Elevator foundation pit structure and elevator foundation pit construction method

The prefabricated elevator foundation pit structure with adjustable support assemblies and columns addresses long construction periods and uneven foundations, enabling rapid, accurate, and cost-effective construction of elevator foundation pits.

CN119061903APending Publication Date: 2024-12-03HEBEI WEIZHU MUNICIPAL ENGINEERING CO LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202411482798.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-23
Publication Date
2024-12-03

AI Technical Summary

Technical Problem

Existing elevator foundation pit construction methods face challenges such as long construction periods, difficulty in adjusting prefabricated components for uneven foundations, and high construction costs due to the need for large lifting equipment and prolonged concrete curing times.

Method used

A prefabricated elevator foundation pit structure with a reinforced concrete raft plate and side vertical plate, featuring adjustable support assemblies and columns, allowing for precise leveling and vertical adjustment without curing delays, and incorporating waterproof and sealing features.

Benefits of technology

The solution enables rapid construction with high accuracy, reduced construction difficulty, and lower costs by allowing for immediate installation and adjustment of prefabricated components, ensuring quality and efficiency in elevator foundation pit construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119061903A_ABST
    Figure CN119061903A_ABST
Patent Text Reader

Abstract

According to the elevator foundation pit structure and the elevator foundation pit construction method, a prefabricated raft is supported through a supporting and adjusting assembly, a pouring cavity is formed between the bottom of the prefabricated raft and a foundation lime soil cushion layer, the prefabricated raft is installed firstly, and then a concrete cushion layer is poured; after the concrete cushion layer is poured, the maintenance period does not need to be waited, the next installation and adjustment of the prefabricated side vertical plates and the prefabricated stand columns are not affected, and the construction period is shortened. The levelness and height of the prefabricated raft can be adjusted through the supporting and adjusting assemblies, the perpendicularity and height of the prefabricated stand columns can be adjusted through combination of the stand column adjusting bolts and the adjusting plates, and the engineering quality of an elevator foundation pit is guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of building engineering, and in particular to an elevator foundation pit structure and an elevator foundation pit construction method. Background Art

[0002] A foundation pit needs to be set up at the bottom of the elevator. When constructing the elevator foundation pit, first excavate the foundation pit, level and compact the soil at the bottom of the foundation pit, then pour the concrete foundation cushion layer, and finally build a mold on the concrete foundation to cast the foundation pit bottom plate and the side walls of the foundation pit. In the actual construction process, after the concrete foundation cushion layer is poured, it needs to be cured for a long time (7-28 days). Only after reaching the designed structural strength can the mold be constructed above the concrete foundation for the next step of construction. Long-term concrete foundation maintenance prolongs the construction period and increases the difficulty of construction. In order to shorten the construction period, some sites will use prefabricated elevator foundation pits. In the prior art, prefabricated elevator foundation pits include split and integral foundation raft slab side wall plates; the integral elevator foundation pit requires large lifting equipment during installation, which is difficult to construct in narrow sections of roads such as residential areas. The concrete foundation cushion layer at the bottom of the bottom plate still needs to be poured and maintained, and the construction period is limited. The split elevator foundation pit generally adopts the method of prefabricating the foundation raft as a whole and prefabricating the side wall plate in sections. If the prefabricated foundation raft is installed on an uneven foundation, the bottom plate will be tilted and cannot be fine-tuned, which will affect the overall quality of the elevator foundation pit. In the patent with announcement number CN217325380U, a prefabricated foundation pit for elevator reconstruction is disclosed, including a bottom plate and multiple side plates. The bottom plate is the foundation raft. The overall prefabrication method is adopted. There are problems such as the bottom plate cannot be adjusted if the foundation is uneven after it is placed, the concrete foundation at the bottom of the bottom plate needs to be poured and maintained, and the construction period is long. In the patent with announcement number CN116607534A, a prefabricated foundation pit for installing an elevator in an existing building is disclosed, including: a prefabricated foundation pit bottom plate, a prefabricated double-sided composite wall, and the prefabricated double-sided composite wall is arranged on the prefabricated foundation pit bottom plate; there is also a problem that a concrete bottom plate cushion layer needs to be poured before the prefabricated foundation pit bottom plate is placed, and the prefabricated foundation pit bottom plate cannot be fine-tuned in terms of inclination. Summary of the invention

[0003] In order to solve the above technical problems, the present invention provides an elevator foundation pit structure and an elevator foundation pit construction method, which have the advantages of short construction period, low construction difficulty, high foundation pit levelness control accuracy, convenient transportation and low construction cost.

