Linear angle steel tower and tower erecting method thereof
By installing new tower legs between adjacent tower legs of the old tower and demolishing the old tower, combined with the design of a straight angle steel tower with diagonal connection nodes and stress adjustment thickness, the problems of increased engineering investment and extended power outage time caused by the construction of new towers were solved, achieving efficient tower replacement and structural stability.
Patent Information
- Application Number
- CN202411128852.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-16
- Publication Date
- 2024-11-29
AI Technical Summary
In existing technologies, in order to shorten the power outage time of transmission lines, it is necessary to build new towers at different locations than the original towers, which leads to an increase in project investment.
A straight angle steel tower and its erection method are provided. A new tower leg is installed between two adjacent tower legs of the original old tower. After the new tower leg is installed, the old tower is removed. The main tower material and crossarm are connected to the new tower leg. The connection stability is ensured by using diagonal connection nodes. The thickness of the main tower material is adjusted according to the stress conditions.
This allowed for the tower to be erected on the original site, making full use of the existing foundation, reducing the need for additional land use, shortening the duration of power outages, and ensuring the stability and economy of the structure.
Smart Images

Figure CN119041764A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of transmission tower design, in particular to a straight angle steel tower and a tower erection method thereof. Background Art
[0002] With the acceleration of urbanization, land resources have become increasingly scarce, resulting in great constraints on the construction of high-voltage transmission lines. In particular, projects involving the use of existing lines to increase the capacity of lines require the reconstruction or construction of new towers on the original lines. In order to shorten the construction period and reduce the duration of power outages on transmission lines, new towers often need to be constructed at different locations from the original towers, resulting in new compensation issues and increased investment in the project. Summary of the invention
[0003] The purpose of the present invention is to provide a straight angle steel tower and a tower erection method thereof, which is used to solve the problem in the prior art that in order to shorten the power outage duration of the transmission line, a new tower needs to be built by staggering the original tower position, thereby generating new compensation items and leading to increased project investment.
[0004] In order to achieve the above objectives, in a first aspect, an embodiment of the present application provides a straight angle steel tower, comprising:
[0005] Tower legs;
[0006] An iron tower main material is matched with the tower legs and connected to the upper ends of the tower legs, and a plurality of the iron tower main materials are staggered and extend upward to form a tower body;
[0007] A cross arm, provided with one or more cross arms, wherein the plurality of cross arms are spaced apart along the extension direction of the tower body, wherein the cross arm comprises a lower chord assembly and an upper chord assembly connected to the upper end of the lower chord assembly, wherein the lower chord assembly has two first connection nodes arranged diagonally opposite to each other, and two second connection nodes staggered from the two first connection nodes and arranged diagonally opposite to each other, wherein the first connection nodes and the second connection nodes are correspondingly connected to the main material of the iron tower; the upper chord assembly has two third connection nodes arranged diagonally opposite to each other, and the third connection nodes are correspondingly connected to the main material of the iron tower; and
[0008] The ground wire bracket is arranged at the top of the tower body.
[0009] In some embodiments of the present application, the lower chord rod assembly includes two first lower chord angle steels connected to one of the first connection nodes and symmetrically arranged with each other, and two second lower chord angle steels connected to another first connection node and symmetrically arranged with each other, and the other ends of the first lower chord angle steels and the second lower chord angle steels on the same side are connected via an auxiliary component;
[0010] It also includes a lower chord diagonal material connected between the first lower chord angle steel and the second lower chord angle steel on the same side and connected to the second connection node.
[0011] In some embodiments of the present application, the first connection node includes first connection members that are symmetrically arranged and connected to the main material of the iron tower, the first connection member includes a first steel plate horizontally connected to the outer side wall of the main material of the iron tower, and a second steel plate perpendicular to the first steel plate and arranged along the length extension direction of the first lower chord angle steel or the second lower chord angle steel, and the first steel plate and the second steel plate are connected and fixed to each other;
[0012] The first lower chord angle steel and the second lower chord angle steel both have a horizontal first connection portion and a second connection portion vertically connected to one side of the first connection portion; the first connection portion is fitted and connected to the corresponding second steel plate, and the second connection portion is fitted and connected to the corresponding first steel plate.
