Laying device and laying method for horizontal drain board treated by sludge vacuum preloading method
By designing paired connection end and vertical plate structures, combined with GPS positioning and floating platform, the problems of complexity and limitations of horizontal drainage plate laying are solved, and efficient laying and consolidation effects in sludge treatment are achieved.
Patent Information
- Application Number
- CN202411173767.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-26
- Publication Date
- 2024-12-03
AI Technical Summary
The existing horizontal drainage slab laying methods are complex and have great limitations, resulting in low consolidation efficiency in sludge treatment, long construction period, and a lot of manpower and material resources.
A laying device including a first connecting end and a second connecting end arranged in pairs is designed, and the horizontal drainage plate is fixed by an arc-shaped interface and a rolling assembly through the relative arrangement of the first vertical plate and the second vertical plate, and combined with the GPS positioning module and floating construction platform realize the rapid and flexible laying and adjustment of horizontal drainage boards.
The laying efficiency of horizontal drainage plates is improved, bending is avoided, the transmission of vacuum pressure is ensured, the construction period is shortened, the consolidation efficiency is improved, and manpower and material consumption is reduced.
Smart Images

Figure CN119061872A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a laying device for a horizontal drainage board treated by a sludge vacuum preloading method. The valve also relates to a laying method for the horizontal drainage board using the laying device. Background Art
[0002] With the development of my country's economic construction, construction land is in short supply. Land reclamation is a way to increase construction land in coastal areas. In engineering construction, silt is often used as a material for land reclamation. This type of silt is highly fluid and basically has no structure and strength. The processing process requires a large amount of land resources and consumes a lot of manpower and material resources. In engineering, vacuum preloading is often used to treat this type of high-water content silt foundation.
[0003] The traditional vacuum preloading method is to lay out drainage boards in the silt, connect a vacuum pump to the drainage board to evacuate the water in the silt. Drainage boards can be divided into horizontal drainage boards and vertical drainage boards according to different layout methods. When using horizontal drainage boards, first blow the silt into the silt pool to a certain height, then lay out the drainage boards horizontally, connect drainage pipes at both ends of the drainage boards, continue to blow the silt to a certain height, and then lay out another layer of drainage boards, and repeat the above steps until the silt reaches the elevation. When using vertical drainage boards, the soft soil surface needs to have a certain hardness or support, and the plugging machine enters the soft soil and vertically inserts the drainage board into the soft soil at a certain distance for drainage. The water content of the blown silt is very high, and it is difficult for the plugging machine to implement the plugging operation in the above environment. In recent years, in the process of using vertical drainage boards combined with vacuum preloading method to treat silt foundations, due to the extremely high water content of this type of silt and the excessive settlement of the soil, the drainage board is very easy to bend, which affects the transmission of vacuum pressure, resulting in poor soil consolidation effect.
[0004] Compared with the vacuum preloading method combined with vertical drain boards, horizontal drain boards can avoid bending during the reinforcement process, ensure the transmission of vacuum pressure, improve consolidation efficiency, and shorten the construction period. However, the existing horizontal drain board laying method has complicated steps, has great limitations in laying distance and depth, and the laying effect is also average under the premise of consuming a lot of manpower and material resources, which greatly affects the drainage consolidation efficiency. Therefore, in view of the above problems, it is urgent to propose a new horizontal drain board laying method and device. Summary of the invention
[0005] In view of the above shortcomings, an object of the present invention is to provide a laying device for improving the laying efficiency of horizontal drain boards in sludge. An object of the present invention is also to provide a method for laying horizontal drain boards including the above-mentioned laying device.
[0006] To this end, the present invention provides a laying device for horizontal drain boards treated by a sludge vacuum preloading method, wherein the laying device connects one or more drain boards in the laying device according to predetermined laying requirements of the horizontal drain boards and the laying device is placed as a whole in the sludge, the laying device includes a first connecting end and a second connecting end arranged in pairs, and the horizontal drain boards are connected to the corresponding first connecting end and the second connecting end.
