Production equipment for heat-conducting fins and working method of production equipment
By designing production equipment for heat conduction sheets, automated bracket loading and riveting operations are realized, solving the problems of position error and low efficiency caused by manual operations, and improving production quality and efficiency.
Patent Information
- Application Number
- CN202411365049.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-29
- Publication Date
- 2024-12-06
AI Technical Summary
During the production process of heat conductor sheets, position errors are caused by manual operation, which affects the quality of riveting, increases the product's unqualification rate, and is inefficient in work, which makes the staff burden.
A production equipment for heat conduction sheets is designed, including a conveyor device, a bracket loading device, an assembly device and a riveting mechanism. Through automated bracket loading, pre-installation and riveting operations, manual intervention is reduced and accuracy is ensured. and efficiency.
It improves the quality and efficiency of heat conductor flake production, reduces the error of manual operation, reduces the burden on staff, and improves the overall production progress and product qualification rate.
Smart Images

Figure CN119077103A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of heat conducting sheets, and in particular to production equipment for heat conducting sheets and a working method thereof. Background Art
[0002] Heat dissipation components are generally used in electronic products to dissipate heat from the products to protect product performance. The heat dissipation components have a number of arranged heat conductive sheets. A single heat conductive sheet generally includes a sheet made of a heat conductive material and brackets mounted on both ends of the sheet.
[0003] At present, when producing thermal conductive sheets, multiple sheets are usually arranged at intervals on a conveying device and conveyed by the conveying device. The staff needs to manually remove the sheets and place them on a workbench next to the conveying device. The protrusions of the two brackets are aligned and penetrated through the through holes formed at both ends of the sheet to pre-install the bracket on the sheet. Then the staff needs to place the sheet pre-installed with the bracket on the transmission device in the manner of placing the sheet on the top of the bracket. The conveying device conveys the sheet pre-installed with the bracket to the bottom of the riveting device, and then the riveting device heats and presses the protrusion of the bracket penetrating the sheet so that the sheet and the bracket are riveted into a thermal conductive sheet. In this process, the position of the sheet pre-installed with the bracket that is re-placed on the conveying device may deviate from the position of the corresponding sheet on the conveying device before taking it. Due to the position error, the riveting welding head of the subsequent riveting welding device may not be able to align with the protrusion of the bracket, resulting in the riveting quality being affected and the unqualified rate of the product increasing. In addition, the entire pre-installation operation is performed manually, which is time-consuming and labor-intensive, with relatively low work efficiency, and prolongs the entire production schedule.
[0004] In addition, before pre-installation, the brackets are usually carried by pallets. Multiple pallets carrying multiple brackets arranged in an array are stacked and pushed to the vicinity of the workbench by the staff using a forklift. When the pallet on the top layer is empty after multiple rounds of taking, the staff needs to manually remove the empty pallet. The empty pallets that have been taken out multiple rounds are stacked and finally pushed away by the staff using a forklift so that the subsequent bracket loading operation can be carried out. In this process, the loading operation of the brackets and the unloading operation of the empty pallets are both performed by the staff, which greatly increases the workload of the staff, and the overall operation is time-consuming and labor-intensive, and the production progress is not ideal. Summary of the invention
[0005] In order to solve the above technical problems and achieve at least one advantage of the present invention, the present invention provides a production device for a thermally conductive sheet, the production device for a thermally conductive sheet comprising:
[0006] Carrying device;
[0007] The rack loading device comprises a first supporting mechanism and an integrated grasping mechanism, the first supporting mechanism comprises a rack loading component and a rack tray unloading component, the rack loading component comprises a loading starting end and a loading terminal arranged opposite to the loading starting end, the rack loading component can drive a plurality of stacked loading racks to move from the loading starting end to the loading terminal, the rack tray unloading component comprises a unloading starting end and a unloading terminal arranged opposite to the unloading starting end, the integrated grasping mechanism can transfer the racks on the rack tray located on the top layer and carried by the loading terminal, and transfer the empty rack racks located on the top layer to the unloading starting end, after the integrated grasping mechanism grasps the empty racks in multiple rounds and stacks them on the unloading starting end, the rack tray unloading component can drive a plurality of stacked empty racks to move from the unloading starting end to the unloading terminal;
[0008] An assembling device, the assembling device comprising:
[0009] A pre-installation mechanism, the pre-installation mechanism comprises a placement platform group and a pre-installation component, the placement platform group comprises a bracket bearing platform and a sheet placing platform, the sheet placing platform is used to place sheets, the integrated grabbing mechanism is configured to grab a plurality of pairs of brackets on the bracket tray carried by the feeding terminal and located on the top layer and transfer them to the bracket bearing platform, the pre-installation component can successively grab at least one pair of brackets carried by the bracket bearing platform and at least one sheet carried by the sheet placing platform and transfer them to the carrying device in sequence, each sheet is pre-installed on a pair of brackets in a manner of being plugged into at least one protrusion of a pair of brackets carried by the carrying device and spaced a predetermined distance apart;
[0010] At least one riveting welding mechanism is arranged above the carrying device and is located in the direction in which the sheet and the bracket are pre-assembled as a whole and are transported by the carrying device. The riveting welding mechanism can heat and press the protrusion of the bracket that passes through the sheet to rivet the sheet and the bracket into a heat conducting sheet.
[0011] According to one embodiment of the present invention, the loading starting end and the unloading starting end are arranged on the same side, the loading terminal and the unloading starting end are arranged on the same side, the conveying direction of the loading bracket pallet through the bracket loading component is opposite to the conveying direction of the empty bracket pallet through the bracket pallet unloading component, and the bracket support platform is on the same side as the loading terminal and is located on the side of the loading terminal away from the unloading starting end.
[0012] According to one embodiment of the present invention, the integrated grasping mechanism includes an integrated grasping component and a power component, the integrated grasping component includes a plurality of bracket grasping components and at least one bracket tray grasping component, the bracket grasping component is used to grasp the bracket, and the bracket tray grasping component is used to grasp an empty bracket tray, the bracket grasping component and the bracket tray grasping component are both installed on the power component and can be driven to move by the power component, and the positions of the bracket loading component, the bracket tray unloading component and the bracket supporting platform are all located below the trajectory of the integrated grasping component being driven by the power component to move.
[0013] According to one embodiment of the present invention, the pre-installed components include at least one pair of bracket grasping components, each pair of the bracket grasping components can grasp a pair of brackets carried by the bracket supporting platform and place the two brackets on the carrying device with a predetermined distance between them. The pre-installed components also include at least one sheet material grasping component, at least one sheet material grasping component can transfer a sheet of material carried by the sheet placing platform to the top of the carrying device and insert each sheet of material into at least one protrusion of a pair of brackets.
[0014] According to one embodiment of the present invention, the riveting mechanism includes a riveting component and a third power component, the riveting component is arranged above the carrying device, the riveting component includes a rivet assembly and a heating element, the rivet assembly is installed on the third power component and can be driven by the third power component to approach or move away from the carrying device, the rivet assembly has at least one pair of rivet heads, the heating element is installed on the rivet heads and can heat the rivet heads, and in the process of the rivet assembly being driven by the third power component to approach the carrying device, the two rivet heads in each pair are respectively pressed against a protrusion of two brackets of a pair, and the heating element heats the rivet heads so that the rivet heads heat-melt the protrusions and press them onto the surface of the sheet.
[0015] According to one embodiment of the present invention, the production equipment for the thermal conductive sheet includes a pressure resistance testing device, and the pressure resistance testing device includes at least one pressure resistance testing mechanism. The pressure resistance testing mechanism is arranged above the carrying device and is located in the direction in which the thermal conductive sheet is transported by the carrying device. The pressure resistance testing mechanism can perform pressure resistance testing on the thermal conductive sheet.
[0016] According to one embodiment of the present invention, the withstand voltage detection mechanism includes a withstand voltage detection component and a first driving mechanism, the withstand voltage detection component is arranged above the carrying device, the withstand voltage detection component includes a detection body and a pair of energized parts, the detection body is installed on the first driving mechanism and can be driven by the first driving mechanism to approach or move away from the carrying device, a pair of energized parts are installed on the detection body and transmit current through the detection body, when the detection body is driven by the first driving mechanism to approach the carrying device to abut against the thermal conductive sheet, the detection body is introduced with current by the energized parts to perform a withstand voltage test on the thermal conductive sheet.