[0013] In some embodiments of the present application, the outer side walls of the two matching first steel plates are provided with a first stiffening plate, and the first stiffening plate at least covers a portion of the outer side walls of each of the first steel plates and is fixedly connected to each of the first steel plates.
[0014] In some embodiments of the present application, the second connection node includes second connecting parts that are symmetrically arranged and connected to the main material of the tower, the second connecting parts include a fourth steel plate horizontally connected to the outer wall of the main material of the tower, and the lower chord diagonal material is connected to the fourth steel plate.
[0015] In some embodiments of the present application, the upper chord rod assembly includes a first upper chord angle steel connected to one of the third connection nodes and symmetrically arranged with each other, and a second upper chord angle steel connected to another of the third connection nodes and symmetrically arranged with each other; and also includes an upper chord diagonal material arranged between the first upper chord angle steel and the second upper chord angle steel on the same side and connected to the third connection node.
[0016] In some embodiments of the present application, the third connection node includes third connecting members that are symmetrically arranged and connected to the main material of the iron tower, and the third connecting member includes a sixth steel plate horizontally connected to the outer wall of the main material of the iron tower, a seventh steel plate perpendicular to the sixth steel plate and arranged along the length extension direction of the first upper chord angle steel or the second upper chord angle steel, and an eighth steel plate perpendicular to the sixth steel plate and fittedly connected to the outer wall of the main material of the iron tower; the seventh steel plate and the eighth steel plate are both connected and fixed to the sixth steel plate;
[0017] The first upper chord angle steel and the second upper chord angle steel both have a horizontal third connection portion and a fourth connection portion vertically connected to one side of the third connection portion; the third connection portion is fit-connected to the corresponding sixth steel plate, the fourth connection portion is fit-connected to the corresponding seventh steel plate, and the upper chord diagonal material is connected to the sixth steel plate.
[0018] In some embodiments of the present application, the outer side walls of the two matching seventh steel plates are provided with a second stiffening plate, and the second stiffening plate at least covers a portion of the outer side wall of each of the seventh steel plates and is fixedly connected to each of the seventh steel plates.
[0019] In some embodiments of the present application, a reinforcing angle steel is further included between the adjacent first connecting member and the second connecting member, and a fifth steel plate arranged along the extension direction of the reinforcing angle steel and connected to the outer side wall of the main material of the iron tower is vertically connected to the fourth steel plate; a third steel plate arranged along the extension direction of the reinforcing angle steel and connected to the outer side wall of the main material of the iron tower is vertically connected to the first steel plate;
[0020] The reinforcing angle steel has a horizontal fifth connection portion and a sixth connection portion vertically connected to one side of the fifth connection portion, the sixth connection portion close to the first connection node is fitted and connected to the third steel plate, and the sixth connection portion close to the second connection node is fitted and connected to the fifth steel plate;
[0021] Auxiliary material components are connected between the plurality of reinforcing angle steels and form reinforcing members together with the auxiliary material components.
[0022] In some embodiments of the present application, a reinforcing angle steel is further included between the adjacent first connecting member and the second connecting member; a fifth steel plate arranged along the extension direction of the reinforcing angle steel and connected to the outer side wall of the main material of the iron tower is vertically connected to the fourth steel plate; a third steel plate arranged along the extension direction of the reinforcing angle steel is vertically connected to the first steel plate;
[0023] The reinforcing angle steel has a horizontal fifth connection portion and a sixth connection portion vertically connected to the fifth connection portion, the sixth connection portion close to the first connection node is fitted and connected to the third steel plate, and the sixth connection portion close to the second connection node is connected to the fifth steel plate;
[0024] Auxiliary material components are connected between the plurality of reinforcing angle steels and form reinforcing members together with the auxiliary material components.
[0025] In some embodiments of the present application, the thickness of the main material of the iron tower connected to the first connection node is greater than the thickness of the main material of the iron tower connected to the second connection node.
