Attitude adjustment parking device and method for zero-gravity deployment test
By designing an attitude adjustment parking device for zero gravity deployment test, the vertical adjustment of the solar wing or antenna rotation axis is achieved using simulated wall components and adjustment components, the problem of gravity influence in ground testing is solved, and the stability of the deployment mechanism is improved. Accuracy and simplify the expansion and transportation of the device.
Patent Information
- Application Number
- CN202410971066.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-19
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2044-07-19
AI Technical Summary
In ground testing, gravity factors affect the expansion mechanism of the solar wing or the deployable antenna, resulting in the rotation axis not being perpendicular to the horizontal plane, affecting the expansion smoothness and accuracy, and it is difficult to achieve an ideal state during installation.
A posture adjustment parking device for zero gravity deployment test is designed, including simulated wall assembly, bracket assembly, pitch adjustment assembly and roll adjustment assembly, which makes the rotation axis perpendicular to the horizontal plane through multiple degrees of freedom adjustment, and utilizes a detachable design Easy to expand and transport.
It realizes accurate adjustment of multi-degree-of-freedom attitudes of deployable solar wings or antennas, eliminates the influence of gravity, protects the deployment mechanism, and has a simple structure, few parts, and is easy to assemble, which is suitable for testing equipment of different sizes.
Smart Images

Figure CN119058979A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of measurement and testing technology, and in particular to a posture adjustment and parking device and method for zero-gravity deployment testing. Background Art
[0002] The deployable solar wing / deployable antenna on the satellite is connected to the satellite through the deployment mechanism. During the satellite AIT stage (assembly, testing, and experiment), the deployment mechanism needs to be tested multiple times to verify the deployment accuracy and mechanical environment adaptability of the deployment mechanism. Generally, the deployable solar wing / deployable antenna base structure adopts a flat plate structure, which has a large surface-to-thickness ratio (the thickness H dimension is much smaller than the length L and width B dimensions), and other accessories are installed on the front and back of the base structure.
[0003] There is a gravity factor on the ground. When testing the deployment mechanism of the solar wing / antenna, it is necessary to unload the gravity of the deployed solar wing / deployable antenna. Otherwise, gravity will generate additional torque on the rotating shaft of the deployment mechanism, which will affect the smoothness of the deployment and damage the accuracy of the deployment mechanism, and finally reduce the reliability of the deployment mechanism in orbit. The usual practice is to make the rotation axis of the deployment mechanism of the deployable solar wing / deployable antenna perpendicular to the horizontal plane (the plane perpendicular to the direction of the gravity vector), so that the center of gravity position of the deployable solar wing / deployable antenna is a constant distance from the deployment mechanism axis. At the same time, the gravity is unloaded (the suspension force is equal to the force) on the upper part of the deployable solar wing / deployable antenna through the suspension system, which makes it easy to eliminate the influence of gravity during the entire deployment process and can better protect the deployment mechanism.
[0004] In order to better unload the gravity of the deployable solar wing / deployable antenna, the ideal state requires that the rotation axis of the deployment mechanism be precisely perpendicular to the horizontal plane. Generally, the solar wing / antenna needs to be installed on a simulated wall and supported and parked with tooling. Since the test ground is usually not ideally level and the processing and assembly process of the supporting tooling will accumulate errors, it will eventually make it difficult for the solar wing / antenna to reach the ideal predetermined state after installation. Therefore, an attitude adjustment parking device is required for the deployment test, which can provide stable support and precise attitude adjustment for the test solar wing / antenna. Adjust the rotation axis of the deployment mechanism of the solar wing / antenna to be as close to the ideal predetermined state as possible, so that multiple deployment tests can also better protect the deployment mechanism. Summary of the invention
[0005] The present invention aims to solve the problem of deployment test of deployable solar wing / antenna, and provides a posture adjustment parking device and method for zero-gravity deployment test, which can support parking and accurately adjust the multi-degree-of-freedom posture of the deployable solar wing / antenna. It adopts a detachable manner, and the storage space in the disassembled state is small, and it is convenient to transport; it is easy to expand according to the size of the test equipment, and only a few parts need to be changed; it has the advantages of simple structure, few types of parts, and easy assembly.
[0006] The present invention provides an attitude adjustment parking device for zero-gravity deployment test, comprising a simulated wall component, a bracket component supported on both sides of the simulated wall component, and a pitch adjustment component and a roll adjustment component respectively connecting the two sides of the simulated wall component to the bracket component, wherein the bracket component can drive the simulated wall component to adjust the yaw direction, the pitch adjustment component can drive the simulated wall component to adjust the pitch direction, and the roll adjustment component can drive the simulated wall component to adjust the roll direction;
[0007] The body-fitting plate of the test product is fixedly connected to the simulated wall assembly. The initial state of the test product is a folded and compressed state. The rotation axis of the test product is made perpendicular to the horizontal plane by adjusting the bracket assembly, the pitch adjustment assembly and the roll adjustment assembly multiple times. The gravity unloading hanger is then adjusted to unload the gravity of the unfolded plate of the test product. The unfolded plate is then unlocked and unfolded.
[0008] The bracket assembly adjusts the yaw direction of the product to be tested around the Y axis through four brake casters connected to the bottom. After adjustment, it is fixed to the ground support using a lead screw screw jack. The components of the bracket assembly are all detachable and can be expanded according to the size of the test product.
[0009] The pitch adjustment assembly is sleeved on the outside of the vertical beam of the bracket assembly along the X-axis direction and is connected to the two sides of the simulated wall assembly through the pitch adjustment block. When the pitch adjustment assembly is loose, it can move up and down along the second vertical beam to allow the product to be tested to be pitch adjusted around the X-axis. When it is adjusted to the appropriate position, it is fixed on the vertical beam of the bracket assembly by rotating and tightening the knurled adjustment screw.