[0004] The present invention adopts the following technical solution: An elevator foundation pit structure, comprising a foundation soil cushion layer, a concrete cushion layer, a prefabricated raft plate, and a prefabricated side vertical plate distributed from bottom to top, wherein the prefabricated raft plate and the prefabricated side vertical plate are both reinforced concrete structures, and are characterized in that: the prefabricated raft plate is square, comprising a square raft plate platform protruding in the middle and a raft plate slot frame sunken at the outer periphery, a vertical retaining edge is formed between the raft plate slot frame and the raft plate platform, a casting hole is provided at the center of the raft plate platform, horizontal adjustment holes are provided at the middle positions of the four sides of the raft plate slot frame, embedded column mounting seats are provided at the four corners of the raft plate slot frame, a support adjustment assembly is installed in the horizontal adjustment hole, a prefabricated column is installed above the embedded column mounting seat, and prefabricated columns are installed between the prefabricated columns above the raft plate slot frame. side plate; the support adjustment assembly includes a nut seat, a support screw and a steel pad, the steel pad is located above the foundation soil cushion layer, the nut seat is fixedly embedded in the bottom of the horizontal adjustment hole, the center of the nut seat is a threaded hole, the support screw passes through the threaded hole and is threadedly connected to the nut seat, the upper end of the support screw is located in the horizontal adjustment hole, and the bottom end passes through the bottom surface of the raft plate slot frame and then rests on the upper surface of the steel pad; the upper end of the support screw is a square head for easy twisting with a wrench, and a sealing steel groove is provided on the connecting surface of the prefabricated column and the prefabricated side plate, both ends of the prefabricated side plate are embedded in the sealing steel groove, the gap between the sealing steel groove and the prefabricated side plate is filled with sealing material, and the gap between the bottom surface of the prefabricated side plate and the raft plate slot frame is filled with sealant.

[0005] Furthermore, a plurality of exhaust holes are provided around the casting hole of the raft platform.

[0006] Furthermore, a waterproof groove is provided on the outer facade of the prefabricated raft slab.

[0007] Furthermore, the sealing material between the sealing steel trough and the prefabricated side panels is foamed rubber or concrete, and a sealing rubber strip is provided on the outer side of the sealing steel trough.

[0008] Furthermore, the outer side surfaces of the prefabricated raft and the prefabricated side panels are provided with waterproof cloth, which extends upward from the waterproof groove on the outer side surface of the prefabricated raft to cover the outer side surface and the upper end surface of the prefabricated side panels.

[0009] Furthermore, a column adjustment bolt is provided above the embedded column mounting seat, an adjustment plate supported by steel bars is provided at the bottom of the prefabricated column, the adjustment plate is provided with bolt holes corresponding to the positions of the column adjustment bolts, the column adjustment bolts are fixed with nuts after being inserted into the bolt holes, and the verticality of the prefabricated column can be adjusted by adjusting the height of the nuts.

[0010] Furthermore, a column cushion layer is provided between the prefabricated column and the embedded column mounting seat.