[0017] According to one embodiment of the present invention, the withstand voltage detection mechanism also includes a monitoring component, which is used to detect the current or voltage of the circuit where the energized component is located. The production equipment for the thermal conductive sheet also includes a controller, and the monitoring component is communicatively connected to the controller. The controller determines whether the corresponding thermal conductive sheet has passed the withstand voltage test based on the feedback from the monitoring component. The withstand voltage detection device also includes a marking mechanism, which is arranged above the carrying device and is located in the direction in which the thermal conductive sheet after the withstand voltage test is transported by the carrying device. The marking mechanism and the carrying device are both controllably connected to the controller. The controller can control the transportation of the thermal conductive sheet by the carrying device and control the marking action of the marking mechanism based on the feedback from the monitoring component.
[0018] According to one embodiment of the present invention, the marking mechanism includes a marking member and a second driving mechanism, the marking member is arranged above the carrying device, and the marking member is installed on the second driving mechanism to drive it close to or away from the carrying device. When the pressure detection component performs a pressure test on a thermal conductive sheet, and the controller determines that the pressure test of the thermal conductive sheet is unqualified based on the feedback control of the monitoring component, the controller controls the carrying device to operate so as to transfer the corresponding thermal conductive sheet to the bottom of the marking member and stay there for a predetermined time, and the controller controls the second driving mechanism to operate so that the second driving mechanism drives the marking member to move close to the corresponding thermal conductive sheet and mark it, thereby marking the corresponding thermal conductive sheet as unqualified. When the pressure detection component performs a pressure test on a thermal conductive sheet, and the controller determines that the pressure test of the thermal conductive sheet is qualified based on the feedback control of the monitoring component, the controller controls the carrying device to operate so that the corresponding thermal conductive sheet moves under the marking member, and the controller controls the second driving mechanism to suspend operation.
[0019] In order to solve the above technical problems and achieve at least one advantage of the present invention, the present invention provides a working method for a production device for a thermally conductive sheet, comprising the following steps:
[0020] The bracket loading component drives a plurality of stacked loading bracket trays to move from the loading starting end to the loading terminal to load the brackets, and the integrated grasping mechanism grasps a plurality of brackets carried by the bracket tray and transfers them to the bracket carrying platform. After the integrated grasping mechanism grasps the brackets for multiple rounds to make the corresponding bracket trays empty, the integrated grasping mechanism grasps the empty bracket tray and transfers it to the unloading starting end. After the empty bracket trays grasped by the integrated grasping mechanism for multiple rounds are placed in a stacked manner at the unloading starting end, the bracket tray unloading component drives a plurality of stacked empty bracket trays to move from the unloading starting end to the unloading terminal to unload the empty bracket trays.
[0021] The pre-installed component successively grabs at least one pair of brackets carried by the bracket carrying platform and at least one sheet carried by the sheet placing platform and successively transfers them to the carrying device, and each sheet is pre-installed on a pair of brackets in a manner of being plugged into at least one protrusion of a pair of brackets carried by the carrying device and spaced a predetermined distance apart;
[0022] The pre-assembled sheet and bracket are transported by the conveying device and moved to the bottom of the riveting mechanism, and the riveting mechanism heats and presses the protrusion of the bracket penetrating the sheet to rivet and weld the sheet and the bracket into a heat conducting sheet. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] Figure 1 The schematic diagram of the structure of the production equipment for the thermal conductive sheet of the present invention is shown.
[0024] Figure 2 A partial structural stereogram of the production equipment for heat-conducting sheets according to the present invention is shown.
[0025] Figure 3 Shows Figure 2 A magnified view of the local structure.
[0026] Figure 4 Another partial structural stereogram of the production equipment for thermal conductive sheets according to the present invention is shown.
[0027] Figure 5 Shows Figure 4 A magnified view of the local structure.
[0028] Figure 6 The schematic diagram of the structure of the riveting welding mechanism of the production equipment for the heat conducting sheet according to the present invention is shown.
[0029] Figure 7 The schematic structural diagram of the pressure resistance detection device for the production equipment of the thermal conductive sheet according to the present invention is shown.
[0030] Figure 8Another partial structural stereogram of the production equipment for thermal conductive sheets according to the present invention is shown.
[0031] Fig. 9 Shows Figure 8 A magnified view of the local structure at point A.
[0032] Fig.10 Shows Figure 8 Enlarged view of the local structure at point B in the middle.
[0033] Fig.11 Shows Figure 8 Enlarged view of the local structure at point C in the middle.
[0034] Fig.12 Shows Figure 8 A three-dimensional diagram of the structure from another perspective. DETAILED DESCRIPTION
[0035] The following description is used to disclose the present invention so that those skilled in the art can implement the present invention. The preferred embodiments described below are only examples, and those skilled in the art can think of other obvious variations. The basic principles of the present invention defined in the following description can be applied to other embodiments, variations, improvements, equivalents, and other technical solutions that do not deviate from the spirit and scope of the present invention.
[0036] Those skilled in the art should understand that, in the disclosure of the present invention, the terms "longitudinal", "lateral", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside" and the like indicating the orientation or position relationship are based on the orientation or position relationship shown in the drawings, which are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operate in a specific orientation. Therefore, the above terms should not be understood as limiting the present invention.
[0037] It is to be understood that the term "one" should be understood as "at least one" or "one or more", that is, in one embodiment, the number of an element may be one, while in another embodiment, the number of the element may be multiple, and the term "one" should not be understood as a limitation on the quantity.
[0038] refer to Figure 1 to Figure 2, a production device for a heat conducting sheet according to a preferred embodiment of the present invention will be described in detail below, the production device for a heat conducting sheet includes a bracket loading device 10 and an assembly device 20, the bracket loading device 10 includes a first supporting mechanism 11 and an integrated grabbing mechanism 12, the first supporting mechanism 11 includes a bracket loading component 111, a plurality of bracket trays are stacked on the bracket loading component 111 and each bracket tray carries a plurality of brackets arranged at intervals. The assembly device 20 includes a pre-installation mechanism 21, the pre-installation mechanism 21 includes a placement platform group 211, the placement platform group 211 includes a bracket bearing platform 2111, the integrated grabbing mechanism 12 is configured to grab a plurality of pairs of brackets on the bracket trays on the top layer carried by the bracket loading component 111 and transfer them to the bracket bearing platform 2111.
[0039] The first supporting mechanism 11 further includes a rack tray unloading component 112. After the multiple racks supported by the rack tray on the top layer are all grabbed by the integrated grabbing mechanism 12 and transferred to the rack carrying platform 2111, the integrated grabbing mechanism 12 can grab an empty rack tray and transfer it to the rack tray unloading component 112. The empty rack trays grabbed by the integrated grabbing mechanism 12 in multiple rounds are placed in the rack tray unloading component 112 in a stacked manner.
[0040] Preferably, the bracket loading component 111 has a loading starting end 1111 and a loading terminal 1112 arranged opposite to the loading starting end 1111, and the bracket loading component 111 can drive a plurality of stacked loading bracket pallets to move from the loading starting end 1111 to the loading terminal 1112, and the integrated grasping mechanism 12 can transfer the bracket on the bracket pallet carried by the loading terminal 1112 and located on the top layer and transfer the empty pallet bracket located on the top layer to the bracket pallet unloading component 112, so that after the loading terminal 1112 is empty, the bracket loading component 111 can be used to supply the bracket in time.
[0041] Preferably, the support tray unloading component 112 has a unloading start end 1121 and a unloading terminal 1122 arranged opposite to the unloading start end 1121, and the integrated grabbing mechanism 12 can grab the empty support tray carried by the loading terminal 1112 and located at the top layer and transfer it to the unloading start end 1121. After the integrated grabbing mechanism 12 grabs the empty support trays for multiple rounds and stacks them at the unloading start end 1121, the support tray unloading component 112 can drive the stacked multiple empty support trays from the unloading start end 1121 to the unloading terminal 1122, so that the staff can fill the empty support trays with supports, thereby supplying the loading support trays to the support loading component 111.
