Intelligent building construction progress management platform

Through the data collection, processing and simulation units of the intelligent building construction progress management platform, the update scope of the construction progress prediction model is adjusted, which solves the problems of reduced prediction accuracy caused by rework of construction sites and irrelevant content of model learning, and improves the construction progress prediction accuracy and model stability.

CN119067356AInactive Publication Date: 2024-12-03TODAY CONSTR CO LTD
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202411045087.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-01
Publication Date
2024-12-03
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The existing building construction progress management platform has reduced the prediction accuracy of the construction site rework, and too much irrelevant content has been learned by the prediction model, resulting in the reduction of the accuracy of the prediction model.

Method used

Design an intelligent building construction progress management platform, including data acquisition, processing and simulation units, establish and update construction progress prediction models by eliminating abnormal data, adjusting the comparison type of secondary construction feature data and the update scope of prediction models, and enhancing the model generalization ability and accuracy.

Benefits of technology

It improves the accuracy of construction progress prediction, reduces the accuracy reduction caused by the model learning irrelevant content, enhances the stability and adaptability of the model, and reduces the performance decline caused by data deviation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119067356A_ABST
    Figure CN119067356A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of construction progress management platforms, in particular to an intelligent building construction progress management platform, which comprises a data acquisition unit; a data processing unit; a progress simulation unit; the control unit is used for judging the accuracy of construction progress management according to the prediction error amount of the construction progress, and determining whether to adjust the number of comparison types of the secondary construction feature data or not according to the judgment result of the accuracy of the construction progress management; adjusting the passive updating range of the construction progress prediction model according to the prediction error amount and the test updating rate of the construction progress prediction model, and adjusting the mapping number of composite mapping according to the test updating rate of the construction progress prediction model and the fitting degree of the mapping variation and the construction progress. The accuracy of construction progress management is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of construction progress management platforms, and in particular to an intelligent building construction progress management platform. Background Art

[0002] In the existing technology, the construction progress management platform is usually built based on advanced information technology, such as cloud computing, big data, and the Internet of Things. Through cloud computing technology, the platform can realize centralized storage and processing of data, and improve data processing capabilities and efficiency. At the same time, big data technology enables the platform to conduct in-depth mining and analysis of massive data, providing strong support for project progress management. The Internet of Things technology uses various sensors and intelligent devices to collect various data on the construction site in real time, such as the status and location information of personnel, equipment, and materials, providing a real-time and accurate data source for the platform. Secondly, the construction progress management platform uses intelligent algorithms and models to intelligently analyze and predict the construction progress. These algorithms and models can automatically adjust and optimize the progress plan based on historical data and real-time data to ensure that the project can be completed on time. At the same time, the platform can also visualize the construction progress through simulation and emulation technology.

[0003] Chinese Patent Publication No.: CN117557065A discloses a construction progress supervision system for a building project based on BIM technology, including a construction supervision platform, a BIM model creation module, a construction progress simulation module, a construction period segmentation module, a progress monitoring and control module, and a background early warning terminal; the BIM model creation module is used to create a BIM model of the corresponding building project, and apply the BIM model to the construction progress simulation module. The construction progress simulation module is based on the BIM model and simulates the construction process to predict the construction progress of the corresponding building project, and obtains the standard construction progress curve of the corresponding building project through prediction; the construction period segmentation module divides the construction period of the corresponding building project, obtains several supervision periods, and marks the corresponding supervision period as i, and i is a natural number greater than 1; the standard construction progress curve is divided into several small segments based on the segmentation method of the construction cycle, and each small segment of the standard construction progress curve corresponds to the corresponding supervision period, and the corresponding small segment in the construction progress curve is marked as a standard construction supervision segment; the progress monitoring and control module monitors the construction progress of the corresponding construction project in the supervision period i, obtains the actual progress curve of the corresponding construction project in the supervision period i, compares the actual progress curve with the corresponding standard construction supervision segment, and generates a progress supervision abnormal signal or a progress supervision normal signal for the corresponding supervision period i through analysis, and sends the progress supervision abnormal signal or the progress supervision normal signal to the background warning terminal via the construction supervision platform, and the background warning terminal issues a corresponding warning when receiving the progress supervision abnormal signal. It can be seen from this that the construction progress supervision system of the construction project based on BIM technology has the problem that the accuracy of the construction progress prediction decreases when there is rework at the construction site and the construction progress prediction model learns too much content that is not related to the construction progress, thereby causing the accuracy of the construction progress prediction model to decrease. Summary of the invention

[0004] To this end, the present invention provides an intelligent building construction progress management platform to overcome the problems in the prior art of decreased accuracy of construction progress prediction when rework occurs at construction sites and decreased accuracy of the construction progress prediction model due to the construction progress prediction model learning too much content that is irrelevant to the construction progress.

