Electrical configuration and comprehensive control method of hydroelectric generating set battery energy storage and calculation center
By configuring the battery energy storage system on the DC bus of the hydropower unit and combining the coordinated control system, the data center and pumped storage electrical grid are realized, the problem of resource waste and mechanical wear is solved, and the system's response and reliability are improved , realizes efficient utilization of resources and second-level adjustment of the power grid.
Patent Information
- Application Number
- CN202411269246.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-11
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2044-09-11
AI Technical Summary
In the prior art, the electrical configuration and comprehensive control methods of the data center and pumped storage fail to fully utilize the electrical coupling between the two, resulting in waste of resources and mechanical wear, and it is difficult to achieve second-level response power adjustment.
The battery energy storage system is configured on the DC bus of the hydroelectric unit, and through the coordination control system, combining hydroelectric power, battery energy storage and calculation load, the three-phase AC bus and DC bus are connected to the grid, and asynchronously through the AC converter and double-feeding The motor rotor is connected to realize peak and frequency regulation of the power grid, reducing frequent frequency regulation of the hydroelectric unit.
It realizes full utilization of resources, reduces mechanical wear of hydroelectric units, improves system reliability and fault response capabilities, reduces operation and maintenance costs, and meets the frequency modulation of the power grid through battery energy storage and second-level response capabilities of calculation load. and peak shaving demand.
Smart Images

Figure CN119070359A_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the field of energy supply, and in particular relates to an electrical configuration and a comprehensive control method of a battery energy storage and computing center of a hydropower unit. Background Art
[0002] The power consumption of computing loads such as data centers and supercomputing centers is growing rapidly. The energy supply mode dominated by thermal power will greatly increase the carbon emissions and pollution of computing loads. Therefore, the low-carbon development of computing loads can be achieved by increasing the proportion of renewable energy in supplying energy to computing loads. In addition, considering the electricity price and future carbon emission costs, new energy as the main power supply to computing loads can save the production cost of computing. Photovoltaic and wind power can be used as important sources of electricity for computing loads. However, photovoltaic and wind power are volatile and intermittent and cannot meet the energy demand of computing loads. Chinese patent application CN202110455530.5 proposes a data center battery charging and discharging optimization control method and device, selects the appropriate time to charge and discharge the battery, realizes the peak shaving and valley filling of the data center power supply, so as to maximize the storage benefits of the energy storage battery, thereby reducing the electricity bill and total cost of ownership of the data center. Chinese patent application CN202010136529.1 proposes a data center photovoltaic storage coordinated optimization configuration method and system, which optimizes the electricity price of the data center through the configuration of photovoltaic and battery energy storage. Although the current battery energy storage capacity can reach 100MW, considering the technical feasibility and economic feasibility, the current battery energy storage system is more suitable for the application scenario of 10MW data center.
[0003] From the perspective of technical feasibility and economic feasibility, pumped storage is still the most ideal energy storage system at present. In the context of a single large data center or data center cluster with a capacity exceeding 1000MW, pumped storage is an ideal peak-shaving power source and backup (emergency) power source for large data centers. Tencent once proposed to build a data center near a pumped storage power station, and believed that: for data centers, pumped storage power stations act like a super battery, charging at night and discharging during the day. This mature energy storage technology can provide frequency stabilization filtering and power outage protection for data centers. At the same time, the two large-capacity reservoirs of the pumped storage power station are equivalent to two super cold storage tanks or reservoirs in the data center. The deep lake water can be used for continuous cooling and heat dissipation and water replenishment in the data center. Storing a large amount of cold water means storing a large amount of standby cooling capacity. In addition, for the computing load itself, it also has the characteristics of flexible scheduling, so that the power can be flexibly adjusted. Tencent has conducted research on the coordination of computing power-power flexibility in data centers. By judging the computing power-power characteristics of computing tasks on the server, it can reduce the peak load of the power grid without affecting business operations. In addition, data centers can also participate in demand-side responses at the minute or second level, or participate in the electricity spot market and the electricity ancillary services market, and have the characteristics of flexible electricity response.