[0026] In a second aspect, an embodiment of the present application provides a tower erection method using the straight angle steel tower in the above embodiment, comprising the following steps:
[0027] Installing the tower legs of the straight angle steel tower between two adjacent tower legs of the old tower;
[0028] The old tower will be demolished;
[0029] An iron tower main material is connected to the upper end of the tower leg of the straight angle steel tower, and a plurality of the iron tower main materials extend upward to form the tower body of the straight angle steel tower;
[0030] Arrange one or more lower chord rod assemblies along the extension direction of the new tower body, wherein the lower chord rod assemblies are connected to the main material of the iron tower through the first connection node and the second connection node;
[0031] An upper chord assembly is connected to the upper end of the lower chord assembly, and the upper chord assembly and the lower chord assembly are connected to form a cross arm, wherein the upper chord assembly is connected to the main material of the iron tower through the third connection node;
[0032] A ground wire bracket is connected to the top of the tower body of the straight angle steel tower.
[0033] In some embodiments of the present application, a new tower leg is disposed in the middle of two adjacent tower legs of the old tower.
[0034] Compared with the prior art, the straight angle steel tower and the tower erection method of the embodiment of the present invention have the following beneficial effects: the present application installs a new tower leg between two adjacent tower legs of the original old tower, and after the installation of the new tower leg is completed, the old tower is dismantled, and the construction of the new iron tower is continued, so that the new tower body and the old tower body are staggered (the foundation of the tower legs of the original old tower is staggered), the tower is erected at the original tower position, the foundation of the original old tower is fully utilized, and there is no need to occupy additional new land area (reducing new compensation items), which effectively shortens the power outage duration of the transmission line; the cross arm is connected to the main material of the iron tower through diagonally arranged connection nodes, thereby ensuring the stability of the connection between the cross arm and the main material of the iron tower; at the same time, according to the stress condition of the tower body, the thickness of the main material of the iron tower at a position with greater stress is set to be larger, and the thickness of the main material of the iron tower at a position with less stress is set to be smaller, thereby ensuring both economic efficiency and structural safety. BRIEF DESCRIPTION OF THE DRAWINGS
[0035] Figure 1 It is a top view schematic diagram of the connection relationship between the lower chord assembly, the main material of the tower, and the reinforcement member of the present invention;
[0036] Figure 2 This is an enlarged schematic diagram of the structure at A of the present invention;
[0037] Figure 3 This is an enlarged schematic diagram of the structure at B of the present invention;
[0038] Figure 4 It is a top view schematic diagram of the connection relationship between the upper chord assembly and the main material of the tower of the present invention;
[0039] Figure 5 This is an enlarged schematic diagram of the structure at position C of the present invention;
[0040] Figure 6 This is a schematic diagram of the overall structure of the new tower of the present invention;
[0041] Figure 7 This is a schematic diagram of the overall structure of the straight angle steel tower of the present invention;
[0042] Figure 8 This is a schematic diagram of the overall structure of the existing old iron tower.
[0043] In the figure, 1, new tower body; 11, new tower leg; 12, main material of the iron tower; 13, ground wire bracket; 2, cross arm; 21, first lower chord angle steel; 211, first connection part; 212, second connection part; 22, second lower chord angle steel; 23, auxiliary parts; 24, lower chord oblique material; 25, first upper chord angle steel; 251, third connection part; 252, fourth connection part; 26, second upper chord angle steel; 27, upper chord oblique material;
[0044] 3. Reinforcement member; 31. Reinforcement angle steel; 311. Fifth connection part; 312. Sixth connection part; 32. Auxiliary material assembly; 33. Connecting plate;
[0045] 4. first connecting member; 41. first steel plate; 42. second steel plate; 43. third steel plate; 44. first stiffening plate;
[0046] 5. second connecting member; 51. fourth steel plate; 52. fifth steel plate;
[0047] 6. The third connecting member; 61. The sixth steel plate; 62. The seventh steel plate; 63. The eighth steel plate; 64. The second stiffening plate;
[0048] 7. Auxiliary plate; 8. Bolts. DETAILED DESCRIPTION
[0049] The specific implementation of the present invention is further described in detail below in conjunction with the accompanying drawings and examples. The following examples are used to illustrate the present invention, but are not intended to limit the scope of the present invention.
[0050] In the description of the present invention, it should be understood that the terms "upper", "lower", "left", "right", "front", "back", "top", "bottom", etc. indicate positions or positional relationships based on the positions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention. It should be understood that the terms "first", "second", etc. are used in the present invention to describe various information, but such information should not be limited to these terms, which are only used to distinguish the same type of information from each other. For example, without departing from the scope of the present invention, "first" information may also be referred to as "second" information, and similarly, "second" information may also be referred to as "first" information.