[0011] The present invention further provides an elevator foundation pit construction method, based on the above elevator foundation pit structure, comprising the following steps: Step 1: making prefabricated raft slabs, prefabricated side panels, prefabricated columns, and support adjustment components; Step 2: excavate the foundation pit, reinforce the side of the foundation pit, fill the surface of the foundation at the bottom of the foundation pit with gray soil, level and compact it, and form a foundation gray soil cushion layer; Step 3: Arrange a steel pad on the foundation soil cushion layer, and adjust the position of the steel pad to correspond to the position of the horizontal adjustment hole on the prefabricated raft; Step 4: hoist the prefabricated raft slab so that the supporting screw rods are against the upper surface of the steel pad, and use the wrench in the hole to rotate the supporting screw rods so that the distance between the prefabricated raft slab and the pit bottom foundation reaches the pouring height requirement of the concrete cushion layer, forming a pouring cavity, and keeping the prefabricated raft slab level at the same time; Step 5: pouring concrete into the pouring cavity at the bottom of the prefabricated raft slab through the pouring holes to form a concrete cushion layer; Step 6: Hoist the prefabricated column, insert the column adjustment bolt into the bolt hole on the adjustment plate and fix it with a nut, adjust the nut height, and then adjust the verticality and height of the prefabricated column to reserve a gap for on-site casting between the prefabricated column and the embedded column mounting seat; Step 7: hoist the prefabricated side panels, embed the two ends of the prefabricated side panels into the sealed steel grooves of the prefabricated columns, and fill the space between the bottom surface of the prefabricated side panels and the raft groove frame with sealant; Step 8: pour concrete in the on-site casting gap at the bottom of the prefabricated column to form a column cushion; Step 9: Fill the gap between the sealing steel channel of the prefabricated column and the prefabricated side plate with concrete or sealant; Step 10: Lay the waterproof cloth, which extends upward from the waterproof groove on the outer side of the prefabricated raft slab to cover the outer side and upper end of the prefabricated side slab; Step 11: Backfill the foundation pit. Use fine sand to backfill the gaps in the foundation pit outside the prefabricated raft slab and prefabricated side slabs, and cover with water and compact it to complete the elevator foundation pit structure.

[0012] Furthermore, after the prefabricated column is adjusted into place in step six, the adjustment plate is fixedly connected with the nut on the column adjustment bolt.

[0013] The present invention supports the prefabricated raft plate by using a support adjustment assembly, forms a casting cavity between the bottom of the prefabricated raft plate and the foundation soil cushion layer, installs the prefabricated raft plate first and then casts the concrete cushion layer, and after casting the concrete cushion layer, there is no need to wait for a curing period and does not affect the installation and adjustment of the prefabricated side panels and prefabricated columns in the next step, thereby shortening the construction period. The present invention can adjust the horizontality and height of the prefabricated raft plate by using a support adjustment assembly, and can adjust the verticality and height of the prefabricated columns by using a combination of column adjustment bolts and adjustment plates, thereby ensuring the engineering quality of the elevator foundation pit. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] Figure 1 It is a structural schematic diagram of the present invention; Figure 2It is a schematic diagram of the top view of the prefabricated raft structure of the present invention; Figure 3 It is a schematic diagram of the connection between the prefabricated side panels and the prefabricated columns of the present invention; Figure 4 It is a schematic diagram of the connection between the bottom of the prefabricated side vertical plate and the raft plate channel frame of the present invention.

[0015] The corresponding parts names in the figure are: 1 foundation soil cushion layer; 2 concrete cushion layer; 3 prefabricated raft slab; 4 prefabricated side vertical plate; 5 raft slab channel frame; 6 retaining edge; 7 casting hole; 8 horizontal adjustment hole; 9 embedded column mounting seat; 10 prefabricated column; 11 nut seat; 12 supporting screw rod; 13 steel pad; 14 sealing steel trough; 15 sealing material; 16 exhaust hole; 17 waterproof groove; 18 sealing rubber strip; 19 column adjustment bolt; 20 adjustment plate; 21 column cushion layer; 22 sealant; 23 waterproof cloth.

[0016] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the accompanying drawings.

