Building construction feedback system based on field real-time monitoring
By dividing areas at the construction site and monitoring in real time, calculating the risk assessment value and differential assessment value, adjusting the monitoring level and layout methods, the problem of low monitoring accuracy on the construction site is solved, and the safety and management efficiency of the construction site are improved.
Patent Information
- Application Number
- CN202411045085.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-01
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2044-08-01
AI Technical Summary
The existing building construction monitoring system has low monitoring accuracy for project construction personnel and cannot guarantee the safety of the construction site.
采用基于现场实时监控的建筑施工反馈系统,通过区域划分单元将施工现场划分为不同等级的区域,监控单元实时采集数据,中心控制单元计算风险评价值和差异评价值,调整监控等级和布控方式,确保监控精准度和安全性。
The monitoring accuracy of project construction personnel has been improved, the safety and management efficiency of the construction site have been ensured, and precise monitoring and safety training of the construction site have been evaluated and adjusted through area division and risk assessment value calculation.
Smart Images

Figure BDA0004973287240000021 
Figure BDA0004973287240000061 
Figure FDA0004973287230000011
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of building construction monitoring, and in particular to a building construction feedback system based on on-site real-time monitoring. Background Art
[0002] In recent years, with the increase in super-high-rise buildings and large-scale urban complex projects, these projects have complex functions, high technical requirements, long time spans, and many participating units, which puts higher requirements on the coordination and management of the construction site. The traditional way of feedback on construction quality can no longer meet the current needs. Therefore, the use of real-time monitoring and intelligent positioning feedback systems has become a trend. Through equipment such as sensors and cameras, various data on the construction site, such as temperature, humidity, pressure, etc., can be obtained in real time, and the location of construction personnel can be tracked to improve the safety and efficiency of the construction site. In addition, using big data and artificial intelligence technology, the collected data can be analyzed and processed to achieve comprehensive monitoring and management of the construction process. In short, the construction feedback system based on real-time on-site monitoring integrates advanced sensing technology and intelligent analysis algorithms to achieve all-round, real-time monitoring and data management of the construction site, thereby improving the construction quality and management level, and ensuring the safety and smooth progress of the project.
[0003] Chinese Patent Publication No.: CN116895142B discloses a global monitoring method and system for construction. The invention provides a global monitoring method and system for construction, which relates to the field of intelligent control technology. The real-time construction content is read to adjust the initial area safety level, the monitoring parameters are set to control the fixed monitoring device to collect and identify images to generate feature recognition results, the monitoring parameters are adjusted in combination with the real-time construction content, the mobile feature recognition results are collected and identified, the construction sound is collected to obtain the construction sound recognition results, and the construction early warning is carried out through comprehensive analysis. The technical problems that the monitoring methods for construction in the prior art are not flexible and rigorous enough, the monitoring dimensions are not comprehensive enough, and the monitoring control parameters are not consistent with the actual construction conditions, resulting in the monitoring data being not accurate and complete enough, and the construction risk management has drawbacks are solved. For multiple monitoring dimensions, the consistency monitoring processing mode and the monitoring data analysis standard are determined, and a multi-dimensional comprehensive analysis and judgment are performed to improve the monitoring coverage and ensure the monitoring accuracy and completeness.
[0004] It can be seen that the global monitoring method and system of the construction site have the following problems: although the invention adjusts the initial area safety level through real-time construction content, and combines the mobile feature recognition results and construction sound recognition results to provide construction early warning to ensure monitoring accuracy and completeness, the invention has low monitoring accuracy for project construction personnel and cannot guarantee the safety of project construction personnel. Summary of the invention
[0005] To this end, the present invention provides a construction feedback system based on on-site real-time monitoring to overcome the problem in the prior art that only the monitoring accuracy of the construction site is guaranteed but the monitoring accuracy of the project construction personnel is insufficient.