[0010] The posture adjustment parking device for zero-gravity deployment test described in the present invention, as a preferred embodiment, the simulation wall assembly includes a simulation wall body and a connecting shaft, the number of the connecting shafts is two, respectively connected to the left and right sides of the simulation wall body;
[0011] The simulation wall body is a plate-like structure, with screw mounting holes set on the left and right sides. The simulation wall body can be drilled according to the mechanical interface of the product to be tested, and the two sides of the simulation wall body are connected to the pitch adjustment components;
[0012] The connecting shaft is T-shaped, one side of which is connected to the side of the simulated wall body through screws, and the other side extends into the roll adjustment component.
[0013] The posture adjustment parking device for zero-gravity deployment test described in the present invention, as a preferred embodiment, comprises a support assembly including two horizontal beams arranged in parallel along the Z-axis direction, a first vertical beam and a second vertical beam vertically connected in sequence to the middle of the horizontal beams and extending in the Y-axis direction, a longitudinal beam connected between the two horizontal beams, a lead screw screw elevator connected to the outside of the horizontal beams and extending to the ground, and casters with brakes connected to both ends of the horizontal beams;
[0014] The second vertical beam is connected to the top of the first vertical beam and is coaxial with the first vertical beam, the simulated wall assembly is arranged between the two first vertical beams and the second vertical beam, the pitch adjustment assembly is movably connected to the first vertical beam or the second vertical beam, and the connecting shaft and the rolling adjustment assembly are both connected to the top of the second vertical beam;
[0015] The number of the horizontal beam, the first vertical beam and the second vertical beam is 2 each, the number of the lead screw screw lift and the casters with brakes is 4, and the casters with brakes can drive the simulated wall body to move or brake separately;
[0016] The cross beam and the first vertical beam, the first vertical beam and the second vertical beam, and the longitudinal beam and the cross beam are all detachably connected by screws;
[0017] The yaw direction around the Y axis is adjusted by four brake casters, and after adjustment, a lead screw screw jack is used to fix it to the ground support;
[0018] Four bosses are left on the four corners of the simulation wall, and the bosses are connected to the lifting point mounting holes for lifting the posture adjustment parking device. One side of the connecting shaft is fixed to the simulation wall by four screws, two in a group.
[0019] The attitude adjustment parking device for zero-gravity deployment test described in the present invention is preferably configured such that the cross beam, the first vertical beam, the second vertical beam, and the longitudinal beam are all hollow steel pipes with assembly interfaces, and the number of longitudinal beams is two and they are symmetrically distributed;
[0020] The heights of the first vertical beam and the second vertical beam may be selected according to the size of the test product.
[0021] The attitude adjustment parking device for zero-gravity deployment test described in the present invention, as a preferred embodiment, the pitch adjustment assembly includes a compression knurled adjustment screw, a pitch mounting plate passing through the compression knurled adjustment screw, an extrusion block pressed against the end of the compression knurled adjustment screw, a connecting rod passing through the extrusion block and connected to both ends of the pitch mounting plate, a pitch adjustment block connected to the other end of the connecting rod, a pitch knurled adjustment screw connected to the other end of the pitch adjustment block, and a mounting tightening column connected to the end of the pitch knurled adjustment screw;
[0022] The connecting rod connects the pitch mounting plate and the pitch adjustment block into a whole and is sleeved onto the second vertical beam. The extrusion block is embedded in the connecting rod. The pitch knurled adjustment screw and the mounting tightening column fix the simulated wall body.
[0023] The compression knurled adjustment screw includes a screw rod, an operating head with knurling and hexagonal features, and the pitch mounting plate is a plate-shaped structure with the middle being threadedly connected to the compression knurled adjustment screw screw and both ends being threadedly connected to the connecting rod. The screw rod of the compression knurled adjustment screw is matched with the thread of the pitch mounting plate, and the knurling of the operating head is adjusted to the matching depth until the screw rod end presses against the extrusion block, and a torque can be applied to the hexagonal feature of the operating head through a tool to tighten the extrusion block;
[0024] The extrusion block is a plate-like structure with notches at both ends to avoid the connecting rod. The extrusion block is placed on the outer wall of the second vertical beam. Threaded holes are set at both ends of the connecting rod and the pitch mounting plate and the pitch adjustment block are connected into a whole by screws. The notches at both ends of the extrusion block allow the connecting rod to be vertically embedded and wrap the second vertical beam inside.
[0025] The pitch adjustment block includes a horizontal plate threadedly connected to the connecting rod and an extension plate vertically connected to both ends of the horizontal plate and extending toward the simulation wall body. The direction of the horizontal plate of the pitch adjustment block is the same as that of the pitch mounting plate and the extrusion block. The ends of the extension plates of the pitch adjustment block are provided with threaded mounting holes. The pitch knurled adjustment screw includes a screw rod and an operating head with knurling and hexagonal features. The screw rod of the pitch knurled adjustment screw cooperates with the threaded hole of the extension plate of the pitch adjustment block and the top end of the screw rod is threadedly connected to the tightening column, which tightens and fixes the simulation wall body.
[0026] The adjustment component can move up and down along the second vertical beam when it is loose. When it is adjusted to a suitable position, manually adjust the compression knurled adjustment screw so that the screw end of the compression knurled adjustment screw presses against the extrusion block. Apply torque through the tool to tighten the extrusion block. The extrusion block and the pitch adjustment block jointly press and fix the second vertical beam.