[0051] First, as Figure 1-Figure 7 As shown, the embodiment of the present application proposes a straight angle steel tower, which is used to be installed at the base position of the old tower and replace the old tower, including: a tower leg 11, which is used to be set between two adjacent tower legs of the old tower, and is provided with four in total; an iron tower main material 12, which is matched with the tower leg 11 and connected to the upper end of the new tower leg 11, and a plurality of iron tower main materials 12 extend upward to form a tower body 1; thereby, the new tower body 1 is staggered relative to the old tower (the new tower leg 11 is staggered with the tower leg of the old tower, so that the new tower body 1 is horizontally rotated a certain angle relative to the old tower); a cross arm 2, which is provided with one or more and is arranged along the extension direction of the new tower body 1, and the cross arm 2 includes a lower chord rod assembly and the lower chord rod assembly has two first connection nodes which are arranged diagonally opposite to each other, and are staggered with the two first connection nodes and are also diagonally opposite to each other. Two second connection nodes are set, and the two first connection nodes are respectively connected to a group of two iron tower main materials 12 set diagonally to each other, and the two second connection nodes are respectively connected to another group of two iron tower main materials 12 set diagonally to each other; it also includes an upper chord rod assembly connected to the lower chord rod assembly, and the upper chord rod assembly has two third connection nodes set diagonally to each other, and the two third connection nodes are respectively connected to a group of two iron tower main materials 12 set diagonally to each other; through the two first connection nodes, the two second connection nodes, the two third connection nodes and the corresponding iron tower main materials 12, the cross arm 2 is fixedly installed on the new tower body 1, and a reliable connection between the cross arm 2 and the new tower body 1 is achieved; and a ground wire bracket 13 is set at the top of the new tower body 1.
[0052] In the specific implementation of this embodiment, the construction personnel first build a new tower leg 11 in the gap between two adjacent tower legs of the original old tower, and after all the new tower legs 11 are installed, the original old tower is dismantled (the power transmission line needs to be shut down before the old tower is dismantled) so as to continue to install the iron tower main material 12 on the new tower leg 11. After the installation of the iron tower main material 12 is completed, a new tower body 1 is formed (the new tower body 1 is staggered with the original old tower), and then an appropriate number of cross arms 2 are installed on the new tower body 1, and the two first connection nodes are connected correspondingly. On the main tower materials 12 arranged diagonally opposite to each other, the two second connection nodes are correspondingly connected to the main tower materials 12 arranged diagonally opposite to each other, and the two third connection nodes are correspondingly connected to the main tower materials 12 arranged diagonally opposite to each other, thereby realizing a reliable connection between the crossarm 2 and the new tower body 1; this embodiment realizes the construction of a new tower in the original location of the old tower without occupying additional new soil area, thereby effectively reducing green compensation matters; and since the power outage of the transmission line is carried out only after the installation of the new tower leg 11 is completed, the power outage duration of the transmission line is effectively shortened.
[0053] In some embodiments of the present application, in some embodiments of the present application, the lower chord rod assembly includes a first lower chord angle steel 21 connected to one of the first connection nodes and symmetrically arranged with each other, a second lower chord angle steel 22 connected to the other first connection node and symmetrically arranged with each other, the other ends of the first lower chord angle steel 21 and the second lower chord angle steel 22 on the same side are connected through an auxiliary part 23; it also includes a lower chord diagonal material 24 connected between the first lower chord angle steel 21 and the second lower chord angle steel 22 on the same side and connected to the second connection node, and there are multiple lower chord diagonal materials 24.
[0054] The two first lower chord angle steels 21 are connected and fixed to the tower main material 12 via one of the first connection nodes, and the two second lower chord angle steels 22 are connected and fixed to the tower main material 12 via another first connection node. At the same time, a plurality of lower chord diagonal materials 24 are arranged between the first lower chord angle steels 21 and the second lower chord angle steels 22 on the same side to increase the structural strength of the lower chord rod assembly; wherein the lower chord diagonal material 24 close to the new tower body 1 is fixedly connected to the second connection node and is connected and fixed to the tower main material 12 via the second connection node.
