historical data includes: wastewater discharge location GPS, wastewater type S, wastewater discharge volume Q, wastewater turbidity TU, wastewater pH, and wastewater conductivity.

[0011] Clean and standardize historical wastewater discharge data; S2, obtaining geological survey data of the highway route, wherein the geological survey data includes: rock formation properties R, geological water content data w; The GPS data of the highway construction line location and the geological survey data of the highway line are integrated to obtain the rock formation properties R and geological water content data w of each area of ​​the highway construction line; S3. According to the GPS data of the highway construction line location, the historical emission data and the geological survey data of the highway line are matched to obtain the corresponding relationship between the historical emission data and the geological survey data as the wastewater discharge training set; S4, using the wastewater discharge training set, using the RNN recurrent neural network to train the wastewater discharge risk assessment model, and obtaining the wastewater discharge risk assessment model based on the GPS information of the highway construction line; S5. During the tunnel construction process, the GPS information of the current construction position of the highway construction line tunnel and the highway line geological survey data are input into the wastewater discharge risk assessment model to obtain the wastewater discharge risk score of the current construction position of the tunnel; S6. Determine the wastewater treatment plan based on the wastewater discharge risk score.

[0012] The wastewater discharge risk assessment method for plateau highway construction of the present invention is aimed at the relationship between the fluctuation characteristics of wastewater discharge and the historical geological water inflow during tunnel construction, and uses geological survey data and wastewater discharge volume Q, wastewater turbidity TU, wastewater pH, and conductivity as wastewater characteristics, and geological survey data as inducement to perform model training to obtain a wastewater discharge risk assessment model. In particular, it can specifically target the relationship between tunnel geology and historical water inflow to obtain a more reliable risk assessment model and scientifically confirm the wastewater treatment plan.

[0013] The wastewater risks of plateau tunnel construction include face wastewater, lining concrete pouring wastewater, rock stratum water inrush, etc. The discharge of conventional construction wastewater is small and relatively stable, and the pollutant composition and content in this part of wastewater are small and relatively stable. However, there is a large uncertainty in tunnel water inrush. By using geological survey data and historical discharge data as training sets, training wastewater discharge risk assessment models can effectively include water inrush risks into the investigation, form a scientific wastewater treatment plan, and effectively prevent abnormal tunnel water inrush from causing wastewater discharge to exceed the treatment capacity and cause environmental pollution.

[0014] Furthermore, data cleaning refers to deleting irrelevant data, filling missing values, and identifying and deleting duplicate data. Through data cleaning and standardization, the accuracy, completeness, and reliability of historical wastewater discharge data are ensured.

[0015] Further, in S1, the wastewater discharge history data are divided by region according to the wastewater discharge location GPS data. According to the wastewater discharge location GPS data of each discharge history data, the data are divided by region, for example, every 20-200 meters is regarded as a region to merge the discharge history data. The type of wastewater discharge and the maximum discharge amount of wastewater are determined according to the sub-regions, so as to facilitate the block sorting of wastewater discharge data of each section of the plateau highway.

[0016] Furthermore, in S1, when the historical data of various wastewater discharges are divided according to regions, the maximum wastewater discharge amount Q in each region is taken as the wastewater discharge amount of the region.

[0017] Further, in S2, the geological survey data also includes tunnel burial depth H. The tunnel burial depth data determines the volume of the rock mass above the tunnel, which is directly related to the rock layer water content in the rock mass volume, so the tunnel burial depth is also included to improve the accuracy of the risk assessment of tunnel water inrush.

[0018] Furthermore, in S3, in the wastewater discharge training set, a matching relationship between the discharge history data and the highway line geological survey data is established, and data points with zero wastewater discharge are deleted.

[0019] Furthermore, in S3, the data within 10-50 meters of the adjacent tunnel entrance is deleted. The causes of wastewater generation and the types of pollutants at the tunnel entrance are affected by environmental factors outside the tunnel, which affects the accuracy of the model. Deleting this part of the data is conducive to improving the accuracy of the risk assessment model.

[0020] Further, in S6, the wastewater treatment plan includes preparing flocculants and neutralizers, and the preparation amounts of the flocculants and neutralizers are determined according to the scoring results.

[0021] Preferably, the method further comprises preparing a reaction tank so that the wastewater can react with the flocculant and the neutralizer in the reaction tank.

[0022] Preferably, the neutralizing agent is oxalic acid.

[0023] Further, in S6, the wastewater treatment plan includes modular wastewater treatment equipment.