[0005] To achieve the above objectives, the present invention provides an intelligent building construction progress management platform, comprising:

[0006] A data collection unit, used to collect primary construction characteristic data and construction standard data;

[0007] a data processing unit connected to the data acquisition unit, for comparing the primary construction feature data with the construction standard data to eliminate abnormal data and output secondary construction feature data;

[0008] a progress simulation unit connected to the data processing unit and used to simulate the construction progress according to the secondary construction feature data, including a prediction modeling component used to establish a construction progress prediction model according to the secondary construction feature data and an updating component connected to the prediction modeling component and used to update the construction progress prediction model;

[0009] A control unit, which is respectively connected to the data acquisition unit, the data processing unit and the progress simulation unit, and is used to determine the accuracy of the construction progress management according to the prediction error of the construction progress, determine whether to adjust the number of comparison types of the secondary construction feature data according to the judgment result of the accuracy of the construction progress management, adjust the passive update range of the construction progress prediction model according to the prediction error and the test update rate of the construction progress prediction model, and adjust the number of mappings of the composite mapping according to the test update rate of the construction progress prediction model and the change amount of the mapping and the degree of fit of the construction progress.

[0010] Furthermore, it also includes a database connected to the data acquisition unit and the data processing unit respectively for storing the primary construction feature data, the secondary construction feature data and the construction standard data respectively.

[0011] Furthermore, the progress simulation unit also includes a real-time modeling component for establishing a real-time construction model according to the secondary construction characteristic data.

[0012] Furthermore, the control unit is respectively connected to the predictive modeling component and the actual modeling component to compare the construction progress prediction model and the actual construction model to obtain the prediction error of the construction progress. If the prediction error of the construction progress is greater than a preset second prediction error, it is determined that the accuracy of the construction progress management does not meet the requirements, and the number of comparison types of the secondary construction feature data is increased.

[0013] Furthermore, the formula for the predicted error of the construction progress is:

[0014] n=n1-n2

[0015] Among them, n is the prediction error of the construction progress, n1 is the actual completed construction progress of the actual construction model, and n2 is the predicted completed construction progress of the construction progress prediction model.

[0016] Furthermore, the increase range of the number of comparison types of the secondary construction feature data is determined according to the difference between the predicted error amount of the construction progress and the preset second predicted error amount.

[0017] Furthermore, the control unit is connected to the update component to initially determine that the accuracy of the construction progress prediction model does not meet the requirements when the prediction error of the construction progress is greater than or equal to a preset first prediction error and less than or equal to a preset second prediction error, and obtain the test update rate of the construction progress prediction model; if the test update rate of the construction progress prediction model is greater than the preset second test update rate, a second determination is made that the accuracy of the construction progress prediction model does not meet the requirements, and the passive update range of the construction progress prediction model is reduced.

[0018] Furthermore, the reduction range of the passive update range of the construction progress prediction model is determined according to the difference between the test update rate of the construction progress prediction model and the preset second test update rate.

[0019] Furthermore, the control unit is respectively connected to the standardization component and the prediction modeling component, so as to initially determine that the accuracy of mapping establishment of the construction progress prediction model does not meet the requirements when the test update rate of the construction progress prediction model is greater than or equal to the preset first test update rate and less than or equal to the preset second test update rate, obtain the change in the mapping and the construction progress, and calculate the degree of fit between the change in the mapping and the construction progress; if the degree of fit between the change in the mapping and the construction progress is less than the preset degree of fit, secondly determine that the accuracy of mapping establishment of the construction progress prediction model does not meet the requirements, and reduce the number of mappings of the composite mapping.

