Molding construction method of wind power cooling oil well
By using an adjustable water stop plate installer and a retractable inclined support rod structure in the steel bar body of the wind power cooling oil well, the problem of inconvenience of up and down adjustment of the water stop plate during construction is solved, and the waterproofness of layered casting is improved and construction efficiency.
Patent Information
- Application Number
- CN202411085563.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-08
- Publication Date
- 2024-12-03
AI Technical Summary
In the prior art, the water stop plate is welded and fixed with the steel bar body, which makes it difficult to adjust up and down during construction, affecting the waterproofness of layered casting.
Adopting an adjustable water stop plate installer and retractable oblique support rod structure, the up and down adjustment of the water stop plate is achieved through hook hangings and bolts, and multi-point contact support is provided through oblique support rods and force-partition rods to ensure water stop. The stable position of the plate in the steel bar body.
It realizes flexible up and down adjustment of the water stop plate during the construction process, solves the problem of inconvenience in fixing the water stop plate, and improves the waterproofness and construction efficiency of layered casting.
Smart Images

Figure CN119062113A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a forming construction method for a wind power cooling oil well, belonging to the technical field of wind power construction. Background Art
[0002] Wind power booster stations need to be equipped with cooling oil wells to hold the cooling oil of the booster. When constructing the cooling oil wells, the steel bars must be tied up first and then poured in layers.
[0003] In order to ensure the waterproofness of the layered casting joint surface, a water stop plate needs to be installed in the steel body. When the water stop plate is installed in the steel body, the position of the water stop plate needs to be ensured. The prior art is that the water stop plate is welded and fixed to the steel body by tie bars (see Chinese patent publication number CN216586661U). Although the position of the water stop plate in the steel body can be stabilized, it is not convenient to adjust the water stop plate up and down during the construction process. Summary of the invention
[0004] In order to solve the above technical problems, the present invention provides a forming construction method for a wind power cooling oil well.
[0005] The present invention is achieved through the following technical solutions.
[0006] The present invention provides a wind power cooling oil well forming construction method, comprising:
[0007] A foundation pit is excavated downwards from the ground, a steel bar body is bundled in the foundation pit, and a water stop plate is installed in the steel bar body with an adjustable position by a water stop plate installer, thus forming a construction process of a steel bar installation structure for a wind power cooling oil well.
[0008] The steel bar body is composed of vertical bars and longitudinal bars, and the longitudinal bars are tied and fixed to surround the vertical bars.
[0009] The construction process also includes: a retractable and adjustable inclined support rod is installed on the side of the steel bar body with a water stop plate, and the inclined support rod is supported by contacting the side of the foundation pit foundation; a load-bearing plate is welded and fixed on the top of the inclined support rod, and a pin is welded and fixed on the load-bearing plate. The pin is inserted between the longitudinal reinforcements for limiting the position, so that the load-bearing plate is in contact with the vertical reinforcement and the longitudinal reinforcement at multiple points.
[0010] The oblique support rod is installed with a force component rod, and the force component rod is supported obliquely upward by contacting the bottom surface of the foundation pit foundation and receiving force.
[0011] The construction process also includes: after the steel bar body is stably supported by the inclined support rods and the formwork is erected, the lower layer of the wind power cooling oil well and the lower layer of the wind power cooling oil well are cast in layers. When the lower layer of the wind power cooling oil well is formed, the steel bar body and the water stop plate can be limited and supported. At this time, the water stop plate installer, the inclined support rods, etc. are removed, and then the lower layer of the wind power cooling oil well is cast. The water stop plate is located between the lower layer of the wind power cooling oil well and the connecting surface of the lower layer of the wind power cooling oil well for water stopping; the lower layer of the wind power cooling oil well and the lower layer of the wind power cooling oil well are connected internally by the steel bar body.
[0012] The water stop plate installer includes a hook body A hooked on the longitudinal reinforcement; a hook body B fixed on the hook body A by adjustable screwing through bolts. After the upper part of the hook body A is hooked on the longitudinal reinforcement, the upper part of the hook body B is screwed through the bolts, and the lower part of the hook body A and the lower part of the hook body B are pressed tightly to lift the water stop plate.
