Switch configuration method and device, power supply and distribution system, electronic equipment and storage medium

By configuring the set protection parameters of the target switch, combining the maximum expected short-circuit current and distance relationship, backup protection and selective coordination are achieved, which solves the power supply stability and continuity of the power supply and distribution system in the event of a fault, and improves the safety of the system Sex and stability.

CN119050967APending Publication Date: 2024-11-29SHANGHAI ZHENGFAN TECH +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411165980.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-23
Publication Date
2024-11-29

AI Technical Summary

Technical Problem

In the event of a fault in the existing power supply and distribution system, the unreasonable switch configuration will affect the power supply stability and continuity, and there may be problems such as widening the power outage range, lagging operation or misjudgment.

Method used

By determining the maximum expected short-circuit current at the target switch installation point and the distance between the switch, the set protection parameters of the target switch are configured to achieve backup protection and selective coordination, ensuring that the switch can operate accurately in the event of a fault and reducing the power outage range. Improve the stability of the power supply and distribution system.

Benefits of technology

It improves the power supply safety and continuity of the power supply and distribution system, reduces the power outage range, and enhances the accuracy of switch operations and the stability of the system.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119050967A_ABST
    Figure CN119050967A_ABST
Patent Text Reader

Abstract

The invention provides a switch configuration method and device, a power supply and distribution system, electronic equipment and a storage medium. The method comprises the steps that the maximum expected short-circuit current of total power input of a target switch mounting point is determined; determining set protection parameters of the target switch according to the distance relation between the target switch and the corresponding upper-level switch or the lower-level switch; determining the switch meeting the maximum expected short-circuit current and the set protection parameters as a target switch; the maximum expected short circuit current is configured to enable the target switch to achieve backup protection, and the set protection parameter is configured to enable the target switch to meet selective cooperation. When the switches in the power supply and distribution system are set, the switch meeting the corresponding condition is selected as the target switch according to the distance relation between the maximum expected short-circuit current of the target switch mounting point and the switches, so that the configured target switch can realize backup protection and selective matching; and the power supply safety and continuity of the power supply and distribution system are improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of power supply and distribution, and specifically, to a switch configuration method, device, power supply and distribution system, electronic equipment and storage medium. Background Art

[0002] In power supply and distribution systems, the main function of switches is to control and protect circuits. They can quickly disconnect circuits when faults occur, preventing the fault from spreading to a wider area, thereby protecting grid equipment and ensuring personnel safety.

[0003] However, if the switch configuration is unreasonable, when a system failure occurs, it will often directly affect the stability and continuity of power supply in the power distribution system. Summary of the invention

[0004] In view of this, an object of the embodiments of the present application is to provide a switch configuration method, device, power supply and distribution system, electronic device and storage medium, which can improve the power supply safety and continuity of the power supply and distribution system.

[0005] In a first aspect, an embodiment of the present application provides a switch configuration method, including: determining a maximum expected short-circuit current of a total incoming power at a target switch installation point; determining set protection parameters of the target switch based on a distance relationship between the target switch and a corresponding upper switch or lower switch; determining a switch that meets the maximum expected short-circuit current and the set protection parameters as the target switch; wherein the maximum expected short-circuit current is configured to enable the target switch to achieve backup protection, and the set protection parameters are configured to enable the target switch to meet selective coordination.

[0006] In the above implementation process, when setting the switch in the power supply and distribution system, the switch that meets the corresponding conditions is selected as the target switch based on the maximum expected short-circuit current of the target switch installation point and the distance relationship between the switches, so that the configured target switch can achieve backup protection and selective coordination, thereby improving the power supply safety and continuity of the power supply and distribution system.

[0007] In one embodiment, determining the set protection parameters of the target switch based on the distance relationship between the target switch and the corresponding upper switch or lower switch includes: determining that the target switch needs to meet the full selectivity requirement when the distance relationship between the target switch and the corresponding upper switch or lower switch is greater than a distance threshold; and determining the set protection parameters for the target switch to meet the full selectivity requirement.

[0008] In the above implementation process, when it is determined that the distance relationship between the target switch and the corresponding upper switch or lower switch is greater than the distance threshold, it is determined that the target switch meets the full selectivity requirements, so that the target switch can meet as many different selectivities as possible, improve the accuracy of the target switch action, and reduce the power outage scope and improve the power supply and distribution stability when a fault occurs in the system.

[0009] In one embodiment, the full selectivity requirement includes: current selectivity; the set protection parameters include: a first target current parameter; the determination of the set protection parameters that the target switch meets the full selectivity requirement includes: determining a first coefficient corresponding to the target switch according to the switch type of the target switch; determining a first target current parameter of the target switch according to the relationship between the first coefficient and a first set current; the first set current relationship is a current relationship between the upper switch and the lower switch; wherein the first target current parameter is configured so that the maximum action characteristic curve of the lower switch is below the minimum action characteristic curve of the upper switch.

[0010] In the above implementation process, the currents of the upper switch and the lower switch are set to satisfy the first set current relationship so that the maximum action characteristic curve of the lower switch is located below the minimum action characteristic curve of the upper switch, thereby achieving that the action current of the upper switch is greater than the action current of the lower switch, and the switch closest to the fault point is controlled to act first, thereby reducing the scope of power outages and improving the stability of power supply and distribution.

[0011] In one embodiment, the full selectivity requirement includes: time selectivity; the set protection parameters include: one or more of set action delay time, short-circuit current and instantaneous maximum set value; the determination of the set protection parameters that the target switch meets the full selectivity requirement includes: when the target switch is a first type switch, turning off the instantaneous protection of the target switch and setting the set action delay time; when the target switch is a second type switch, setting the short-circuit current of the lower switch to be less than the instantaneous maximum set value of the upper switch.

[0012] In the above implementation process, when setting the time selectivity of the target switch, the corresponding time selectivity coordination strategy is used to determine the corresponding set protection parameters of the target switch according to the switch type to which the target switch belongs, so as to improve the accuracy of the target switch action, reduce the power outage scope and improve the power supply and distribution stability when a fault occurs in the system.

[0013] In one embodiment, the full selectivity requirement includes: energy selectivity; the set protection parameters include: a second target current parameter; the determination of the set protection parameters that the target switch meets the full selectivity requirement includes: determining a second coefficient corresponding to the target switch; determining the second target current parameter of the target switch based on the relationship between the second coefficient and the second set current; wherein the second set current relationship is the rated current extreme difference relationship between the upper switch and the lower switch; wherein the second target current parameter is configured to make the current of the instantaneous action of the upper switch greater than or equal to the energy tripping of the lower switch.

