Construction technology and equipment for high-penetrating-force vibration impact guide hole immersed tube pile

By combining high-frequency vibration hammer and impact pipe, solid alloy steel prefabricated conical pile tips hit the broken stone, the penetration difficulty of immersed pipe piles in the block gravel fill layer is solved, and efficient immersed pipe piles are realized The construction overcomes the problems of insufficient penetration and equipment damage of traditional technologies.

CN119041385APending Publication Date: 2024-11-29SHANGHAI HARBOUR SOFT SOIL TREATMENT ENG (GRP) CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411134692.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-19
Publication Date
2024-11-29

AI Technical Summary

Technical Problem

The existing immersed pipe pile construction technology is difficult to penetrate the gravel filling layer, resulting in low construction efficiency and equipment damage.

Method used

High-frequency vibration hammer combined with impact pipes are used to lead holes through solid alloy steel prefabricated conical pile tips to crush or squeeze out blocks, and vibrate or hammer the immersed pipe pile machine to form a compact pile body, overcoming traditional immersed pipe piles Difficulty in penetration in complex strata.

Benefits of technology

Effectively penetrate deep gravel layers, improve the penetration and construction efficiency of immersed pipe piles, avoid equipment damage, and meet the pile formation needs of deep immersed pipe piles in soft soil foundations.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119041385A_ABST
    Figure CN119041385A_ABST
Patent Text Reader

Abstract

The invention discloses a high-penetrating-power vibration impact guide hole immersed tube pile construction technology and equipment, and relates to the technical field of foundation treatment.The high-penetrating-power vibration impact guide hole immersed tube pile construction technology comprises the following steps that 1, guide hole equipment is in place, specifically, a vibration hammer fixes a sleeved impact tube through a fixator, and a pile frame is aligned with a pile position; (2) the impact pipe leads a hole to the position about 1 m below the bottom face of the block gravel filling layer, a vibration hammer is started, the vibration hammer drives the impact pipe to synchronously sink, vibration sinking is conducted in sequence from top to bottom till the bottom of the block gravel filling layer forms a hole, and then the vibration hammer pulls out the impact pipe; and (3) pipe sinking pile construction is conducted, specifically, a pile pipe sinks into the hole from the position above the guided hole opening, the pile pipe penetrates through the block gravel filling layer guiding hole, sludge and other soft soil layers till the needed depth is reached, then feeding is conducted in the pile pipe, and the pile pipe is vibrated and lifted up while feeding is conducted to form a dense pile body. The equipment comprises a vibratory hammer, a fixer and an impact tube, wherein the impact tube is fixed on the vibratory hammer through the fixer; the device further comprises an immersed tube pile machine and an immersed tube. The problem that a broken stone filling layer is difficult to penetrate during pipe sinking of an existing pipe sinking pile is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of foundation treatment and pile foundation engineering, and in particular to a construction process and equipment for high-penetration vibration impact lead-hole sinking pipe piles. Background Art

[0002] In the field of foundation reinforcement for construction projects, sinking pipe piles are often used for foundation reinforcement in the treatment of soft foundations. Sinking pipe piles include sinking pipe gravel piles and sinking pipe concrete cast-in-place piles. Sinking pipe gravel piles refer to sinking pipes with pile tips or valve pile tips that are vibrated or hammered to form holes in soft foundations, and then gravel is pressed into the formed holes through pile pipes. During the pile-forming process, the piles are gradually compacted and vibrated to form a dense pile body composed of gravel. Sinking pipe cast-in-place piles are cast-in-place piles in which a steel skeleton is suspended in the pile pipe after the hole is formed, and then concrete is poured while the pipes are pulled out by vibration. The vibration during the pipe pulling is used to compact the concrete to form the required cast-in-place piles.

[0003] At present, there are such geological conditions in foundation reinforcement and pile foundation projects. The strata contain gravel fill or construction waste fill. The particle size distribution of the fill layer is very uneven, the soft and hard distribution is extremely uneven, and the thickness varies greatly. The maximum particle size is 1.5m and the maximum thickness is 22m. There is also a certain thickness of silt and other soft soil and clay layers under the fill layer. In view of this geological situation, the sinking resistance of the pipe pile is large, and the penetration force of the construction equipment is very high.