[0017] Example: See Figure 1-4As shown, the present invention provides an elevator foundation pit structure, including a foundation soil cushion layer 1, a concrete cushion layer 2, a prefabricated raft 3, and a prefabricated side vertical plate 4 distributed from bottom to top, wherein the prefabricated raft and the prefabricated side vertical plate are both reinforced concrete structures, the prefabricated raft is square, including a square raft platform protruding in the middle and a raft trough frame 5 sunken at the outer periphery, a vertical retaining edge 6 is formed between the raft trough frame and the raft platform, a casting hole 7 is provided in the center of the raft platform, a horizontal adjustment hole 8 is provided in the middle of the four sides of the raft trough frame, and pre-buried column mounting seats 9 are provided at the four corners of the raft trough frame, a support adjustment component is installed in the horizontal adjustment hole, a prefabricated column 10 is installed above the pre-buried column mounting seat, and the prefabricated side vertical plates 4 are installed between the prefabricated columns above the raft trough frame. The support adjustment assembly includes a nut seat 11, a support screw rod 12, and a steel pad 13. The steel pad 13 is located above the foundation soil cushion layer 1. The nut seat 11 is fixedly embedded in the bottom of the horizontal adjustment hole 8. The center of the nut seat is a threaded hole. The support screw rod 12 passes through the threaded hole and is threadedly connected to the nut seat. The upper end of the support screw rod is located in the horizontal adjustment hole, and the lower end passes through the bottom surface of the raft groove frame and abuts against the upper surface of the steel pad 13. The upper end of the support screw rod is a square head that is convenient for the wrench to twist. The connection surface between the prefabricated column and the prefabricated side vertical plate is provided with a sealing steel groove 14. The two ends of the prefabricated side vertical plate are embedded in the sealing steel groove. The gap between the sealing steel groove and the prefabricated side vertical plate is filled with sealing material 15, and the gap between the bottom surface of the prefabricated side vertical plate and the raft groove frame is filled with sealant 22. A plurality of exhaust holes 16 are provided on the periphery of the casting hole of the raft platform. A waterproof groove 17 is provided on the outer facade of the prefabricated raft. The sealing material 15 between the sealing steel trough and the prefabricated side vertical plate is foamed rubber or concrete, and a sealing rubber strip 18 is provided on the outer side of the sealing steel trough. The outer side surfaces of the prefabricated raft and the prefabricated side vertical plate are provided with a waterproof cloth 23, which extends upward from the waterproof groove on the outer vertical surface of the prefabricated raft to cover the outer vertical surface and the upper end surface of the prefabricated side vertical plate. A column adjustment bolt 19 is provided above the embedded column mounting seat, and an adjustment plate 20 supported by steel bars is provided at the bottom of the prefabricated column. The adjustment plate is provided with a bolt hole corresponding to the position of the column adjustment bolt. The column adjustment bolt is inserted into the bolt hole and fixed with a nut. The verticality of the prefabricated column can be adjusted by adjusting the height of the nut. A column cushion layer 21 is provided between the prefabricated column and the embedded column mounting seat.

[0018] The elevator foundation pit construction method of the present invention is as follows: based on the above elevator foundation pit structure, it includes the following steps: Step 1: Prefabricate the raft 3, prefabricate the side panels 4, prefabricate the columns 10, and support adjustment components; during the prefabrication of the raft, make the vent holes 16 and the casting holes, and pre-embed the pre-embedded column mounting seat 9 and the nut seat 11 in place. When prefabricate the columns, connect and fix the adjustment plate 20 to the steel bar frame inside the prefabricated columns.

[0019] Step 2: excavate a foundation pit, reinforce the side of the foundation pit, fill the surface of the foundation at the bottom of the foundation pit with ash soil, level it and compact it to form a foundation ash soil cushion layer 1; Step 3: Arrange a steel pad 13 above the foundation soil cushion layer, and adjust the position of the steel pad to make it correspond to the position of the horizontal adjustment hole 8 on the prefabricated raft; Step 4: hoist the prefabricated raft 3. Before hoisting, install the support screw 12 on the nut seat 11. During hoisting, make the support screw against the upper surface of the steel pad 13. Use the wrench in the hole to rotate the support screw 12 so that the distance between the prefabricated raft and the pit bottom foundation reaches the casting height requirement of the concrete cushion layer, forming a casting cavity and keeping the prefabricated raft level at the same time. Step 5: pouring concrete into the pouring cavity at the bottom of the prefabricated raft 3 through the pouring holes 7 to form a concrete cushion layer 2; Step six, hoist the prefabricated column 10, insert the column adjustment bolt 19 into the bolt hole on the adjustment plate 20 and fix it with a nut, adjust the nut height, and then adjust the verticality and height of the prefabricated column, so that a gap for on-site casting is reserved between the prefabricated column and the embedded column mounting seat; after the prefabricated column is adjusted into place, fix the adjustment plate and the nut on the column adjustment bolt, and the fixing method can be welding connection.

