Anti-cracking maintenance device for concrete member

By designing a crack-proof maintenance device for concrete components of base, support plate, placement rack and spraying mechanism, the problems of uneven dry and wet and inconvenient pick-up and placement in the prior art are solved, and uniform spraying and efficient maintenance are achieved.

CN119077920APending Publication Date: 2024-12-06BEIJING MUNICIPAL CONSTR +1
View PDF 0 Cites 2 Cited by

Patent Information

Application Number
CN202411228725.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-03
Publication Date
2024-12-06

AI Technical Summary

Technical Problem

The existing anti-cracking and curing devices for concrete components are unevenly dry and wet during the spraying process, which affects the quality of curing. The equipment design is not convenient for the pick-up and placement of concrete components and the recycling of defective products, reducing the maintenance efficiency.

Method used

A device including a base, a support plate, a placing frame and a spraying mechanism is designed to ensure that the spray water is uniformly received on both sides of the concrete member, and through structures such as opening and closing mechanism and articulation shaft, it is convenient for the pick-up and residing of the concrete member. Product recycling.

Benefits of technology

It realizes uniform spraying and curing of concrete components, improves curing quality and efficiency, and simplifies the pick-up and placement of concrete components and the recycling of defective products.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119077920A_ABST
    Figure CN119077920A_ABST
Patent Text Reader

Abstract

The invention belongs to the technical field of concrete member anti-cracking maintenance, and particularly relates to a concrete member anti-cracking maintenance device which comprises a base, two sets of supporting plates are symmetrically and fixedly installed on the base, a plurality of sets of containing frames used for supporting concrete members are fixedly installed on one sides of the two sets of supporting plates at equal intervals, and a water drainage pipe is connected to one side of the base. Due to the fact that the upper face and the lower face of the concrete member directly face the spraying holes, the upper face and the lower face of the concrete member can receive spraying water, the concrete member can receive the spraying water more evenly, and the curing quality of the concrete member is improved; stacking of a plurality of sets of concrete members is achieved, then the concrete members are sprayed through the spraying mechanism, the device integrates storage and curing, and the curing efficiency of the concrete members is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of concrete component anti-cracking maintenance, in particular to a concrete component anti-cracking maintenance device. Background Art

[0002] After the concrete components are formed, when the outside temperature exceeds 5°C, they need to be sprayed and cured. Spraying curing is a method to ensure that the concrete maintains appropriate humidity during the hardening process, prevents the internal moisture of the concrete from evaporating too quickly, and ensures that the cement is fully hydrated, which is crucial for the strength development of the concrete and the prevention of cracks.

[0003] The patent with publication number CN219599905U discloses an anti-cracking maintenance device for super-long concrete components, including a working box, a supporting frame fixedly installed on one side of the working box, a placing frame for placing super-long concrete components fixedly installed on the top of the supporting frame, a plurality of groups of spray heads are arranged on the placing frame, and the plurality of groups of spray heads are fixedly installed on a connecting head, one end of the connecting head is connected to the water outlet end of a water pump, and the water pump is fixedly installed on the working box, and a recovery and cleaning component for filtering spray water is arranged inside the working box. This scheme realizes the maintenance of the super-long concrete components by placing the super-long concrete components on the placing frame so that multiple spray heads evenly spray water on the super-long concrete components below. Secondly, the waste water generated by the maintenance is recovered and filtered by the recovery and cleaning component inside the working box, so that the waste water generated by the maintenance can be reused.

[0004] In the above scheme, the concrete component is placed on the placement rack for spraying. First, during the spraying process, only one side of the concrete component is facing the spray head, while the other side is facing the placement rack, so that the other side cannot fully contact the spray water, resulting in uneven dryness and wetness, and reducing the maintenance quality of the concrete component. Secondly, the manufactured concrete components are generally stacked in the storage area. Therefore, when the concrete components are sprayed, the concrete components need to be moved to the placement rack. After the spraying is completed, the concrete components are moved down from the placement rack. The back and forth transportation is time-consuming and labor-intensive, which affects the maintenance efficiency of the concrete components. For this reason, the present invention provides a concrete component anti-cracking maintenance device. Summary of the invention

[0005] In order to make up for the deficiencies of the prior art, at least one technical problem raised in the background technology is solved.