[0004] The existing patent authorization announcement number is CN101575852A, which is a Chinese invention patent. It discloses a wall-protecting type bottom-expanding pipe-sinking pile construction method. The vibrating hammer is used as a power device. The sinking pipe is an inner and outer double-layer sinking pipe. The lower end of the core pipe is provided with a valve pile tip, and the outer sinking pipe is extended. First, the inner and outer sinking pipes are sunk into the pile position by the vibrating hammer, and then the core pipe is lifted, and the outer sinking pipe is filled with the designed amount of bottom-expanding concrete. The outer sinking pipe is lifted up so that the outer sinking pipe does not separate from the bottom-expanding concrete. The core pipe is driven by the vibrating hammer to repeatedly vibrate and tamp along the outer sinking pipe to expand and fill concrete until the bottom expansion requirement is met; then the core pipe is pulled out, and the steel cage is placed along the outer sinking pipe to form a pile. The pile operation can overcome the technical drawbacks of the existing sinking pipe-sinking pile construction method, such as shrinkage and collapse. However, in this technical solution, the bottom of the core pipe is a valve-type conical head, and the valve-type conical head of the outer pipe is easily damaged when passing through the hard layer of backfilled block stone with a larger particle size, so it cannot penetrate the thicker block gravel fill layer. Summary of the invention

[0005] Based on the above problems, the present invention aims to propose a high-penetration vibration impact lead-hole sinking pipe pile construction process and equipment to solve the problem that the current sinking pipe pile is difficult to penetrate the gravel fill layer when sinking the pipe. The specific solution is as follows:

[0006] A high-penetration vibration impact lead-hole sinking pipe pile construction process comprises the following steps:

[0007] Step 1) The drilling equipment is in place: the vibrating hammer fixes the impact pipe through the fixture, and the pile frame is aligned with the pile position;

[0008] Step 2) The impact pipe is led to a hole about 1m below the bottom of the gravel filling layer: the vibrating hammer is turned on, and the vibrating hammer drives the impact pipe to sink synchronously, and vibrates and sinks from top to bottom to form a hole at the bottom of the gravel filling layer, and then the vibrating hammer pulls out the impact pipe;

[0009] Step 3) Pipe-sinking pile construction: sink the pile pipe from the top of the hole, through the gravel fill layer, silt and other soft soil layers to the required depth, then add material into the pile pipe, and vibrate and lift the pile pipe to form a dense pile body while adding material.

[0010] Furthermore, in step 2), after the vibration hammer pulls out the impact tube, the impact tube remains on the pile frame waiting for the next construction step.

[0011] Furthermore, in step 3), the pipe-sinking piles include: gravel piles and concrete cast-in-place piles.

[0012] Furthermore, in the step 3), the method of pipe pile construction includes: using a vibration or hammer pipe pile driving machine.

[0013] A high-penetration vibration impact hole sinking pile construction equipment, comprising a vibration hammer, a fixture, and an impact pipe, wherein the impact pipe is fixed by the fixture, and the vibration hammer is fixed on the top of the fixture;

[0014] It also includes a pipe sinking pile machine and a pipe sinking, wherein the pipe sinking pile machine is used to form a pipe sinking gravel pile or concrete pile. Preferably, the diameter of the gravel pile or concrete pile during construction is generally 500-700mm, the pile length can reach 20-40m, and the lead hole diameter is about 100mm larger than the pipe sinking pile diameter.

[0015] Furthermore, the vibration hammer adopts a high-power high-frequency vibration hammer of more than 300kw.

[0016] Furthermore, the impact tube head is a solid alloy steel prefabricated conical pile tip.

[0017] Furthermore, the outer diameter of the immersed tube is smaller than the inner diameter of the immersed tube pile.

[0018] Furthermore, the fixer is a pile clamp or a flange.

[0019] Compared with the prior art, the present invention has the following beneficial effects:

[0020] In the present invention, the pipe-sinking pile construction process adopts a vibrating hammer combined with an impact tube to drill holes in a thick block gravel fill layer, that is, a relatively high-frequency vibrating hammer is used for impact vibration to form holes, and the impact tube is synchronously sunk by a vibrating hammer fixture, and the end of the impact tube is equivalent to a solid alloy steel prefabricated pile tip, which can impact and crush or squeeze the block stone directly below until the pipe pile is formed in the block gravel fill layer, silt and other soft soil layers and then pulled out. This can effectively overcome the disadvantage that conventional pipe-sinking pile machines cannot penetrate complex formations such as pebbles, large boulders, and large stones, and can meet the needs of pipe-sinking piles in soft soil foundations with hard layers such as thick block gravel layers. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] Figure 1 It is an overall schematic diagram of the present invention.

[0022] In the figure: 1. Vibratory hammer; 2. Fixer; 3. Impact pipe; 4. Pipe pile;

[0023] 100. Gravel fill layer; 200. Silt and other soft soil layers; 300. Non-soft soil layer. DETAILED DESCRIPTION

[0024] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments.

[0025] like Figure 1 As shown, a high-penetration vibration impact boring and pipe-sinking pile construction equipment comprises a vibration hammer 1, a fixture 2, and an impact pipe 3. The impact pipe 3 is fixed by the fixture 2, and the vibration hammer 1 is fixed on the top of the fixture 3.

[0026] The construction equipment also includes a pipe pile driving machine (not shown in the figure), which is used to form pipe piles 4. It should be noted that the pipe pile driving machine is a prior art and will not be described in detail here.

[0027] The vibrating hammer 1 is a high-power high-frequency vibrating hammer. Preferably, the vibrating hammer 1 is a high-power high-frequency vibrating hammer 1 with a power of more than 300 kW.