[0042] It is worth mentioning that the loading starting end 1111 and the unloading starting end 1121 are arranged on the same side, the loading terminal 1112 and the unloading starting end 1121 are arranged on the same side, the conveying direction of the loading support pallet through the support loading component 111 is opposite to the conveying direction of the empty support pallet through the support pallet unloading component 112, and the support support platform 2111 is on the same side as the loading terminal 1112 and is located on the side of the loading terminal 1112 away from the unloading starting end 1121, so that the integrated grasping mechanism 12 can transfer the empty support pallet and the support while also facilitating the staff to fill the support and replenish the loading support pallet, thereby reducing the workload of the staff.
[0043] Preferably, the support loading component 111 and the support tray unloading component 112 are both implemented as belt conveyors.
[0044] refer to Figures 2 to 3 The integrated grabbing mechanism 12 includes an integrated grabbing member 121 and a power member 122. The integrated grabbing member 121 includes a plurality of support grabbing components 1211 and at least one support tray grabbing component 1212. The support grabbing component 1211 is used to grab a support, and the support tray grabbing component 1212 is used to grab an empty support tray. The support grabbing component 1211 and the support tray grabbing component 1212 are both mounted on the power member 122 and can be driven to move by the power member 122. The positions of the support loading component 111, the support tray unloading component 112 and the support bearing platform 2111 are all located below the track where the integrated grabbing member 121 is driven to move by the power member 122.
[0045] Specifically, when the bracket grabbing assembly 1211 is driven by the power component 122 to move above the loading terminal 1112 and each of the bracket grabbing assembly 1211 corresponds to a bracket carried by the bracket tray on the top layer, the bracket grabbing assembly 1211 is driven by the power component 122 to approach the bracket and grab the bracket, and then the bracket grabbing assembly 1211 is driven by the power component 122 to move above the bracket supporting platform 2111 and place the bracket on the bracket supporting platform 2111. After being carried by the loading terminal 1112 and being located at the top-level support pallet being empty, the support pallet grabbing assembly 1212 is driven by the power component 122 to move above the loading terminal 1112 and correspond to the empty support pallet, and then the support pallet grabbing assembly 1212 is driven by the power component 122 to approach the empty support pallet and grab the empty support pallet, and then the support pallet grabbing assembly 1212 is driven by the power component 122 to move above the unloading starting end 1121 and place the empty support pallet at the unloading starting end 1121.
[0046] Preferably, both the support grabbing assembly 1211 and the support tray grabbing assembly 1212 are implemented to include suction cups.
[0047] Preferably, the power component 122 is implemented including but not limited to a cylinder, a motor, a lead screw, etc.
[0048] refer to Figure 3 Furthermore, the support support platform 2111 includes a platform 21111 and multiple groups of positioning components 21112, wherein the positioning components 21112 are movably mounted on the upper surface of the platform 21111, and the platform 21111 is used to support the support grasped and moved by the integrated grasping mechanism 12. Each group of the positioning components 21112 is provided with two pairs, and the two positioning components 21112 of each pair are arranged opposite to each other and can be driven to increase or decrease the distance between them. After the support is transferred by the integrated grasping mechanism 12 and placed on the platform 21111, each pair of the positioning components 21112 is located on both sides of the corresponding support, and the two pairs of the positioning components 21112 of each group are respectively distributed in the length direction and the width direction of the corresponding support. The two pairs of positioning components 21112 in each group can be driven close to each other to clamp the bracket in the length and width directions of the bracket, so as to position the bracket, ensure the accuracy of the subsequent installation position, and ensure that the sheet can be accurately pre-installed on the bracket.
[0049] refer to Figure 1The production equipment for heat conducting sheets further comprises a conveying device 30, the pre-installation mechanism 21 further comprises a pre-installation component 212, and the placement platform group 211 further comprises a sheet placement platform 2112, and the sheet placement platform 2112 is used to place sheets. The pre-installation component 212 can successively grab at least one pair of brackets carried by the platform 21111 and at least one sheet carried by the sheet placement platform 2112 and successively transfer them to the conveying device 30, and each sheet is pre-installed on a pair of brackets in a manner of being plugged into at least one protrusion of a pair of brackets carried by the conveying device 30 and spaced a predetermined distance apart.
[0050] refer to Figures 2 to 3 The pre-installed component 212 includes at least one pair of bracket grabbing components 2121, and each pair of the bracket grabbing components 2121 can grab a pair of brackets carried by the bracket supporting platform 2111 and place them on the carrying device 30 in a manner such that the two brackets are spaced a predetermined distance apart.
[0051] The bracket grabbing and installing member 2121 includes at least one pair of bracket grabbing and installing components 21211 and a first power component 21212. The bracket grabbing and installing components 21211 are used to grab the bracket. The bracket grabbing and installing components 21211 are installed on the first power component 21212 and can be driven and moved by the first power component 21212. The positions of the bracket bearing platform 2111 and the carrying device 30 are both located below the moving track of the bracket grabbing and installing components 21211.
[0052] Preferably, the bracket capture assembly 21211 is implemented to include a suction cup.
[0053] Preferably, the first power assembly 21212 is implemented including but not limited to a cylinder, a motor, a lead screw, etc.
[0054] Specifically, when the bracket grasping and mounting assembly 21211 is driven by the first power assembly 21212 to move above the bracket supporting platform 2111 and each pair of the bracket grasping and mounting assembly 21211 corresponds to a pair of brackets, the bracket grasping and mounting assembly 21211 is driven by the first power assembly 21212 to approach the bracket and grasp the bracket, and then the bracket grasping and mounting assembly 21211 is driven by the first power assembly 21212 to move above the carrying device 30 and place the bracket on the carrying device 30, so that the carrying device 30 can transfer the bracket to the next process.
[0055] refer to Figures 4 to 5The pre-installed component 212 also includes at least one sheet material grasping and mounting component 2122. At least one sheet material grasping and mounting component 2122 can transfer a sheet material carried by the sheet material placement platform 2112 to the top of the carrier device 30 and insert each sheet material into at least one protrusion of a pair of brackets for pre-installation.
[0056] The sheet material grabbing and placing component 2122 includes at least one set of sheet material grabbing and placing components 21221 and a second power component 21222. The sheet material grabbing and placing components 21221 are used to grab sheets. The sheet material grabbing and placing components 21221 are installed on the second power component 21222 and can be driven and moved by the second power component 21222. The sheet material placement platform 2112 and the carrier device 30 are located below the moving track of the sheet material grabbing and placing components 21221.
[0057] Preferably, the sheet material grasping and mounting assembly 21221 is implemented to include a suction cup.
[0058] Preferably, the second power assembly 21222 is implemented to include but not limited to a cylinder, a motor, a lead screw, etc.
[0059] Specifically, when the sheet material grasping and mounting assembly 21221 is driven by the second power assembly 21222 to move above the sheet material placement platform 2112 and each group of the sheet material grasping and mounting assembly 21221 corresponds to a sheet material, the sheet material grasping and mounting assembly 21221 is driven by the second power assembly 21222 to approach the sheet material and grasp the sheet material, and then the sheet material grasping and mounting assembly 21221 is driven by the second power assembly 21222 to move above the carrying device 30, so that the sheet material and a pair of brackets can be pre-installed by the sheet material grasping and mounting assembly 21221.
[0060] refer to Figure 1 The conveying device 30 includes a plurality of carriers 31 and a conveying member 32. The plurality of carriers 31 are arranged side by side on the conveying member 32 and can be driven to move by the conveying member 32. A plurality of bearing portions 311 are formed on the surface of each carrier 31, and each pair of brackets is positioned at intervals on one of the bearing portions 311. The bracket grabbing assembly 21211 and the sheet material grabbing assembly 21221 can both be driven to move above the conveying member 32 to correspond to the carrier 31 conveyed by the conveying member 32. When a pair of brackets are positioned on one of the bearing portions 311, the sheet material is carried by the bearing portion 311 in a manner that the protrusions of the brackets penetrate through it.
[0061] Preferably, the conveying member 32 is implemented as a belt conveyor.
[0062] refer to Figure 1, the assembly device 20 includes at least one riveting and welding mechanism 22, which is arranged above the carrier device 30 and is located in the direction in which the sheet and the bracket are transported as a whole after pre-assembly by the carrier device 30. The riveting and welding mechanism 22 can heat and press the protrusion of the bracket that penetrates the sheet to rivet and weld the sheet and the bracket into a thermal conductive sheet. In this process, through the cooperation of the bracket feeding device 10, the assembly device 20 and the carrier device 30, the automatic loading of the bracket and the automatic unloading of the empty tray are realized. Compared with the prior art, there is no need to manually move the multiple stacked loading bracket trays, and when the bracket tray is emptied, there is no need for the staff to move the empty bracket trays one by one and then move them as a whole, which greatly reduces the workload of the staff. In addition, the pre-assembly operation and riveting and welding operation of the bracket and the sheet are both automated. Compared with manual operation, it effectively avoids the problem of riveting and welding quality being affected due to position deviation, thereby ensuring the production quality of the thermal conductive sheet.