[0004] However, the combination of data centers and pumped storage should not be just about geographical proximity and using the water source of pumped storage for cooling, or the data center and pumped storage being controlled and responded to according to the needs of the power grid respectively. Therefore, it is necessary to continue to deeply explore the electrical configuration between the two and the comprehensive control method of mutual coupling. Summary of the invention
[0005] In order to solve the above technical problems, the present invention provides an electrical configuration and comprehensive control method for a battery energy storage and computing center of a hydropower unit. A battery energy storage system is configured on the DC bus of the motor of the hydropower unit. At the same time, the DC bus and the three-phase AC bus simultaneously supply energy for the computing load (data center or supercomputing center). The AC bus is connected to the stator of the doubly fed asynchronous motor. The doubly fed asynchronous motor, battery energy storage (after AC-DC conversion), and computing load are all connected to the grid through a three-phase AC bus connection transformer. At the same time, the battery energy storage and computing load are connected to the rotor of the doubly fed asynchronous motor and the three-phase AC bus through the DC bus and the AC-DC converter.
[0006] Under the control of the coordinated control system, the hydropower, battery energy storage, and computational load are controlled by the hydropower power control system, the battery power control system, and the computational load power control system to respond to the power command of the power grid and participate in the power regulation of the power grid. Among them, the computational load can flexibly respond to the change of power command, and cooperate with hydropower and battery energy storage to participate in the peak regulation of the power grid; the computational load and battery energy storage have the power response capability of seconds. As the frequency modulation power supply, the hydropower unit does not participate in the frequency modulation, reducing the mechanical wear caused by frequent dynamic power changes. When the hydropower unit uses a full-power converter to drive the synchronous motor, the battery energy storage is configured on the DC bus of the full-power converter, and the DC bus and the three-phase AC bus supply power to the computational load at the same time. When the hydropower unit uses a synchronous motor to directly connect to the grid, the battery energy storage is connected to the three-phase AC bus through the AC-DC converter, and the DC bus and the three-phase AC bus supply energy to the computational load at the same time. In addition, the battery energy storage and the computational load can share a grid-connected transformer with the synchronous motor, or use another transformer to connect to the grid.
[0007] In order to achieve the above object, the present invention adopts the following technical solution: The electrical configuration and comprehensive control method of the battery energy storage and computing center of the hydropower unit is that the battery energy storage is configured on the DC bus of the motor of the hydropower unit. At the same time, the DC bus and the three-phase AC bus supply energy to the computing load at the same time. The three-phase AC bus is connected to the stator of the doubly-fed asynchronous motor. The doubly-fed asynchronous motor, battery energy storage, and computing load are all connected to the grid through the three-phase AC bus connection transformer. At the same time, the battery energy storage and computing load are connected to the rotor of the motor and the three-phase AC bus through the DC bus; the computing load is powered by the DC bus and the three-phase AC bus, and the power of the DC bus comes from the battery Energy storage and converter, the power of the three-phase AC bus comes from the hydropower unit and the power grid, and the power supply instructions of the DC bus and the three-phase AC bus are distributed by the computing load power control system; the coordination control system is connected to the hydropower power control system, the battery energy storage power control system, and the computing power control system, and sends power control instructions and receives status feedback signals; the hydropower power control system is connected to the AC-DC-AC converter and the guide vane; the battery energy storage power control system is connected to the AC-DC-AC converter; the computing task scheduling system receives the computing task instructions, connects to the computing power control system, and connects to the computing load actuator; The coordinated control system receives power instructions from the power grid and the power grid frequency signal. According to the status of the hydropower units, battery energy storage and computing center, the coordinated control system sends power instructions to the hydropower units, battery energy storage and computing center respectively. The hydropower units, battery energy storage and computing center respond to the power instructions and feed back the power tracking response information to the coordinated control system for mutual power ratio compensation. The coordinated control system configures the upper and lower limits of the frequency modulation power of the battery energy storage and computing center according to the status of the battery energy storage and computing center, and transmits the instructions to the battery energy storage power control system and the computing load power control system. The battery energy storage power control system and the computing load power control system determine the frequency modulation response rate according to the status of the battery energy storage and the computing load, receive the power grid frequency signal from the coordinated control system, and participate in the power grid frequency modulation.