[0014] In the above implementation process, the rated current extreme difference relationship between the upper switch and the lower switch is set to meet the second set current relationship, so that the lower switch can realize energy selection between the upper and lower switches, and then control the switch closest to the fault point to act first, reduce the scope of power outage, and improve the stability of power supply and distribution.

[0015] In one embodiment, determining the set protection parameters of the target switch according to the distance relationship between the target switch and the corresponding upper switch or lower switch includes: determining that the target switch needs to meet a local selectivity requirement when the distance relationship between the target switch and the corresponding upper switch or lower switch is less than or equal to a distance threshold; determining the set protection parameters of the target switch that meet the local selectivity requirement; wherein the local selectivity includes one or more of time selectivity and current selectivity.

[0016] In the above implementation process, when it is determined that the distance relationship between the target switch and the corresponding upper switch or lower switch is less than or equal to the distance threshold, it is determined that the target switch meets the local selectivity requirements, and then the target switch meets the partial selectivity, so as to improve the accuracy of the target switch action as much as possible. When a fault occurs in the system, the power outage scope is reduced as much as possible to improve the stability of power supply and distribution.

[0017] In the second aspect, an embodiment of the present application also provides a power supply and distribution system, comprising: a multi-level distribution box; wherein each level of the distribution box includes one or more switches, and the switch is configured by the switch configuration method described in the above-mentioned first aspect, or any possible implementation method of the first aspect; the busbars of two adjacent levels of the distribution box are connected by multiple cables.

[0018] In a third aspect, an embodiment of the present application further provides a switch configuration device, comprising: a first determination module, used to determine the maximum expected short-circuit current of the total power incoming to the target switch installation point; a second determination module, used to determine the set protection parameters of the target switch based on the distance relationship between the target switch and the corresponding upper switch or lower switch; a third determination module, used to determine that the switch that meets the maximum expected short-circuit current and the set protection parameters is the target switch; wherein the maximum expected short-circuit current is configured to enable the target switch to achieve backup protection, and the set protection parameters are configured to enable the target switch to meet selective coordination.

[0019] In a fourth aspect, an embodiment of the present application further provides an electronic device, comprising: a processor and a memory, wherein the memory stores machine-readable instructions executable by the processor, and when the electronic device is running, the machine-readable instructions are executed by the processor to perform the steps of the method in the above-mentioned first aspect, or any possible implementation of the first aspect.

[0020] In a fifth aspect, an embodiment of the present application further provides a computer-readable storage medium, on which a computer program is stored. When the computer program is executed by a processor, the steps of the switch configuration method in the above-mentioned first aspect, or any possible implementation of the first aspect are executed.

[0021] In order to make the above-mentioned objects, features and advantages of the present application more obvious and understandable, embodiments are given below and described in detail with reference to the attached drawings. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] In order to more clearly illustrate the technical solutions of the embodiments of the present application, the drawings required for use in the embodiments will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present application and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without paying creative work.

[0023] Figure 1 A schematic diagram of the system structure of a power supply and distribution system provided in an embodiment of the present application;

[0024] Figure 2 A block diagram of an electronic device provided in an embodiment of the present application;

[0025] Figure 3 A flow chart of a switch configuration method provided in an embodiment of the present application;

[0026] Figure 4 A schematic diagram of a time-current characteristic curve corresponding to the current selectivity provided in an embodiment of the present application;

[0027] Figure 5 A schematic diagram of a time-current characteristic curve corresponding to the time selectivity provided in an embodiment of the present application;

[0028] Figure 6 A schematic diagram of a time-current characteristic curve corresponding to the energy selectivity provided in an embodiment of the present application;

[0029] Figure 7 The upper and lower switches provided for the embodiment of the present application are: a schematic diagram of the time-current characteristics of a circuit breaker of NSX400H-Mic5.3A-400 and NSX100H-Mic2.2-100 connected in series;

[0030] Figure 8 A schematic diagram of the functional modules of the switch configuration device provided in an embodiment of the present application. DETAILED DESCRIPTION

[0031] The technical solutions in the embodiments of the present application will be described below in conjunction with the accompanying drawings in the embodiments of the present application.

[0032] It should be noted that similar reference numerals and letters represent similar items in the following drawings, so once an item is defined in one drawing, it does not need to be further defined and explained in subsequent drawings. At the same time, in the description of this application, the terms "first", "second", etc. are only used to distinguish the description and cannot be understood as indicating or implying relative importance.

[0033] The reliability of power supply and distribution system is measured from the aspects of safety and continuity. As the core component of power supply and distribution system, the coordination between switches should be measured from the aspects of backup protection and selectivity. Backup protection focuses on safety during coordination, while selectivity focuses more on continuity during coordination. The two complement each other to jointly guarantee the reliability of power supply and distribution system. Backup protection is that the upper switch helps the lower switch to improve its rated short-circuit breaking capacity and helps the lower switch to break the fault current that exceeds its rated short-circuit breaking capacity. Selectivity means that the overcurrent should be cut off by the circuit breaker on the upstream power supply side to avoid overstepping and expand the scope of power supply interruption.

[0034] Among them, the switch of two-stage protection can achieve time selectivity when the latter is closed within the maximum settable range of the upper instantaneous action. If the upper instantaneous protection is set high, the level of selectivity between the upper and lower levels can be appropriately improved, but there may be a risk of insufficient sensitivity to small current faults. The short-delay protection of the three-stage protection switch can effectively solve the contradiction between selectivity and sensitivity. In addition, for switches used for impact load and loop protection, the short-circuit short delay can not only avoid normal impact current, but also improve the sensitivity of ground fault and short-circuit protection.

[0035] High reliability is the core requirement of the power supply and distribution system. As a key indicator of the power supply and distribution system, reliability is usually evaluated from two aspects. One is the safety of the power supply and distribution system, and the other is the continuity of the power supply and distribution system. As an important device in the power supply and distribution system, the switch connects the rated current, carries the rated current and disconnects the fault current under normal circumstances. When an overload current fault occurs in the power supply and distribution system, the switches should coordinate with each other to cut off and isolate the fault current, protect the electrical equipment in the power supply and distribution system, and ensure the power supply of the electrical system, so as to meet the safety and continuity requirements of the low-voltage distribution system to the greatest extent. However, when a fault occurs in the system, the current switches may have lags or misjudgments in detection, judgment and execution, resulting in improper power outages and affecting the power supply safety and continuity of the power supply and distribution system.