[0063] refer to Figure 6 The riveting mechanism 22 includes a riveting component 221 and a third power assembly 222. The riveting component 221 is disposed above the carrying device 30. The riveting component 221 includes a pressure riveting assembly 2211 and a heating element 2212. The pressure riveting assembly 2211 is installed on the third power assembly 222 and can be driven by the third power assembly 222 to approach or move away from the carrying device 30. The pressure riveting assembly 2211 has at least one pair of pressure riveting heads 22111. The heating element 2212 is installed on the pressure riveting heads 22111 and can heat the pressure riveting heads 22111. When the rivet assembly 2211 is driven by the third power assembly 222 and approaches the carrying device 30, the two rivet heads 22111 of each pair are pressed toward a protrusion of two brackets of a pair respectively, and at the same time, the heating element 2212 heats the rivet heads 22111 so that the rivet heads 22111 can melt the protrusions and press them onto the surface of the sheet, thereby riveting the sheet and the bracket.
[0064] Preferably, the third power assembly 222 is implemented as a cylinder.
[0065] Preferably, a plurality of the riveting and welding mechanisms 22 are provided, so that a plurality of sheets can be riveted and welded to the brackets provided at both ends of the sheets at the same time by the plurality of the riveting and welding mechanisms 22, so as to improve the processing efficiency.
[0066] refer to Figure 1The production equipment for the thermal conductive sheet includes a pressure-resistant testing device 40, and the pressure-resistant testing device 40 includes at least one pressure-resistant testing mechanism 41. The pressure-resistant testing mechanism 41 is arranged above the carrying device 30 and is located in the direction in which the thermal conductive sheet is conveyed by the carrying device 30. The pressure-resistant testing mechanism 41 can perform pressure resistance testing on the thermal conductive sheet.
[0067] Preferably, a plurality of the withstand voltage detection mechanisms 41 are provided, so that the plurality of withstand voltage detection mechanisms 41 can simultaneously perform withstand voltage detection on a plurality of thermal conductive sheets, so as to improve processing efficiency.
[0068] refer to Figure 7 The withstand voltage detection mechanism 41 includes a withstand voltage detection component 411 and a first driving mechanism 412. The withstand voltage detection component 411 is disposed above the carrier 30. The withstand voltage detection component 411 includes a detection body 4111 and a pair of energizing members 4112. The detection body 4111 is mounted on the first driving mechanism 412 and can be driven by the first driving mechanism 412 to approach or move away from the carrier 30. The pair of energizing members 4112 are mounted on the detection body 4111 and transmit current through the detection body 4111. When the detection body 4111 is driven by the first driving mechanism 412 to approach the carrier 30 to abut against the thermal conductive sheet, the detection body 4111 is introduced with current by the energizing members 4112 to perform a withstand voltage test on the thermal conductive sheet.
[0069] Preferably, the first driving mechanism 412 is implemented as a cylinder.
[0070] The withstand voltage detection mechanism 41 also includes a monitoring component 413, and the monitoring component 413 is used to detect the current or voltage of the circuit where the power supply component 4112 is located. The production equipment for thermal conductive sheets also includes a controller 50, and the monitoring component 413 is connected to the controller 50 for communication. The controller 50 determines whether the corresponding thermal conductive sheet has passed the withstand voltage test based on the feedback of the monitoring component 413. The withstand voltage detection device 40 also includes a marking mechanism 42, and the marking mechanism 42 is arranged above the carrier device 30 and is located in the direction in which the thermal conductive sheet after the withstand voltage test is transported by the carrier device 30. The marking mechanism 42 and the carrier device 30 are both controllably connected to the controller 50, and the controller 50 can control the conveyance of the thermal conductive sheet by the carrier device 30 and control the marking action of the marking mechanism 42 based on the feedback of the monitoring component 413.
[0071] Preferably, the monitoring component 413 is implemented as a current sensor or a voltage sensor.
[0072] The marking mechanism 42 includes a marking component 421 and a second driving mechanism 422 . The marking component 421 is disposed above the carrier device 30 . The marking component 421 is installed on the second driving mechanism 422 and driven to approach or move away from the carrier device 30 . When the pressure-resistant detection component 411 performs a pressure test on a thermal conductive sheet, and the controller 50 determines that the pressure test of the thermal conductive sheet is unqualified based on the feedback control of the monitoring component 413, the controller 50 controls the carrying device 30 to operate so as to transfer the corresponding thermal conductive sheet to the bottom of the marking component 421 and stay there for a predetermined time, and the controller 50 controls the second driving mechanism 422 to operate so that the second driving mechanism 422 drives the marking component 421 to move close to the corresponding thermal conductive sheet and mark it, thereby marking the corresponding thermal conductive sheet as unqualified; when the pressure-resistant detection component 411 performs a pressure test on a thermal conductive sheet, and the controller 50 determines that the pressure test of the thermal conductive sheet is qualified based on the feedback control of the monitoring component 413, the controller 50 controls the carrying device 30 to operate so that the corresponding thermal conductive sheet moves under the marking component 421, and the controller 50 controls the second driving mechanism 422 to suspend operation, thereby distinguishing the thermal conductive sheets.
[0073] Preferably, the second driving mechanism 422 is implemented as a cylinder.
[0074] refer to Figure 1 , Figure 8 , Fig. 9 and Fig.10 The production equipment for thermal conductive sheets further comprises a sorting device 60, the sorting device 60 comprises a sorting platform 61, a material transfer mechanism 62 and a quality inspection mechanism 63, the sorting platform 61 has at least one loading portion 611. The material transfer mechanism 62 comprises a delivery member 621, the delivery member 621 can transfer the thermal conductive sheet that has been transferred from the marking mechanism 42 by the conveying device 30 to one of the loading portions 611 of the sorting platform 61. The quality inspection mechanism 63 comprises a mark detection member 631 and a size detection member 632, the mark detection member 631 is located above one of the loading portions 611, and the size detection member 632 corresponds to one of the loading portions 611, the mark detection member 631 is used to identify whether the thermal conductive sheet located at the corresponding loading portion 611 has a mark, and the size detection member 632 is used to detect the length and width of the thermal conductive sheet carried by the corresponding loading portion 611.
[0075] Preferably, the size detection component 632 is implemented to include a length measuring sensor, which radiates a signal in the width direction of the heat conducting plate to detect the width of the heat conducting plate, and the length measuring sensor radiates a signal to the heat conducting plate and is driven to move along the length direction of the heat conducting plate to detect its length.
[0076] Preferably, the mark detection member 631 is implemented as a camera.
[0077] The inspection member 621 includes at least one first pick-and-place assembly 6211 and a first drive assembly 6212. The first pick-and-place assembly 6211 is installed on the first drive assembly 6212 and can be driven to move by the first drive assembly 6212. The conveying device 30 and the sorting platform 61 are both located below the moving track of the first pick-and-place assembly 6211. The first pick-and-place assembly 6211 is used to grab and place the thermal conductive sheet. When each of the first pick-and-place assembly 6211 is driven by the first drive assembly 6212 to move to the top of the conveying device 30 and corresponds to a thermal conductive sheet, the first pick-and-place assembly 6211 is driven by the first drive assembly 6212 to approach the thermal conductive sheet and grab the thermal conductive sheet. Subsequently, the first pick-and-place assembly 6211 grabbing the thermal conductive sheet is driven to move to the top of the sorting platform 61 and place the thermal conductive sheet above the loading portion 611 corresponding to the size detection member 632.
[0078] Preferably, the first pick-and-place component 6211 is implemented to include a suction cup.
[0079] Preferably, the first driving component 6212 is implemented including but not limited to a cylinder, a motor, a screw and the like.