[0013] The beneficial effects of the present invention are that when the hook body A and the lower part of the hook body B are separated to produce a gap, the water stop plate can be adjusted up and down, so that the water stop plate can be installed in the steel body with an adjustable position through the water stop plate installer, which solves the problem that the water stop plate is welded and fixed to the steel body by tie bars, which makes it inconvenient to adjust the water stop plate up and down during construction. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 It is a schematic diagram of the structure of the steel bar body of the present invention in the foundation pit;
[0015] Figure 2 It is a schematic diagram of the structure when the steel bar body of the present invention is in contact with the oblique support rod support;
[0016] Figure 3 It is a schematic diagram of the distribution of the water stop plate, the water stop plate installer, and the steel bar body of the present invention;
[0017] Figure 4 It is a schematic diagram of the distribution of the water stop plate, the lower layer of the wind power cooling oil well, and the lower layer of the wind power cooling oil well of the present invention;
[0018] In the figure: 1- foundation pit; 2- reinforcement body; 21- vertical reinforcement; 22- longitudinal reinforcement; 3- water stop plate;
[0019] 4-water stop plate installer; 41-hook body A; 42-hook body B; 43-bolt;
[0020] 5- oblique support rod; 51- sleeve; 52- threaded rod; 53- adjustment plate; 54- force-bearing rotating ear;
[0021] 61- load-bearing plate; 62- pin; 63- force-dividing rod; 71- wind power cooling the lower layer of the oil well; 72- wind power cooling the lower layer of the oil well. DETAILED DESCRIPTION
[0022] The technical solution of the present invention is further described below, but the scope of protection claimed is not limited to the description.
[0023] like Figures 1 to 4 shown.
[0024] A forming construction method of a wind power cooling oil well in the present application includes:
[0025] A foundation pit 1 is excavated downwards from the ground, vertical reinforcements 21 and longitudinal reinforcements 22 are constructed in the foundation pit 1, and the longitudinal reinforcements 22 are bundled and fixedly enclosed on the vertical reinforcements 21 to form a reinforcement body 2. A water stop plate 3 is installed in the reinforcement body 2, and the water stop plate 3 is installed in the reinforcement body 2 with an adjustable position by a water stop plate installer 4, thereby forming a reinforcement installation structure for a wind power cooling oil well.
[0026] The side of the steel bar body 2 with the water stop plate 3 is installed with a telescopically adjustable oblique support rod 5, which is supported by the side contact of the foundation pit foundation 1; a force plate 61 is welded and fixed on the top of the oblique support rod 5, and a pin 62 is welded and fixed on the force plate 61. The pin 62 is inserted between the longitudinal bars 22 for limiting, so that the force plate 61 contacts the vertical bars 21 and the longitudinal bars 22 at multiple points, forming a force system supporting the wind power cooling oil well steel bar body. The oblique support rod 5 is installed with a force dividing rod 63, which is supported by the bottom surface of the foundation pit foundation 1 and is supported obliquely upward.
[0027] After the steel bar body 2 is stably supported by the inclined support rod 5 and the formwork is erected, the wind power cooling oil well lower layer 71 and the wind power cooling oil well lower layer 72 are cast in layers. When the wind power cooling oil well lower layer 71 is formed, the steel bar body 2 and the water stop plate 3 can be limited and supported. At this time, the water stop plate installer 4, the inclined support rod 5, etc. are removed, and then the wind power cooling oil well lower layer 72 is cast. The water stop plate 3 is located between the joint surfaces of the wind power cooling oil well lower layer 71 and the wind power cooling oil well lower layer 72 for water stopping; the wind power cooling oil well lower layer 71 and the wind power cooling oil well lower layer 72 are connected internally by the steel bar body 2.
[0028] A steel bar installation structure for a wind power cooling oil well of the present application includes:
[0029] The steel bar body 2 is composed of vertical bars 21 and longitudinal bars 22 surrounding the vertical bars 21 , and the steel bar body 2 is located in the foundation 1 ; the longitudinal bars 22 are tied and fixed to the vertical bars 21 .
[0030] The water stop plate 3 is installed in the steel bar body 2 , and the water stop plate 3 can be installed in the steel bar body 2 in an adjustable position through a water stop plate installer 4 .
[0031] The waterstop plate installer 4 includes a hook body A41 hooked on the longitudinal reinforcement 22; a hook body B42 adjustably screwed and fixed on the hook body A41 by a bolt 43, after the upper part of the hook body A41 is hooked on the longitudinal reinforcement 22, the upper part of the hook body B42 is screwed by the bolt 43, the lower part of the hook body A41 and the lower part of the hook body B42 are pressed and lifted up the waterstop plate 3, and when the hook body A41 and the lower part of the hook body B42 are separated to produce a gap, the waterstop plate 3 can be adjusted up and down, so that the waterstop plate 3 can be installed in the steel bar body 2 by the waterstop plate installer 4 with an adjustable position, which solves the problem that the waterstop plate is fixed to the steel bar body by welding through the tie bar, and it is inconvenient to adjust the waterstop plate up and down during construction.
[0032] A force bearing system for supporting a steel bar body of a wind power cooling oil well of the present application comprises:
[0033] The steel bar body 2 in the foundation pit 1 is composed of vertical bars 21 and longitudinal bars 22 surrounding the vertical bars 21 ; the longitudinal bars 22 are tied and fixed to the vertical bars 21 .