[0007] Furthermore, the laying device includes a first vertical plate and a second vertical plate, the first vertical plate and the second vertical plate are arranged opposite to each other, the first connecting end and the second connecting end are respectively arranged at positions opposite to each other of the first vertical plate and the second vertical plate, so that the horizontal drainage plate is arranged horizontally, and one or more first vertical plates and the second vertical plates are provided, the first vertical plate and the adjacent first vertical plate are connected end to end by a detachable connection, and the second vertical plate and the adjacent second vertical plate are connected end to end by a detachable connection.
[0008] Furthermore, it also includes a floating construction platform, which is connected to the first vertical plate and / or the second vertical plate and can move the first vertical plate and / or the second vertical plate to a designated position.
[0009] Furthermore, the first vertical plate and the second vertical plate are provided with a vertical drainage plate channel and rolling components arranged on both sides of the drainage plate channel. The first connecting end and the second connecting end include an arc-shaped interface. The horizontal drainage plate passes through the arc-shaped interface and is restricted in the drainage plate channel by the rolling component.
[0010] Furthermore, a plurality of circular holes are provided in the first vertical plate and the second vertical plate, or windows are provided in the middle of the first vertical plate and the second vertical plate to form a frame structure.
[0011] Furthermore, it also includes a positioning device, which includes a GPS positioning module arranged on the first vertical plate and the second vertical plate, and also includes a positioning part for realizing the vertical arrangement of the first vertical plate or the second vertical plate; the positioning part is arranged on the floating construction platform or preset at a designated position;
[0012] The positioning portion includes a clamping member and a limiting groove, the clamping member is clamped at the upper end of the first vertical plate or the second vertical plate, the clamping member can drive the first vertical plate or the second vertical plate to move vertically downward, the edge of the first vertical plate or the second vertical plate is placed in the limiting groove, and the limiting groove can move vertically downward, in this way, the first vertical plate or the second vertical plate is driven to achieve a vertical setting; or
[0013] The positioning portion includes a connecting rope connected to the first and second vertical plates, and the verticality of the first and second vertical plates is adjusted by the connecting rope.
[0014] Furthermore, the first connection end and the second connection end are rotatably connected to the first vertical plate and the second vertical plate, and the first connection end and the second connection end can realize that the horizontal drainage board between the first connection end and the second connection end is in a horizontal state or flipped into a sideways state.
[0015] Furthermore, one side of the first connecting end and the second connecting end is fixed on a rotating shaft, the rotating shaft passes through a sleeve on the first vertical plate or the second vertical plate, and the other end of the rotating shaft is provided with a rotating part, and the lifting rod is connected to the rotating part and drives the rotating shaft to rotate by lifting.
[0016] Furthermore, a protection plate is provided between the first connection end and the second connection end, the horizontal drainage plate is arranged inside the protection plate, both sides of the protection plate are wedge-shaped, and a plurality of through holes are provided on both sides of the protection plate.
[0017] The present invention also includes a method for laying a horizontal drainage board, using the above-mentioned laying device, including connecting the horizontal drainage board to the laying device, and then placing the laying device connected with the horizontal drainage board as a whole into the silt or moving the laying device to a designated position through a floating construction platform.
[0018] Beneficial technical effects of the present invention:
[0019] The present invention discloses a laying device for horizontal drainage boards treated by a sludge vacuum preloading method. The horizontal drainage boards are first horizontally connected to a first connection end and a second connection end that are arranged in pairs in the laying device, and the laying device is placed in the sludge as a whole. In a specific implementation, a first vertical plate and a second vertical plate that are relatively arranged can be used, and the first connection end and the second connection end are respectively connected to the first vertical plate and the second vertical plate. Multiple layers of horizontal drainage boards are horizontally connected between the first vertical plate and the second vertical plate as required, and the first vertical plate and the second vertical plate are placed in the sludge. The horizontal drainage boards are laid to a designated location by dragging the first vertical plate or the second vertical plate. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] Figure 1 A schematic diagram of a specific embodiment of the present invention;
[0021] Figure 2 It is a schematic diagram of the laying device after connecting the horizontal drainage board;
[0022] Figure 3 is a top view schematic diagram of one embodiment of a positioning portion;
[0023] Figure 4 for Figure 3 Side view of
[0024] Figure 5 A schematic diagram of a frame structure for a first vertical plate and a second vertical plate;
[0025] Figure 6 is a schematic diagram of a rotation structure of a first connection end and a second connection end;
[0026] Figure 7 It is a structural diagram of the protection board;
[0027] Figure 8 It is a schematic diagram of the drainage plate channel and the fixed pulley;
[0028] Fig. 9 Schematic diagram of the fixed pulley.