[0027] The attitude adjustment parking device for zero-gravity deployment test described in the present invention is preferably provided with four connecting rods, two of which form a group, and two pitch knurled adjustment screws and two jacking columns;
[0028] Four connecting rods connect the pitch mounting plate and the pitch adjusting block into a whole and are sleeved on the second vertical beam, and the extrusion block is embedded in the four connecting rods.
[0029] The attitude adjustment parking device for zero-gravity deployment test described in the present invention is, as a preferred embodiment, the lower end of the rolling adjustment component is embedded in the second vertical beam, and the horizontal axis of the connecting axis is pressed and fixed on the lifting block of the rolling adjustment component. The rolling direction of the connecting axis is adjusted by changing the height of the lifting block of the rolling adjustment component and the simulated wall is driven to adjust the rolling direction around the Z axis.
[0030] The attitude adjustment and parking device for zero-gravity deployment test described in the present invention, as a preferred embodiment, the rolling adjustment component includes a vertical beam mounting block embedded in the second vertical beam at the lower end, an adjustment lifting ring matched with the center hole of the vertical beam mounting block through a lower end cylinder, a lifting block screwed with the adjustment lifting ring at the lower end, a clamping connecting rod connected to one side of the top of the lifting block, a connecting shaft pin connecting the top of the clamping connecting rod with one side of the lifting block, a lifting and clamping plate movably connected to the connecting shaft pin, a connecting screw detachably connected to the other end of the lifting and clamping plate through the lifting block, and a set screw that sequentially passes through the second vertical beam and the vertical beam mounting block and is pressed against the side wall of the adjustment lifting ring;
[0031] The lower end of the vertical beam mounting block is a square structure smaller than the inner length and width of the second vertical beam, the upper end is a docking boss larger than the outer length and width of the second vertical beam, the side along the Y-axis direction is provided with a threaded mounting hole for mounting a set screw, and the center is provided with a round through hole for inserting an adjustment lifting ring;
[0032] The lower end of the adjustment lifting ring is a cylinder, the lower part of the cylinder is connected to a transversely distributed annular notch, and the upper end is a polygonal flange structure with a circular hole connected to the side, and the center of the adjustment lifting ring is an internal threaded through hole threadedly connected to the lower end of the lifting block;
[0033] The lower end of the lifting block is an external threaded rod, and the upper end is a boss with a V-shaped groove, and the horizontal shaft of the connecting shaft extends into the V-shaped groove;
[0034] The lifting and pressing plate is opened and closed with the connecting shaft pin as the axis. The bottom of the lifting and pressing plate is connected to an arc-shaped notch in the same extension direction as the connecting shaft. The connecting shaft is placed in the V-shaped groove of the lifting block. The connecting screw presses the connecting shaft between the lifting blocks of the lifting and pressing plate.
[0035] The cylinder at the lower end of the adjustment lifting ring is installed in the central hole of the vertical beam mounting block. Two set screws pass through the side wall of the second vertical beam and the side wall of the vertical beam mounting block in sequence and are embedded in the annular notch at the lower end of the adjustment lifting ring for limiting. The lifting block is screwed to the adjustment lifting ring through the lower end screw rod. The height of the lifting block can be changed by changing the thread matching length.
[0036] The number of the adjustment components 4 is 2 groups, which respectively press the 2 connecting shafts.
[0037] The present invention provides a posture adjustment parking method for zero-gravity deployment test, comprising the following steps:
[0038] S1, assembling the simulation wall assembly, the bracket assembly, the pitch adjustment assembly and the roll adjustment assembly;
[0039] S2. First, the body contact board of the test product is installed on the simulated wall, and the unfolded board is hung by the gravity unloading hanger. The initial state of the test product is that the unfolded board is folded and pressed against the body contact board;
[0040] S3, adjust the yaw direction around the Y axis by adjusting the brake caster of the bracket assembly multiple times, adjust the pitch adjustment around the X axis by adjusting the compression knurled adjustment screw of the pitch adjustment assembly multiple times, and adjust the height of the lifting block of the roll adjustment assembly multiple times to adjust the roll direction around the Z axis until the rotation axis of the test product is perpendicular to the horizontal plane, and the horizontal plane is a plane perpendicular to the direction of the gravity vector;
[0041] S4. Adjust the gravity unloading hanger to enable gravity unloading of the unfolded plate;
[0042] S5. The deployment plate is deployed around the body-contacting plate until it is coplanar with the body-contacting plate, thereby completing a posture adjustment parking method for a zero-gravity deployment test.
[0043] The attitude adjustment parking method for zero-gravity deployment test described in the present invention is, as a preferred embodiment, in step S2, the test product is a solar wing sailboard or a phased array antenna including three sub-arrays. When the test product is a phased array antenna, the initial state of the phased array antenna is that the left and right phased array antenna sub-arrays are gathered and pressed on the middle phased array antenna sub-array at the same side, the middle phased array antenna sub-array is connected to the simulated wall body, and the number of gravity unloading hangers is two, and the left and right phased array antenna sub-arrays are suspended respectively;
[0044] In step S5, the left and right phased array antenna subarrays are deployed in a time sequence, first deploying the outermost phased array antenna subarray, then deploying another phased array antenna subarray until the three phased array antenna subarrays are coplanar.