[0020] Furthermore, the reduction range of the number of mappings of the composite mapping is determined according to the difference between the preset degree of fit and the degree of fit between the amount of change of the mapping and the construction progress.

[0021] Compared with the prior art, the beneficial effect of the present invention lies in that the system of the present invention simulates and models the construction progress management platform and provides feedback by setting a data acquisition unit and a data processing unit. Since rework at a certain construction site results in an increase in materials used, a large difference between the construction progress prediction model and the actual construction progress occurs. By adjusting the number of comparison types of secondary construction feature data, the diversity of the data set is improved, thereby enhancing the generalization ability of the model and improving the accuracy of the construction progress prediction. By adjusting the passive update range of the construction progress prediction model and the number of mappings of the composite mapping, the changing factors that depend on the data or environment associated with the model are supplemented, the accuracy of the model establishment is improved, and the situation in which the accuracy of the construction progress prediction model decreases due to the model learning too much content that is not related to the construction progress is reduced, thereby improving the accuracy of the construction progress prediction model and the accuracy of the mapping establishment of the construction progress prediction model.

[0022] Furthermore, the system of the present invention can process the primary construction feature data by setting up a data processing unit, thereby removing noise, enhancing features, correcting geometric distortion, etc., which helps to extract three-dimensional information more accurately. At the same time, data processing can also optimize image quality, making it more suitable for subsequent modeling algorithms, thereby accelerating modeling speed, reducing the amount of calculation, and improving the stability and reliability of the model.

[0023] Furthermore, the system of the present invention sets a preset second prediction error amount. Due to the force majeure occurring during the construction process, which leads to the difference between the construction progress prediction model and the actual construction progress, by increasing the number of comparison types of the secondary construction feature data, the model is prevented from having too strong a dependence on only a certain type of specific data. This enables the model to better adapt and respond to new and unseen data, reduces the performance degradation caused by data deviation or deficiency, and further improves the accuracy of construction progress management.

[0024] Furthermore, the system of the present invention sets a preset first test update rate. Since the content related to the construction progress does not appear in the updated content, the real-time and accuracy of the update of the construction progress prediction model are reduced. By adjusting the passive update range of the construction progress prediction model, the details of the model are increased and the model accuracy is improved, the accuracy of the construction progress prediction model is improved.

[0025] Furthermore, the system of the present invention sets a preset degree of fit. During construction, certain construction conditions may change with changes in the environment or time, resulting in differences between the construction progress and the actual model. By reducing the number of mappings of the composite mapping, information loss can be compensated, and more abundant constraints can be provided for the model, thereby reducing uncertainty in the modeling process and further improving the accuracy of mapping establishment of the construction progress prediction model. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] Figure 1 This is an overall structural diagram of the intelligent building construction progress management platform according to an embodiment of the present invention;

[0027] Figure 2 It is a specific structural block diagram of the progress simulation unit of the intelligent building construction progress management platform according to an embodiment of the present invention;

[0028] Figure 3 It is a specific structural block diagram of a progress simulation unit and a control unit of an intelligent building construction progress management platform according to an embodiment of the present invention;

[0029] Figure 4 The following is a logical flow chart of the intelligent building construction progress management platform according to an embodiment of the present invention. DETAILED DESCRIPTION

[0030] In order to make the objects and advantages of the present invention more clearly understood, the present invention is further described below in conjunction with embodiments; it should be understood that the specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention.

[0031] The preferred embodiments of the present invention are described below with reference to the accompanying drawings. It should be understood by those skilled in the art that these embodiments are only used to explain the technical principles of the present invention and are not intended to limit the protection scope of the present invention.

[0032] It should be noted that, in the description of the present invention, terms such as "up", "down", "left", "right", "inside" and "outside" indicating directions or positional relationships are based on the directions or positional relationships shown in the drawings. This is merely for the convenience of description and does not indicate or imply that the device or element must have a specific orientation, be constructed and operated in a specific orientation. Therefore, it cannot be understood as a limitation on the present invention.