[0029] Explanation of the accompanying drawings: 1. horizontal drainage board; 2. first vertical board; 3. second vertical board; 4. arc interface; 5. floating construction platform; 6. connecting rope; 7. connection point; 8. circular hole; 9. drainage board channel; 901. fixed pulley; 10. GPS positioning module; 11. clamping part; 12. limit block; 13. rotating shaft; 14. lifting rod; 15. protection plate; 16. through hole. DETAILED DESCRIPTION
[0030] In order to further explain the technical means and effects adopted by the present invention to achieve the predetermined invention purpose, the specific implementation mode, structure, characteristics and effects of the present invention are described in detail below in combination with the accompanying drawings and preferred embodiments.
[0031] Reference Figure 1 and Figure 2 As shown, a laying device for horizontal drain boards treated by a sludge vacuum preloading method of the present invention, the laying device connects one or more horizontal drain boards to the laying device according to the predetermined laying requirements of the horizontal drain boards 1 and the laying device is placed in the sludge as a whole, the laying device includes a first connection end and a second connection end arranged in pairs, and the horizontal drain boards 1 are connected to the corresponding first connection end and the second connection end. The laying method adopted by the laying device of the present invention is different from the traditional laying method. In the traditional laying method, the horizontal drain boards are laid layer by layer from low to high in the sludge. The present invention adopts a method of connecting the horizontal drain boards 1 to the laying device according to the laying requirements of the horizontal drain boards 1, and then placing the laying device in the blown sludge, without the need to lay the horizontal drain boards 1 layer by layer on site.
[0032] Reference Figure 1 and Figure 2As shown, the laying device includes a first vertical plate 2 and a second vertical plate 3, the first vertical plate 2 and the second vertical plate 3 are rectangular thin plates, made of metal materials, the first vertical plate 2 and the second vertical plate 3 are arranged oppositely, the first connecting end and the second connecting end include interfaces, which are arc interfaces 4 in this embodiment, which are arranged at the relative positions of the first vertical plate 2 and the second vertical plate 3, respectively, and the horizontal drain plate 1 is connected to the first connecting end and the second connecting end so that the horizontal drain plate 1 is arranged horizontally. The arc interfaces 4 are arranged in two layers, each layer is on the same horizontal plane and a plurality of arc interfaces 4 are arranged, the number of layers and the number of arc interfaces 4 of each layer can be adjusted according to actual needs or design requirements, and the arc interfaces 4 can prevent the drain plate from bending. The distance between the first vertical plate 2 and the second vertical plate 3 can be pre-set, and the first vertical plate 2 and the second vertical plate 3 are inserted into the corresponding silt. At this time, the horizontal drain plate 1 can be fixed on the first connecting end and the second connecting end. Different from the above embodiment, the laying work of horizontal drain plates at different distances can also be adjusted and adapted by moving one or two relative vertical plates. When the first vertical plate 2 and the second vertical plate 3 are placed in the mud and then the distance between them is adjusted, the horizontal drain board 1 can be fixed at one of the first connection end and the second connection end, and the connection end of the first vertical plate 2 or the second vertical plate 3 to be dragged is not fixed to the horizontal drain board 1, or both the first connection end and the second connection end are not fixed to the horizontal drain board 1, but pass through the first connection end and the second connection end, drag the first vertical plate 2 and / or the second vertical plate 3 to the specified position, and the horizontal drain board 1 can move in the first connection end or the second connection end for adaptation, and connect the two ends of the horizontal drain board 1 to the vacuum pump for vacuum extraction.