[0045] The present invention has the following advantages:
[0046] (1) The present invention can accurately adjust the support parking and multi-degree-of-freedom posture of the deployable solar wing / antenna, eliminate the influence of gravity during the deployment test, and better protect the satellite deployment mechanism;
[0047] (2) The present invention is detachable, and in the disassembled state, it occupies little storage space and is convenient to transport. It is easy to expand according to the size of the test equipment, and only a few parts need to be changed. It has the advantages of simple structure, few types of parts, and easy assembly. BRIEF DESCRIPTION OF THE DRAWINGS
[0048] Figure 1 It is a structural schematic diagram of an attitude adjustment parking device used for zero-gravity deployment test;
[0049] Figure 2 A schematic diagram of the structure of a simulated wall assembly of an attitude adjustment parking device for zero-gravity deployment testing;
[0050] Figure 3A schematic diagram of the structure of a bracket assembly of an attitude adjustment parking device for zero-gravity deployment testing;
[0051] Figure 4 A schematic diagram of a disassembled support assembly of a posture adjustment parking device for zero-gravity deployment testing;
[0052] Figure 5 A schematic diagram of a disassembled pitch adjustment assembly of an attitude adjustment parking device for zero-gravity deployment testing;
[0053] Figure 6 A schematic diagram of the structure of a pitch adjustment assembly of an attitude adjustment parking device for zero-gravity deployment testing;
[0054] Figure 7 A front view of a pitch adjustment assembly of an attitude adjustment parking device for zero-gravity deployment testing;
[0055] Figure 8 A schematic diagram of a disassembled rolling adjustment assembly of a posture adjustment parking device for zero-gravity deployment testing;
[0056] Fig. 9 A schematic diagram of the structure of a rolling adjustment assembly of an attitude adjustment parking device for zero-gravity deployment testing;
[0057] Fig.10 A cross-sectional schematic diagram of the installation state of a rolling adjustment component of an attitude adjustment parking device for a zero-gravity deployment test;
[0058] Fig.11 A schematic diagram of a use state of an attitude adjustment parking device for zero-gravity deployment test;
[0059] Fig.12a A schematic diagram of a posture adjustment parking device for zero-gravity deployment test in the initial deployment state;
[0060] Figure 12b A schematic diagram of a posture adjustment parking device used for zero-gravity deployment test during deployment;
[0061] Fig.12c A schematic diagram of a posture adjustment parking device for zero-gravity deployment test when the deployment is completed;
[0062] Fig.13 A schematic diagram of a use state of adjusting a phased array antenna by an attitude adjustment parking device used for a zero-gravity deployment test;
[0063] Fig.14 A partial enlarged view of the hoisting of a phased array antenna for an attitude adjustment parking device used in zero-gravity deployment testing;
[0064] Fig.15a A schematic diagram of a posture adjustment parking device for zero-gravity deployment test adjusting a phased array antenna to start deployment;
[0065] Fig.15b A schematic diagram of the state of an attitude adjustment parking device used for zero-gravity deployment test during the deployment process of a phased array antenna;
[0066] Fig.15c A schematic diagram of a posture adjustment parking device for zero-gravity deployment test when the deployment of a phased array antenna is completed;
[0067] Fig.16 The present invention is a flow chart of a method for using a posture adjustment parking device for zero-gravity deployment testing.
[0068] Reference numerals:
[0069] 1. Simulated wall assembly; 11. Simulated wall body; 12. Connecting shaft; 2. Bracket assembly; 21. Crossbeam; 22. First vertical beam; 23. Second vertical beam; 24. Longitudinal beam; 25. Lead screw screw lift; 26. Caster with brake; 3. Pitch adjustment assembly; 31. Pressing knurled adjustment screw; 32. Pitch mounting plate; 33. Extrusion block; 34. Connecting rod; 35. Pitch adjustment block; 36. Pitch knurled adjustment screw; 37. Installing top column; 4. Rolling adjustment assembly; 41. Vertical beam mounting block; 42. Adjusting lifting ring; 43. Lifting block; 44. Pressing connecting rod; 45. Connecting shaft pin; 46. Lifting and clamping plate; 47. Connecting screw; 48. Set screw; 5. Body plate; 6. Unfolding plate; 7. Inter-plate unfolding mechanism; 8. Gravity unloading sling. DETAILED DESCRIPTION
[0070] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments.
[0071] Example 1
[0072] An attitude adjustment parking device and method for zero gravity deployment test,
[0073] like Figure 1As shown, the attitude adjustment parking device schematically includes a simulation wall component 1, a bracket component 2, a pitch adjustment component 3, and a roll adjustment component 4. The simulation wall component 1 is installed on the roll adjustment component 4, and the pitch adjustment component 3 and the roll adjustment component 4 are installed on the bracket component 2. The prescribed coordinate system is located at the geometric center of the simulation wall component 1, and the three coordinate axes are shown in the figure. The simulation wall component 1 rotates around the X axis in the pitch direction, around the Y axis in the yaw direction, and around the Z axis in the roll direction.
[0074] like Figure 2 As shown, the simulation wall assembly 1 mainly includes two parts: a simulation wall 11 and two connecting shafts 12. The two connecting shafts 12 are located on both sides of the simulation wall 11 in the X direction and are connected by screws. Four bosses and hanging point mounting holes are left on the four corners of the simulation wall 11 for hanging. Holes can be opened in the surface of the simulation wall 11 according to the mechanical interface of the installed solar wing sailboard or antenna.
[0075] Figure 3 , Figure 4 The figure is a schematic diagram of the bracket assembly 2. It mainly includes 2 cross beams 21, 2 first vertical beams 22, 2 second vertical beams 23, 2 longitudinal beams 24, 4 screw screw elevators 25, and 4 braked casters 26. The cross beam 21, the first vertical beam 22, the second vertical beam 23, and the longitudinal beam 24 are all welded by Q235 steel pipes with square cross sections and 4mm and 8mm thick steel plates, and the thick steel plates have external interfaces for assembly. The screw screw elevators 25 and the braked casters 26 are installed on the cross beam 21, and the two ends of the longitudinal beam 24 are connected to the cross beam 21 by screws; the first vertical beam 22 and the second vertical beam 23 are connected by screws, and the first vertical beam 22 is connected to the cross beam 21 by screws. The four braked casters 26 can adjust the bracket assembly 2 in the yaw direction around the Y axis. After adjustment, the four screw screw elevators 25 are used to fix it to the ground support. The bracket assembly is detachable, and takes up little storage space when disassembled, making it convenient to transport. The bracket assembly can be easily expanded according to the size of the test equipment. If the size of the unfolded solar wing / deployable antenna is too large and exceeds the size of the current simulation wall assembly 1, it is only necessary to replace the second vertical beam 23 and the longitudinal beam 24 with a longer size.