[0006] The technical solution adopted by the present invention to solve the technical problem is as follows: a concrete component anti-cracking maintenance device described in the present invention comprises a base, two groups of support plates are symmetrically fixedly installed on the base, a plurality of placement racks for supporting concrete components are evenly fixedly installed on one side of the two groups of support plates, a drainage pipe is connected to one side of the base, a spray mechanism is arranged on the other side of the base, the spray mechanism comprises a main pipe, the lower end of the main pipe is located in the base, a water inlet pipe is connected to one side of the main pipe, a plurality of spray pipes are evenly installed on the other side of the main pipe, a plurality of spray holes are opened on the spray pipe, a screw rod is screwed to the lower end of the main pipe, and the screw rod is rotatably installed in the base, the placement rack comprises a main frame body, and a support plate for supporting the concrete component is arranged on the main frame body;

[0007] Since the upper and lower surfaces of the concrete component are directly opposite to the spray holes, the upper and lower surfaces of the concrete component can receive the spray water, so that the concrete component receives the spray water more evenly, thereby improving the maintenance quality of the concrete component. By setting a plurality of groups of placement racks, a plurality of groups of concrete components can be stacked, and then the concrete components are sprayed by the spray mechanism, so that the device integrates storage and maintenance, thereby improving the maintenance efficiency of the concrete components.

[0008] Preferably, two sets of linear bearings are embedded and installed at the lower end of the main pipe, and the two sets of linear bearings are slidably connected to two sets of sliding rods respectively, and the sliding rods are fixedly installed in the base;

[0009] The cooperation between the linear bearing and the slide rod guides the movement of the main pipe.

[0010] Preferably, a plurality of opening and closing mechanisms are equidistantly arranged in the support plate, the opening and closing mechanisms include two groups of fixed blocks, the two groups of fixed blocks are fixedly installed in the support plate, a rotating shaft, and two ends of the rotating shaft are rotatably connected to the two groups of fixed blocks, a gear fixedly sleeved on the rotating shaft, two groups of torsion springs symmetrically arranged on both sides of the gear, two groups of T-racks meshing the gears, one group of T-racks is fixedly connected to the pressure block, and the other group of T-racks is fixedly connected to the driven block, the torsion spring is sleeved on the rotating shaft, one end of the torsion spring is fixedly connected to the fixed block, and the other end of the torsion spring is fixedly connected to the gear, a movable cavity is opened in the main frame body, the support plate is movably inserted into the movable cavity, and one end of the support plate is fixedly connected to the driven block, a rectangular groove is opened on the main frame body, a plurality of groups of second guide holes are opened on one side of the support plate, the pressure block passes through the second guide hole and extends into the rectangular groove, and an inverted inclined surface is arranged on the end of the pressure block, and a plurality of groups of first guide holes are also opened on one side of the support plate, and the driven block passes through the first guide hole;

[0011] Through the setting of the opening and closing mechanism, the staff can lift the concrete components out of the device and into the device through the equipment, which is convenient for the staff to take and place the concrete components.

[0012] Preferably, the placement frame also includes a hinge shaft, which is hinged in a hinge groove opened at the end of the main frame body, a baffle, and the end of the baffle is fixedly connected to the hinge shaft. A worm gear is fixedly sleeved on the upper end of the hinge shaft, and the worm gear engages with the worm, and the worm is rotatably mounted on the end of the main frame body. The baffle is used to limit the concrete component, and a plurality of groups of rollers are rotatably mounted on the support plate;

[0013] Since rollers are installed on the pallet, the defective products that have been released from the limit will slide along the inclined pallet until the defective products are completely separated from between the two sets of placement racks, so that the defective products can be removed from the device. The operation is simple and fast, which is convenient for the staff to recycle the defective products.

[0014] The beneficial effects of the present invention are as follows:

[0015] 1. Since the upper and lower surfaces of the concrete components are directly facing the spray holes, the upper and lower surfaces of the concrete components can receive the spray water, so that the concrete components receive the spray water more evenly, which improves the maintenance quality of the concrete components. By setting a plurality of groups of placement racks, a plurality of groups of concrete components can be stacked, and then the concrete components are sprayed by the spray mechanism, so that the device integrates storage and maintenance, thereby improving the maintenance efficiency of the concrete components.