[0024] Preferably, modular wastewater treatment equipment can be connected in series or in parallel. When the amount of wastewater is small, the modules can be connected in series to improve the quality of wastewater treatment; when the amount of water inflow increases, the modules can be connected in parallel to improve the wastewater treatment capacity and avoid wastewater exceeding the treatment capacity and causing pollution risks. Therefore, different wastewater treatment goals can be met through series and parallel connection.

[0025] Further, in S6, the wastewater treatment plan is planned according to the state of the tunnel along the slope or against the slope. The state of the tunnel along the slope or against the slope affects the time / space opportunity for tunnel wastewater treatment. If there is sufficient time / space for wastewater treatment after water inrush, the difficulty of tunnel wastewater treatment is relatively low, otherwise the difficulty of tunnel wastewater treatment is relatively high.

[0026] Compared with the prior art, the present invention has the following beneficial effects: 1. The tunnel construction wastewater discharge risk assessment method of the present invention adopts geological survey data and wastewater discharge volume Q, wastewater turbidity TU, wastewater pH, and electrical conductivity as wastewater characteristics, and trains a wastewater discharge risk assessment model according to the geological water gushing fluctuation characteristics. The water gushing volume of historical water gushing events that occurred during the tunnel construction process is targeted for model training to obtain a more reliable risk assessment model and scientifically confirm the wastewater treatment plan.

[0027] 2. The tunnel construction wastewater discharge risk assessment method of the present invention pays less attention to the wastewater risks of plateau tunnel construction, including face wastewater, lining concrete pouring wastewater, and rock stratum water gushing, and focuses on the abnormal changes in construction wastewater discharge to prevent abnormal tunnel water gushing from causing wastewater discharge to exceed the treatment capacity and cause environmental pollution.

[0028] 3. The tunnel construction wastewater discharge risk assessment method of the present invention sets up a treatment plan to modularly prepare wastewater treatment equipment to achieve series and parallel working modes. When there is less wastewater, the quality of wastewater treatment can be improved by series connection; when there is tunnel water inrush and the amount of wastewater is high, the wastewater treatment capacity can be improved in parallel to avoid the risk of pollution caused by wastewater exceeding the treatment capacity. BRIEF DESCRIPTION OF THE DRAWINGS

[0029] Figure 1 It is a schematic diagram of the process of Example 1. DETAILED DESCRIPTION

[0030] The present invention is further described in detail below in conjunction with test examples and specific implementation methods. However, this should not be understood as the scope of the above subject matter of the present invention being limited to the following embodiments, and all technologies realized based on the content of the present invention belong to the scope of the present invention.

[0031] Unless otherwise specified, in the description of the specific embodiments of the present invention, the terms indicating the orientation or position relationship such as "up", "down", "left", "right", "center", "inside", "outside", etc. are all expressions based on the orientation or position relationship shown in the drawings, or the orientation or position relationship in which the invented product / equipment / device is placed when it is usually used. These terms of orientation or position relationship are only for the convenience of describing the scheme of the present invention or simplifying the description in the specific embodiments, so as to facilitate the technicians to quickly understand the scheme, and do not indicate or imply that a specific device / component / element must have a specific orientation, or be constructed and operated in a specific position relationship, and therefore cannot be understood as a limitation on the present invention.

[0032] In addition, if the terms "horizontal", "vertical", "overhanging", "parallel" and the like appear, it does not mean that the corresponding devices / components / elements are required to be absolutely horizontal or vertical or overhanging or parallel, but may be slightly tilted or have deviations. For example, "horizontal" only means that its direction is more horizontal than "vertical", and does not mean that the structure must be completely horizontal, but may be slightly tilted. Alternatively, it can be simplified to mean that the corresponding devices / components / elements are set in directions such as "horizontal", "vertical", "overhanging", "parallel", etc., and can have an error / deviation of ±10% relative to the corresponding direction setting, more preferably an error / deviation within ±8%, more preferably an error / deviation within ±6%, more preferably an error / deviation within ±5%, and more preferably an error / deviation within ±4%. As long as the corresponding device / component / element is within the error / deviation range, it can still achieve its role in the scheme of the present invention.

[0033] In addition, the expressions “first”, “second”, “third”, etc. that appear in the terms are merely descriptions used to distinguish the same or similar components and should not be understood as emphasizing or implying the relative importance of specific components.

[0034] In addition, in the description of the embodiments of the present invention, "several", "plurality" and "a number" represent at least 2. It can be any number such as 2, 3, 4, 5, 6, 7, 8, 9, and even more than 9.