[0028] The head of the impact pipe 3 is a solid alloy steel prefabricated conical pile tip. The solid alloy steel prefabricated conical pile tip is used to impact and crush or squeeze out the block stone or construction waste directly below.

[0029] The fixer 2 is a pile clamp or a flange. The pile clamp is a prior art and will not be described in detail here; the flange can be connected between the vibration hammer 1 and the impact tube 3 by bolt connection.

[0030] In a possible embodiment, the outer diameter of the immersed tube is smaller than the inner diameter of the impact tube 3 .

[0031] In addition, the construction equipment of this embodiment also includes a pile frame (not shown in the figure). It should be noted that the pile frame is a prior art and will not be described in detail here.

[0032] Based on the given construction equipment, this embodiment also provides a high-penetration vibration impact hole-drilling pipe pile construction process, by appropriately increasing the hole depth of the impact pipe 3 to the bottom elevation of the gravel fill layer 100, and sinking the pipe in the hole to the designed elevation of the bottom of the pipe pile, and then pulling out the pile after pouring the pile body material.

[0033] See also Figure 1 , specifically including the following steps:

[0034] Step 1) The hole-guiding equipment is in place: the vibrating hammer 1 fixes the impact pipe 3 through the fixture 2, and the pile frame is aligned with the pile position;

[0035] Step 2) The impact pipe 3 is led to a hole about 1m below the bottom surface of the gravel filling layer 100: the vibrating hammer 1 is turned on, and the vibrating hammer 1 drives the impact pipe 3 to sink synchronously, and vibrates and sinks from top to bottom to form a hole at the bottom of the gravel filling layer 100, and then the vibrating hammer 1 pulls out the impact pipe 3; after the vibrating hammer 1 pulls out the impact pipe 3, the impact pipe 3 is retained on the pile frame waiting for the next step of construction;

[0036] Step 3) Construction of pipe-sinking pile 4: sink the pile pipe from the top of the hole into the hole, pass through the block gravel filling layer 100, the soft soil layer 200 such as silt to the required depth, then add materials into the pile pipe, and vibrate and lift the pile pipe to form a dense pile body while adding materials; wherein, the method of construction of pipe-sinking pile 4 includes: using vibration or hammer pipe-sinking pile machine, and measures such as reverse insertion and vibration retention during the filling process; pipe-sinking pile 4 includes: gravel pile, concrete cast-in-place pile;

[0037] Preferably, the diameter of the gravel pile or concrete pile during construction is generally 500-700 mm, the pile length can reach 20-40 m, and the lead hole diameter is about 100 mm larger than the inner diameter of the immersed pipe pile 4 .

[0038] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical scheme and inventive concept of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.

Claims

1. A high-penetration vibration impact lead-hole sinking pipe pile construction process, characterized in that: The following steps are involved: Step 1) The drilling equipment is in place: the vibrating hammer fixes the impact pipe through the fixture, and the pile frame is aligned with the pile position; Step 2) The impact pipe is led to a hole about 1m below the bottom of the gravel filling layer: the vibrating hammer is turned on, and the vibrating hammer drives the impact pipe to sink synchronously, and vibrates and sinks from top to bottom to form a hole at the bottom of the gravel filling layer, and then the vibrating hammer pulls out the impact pipe; Step 3) Pipe-sinking pile construction: sink the pile pipe from the top of the hole, through the gravel fill layer, silt and other soft soil layers to the required depth, then add material into the pile pipe, and vibrate and lift the pile pipe to form a dense pile body while adding material.

2. The high-penetration vibration impact hole sinking pile construction process according to claim 1 is characterized in that: In step 3), the pipe-sinking piles include: gravel piles and concrete cast-in-place piles.

3. The high-penetration vibration impact hole sinking pile construction process according to claim 1 is characterized in that: In the step 3), the method of pipe pile construction includes: using a vibration or hammer pipe pile driving machine.

4. A high-penetration vibration impact hole sinking pile construction equipment, characterized in that: It includes a vibrating hammer, a fixture, and an impact tube, wherein the impact tube is fixed by the fixture, and the vibrating hammer is fixed on the top of the fixture; It also includes a pipe-sinking pile machine and a pipe-sinking pile, wherein the pipe-sinking pile machine is used to form a pipe-sinking gravel pile or a concrete pile.

5. The high-penetration vibration impact hole sinking pile construction equipment according to claim 4 is characterized in that: The vibrating hammer adopts a high-power high-frequency vibrating hammer of more than 300kw.

6. The high-penetration vibration impact hole sinking pile construction equipment according to claim 4 is characterized in that: The impact tube head is a solid alloy steel prefabricated conical pile tip.

7. The high-penetration vibration impact hole sinking pile construction equipment according to claim 4 is characterized in that: The outer diameter of the immersed tube is smaller than the inner diameter of the immersed tube pile.

8. The high-penetration vibration impact hole sinking pile construction equipment according to claim 4 is characterized in that: The fixing device is a pile clamp or a flange.