[0080] The mark detection member 631 and the size detection member 632 are both communicatively connected to the controller 50, and the controller 50 determines whether the heat conductive sheet has passed the pressure test according to the feedback of the mark detection member 631, and the controller 50 determines whether the heat conductive sheet has passed the size test according to the feedback of the size detection member 632. The sorting device 60 also includes a material unloading platform group 64, and the material unloading platform group 64 includes a qualified material platform 641. The material transfer mechanism 62 includes a qualified transfer member 622, and the qualified transfer member 622 is controllably connected to the controller 50. When the controller 50 determines that the heat conductive sheet has passed the pressure test according to the feedback of the mark detection member 631 and that the heat conductive sheet has passed the size test according to the feedback of the size detection member 632, the controller 50 controls the qualified transfer member 622 to grab the qualified heat conductive sheet and transfer it to the qualified material platform 641.
[0081] The qualified transfer member 622 includes at least one second pick-and-place component 6221 and a second drive component 6222. The second pick-and-place component 6221 and the second drive component 6222 are both controllably connected to the controller 50. The second pick-and-place component 6221 is installed on the second drive component 6222 and can be driven to move by the second drive component 6222. The qualified material table 641 and the sorting table 61 are both located below the moving track of the second pick-and-place component 6221. The second pick-and-place component 6221 is used to grab and place qualified thermal conductive sheets.
[0082] When the controller 50 determines that the thermal conductive sheet has passed the pressure resistance test based on the feedback from the mark detection component 631 and has passed the size test based on the feedback from the size detection component 632, the controller 50 controls the second drive assembly 6222 and the second pick-and-place assembly 6221 to operate, so that the second drive assembly 6222 drives the second pick-and-place assembly 6221 to move to above the corresponding loading portion 611 so that the second pick-and-place assembly 6221 can grab the qualified thermal conductive sheet carried by the corresponding loading portion 611, and then the second pick-and-place assembly 6221 grabbing the qualified thermal conductive sheet is driven by the second drive assembly 6222 to move to above the qualified material platform 641 and place the qualified thermal conductive sheet on the qualified material platform 641.
[0083] Preferably, the second pick-and-place assembly 6221 is implemented to include a suction cup.
[0084] Preferably, the second driving assembly 6222 is implemented including but not limited to a cylinder, a motor, a screw and the like.
[0085] The unloading platform group 64 further includes a primary product platform 642, and the material transfer mechanism 62 further includes a primary product transfer member 623, and the secondary product transfer member 623 is controllably connected to the controller 50. When the controller 50 determines that the heat conductive sheet has passed the pressure test according to the feedback of the mark detection member 631 and / or determines that the heat conductive sheet has failed the size test according to the feedback of the size detection member 632, the controller 50 controls the secondary product transfer member 623 to grab the unqualified heat conductive sheet and transfer it to the secondary product platform 642.
[0086] The defective product transfer component 623 includes a third pick-and-place component 6231 and a third drive component 6232. The third pick-and-place component 6231 and the third drive component 6232 are both controllably connected to the controller 50. The third pick-and-place component 6231 is installed on the third drive component 6232 and can be driven to move by the third drive component 6232. The defective product material table 642 and the sorting table 61 are both located below the moving track of the third pick-and-place component 6231. The third pick-and-place component 6231 is used to grab and place unqualified thermal conductive sheets. When the controller 50 determines that the thermal conductive sheet has passed the pressure resistance test based on the feedback from the mark detection component 631 and / or determines that the thermal conductive sheet has failed the size test based on the feedback from the size detection component 632, the controller 50 controls the third drive assembly 6232 and the third pick-and-place assembly 6231 to operate, so that the third drive assembly 6232 drives the third pick-and-place assembly 6231 to move to above the corresponding loading portion 611 so that the third pick-and-place assembly 6231 can grab the unqualified thermal conductive sheet carried by the loading portion 611, and then the third pick-and-place assembly 6231 grabbing the unqualified thermal conductive sheet is driven by the third drive assembly 6232 to move to above the defective material table 642 and place the unqualified thermal conductive sheet on the defective material table 642.
[0087] Preferably, the third pick-and-place assembly 6231 is implemented to include a suction cup.
[0088] Preferably, the third driving assembly 6232 is implemented including but not limited to a cylinder, a motor, a screw and the like.
[0089] Preferably, the defective material platform 642 includes a size defective placement part 6421 and a pressure-resistant defective placement part 6422, and the size defective placement part 6421 and the pressure-resistant defective placement part 6422 are adjacently arranged and are both located below the track where the unqualified thermal conductive sheet is driven and moved by the defective transfer member 623. When the controller 50 determines that the thermal conductive sheet is unqualified in the pressure test according to the feedback of the mark detection member 631, the controller 50 controls the defective transfer member 623 to operate so as to transfer the corresponding unqualified thermal conductive sheet to the pressure-resistant defective placement part 6422; when the controller 50 determines that the thermal conductive sheet size test is unqualified according to the feedback of the size detection member 632, the controller 50 receives the feedback of the size detection member 632 and controls the defective transfer member 623 to operate so as to transfer the corresponding unqualified thermal conductive sheet to the size defective placement part 6421, so as to classify the unqualified thermal conductive sheets.
[0090] It is worth mentioning that when the controller 50 determines that the thermal conductive sheet fails the pressure resistance test based on the feedback from the mark detection component 631 and determines that the thermal conductive sheet fails the size test based on the feedback from the size detection component 632, the controller 50 controls the defective product transfer component 623 to operate so as to transfer the corresponding unqualified thermal conductive sheet to the pressure-resistant defective product placement section 6422.
[0091] In this process, through the cooperation of the pressure detection device 40, the controller 50 and the sorting device 60, the pressure detection and size detection are performed on the thermal conductive sheet, and qualified products and defective products are automatically sorted according to the detection results. The defective products are further classified according to the reasons for their failure, so that the thermal conductive sheets with unqualified sizes can be distinguished, which facilitates the smooth recycling of the thermal conductive sheets with unqualified sizes and greatly reduces the production cost.
[0092] It is worth mentioning that the sorting platform 61 is configured to be able to intermittently rotate 90 degrees. The position of the sorting platform 61 deviating from its rotation center forms four loading parts 611 distributed at intervals with the rotation center of the sorting platform 61 as the center. When the first pick-and-place component 6211, the second pick-and-place component 6221 and the third pick-and-place component 6231 are all located above the sorting platform 61, the sorting platform 61 is driven to rotate so that three of the loading parts 611 are respectively located below the first pick-and-place component 6211, the second pick-and-place component 6221 and the third pick-and-place component 6231, the size detection component 632 corresponds to the remaining loading parts 611, and the second pick-and-place component 6221 is arranged opposite to the size detection component 632, and the first pick-and-place component 6211 is arranged opposite to the third pick-and-place component 6231, so that when the first pick-and-place component 6211 is transferring the thermal conductive sheet, the second pick-and-place component 6221, the third pick-and-place component 6231 and the size detection component 632 can simultaneously process the thermal conductive sheet on the corresponding loading part 611. The mark detection component 631 is installed on the second driving assembly 6222 so that when the first picking and placing assembly 6211 is driven by the second driving assembly 6222 to transfer the thermal conductive sheet, the mark detection component 631 performs mark detection on the thermal conductive sheet.
[0093] When the first pick-and-place assembly 6211, the second pick-and-place assembly 6221 and the third pick-and-place assembly 6231 are all located above the sorting platform 61, the heat conducting sheet placed on the corresponding material loading portion 611 by the first pick-and-place assembly 6211 can be driven by the sorting platform 61 to move through the outside of the size detection component 632 and then to the bottom of the third pick-and-place assembly 6231, or to move through the bottom of the third pick-and-place assembly 6231 and finally to the bottom of the second pick-and-place assembly 6221, so as to be moved by the third pick-and-place assembly 6231 and the second The pick-and-place component 6221 selectively grabs, and in this process, the rhythm of the thermal conductive sheet supplied by the inspection component 621 matches the operating rhythm of the qualified transfer component 622, the defective transfer component 623 and the size detection component 632, that is, the inspection component 621 transfers the thermal conductive sheet, the size detection component 632 detects the thermal conductive sheet, the qualified transfer component 622 transfers the qualified thermal conductive sheet, or the defective transfer component 623 transfers the unqualified thermal conductive sheet. The operation can be performed synchronously, and they can cooperate flexibly and operate efficiently. In addition, the use of the sorting table 61 that rotates 90° intermittently to transfer the thermal conductive sheet effectively reduces the overall length of the equipment and reduces the space occupied by the equipment compared to the common belt transmission method.