[0036] In view of this, the present application proposes a switch configuration method, device, power supply and distribution system, electronic device and storage medium. When setting the switch in the power supply and distribution system, the switch that meets the corresponding conditions is selected as the target switch based on the maximum expected short-circuit current of the target switch installation point and the distance relationship between the switches, so that the configured target switch can achieve backup protection and selective coordination, thereby improving the power supply safety and continuity of the power supply and distribution system.

[0037] To facilitate understanding of this embodiment, a power supply and distribution system disclosed in an embodiment of the present application is first introduced in detail.

[0038] like Figure 1 The figure is a schematic diagram of the system structure of the power supply and distribution system provided in an embodiment of the present application, including: a multi-level distribution box.

[0039] Each level of distribution box includes one or more switches ( Figure 1 QF in the figure), the busbars of two adjacent distribution boxes are connected by multiple cables.

[0040] Optionally, the switch may be a circuit breaker, an air switch, an isolating switch, etc. The switch may be selected according to actual conditions.

[0041] The switch here is configured by the switch configuration method in the embodiment of the present application. The switch configured by the switch configuration method in the embodiment of the present application satisfies one or more of backup protection and selective coordination.

[0042] Each level of the above-mentioned distribution box includes one or more power supply and distribution lines, and each power supply and distribution line may include an upper switch and / or a lower switch. Among them, the upper switch and the lower switch can be configured according to the switch configuration method in the embodiment of the present application.

[0043] It should be understood that by setting the upper switch and the lower switch according to the switch configuration method in the embodiment of the present application, when a fault occurs in a certain line, the switch on the power supply side closest to the fault point is preferentially controlled to operate, while the switch upstream of the power supply side that carries the flow at the fault point is kept as inoperative as possible, thereby reducing the scope of the power outage.

[0044] In one embodiment, when the power supply and distribution system includes multiple distribution boxes, the switch in the upper distribution box is an upper switch relative to the switch in the lower distribution box. That is, the switch in the upper distribution box and the switch in the lower distribution box can also be directly configured according to the switch configuration method in the embodiment of the present application. As a result, when the power supply and distribution system is viewed as a whole, when there is a storage fault in the connection circuit of the distribution boxes at each level, the switch in the distribution box closest to the fault point is preferentially controlled to operate, and the switch in the distribution box upstream of the power supply side that carries the fault point flow is kept as inactive as possible, thereby reducing the scope of the power outage.

[0045] The input end of the above-mentioned power supply and distribution system can be connected to a power supply device or a power supply system, and the output end of the power supply and distribution system can be connected to a load or a lower-level power distribution system. The power supply and distribution system can be connected to corresponding equipment or systems according to different application scenarios, and the connection method of the power supply and distribution system can be selected according to actual conditions.

[0046] In another embodiment, the power supply and distribution system further includes an electronic device, which is used to execute the switch configuration method in the embodiment of the present application.

[0047] To facilitate understanding of this embodiment, an electronic device that executes the switch configuration method disclosed in the embodiment of the present application is described in detail below.

[0048] like Figure 2 , which is a block diagram of an electronic device. The electronic device 100 may include a memory 111 and a processor 113. A person skilled in the art may understand that Figure 2 The structure shown is only for illustration and does not limit the structure of the electronic device 100. For example, the electronic device 100 may further include Figure 2 More or fewer components as shown, or with Figure 2 Different configurations shown.

[0049] The memory 111 and the processor 113 are directly or indirectly electrically connected to each other to achieve data transmission or interaction. For example, these elements can be electrically connected to each other via one or more communication buses or signal lines. The processor 113 is used to execute the executable module stored in the memory.

[0050] The memory 111 may be, but is not limited to, a random access memory (RAM), a read only memory (ROM), a programmable read-only memory (PROM), an erasable programmable read-only memory (EPROM), an electrically erasable read-only memory (EEPROM), etc. The memory 111 is used to store programs, and the processor 113 executes the program after receiving the execution instruction. The method executed by the electronic device 100 defined by the process disclosed in any embodiment of the present application can be applied to the processor 113, or implemented by the processor 113.

[0051] The processor 113 may be an integrated circuit chip with signal processing capability. The processor 113 may be a general-purpose processor, including a central processing unit (CPU), a network processor (NP), etc.; it may also be a digital signal processor (DSP), an application-specific integrated circuit (ASIC), a field programmable gate array (FPGA) or other programmable logic devices, discrete gates or transistor logic devices, discrete hardware components. The methods, steps and logic block diagrams disclosed in the embodiments of the present application may be implemented or executed. The general-purpose processor may be a microprocessor or the processor may also be any conventional processor, etc.

[0052] The electronic device 100 in this embodiment can be used to execute each step in each method provided in the embodiments of the present application. The implementation process of the switch configuration method is described in detail below through several embodiments.

[0053] See also Figure 3 , is a flow chart of the switch configuration method provided in the embodiment of the present application. Figure 3 The specific process shown is described in detail.

[0054] Step 201, determining the maximum expected short-circuit current of the total incoming power at the target switch installation point.

[0055] The target switch refers to the switch to be configured, and the target switch can be any switch in the power supply and distribution system in the embodiment of the present application. For example, the target switch can be an upper switch or a lower switch. The target switch can be selected according to actual conditions.

[0056] The target switch installation point here refers to the location point where the target switch is installed.

[0057] For example, Figure 1 Take the power supply and distribution system as an example. Figure 1 The figure shows that the upstream multi-switch sends power to the upper end of the switch of the secondary distribution box through multiple cables, and the maximum expected short-circuit current upstream is 50KA. That is, the maximum expected short-circuit current of the total incoming power at the target switch installation point is 50KA.

[0058] The above-mentioned maximum expected short-circuit current refers to the maximum value of the short-circuit current formed by the strong current provided by the power supply equipment when a short circuit fault occurs at a certain point or a certain line in the system under normal power supply conditions.

[0059] The maximum prospective short-circuit current here can be calculated using the corresponding short-circuit current calculation formula.

[0060] Step 202: Determine the set protection parameter of the target switch according to the distance relationship between the target switch and the corresponding upper switch or lower switch.

[0061] The distance relationship refers to the physical distance between the two switches.

[0062] Optionally, if the target switch is an upper switch, the distance relationship is the physical distance between the target switch and the corresponding lower switch. If the target switch is a lower switch, the distance relationship is the physical distance between the target switch and the corresponding upper switch. The distance relationship can be determined according to the actual installation position of the target switch.