[0016] 2. Move the end of the pallet to the outside of the movable cavity until the end of the concrete component falls onto the pallet on the lowest placement rack, thereby placing the first group of concrete components. At the same time, the end of the pallet on the second group of placement racks located directly above the lowest placement rack moves out of the movable cavity, and the staff places the remaining concrete components on the device in turn in the same way. Conversely, when removing the concrete component from the placement rack, after the concrete component is separated from the placement rack, the pallet on the placement rack above the concrete component is moved into the movable cavity under the action of the torsion spring counter-torque force, thereby removing the obstruction caused by the upper pallet to the removal of the concrete component. Therefore, through the setting of the opening and closing mechanism, the staff can lift the concrete component out of the device through the equipment, which is convenient for the staff to take and place the concrete component.

[0017] 3. When recycling defective products, rotate the worm to rotate the worm wheel together with the hinge shaft and the baffle until the baffle is parallel to the main frame, and release the limit of the baffle on the concrete member. Since rollers are installed on the pallet, the defective products that have been released from the limit will slide along the inclined pallet until the defective products are completely separated from the two sets of placement racks, so that the defective products can be removed from the device. The operation is simple and fast, which is convenient for the staff to recycle the defective products. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] The present invention will be further described below in conjunction with the accompanying drawings.

[0019] Figure 1 It is a schematic diagram of the structure of the present invention.

[0020] Figure 2 It is a schematic diagram of the combination of the base, support plate, placement rack and spray mechanism of the present invention.

[0021] Figure 3 It is a schematic diagram of the spray pipe of the present invention.

[0022] Figure 4 It is a schematic diagram of a placement rack of the present invention.

[0023] Figure 5 It is a schematic diagram of the combination of the support plate, the placement rack and the opening and closing mechanism of the present invention in cross section.

[0024] Figure 6 It is a schematic diagram of the combination of the placement rack and the opening and closing mechanism of the present invention.

[0025] Figure 7 This is a schematic diagram of the combination of the placement rack and the opening and closing mechanism of the present invention from another perspective.

[0026] Figure 8 This is a schematic diagram of the placement rack of the present invention from another viewing angle.

[0027] Fig. 9 It is a schematic diagram of a support plate of the present invention.

[0028] In the figure: 1, base; 2, support plate; 201, first guide hole; 202, second guide hole; 3, placement rack; 4, concrete member; 5, drainage pipe; 6, spray mechanism; 7, opening and closing mechanism; 601, main pipe; 602, water inlet pipe; 603, spray pipe; 6031, spray hole; 604, screw; 605, linear bearing; 606, slide rod; 301, main frame; 3011, movable cavity; 3012, rectangular groove; 3013, hinge groove; 302, support plate; 3021, roller; 303, baffle; 304, hinge shaft; 305, worm gear; 306, worm; 701, rotating shaft; 702, fixed block; 703, gear; 704, torsion spring; 705, T-shaped rack; 706, pressure block; 7061, inverted slope; 707, driven block. DETAILED DESCRIPTION

[0029] In order to make the technical means, creative features, objectives and effects achieved by the present invention easy to understand, the present invention is further explained below in conjunction with specific implementation methods.

[0030] Embodiment 1

[0031] like Figures 1 to 4As shown, a concrete component anti-cracking maintenance device described in an embodiment of the present invention includes a base 1, on which two groups of support plates 2 are symmetrically fixedly installed, and a plurality of placement racks 3 for supporting concrete components 4 are evenly fixedly installed on one side of the two groups of support plates 2, a drainage pipe 5 is connected to one side of the base 1, and a spray mechanism 6 is arranged on the other side of the base 1, the spray mechanism 6 includes a main pipe 601, the lower end of the main pipe 601 is located in the base 1, one side of the main pipe 601 is connected to a water inlet pipe 602, and a plurality of groups of spray pipes 603 are evenly installed on the other side of the main pipe 601, and a plurality of groups of spray holes 6031 are opened on the spray pipe 603, and a screw 604 is screwed to the lower end of the main pipe 601, and the screw 604 is rotatably installed in the base 1, and the placement rack 3 includes a main frame 301, and a supporting plate 302 for supporting the concrete component 4 is arranged on the main frame 301.