[0094] refer to Figure 1 , Figure 8 , Fig.11 and Fig.12 The production equipment for thermal conductive sheets also includes a finished product loading device 70, and the finished product loading device 70 includes a second supporting mechanism 71 and a finished product loading mechanism 72. The second supporting mechanism 71 includes a loading platform 711, and the finished product loading mechanism 72 can grab at least one qualified thermal conductive sheet carried by the qualified material table 641 and transfer it to a finished product pallet carried by the loading platform 711.
[0095] It is worth mentioning that since the second picking and placing component 6221 is arranged opposite to the size detection component 632, and the first picking and placing component 6211 is arranged opposite to the third picking and placing component 6231, the finished product loading device 70 can be arranged in the extension direction of the carrying device 30 to minimize the size of the equipment in the direction perpendicular to the conveying direction of the conveying device 30.
[0096] The second supporting mechanism 71 further includes a finished product tray loading member 712, and a plurality of empty finished product trays are carried in a stacked manner by the finished product tray loading member 712. The finished product loading mechanism 72 can grab the empty finished product trays carried by the finished product tray loading member 712 and located at the top layer and transfer them to the loading platform 711. After the finished product loading mechanism 72 grabs qualified heat conducting sheets and empty finished product trays for multiple rounds, a plurality of loaded finished product trays are stacked and arranged on the loading platform 711.
[0097] The finished product loading mechanism 72 includes a comprehensive pick-up and placement mechanism 721 and a belt-shifting mechanism 722. The comprehensive pick-up and placement mechanism 721 includes at least one finished product pick-up and placement component 7211 and at least one finished product pallet pick-up and placement component 7212. The finished product pick-up and placement component 7211 is used to grab the qualified thermal conductive sheet carried by the qualified material platform 641, and the finished product pallet pick-up and placement component 7212 is used to grab and place an empty finished product pallet. The finished product pick-up and placement component 7211 and the finished product pallet pick-up and placement component 7212 are both installed on the belt-shifting mechanism 722 and can be moved by the belt-shifting mechanism 722. The qualified material platform 641, the loading platform 711 and the finished product pallet loading component 712 are all located below the track where the comprehensive pick-up and placement mechanism 721 is moved by the belt-shifting mechanism 722.
[0098] Specifically, when the finished product picking and placing component 7211 is driven by the belt shifting mechanism 722 to move above the qualified material platform 641 and each of the finished product picking and placing components 7211 corresponds to each qualified thermal conductive sheet carried by the qualified material platform 641, the finished product picking and placing component 7211 is driven by the belt shifting mechanism 722 to approach the qualified thermal conductive sheet and grab it, and then the finished product picking and placing component 7211 is driven by the belt shifting mechanism 722 to move above the loading platform 711 and place the qualified thermal conductive sheet on the finished product tray carried by the loading platform 711 and located on the top layer. After the finished product pallet carried by the loading platform 711 and located on the top layer carries a predetermined number of qualified thermal conductive sheets, the finished product pallet picking and placing assembly 7212 is driven by the belt conveyor mechanism 722 to move above the finished product pallet loading component 712 and correspond to the empty finished product pallet. At this time, the finished product pallet picking and placing assembly 7212 is driven by the belt conveyor mechanism 722 to approach the empty finished product pallet and grab it. Subsequently, the finished product pallet picking and placing assembly 7212 is driven by the belt conveyor mechanism 722 to move above the loading platform 711 and stack the empty finished product pallets on the loaded finished product pallets carried by the loading platform 711.
[0099] Preferably, the finished product picking and placing assembly 7211 and the finished product pallet picking and placing assembly 7212 are both implemented to include suction cups.
[0100] Preferably, the belt moving mechanism 722 is implemented including but not limited to a cylinder, a motor, a lead screw, etc.
[0101] Furthermore, the loading platform 711 has a loading end 7111 and a downloading end 7112 arranged opposite to the loading end 7111. The loading end 7111 and the qualified material platform 641 are located below the moving track of the finished product pick-up and placement assembly 7211. The finished product pick-up and placement assembly 7211 can grab the qualified thermal conductive sheet carried by the qualified material platform 641 and be driven by the belt transfer mechanism 722 to transfer the qualified thermal conductive sheet to the finished product tray carried by the loading end 7111 and located at the top layer. When each finished product tray located at the loading end 7111 carries a predetermined number of qualified thermal conductive sheets and multiple loaded finished product trays are stacked to reach a predetermined height, the loading platform 711 can drive the stacked multiple loaded finished product trays to move from the loading end 7111 to the downloading end 7112 for subsequent loading operations.
[0102] The finished product pallet loading component 712 has a supply end 7121 and a to-be-moved end 7122 disposed opposite to the supply end 7121. The to-be-moved end 7122 and the loading end 7111 are located below the moving track of the finished product pallet picking and placing component 7212. The finished product pallet picking and placing component 7212 can grab the empty finished product pallet carried by the to-be-moved end 7122 and located at the top layer and be driven by the belt transfer mechanism 722 to transfer the empty finished product pallet to the loading end 7111. After the finished product pallet picking and placing component 7212 grabs the empty finished product pallet for multiple rounds to make the to-be-moved end 7122 empty, the finished product pallet loading component 712 can drive the stacked multiple empty finished product pallets to move from the supply end 7121 to the to-be-moved end 7122, so as to continuously supply empty finished product pallets.
[0103] Preferably, the loading end 7111 and the end to be moved 7122 are arranged on the same side, the unloading end 7112 and the supply end 7121 are arranged on the same side, and the conveying direction of the stacked multiple empty finished product pallets through the finished product pallet loading component 712 is opposite to the conveying direction of the stacked multiple loaded finished product pallets through the loading platform 711, and the qualified material table 641 is on the same side as the loading end 7111, so that when the integrated picking and placing mechanism 721 transfers the qualified thermal conductive sheet and the empty finished product pallets, it is convenient for the staff to unload the stacked multiple loaded finished product pallets and stack the multiple empty finished product pallets at the supply end 7121, thereby reducing the workload of the staff.
[0104] Preferably, the loading platform 711 and the finished product pallet loading member 712 are implemented as belt conveyors.
[0105] The present application also proposes a working method for a production device for a thermal conductive sheet, comprising the following steps:
[0106] The bracket loading component 111 drives the stacked multiple loading bracket trays to move from the loading starting end 1111 to the loading terminal 1112 to load the brackets, and the integrated grasping mechanism 12 grasps the multiple brackets carried by the bracket tray and transfers them to the bracket bearing platform 2111. After the integrated grasping mechanism 12 grasps the brackets for multiple rounds to make the corresponding bracket trays empty, the integrated grasping mechanism 12 grasps the empty bracket tray and transfers it to the unloading starting end 1121. After the empty bracket trays grasped by the integrated grasping mechanism 12 for multiple rounds are placed in a stacked manner at the unloading starting end 1121, the bracket tray unloading component 112 drives the stacked multiple empty bracket trays to move from the unloading starting end 1121 to the unloading terminal 1122 to unload the empty bracket trays.
[0107] The pre-installed component 212 successively grabs at least one pair of brackets carried by the bracket carrying platform 2111 and at least one sheet carried by the sheet placing platform 2112 and successively transfers them to the carrying device 30, and each sheet is pre-installed on a pair of brackets by being plugged into at least one protrusion of a pair of brackets carried by the carrying device 30 and spaced a predetermined distance apart;
[0108] The pre-assembled sheet and bracket are transported by the carrier device 30 and moved to the bottom of the riveting mechanism 22. The riveting mechanism 22 heats and presses the protrusion of the bracket penetrating the sheet to rivet the sheet and the bracket into a heat conducting sheet.
[0109] Furthermore, the working method of the production equipment for the thermal conductive sheet further comprises the following steps:
[0110] After the bracket grasped by the integrated grasping mechanism 12 is placed on the table body 21111 of the bracket supporting platform 2111, the two pairs of positioning components 21112 distributed around the corresponding bracket are driven to clamp the bracket in the length direction and width direction of the bracket, so as to position the bracket.