[0063] It should be understood that when the distance between the target switch and the corresponding upper switch or lower switch is too close, the distribution characteristics of the short-circuit current may become complicated when it flows through the target switch and the corresponding upper switch or lower switch. In particular, in a low-voltage power distribution system, when a short circuit occurs at the outlet of the low-voltage bus distribution circuit breaker, the current flowing through the main power switch and the distribution switch of the fault circuit is almost the same. In this case, if the short-circuit current reaches the instantaneous action value of the upper and lower protection switches at the same time, the upper and lower switches may act at the same time, thereby losing selectivity.

[0064] When the upper and lower switches are separated by a certain distance, the distribution characteristics of the short-circuit current when flowing through the two switches will be different. Due to factors such as the resistance and inductance of the wire, the short-circuit current will attenuate during the propagation process as the distance increases. This means that the value of the short-circuit current at the lower switch, which is farther away, may be lower than the value at the upper switch. This difference provides the possibility of selective protection, allowing the upper switch to remain closed when the short-circuit current does not reach its action threshold, while the lower switch can respond faster and cut off the fault point circuit.

[0065] Therefore, the selective coordination requirement that the target switch needs to meet can be determined based on the distance relationship. Different selective coordination requirements may require different set protection parameters for the target switch.

[0066] Optionally, the set protection parameter may be a current parameter, a delay parameter, an energy parameter, etc. The set protection parameter may be selected according to actual conditions.

[0067] Step 203: determine a switch that meets the maximum expected short-circuit current and the set protection parameters as a target switch.

[0068] Among them, the maximum expected short-circuit current is configured to enable the target switch to achieve backup protection, and the set protection parameter is configured to enable the target switch to meet selective coordination.

[0069] The backup protection here refers to an overcurrent coordination between two overcurrent protection devices connected in series. The backup protection is that the expected maximum short-circuit current of the power supply and distribution system located downstream of the protection device exceeds the rated short-circuit breaking capacity of the protection device itself. The protection device located upstream of the protection device should have sufficient short-circuit breaking capacity, which can not only break the maximum expected short-circuit current between the upstream and downstream protection devices, but also help the downstream protection device to break the maximum expected short-circuit current higher than its rated short-circuit breaking capacity. The backup protection is a measure of the coordination between the upper and lower switches from the perspective of power supply safety. In the power supply and distribution system, when the rated short-circuit breaking capacity of a single switch is less than the expected short-circuit current at the installation point, the upper molded case circuit breaker (MCCB) or miniature circuit breaker (MCB) can be used to increase the short-circuit breaking capacity of the upper and lower switch combination to exceed the rated short-circuit breaking capacity of the lower switch itself, so as to meet the expected short-circuit current of the disconnecting installation point. Therefore, the backup protection helps the lower level to improve its short-circuit breaking capacity by limiting the current through the upper level breaking or limiting the current without breaking the upper level, so as to enable the lower level to cut off the expected short-circuit current that exceeds its rated breaking capacity and prevent the lower level switch from being damaged.

[0070] Selective coordination refers to the coordination of an action characteristic of two or more overcurrent protection devices. For example, one protection device implements overcurrent protection under the condition of overcurrent of the specified limit, while the other protection device does not operate. Selectivity is a measure of the coordination between the upper and lower switches from the perspective of power supply continuity. In the event of an overcurrent fault, only the switch on the power supply side closest to the fault point operates, while the switch upstream of the power supply side that carries the fault point flow remains inoperative. The upstream switch remains inoperative because the fault point flow has not reached the threshold of overcurrent action, or because the current has reached the threshold, but the duration of the fault has not reached the delay set for the upstream protection action. At this time, the overcurrent fault is quickly removed by the lower switch in a shorter time than the delay set by the upper switch.

[0071] The selective coordination here may include full selective coordination and partial selective coordination. The selective coordination may be determined according to actual conditions.

[0072] Among them, full selectivity refers to the overcurrent selective protection in which, when two overcurrent protection devices are connected in series, the protection device on the load side implements protection without causing the other protection device to operate. In the low-voltage power distribution system, full selectivity means that the selectivity limit current of the overcurrent selectivity is greater than or equal to the expected short-circuit current at the installation point of the lower switch, and only the lower switch operates while the upper switch remains closed.

[0073] Local selectivity is the overcurrent selective protection in which, in the case of two overcurrent protective devices connected in series, the protective device on the load side implements protection at a given overcurrent value or below without causing the other protective device to operate. In the low-voltage power distribution system, local selectivity means that the selective limit current of the overcurrent selectivity is less than the expected short-circuit current at the installation point of the lower switch. Below the selective polarity current, there is selectivity between the upper and lower switches. Above the selective limit current and below the expected short-circuit current, there is no selectivity between the upper and lower switches. The upper and lower switches will operate at the same time or the upper switch will operate while the lower switch will not.

[0074] Optionally, the switch selectivity is divided into current selectivity, time selectivity, energy selectivity, etc. Among them, full selectivity coordination can be achieved by current selectivity, time selectivity, energy selectivity, or a combination of current selectivity and time selectivity. Local selectivity can be achieved by current selectivity or time selectivity. The selectivity coordination can be determined according to the actual situation of the target switch.

[0075] The above-mentioned set protection parameters are protection parameters corresponding to the corresponding selective coordination that the target switch needs to meet. By selecting a switch that meets the set protection parameters, the target switch is controlled to meet the corresponding selective coordination.

[0076] It can be understood that when the limit breaking current of the switch is greater than or equal to the maximum expected short-circuit current, it can be determined that the switch meets the maximum expected short-circuit current. When the switch meets the maximum expected short-circuit current, the switch can achieve backup protection.

[0077] For example, if the maximum expected short-circuit current of the total incoming power at the target switch installation point is 50KA, and the rated limit breaking current of a certain switch is 50KA, it is determined that the switch meets the maximum expected short-circuit current.

[0078] If the maximum expected short-circuit current of the total power supply at the target switch installation point is 30KA, and the rated limit breaking current of a certain switch is 50KA, it is determined that the switch meets the maximum expected short-circuit current.

[0079] In the above implementation process, when setting the switch in the power supply and distribution system, the switch that meets the corresponding conditions is selected as the target switch based on the maximum expected short-circuit current of the target switch installation point and the distance relationship between the switches, so that the configured target switch can achieve backup protection and selective coordination, thereby improving the power supply safety and continuity of the power supply and distribution system.

[0080] In a possible implementation, step 202 includes: when the distance relationship between the target switch and the corresponding upper switch or lower switch is greater than a distance threshold, determining that the target switch needs to meet the full selectivity requirement; and determining the set protection parameters for the target switch to meet the full selectivity requirement.