[0055] In some embodiments of the present application, the first connection node includes first connection members 4 that are symmetrically arranged and connected to the main tower material 12. The first connection member 4 includes a first steel plate 41 horizontally connected to the outer wall of the main tower material 12, and a second steel plate 42 that is perpendicular to the first steel plate 41 and arranged along the length extension direction of the first lower chord angle steel 21 or the second lower chord angle steel 22. The first steel plate 41 and the second steel plate 42 are fixedly connected by welding.
[0056] The first lower chord angle steel 21 and the second lower chord angle steel 22 both have a horizontal first connection portion 211 and a second connection portion 212 vertically connected to the first connection portion 211; the first connection portion 211 is fitted with the corresponding second steel plate 42 and fixedly connected by bolts 8, and the second connection portion 212 is fitted with the corresponding first steel plate 41 and fixedly connected by bolts 8.
[0057] In some embodiments of the present application, a first stiffening plate 44 is provided on the outer side walls of the two matching first steel plates 41. The first stiffening plate 44 at least covers a portion of the outer side walls of the two first steel plates 41. The first stiffening plate 44 and the outer side walls of the two first steel plates 41 are fixedly connected by welding. The provision of the first stiffening plate 44 connects the two first steel plates 41 together, effectively improving the structural strength and stability of the first connection node.
[0058] In some embodiments of the present application, the second connection node includes second connecting members 5 that are symmetrically arranged and connected to the main tower material 12. The second connecting member 5 includes a fourth steel plate 51 horizontally connected to the outer wall of the main tower material 12. The lower chord diagonal material 24 near the second connection node is fixedly connected to the fourth steel plate 51 by bolts 8.
[0059] In some embodiments of the present application, the upper chord rod assembly includes a first upper chord angle steel 25 connected to one of the third connection nodes and symmetrically arranged with each other, and a second upper chord angle steel 26 connected to another third connection node and symmetrically arranged with each other; it also includes an upper chord diagonal material 27 arranged between the first upper chord angle steel 25 and the second upper chord angle steel 26 on the same side, and a plurality of upper chord diagonal materials 27 are provided, which are staggered and connected between the first upper chord angle steel 25 and the second upper chord angle steel 26 on the same side, and the upper chord diagonal material 27 close to the third connection node is fixedly connected to the third connection node.
[0060] In some embodiments of the present application, the third connection node includes third connecting members 6 that are symmetrically arranged and connected to the tower main material 12. The third connecting member 6 includes a sixth steel plate 61 horizontally connected to the outer wall of the tower main material 12, a seventh steel plate 62 perpendicular to the sixth steel plate 61 and arranged along the length extension direction of the first upper chord angle steel 25 or the second upper chord angle steel 26, and an eighth steel plate 63 perpendicular to the sixth steel plate 61 and fittedly connected to the outer wall of the tower main material 12. The sixth steel plate 61, the seventh steel plate 62, and the eighth steel plate 63 are fixedly connected by welding to form an integral structure, and the eighth steel plate 63 is fixedly connected to the outer wall of the tower main material 12 by welding.
[0061] The first upper chord angle steel 25 and the second upper chord angle steel 26 both have a horizontal third connection portion 251 and a fourth connection portion 252 vertically connected to the third connection portion 251; the third connection portion 251 is fitted with the corresponding sixth steel plate 61 and fixedly connected by bolts 8, the fourth connection portion 252 is fitted with the corresponding seventh steel plate 62 and fixedly connected by bolts 8, and the upper chord diagonal material 27 near the third connection node and the corresponding sixth steel plate 61 are fixedly connected by bolts 8.
[0062] In some embodiments of the present application, a second stiffening plate 64 is provided on the outer side walls of the two matching seventh steel plates 62, and the second stiffening plate 64 at least covers a portion of the outer side walls of the two seventh steel plates 62. The second stiffening plate 64 and the outer side walls of the two seventh steel plates 62 are fixedly connected by welding. The provision of the second stiffening plate 64 connects the two seventh steel plates 62 together, effectively improving the structural strength and stability of the third connection node.