[0006] To achieve the above object, the present invention provides a construction feedback system based on on-site real-time monitoring, comprising:
[0007] Area division units are used to divide the construction site into areas of different levels, including key construction areas, basic construction areas and auxiliary operation areas;
[0008] A monitoring unit connected to the area division unit, for real-time monitoring of each divided area and collecting real-time monitoring data, wherein the monitoring data includes worker safety monitoring data, construction equipment monitoring data and construction process monitoring data;
[0009] A central control unit connected to the monitoring unit, for calculating the risk evaluation value corresponding to each of the divided areas according to the monitoring data, and determining the monitoring level according to the risk evaluation value, and determining whether the control mode of the corresponding monitoring level meets the standard according to the difference evaluation value of the construction process under the monitoring level, and adjusting the number of monitoring devices or the monitoring image resolution based on the difference evaluation value difference under the condition that the control mode does not meet the standard, wherein the monitoring levels include level one, level two and level three;
[0010] A worker safety evaluation unit is connected to the monitoring unit and the central control unit to calculate the safety evaluation value of an individual worker to determine whether the construction behavior of an individual worker meets the standards, and to count the percentage of individual workers' construction behaviors that do not meet the standards, and to determine whether the safety training process meets the standards based on the percentage.
[0011] Furthermore, the formula for calculating the risk assessment value by the central control unit is as follows:
[0012]
[0013] Among them, L represents the risk assessment value, n represents the total number of equipment in a single area, ai represents the probability of failure of the i-th equipment, and wi represents the impact of the failure of the i-th equipment on the construction progress.
[0014] Further, the central control unit determines the monitoring level based on the risk assessment value, wherein:
[0015] If the risk assessment value is greater than a first preset risk assessment value, the central control unit determines that the monitoring level is level one;
[0016] If the risk assessment value is less than or equal to the first preset risk assessment value and greater than the second preset risk assessment value, the central control unit determines that the monitoring level is level 2;
[0017] If the risk assessment value is less than or equal to the second preset risk assessment value, the central control unit determines that the monitoring level is level three.
[0018] Furthermore, the central control unit acquires images of the same construction process at different angles under a determined monitoring level, extracts image features, and calculates a difference evaluation value based on a corresponding image feature offset.
[0019] Furthermore, the central control unit determines whether the monitoring arrangement meets the standard based on the difference evaluation value.
[0020] If the difference evaluation value is greater than a preset difference evaluation value, the central control unit determines that the control mode does not meet the standard;
[0021] If the difference evaluation value is less than or equal to the preset difference evaluation value, the central control unit determines that the control mode meets the standard.
[0022] Further, under the condition that the deployment mode does not meet the standard, the central control unit determines to adjust the number of monitoring devices or the resolution of monitoring images based on the difference evaluation value difference,
[0023] If the difference evaluation value difference is greater than the preset evaluation value difference, the central control unit determines to adjust the number of monitoring devices;
[0024] If the difference evaluation value difference is less than or equal to the preset evaluation value difference, the central control unit determines to adjust the monitoring image resolution.
[0025] Furthermore, the central control unit sets several adjustment methods for the number of monitoring devices, and each adjustment method has a different adjustment range for the number of monitoring devices.
[0026] Furthermore, the central control unit sets several adjustment modes for the monitoring image resolution, and each adjustment mode has a different adjustment range for the monitoring image resolution.
[0027] Furthermore, the worker safety evaluation unit determines whether the construction behavior of a single worker meets the standard based on the safety evaluation value.
[0028] If the safety evaluation value is greater than or equal to a preset safety evaluation value, the worker safety evaluation unit determines that the construction behavior of the individual worker meets the standard;
[0029] If the safety evaluation value is less than the preset safety evaluation value, the worker safety evaluation unit determines that the construction behavior of the individual worker does not meet the standard.
[0030] Further, the worker safety evaluation unit determines that the safety training process does not meet the standard under the condition that the quantity ratio is less than the preset quantity ratio, and sets several adjustment methods for the safety training process based on the quantity ratio difference under the condition that the safety training process does not meet the standard, and each adjustment method has a different adjustment range for the safety training process.