[0081] The distance threshold refers to the distance limit value at which the upper switch and the lower switch cannot achieve energy selection. The distance threshold can be determined through multiple experiments or calculated using a corresponding distance threshold calculation formula. The method for determining the distance threshold can be selected according to actual conditions.

[0082] It should be understood that when the distance relationship between the target switch and the corresponding upper switch or lower switch is greater than the distance threshold, it means that the target switch and the corresponding upper switch or lower switch meet the time selectivity, current selectivity and energy selectivity.

[0083] Optionally, the full selectivity requirement includes one or more of time selectivity, current selectivity and energy selectivity. The selectivity requirement can be determined according to actual requirements of the power supply and distribution system.

[0084] The above-mentioned set protection parameters include: one or more of: a first target current parameter, a second target current parameter, a set action delay time, a short-circuit current and an instantaneous maximum set value. The set protection parameters can be adjusted according to the corresponding selective coordination.

[0085] In the above implementation process, when it is determined that the distance relationship between the target switch and the corresponding upper switch or lower switch is greater than the distance threshold, it is determined that the target switch meets the full selectivity requirements, so that the target switch can meet as many different selectivities as possible, improve the accuracy of the target switch action, and reduce the power outage scope and improve the power supply and distribution stability when a fault occurs in the system.

[0086] In a possible implementation, determining the set protection parameters of the target switch that meet the full selectivity requirement includes: determining a first coefficient corresponding to the target switch according to the switch type of the target switch; and determining a first target current parameter of the target switch according to the relationship between the first coefficient and the first set current.

[0087] It should be understood that overcurrent in the power supply and distribution system can only cause the lower switch in series to operate, while the upper switch does not operate. In this case, the coordination of the upper and lower switches should have current selectivity for the current in this range. Current selectivity is often used for coordination between switches when the difference between the upper and lower switches is large, so as to achieve overload protection for the power supply and distribution system. For example, Figure 4 As shown, Figure 4 The shaded area is the current selective region.

[0088] The switch types here can be divided according to the switch model, switch adjustability, switch material, etc. The switch type can be adjusted according to actual conditions.

[0089] The first set current relationship is the current relationship between the upper switch and the lower switch.

[0090] In one embodiment, the first set current relationship is: I 上级 >AI 下级 . Among them, A is the first coefficient, I 上级 is the current of the upper switch, and Ilower is the current of the lower switch.

[0091] The first target current parameter is configured so that the maximum operating characteristic curve of the lower switch is located below the minimum operating characteristic curve of the upper switch.

[0092] It should be understood that for the selective judgment of the overload area, taking into account the error of the switch overload protection action, the overload setting current (adjustable) or the rated current of the switch (non-adjustable) should satisfy that the maximum action characteristic curve of the lower switch is below the minimum action characteristic curve of the upper switch.

[0093] For example, if the target switch is an MCCB circuit breaker, the inverse time overcurrent disconnecting release should meet the tripping action characteristics at the reference temperature: the agreed non-tripping current is 1.05 times the setting current, the agreed tripping current is 1.3 times the setting current, and the agreed tripping time is 2 hours or 1 hour (1 hour when the rated current is less than or equal to 63A). Therefore, from the perspective of current, if 1.2Ir lower level < 1.05Ir upper level is met, that is, Ir upper level ≥ 1.2Ir lower level is met, the current selectivity in the overload area can be achieved.

[0094] If the target switch is a thermal-magnetic circuit breaker, taking into account that the time-current tripping band is slightly wider under high overload conditions than under low overload conditions, the ratio coefficient of the upper and lower overload protection currents should be appropriately adjusted to meet the requirement that Ir upper ≥ 1.6Ir lower to achieve selective coordination.

[0095] In the above implementation process, the currents of the upper switch and the lower switch are set to satisfy the first set current relationship so that the maximum action characteristic curve of the lower switch is located below the minimum action characteristic curve of the upper switch, thereby achieving that the action current of the upper switch is greater than the action current of the lower switch, and the switch closest to the fault point is controlled to act first, thereby reducing the scope of power outages and improving the stability of power supply and distribution.

[0096] In one possible implementation, determining the set protection parameters for the target switch to meet full selectivity requirements includes: when the target switch is a first type switch, turning off the instantaneous protection of the target switch and setting a set action delay time; when the target switch is a second type switch, setting the short-circuit current of the lower switch to be less than the instantaneous maximum setting value of the upper switch.

[0097] It should be understood that the current when the upper and lower switches are connected in series can cause the upper switch to trip or the lower switch to trip, but the upper switch tripping time is longer than the lower switch tripping time. When an overcurrent fault occurs, because the lower switch tripping time is faster than the upper switch, only the lower switch will act while the upper switch will remain stationary. Time selectivity is achieved through the time difference between the upper and lower switches. For example, Figure 5 As shown, Figure 5 The middle shaded area is the time-selective region.

[0098] The set action delay time here can be determined through multiple experiments, and can also be calculated through a set calculation formula. The set action delay time can be selected according to actual conditions.

[0099] It should be understood that the prerequisite for current selectivity to achieve full selectivity is that the maximum expected short-circuit current of the lower switch does not exceed the instantaneous protection setting of the upper switch. Once it exceeds the instantaneous setting of the upper switch, it will lose selectivity theoretically based on the time-current characteristic curve. At this time, time selectivity can be achieved by delaying the action of the upper switch by Δt in this short-circuit situation.

[0100] The first type of switch mentioned above may be a switch with an artificial short delay (adjustable) for selective protection in the event of a short circuit. That is, in the event of a short circuit, the circuit breaker explicitly provides selective protection for another short circuit protection device connected in series on the load side, that is, in the event of a short circuit, the circuit breaker explicitly provides selective protection for another short circuit protection device connected in series on the load side.

[0101] The second type of switch may be a switch that selectively protects without artificial short delay in case of short circuit, that is, in case of short circuit, the circuit breaker is not explicitly designated as a selective protection for another short circuit protection device connected in series on the load side.

[0102] For example, the first type of switch is often used for time selectivity due to its high short-time tolerance. Among them, the expected short-circuit current of the lower level in the primary and secondary power supply and distribution is often large, and in most cases it will exceed the maximum settable value of the upper switch instantaneous protection. At this time, the instantaneous protection of this type of switch can be turned off and a certain action delay time (i.e., setting the action delay time) can be set to achieve full selectivity with its high short-circuit tolerance.