[0035] In addition, in the description of the technical solution of the present invention, unless otherwise clearly specified / defined / restricted, the terms "set", "install", "connect", "connected", "provided with", "laid", and "arranged" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection, and can be welding, riveting, bolting, threading, and other commonly used connection means in the field. This connection can be a mechanical connection, an electrical connection, or a communication connection; it can be a direct connection, or an indirect connection through an intermediate medium, and it can be the internal connection of two elements.

[0036] Example 1 Taking a certain highway as an example, factors such as the number of environmental protection equipment and economic cost are classified as environmental benefits and economic benefits as indicators. The weight of each factor is determined by the hierarchical analysis method for the completed sections, and a total benefit evaluation system for the entire highway construction process is constructed. The evaluation of the completed sections is used as a reference, a tunnel wastewater discharge risk assessment model is established, and a wastewater discharge assessment model method is proposed.

[0037] According to the wastewater treatment of completed tunnel construction sections, the established model is used for wastewater discharge risk assessment of unfinished tunnel construction sections, forming an assessment and management model based on geological data. Highway tunnel construction wastewater mainly comes from production wastewater generated by tunnel construction face construction, lining construction and bottom water gushing. Among them, construction production wastewater is alkaline water with high turbidity. The main pollutants are inorganic substances represented by SS, with less organic pollutants. Ammonia nitrogen and CODcr are not its pollution factors; the CODcr content of construction domestic sewage is the highest, far exceeding the first-level standard of the "Comprehensive Sewage Discharge Standard" (GB8978-1996), and the water body is rich in SS and petroleum grease. After the construction production wastewater is treated by natural sedimentation, mechanical treatment, flocculation sedimentation, etc., except for SS and PH, the effluent can basically meet the discharge requirements of Class III receiving water bodies, and generally meet the reuse requirements.

[0038] Tunnel water inrush is the main cause of wastewater discharge fluctuations. Through geological survey data, we obtain the rock properties of the stratum and historical water inrush data. Combined with the historical wastewater discharge, we train the wastewater discharge risk assessment model and obtain a risk assessment model that can accurately assess the relevant wastewater discharge volume. This can well guide the wastewater prevention and treatment work during tunnel construction.

[0039] In order to overcome the wastewater discharge risk problem during the construction of a certain high-speed tunnel, a wastewater discharge risk assessment method for plateau highway construction is proposed, which includes the following steps: S1. Obtain the historical data of wastewater discharge from plateau highway construction tunnels, including: wastewater discharge location GPS, wastewater type S, wastewater discharge volume Q, wastewater turbidity TU, wastewater pH, and wastewater conductivity. Clean and standardize the wastewater discharge historical data.

[0040] The conductivity of wastewater is positively correlated with the total dissolved solids (TDS) in the water. By measuring the conductivity of wastewater, we can quickly determine the amount of dissolved substances in the wastewater. The more substances dissolved in the water, the better the conductivity of the water, and the greater the conductivity value.

[0041] Table 1: Some wastewater types and physical and chemical properties case data

[0042] S2, obtaining geological survey data of the highway route, wherein the geological survey data includes: rock formation properties R, geological water content data w, normal water inflow of the formation, and maximum water inflow of the formation; Table 2: Case data of rock formation properties and wastewater discharge at different locations

[0043] The GPS data of the highway construction line location and the geological survey data of the highway line are integrated to obtain the rock layer properties R, geological water content data w, and historical water inflow in each area of ​​the highway construction line. The above data are collected according to the needs of model training. According to the water inflow accidents that occur during tunnel construction, the data set is collected and updated simultaneously, and the model update training is performed. As the tunnel construction position advances, the geological layer also changes accordingly. For example, the water inflow accident data closer to the construction face has a greater impact on the subsequent results, so the collected historical data can be updated to improve the accuracy of model prediction.

[0044] S3. According to the GPS data of the highway construction line location, the historical emission data and the geological survey data of the highway line are matched to obtain the corresponding relationship between the historical emission data and the geological survey data as the wastewater discharge training set; S4. Using the wastewater discharge training set, the RNN recurrent neural network is used to train the wastewater discharge risk assessment model to obtain the wastewater discharge risk assessment model based on the GPS information of the highway construction line.

[0045] Use Python combined with the RNN recurrent neural network algorithm to train the model. The training process is imported into the torch framework. The reference code is as follows: import torch import torch.nn as nn import torch.optim as optim The parameters of the RNN recurrent neural network are set as follows: 64 hidden layers, sequence length 100, and the reference code is as follows.