[0031] Compared with the prior art, the beneficial effects of the present invention are as follows: the present invention divides the construction site into areas of different levels by setting an area division unit, thereby preventing construction personnel from non-corresponding areas from mistakenly entering, and facilitating construction management personnel to quickly and accurately view the situation in key areas; the risk assessment value of the corresponding area is calculated based on areas of different levels, the risk situation is objectively evaluated based on the characteristics of each level of the area, and the monitoring level is determined based on the risk assessment value, thereby improving the use efficiency of the monitoring system while ensuring safety; under the condition that the monitoring system meets the standards, the completeness of the workers' safety protective gear and the workers' movement trajectories are captured to determine whether the workers' safety protection meets the standards and whether the safety training process meets the standards, thereby improving the monitoring accuracy of project construction personnel while ensuring the accuracy of on-site construction monitoring.
[0032] Furthermore, the present invention calculates the risk assessment value through a formula. The equipment existing in each divided area and its impact degree are different. Based on this feature, the risk assessment value calculated can objectively evaluate the risk level of each area, and the monitoring level is determined based on the risk level to carry out targeted monitoring and control, thereby ensuring the accuracy of on-site construction monitoring and improving the monitoring accuracy of project construction personnel.
[0033] Furthermore, the present invention obtains images of different angles of the same construction process under a determined monitoring level, extracts and compares image features, calculates the image feature offset to determine whether the deployment method of the monitoring equipment meets the standards, and determines the adjustment method based on the difference in difference evaluation values when it is determined that it does not meet the standards, thereby improving the monitoring accuracy of the construction site.
[0034] Furthermore, under the condition that the monitoring deployment mode meets the standards, the present invention further accurately monitors the construction status of the workers, determines the safety evaluation value of a single worker by the completeness of the wearing of the safety protective gear and the movement trajectory of the workers, so as to determine the degree of risk of the single worker, and counts the percentage of workers with high risk levels, objectively and accurately evaluates the safety training process, and makes adjustments based on the difference in the percentage when the safety training process does not meet the standards, thereby improving the monitoring accuracy of project construction personnel while ensuring the accuracy of on-site construction monitoring. BRIEF DESCRIPTION OF THE DRAWINGS
[0035] Figure 1 It is a structural block diagram of a construction feedback system based on on-site real-time monitoring according to an embodiment of the present invention;
[0036] Figure 2 A flow chart for determining a monitoring level according to an embodiment of the present invention;
[0037] Figure 3 A flowchart for determining whether a monitoring deployment method meets the standards according to an embodiment of the present invention;
[0038] Figure 4 A flow chart for determining and adjusting monitoring parameters according to an embodiment of the present invention. DETAILED DESCRIPTION
[0039] In order to make the objects and advantages of the present invention more clearly understood, the present invention is further described below in conjunction with embodiments; it should be understood that the specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention.
[0040] The preferred embodiments of the present invention are described below with reference to the accompanying drawings. It should be understood by those skilled in the art that these embodiments are only used to explain the technical principles of the present invention and are not intended to limit the protection scope of the present invention.
[0041] It should be noted that, in the description of the present invention, terms such as "up", "down", "left", "right", "inside" and "outside" indicating directions or positional relationships are based on the directions or positional relationships shown in the drawings. This is merely for the convenience of description and does not indicate or imply that the device or element must have a specific orientation, be constructed and operated in a specific orientation. Therefore, it cannot be understood as a limitation on the present invention.
[0042] In addition, it should be noted that in the description of the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For those skilled in the art, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0043] See also Figure 1 As shown, it is a structural block diagram of a construction feedback system based on on-site real-time monitoring according to an embodiment of the invention.