[0033] In addition, it should be noted that in the description of the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For those skilled in the art, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0034] See also Figure 1 , Figure 2 , Figure 3 as well as Figure 4 As shown, they are respectively an overall structural block diagram of the intelligent building construction progress management platform of the embodiment of the present invention, a specific structural block diagram of the progress simulation unit, a specific structural block diagram of the progress simulation unit and the control unit, and a logic flow chart. An intelligent building construction progress management platform of the present invention includes:

[0035] A data collection unit, used to collect primary construction characteristic data and construction standard data;

[0036] a data processing unit connected to the data acquisition unit, for comparing the primary construction feature data with the construction standard data to eliminate abnormal data and output secondary construction feature data;

[0037] a progress simulation unit connected to the data processing unit and used to simulate the construction progress according to the secondary construction feature data, including a prediction modeling component used to establish a construction progress prediction model according to the secondary construction feature data and an updating component connected to the prediction modeling component and used to update the construction progress prediction model;

[0038] A control unit, which is respectively connected to the data acquisition unit, the data processing unit and the progress simulation unit, and is used to determine the accuracy of the construction progress management according to the prediction error of the construction progress, determine whether to adjust the number of comparison types of the secondary construction feature data according to the judgment result of the accuracy of the construction progress management, adjust the passive update range of the construction progress prediction model according to the prediction error and the test update rate of the construction progress prediction model, and adjust the number of mappings of the composite mapping according to the test update rate of the construction progress prediction model and the change amount of the mapping and the degree of fit of the construction progress.

[0039] Specifically, the data collection unit includes a drone that uses stereo polygon task photography technology to periodically photograph the construction site and a number of cameras set up at the construction site.

[0040] Specifically, the first-level construction feature data includes construction image information, construction site area, the actual number of steel bars used per unit construction area, the actual volume of cement ash used per square meter of construction wall, building height, and coordinate data of construction points.

[0041] Specifically, the meaning of construction standard data is the construction parameters within the specified range required by the construction specifications. The construction standard data includes the number of steel bars required per unit construction area and the volume of cement ash required per square meter of wall construction.

[0042] Specifically, the coordinate data of the construction point refers to the set of coordinates of each construction location obtained by dividing the building into spatial locations.

[0043] Specifically, the difference between the secondary construction feature data and the primary construction feature data is that the number of abnormal data in the secondary construction feature data is smaller than the number of abnormal data in the secondary construction feature data.

[0044] Specifically, the modeling components of the construction progress prediction model can be Autodesk Revit, Graph isoft Arch iCAD, Bentley AECOsim, and Trimble SketchUp.

[0045] Specifically, the modeling process of the construction progress prediction model is to train the secondary construction feature data, generate several groups of mappings through training, and compose the construction progress prediction model according to the several groups of mappings. The data training process and the mapping generation process as well as the process of composing the construction progress prediction model through mapping are conventional technical means well known to technical personnel in this field. Therefore, the data training process, the mapping generation process and the process of generating the construction progress prediction model through mapping will not be repeated here.

[0046] Specifically, the abnormal data eliminated by the data processing unit is data that deviates from the normal range compared with the construction standard data.

[0047] In implementation, the system of the present invention simulates and models the construction progress management platform and provides feedback by setting a data acquisition unit and a data processing unit. Since rework at a certain construction site results in an increase in materials used, a large difference occurs between the construction progress prediction model and the actual construction progress. By adjusting the number of comparison types of secondary construction feature data, the diversity of the data set is improved, thereby enhancing the generalization ability of the model and improving the accuracy of the construction progress prediction. By adjusting the passive update range of the construction progress prediction model and the number of mappings of the composite mapping, the changing factors that depend on the data or environment associated with the model are supplemented, and the accuracy of model establishment is improved, thereby reducing the situation where the accuracy of the construction progress prediction model decreases due to the model learning too much content that is not related to the construction progress, thereby improving the accuracy of the construction progress prediction model and the accuracy of the mapping establishment of the construction progress prediction model.

[0048] Specifically, the system of the present invention processes the primary construction feature data by setting up a data processing unit, which can remove noise, enhance features, correct geometric distortion, etc., which helps to extract three-dimensional information more accurately. At the same time, data processing can also optimize image quality, making it more suitable for subsequent modeling algorithms, thereby accelerating modeling speed, reducing calculation amount, and improving the stability and reliability of the model.

[0049] Specifically, it also includes a database connected to the data acquisition unit and the data processing unit respectively for storing the primary construction feature data, the secondary construction feature data and the construction standard data respectively.