[0076] Figure 5As shown; the pitch adjustment assembly 3 is mainly composed of a compression knurled adjustment screw 31, a pitch mounting plate 32, an extrusion block 33, a connecting rod 34, a pitch adjustment block 35, a pitch knurled adjustment screw 36, and a tightening column 37. The compression knurled adjustment screw 31 is composed of a screw rod and an operating head with knurling and hexagonal features. The screw rod is used to cooperate with the thread of the pitch mounting plate 32. The knurling is used to quickly adjust the fitting depth until the end of the screw rod presses against the extrusion block 33. The hexagonal feature can apply torque to tighten the extrusion block 33 through a tool; the four connecting rods 34 have threaded holes at both ends, and the pitch mounting plate 32 and the pitch adjustment block 35 are connected into a whole by screws; the notches at both ends of the extrusion block 33 can be embedded in the four connecting rods 34; the pitch knurled adjustment screw 36 is composed of a screw rod and an operating head with knurling and hexagonal features. The screw rod cooperates with the threaded hole of the pitch adjustment block 35, and a tightening column 37 is installed at the top of the screw rod.
[0077] Figure 6 The diagram is a schematic diagram of the pitch adjustment assembly 3 being installed on the second vertical beam 23. The four connecting rods 34 connect the pitch mounting plate 32 and the pitch adjustment block 35 into a whole and insert it into the second vertical beam 23. The extrusion block 33 is embedded in the four connecting rods 34. The adjustment assembly 3 can move up and down the second vertical beam 23 when it is loose. When it is adjusted to a suitable position, the compression knurled adjustment screw 31 is manually adjusted so that the screw end of the compression knurled adjustment screw 31 presses against the extrusion block 33. The extrusion block 33 is tightened by applying torque through a tool. The extrusion block 33 and the pitch adjustment block 35 jointly press the second vertical beam 23 to fix the position.
[0078] Figure 7 The diagram is a diagram of the pitch adjustment assembly 3 adjusting the pitch of the simulated wall assembly 1. After the two pitch knurled adjustment screws 36 are screwed into the pitch adjustment block 35, the tightening column 37 is installed. The two tightening columns 37 cooperate to limit the simulated wall 11 of the simulated wall assembly 1 to a fixed angle around the connecting axis 12. When the pitch adjustment of the simulated wall assembly 1 is required, the screwing depth of the two pitch knurled adjustment screws 36 is adjusted to adjust the rotation angle of the simulated wall assembly 1 around the connecting axis 12.
[0079] Figure 8It is composed of a rolling adjustment component 4. It is mainly composed of a vertical beam mounting block 41, an adjustment lifting ring 42, a lifting block 43, a clamping connecting rod 44, a connecting shaft pin 45, a lifting and clamping plate 46, a connecting screw 47, and a set screw 48. The lower end of the vertical beam mounting block 41 is square and can be embedded in the second vertical beam 23, and a docking boss is left outside at the upper end. Two threaded holes are left at the lower end of the vertical beam mounting block 41 to install the set screw 48, and the center of the vertical beam mounting block 41 is a round through hole; the lower end of the adjustment lifting ring 42 is a cylinder, and there is a ring notch at the bottom of the cylinder, and the upper end is a polygonal flange, and there is a round hole on the edge of the flange, and the center of the adjustment lifting ring 42 is an internal threaded through hole. The adjusting lifting ring 42 cooperates with the center hole of the vertical beam mounting block 41 through the cylinder at the lower end. The circular hole of the polygonal flange at the upper end of the adjusting lifting ring 42 can be operated by a tool to make it rotate relatively. The fixing screw 48 passes through the vertical beam mounting block 41 and will be stuck in the annular notch of the cylinder at the lower end of the adjusting lifting ring 42, so that it cannot fall out. When the fixing screw 48 is tightened, the adjusting lifting ring 42 can be tightened; the lower end of the lifting block 43 is an externally threaded rod, and the upper end has a V-groove boss. The lifting block 43 is screwed with the adjusting lifting ring 42 through the screw at the lower end, and cooperates with the connecting shaft 12 of the simulated wall assembly 1 through the V-groove at the upper end, and the connecting shaft 12 is pressed onto the lifting block 43 by pressing the connecting rod 44, the connecting shaft pin 45, and the lifting and lowering clamping plate 46.
[0080] Fig. 9 , Fig.10 The schematic diagram of the pitch adjustment of the simulated wall component 1 by the rolling adjustment component 4 is shown. The lower end of the vertical beam mounting block 41 is embedded in the second vertical beam 23, and the adjustment lifting ring 42 is installed to the center hole of the vertical beam mounting block 41 through the cylinder at the lower end. Two set screws 48 are installed on the vertical beam mounting block 41 and embedded in the annular notch of the lower end cylinder of the adjustment lifting ring 42 for position limiting. The lifting block 43 is screwed with the adjustment lifting ring 42 through the screw at the lower end. Changing the length of the threaded fit can change the height of the lifting block 43. The pressing connecting rod 44, the connecting shaft pin 45, and the lifting and clamping plate 46 cooperate to press the connecting shaft 12 on the lifting block 43. There are 2 sets of rolling adjustment components 4 to press the 2 connecting shafts 12 of the simulated wall component 1.