[0044] The embodiment of the present invention provides a construction feedback system based on on-site real-time monitoring, including:
[0045] Area division units are used to divide the construction site into areas of different levels and set up corresponding isolation facilities and warning signs, including key construction areas, basic construction areas and auxiliary operation areas;
[0046] A monitoring unit connected to the area division unit, for real-time monitoring of each divided area and collecting real-time monitoring data, wherein the monitoring data includes worker safety monitoring data, construction equipment monitoring data and construction process monitoring data;
[0047] A central control unit connected to the monitoring unit, for calculating the risk evaluation value corresponding to each of the divided areas according to the monitoring data, and determining the monitoring level according to the risk evaluation value, and determining whether the control mode of the corresponding monitoring level meets the standard according to the difference evaluation value of the construction process under the monitoring level, and adjusting the number of monitoring devices or the monitoring image resolution based on the difference evaluation value difference under the condition that the control mode does not meet the standard, wherein the monitoring levels include level one, level two and level three;
[0048] A worker safety evaluation unit is connected to the monitoring unit and the central control unit to calculate the safety evaluation value of an individual worker to determine whether the construction behavior of an individual worker meets the standards, and to count the percentage of individual workers' construction behaviors that do not meet the standards, and to determine whether the safety training process meets the standards based on the percentage.
[0049] Specifically, in the embodiment of the present invention, the isolation facilities such as fences are not specifically limited, and the warning indication is determined according to the actual situation and is not specifically limited.
[0050] Specifically, in the embodiment of the present invention, the worker safety monitoring data includes the workers' wearing of safety protective gear and the number of prohibited areas in the workers' movement trajectory; the construction equipment monitoring data includes the operating parameters of all equipment at the project construction site, such as the operating route of the excavator and the working range of the tower crane, without specific limitation.
[0051] Specifically, the present invention divides the construction site into areas of different levels by setting up an area division unit, so as to prevent construction personnel from non-corresponding areas from mistakenly entering, and facilitate construction management personnel to quickly and accurately check the situation in key areas; the risk assessment value of the corresponding area is calculated based on the areas of different levels, the risk situation is objectively evaluated according to the characteristics of each level of the area, and the monitoring level is determined according to the risk assessment value, so as to improve the use efficiency of the monitoring system while ensuring safety; under the condition that the monitoring system meets the standards, the completeness of the workers' safety protective gear and the workers' movement trajectories are captured to determine whether the workers' safety protection meets the standards and whether the safety training process meets the standards, so as to improve the monitoring accuracy of project construction personnel while ensuring the accuracy of on-site construction monitoring.
[0052] Specifically, the formula for calculating the risk assessment value by the central control unit is as follows:
[0053]
[0054] Among them, L represents the risk assessment value, n represents the total number of equipment in a single area, ai represents the probability of failure of the i-th equipment, and wi represents the impact of the failure of the i-th equipment on the construction progress.
[0055] Specifically, the probability of equipment failure is determined based on the historical number of failures and the historical working hours, and is not specifically limited; the impact of equipment failure on the construction progress, for example, in key construction areas, the impact of tower crane failure is 20%, the impact of concrete mixer truck failure is 30%, and the impact of rebar cutting machine failure is 10%, for example, and is not specifically limited.
[0056] See also Figure 2 As shown, it is a flow chart of determining the monitoring level according to an embodiment of the present invention.
[0057] Specifically, the central control unit determines the monitoring level based on the risk assessment value, wherein:
[0058] If the risk assessment value is greater than 70% of the first preset risk assessment value, the central control unit determines that the monitoring level is level one;
[0059] If the risk assessment value is less than or equal to 70% of the first preset risk assessment value and greater than 50% of the second preset risk assessment value, the central control unit determines that the monitoring level is level 2;
[0060] If the risk assessment value is less than or equal to 50% of the second preset risk assessment value, the central control unit determines that the monitoring level is level three.
[0061] Specifically, the deployment methods of first-level monitoring include, for example, the use of high-definition cameras and infrared night vision goggles, with a monitoring range coverage rate of 100%, and the installation of warning signs and warning lights in highly dangerous areas, and regular inspections by dedicated personnel, and the formulation and drills of emergency plans for possible major accidents, with no specific restrictions; the deployment methods of second-level monitoring include, for example, the deployment of monitoring equipment at key locations and links, and regular inspection and maintenance of monitoring equipment and safety facilities, with no specific restrictions; the deployment methods of third-level monitoring include, for example, the use of conventional cameras to monitor key areas, with no specific restrictions.