[0103] For the second type of switch, its short-time tolerance capability is relatively low. When the short-circuit current is less than the maximum setting value of the upper instantaneous action, time selectivity can be achieved. The instantaneous action can also be turned off within the short-time tolerance range, which improves the selectivity level to a certain extent. Therefore, time selectivity is often used for selective coordination under short-circuit conditions between air circuit breakers and between air circuit breakers and molded case circuit breakers.

[0104] In one embodiment, the full selectivity requirement also includes time + current selectivity, that is, the selective coordination of switches in the power supply and distribution system can be achieved by combining current selectivity with time selectivity.

[0105] For switches with two-stage protection, that is, switches that have overload protection in addition to short circuit, through reasonable settings, the overcurrent before the overload protection of the upper switch is activated will be activated first by the lower-level overload protection or short-circuit protection.

[0106] The overcurrent before the upper short-circuit action can only trigger the upper overload protection action at most. Since the lower short-circuit protection will act first, the time selectivity is achieved through a certain time difference between the upper and lower protection actions. Even if the upper is a two-stage protection switch (i.e. overload + instantaneous action), the current selectivity is used for small currents and the time selectivity is used for large currents. As long as the maximum expected short-circuit current is less than the maximum settable value of the instantaneous action of the upper switch, the two-stage protection switch can achieve current and time selectivity by setting a higher upper instantaneous protection setting value.

[0107] For switches with three-stage protection (i.e. overload + short-circuit short delay + instantaneous), the three-stage protection is more superior in achieving time selectivity with the help of the short-circuit short delay function. Under short-circuit conditions, the three-stage protection switch does not need to set a higher instantaneous protection setting like the two-stage protection. The short-circuit short delay protection current can be set to a lower setting value to improve the short-circuit protection sensitivity and reduce the let-through energy. In this way, the sensitivity of short-circuit faults between the upper and lower levels, especially impedance short-circuit or arc-burning short-circuit faults, can be greatly improved, avoiding the risk of insufficient protection sensitivity for faults between the upper and lower levels due to too large instantaneous settings.

[0108] In the above implementation process, when setting the time selectivity of the target switch, the corresponding time selectivity coordination strategy is used to determine the corresponding set protection parameters of the target switch according to the switch type to which the target switch belongs, so as to improve the accuracy of the target switch action, reduce the power outage scope and improve the power supply and distribution stability when a fault occurs in the system.

[0109] In a possible implementation, determining the set protection parameters of the target switch that meet the full selectivity requirement includes: determining a second coefficient corresponding to the target switch; and determining a second target current parameter of the target switch according to a relationship between the second coefficient and a second set current.

[0110] It should be understood that after the short-circuit current exceeds the upper instantaneous protection, from the comparison of the time-current characteristic curve, the upper and lower switches may be tripped instantaneously at the same time, or the upper instantaneous action may be first activated and an over-tripping may occur. Energy tripping is a special tripping mode, independent of the normal overload, short-circuit short delay and instantaneous tripping protection of the switch, similar to the instantaneous protection with non-adjustable current. However, unlike conventional protection where the tripper is activated to drive the mechanism to trip, the energy tripping is directly driven by the circuit breaker disconnecting unit to drive the mechanism to trip.

[0111] For example, the conventional instantaneous tripping inherent delay is ≥10ms, the full segmentation time is ≤50ms, the current setting threshold is ≤15In, while the energy tripping threshold is 25In, the tripping current is higher than the instantaneous protection threshold, the breaking time is <10ms, and the current and time are not adjustable. Figure 6 As shown in Figure 6, the shaded area is the energy selective area. Figure 6It can be seen that in the low-voltage power distribution system, when the short-circuit current exceeds the upper instantaneous protection, judging from the time-current characteristic curve, there is no selectivity between the upper and lower switches, but judging from the tripping energy curve, the upper and lower selectivity can still achieve energy selectivity between the upper and lower switches.

[0112] The second set current relationship is a rated current range difference relationship between the upper switch and the lower switch.

[0113] In one embodiment, the second set current relationship is: In 上级 ≥BIn 下级 Among them, B is the second coefficient, In 上级 is the rated current of the upper switch, In 下级 is the rated current of the downstream switch.

[0114] The second target current parameter here is configured to make the current of the instantaneous action of the upper switch greater than or equal to the energy tripping of the lower switch.

[0115] The following takes the molded case circuit breaker as an example to further describe the determination method of energy selectivity:

[0116] Among them, the molded case circuit breaker has energy tripping. As a special tripping mode, energy tripping is independent of the normal overload, short-circuit short-delay and instantaneous tripping protection of the switch. It is similar to the instantaneous protection with non-adjustable current. The energy tripping threshold is 25In, the tripping current is higher than the instantaneous protection threshold, the breaking time is <10ms, and the current and time are not adjustable. For the expected short-circuit current less than the energy tripping threshold of the upper switch, the upper instantaneous maximum setting value ≥ the threshold of the lower energy tripping, that is, when the rated current difference between the upper and lower levels is ≥2.5 times, the upper and lower levels can select between the upper and lower levels through the energy tripping of the lower level to the threshold of the energy tripping of the upper circuit breaker. Because the maximum value that can be set for the instantaneous action of the molded case circuit breaker is usually >10In, and the energy tripping is 25In. Therefore, if 10In upper level ≥ 25In lower level, and the rated current of the upper and lower levels satisfy In upper level ≥ 2.5In lower level, the current of the upper level instantaneous action ≥ the energy tripping of the lower level can be satisfied to achieve selectivity, and the fault point flow of In upper level < 25In upper level (upper level energy tripping threshold) is selective.

[0117] In one embodiment, the full selectivity requirement may also include time selectivity+current selectivity+energy selectivity.

[0118] For example, if the upper and lower switches in a certain line are: NSX400H-Mic5.3A-400 and NSX100H-Mic2.2-100 series combination circuit breaker: then,

[0119] Upper circuit breaker: The maximum setting of instantaneous protection is 12 times, that is, Iimaxupper=4.8kA (Iimaxupper=12×400A), Iupper energy=25Inupper=10kA.

[0120] Lower level circuit breaker: The maximum setting of instantaneous protection is 15 times, Iimax lower level = 1.5kA, energy tripping threshold I lower level energy = 25In lower level = 2.5Ka.

[0121] The time-current characteristics and short-circuit protection threshold of the series combination are as follows: Figure 7 shown.

[0122] Among them, area A: 1.5kA to 2.5kA, coordination is achieved through time selectivity. The upper level overload or short circuit short delay tripping is actuated, but the lower level instantaneous tripping is actuated first to achieve selectivity.