[0081] Fig.11 and Fig.12a , 12b12c briefly introduces the solar wing sailboard deployment test process. First, the solar wing sailboard is installed on the simulation wall component 1 of the attitude adjustment parking device. The solar wing sailboard includes a body plate 5, an unfolding plate 6, and two inter-plate unfolding mechanisms 7. The body plate 5 is installed on the simulation wall 11, and the unfolding plate 6 is suspended by a gravity unloading hanger 8. The initial state is that the unfolding plate 6 is folded and pressed. The pitch adjustment component 3 and the roll adjustment component 4 of the attitude adjustment parking device are adjusted multiple times until the rotation axis of the two inter-plate unfolding mechanisms 7 is perpendicular to the horizontal plane (the plane perpendicular to the direction of the gravity vector), and then the gravity unloading hanger 8 is adjusted to unload the gravity of the unfolding plate 6. Fig.12a , 12b 12a and 12b are schematic diagrams of the unfolding process of the unfolding plate 6 of the solar wing, which respectively show the states of just beginning to unfold, in the process of unfolding, and when the unfolding is completed.
[0082] like Fig.16 As shown, a method for using an attitude adjustment parking device for zero-gravity deployment test is as follows: first, install the test product such as a deployable solar wing / deployable antenna on the simulated wall component 1 of the attitude adjustment parking device. The initial state is a folded and compacted state. The pitch adjustment component 3 and the roll adjustment component 4 of the attitude adjustment parking device are adjusted multiple times until the rotation axis of the test product is perpendicular to the horizontal plane (a plane perpendicular to the direction of the gravity vector), and then adjust the gravity unloading hanger 8 to unload the gravity of the deployment plate. Then unlock and deploy.
[0083] Fig.13 , 14 15a, 15b, and 15c are schematic diagrams of a phased array antenna composed of three sub-boards undergoing a zero-gravity deployment test. The phased array antenna is placed in a zero-gravity state during deployment by means of an attitude adjustment parking device and a hanging beam fixture, which can better protect the deployment mechanism. The body-mounted sub-array of the phased array antenna is installed on the simulated wall of the attitude adjustment parking device. The attitude adjustment parking device can provide stable support and precise attitude adjustment for the phased array antenna, and adjust the rotation axis of the deployment mechanism to be as close to the ideal predetermined state as possible; each deployment sub-array is installed with a hanging beam fixture, which has the function of coarse and fine adjustment of the two-dimensional position, and can accurately adjust the suspension force of the zero-gravity hanging system to the center of gravity of the deployable sub-array, so that there is no disturbance torque during the deployment of the deployment mechanism.
[0084] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical scheme and inventive concept of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.
Claims
1. An attitude adjustment parking device for zero gravity deployment test, characterized in that: The invention comprises a simulated wall component (1), a bracket component (2) supported on both sides of the simulated wall component (1), and a pitch adjustment component (3) and a roll adjustment component (4) respectively connecting the two sides of the simulated wall component (1) to the bracket component (2), wherein the bracket component (2) can drive the simulated wall component (1) to adjust the yaw direction, the pitch adjustment component (3) can drive the simulated wall component (1) to adjust the pitch direction, and the roll adjustment component (4) can drive the simulated wall component (1) to adjust the roll direction; The body contact plate of the test product is fixedly connected to the simulated wall assembly (1), the initial state of the test product is a folded and compressed state, and the rotation axis of the test product is made perpendicular to the horizontal plane by adjusting the support assembly (2), the pitch adjustment assembly (3) and the roll adjustment assembly (4) multiple times, and then the gravity unloading hanger is adjusted to unload the gravity of the unfolded plate of the test product, and then the unfolded plate is unlocked and unfolded; The support assembly (2) is used to adjust the yaw direction of the product to be tested around the Y axis through four brake casters connected to the bottom, and after being adjusted into place, it is fixed to the ground support using a lead screw screw lift; the components of the support assembly (2) are all detachably connected and can be expanded according to the size of the product to be tested; The pitch adjustment component (3) is sleeved on the outside of the vertical beam of the support component (2) along the X-axis direction and is connected to the two sides of the simulated wall component (1) through the pitch adjustment block. When the pitch adjustment component (3) is loose, it can move up and down along the second vertical beam (23) to adjust the pitch of the product to be tested around the X-axis. When adjusted to a suitable position, it is fixed on the vertical beam of the support component (2) by rotating and tightening the knurled adjustment screw.
2. The attitude adjustment parking device for zero gravity deployment test according to claim 1, characterized in that: The simulated wall assembly (1) comprises a simulated wall body (11) and connecting shafts (12); the connecting shafts (12) are two in number and are respectively connected to the left and right sides of the simulated wall body (11); The simulated wall body (11) is a plate-like structure, with screw mounting holes arranged on the left and right sides. The simulated wall body (11) can be opened according to the mechanical interface of the product to be tested. Both sides of the simulated wall body (11) are connected to the pitch adjustment assembly (3); The connecting shaft (12) is T-shaped, one side of which is connected to the side of the simulated wall body (11) via screws, and the other side of which extends into the roll adjustment assembly (4).