[0008] Furthermore, the coordinated control system receives power commands and frequency signals from the power grid; at the same time, the coordinated control system receives information from the hydropower power control system to obtain the status of each hydropower unit and the water level of the reservoir, which are used to form the hydropower power and power generation curve; the coordinated control system receives information from the battery energy storage power control system to obtain the battery health status; the coordinated control system receives information from the computational load power control system to obtain the real-time computational load power, the minimum required computational load power, and the predicted curve of the future computational load power.
[0009] Furthermore, the computing load responds to the computing task instructions and the power instructions of the coordination control system at the same time. The computing task instructions are issued to the computing task scheduling system, which decomposes the tasks into delay-tolerant tasks and non-delay-tolerant tasks, and calculates the power of the two types of tasks respectively, and feeds back the power to the computing load power control system. The computing load power control system calculates the allowable fluctuation range of the overall power of the computing load and feeds back to the coordination control system; in the power composition of the total computing load, the power of non-delay-tolerant tasks is a power component that must be met, and the power of delay-tolerant tasks can be adjusted and belongs to the fluctuating component in the total computing load power.
[0010] Furthermore, the coordinated control system calculates and issues power control instructions for the computing load based on the allowable fluctuation range of the overall power of the computing load, and transmits them to the computing task scheduling system through the computing load power control system. The computing task scheduling system processes and decomposes the allocation of delay-tolerant tasks and non-delay-tolerant tasks, and transmits the instructions to the computing load execution unit. At the same time, the measured actual computing load power is fed back to the coordinated control system through the computing load power control system to compensate for the error in tracking the computing load power instruction.
[0011] Furthermore, when the system composed of hydropower units, battery energy storage and computing loads performs peak load regulation on the power grid, the coordinated control system calculates and distributes power instructions based on the status, power and output forecast of the hydropower units, battery energy storage and computing center.
[0012] Furthermore, when the system composed of hydropower units, battery energy storage and computing loads modulates the frequency of the power grid, the hydropower units do not participate in the frequency modulation response, and the dynamic changes in power are borne by the battery energy storage and the computing load; the battery energy storage power control system and the computing load power control system respectively feed back the adjustable power range to the coordinated control system, and at the same time receive the power grid frequency signal from the coordinated control system, the coordinated control system determines the upper and lower limits of the frequency modulation power borne by the battery energy storage and the computing load respectively and passes the configuration instructions to the power control systems of the battery energy storage and the computing load, and the frequency modulation response rate and climbing rate are determined by the power control systems of the battery energy storage and the computing load according to their respective states.
[0013] Furthermore, the computational load responds to the dynamic power required by frequency modulation by dynamically changing the power of delay-tolerant tasks.
[0014] Beneficial effects: (1) Hydropower units can not only serve as power sources or energy storage systems for the power grid, but can also serve as regulating power sources and long-term backup power sources for computing loads (data centers or supercomputing centers). Since computing loads must be equipped with battery energy storage as an emergency power source, but battery energy storage is only activated in an emergency, resulting in a waste of resources, the integrated configuration of computing loads and their battery energy storage systems with hydropower can broaden the frequency regulation and peak regulation functions of battery energy storage power grids. In this way, hydropower can serve as an emergency power source and peak regulation power source for computing loads, and the battery energy storage that is standard for computing loads can participate in peak regulation and frequency regulation of the power grid, achieving the effect of full utilization of resources.
[0015] (2) The calculated load itself can flexibly adjust power, and the battery energy storage power response is fast. The two can jointly provide the frequency response power required by the power grid. There is no need for frequent frequency adjustment of hydropower units. Hydropower units only perform peak regulation and respond to slowly changing power instructions. This can reduce mechanical wear of hydropower units, reduce the probability of maintenance and power outages, and save operation and maintenance costs.
[0016] (3) The computing load is powered by both the DC bus and the AC bus. The dual power supply mode can greatly improve the reliability of the system and its ability to cope with faults. Battery energy storage is configured on the DC bus, which can flexibly adjust and coordinate the power supply of the battery energy storage and the AC bus to the computing load. At the same time, the power distribution between the AC bus, rotor, battery energy storage, and computing load is more flexible and the control is simpler. In this way, the power at the three-phase AC bus end and the rotor winding end of the AC-DC-AC converter does not have to be equal, which achieves decoupling between the two, decoupling the motor control and the grid-side AC-DC conversion control, and reducing the control requirements.