[0046] input_size = feature_dimension hidden_size = 64 sequence_length = 100 batch_size = 100 model = RNNModel(input_size, hidden_size, output_size) criterion = nn.BCEWithLogitsLoss() optimizer = optim.Adam(model.parameters(), lr=0.001) X_train = torch.randn(batch_size, sequence_length, input_size) y_train = torch.randint(0, 2, (batch_size, 1)).float() Training the model for epoch in range(10): model.zero_grad() output = model(X_train) loss = criterion(output.view(-1), y_train.view(-1)) loss.backward() optimizer.step() print(f'Epoch {epoch+1}, Loss: {loss.item()}') The above code for training the RNN neural recurrent network model using Python is only for reference. Those skilled in the art can adjust the code parameters as needed, and can also use TensorFlow to build and train an RNN model. Using different Python or TensorFlow components for the RNN neural recurrent network training method does not affect the training of the model.

[0047] S5. During the tunnel construction process, the GPS and highway route geological survey data of the tunnel construction surface of the highway construction line are input into the wastewater discharge risk assessment model to obtain the wastewater discharge risk score of the current tunnel construction surface; S6. Determine the wastewater treatment plan based on the wastewater discharge risk score.

[0048] Example 2 During the construction of a certain tunnel, the actual lithology data obtained was entered into the database and compared with the rock layer distribution in the geological survey data to estimate the lithology / surrounding rock grade of the next section of the tunnel excavation. Different surrounding rock grades correspond to different risk levels. Analysis of sewage generation: Through the analysis of tunnel wastewater collected on site, it was found that tunnel wastewater is mainly wastewater formed by stable construction water discharge. The pollutants in this part of wastewater are mainly various greases of construction equipment and chemical reagents used in the construction process, which are mixed into the water to form wastewater. The pollution degree is high, but the amount is small and stable. It grows steadily with the depth of tunnel construction. It can be treated by setting up conventional wastewater treatment equipment and chemicals.

[0049] In order to assess the risk of wastewater discharge from plateau highway construction, the following steps were adopted: S1. Obtain the historical data of wastewater discharge from tunnels during plateau highway construction, including: wastewater discharge location GPS, wastewater type S, wastewater discharge volume Q, wastewater turbidity TU, wastewater pH, and wastewater conductivity. Divide the wastewater discharge location GPS of each historical data by region, merge the historical data of discharge every 30 meters as a region, and sort out the wastewater discharge data of each section of the plateau highway in a block manner, and take the largest wastewater discharge volume Q in the region as the wastewater discharge volume of the region.

[0050] S2. Obtaining geological survey data of the highway route, wherein the geological survey data includes: rock formation properties R, geological water content data w, historical formation water inflow, and tunnel burial depth.

[0051] The GPS data of the highway construction line location and the geological survey data of the highway line are integrated to obtain the rock formation properties R, geological water content data w, stratum water inflow and tunnel depth in each area of ​​the highway construction line. The tunnel depth determines the volume of the rock mass above the tunnel, which can affect the water inflow volume and speed.

[0052] S3. According to the GPS data of the highway construction line location, the emission history data and the highway line geological survey data are matched to obtain the corresponding relationship between the emission history data and the geological survey data. The data points with zero wastewater discharge are deleted, and the data within 10-50 meters of the tunnel entrance are deleted. The remaining data is used as the wastewater discharge training set.

[0053] S4. Using the wastewater discharge training set, a wastewater discharge risk assessment model is trained to obtain a wastewater discharge risk assessment model based on GPS information of highway construction routes.

[0054] S5. During the tunnel construction process, the GPS and highway route geological survey data of the tunnel construction surface of the highway construction line are input into the wastewater discharge risk assessment model to obtain the wastewater discharge risk score of the current tunnel construction surface; S6. According to the wastewater discharge risk score, determine the wastewater treatment plan, prepare flocculants (polyacrylamide PAM), neutralizers (oxalic acid) and wastewater treatment equipment. The wastewater treatment equipment is modularized, and multiple modular wastewater treatment equipment are set up according to the wastewater discharge risk score. When the amount of wastewater is small, some modules can complete the wastewater treatment; when there is a sudden influx, the modular wastewater treatment equipment is connected in parallel to meet the wastewater volume demand.

[0055] Further, in S6, a wastewater treatment plan is prepared according to the state of the tunnel's slope or reverse slope. The slope or reverse slope directly affects the timing of tunnel wastewater treatment. If there is sufficient time and space, the preparation amount of treatment agents and equipment in the plan can be reduced accordingly. Otherwise, the treatment agents and equipment should be prepared in large batches.