[0034] The oblique support rod 5 contacts the side surface of the foundation pit 1 , and a force plate 61 is fixed on the top of the retractable oblique support rod 5 . The force plate 61 contacts the vertical bars 21 and the longitudinal bars 22 of the steel bar body 2 at multiple points.
[0035] The inclined support rod 5 is extended and retracted so that its bottom contacts the side of the foundation pit 1, and the top of the inclined support rod 5 contacts the vertical bars 21 and the longitudinal bars 22 of the steel bar body 2 at multiple points through the load-bearing plate 61, avoiding the problem of direct single-point contact support at the top of the inclined support rod 5, which may easily cause deformation of a single steel bar at the contact point.
[0036] The stress-bearing plate 61 is welded with a plurality of pins 62 which are fixedly distributed on the stress-bearing plate 61 at intervals. The pins 62 are inserted between the longitudinal bars 22 , and the bottom edges of the longitudinal bars 22 and the sides of the vertical bars 21 are in contact with the pins 62 for positioning.
[0037] The bottom surface of the foundation pit foundation 1 is provided with a force component rod 63 inclined upward, the top of the force component rod 63 is bound and fixedly connected with the oblique support rod 5, and the force component rod 63 supports the weight load component of the oblique support rod 5.
[0038] The oblique support rod 5 comprises a sleeve 51 with a hollow interior, a threaded rod 52 sleeved in the sleeve 51, the threaded rod 52 extends into the sleeve 51, an adjustment plate 53 is screwed on the threaded rod 52 through a thread pair, and the adjustment plate 53 is screwed on the threaded rod 52 to abut against the sleeve 51. After adjusting the distance between the sleeve 51 and the threaded rod 52, the adjustment plate 53 is screwed on the threaded rod 52 so that the sleeve 51 abuts against the adjustment plate 53, thereby realizing the telescopicity of the oblique support rod 5.
[0039] The side of the adjustment plate 53 is provided with symmetrically distributed force-bearing rotating ears 54 , so as to facilitate the adjustment plate 53 to be rotated by the force received by the rotating ears 54 .
Claims
1. A forming construction method for a wind power cooling oil well, characterized in that: include: A foundation pit (1) is excavated downwards from the ground, a steel bar body (2) is bundled in the foundation pit (1), and a water stop plate (3) is installed in the steel bar body (2) in an adjustable position by means of a water stop plate installer (4), thereby forming a construction process of a steel bar installation structure for a wind power cooling oil well.
2. The forming construction method of the wind power cooling oil well according to claim 1, characterized in that: The steel bar body (2) is composed of vertical bars (21) and longitudinal bars (22), and the longitudinal bars (22) are tied and fixed to surround the vertical bars (21).
3. The forming construction method of the wind power cooling oil well according to claim 1, characterized in that: The construction process also includes: a retractable and adjustable oblique support rod (5) is installed on the side of the steel bar body (2) installed with the water stop plate (3), and the oblique support rod (5) is supported by the side contact of the foundation pit foundation (1); a load-bearing plate (61) is welded and fixed on the top of the oblique support rod (5), and a plug pin (62) is welded and fixed on the load-bearing plate (61), and the plug pin (62) is inserted between the longitudinal bars (22) for limiting, so that the load-bearing plate (61) contacts the vertical bars (21) and the longitudinal bars (22) at multiple points.
4. The forming construction method of the wind power cooling oil well according to claim 3, characterized in that: The oblique support rod (5) is installed with a force component rod (63), and the force component rod (63) is supported obliquely upward by contacting the bottom surface of the foundation pit foundation (1) to receive force.
5. The forming construction method of the wind power cooling oil well according to claim 1, characterized in that: The construction process also includes: after the steel bar body (2) is stably supported by the oblique support rod (5), a formwork is set up, and the wind power cooling oil well lower layer (71) and the wind power cooling oil well lower layer (72) are cast in layers. When the wind power cooling oil well lower layer (71) is formed, the steel bar body (2) and the water stop plate (3) can be limited and supported. At this time, the water stop plate installer (4), the oblique support rod (5), etc. are removed, and then the wind power cooling oil well lower layer (72) is cast. The water stop plate (3) is located between the connection surfaces of the wind power cooling oil well lower layer (71) and the wind power cooling oil well lower layer (72) to stop water; the wind power cooling oil well lower layer (71) and the wind power cooling oil well lower layer (72) are connected internally by the steel bar body (2).
6. The forming construction method of the wind power cooling oil well according to claim 1, characterized in that: The water stop plate installer (4) comprises a hook body A (41) hooked on the longitudinal reinforcement (22); a hook body B (42) adjustable and screwed to the hook body A (41) by means of a bolt (43); after the upper part of the hook body A (41) is hooked on the longitudinal reinforcement (22), the upper part of the hook body B (42) is screwed together by means of the bolt (43), and the lower part of the hook body A (41) and the lower part of the hook body B (42) are pressed tightly to lift the water stop plate (3).