3. The attitude adjustment parking device for zero gravity deployment test according to claim 2, characterized in that: The support assembly (2) comprises two horizontal beams (21) arranged in parallel along the Z-axis direction, a first vertical beam (22) and a second vertical beam (23) vertically connected in sequence to the middle of the horizontal beams (21) and extending in the Y-axis direction, a longitudinal beam (24) connected between the two horizontal beams (21), a lead screw screw elevator (25) connected to the outside of the horizontal beams (21) and extending to the ground, and casters (26) with brakes connected to both ends of the horizontal beams (21); The second vertical beam (23) is connected to the top of the first vertical beam (22) and is coaxial with the first vertical beam (22); the simulated wall component (1) is arranged between the two first vertical beams (22) and the second vertical beam (23); the pitch adjustment component (3) is movably connected to the first vertical beam (22) or the second vertical beam (23); the connecting shaft (12) and the rolling adjustment component (4) are both connected to the top of the second vertical beam (23); The number of the horizontal beam (21), the first vertical beam (22) and the second vertical beam (23) is 2 each, the number of the lead screw screw elevator (25) and the number of the casters with brakes (26) is 4, and the casters with brakes (26) can drive the simulated wall body (11) to move or brake independently; The cross beam (21) and the first vertical beam (22), the first vertical beam (22) and the second vertical beam (23), and the longitudinal beam (24) and the cross beam (21) are all detachably connected by screws; The yaw direction around the Y axis is adjusted by using the four brake casters (26), and after the adjustment is in place, the lead screw screw elevator (25) is used to fix it to the ground support; Four bosses are left on the four corners of the simulation wall (11), and the bosses are connected to the hanging point installation holes for hanging the posture adjustment parking device. One side of the connecting shaft (12) is fixed to the simulation wall (11) by four screws, two in a group.
4. The attitude adjustment parking device for zero gravity deployment test according to claim 3, characterized in that: The cross beam (21), the first vertical beam (22), the second vertical beam (23), and the longitudinal beam (24) are all hollow steel pipes with assembly interfaces, and the number of the longitudinal beams (24) is two and they are symmetrically distributed; The heights of the first vertical beam (22) and the second vertical beam (23) can be selected according to the size of the test product.
5. The attitude adjustment parking device for zero gravity deployment test according to claim 3, characterized in that: The pitch adjustment assembly (3) comprises a pressing knurled adjustment screw (31), a pitch mounting plate (32) passing through the pressing knurled adjustment screw (31), an extrusion block (33) pressed against the end of the pressing knurled adjustment screw (31), a connecting rod (34) passing through the extrusion block (33) and connected to both ends of the pitch mounting plate (32), a pitch adjustment block (35) connected to the other end of the connecting rod (34), a pitch knurled adjustment screw (36) connected to the other end of the pitch adjustment block (35), and a mounting pressing column (37) connected to the end of the pitch knurled adjustment screw (36); The connecting rod (34) connects the pitch mounting plate (32) and the pitch adjustment block (35) into a whole and is inserted into the second vertical beam (23); the extrusion block (33) is embedded in the connecting rod (34); the pitch knurled adjustment screw (36) and the mounting tightening column (37) are fixedly connected to the simulated wall body (11); The compression knurled adjustment screw (31) comprises a screw rod, an operating head with knurling and hexagonal features, the pitch mounting plate (32) is a plate-like structure with the middle being threadedly connected to the screw rod of the compression knurled adjustment screw (31) and the two ends being threadedly connected to the connecting rod (34), the screw rod of the compression knurled adjustment screw (31) is matched with the thread of the pitch mounting plate (32), the knurling of the operating head is adjusted to the matching depth until the screw rod end presses against the extrusion block (33), and a torque can be applied to the hexagonal feature of the operating head through a tool to tighten the extrusion block (33); The extrusion block (33) is a plate-like structure with notches at both ends for avoiding the connecting rod (34). The extrusion block (33) is placed on the outer wall of the second vertical beam (23). Threaded holes are provided at both ends of the connecting rod (34) and the pitch mounting plate (32) and the pitch adjustment block (35) are connected into a whole by screws. The notches at both ends of the extrusion block (33) enable the connecting rod (34) to be vertically embedded and wrap the second vertical beam (23) inside. The pitch adjustment block (35) comprises a transverse plate threadedly connected to the connecting rod (34) and an extension plate vertically connected to both ends of the transverse plate and extending toward the simulation wall body (11); the direction of the transverse plate of the pitch adjustment block (35) is the same as that of the pitch mounting plate (32) and the extrusion block (33); threaded mounting holes are arranged at the ends of the extension plates of the pitch adjustment block (35); the pitch knurled adjustment screw (36) comprises a screw rod and an operating head with knurling and hexagonal features; the screw rod of the pitch knurled adjustment screw (36) cooperates with the threaded hole of the extension plate of the pitch adjustment block (35) and the top end of the screw rod is threadedly connected to the tightening column (37); the tightening column (37) tightens and fixes the simulation wall body (11); The adjustment assembly (3) can move up and down along the second vertical beam (23) when it is loose. When it is adjusted to a suitable position, the compression knurled adjustment screw (31) is manually adjusted so that the screw end of the compression knurled adjustment screw (31) presses against the extrusion block (33). A torque is applied by a tool to tighten the extrusion block (33). The extrusion block (33) and the pitch adjustment block (35) jointly press and fix the second vertical beam (23).
6. The attitude adjustment parking device for zero gravity deployment test according to claim 5, characterized in that: The number of the connecting rods (34) is four, two in a group, and the number of the pitch knurled adjustment screws (36) and the number of the tightening columns (37) are both two; The four connecting rods (34) connect the pitch mounting plate (32) and the pitch adjusting block (35) into a whole which is inserted into the second vertical beam (23), and the extrusion block (33) is embedded in the four connecting rods (34).
7. The attitude adjustment parking device for zero gravity deployment test according to claim 5, characterized in that: The lower end of the rolling adjustment component (4) is embedded in the second vertical beam (23), and the horizontal axis of the connecting shaft (12) is pressed and fixed on the lifting block of the rolling adjustment component (4). By changing the height of the lifting block of the rolling adjustment component (4), the rolling direction of the connecting shaft (12) is adjusted and the simulation wall (11) is driven to adjust the rolling direction around the Z axis.