[0063] In some embodiments of the present application, a reinforcing angle steel 31 is further included, which is arranged between the adjacent first connecting members 4 and the second connecting members 5; a fifth steel plate 52 is vertically connected to the fourth steel plate 51 and is arranged along the extension direction of the reinforcing angle steel 31 and is fitted and connected to the outer wall of the tower main material 12; the fifth steel plate 52 is fixedly connected to the outer wall of the tower main material 12 by welding, and the fifth steel plate 52 and the fourth steel plate 51 are welded together (forming an integral structure); a third steel plate 43 is vertically connected to the first steel plate 41 and is arranged along the extension direction of the reinforcing angle steel 31; the third steel plate 43 is fixedly connected to the outer wall of the tower main material 12 by welding, and the third steel plate 43 is fixedly connected to the first steel plate 41 by welding, so that the first steel plate 41, the second steel plate 42, and the third steel plate 43 are connected and fixed to each other to form an integral structure.
[0064] The reinforcing angle steel 31 has a horizontal fifth connection part 311 and a sixth connection part 312 vertically connected to the fifth connection part 311. The sixth connection part 312 near the first connection node is fitted with the third steel plate 43 and fixedly connected by bolts 8, and the sixth connection part 312 near the second connection node is fitted with the fifth steel plate 52 and fixedly connected by bolts 8; auxiliary material assemblies 32 are connected between multiple reinforcing angle steels 31 and form reinforcing members 3 with the auxiliary material assemblies 32. The setting of the reinforcing members 3 improves the structural strength of the connection between the main material 12 of the iron tower and the crossarm 2, so that when the crossarm 2 is subjected to the load force from the transmission line and transmitted to the new tower body 1, it can be evenly transmitted to the new tower body 1 through several reinforcing angle steels 31 and auxiliary material assemblies 32 connected to the main material 12 of the iron tower, so that the force on the new tower body 1 is more balanced, and the connection between the main material 12 of the iron tower and the crossarm 2 is more firm and more stable.
[0065] In some embodiments of the present application, a connecting plate 33 is provided at one end of two adjacent reinforcing angle steels 31, and the fifth connecting portion 311 is fitted with the corresponding connecting plate 33 and fixedly connected via bolts 8. The setting of the connecting plate 33 enables the multiple reinforcing angle steels 31 to be connected as a whole, further improving the stability of the overall structure of the reinforcing member 3 and the connection strength. Figure 2 As shown, an auxiliary plate 7 can be horizontally welded on the fifth connection portion 311 of the reinforcing angle steel 31 and the auxiliary plate 7 can be attached to the bottom wall of the first steel plate 41. The auxiliary plate 7 and the first steel plate 41 are fixedly connected together by bolts 8, thereby effectively improving the connection strength between the reinforcing angle steel 31 and the first connection node.
[0066] In some embodiments of the present application, the new tower leg 11 can be arranged in the middle position between two adjacent tower legs of the old tower, where there is a larger operating and construction space, so that construction workers can better install the new tower leg 11 between the two old tower legs. After the construction of the new tower body 1 is completed, the new tower body 1 is rotated 45° horizontally relative to the old tower.
[0067] In some embodiments of the present application, the main materials 12 of the iron tower are all made of materials of the same specifications, but the main materials 12 of the iron tower connected to the first connection node are subjected to a larger load force from the crossarm 2, and the main materials 12 of the iron tower connected to the second connection node are subjected to a smaller load force from the crossarm 2. Under the premise of ensuring the safety of the structure, the thickness of the main materials 12 of the iron tower connected to the first connection node is thicker, and the thickness of the main materials 12 of the iron tower connected to the second connection node is thinner, taking into account both safety and economy.
[0068] In the second aspect, an embodiment of the present application provides a tower erection method using the straight angle steel tower in the above-mentioned embodiment, comprising: firstly, setting a new tower leg 11 between two adjacent tower legs of the old tower, and after completing the installation of the new tower leg 11, dismantling the old tower; then connecting the iron tower main material 12 to the upper end of the new tower leg 11, and a plurality of iron tower main materials 12 extend upward to form a new tower body 1; arranging one or more lower chord rod assemblies along the extension direction of the new tower body 11, and connecting the upper chord rod assembly to the lower chord rod assembly to form a cross arm 2; the lower chord rod assembly has two first connection nodes arranged diagonally opposite to each other, and two second connection nodes staggered from the two first connection nodes and arranged diagonally opposite to each other, and the first connection node and the second connection node are correspondingly connected to the iron tower main material 12; the upper chord rod assembly has two third connection nodes arranged diagonally opposite to each other, and the third connection node is correspondingly connected to the iron tower main material 12; a ground wire bracket 13 is connected to the top of the new tower body 1.