[0050] Specifically, the progress simulation unit also includes a real-time modeling component for establishing a real-time construction model according to the secondary construction feature data.

[0051] Specifically, the actual construction model is a BIM construction model in implementation. Those skilled in the art will understand that the modeling process of the BIM construction model is to restore the three-dimensional structure of the construction object based on the secondary construction feature data in the actual construction scene. The process of restoring the three-dimensional structure of the construction object is a conventional technical means well known to those skilled in the art, so the restoration process will not be described in detail.

[0052] Specifically, the control unit is connected to the prediction modeling component and the actual modeling component respectively, and is used to compare the construction progress prediction model and the actual construction model to obtain the prediction error of the construction progress. If the prediction error of the construction progress is greater than a preset second prediction error, it is determined that the accuracy of the construction progress management does not meet the requirements, and the number of comparison types of the secondary construction feature data is increased.

[0053] Specifically, the formula for the predicted error of the construction progress is:

[0054] n=n1-n2

[0055] Among them, n is the prediction error of the construction progress, n1 is the actual completed construction progress of the actual construction model, and n2 is the predicted construction progress of the construction progress prediction model.

[0056] Specifically, the increase range of the number of comparison types of the secondary construction feature data is determined according to the difference between the predicted error amount of the construction progress and the preset second predicted error amount.

[0057] Specifically, the comparison types of secondary construction characteristic data include the probability of rework in special areas of the building, the difference in materials used for rework, the average daily precipitation in the construction area, the growth rate of consumables, and the turnover rate of construction personnel.

[0058] In implementation, the general value range of the preset second prediction error amount is [1.2%, 1.5%].

[0059] Preferably, the second prediction error amount is preset to be 1.3%.

[0060] Specifically, when the difference between the predicted error amount of the construction progress and the preset second predicted error amount is within 0.1%, the number of comparison types of the secondary construction feature data increases to 1.1 times the original; when the difference between the predicted error amount of the construction progress and the preset second predicted error amount exceeds 0.1%, the number of comparison types of the secondary construction feature data increases by 3 for every 0.1% exceeding it. For example, when the predicted error amount of the construction progress is 1.6%, the current number of comparison types of the secondary construction feature data is 20, and the number of comparison types of the secondary construction feature data increases to 20×1.1+3×2=28.

[0061] In implementation, the system of the present invention sets a preset second prediction error amount. Due to the force majeure occurring during the construction process, there is a difference between the construction progress prediction model and the actual construction progress. By increasing the number of comparison types of the secondary construction feature data, the model is prevented from having too strong a dependence on only a certain type of specific data. This enables the model to better adapt and respond to new and unseen data, reduces performance degradation caused by data deviation or deficiency, and further improves the accuracy of construction progress management.

[0062] Specifically, the control unit is connected to the update component to initially determine that the accuracy of the construction progress prediction model does not meet the requirements when the prediction error of the construction progress is greater than or equal to the preset first prediction error and less than or equal to the preset second prediction error, and obtain the test update rate of the construction progress prediction model. If the test update rate of the construction progress prediction model is greater than the preset second test update rate, a second determination is made that the accuracy of the construction progress prediction model does not meet the requirements, and the passive update range of the construction progress prediction model is reduced.

[0063] Specifically, the reduction range of the passive update range of the construction progress prediction model is determined according to the difference between the test update rate of the construction progress prediction model and the preset second test update rate.

[0064] Specifically, the reduction range of the passive update range of the construction progress prediction model is determined according to the difference between the test update rate of the construction progress prediction model and the preset second test update rate.

[0065] Specifically, the passive update range of the construction progress prediction model means the update ratio of all model data of the construction progress prediction model within the inaccurate prediction time period when the construction progress prediction model is inaccurate.

[0066] In implementation, the general value range of the preset first prediction error amount is [0.6%, 1%].

[0067] Preferably, the first prediction error amount is preset to be 0.8%.

[0068] In implementation, the general value range of the preset second test update rate is [0.03, 0.05].

[0069] Preferably, the preferred embodiment of the preset second test update rate is 0.04.