[0017] (4) The electrical and control systems of the hydropower units and computing loads are integrated and share power and communication (control) interfaces, enabling flexible scheduling of power and computing power within the station. There is no need to build separate power and communication networks, saving costs and resources. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1 It is a schematic diagram of the configuration of the double-fed asynchronous motor and the electrical system of the data center / supercomputing center; Figure 2 Schematic diagram of the electrical system configuration of the synchronous motor controlled by the full power inverter and the data center / supercomputing center; Figure 3 Schematic diagram of the electrical system configuration of synchronous motors directly connected to the grid and data centers / supercomputing centers; Figure 4 Schematic diagram of the direct grid-connected synchronous motor and the data center / supercomputing center connected to the grid through different transformers; Figure 5This is a control block diagram of the battery energy storage of the hydropower unit and the electrical configuration and integrated control method of the data center / supercomputing center of the present invention.
[0019] Among them, the figure marks are: 101 is a hydraulic unit, 102 is a water diversion pipe, 103 is a water outlet, 104 is a guide vane system, 105 is a doubly fed asynchronous motor, 106 is an AC-DC-AC converter, 107 is a first calculated load, 108 is a first battery energy storage, 109 is a first DC bus, 110 is a first three-phase AC bus, 111 is a fifth transformer, 112 is a first hydropower power control system, 113 is a first calculated load power control system, 114 is a first coordinated control system, 201 is a first synchronous motor, 202 is a first converter, 203 is a grid-connected transformer, 204 is a second battery energy storage, 205 is a second three-phase AC bus, 206 is a second DC bus, 207 is a second calculated load, 208 is a first 2. The second calculated load power control system, 209 is the second hydropower power control system, 210 is the second coordinated control system, 301 is the second synchronous motor, 302 is the second transformer, 303 is the AC-DC converter, 304 is the third battery energy storage, 305 is the third DC bus, 306 is the third three-phase AC bus, 307 is the third calculated load, 308 is the third calculated load power control system, 309 is the third hydropower power control system, 310 is the third coordinated controller, 401 is the third synchronous motor, 402 is the third transformer, 403 is the fourth calculated load, 404 is the fourth transformer, 405 is the AC-DC converter, 406 is the fourth three-phase AC bus, 407 is the fourth battery energy storage, and 408 is the fourth DC bus. DETAILED DESCRIPTION
[0020] In order to make the purpose, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not intended to limit the present invention. In addition, the technical features involved in the various embodiments of the present invention described below can be combined with each other as long as they do not conflict with each other.
[0021] like Figure 1As shown, the hydropower unit 101 is connected to the doubly-fed asynchronous motor 105, the three-phase output of the stator winding of the doubly-fed asynchronous motor 105 is connected to the fifth transformer 111, the fifth transformer 111 is connected to the power grid, the three-phase output of the rotor winding of the doubly-fed asynchronous motor 105 is connected to the AC-DC-AC converter 106, the AC-DC-AC converter 106 has a first DC bus 109, the first DC bus 109 is connected to the first battery energy storage 108, the first three-phase AC bus 110 and the first DC bus 109 are simultaneously connected to the first calculated load 107, and jointly supply power to the first calculated load 107. The power of the hydropower unit is controlled by controlling the first coordinated control system 114 to change the guide vane and controlling the AC-DC-AC converter 106 to change the working condition of the doubly-fed asynchronous motor 105. The first calculated load power control system 113 is connected to the first calculated load 107 and the first coordinated control system 114, and is used to change the real-time power of the first calculated load 107 in different ways. The AC-DC-AC converter 106 can not only control the working condition of the double-fed asynchronous motor 105, but also control the power of the first battery energy storage 108 connected to the grid through the AC-DC-AC converter 106. The first coordinated control system 114 is connected to the first hydropower power control system 112, the first calculated load power control system 113, and the AC-DC-AC converter 106, and is used to coordinate the power of the first hydropower power control system 112, the first calculated load power control system 113, and the AC-DC-AC converter 106, and control the power of the entire system connected to the grid through the fifth transformer 111. The first hydropower power control system 112 is connected to the guide vane system 104, the AC-DC-AC converter 106, and the first coordinated control system 114. The hydropower power control system 112 receives instructions from the first coordinated control system 114 and feeds back the state of the hydropower unit. The first hydropower power control system 112 controls the guide vane opening of the guide vane system 104, and controls the working condition of the double-fed asynchronous motor 105 by controlling the AC-DC-AC converter 106, thereby controlling the power of the hydropower unit.