[0069] In some embodiments of the present application, the new tower leg 11 is arranged in the middle of two adjacent tower legs of the old tower, which can provide a larger operating space and is more conducive to the installation of the new tower leg 11 by construction workers.
[0070] The working process of the present invention is as follows: first, a new tower leg 11 is constructed between two adjacent tower legs of the old tower. After the construction of the new tower leg 11 is completed, the power transmission line is shut down and the old tower is dismantled. Subsequently, an iron tower main material 12 is connected to the new tower leg 11 to form a new tower body 1. One or more cross arms 2 are arranged on the new tower body 1, and the cross arms 2 are connected to the diagonally arranged iron tower main material 12 via a first connection node, a second connection node, and a third connection node, thereby completing the construction of the new tower body 1.
[0071] In summary, the embodiment of the present invention provides a straight angle steel tower and a tower erection method thereof. The present application installs a new tower leg 11 between two adjacent tower legs of the original old tower. After the installation of the new tower leg 11 is completed, the old tower is dismantled, and the construction of the new iron tower is continued, so that the new tower body 1 and the old tower body are staggered (the foundation of the original old tower is staggered), and the tower is erected at the original tower position, which makes full use of the foundation of the original old tower and does not require additional occupation of new land area (reducing new compensation items), effectively shortening the power outage duration of the transmission line; the cross arm 2 is connected to the iron tower main material 12 through a diagonally arranged connection node, ensuring the stability of the connection between the cross arm 2 and the iron tower main material 12; at the same time, according to the stress condition of the tower body, the thickness of the iron tower main material 12 at a position with greater stress is set to be larger, and the thickness of the iron tower main material 12 at a position with less stress is set to be smaller, so as to ensure both economic efficiency and structural safety.
[0072] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and substitutions can be made without departing from the technical principles of the present invention. These improvements and substitutions should also be regarded as the scope of protection of the present invention.
Claims
1. A straight angle steel tower, characterized in that: include: Tower legs; An iron tower main material is matched with the tower legs and connected to the upper ends of the tower legs, and a plurality of the iron tower main materials are staggered and extend upward to form a tower body; A cross arm is provided with one or more cross arms, and the plurality of cross arms are arranged at intervals along the extension direction of the tower body, the cross arm comprises a lower chord assembly and an upper chord assembly connected to the upper end of the lower chord assembly, the lower chord assembly has two first connection nodes arranged diagonally to each other, and two second connection nodes staggered from the two first connection nodes and arranged diagonally to each other, the first connection node and the second connection node are both correspondingly connected to the main material of the iron tower; the upper chord assembly has two third connection nodes arranged diagonally to each other, and the third connection node is correspondingly connected to the main material of the iron tower; as well as The ground wire bracket is arranged at the top of the tower body.
2. The straight angle steel tower according to claim 1, characterized in that: The lower chord rod assembly includes two first lower chord angle steels connected to one of the first connection nodes and symmetrically arranged with each other, and two second lower chord angle steels connected to the other first connection node and symmetrically arranged with each other, and the other ends of the first lower chord angle steels and the second lower chord angle steels on the same side are connected via an auxiliary component; It also includes a lower chord diagonal material connected between the first lower chord angle steel and the second lower chord angle steel on the same side and connected to the second connection node.
3. The straight angle steel tower according to claim 2, characterized in that: The first connection node includes first connection members that are symmetrically arranged and connected to the main material of the iron tower, the first connection member includes a first steel plate horizontally connected to the outer side wall of the main material of the iron tower, and a second steel plate perpendicular to the first steel plate and arranged along the length extension direction of the first lower chord angle steel or the second lower chord angle steel, and the first steel plate and the second steel plate are connected and fixed to each other; The first lower chord angle steel and the second lower chord angle steel both have a horizontal first connection portion and a second connection portion vertically connected to one side of the first connection portion; the first connection portion is fitted and connected to the corresponding second steel plate, and the second connection portion is fitted and connected to the corresponding first steel plate.
4. The straight angle steel tower according to claim 3, characterized in that: The outer side walls of the two matching first steel plates are provided with first stiffening plates, which at least cover a portion of the outer side walls of each of the first steel plates and are fixedly connected to each of the first steel plates.