[0070] Specifically, when the difference between the test update rate of the construction progress prediction model and the preset first test update rate is within 0.01, the passive update range of the construction progress prediction model is reduced to 0.9 times the original value; when the difference between the test update rate of the construction progress prediction model and the preset first test update rate exceeds 0.01, the passive update range of the construction progress prediction model is reduced to 0.95 times the original value for every 0.01 increase. For example, the test update rate of the construction progress prediction model is 0.06, and the edge recognition area of ​​the construction site in the passive update range of the construction progress prediction model for a building with a current area of ​​2,000 m2 is 400 m2. The edge recognition area of ​​the construction site in the passive update range of the construction progress prediction model is reduced to 400 m2×0.9×0.95=342 m2.

[0071] In implementation, the system of the present invention sets a preset first test update rate. Since the content related to the construction progress does not appear in the updated content, the real-time and accuracy of the update of the construction progress prediction model are reduced. By adjusting the passive update range of the construction progress prediction model, the details of the model are increased and the model accuracy is improved, the accuracy of the construction progress prediction model is improved.

[0072] Specifically, the control unit is connected to the standardization component and the prediction modeling component respectively, and is used to initially determine that the accuracy of the mapping establishment of the construction progress prediction model does not meet the requirements when the test update rate of the construction progress prediction model is greater than or equal to the preset first test update rate and less than or equal to the preset second test update rate, obtain the change in the mapping and the construction progress, and calculate the fit between the change in the mapping and the construction progress; if the fit between the change in the mapping and the construction progress is less than the preset fit, it is secondary determined that the accuracy of the mapping establishment of the construction progress prediction model does not meet the requirements, and the number of mappings of the composite mapping is reduced.

[0073] Specifically, the reduction range of the number of mappings of the composite mapping is determined according to the difference between the preset degree of fit and the degree of fit between the amount of change of the mapping and the construction progress.

[0074] Specifically, a composite mapping is one in which more than one mapping exists between two objects.

[0075] Specifically, the mapping variation means the variation of several groups of mappings between two objects.

[0076] Specifically, the calculation formula for the fitting degree between the mapped change and the construction progress is:

[0077]

[0078] Among them, r is the fitting degree between the mapping change and the construction progress, xi ,y i are the change amount and construction progress of the i-th group mapping, are the change amount of each group of mappings and the average value of construction progress respectively, and n is a natural number greater than 1.

[0079] In implementation, the general value range of the preset second test update rate is [0.01, 0.03].

[0080] Preferably, the preferred embodiment of the preset second test update rate is 0.02.

[0081] In implementation, the general range of preset fitness is [0.28, 0.34].

[0082] Preferably, the preset fitness degree is 0.3.

[0083] Specifically, the preset fit is determined by the difference between the change in the mapping and the fit of the construction progress. When the difference between the preset fit and the change in the mapping and the fit of the construction progress is within 0.02, the number of mappings of the composite mapping is reduced by 5; when the difference between the preset fit and the change in the mapping and the fit of the construction progress exceeds 0.02, the number of mappings of the composite mapping is reduced by 2 for every 0.01 that exceeds, for example, the fit of the change in the mapping and the construction progress is 0.26, the number of mappings of the current composite mapping is 20, and the number of mappings of the composite mapping is reduced to 20-5-2×2=11.

[0084] In implementation, the system of the present invention sets a preset degree of fit. During construction, certain construction conditions may change with changes in the environment or time, resulting in differences between the construction progress and the actual model. By reducing the number of mappings of the composite mapping, information loss can be compensated, and more abundant constraints can be provided for the model, thereby reducing uncertainty in the modeling process and further improving the accuracy of mapping establishment of the construction progress prediction model.

[0085] So far, the technical solutions of the present invention have been described in conjunction with the preferred embodiments shown in the accompanying drawings. However, it is easy for those skilled in the art to understand that the protection scope of the present invention is obviously not limited to these specific embodiments. Without departing from the principle of the present invention, those skilled in the art can make equivalent changes or substitutions to the relevant technical features, and the technical solutions after these changes or substitutions will fall within the protection scope of the present invention.