[0123] Area B: 2.5kA to 4.8kA, coordination is achieved through time selectivity, the upper short-delay tripping is actuated, but the lower energy tripping is actuated first to achieve selectivity.

[0124] Area C: 4.8kA to 10kA, through time selectivity coordination, and because the upper and lower levels have energy tripping in addition to instantaneous tripping, the short-circuit current is less than the energy tripping of the upper circuit breaker. At this time, the lower circuit breaker will quickly cut off the fault because the energy tripping precedes its own instantaneous protection action, and the duration of the fault point flow is less than the inherent action time of the instantaneous protection of the upper circuit breaker. Therefore, the upper instantaneous protection has not had time to act, and the upper energy tripping cannot trip due to insufficient energy. Therefore, at this time, time selectivity between the upper and lower levels can also be achieved. If the lower circuit breaker does not have energy tripping to quickly disconnect, then the upper and lower levels will simultaneously trip the instantaneous protection, and it is impossible to still have selectivity for the fault point flow after exceeding the upper instantaneous protection, unless the instantaneous protection is turned off to a certain extent.

[0125] Area D: 10kA to 70kA, in this area both the upper and lower levels may experience energy tripping.

[0126] In the above implementation process, the rated current extreme difference relationship between the upper switch and the lower switch is set to meet the second set current relationship, so that the lower switch can realize energy selection between the upper and lower switches, and then control the switch closest to the fault point to act first, reduce the scope of power outage, and improve the stability of power supply and distribution.

[0127] In a possible implementation, step 202 includes: when the distance relationship between the target switch and the corresponding upper switch or lower switch is less than or equal to a distance threshold, determining that the target switch needs to meet a local selectivity requirement; and determining a set protection parameter for the target switch to meet the local selectivity requirement.

[0128] The local selectivity includes one or more of time selectivity and current selectivity.

[0129] It should be understood that when the distance relationship between the target switch and the corresponding upper switch or lower switch is less than or equal to the distance threshold, it means that the energy selectivity between the target switch and the corresponding upper switch or lower switch is difficult to satisfy.

[0130] In this case, it is determined that the target switch meets the local selectivity requirements so that the target switch can meet as many selectivity coordination as possible, thereby reducing the scope of the power outage.

[0131] Optionally, the local selectivity may include only current selectivity, or only time selectivity, or current selectivity + time selectivity. The local selectivity may be adjusted according to the actual situation of the power supply and distribution system.

[0132] In the above implementation process, when it is determined that the distance relationship between the target switch and the corresponding upper switch or lower switch is less than or equal to the distance threshold, it is determined that the target switch meets the local selectivity requirements, and then the target switch meets the partial selectivity, so as to improve the accuracy of the target switch action as much as possible. When a fault occurs in the system, the power outage scope is reduced as much as possible to improve the stability of power supply and distribution.

[0133] Based on the same application concept, a switch configuration device corresponding to the switch configuration method is also provided in the embodiment of the present application. Since the principle of solving the problem by the device in the embodiment of the present application is similar to that of the aforementioned switch configuration method embodiment, the implementation of the device in this embodiment can refer to the description in the embodiment of the above method, and the repeated parts will not be repeated.

[0134] See also Figure 8 , is a functional module diagram of a switch configuration device provided in an embodiment of the present application. Each module in the switch configuration device in this embodiment is used to execute each step in the above method embodiment. The switch configuration device includes a first determination module 301, a second determination module 302, and a third determination module 303; wherein,

[0135] The first determination module 301 is used to determine the maximum expected short-circuit current of the total incoming power at the target switch installation point.

[0136] The second determination module 302 is used to determine the set protection parameter of the target switch according to the distance relationship between the target switch and the corresponding upper switch or lower switch.

[0137] The third determination module 303 is used to determine a switch that meets the maximum expected short-circuit current and set protection parameters as a target switch; wherein the maximum expected short-circuit current is configured to enable the target switch to achieve backup protection, and the set protection parameters are configured to enable the target switch to meet selective coordination.

[0138] In a possible implementation, the second determination module 302 is further used to: determine that the target switch needs to meet the full selectivity requirement when the distance relationship between the target switch and the corresponding upper switch or lower switch is greater than a distance threshold; and determine the set protection parameters for the target switch to meet the full selectivity requirement.

[0139] In one possible implementation, the second determination module 302 is specifically used to: determine the first coefficient corresponding to the target switch according to the switch type of the target switch; determine the first target current parameter of the target switch according to the first coefficient and the first set current relationship; the first set current relationship is the current relationship between the upper switch and the lower switch; wherein the first target current parameter is configured so that the maximum action characteristic curve of the lower switch is located below the minimum action characteristic curve of the upper switch.

[0140] In one possible implementation, the second determination module 302 is specifically used to: when the target switch is a first type switch, turn off the instantaneous protection of the target switch and set a set action delay time; when the target switch is a second type switch, set the short-circuit current of the lower switch to be less than the instantaneous maximum setting value of the upper switch.

[0141] In one possible implementation, the second determination module 302 is specifically used to: determine a second coefficient corresponding to the target switch; determine a second target current parameter of the target switch based on the relationship between the second coefficient and the second set current; wherein the second set current relationship is a rated current range relationship between the upper switch and the lower switch; wherein the second target current parameter is configured so that the current of the instantaneous action of the upper switch is greater than or equal to the energy tripping of the lower switch.

[0142] In a possible implementation, the second determination module 302 is further used to: determine that the target switch needs to meet a local selectivity requirement when the distance relationship between the target switch and the corresponding upper switch or lower switch is less than or equal to a distance threshold; determine the set protection parameters for the target switch to meet the local selectivity requirement; wherein the local selectivity includes one or more of time selectivity and current selectivity.

[0143] In addition, an embodiment of the present application further provides a computer-readable storage medium, on which a computer program is stored. When the computer program is executed by a processor, the steps of the switch configuration method in the above method embodiment are executed.

[0144] The computer program product of the switch configuration method provided in the embodiment of the present application includes a computer-readable storage medium storing program code. The instructions included in the program code can be used to execute the steps of the switch configuration method in the above method embodiment. For details, please refer to the above method embodiment, which will not be repeated here.