[0062] Specifically, the present invention calculates the risk assessment value through a formula. The equipment existing in each divided area and its impact degree are different. Based on this feature, the risk assessment value calculated can objectively evaluate the risk level of each area, and the monitoring level is determined based on the risk level to carry out targeted monitoring and control, thereby ensuring the accuracy of on-site construction monitoring and improving the monitoring accuracy of project construction personnel.
[0063] Specifically, the central control unit acquires images of the same construction process at different angles under a determined monitoring level, extracts image features, and calculates a difference evaluation value based on a corresponding image feature offset.
[0064] Specifically, image features such as the verticality of the tower crane and the construction position are not specifically limited; the offset degree is determined according to the specific image features, such as the offset angle between the tower crane and the vertical direction, the relative distance between the construction positions or the deviation in the relative direction, which are not specifically limited. The corresponding offset degree is preset for the offset angle value, for example, the offset degree of the offset angle between 0-10° is 0, the offset degree of the offset angle between 10-15° is 1, and the offset degree greater than 15° is 2; the corresponding offset degree is preset for the distance deviation of the relative distance and the angle deviation of the relative direction, for example, the offset degree of the distance deviation between 0-1cm is 0, the offset degree between 1-3cm is 1, and the offset degree greater than 3cm is 2; the offset degree of the angle deviation between 0-30° is 0, the offset degree between 30-60° is 1, and the offset degree greater than 60° is 2, which are not specifically limited.
[0065] Specifically, the difference evaluation value is the sum of the deviations.
[0066] See also Figure 3 As shown, it is a flow chart of an embodiment of the present invention for determining whether the monitoring deployment mode meets the standards.
[0067] Specifically, the central control unit determines whether the monitoring arrangement meets the standard based on the difference evaluation value.
[0068] If the difference evaluation value is greater than the preset difference evaluation value 8, the central control unit determines that the control mode does not meet the standard;
[0069] If the difference evaluation value is less than or equal to the preset difference evaluation value 8, the central control unit determines that the control mode meets the standard.
[0070] See also Figure 4 As shown, it is a flow chart of determining and adjusting monitoring parameters according to an embodiment of the present invention.
[0071] Specifically, under the condition that the deployment mode does not meet the standard, the central control unit determines to adjust the number of monitoring devices or the resolution of monitoring images based on the difference evaluation value difference,
[0072] If the difference evaluation value difference is greater than the preset evaluation value difference 3, the central control unit determines to adjust the number of monitoring devices;
[0073] If the difference evaluation value difference is less than or equal to the preset evaluation value difference 3, the central control unit determines to adjust the monitoring image resolution.
[0074] Specifically, the central control unit sets several adjustment methods for the number of monitoring devices, and each adjustment method has a different adjustment range for the number of monitoring devices.
[0075] Specifically, the central control unit records the ratio of the difference between the difference evaluation value and the preset evaluation value difference to the preset evaluation value difference as the first difference percentage.
[0076] If the first difference percentage is less than or equal to a preset first difference percentage of 20%, the central control unit determines to increase the number of monitoring devices by a first quantity coefficient of 1.1;
[0077] If the first difference percentage is greater than the preset first difference percentage of 20%, the central control unit determines to increase the number of monitoring devices by a second quantity coefficient of 1.2.
[0078] Specifically, the central control unit sets several adjustment modes for the monitoring image resolution, and each adjustment mode has a different adjustment range for the monitoring image resolution.
[0079] Specifically, the central control unit records the ratio of the difference between the preset evaluation value difference and the difference evaluation value difference to the preset evaluation value difference as the second difference percentage.
[0080] If the second difference percentage is less than or equal to a preset second difference percentage of 10%, the central control unit determines to increase the image resolution by using a first resolution coefficient of 1.3;
[0081] If the second difference percentage is greater than a preset second difference percentage of 10%, the central control unit determines to increase the image resolution by a second resolution coefficient of 1.5.