Claims

1. An intelligent building construction progress management platform, characterized in that: include: A data collection unit, used to collect primary construction characteristic data and construction standard data; a data processing unit connected to the data acquisition unit, for comparing the primary construction feature data with the construction standard data to eliminate abnormal data and output secondary construction feature data; a progress simulation unit connected to the data processing unit and used to simulate the construction progress according to the secondary construction feature data, including a prediction modeling component used to establish a construction progress prediction model according to the secondary construction feature data and an updating component connected to the prediction modeling component and used to update the construction progress prediction model; A control unit, which is respectively connected to the data acquisition unit, the data processing unit and the progress simulation unit, and is used to determine the accuracy of the construction progress management according to the prediction error of the construction progress, determine whether to adjust the number of comparison types of the secondary construction feature data according to the judgment result of the accuracy of the construction progress management, adjust the passive update range of the construction progress prediction model according to the prediction error and the test update rate of the construction progress prediction model, and adjust the number of mappings of the composite mapping according to the test update rate of the construction progress prediction model and the change amount of the mapping and the degree of fit of the construction progress.

2. The intelligent building construction progress management platform according to claim 1 is characterized in that: It also includes a database connected to the data acquisition unit and the data processing unit respectively for storing the primary construction feature data, the secondary construction feature data and the construction standard data respectively.

3. The intelligent building construction progress management platform according to claim 2 is characterized in that: The progress simulation unit also includes a real-time modeling component for establishing a real-time construction model according to the secondary construction feature data.

4. The intelligent building construction progress management platform according to claim 3 is characterized in that: The control unit is respectively connected to the prediction modeling component and the actual modeling component, and is used to compare the construction progress prediction model and the actual construction model to obtain the prediction error of the construction progress. If the prediction error of the construction progress is greater than a preset second prediction error, it is determined that the accuracy of the construction progress management does not meet the requirements, and the number of comparison types of the secondary construction feature data is increased.

5. The intelligent building construction progress management platform according to claim 4 is characterized in that: The formula for the predicted error of the construction progress is: n=n1-n2 Among them, n is the prediction error of the construction progress, n1 is the actual completed construction progress of the actual construction model, and n2 is the predicted completed construction progress of the construction progress prediction model.

6. The intelligent building construction progress management platform according to claim 5 is characterized in that: The increase range of the number of comparison types of the secondary construction feature data is determined according to the difference between the predicted error amount of the construction progress and the preset second predicted error amount.

7. The intelligent building construction progress management platform according to claim 6 is characterized in that: The control unit is connected to the update component, and is used to initially determine that the accuracy of the construction progress prediction model does not meet the requirements when the prediction error of the construction progress is greater than or equal to the preset first prediction error and less than or equal to the preset second prediction error, and obtain the test update rate of the construction progress prediction model. If the test update rate of the construction progress prediction model is greater than the preset second test update rate, it is secondary determined that the accuracy of the construction progress prediction model does not meet the requirements, and the passive update range of the construction progress prediction model is reduced.

8. The intelligent building construction progress management platform according to claim 7 is characterized in that: The reduction range of the passive update range of the construction progress prediction model is determined according to the difference between the test update rate of the construction progress prediction model and the preset second test update rate.

9. The intelligent building construction progress management platform according to claim 8, characterized in that: The control unit is connected to the standardization component and the prediction modeling component respectively, and is used to initially determine that the accuracy of the mapping establishment of the construction progress prediction model does not meet the requirements when the test update rate of the construction progress prediction model is greater than or equal to the preset first test update rate and less than or equal to the preset second test update rate, obtain the change in the mapping and the construction progress, and calculate the fit between the change in the mapping and the construction progress; if the fit between the change in the mapping and the construction progress is less than the preset fit, secondly determine that the accuracy of the mapping establishment of the construction progress prediction model does not meet the requirements, and reduce the number of mappings of the composite mapping.

10. The intelligent building construction progress management platform according to claim 9, characterized in that: The reduction range of the number of mappings of the composite mapping is determined according to the difference between the preset degree of fit and the degree of fit between the amount of change of the mapping and the construction progress.

Citation Information

Patent Citations

  • Method for three-dimensional design and construction progress simulating interaction of underground cavern group

    CN105912780A

  • Project progress supervision system based on BIM

    CN111369226A

  • Construction project distribution system based on decoration construction progress analysis

    CN117172509A

  • Progress, quality and cost integrated management and control system based on BIM and block chain

    CN118378953A