[0022] Preferably, the hydraulic unit 101 may be a water turbine, a water pump or a water pump turbine.
[0023] Preferably, the first computing load 107 may be a data center, a supercomputing center or an intelligent data center.
[0024] like Figure 2As shown, when the motor is a synchronous motor controlled by a full-power power electronic converter, the first synchronous motor 201 is connected to the grid through the grid-connected transformer 203 after passing through the first converter 202, and the second battery energy storage 204 is configured on the second DC bus 206 of the first converter 202, and the second three-phase AC bus 205 and the second DC bus 206 simultaneously supply energy to the second calculated load 207. The second calculated load power control system 208 controls the power of the second calculated load 207. The second hydropower power control system 209 controls the working condition of the first synchronous motor 201 by controlling the first converter 202, and controls the water flow by controlling the guide vanes, so as to achieve the purpose of controlling the hydropower power. The first converter 202 is a full-power frequency converter, which can not only control the working condition of the first synchronous motor 201, but also control the grid-connected power of the second battery energy storage 204 through the first converter 202. The second coordinated control system 210 coordinates and controls the power instructions of the second calculated load power control system 208, the second hydropower power control system 209, and the first converter 202, and controls the power of the entire system composed of the hydropower unit, the battery energy storage and the computing center connected to the grid through the grid-connected transformer 203. The second coordinated control system 210 is respectively connected to the second calculated load power control system 208, the second hydropower power control system 209, and the first converter 202. The second calculated load power control system 208 is also connected to the second calculated load 207, and the second hydropower power control system 209 is also connected to the first converter 202 and the guide vane system.
[0025] like Figure 3 As shown, when the motor is a synchronous motor directly connected to the grid, the three-phase output of the stator of the second synchronous motor 301 is connected to the second transformer 302, and connected to the grid through the second transformer 302. The AC-DC converter 303 is connected to the third three-phase AC bus 306 and the third DC bus 305, wherein the third battery energy storage 304 is connected to the third DC bus 305, and the third three-phase AC bus 306 and the third DC bus 305 jointly supply energy for the third calculated load 307. The third calculated load power control system 308 controls the power of the third calculated load 307 in real time, the third hydropower power control system 309 controls the power of the hydropower unit by controlling the guide vanes, the AC-DC converter 303 controls the grid-connected power of the third battery energy storage 304, and the third coordination controller 310 coordinates the power control instructions of the third calculated load power control system 308, the third hydropower power control system 309, and the AC-DC converter 303.
[0026] like Figure 4 As shown in Figure 2, when the synchronous motor directly connected to the grid and the data center / supercomputing center (including battery energy storage) are connected to the grid through their own transformers, their structure is similar to Figure 3The systems shown are similar, except that the third synchronous motor 401 is connected to the grid via the third transformer 402, and the fourth calculation load 403 is connected to the grid via the fourth transformer 404. The fourth three-phase AC bus 406 and the fourth DC bus 408 simultaneously supply energy to the fourth calculation load 403, the AC-DC converter 405 connects the fourth three-phase AC bus 406 and the fourth DC bus 408, and the fourth battery energy storage 407 is configured on the fourth DC bus 408.
[0027] like Figure 5 As shown, the electrical configuration and comprehensive control method of the battery energy storage and computing center of the hydropower unit of the present invention include: the coordinated control system receives the power command of the power grid and the frequency signal of the power grid; at the same time, the coordinated control system receives information from the hydropower power control system to obtain the status of each hydropower unit, the water level of the reservoir and other information related to the hydropower power and the power generation curve (or the pumped storage power and the storage energy); the coordinated control system receives information from the battery energy storage power control system to obtain the battery health status, the available energy storage power and the storage energy and other related information; the coordinated control system receives information from the calculation load power control system to obtain the real-time calculation load power, the minimum required calculation load power, and the prediction curve of the future calculation load power.