[0082] Specifically, the present invention obtains images of different angles of the same construction process under a determined monitoring level, extracts and compares image features, calculates the image feature offset to determine whether the deployment mode of the monitoring equipment meets the standards, and determines the adjustment mode based on the difference evaluation value difference when it is determined that it does not meet the standards, thereby improving the monitoring accuracy of the construction site.
[0083] Specifically, the worker safety evaluation unit determines whether the construction behavior of a single worker meets the standard based on the safety evaluation value.
[0084] If the safety evaluation value is greater than or equal to a preset safety evaluation value of 90, the worker safety evaluation unit determines that the construction behavior of the individual worker meets the standard;
[0085] If the safety evaluation value is less than the preset safety evaluation value of 90, the worker safety evaluation unit determines that the construction behavior of the individual worker does not meet the standard.
[0086] Specifically, the safety assessment value is determined based on the completeness of the safety gear worn by workers at the project construction site and the proportion of prohibited areas in the workers' movement trajectory.
[0087] Specifically, workers' safety gear includes but is not limited to safety helmets, safety ropes, protective shoes, safety gloves, and protective masks.
[0088] Specifically, the worker safety evaluation unit determines that the safety training process does not meet the standards under the condition that the number proportion is less than 85% of the preset number proportion, and, under the condition that the safety training process does not meet the standards, sets several adjustment methods for the safety training process based on the number proportion difference, and each adjustment method has a different adjustment range for the safety training process.
[0089] Specifically, if the quantity ratio difference is greater than a preset quantity ratio difference of 5%, the worker evaluation unit determines to increase the number of safety training times by a first quantity coefficient of 1.5;
[0090] If the quantity ratio difference is less than or equal to the preset quantity ratio difference of 5%, the worker evaluation unit determines to increase the number of safety training times by a second quantity coefficient of 1.3;
[0091] The adjusted number of safety training times is the product of the first quantity coefficient or the second quantity coefficient and the preset number of safety training times, wherein the preset number of safety training times is determined based on engineering requirements and is not specifically limited.
[0092] Specifically, under the condition that the monitoring deployment mode meets the standards, the present invention further accurately monitors the construction status of the workers, determines the safety evaluation value of a single worker by the completeness of the wearing of the safety protective gear and the movement trajectory of the workers, so as to determine the degree of risk of the single worker, and counts the percentage of workers with high risk levels, objectively and accurately evaluates the safety training process, and makes adjustments based on the difference in the percentage when the safety training process does not meet the standards, thereby improving the monitoring accuracy of project construction personnel while ensuring the accuracy of on-site construction monitoring.
[0093] So far, the technical solutions of the present invention have been described in conjunction with the preferred embodiments shown in the accompanying drawings. However, it is easy for those skilled in the art to understand that the protection scope of the present invention is obviously not limited to these specific embodiments. Without departing from the principle of the present invention, those skilled in the art can make equivalent changes or substitutions to the relevant technical features, and the technical solutions after these changes or substitutions will fall within the protection scope of the present invention.
Claims
1. A construction feedback system based on real-time on-site monitoring, It is characterized in that include: Area division units are used to divide the construction site into areas of different levels and set up corresponding isolation facilities and warning signs, including key construction areas, basic construction areas and auxiliary operation areas; A monitoring unit connected to the area division unit, for real-time monitoring of each divided area and collecting real-time monitoring data, wherein the monitoring data includes worker safety monitoring data, construction equipment monitoring data and construction process monitoring data; A central control unit connected to the monitoring unit, for calculating the risk evaluation value corresponding to each of the divided areas according to the monitoring data, and determining the monitoring level according to the risk evaluation value, and determining whether the control mode of the corresponding monitoring level meets the standard according to the difference evaluation value of the construction process under the monitoring level, and adjusting the number of monitoring devices or the monitoring image resolution based on the difference evaluation value difference under the condition that the control mode does not meet the standard, wherein the monitoring levels include level one, level two and level three; A worker safety evaluation unit is connected to the monitoring unit and the central control unit to calculate the safety evaluation value of an individual worker to determine whether the construction behavior of an individual worker meets the standards, and to count the percentage of individual workers' construction behaviors that do not meet the standards, and to determine whether the safety training process meets the standards based on the percentage.