[0033] In the above embodiment, a floating construction platform 5 may also be used. The floating construction platform 5 is connected to the first vertical plate 2 and / or the second vertical plate 3 to move the first vertical plate 2 and / or the second vertical plate 3 to a specified position. In this embodiment, the floating construction platform 5 and the connection point 7 at the upper end of the first vertical plate 2 or the second vertical plate 3 are connected by a connecting rope 6. Figure 1 and Figure 2 As shown, the first vertical plate 2 and the second vertical plate 3 are provided with a plurality of circular holes 8 of the same diameter, which reduce the resistance during the movement of the first vertical plate 2 or the second vertical plate 3, are conducive to the stability of the vertical plate, and improve the laying efficiency of the horizontal drainage board 1. Figure 5 As shown, the middle parts of the first vertical plate 2 and the second vertical plate 3 can also be arranged in a window shape, and the first vertical plate 2 and the second vertical plate 3 form a frame structure.
[0034] Reference Figure 8 and Fig. 9As shown, in the above embodiment, the first vertical plate 2 and the second vertical plate 3 are provided with a vertical drain plate channel 9 and a rolling assembly arranged on the side of the drain plate channel 9, and the rolling assembly includes a plurality of fixed pulleys 901 arranged in pairs, and the fixed pulleys 901 are installed on the inner side of the drain plate channel 9 through a fixing rod, and the wheel surface of the fixed pulley 901 can be high on both sides and low in the middle. After the drain plate passes through the arc interface 4, the two sides of the drain plate are restricted in the wheel surface of the fixed pulley 901, so that the drain plate is restricted in the drain plate channel 9 by the rolling assembly to avoid twisting when the drain plate moves relative to each other. The upper and lower sides of the drain plate channel 9 are both open structures, and the opening structure of the drain plate channel 9 is set in an arc shape. The arc setting at the outlet can avoid bending of the drain plate and affect the consolidation effect. The vacuum pumping device is placed on the shore, and the horizontal drain plate 1 extends from the upper outlet of the first vertical plate 2 and the second vertical plate 3 and is connected to the vacuum pump.
[0035] In the above embodiment, in order to adapt to the different depths of sludge treatment, it is necessary to arrange the horizontal drainage boards 1 corresponding to the different depths. Figure 1 and Figure 2 As shown, the first vertical plate 2 and the second vertical plate 3 can be provided with several, specifically, the first vertical plate 2 and the adjacent first vertical plate 2 are connected end to end by a detachable connection method, and the second vertical plate 3 and the adjacent second vertical plate 3 are connected end to end by a detachable connection method, and the detachable method includes drilling holes in the first vertical plate 2 and the second vertical plate 3, and connecting them with several bolts and gaskets. Through the above technical solution, the drainage plate channel 9 can remain unobstructed after the vertical plates are bolted, so that the horizontal drainage plate 1 can reach the specified depth and then extend outward. A positioning device can also be provided, including a GPS positioning system, and the GPS positioning system includes a GPS positioning module 10, a signal transmission module and an information receiving module. The GPS positioning module 10 is installed on the side of the first vertical plate 2 and / or the second vertical plate 3. Through the technical solution of this embodiment, according to the different laying depth requirements of the horizontal drainage board 1 of the sludge field, several vertical boards are vertically connected by bolts until they can meet the laying requirements of the specified depth. The floating construction platform 5 moves the first vertical board 2 or the second vertical board 3 horizontally to the specified position through the connecting rope 6. The first vertical board 2 and the second vertical board 3 can change their depths under the action of gravity. Therefore, the depth of the first vertical board 2 and the second vertical board 3 can be adjusted by controlling the length of the connecting rope 6. The GPS positioning module 10 can locate the position of the first vertical board 2 or the second vertical board 3, and transmit it to the receiving device through the information transmission module.