[0111] Furthermore, the working method of the production equipment for the thermal conductive sheet further comprises the following steps:
[0112] The bracket grasping and mounting component 2121 grasps at least one pair of brackets carried by the bracket supporting platform 2111 and places the two brackets on the carrying device 30 with a predetermined distance between them. After the carrying device 30 transports the brackets a predetermined distance, the sheet material grasping and mounting component 2122 grasps at least one sheet material carried by the sheet material placing platform 2112 and places each sheet material on the carrying device 30 by being plugged into at least one protrusion of a pair of brackets, thereby realizing the pre-installation of the sheet material and the bracket.
[0113] Furthermore, the working method of the production equipment for the thermal conductive sheet further comprises the following steps:
[0114] The heat conducting sheet is transported by the carrier device 30 and moved to the bottom of the withstand voltage detection mechanism 41. The withstand voltage detection member 411 performs a withstand voltage test on the heat conducting sheet. The monitoring member 413 monitors the current or voltage during the withstand voltage test and feeds back to the controller 50.
[0115] When the controller 50 determines that the corresponding heat conducting sheet fails the withstand voltage test according to the feedback of the monitoring component 413, the controller 50 controls the marking mechanism 42 and the carrying device 30 to operate, so that the corresponding heat conducting sheet is moved to the bottom of the marking mechanism 42 by the carrying device 30, and is marked by the marking mechanism 42;
[0116] When the controller 50 determines that the corresponding thermal conductive sheet has passed the withstand voltage test based on the feedback from the monitoring component 413, the controller 50 controls the carrier device 30 to move the corresponding thermal conductive sheet under the marking mechanism 42, and controls the marking mechanism 42 to suspend operation.
[0117] Furthermore, the working method of the production equipment for the thermal conductive sheet further comprises the following steps:
[0118] The inspection member 621 grabs the heat conducting sheet that is transported by the transport device 30 and moves away from the marking mechanism 42 and transfers it to a loading portion 611 of the sorting table 61, and the mark detection member 631 detects whether the corresponding heat conducting sheet has a mark and feeds back to the controller 50, and the size detection member 632 detects the length and width of the corresponding heat conducting sheet and feeds back to the controller 50;
[0119] When the controller 50 determines that the corresponding thermal conductive sheet has passed the withstand voltage test according to the feedback of the mark detection member 631 and that the corresponding thermal conductive sheet has passed the size test according to the feedback of the size detection member 632, the controller 50 controls the qualified transfer member 622 to grab the corresponding qualified thermal conductive sheet and transfer it to the qualified material platform 641;
[0120] When the controller 50 determines that the corresponding thermal conductive sheet fails the pressure resistance test based on the feedback from the mark detection component 631 and / or determines that the corresponding thermal conductive sheet fails the size test based on the feedback from the size detection component 632, the controller 50 controls the defective product transfer component 623 to grab the corresponding unqualified thermal conductive sheet and transfer it to the defective product material table 642.
[0121] Furthermore, the working method of the production equipment for the thermal conductive sheet further comprises the following steps:
[0122] After the heat conductive sheet is transferred to the loading portion 611 of the sorting platform 61 by the inspection member 621 and inspected by the mark inspection member 631, the heat conductive sheet is driven by the sorting platform 61 to move through the outside of the size inspection member 632 and then to the bottom of the third pick-and-place assembly 6231 or to move through the bottom of the third pick-and-place assembly 6231 and finally to the bottom of the second pick-and-place assembly 6221, so as to be selectively grasped by the third pick-and-place assembly 6231 and the second pick-and-place assembly 6221;
[0123] When the controller 50 determines that the corresponding heat conductive sheet fails the pressure test according to the feedback of the mark detection component 631 and / or determines that the corresponding heat conductive sheet fails the size test according to the feedback of the size detection component 632, the heat conductive sheet is driven by the sorting table 61 and moves through the outside of the size detection component 632 and then to the bottom of the third pick-and-place component 6231, and the controller 50 controls the defective product transfer component 623 to grab the corresponding defective heat conductive sheet and transfer it to the defective product material table 642;
[0124] When the controller 50 determines that the corresponding thermal conductive sheet has passed the pressure resistance test based on the feedback from the mark detection component 631 and that the corresponding thermal conductive sheet has passed the size test based on the feedback from the size detection component 632, the thermal conductive sheet is driven by the sorting table 61 and moves through the outside of the size detection component 632, then moves under the third pick-and-place component 6231 and finally moves to under the second pick-and-place component 6221. The controller 50 controls the qualified transfer component 622 to grab the corresponding qualified thermal conductive sheet and transfer it to the qualified material table 641.
[0125] Furthermore, the working method of the production equipment for the thermal conductive sheet further comprises the following steps:
[0126] When the controller 50 determines that the corresponding thermal conductive sheet fails the pressure test according to the feedback of the mark detection member 631 or determines that the corresponding thermal conductive sheet fails the pressure test and the size test according to the feedback of the mark detection member 631 and the size detection member 632, the controller 50 controls the defective product transfer member 623 to operate so as to transfer the corresponding defective thermal conductive sheet to the pressure-resistant defective product placement portion 6422;
[0127] When the controller 50 determines that the corresponding thermal conductive sheet size test fails based on the feedback from the size detection component 632, the controller 50 controls the defective product transfer component 623 to operate so as to transfer the corresponding unqualified thermal conductive sheet to the defective size placement portion 6421, so as to classify the unqualified thermal conductive sheets.
[0128] Furthermore, the working method of the production equipment for the thermal conductive sheet further comprises the following steps:
[0129] The finished product pick-up and placement assembly 7211 is driven by the belt transfer mechanism 722 to move above the qualified material platform 641 so that each of the finished product pick-up and placement assembly 7211 corresponds to each qualified thermal conductive sheet carried by the qualified material platform 641, and the finished product pick-up and placement assembly 7211 is driven by the belt transfer mechanism 722 to approach the qualified thermal conductive sheet and grab it, and then the finished product pick-up and placement assembly 7211 is driven by the belt transfer mechanism 722 to move above the loading platform 711 and place the qualified thermal conductive sheet on the finished product tray carried by the loading platform 711 and located on the top layer;
[0130] After the finished product picking and placing assembly 7211 has carried out multiple rounds of grabbing so that the finished product pallet carried by the loading platform 711 and located on the top layer carries a predetermined number of qualified thermal conductive sheets, the finished product pallet picking and placing assembly 7212 is driven by the belt shifting mechanism 722 to move above the finished product pallet loading component 712 and correspond to the empty finished product pallet, and the finished product pallet picking and placing assembly 7212 is driven by the belt shifting mechanism 722 to approach the empty finished product pallet and grab it, and then the finished product pallet picking and placing assembly 7212 is driven by the belt shifting mechanism 722 to move above the loading platform 711 and stack the empty finished product pallets on the loaded finished product pallets carried by the loading platform 711.
[0131] Furthermore, the working method of the production equipment for the thermal conductive sheet further comprises the following steps:
[0132] When the integrated pick-and-place mechanism 721 grabs qualified heat-conducting sheets and empty finished product trays in multiple rounds so that each finished product tray at the loading end 7111 of the loading platform 711 carries a predetermined number of qualified heat-conducting sheets and multiple loaded finished product trays are stacked to reach a predetermined height, the loading platform 711 can drive the multiple stacked loaded finished product trays to move from the loading end 7111 to the unloading end 7112 for subsequent loading operations;
[0133] After the finished product pallet picking and placing component 7212 grabs empty finished product pallets for multiple rounds and makes the end 7122 to be moved of the finished product pallet loading component 712 empty, the finished product pallet loading component 712 can drive multiple stacked empty finished product pallets to move from the supply end 7121 to the end 7122 to be moved, so as to continuously supply empty finished product pallets.
[0134] It should be understood by those skilled in the art that the embodiments of the present invention described above and shown in the accompanying drawings are only examples and do not limit the present invention. The advantages of the present invention have been fully and effectively achieved. The functional and structural principles of the present invention have been demonstrated and explained in the embodiments, and the embodiments of the present invention may be deformed or modified in any way without departing from the principles.