[0056] The plateau tunnel exit is at a high altitude, low temperature, and has a complex geographical environment. The mountainous area lacks space for special wastewater treatment purification equipment. Once the wastewater flows out of the tunnel, the difficulty of treatment will increase exponentially. The layout of related wastewater treatment equipment is difficult, and the operating efficiency of the facilities is reduced. Once it flows out of the tunnel, the wastewater may have a serious impact on the fragile ecological environment of the plateau, such as water source and soil pollution, and cause serious damage to the surrounding ecological environment. Therefore, it is necessary to use the plateau highway construction wastewater discharge risk assessment method of the present invention to conduct scientific research, prepare plans, and fully and efficiently complete the wastewater treatment work.

[0057] The wastewater discharge risk assessment method of the present invention collects wastewater discharge data during tunnel construction, combines geological survey data for quantitative analysis, calculates the discharge risk index and pollution probability of various pollutants, and then evaluates the size of environmental risks. With reference to the decision-making water environment characteristic pollutant treatment plan, the key risk sources in the tunnel construction process are fully considered, scientific decisions are made, and risk scores are scored. According to the scores, they can be divided into grades, such as major risk sources, large risk sources and general risk sources, etc., and matching treatment plans are set up to build a monitoring plan for major pollutant emission risk sources.

Claims

1. A method for risk assessment of wastewater discharge in plateau highway construction, characterized in that: The following steps are involved: S1. Obtain historical data of wastewater discharge from tunnels during plateau highway construction, wherein the historical data includes: wastewater discharge location GPS, wastewater type S, wastewater discharge volume Q, wastewater turbidity TU, wastewater pH, and wastewater conductivity; Clean and standardize historical wastewater discharge data; S2, obtaining geological survey data of the highway route, wherein the geological survey data includes: rock formation properties R, geological water content data w, normal water inflow of the formation, and maximum water inflow of the formation; The GPS data of the highway construction line location and the geological survey data of the highway line are integrated to obtain the rock formation properties R, geological water content data w, normal formation water inflow and maximum formation water inflow in each area of ​​the highway construction line; S3. According to the GPS data of the highway construction line location, the historical emission data and the geological survey data of the highway line are matched to obtain the corresponding relationship between the historical emission data and the geological survey data as the wastewater discharge training set; S4, using the wastewater discharge training set, using the RNN recurrent neural network to train the wastewater discharge risk assessment model, and obtaining the wastewater discharge risk assessment model based on the GPS information of the highway construction line; S5. During the tunnel construction process, the GPS information of the current construction position of the highway construction line tunnel and the highway line geological survey data are input into the wastewater discharge risk assessment model to obtain the wastewater discharge risk score of the current construction position of the tunnel; S6. Determine the wastewater treatment plan based on the wastewater discharge risk score.

2. A plateau highway construction wastewater discharge risk assessment method according to claim 1, characterized in that: In S1, the wastewater discharge historical data are divided by region according to the wastewater discharge location GPS data.

3. According to claim 2, a method for risk assessment of wastewater discharge in plateau highway construction is characterized in that: In S1, when the historical data of wastewater discharge are divided by region, the maximum wastewater discharge amount Q in each region is taken as the wastewater discharge amount of the region.

4. According to claim 1, a method for risk assessment of wastewater discharge in plateau highway construction is characterized in that: In S2, the geological survey data further includes the tunnel burial depth H.

5. According to claim 1, a method for risk assessment of wastewater discharge in plateau highway construction is characterized in that: In S3, in the wastewater discharge training set, a matching relationship between the historical discharge data and the highway line geological survey data is established, and data points with zero wastewater discharge are deleted.

6. According to claim 1, a method for risk assessment of wastewater discharge in plateau highway construction is characterized in that: In S3, delete the data within 10-50 meters of the tunnel entrance.

7. A plateau highway construction wastewater discharge risk assessment method according to claim 1, characterized in that: In S6, the wastewater treatment plan includes preparing flocculants and neutralizers.

8. A method for risk assessment of wastewater discharge from plateau highway construction according to claim 7, characterized in that: It also includes preparing the reaction cell.

9. A plateau highway construction wastewater discharge risk assessment method according to claim 1, characterized in that: In S6, the wastewater treatment plan includes modular wastewater treatment equipment.

10. A method for risk assessment of wastewater discharge from plateau highway construction according to claim 9, characterized in that: Modular wastewater treatment equipment can be connected in series or in parallel.

Citation Information

Patent Citations

  • Model training method, nuclear pollution information determination method, device and equipment

    CN118228794A

  • Construction tunnel water gushing and inrush monitoring and early warning method

    CN118391096A

  • Construction risk assessment system and method for sewage treatment facility

    CN118552087A