[0036] In the above embodiment, after the first vertical plate 2 and the second vertical plate 3 are moved, they are made vertical by their own weight, and the depth is adjusted by the connecting rope 6. Figure 1 and Figure 2As shown, connection points 7 can be set at the two corners and the middle of the upper ends of the first vertical plate 2 and the second vertical plate 3, and multiple connection ropes 6 are used. Several connection points 7 can also be set at the lower ends of the first vertical plate 2 and the second vertical plate 3, and the connection ropes 6 are used as positioning parts to control the first vertical plate 2 and the second vertical plate 3 relative to each other. Figure 3 and Figure 4 As shown, the positioning device may also include a positioning part for realizing the vertical setting of the first vertical plate 2 or the second vertical plate 3. The positioning part may be arranged on the floating construction platform 5, or a pile column may be pre-driven at a designated position as the positioning part. The positioning part includes a clamp 11 and a limit groove. The clamp 11 is clamped at the upper end of the first vertical plate 2 or the second vertical plate 3. The clamp 11 can drive the first vertical plate 2 or the second vertical plate 3 to move vertically downward. The edge of the first vertical plate 2 or the second vertical plate 3 is placed in the limit groove. The limit groove is longitudinally arranged in a limit block 12, and the limit block 12 can move vertically downward, so as to drive the first vertical plate 2 or the second vertical plate 3 to realize vertical setting. When adjusting the vertical degree, the clamp 11 can be used for clamping, and the limit groove moves downward to drive the first vertical plate 2 or the second vertical plate 3 to adjust to vertical. In cooperation with the GPS positioning module 10, the clamp 11 moves downward to a predetermined depth. The movement of the clamping member 11 and the limiting groove can be controlled by a hydraulic system or a cylinder.
[0037] In this embodiment, the distance between the first vertical plate 2 and the second vertical plate 3 is determined first, and the horizontal drain plate 1 is laid on the laying device and then placed in the mud as a whole. The mud provides resistance during the descent of the horizontal drain plate 1, which may cause the horizontal drain plate 1 between the first vertical plate 2 and the second vertical plate 3 to twist or form an arc, especially when the water content of the mud is relatively low. Figure 6 and Figure 7As shown, the first connection end and the second connection end are rotatably connected to the first vertical plate 2 and the second vertical plate 3, and the first connection end and the second connection end can realize that the horizontal drainage board 1 between the first connection end and the second connection end is in a horizontal state or flipped into a sideways state. Specifically, the lower sides of the first connection end and the second connection end are fixed on the rotating shaft 13, and the rotating shaft 13 passes through the sleeve on the first vertical plate 2 or the second vertical plate 3. The other end of the rotating shaft 13 is provided with a rotating part, and the rotating part can be a wing plate or a rod protruding outward. The lifting rod 14 is connected to the rotating part and drives the rotating shaft 13 to rotate by lifting, thereby driving the first connection end or the second connection end to flip into a sideways state. The thickness of the horizontal drainage board 1 is smaller than the width, and the silt resistance is much smaller after being sideways. When the laying device is put in place, the horizontal drainage board 1 in the sideways state is flipped over. In this embodiment, if the moisture content of the sludge is low, the flipping of the first connection end and the second connection end cannot drive the drainage board to completely flip or is in a twisted state. An improved solution is that a protective plate 15 is provided between the first connection end and the second connection end, and the horizontal drainage board 1 is arranged inside the protective plate. The two sides of the protective plate 15 are wedge-shaped, and a plurality of through holes 16 are provided on both sides of the protective plate.
[0038] The present invention also includes a method for laying a horizontal drainage board 1, comprising the following steps:
[0039] (1) Connect the horizontal drainage board 1 to the laying device;
[0040] (2) placing the laying device into the mud and moving it to the designated location;
[0041] (3) The first vertical plate 2 and the second vertical plate 3 are placed at a predetermined depth through the GPS positioning module 10 .
[0042] In the above step (1), the distance between the first vertical plate 2 and the second vertical plate 3 is fixed, such as connecting the first vertical plate 2 and the second vertical plate 3 through a protective plate or other support rods, and then moving the laying device as a whole to a specified position through the floating construction platform 5; in the above step (1), the horizontal drainage board 1 can also be connected to the first vertical plate 2 and the second vertical plate 3, and the distance between them can be adjusted by dragging one or both of the vertical plates.
[0043] The above description is only a preferred embodiment of the present invention and does not limit the present invention in any form. Although the present invention has been disclosed as a preferred embodiment as above, it is not used to limit the present invention. Any technical personnel in this field can make some changes or modify the technical contents disclosed above into equivalent embodiments without departing from the scope of the technical solution of the present invention. However, any brief modifications, equivalent changes and modifications made to the above embodiments based on the technical essence of the present invention without departing from the content of the technical solution of the present invention are still within the scope of the technical solution of the present invention.