Claims
1. A production device for a thermally conductive sheet, characterized in that: The production equipment for the thermal conductive sheet comprises: Carrying device; The rack loading device comprises a first supporting mechanism and an integrated grasping mechanism, the first supporting mechanism comprises a rack loading component and a rack tray unloading component, the rack loading component comprises a loading starting end and a loading terminal arranged opposite to the loading starting end, the rack loading component can drive a plurality of stacked loading racks to move from the loading starting end to the loading terminal, the rack tray unloading component comprises a unloading starting end and a unloading terminal arranged opposite to the unloading starting end, the integrated grasping mechanism can transfer the racks on the rack tray located on the top layer and carried by the loading terminal, and transfer the empty rack racks located on the top layer to the unloading starting end, after the integrated grasping mechanism grasps the empty racks in multiple rounds and stacks them on the unloading starting end, the rack tray unloading component can drive a plurality of stacked empty racks to move from the unloading starting end to the unloading terminal; An assembling device, the assembling device comprising: A pre-installation mechanism, the pre-installation mechanism comprises a placement platform group and a pre-installation component, the placement platform group comprises a bracket bearing platform and a sheet placing platform, the sheet placing platform is used to place sheets, the integrated grabbing mechanism is configured to grab a plurality of pairs of brackets on the bracket tray carried by the feeding terminal and located on the top layer and transfer them to the bracket bearing platform, the pre-installation component can successively grab at least one pair of brackets carried by the bracket bearing platform and at least one sheet carried by the sheet placing platform and transfer them to the carrying device in sequence, each sheet is pre-installed on a pair of brackets in a manner of being plugged into at least one protrusion of a pair of brackets carried by the carrying device and spaced a predetermined distance apart; At least one riveting welding mechanism is arranged above the carrying device and is located in the direction in which the sheet and the bracket are pre-assembled as a whole and are transported by the carrying device. The riveting welding mechanism can heat and press the protrusion of the bracket that passes through the sheet to rivet the sheet and the bracket into a heat conducting sheet.
2. The production equipment for thermally conductive sheets according to claim 1, characterized in that: The loading starting end and the unloading starting end are arranged on the same side, the loading terminal and the unloading starting end are arranged on the same side, the conveying direction of the loading bracket pallet through the bracket loading component is opposite to the conveying direction of the empty bracket pallet through the bracket pallet unloading component, and the bracket support platform is on the same side as the loading terminal and is located on the side of the loading terminal away from the unloading starting end.
3. The production equipment for thermally conductive sheets according to claim 1, characterized in that: The integrated grabbing mechanism includes an integrated grabbing component and a power component, the integrated grabbing component includes a plurality of bracket grabbing assemblies and at least one bracket tray grabbing assembly, the bracket grabbing assembly is used to grab a bracket, the bracket tray grabbing assembly is used to grab an empty bracket tray, the bracket grabbing assembly and the bracket tray grabbing assembly are both installed on the power component and can be driven to move by the power component, the bracket loading component, the bracket tray unloading component and the bracket supporting platform are all located below the trajectory of the integrated grabbing component being driven to move by the power component.
4. The production equipment for thermally conductive sheets according to claim 1, characterized in that: The pre-installed components include at least one pair of bracket grasping components, each pair of the bracket grasping components can grasp a pair of brackets carried by the bracket supporting platform and place the two brackets on the carrying device with a predetermined distance between them. The pre-installed components also include at least one sheet material grasping component, at least one sheet material grasping component can transfer a sheet of material carried by the sheet placing platform to the top of the carrying device and insert each sheet of material into at least one protrusion of a pair of brackets.
5. The production equipment for thermally conductive sheets according to claim 1, characterized in that: The riveting mechanism includes a riveting component and a third power assembly, wherein the riveting component is arranged above the carrying device, and the riveting component includes a rivet assembly and a heating element, wherein the rivet assembly is installed on the third power assembly and can be driven by the third power assembly to approach or move away from the carrying device, and the rivet assembly has at least one pair of rivet heads, and the heating element is installed on the rivet heads and can heat the rivet heads. In the process of the rivet assembly being driven by the third power assembly to approach the carrying device, the two rivet heads in each pair are respectively pressed against a protrusion of two brackets of a pair, and the heating element heats the rivet heads at the same time, so that the rivet heads can heat-melt the protrusions and press them onto the surface of the sheet.
6. The production equipment for thermally conductive sheets according to any one of claims 1 to 5, characterized in that: The production equipment for the thermal conductive sheet includes a pressure resistance testing device, which includes at least one pressure resistance testing mechanism. The pressure resistance testing mechanism is arranged above the carrier device and is located in the direction in which the thermal conductive sheet is conveyed by the carrier device. The pressure resistance testing mechanism can perform pressure resistance testing on the thermal conductive sheet.
7. The production equipment for thermally conductive sheets according to claim 6, characterized in that: The withstand voltage detection mechanism includes a withstand voltage detection component and a first driving mechanism. The withstand voltage detection component is arranged above the carrying device. The withstand voltage detection component includes a detection body and a pair of energized parts. The detection body is installed on the first driving mechanism and can be driven by the first driving mechanism to approach or move away from the carrying device. The pair of energized parts are installed on the detection body and transmit current through the detection body. When the detection body is driven by the first driving mechanism to approach the carrying device to abut against the thermal conductive sheet, the detection body is introduced with current by the energized parts to perform a withstand voltage test on the thermal conductive sheet.
8. The production equipment for thermally conductive sheets according to claim 7, characterized in that: The withstand voltage detection mechanism also includes a monitoring component, which is used to detect the current or voltage of the circuit where the energized component is located. The production equipment for the thermal conductive sheet also includes a controller. The monitoring component is communicatively connected to the controller. The controller determines whether the corresponding thermal conductive sheet has passed the withstand voltage test based on the feedback from the monitoring component. The withstand voltage detection device also includes a marking mechanism, which is arranged above the carrying device and is located in the direction in which the thermal conductive sheet after the withstand voltage test is transported by the carrying device. The marking mechanism and the carrying device are both controllably connected to the controller. The controller can control the transportation of the thermal conductive sheet by the carrying device and control the marking action of the marking mechanism based on the feedback from the monitoring component.
9. The production equipment for thermally conductive sheets according to claim 8, characterized in that: The marking mechanism includes a marking part and a second driving mechanism, wherein the marking part is arranged above the carrying device, and the marking part is installed on the second driving mechanism to drive it to approach or move away from the carrying device. When the pressure-resistant detection component performs a pressure test on a thermal conductive sheet, and the controller determines that the pressure test of the thermal conductive sheet is unqualified based on the feedback control of the monitoring component, the controller controls the carrying device to operate so as to transfer the corresponding thermal conductive sheet to the bottom of the marking part and stay there for a predetermined time, and the controller controls the second driving mechanism to operate so that the second driving mechanism drives the marking part to move close to the corresponding thermal conductive sheet and mark it, thereby marking the corresponding thermal conductive sheet as unqualified. When the pressure-resistant detection component performs a pressure test on a thermal conductive sheet, and the controller determines that the pressure test of the thermal conductive sheet is qualified based on the feedback control of the monitoring component, the controller controls the carrying device to operate so that the corresponding thermal conductive sheet moves under the marking part, and the controller controls the second driving mechanism to suspend operation.
10. A working method of a production device for a thermally conductive sheet, applied to the production device for a thermally conductive sheet according to any one of claims 1 to 9, characterized in that: The steps include: The bracket loading component drives a plurality of stacked loading bracket trays to move from the loading starting end to the loading terminal to load the brackets, and the integrated grasping mechanism grasps a plurality of brackets carried by the bracket tray and transfers them to the bracket carrying platform. After the integrated grasping mechanism grasps the brackets for multiple rounds to make the corresponding bracket trays empty, the integrated grasping mechanism grasps the empty bracket tray and transfers it to the unloading starting end. After the empty bracket trays grasped by the integrated grasping mechanism for multiple rounds are placed in a stacked manner at the unloading starting end, the bracket tray unloading component drives a plurality of stacked empty bracket trays to move from the unloading starting end to the unloading terminal to unload the empty bracket trays. The pre-installed component successively grabs at least one pair of brackets carried by the bracket carrying platform and at least one sheet carried by the sheet placing platform and successively transfers them to the carrying device, and each sheet is pre-installed on a pair of brackets in a manner of being plugged into at least one protrusion of a pair of brackets carried by the carrying device and spaced a predetermined distance apart; The pre-assembled sheet and bracket are transported by the conveying device and moved to the bottom of the riveting mechanism, and the riveting mechanism heats and presses the protrusion of the bracket penetrating the sheet to rivet and weld the sheet and the bracket into a heat conducting sheet.
Citation Information
Cited By
Double-layer automatic wiring tool and assembling method applying same
CN120055746A