[0020] Step 7: hoist the prefabricated side panels 4, embed the two ends of the prefabricated side panels 4 into the sealing steel grooves 14 of the prefabricated columns, and fill the space between the bottom surface of the prefabricated side panels and the raft groove frame with sealant; Step 8: pour concrete in the on-site casting gap at the bottom of the prefabricated column to form a column cushion; Step 9: Fill the gap between the sealing steel channel of the prefabricated column and the prefabricated side plate with concrete or sealant; Step 10: Lay the waterproof cloth, which extends upward from the waterproof groove on the outer side of the prefabricated raft slab to cover the outer side and upper end of the prefabricated side slab; Step 11: Backfill the foundation pit. Use fine sand to backfill the gaps in the foundation pit outside the prefabricated raft slab and prefabricated side slabs, and cover with water and compact it to complete the elevator foundation pit structure.

[0021] The present invention supports the prefabricated raft 3 by using a support adjustment assembly, forms a casting cavity between the bottom of the prefabricated raft and the foundation soil cushion layer, first installs the prefabricated raft 3 and then casts the concrete cushion layer 2. After casting the concrete cushion layer, there is no need to wait for the curing period and does not affect the installation and adjustment of the prefabricated side panels and prefabricated columns in the next step, thus shortening the construction period. The present invention can adjust the horizontality and height of the prefabricated raft by using a support adjustment assembly, and can adjust the verticality and height of the prefabricated columns by using a combination of column adjustment bolts and adjustment plates, thus ensuring the engineering quality of the elevator foundation pit.

[0022] The above is only the best embodiment of the present invention and does not limit the present invention in any form. Any technician familiar with the field can make many possible changes and modifications to the technical solution of the present invention by using the method disclosed above without departing from the scope of the technical solution of the present invention, which all fall within the scope of protection of the claims.

Claims

1. An elevator foundation pit structure, comprising a foundation soil cushion layer, a concrete cushion layer, a prefabricated raft plate, and a prefabricated side plate distributed from bottom to top, wherein the prefabricated raft plate and the prefabricated side plate are both steel concrete structures, characterized in that: The prefabricated raft is square, including a square raft platform protruding in the middle and a raft trough frame sunken at the outer periphery, a vertical retaining edge is formed between the raft trough frame and the raft platform, a casting hole is provided in the center of the raft platform, horizontal adjustment holes are provided in the middle positions of the four sides of the raft trough frame, and embedded column mounting seats are provided at the four corners of the raft trough frame, a support adjustment assembly is installed in the horizontal adjustment hole, a prefabricated column is installed above the embedded column mounting seat, and a prefabricated side plate is installed between the prefabricated columns above the raft trough frame; the support adjustment assembly includes a nut seat, a support screw rod, and a steel pad, and the steel pad Located above the foundation ash soil cushion layer, the nut seat is fixedly embedded in the bottom of the horizontal adjustment hole, the center of the nut seat is a threaded hole, the support screw rod passes through the threaded hole and is threadedly connected to the nut seat, the upper end of the support screw rod is located in the horizontal adjustment hole, and the bottom end passes through the bottom surface of the raft slab groove frame and rests on the upper surface of the steel pad; the upper end of the support screw rod is a square head for easy wrench turning, and the connecting surface of the prefabricated column and the prefabricated side vertical plate is provided with a sealing steel groove, both ends of the prefabricated side vertical plate are embedded in the sealing steel groove, the gap between the sealing steel groove and the prefabricated side vertical plate is filled with sealing material, and the gap between the bottom surface of the prefabricated side vertical plate and the raft slab groove frame is filled with sealant.