2. The construction feedback system based on on-site real-time monitoring according to claim 1, It is characterized in that The formula for calculating the risk assessment value by the central control unit is as follows: Among them, L represents the risk assessment value, n represents the total number of equipment in a single area, ai represents the probability of failure of the i-th equipment, and wi represents the impact of the failure of the i-th equipment on the construction progress.
3. The construction feedback system based on on-site real-time monitoring according to claim 2, It is characterized in that The central control unit determines the monitoring level based on the risk assessment value, wherein: If the risk assessment value is greater than a first preset risk assessment value, the central control unit determines that the monitoring level is level one; If the risk assessment value is less than or equal to the first preset risk assessment value and greater than the second preset risk assessment value, the central control unit determines that the monitoring level is level 2; If the risk assessment value is less than or equal to the second preset risk assessment value, the central control unit determines that the monitoring level is level three.
4. The construction feedback system based on on-site real-time monitoring according to claim 3, It is characterized in that The central control unit acquires images of the same construction process at different angles under a determined monitoring level, extracts image features, and calculates a difference evaluation value based on a corresponding image feature deviation.
5. The construction feedback system based on on-site real-time monitoring according to claim 4, It is characterized in that The central control unit determines whether the monitoring arrangement meets the standard based on the difference evaluation value, If the difference evaluation value is greater than a preset difference evaluation value, the central control unit determines that the control mode does not meet the standard; If the difference evaluation value is less than or equal to the preset difference evaluation value, the central control unit determines that the control mode meets the standard.
6. The construction feedback system based on on-site real-time monitoring according to claim 5, It is characterized in that Under the condition that the deployment mode does not meet the standard, the central control unit determines to adjust the number of monitoring devices or the monitoring image resolution based on the difference evaluation value difference, If the difference evaluation value difference is greater than the preset evaluation value difference, the central control unit determines to adjust the number of monitoring devices; If the difference evaluation value difference is less than or equal to the preset evaluation value difference, the central control unit determines to adjust the monitoring image resolution.
7. The construction feedback system based on on-site real-time monitoring according to claim 6, It is characterized in that The central control unit sets several adjustment methods for the number of monitoring devices, and each adjustment method has a different adjustment range for the number of monitoring devices.
8. The construction feedback system based on on-site real-time monitoring according to claim 6, It is characterized in that The central control unit sets several adjustment modes for the monitoring image resolution, and each adjustment mode has a different adjustment range for the monitoring image resolution.
9. The construction feedback system based on on-site real-time monitoring according to claim 8, It is characterized in that The worker safety evaluation unit determines whether the construction behavior of a single worker meets the standard based on the safety evaluation value, If the safety evaluation value is greater than or equal to a preset safety evaluation value, the worker safety evaluation unit determines that the construction behavior of the individual worker meets the standard; If the safety evaluation value is less than the preset safety evaluation value, the worker safety evaluation unit determines that the construction behavior of the individual worker does not meet the standard.
10. The construction feedback system based on on-site real-time monitoring according to claim 9, It is characterized in that The worker safety evaluation unit determines that the safety training process does not meet the standards under the condition that the quantity proportion is less than the preset quantity proportion, and sets several adjustment methods for the safety training process based on the quantity proportion difference under the condition that the safety training process does not meet the standards, and each adjustment method has a different adjustment range for the safety training process.
Citation Information
Patent Citations
Building construction safety data index processing system
CN114548721A
Building construction site distribution type fire monitoring system and method
CN115565330A
Abnormality identification method for construction monitoring system
CN116416577A
Global monitoring method and system for building construction
CN116895142A
Construction site safety monitoring system and early warning method
CN117475603A
Cited By
Visual monitoring system for curb construction site
CN120088093A