5. The straight angle steel tower according to claim 3, characterized in that: The second connection node includes second connection members which are symmetrically arranged and connected to the main material of the iron tower. The second connection member includes a fourth steel plate horizontally connected to the outer side wall of the main material of the iron tower, and the lower chord diagonal material is connected to the fourth steel plate.
6. The straight angle steel tower according to claim 1, characterized in that: The upper chord rod assembly includes a first upper chord angle steel connected to one of the third connection nodes and symmetrically arranged with each other, and a second upper chord angle steel connected to the other third connection node and symmetrically arranged with each other; and also includes an upper chord diagonal material arranged between the first upper chord angle steel and the second upper chord angle steel on the same side and connected to the third connection node.
7. The straight angle steel tower according to claim 6, characterized in that: The third connection node includes third connection members that are symmetrically arranged and connected to the main material of the iron tower, and the third connection members include a sixth steel plate horizontally connected to the outer wall of the main material of the iron tower, a seventh steel plate perpendicular to the sixth steel plate and arranged along the length extension direction of the first upper chord angle steel or the second upper chord angle steel, and an eighth steel plate perpendicular to the sixth steel plate and connected to the outer wall of the main material of the iron tower; the seventh steel plate and the eighth steel plate are both connected and fixed to the sixth steel plate; The first upper chord angle steel and the second upper chord angle steel both have a horizontal third connection portion and a fourth connection portion vertically connected to one side of the third connection portion; the third connection portion is fit-connected to the corresponding sixth steel plate, the fourth connection portion is fit-connected to the corresponding seventh steel plate, and the upper chord diagonal material is connected to the sixth steel plate.
8. The straight angle steel tower according to claim 7, characterized in that: The outer side walls of the two matching seventh steel plates are provided with a second stiffening plate, and the second stiffening plate at least covers a portion of the outer side walls of each of the seventh steel plates and is fixedly connected to each of the seventh steel plates.
9. The straight angle steel tower according to claim 5, characterized in that: It also includes a reinforcing angle steel disposed between the adjacent first connecting member and the second connecting member, the fourth steel plate is vertically connected to a fifth steel plate arranged along the extension direction of the reinforcing angle steel and connected to the outer side wall of the main material of the iron tower; the first steel plate is vertically connected to a third steel plate arranged along the extension direction of the reinforcing angle steel and connected to the outer side wall of the main material of the iron tower; The reinforcing angle steel has a horizontal fifth connection portion and a sixth connection portion vertically connected to one side of the fifth connection portion, the sixth connection portion close to the first connection node is fitted and connected to the third steel plate, and the sixth connection portion close to the second connection node is fitted and connected to the fifth steel plate; Auxiliary material components are connected between the plurality of reinforcing angle steels and form reinforcing members together with the auxiliary material components.
10. The straight angle steel tower according to claim 9, characterized in that: A connecting plate is horizontally provided at one end of two adjacent reinforcing angle steels, and two sides of the connecting plate are fitted and connected to the fifth connecting portion.
11. The straight angle steel tower according to any one of claims 1 to 10, characterized in that: The thickness of the main material of the iron tower connected to the first connection node is greater than the thickness of the main material of the iron tower connected to the second connection node.
12. A method for erecting a straight angle steel tower according to any one of claims 1 to 11, characterized in that: The following steps are involved: Installing the tower legs of the straight angle steel tower between two adjacent tower legs of the old tower; The old tower will be demolished; An iron tower main material is connected to the upper end of the tower leg of the straight angle steel tower, and a plurality of the iron tower main materials extend upward to form the tower body of the straight angle steel tower; Arrange one or more lower chord rod assemblies along the extension direction of the new tower body, wherein the lower chord rod assemblies are connected to the main material of the iron tower through the first connection node and the second connection node; An upper chord assembly is connected to the upper end of the lower chord assembly, and the upper chord assembly and the lower chord assembly are connected to form a cross arm, wherein the upper chord assembly is connected to the main material of the iron tower through the third connection node; A ground wire bracket is connected to the top of the tower body of the straight angle steel tower.
13. The tower erection method according to claim 12, characterized in that: When installing the tower leg of the straight angle steel tower, the tower leg of the straight angle steel tower is arranged at the middle position between two adjacent tower legs of the old tower.