Claims
1. A laying device for horizontal drainage boards treated by sludge vacuum preloading method, Features: The laying device connects one or several drain boards in the laying device according to the predetermined laying requirements of the horizontal drain boards and the laying device is placed as a whole in the mud. The laying device includes a first connecting end and a second connecting end arranged in pairs, and the horizontal drain boards are connected to or pass through the corresponding first connecting end and the second connecting end.
2. A device for laying horizontal drainage boards treated by sludge vacuum preloading method according to claim 1, Features: The laying device includes a first vertical plate and a second vertical plate, the first vertical plate and the second vertical plate are arranged opposite to each other, the first connecting end and the second connecting end are respectively arranged at positions opposite to each other of the first vertical plate and the second vertical plate, so that the horizontal drainage plate is arranged horizontally, one or more first vertical plates and the second vertical plates are provided, the first vertical plate and the adjacent first vertical plate are connected end to end by a detachable connection, and the second vertical plate and the adjacent second vertical plate are connected end to end by a detachable connection.
3. A laying device for horizontal drainage boards treated by sludge vacuum preloading method according to claim 1 or 2, Features: It also includes a floating construction platform, which is connected to the first vertical plate and / or the second vertical plate and can move the first vertical plate and / or the second vertical plate to a designated position.
4. A laying device for horizontal drainage boards treated by sludge vacuum preloading method according to claim 3, Features: The first vertical plate and the second vertical plate are provided with a vertical drainage plate channel and rolling components arranged on both sides of the drainage plate channel. The first connecting end and the second connecting end include an arc interface. The horizontal drainage plate passes through the arc interface and is restricted in the drainage plate channel by the rolling component.
5. The laying device of the horizontal drainage board treated by the sludge vacuum preloading method according to claim 3, Features: A plurality of circular holes are provided in the first vertical plate and the second vertical plate, or windows are provided in the middle of the first vertical plate and the second vertical plate to form a frame structure.
6. A device for laying horizontal drainage boards treated by sludge vacuum preloading method according to claim 5, Features: It also includes a positioning device, which includes a GPS positioning module arranged on the first vertical plate and the second vertical plate, and also includes a positioning part for realizing the vertical arrangement of the first vertical plate or the second vertical plate; the positioning part is arranged on the floating construction platform or preset at a designated position; The positioning portion includes a clamping member and a limiting groove, the clamping member is clamped at the upper end of the first vertical plate or the second vertical plate, the clamping member can drive the first vertical plate or the second vertical plate to move vertically downward, the edge of the first vertical plate or the second vertical plate is placed in the limiting groove, and the limiting groove can move vertically downward, in this way, the first vertical plate or the second vertical plate is driven to achieve a vertical setting; or The positioning portion includes a connecting rope connected to the first and second vertical plates, and the verticality of the first and second vertical plates is adjusted by the connecting rope.
7. The laying device of the horizontal drainage board treated by the sludge vacuum preloading method according to claim 5, Features: The first connection end and the second connection end are rotatably connected to the first vertical plate and the second vertical plate, and the first connection end and the second connection end can realize that the horizontal drainage board between the first connection end and the second connection end is in a horizontal state or flipped into a sideways state.
8. The device for laying horizontal drainage boards treated by sludge vacuum preloading method according to claim 7, Features: One side of the first connecting end and the second connecting end is fixed on the rotating shaft, and the rotating shaft passes through the sleeve on the first vertical plate or the second vertical plate. The other end of the rotating shaft is provided with a rotating part, and the lifting rod is connected to the rotating part and drives the rotating shaft to rotate by lifting.
9. A device for laying horizontal drainage boards treated by sludge vacuum preloading method according to claim 8, Features: A protection plate is provided between the first connection end and the second connection end, the horizontal drainage plate is arranged inside the protection plate, both sides of the protection plate are wedge-shaped, and a plurality of through holes are provided on both sides of the protection plate.
10. A method for laying a horizontal drainage board, using the laying device according to claim 3, Features: Connect the horizontal drain board to the laying device, and then place the laying device connected with the horizontal drain board into the silt as a whole or move the laying device to the designated position through a floating construction platform.