[0028] The computing load responds to the computing task instruction and the power instruction of the coordinated control system at the same time. The computing task instruction is issued to the computing task scheduling system, which decomposes the task into delay-tolerant tasks and non-delay-tolerant tasks, and calculates the power of the two types of tasks respectively (in the composition of the total computing load power, the power of non-delay-tolerant tasks is a power component that must be satisfied, and the power of delay-tolerant tasks can be adjusted, which belongs to the fluctuating component of the total computing load power), and feeds it back to the computing load power control system. The computing load power control system can calculate the allowable fluctuation range of the overall computing load power and feed it back to the coordinated control system. The coordinated control system calculates and issues the power control instruction of the computing load according to the allowable fluctuation range of the overall computing load power, and transmits it to the computing task scheduling system through the computing load power control system. The system processes and decomposes the allocation of delay-tolerant tasks and non-delay-tolerant tasks, and transmits the instruction to the computing load execution unit. At the same time, the measured actual computing load power is fed back to the coordinated control system through the computing load power control system to compensate for the error of computing load power instruction tracking.
[0029] In addition, the computational load is powered by both the DC bus and the three-phase AC bus. The DC bus power comes from battery energy storage and converters, and the three-phase AC bus power comes from hydropower units and the power grid. The computational load power control system distributes the power supply instructions for the DC bus and the three-phase AC bus.
[0030] When the system performs peak load regulation on the power grid, the coordinated control system calculates and distributes power instructions based on the hydropower units, battery energy storage, calculated load status, power, and output forecast.
[0031] When the system composed of hydropower units, battery energy storage and computing load modulates the frequency of the power grid, in order to avoid mechanical wear of the hydropower units (dynamic hydraulic impacts such as pump / turbine blades, water diversion pipes, volutes, bearings, etc.), the hydropower units do not participate in the frequency modulation response, and the dynamic power changes are borne by the battery energy storage and the computing load. The battery energy storage power control system is set together with the battery energy storage and the frequency converter / converter, connected to the coordination control system, receives the instructions of the coordination control system, and feeds back the status of the battery energy storage system to the coordination control system. The battery energy storage power control system and the computing load power control system respectively feed back the adjustable power range to the coordination control system, and at the same time receive the grid frequency signal from the coordination control system. The coordination control system determines the upper and lower limits of the frequency modulation power borne by the battery energy storage and the computing load, and transmits the configuration instructions (the upper and lower limits of the frequency modulation power borne by the battery energy storage and the computing load) to the battery energy storage power control system and the computing load power control system.
[0032] The frequency modulation response rate and ramp rate are determined by the battery energy storage power control system and the computing load power control system according to their respective states. The computing load responds to the dynamic power required by the frequency modulation by dynamically changing the power of the delay-tolerant task.
Claims
1. Electrical configuration and integrated control method of battery energy storage and computing center of hydropower unit, characterized in that: Battery energy storage is configured on the DC bus of the motor of the hydropower unit. At the same time, the DC bus and the three-phase AC bus supply energy to the calculation load at the same time. The three-phase AC bus is connected to the stator of the doubly fed asynchronous motor. The doubly fed asynchronous motor, battery energy storage, and calculation load are all connected to the grid through the three-phase AC bus to connect the transformer. At the same time, the battery energy storage and calculation load are connected to the rotor of the motor and the three-phase AC bus through the DC bus; the calculation load is powered by the DC bus and the three-phase AC bus. The power of the DC bus comes from the battery energy storage and the converter, and the power of the three-phase AC bus comes from the hydropower unit and the power grid. The power control system of the calculation load distributes the power supply instructions of the DC bus and the three-phase AC bus; the coordination control system is connected to the hydropower power control system, the battery energy storage power control system, and the calculation power control system and sends power control instructions and receives state feedback signals; the hydropower power control system is connected to the AC-DC-AC converter and the guide vane; the battery energy storage power control system is connected to the AC-DC-AC converter; the calculation task scheduling system receives the calculation task instructions, connects to the calculation power control system, and connects to the calculation load actuator; The coordinated control system receives power instructions from the power grid and the power grid frequency signal. According to the status of the hydropower units, battery energy storage and computing center, the coordinated control system sends power instructions to the hydropower units, battery energy storage and computing center respectively. The hydropower units, battery energy storage and computing center respond to the power instructions and feed back the power tracking response information to the coordinated control system for mutual power ratio compensation. The coordinated control system configures the upper and lower limits of the frequency modulation power of the battery energy storage and computing center according to the status of the battery energy storage and computing center, and transmits the instructions to the battery energy storage power control system and the computing load power control system. The battery energy storage power control system and the computing load power control system determine the frequency modulation response rate according to the status of the battery energy storage and the computing load, receive the power grid frequency signal from the coordinated control system, and participate in the power grid frequency modulation.