8. The attitude adjustment parking device for zero gravity deployment test according to claim 7, characterized in that: The rolling adjustment assembly (4) comprises a vertical beam mounting block (41) whose lower end is embedded in the interior of the second vertical beam (23), an adjustment lifting ring (42) matched with the center hole of the vertical beam mounting block (41) through a lower end cylinder, a lifting block (43) whose lower end is screwed to the adjustment lifting ring (42), a clamping connecting rod (44) connected to one side of the top of the lifting block (43), a connecting shaft pin (45) connecting the top of the clamping connecting rod (44) to one side of the lifting block (43), a lifting clamping plate (46) movably connected to the connecting shaft pin (45), a connecting screw (47) passing through the lifting block (43) and the other end of the lifting clamping plate (46) detachably connected, and a set screw (48) passing through the second vertical beam (23) and the vertical beam mounting block (41) in sequence and pressing against the side wall of the adjustment lifting ring (42); The lower end of the vertical beam mounting block (41) is a square structure smaller than the inner length and width of the second vertical beam (23), the upper end is a docking boss larger than the outer length and width of the second vertical beam (23), a threaded mounting hole for mounting the set screw (48) is arranged on the side along the Y-axis direction, and a round through hole for inserting the adjustment lifting ring (42) is arranged in the center; The lower end of the adjusting lifting ring (42) is a cylinder, the lower part of the cylinder is connected to a transversely distributed annular notch, and the upper end is a polygonal flange structure with a circular hole connected to the side, and the center of the adjusting lifting ring (42) is an internal threaded through hole threadedly connected to the lower end of the lifting block (43); The lower end of the lifting block (43) is an externally threaded rod, and the upper end is a boss with a V-shaped groove, and the horizontal axis of the connecting shaft (12) extends into the V-shaped groove; The lifting and pressing plate (46) is opened and closed with the connecting shaft pin (45) as the axis, the bottom of the lifting and pressing plate (46) is connected to an arc-shaped notch extending in the same direction as the connecting shaft (12), the connecting shaft (12) is placed in the V-shaped groove of the lifting block (43), and the connecting screw (47) presses the connecting shaft (12) between the lifting and pressing plate (46) and the lifting block (43); The cylinder at the lower end of the adjusting lifting ring (42) is installed in the central hole of the vertical beam mounting block (41), and the two fixing screws (48) respectively pass through the side wall of the second vertical beam (23) and the side wall of the vertical beam mounting block (41) in sequence and are embedded in the annular notch at the lower end of the adjusting lifting ring (42) for limiting. The lifting block (43) is screwed to the adjusting lifting ring (42) through the screw at the lower end, and the height of the lifting block (43) can be changed by changing the thread matching length; The number of the adjustment components 4 is 2, and each of them presses the two connecting shafts (12).
9. A method for attitude adjustment and parking for zero gravity deployment test according to any one of claims 1 to 8, characterized in that: The following steps are involved: S1, assembling the simulated wall assembly (1), the bracket assembly (2), the pitch adjustment assembly (3) and the roll adjustment assembly (4); S2, firstly, the body contact plate (5) of the test product is installed on the simulation wall (11), and the unfolded plate (6) is suspended by the gravity unloading hanger (8), and the initial state of the test product is that the unfolded plate (6) is folded and pressed against the body contact plate (5); S3, adjusting the yaw direction around the Y axis by repeatedly adjusting the brake caster (26) of the bracket assembly (2), adjusting the pitch adjustment around the X axis by repeatedly adjusting the compression knurled adjustment screw (31) of the pitch adjustment assembly (3), and adjusting the height of the lifting block (43) of the roll adjustment assembly (4) to adjust the roll direction around the Z axis until the rotation axis of the test product is perpendicular to the horizontal plane, which is a plane perpendicular to the direction of the gravity vector; S4, adjusting the gravity unloading sling (8) to enable the gravity unloading of the unfolded plate (6); S5. The unfolding plate (6) is unfolded around the body-contacting plate (5) until it is coplanar with the body-contacting plate (5), thereby completing a posture adjustment parking method for a zero-gravity unfolding test.
10. The method for attitude adjustment and parking for zero gravity deployment test according to claim 9, characterized in that: In step S2, the test product is a solar wing sail panel or a phased array antenna including three sub-arrays. When the test product is a phased array antenna, the initial state of the phased array antenna is that the left and right phased array antenna sub-arrays are gathered together and pressed against the middle phased array antenna sub-array on the same side, the middle phased array antenna sub-array is connected to the simulated wall body (11), and the number of the gravity unloading hangers (8) is two and the left and right phased array antenna sub-arrays are suspended respectively; In step S5, the left and right phased array antenna subarrays are deployed in a time sequence, first deploying the outermost phased array antenna subarray, and then deploying another phased array antenna subarray until the three phased array antenna subarrays are coplanar.
Citation Information
Patent Citations
Suspended gravity compensation solar wing ground three-dimensional unfolding test device
CN103010493A
General satellite sun wing expanding frame automatically adjusting levelness
CN104943877A
Automatic debugging system for solar wing stimulation wall attitude
CN109436385A
Self-adaptive six-degree-of-freedom air floating simulation test bench and calculation method thereof
CN113406887A
Solar wing secondary expansion gravity unloading test device
CN115636115A
Cited By
Product transfer device suitable for solar wing
CN119429613A
High-precision large-scale multi-degree-of-freedom unfolding arm assembling and adjusting method
CN120902996A
A high-precision large-scale multi-degree-of-freedom deployment arm adjustment method
CN120902996B
Solar wing simulation wall support vehicle
CN121625070A