2. An elevator foundation pit structure according to claim 1, characterized in that: A plurality of exhaust holes are arranged on the periphery of the casting hole of the raft platform.

3. An elevator foundation pit structure according to claim 1, characterized in that: The outer facade of the prefabricated raft is provided with a waterproof groove.

4. The elevator foundation pit structure according to claim 1, characterized in that: The sealing material between the sealing steel trough and the prefabricated side vertical plate is foamed rubber or concrete, and a sealing rubber strip is arranged on the outer side of the sealing steel trough.

5. An elevator foundation pit structure according to claim 4, characterized in that: The outer sides of the prefabricated raft and the prefabricated side panels are provided with waterproof cloths, which extend upward from the waterproof grooves on the outer side panels of the prefabricated raft to cover the outer side panels and the upper end surfaces of the prefabricated side panels.

6. The elevator foundation pit structure according to claim 1, characterized in that: A column adjustment bolt is provided above the embedded column mounting seat, an adjustment plate supported by steel bars is provided at the bottom of the prefabricated column, bolt holes corresponding to the positions of the column adjustment bolts are provided on the adjustment plate, and the column adjustment bolts are fixed with nuts after being inserted into the bolt holes, and the verticality of the prefabricated column can be adjusted by adjusting the height of the nuts.

7. The elevator foundation pit structure according to claim 1, characterized in that: A column cushion layer is provided between the prefabricated column and the embedded column mounting seat.

8. An elevator foundation pit construction method, characterized in that: The elevator foundation pit structure according to any one of claims 1 to 7 comprises the following steps: Step 1: making prefabricated raft slabs, prefabricated side panels, prefabricated columns, and support adjustment components; Step 2: excavate the foundation pit, reinforce the side of the foundation pit, fill the surface of the foundation at the bottom of the foundation pit with gray soil, level and compact it, and form a foundation gray soil cushion layer; Step 3: Arrange a steel pad on the foundation soil cushion layer, and adjust the position of the steel pad to correspond to the position of the horizontal adjustment hole on the prefabricated raft; Step 4: hoist the prefabricated raft slab so that the supporting screw rods are against the upper surface of the steel pad, and use the wrench in the hole to rotate the supporting screw rods so that the distance between the prefabricated raft slab and the pit bottom foundation reaches the pouring height requirement of the concrete cushion layer, forming a pouring cavity, and keeping the prefabricated raft slab level at the same time; Step 5: pouring concrete into the pouring cavity at the bottom of the prefabricated raft slab through the pouring holes to form a concrete cushion layer; Step 6: Hoist the prefabricated column, insert the column adjustment bolt into the bolt hole on the adjustment plate and fix it with a nut, adjust the nut height, and then adjust the verticality and height of the prefabricated column to reserve a gap for on-site casting between the prefabricated column and the embedded column mounting seat; Step 7: hoist the prefabricated side panels, embed the two ends of the prefabricated side panels into the sealed steel grooves of the prefabricated columns, and fill the space between the bottom surface of the prefabricated side panels and the raft groove frame with sealant; Step 8: pour concrete in the on-site casting gap at the bottom of the prefabricated column to form a column cushion; Step 9: Fill the gap between the sealing steel channel of the prefabricated column and the prefabricated side plate with concrete or sealant; Step 10: Lay the waterproof cloth, which extends upward from the waterproof groove on the outer side of the prefabricated raft slab to cover the outer side and upper end of the prefabricated side slab; Step 11: Backfill the foundation pit. Use fine sand to backfill the gaps in the foundation pit outside the prefabricated raft slab and prefabricated side slabs, and cover with water and compact it to complete the elevator foundation pit structure.

9. An elevator foundation pit construction method according to claim 8, characterized in that: After the prefabricated column is adjusted into place in step six, the adjustment plate is fixedly connected with the nut on the column adjustment bolt.

Citation Information

Patent Citations

  • Assembling type prefabricated foundation pit for adding elevator to existing building

    CN116607534A

  • Prefabricated foundation pit for elevator transformation

    CN217325380U