2. The electrical configuration and integrated control method of the battery energy storage and computing center of the hydropower unit according to claim 1 is characterized in that: The coordinated control system receives power commands and frequency signals from the power grid. At the same time, the coordinated control system receives information from the hydropower power control system to obtain the status of each hydropower unit and the water level of the reservoir, which are used to form the hydropower power and power generation curves. The coordinated control system receives information from the battery energy storage power control system to obtain the battery health status. The coordinated control system receives information from the calculated load power control system to obtain the real-time calculated load power, the minimum required calculated load power, and the predicted curve of the future calculated load power.
3. The electrical configuration and integrated control method of the battery energy storage and computing center of the hydropower unit according to claim 1 is characterized in that: The computing load responds to the computing task instructions and the power instructions of the coordination control system at the same time. The computing task instructions are issued to the computing task scheduling system, which decomposes the tasks into delay-tolerant tasks and non-delay-tolerant tasks, and calculates the power of the two types of tasks respectively, and feeds back to the computing load power control system. The computing load power control system calculates the allowable fluctuation range of the overall power of the computing load and feeds back to the coordination control system; in the power composition of the total computing load, the power of non-delay-tolerant tasks is a power component that must be met, and the power of delay-tolerant tasks can be adjusted, which belongs to the fluctuating component in the total computing load power.
4. The electrical configuration and integrated control method of the battery energy storage and computing center of the hydropower unit according to claim 1 is characterized in that: The coordinated control system calculates and issues power control instructions for the computing load based on the allowable fluctuation range of the overall power of the computing load, and transmits them to the computing task scheduling system through the computing load power control system. The computing task scheduling system processes and decomposes the allocation of delay-tolerant tasks and non-delay-tolerant tasks, and transmits the instructions to the computing load execution unit. At the same time, the measured actual computing load power is fed back to the coordinated control system through the computing load power control system to compensate for the error in computing load power instruction tracking.
5. The electrical configuration and integrated control method of the battery energy storage and computing center of the hydropower unit according to claim 1 is characterized in that: When the system composed of hydropower units, battery energy storage and computing loads performs peak load regulation on the power grid, the coordinated control system calculates and distributes power instructions based on the status, power and output forecast of the hydropower units, battery energy storage and computing center.
6. The electrical configuration and integrated control method of the battery energy storage and computing center of the hydropower unit according to claim 3 is characterized in that: When the system composed of hydropower units, battery energy storage and computing loads modulates the frequency of the power grid, the hydropower units do not participate in the frequency modulation response, and the dynamic changes in power are borne by the battery energy storage and the computing load; the battery energy storage power control system and the computing load power control system respectively feed back the adjustable power range to the coordinated control system, and at the same time receive the grid frequency signal from the coordinated control system. The coordinated control system determines the upper and lower limits of the frequency modulation power borne by the battery energy storage and the computing load respectively and passes the configuration instructions to the power control systems of the battery energy storage and the computing load. The frequency modulation response rate and climbing rate are determined by the power control systems of the battery energy storage and the computing load according to their respective states.
7. The electrical configuration and integrated control method of the battery energy storage and computing center of the hydropower unit according to claim 1 is characterized in that: The computational load responds to the dynamic power required by frequency modulation by dynamically changing the power of delay-tolerant tasks.
Citation Information
Patent Citations
Data center battery charging and discharging optimization control method and device
CN113131584A
A method and system for coordinated optimization of optical and energy storage configuration in data centers
CN113364042B
Data center contact line power control method based on demand side responses
CN107086587A
Integrated power supply device for energy storage power station and data center load
CN111917170A
Distributed energy storage control coordination system
CN210178508U