[0145] In several embodiments provided in the present application, it should be understood that the disclosed devices and methods can also be implemented in other ways. The device embodiments described above are merely schematic. For example, the flowcharts and block diagrams in the accompanying drawings show the possible architecture, functions and operations of the devices, methods and computer program products according to multiple embodiments of the present application. In this regard, each box in the flowchart or block diagram can represent a module, a program segment or a part of the code, and a part of the module, program segment or code contains one or more executable instructions for implementing the specified logical function. It should also be noted that in some alternative implementations, the functions marked in the box can also occur in a different order from the order marked in the accompanying drawings. For example, two consecutive boxes can actually be executed substantially in parallel, and they can sometimes be executed in the opposite order, depending on the functions involved. It should also be noted that each box in the block diagram and / or flowchart, and the combination of boxes in the block diagram and / or flowchart can be implemented with a dedicated hardware-based system that performs a specified function or action, or can be implemented with a combination of dedicated hardware and computer instructions.

[0146] In addition, the functional modules in the various embodiments of the present application may be integrated together to form an independent part, or each module may exist separately, or two or more modules may be integrated to form an independent part.

[0147] If the function is implemented in the form of a software function module and sold or used as an independent product, it can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present application is essentially or the part that contributes to the prior art or the part of the technical solution can be embodied in the form of a software product, and the computer software product is stored in a storage medium, including several instructions to enable a computer device (which can be a personal computer, a server, or a network device, etc.) to perform all or part of the steps of the various embodiments of the present application. The aforementioned storage medium includes: U disk, mobile hard disk, read-only memory (ROM, Read-Only Memory), random access memory (RAM, Random Access Memory), disk or optical disk and other media that can store program code. It should be noted that in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprises" or any other variations thereof are intended to cover non-exclusive inclusion, so that a process, method, article or apparatus that includes a series of elements includes not only those elements, but also includes other elements not explicitly listed, or also includes elements inherent to such process, method, article or apparatus. In the absence of more restrictions, the elements defined by the sentence "includes..." do not exclude the presence of other identical elements in the process, method, article or apparatus that includes the elements.

[0148] The above are only preferred embodiments of the present application and are not intended to limit the present application. For those skilled in the art, the present application may have various modifications and variations. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present application shall be included in the protection scope of the present application. It should be noted that similar numbers and letters represent similar items in the following drawings, so once an item is defined in one drawing, it does not need to be further defined and explained in the subsequent drawings.

[0149] The above are only specific implementations of the present application, but the protection scope of the present application is not limited thereto. Any technician familiar with the technical field can easily think of changes or substitutions within the technical scope disclosed in the present application, which should be included in the protection scope of the present application. Therefore, the protection scope of the present application should be based on the protection scope of the claims.

Claims

1. A switch configuration method, characterized in that: include: Determine the maximum expected short-circuit current of the total incoming power at the target switch installation point; Determining a set protection parameter of the target switch according to a distance relationship between the target switch and a corresponding upper switch or lower switch; Determine a switch that satisfies the maximum expected short-circuit current and the set protection parameter as the target switch; The maximum expected short-circuit current is configured to enable the target switch to achieve backup protection, and the set protection parameter is configured to enable the target switch to meet selective coordination.

2. The method according to claim 1, characterized in that The step of determining the set protection parameter of the target switch according to the distance relationship between the target switch and the corresponding upper switch or lower switch includes: When the distance relationship between the target switch and the corresponding upper switch or lower switch is greater than a distance threshold, determining that the target switch needs to meet the full selectivity requirement; Determine the set protection parameters of the target switch to meet the full selectivity requirement.

3. The method according to claim 2, characterized in that in, The full selectivity requirement includes: current selectivity; the set protection parameter includes: a first target current parameter; The step of determining the setting protection parameters of the target switch to meet the full selectivity requirement includes: Determining a first coefficient corresponding to the target switch according to the switch type of the target switch; Determine a first target current parameter of the target switch according to the first coefficient and a first set current relationship; the first set current relationship is a current relationship between the upper switch and the lower switch; The first target current parameter is configured so that the maximum operating characteristic curve of the lower switch is located below the minimum operating characteristic curve of the upper switch.

4. The method according to claim 2, characterized in that: in, The full selectivity requirement includes: time selectivity; the setting protection parameters include: setting one or more of the action delay time, short-circuit current and instantaneous maximum setting value; The step of determining that the target switch satisfies the setting protection parameter of the full selectivity requirement includes: When the target switch is a first type switch, turning off the instantaneous protection of the target switch and setting a set action delay time; When the target switch is a second type switch, the short-circuit current of the lower switch is set to be smaller than the maximum instantaneous setting value of the upper switch.

5. The method according to claim 2, characterized in that: in, The full selectivity requirement includes: energy selectivity; the set protection parameter includes: a second target current parameter; The step of determining the setting protection parameters of the target switch to meet the full selectivity requirement includes: Determining a second coefficient corresponding to the target switch; Determine a second target current parameter of the target switch according to the second coefficient and the second set current relationship; wherein the second set current relationship is a rated current range difference relationship between the upper switch and the lower switch; The second target current parameter is configured to make the current of the upper switch instantaneous action greater than or equal to the energy tripping of the lower switch.

6. The method according to claim 1, characterized in that The step of determining the set protection parameter of the target switch according to the distance relationship between the target switch and the corresponding upper switch or lower switch includes: In a case where the distance relationship between the target switch and the corresponding upper switch or lower switch is less than or equal to a distance threshold, determining that the target switch needs to meet the local selectivity requirement; Determining a set protection parameter of the target switch that satisfies the local selectivity requirement; The local selectivity includes one or more of time selectivity and current selectivity.

7. A power supply and distribution system, characterized in that: include: Multi-level distribution box; Wherein, each level of the distribution box includes one or more switches, and the switches are configured by the switch configuration method according to any one of claims 1 to 6 above; The busbars of two adjacent distribution boxes are connected by multiple cables.

8. A switch configuration device, characterized in that: include: A first determination module is used to determine the maximum expected short-circuit current of the total incoming power at the target switch installation point; A second determination module, configured to determine a set protection parameter of the target switch according to a distance relationship between the target switch and a corresponding upper switch or lower switch; A third determination module, configured to determine a switch that satisfies the maximum expected short-circuit current and the set protection parameter as the target switch; The maximum expected short-circuit current is configured to enable the target switch to achieve backup protection, and the set protection parameter is configured to enable the target switch to meet selective coordination.

9. An electronic device, characterized in that: include: A processor and a memory, wherein the memory stores machine-readable instructions executable by the processor, and when the electronic device is running, the machine-readable instructions are executed by the processor to perform the steps of any method described in claims 1 to 7.

10. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores a computer program, and when the computer program is executed by a processor, the steps of the method according to any one of claims 1 to 7 are executed.