[0032] Specifically, the water inlet pipe 602 is connected to the water pump, and the drainage pipe 5 is connected to the rear-end sewage treatment system. In the initial state, several groups of spray pipes 603 are respectively located directly below several groups of placement racks 3, and the placement racks 3 are located above the base 1 in an inclined posture. Both ends of the concrete component 4 are placed on the support plates 302 on the two groups of placement racks 3, and the concrete component 4 is also inclined. When the concrete component 4 needs to be maintained, tap water is input into the water inlet pipe 602 through the water pump, and the tap water flows into the main pipe 601 along the water inlet pipe 602, and then the tap water is diverted to several groups of spray pipes 603 through the main pipe 601, and the tap water is sprayed onto the concrete component 4 through the spray holes 6031 on the spray pipes 603. In this process, the screw 604 is driven by the motor to rotate, so that the main pipe 601 together with the several groups of spray pipes 603 is connected to the water inlet pipe 602. The shower pipe 603 moves together, so that the tap water sprayed by the spray hole 6031 is evenly distributed on the concrete component 4, and the excess water sprayed on the concrete component 4 will fall into the base 1 along the inclined concrete component 4, and then be discharged through the drain pipe 5, so as to realize the maintenance of the concrete component 4. Compared with the existing mechanism, since the upper and lower surfaces of the concrete component 4 are directly facing the spray hole 6031, the upper and lower surfaces of the concrete component 4 can receive the spray water, so that the concrete component 4 receives the spray water more evenly, and the maintenance quality of the concrete component 4 is improved. By setting a plurality of groups of placement racks 3, a plurality of groups of concrete components 4 can be stacked, and then the concrete components 4 are sprayed by the spray mechanism 6, so that the device integrates storage and maintenance, and improves the maintenance efficiency of the concrete components 4.

[0033] Furthermore, two sets of linear bearings 605 are embedded and installed at the lower end of the main pipe 601 . The two sets of linear bearings 605 are slidably connected to two sets of sliding rods 606 , respectively. The sliding rods 606 are fixedly installed in the base 1 .

[0034] Specifically, during the movement of the main pipe 601 , the main pipe 601 drives the two sets of linear bearings 605 to slide along the two sets of slide bars 606 , respectively. The cooperation between the linear bearings 605 and the slide bars 606 guides the movement of the main pipe 601 .

[0035] like Figures 5 to 7 As shown, a plurality of groups of opening and closing mechanisms 7 are arranged at equal distances in the support plate 2, and the opening and closing mechanism 7 includes two groups of fixed blocks 702, the two groups of fixed blocks 702 are fixedly installed in the support plate 2, a rotating shaft 701, and the two ends of the rotating shaft 701 are respectively rotatably connected to the two groups of fixed blocks 702, a gear 703 fixedly sleeved on the rotating shaft 701, two groups of torsion springs 704 symmetrically arranged on both sides of the gear 703, two groups of T-shaped racks 705 meshing with the gear 703, one group of T-shaped racks 705 is fixedly connected to the pressure block 706, and the other group of T-shaped racks 705 is fixedly connected to the driven block 707, and the torsion spring 704 is sleeved on the rotating shaft 701, and one end of the torsion spring 704 is fixed The fixed block 702 is fixedly connected, and the other end of the torsion spring 704 is fixedly connected to the gear 703. A movable cavity 3011 is opened in the main frame body 301, and the support plate 302 is movably inserted into the movable cavity 3011, and one end of the support plate 302 is fixedly connected to the driven block 707. A rectangular groove 3012 is opened on the main frame body 301, and a plurality of groups of second guide holes 202 are opened on one side of the support plate 2. The pressure block 706 passes through the second guide hole 202 and extends into the rectangular groove 3012, and an inverted slope 7061 is provided at the end of the pressure block 706. A plurality of groups of first guide holes 201 are also opened on one side of the support plate 2, and the driven block 707 passes through the first guide hole 201.

[0036] Specifically, the setting of several groups of placement racks 3 enables several groups of concrete components 4 to be stacked together. However, when placing the concrete components 4 on the placement racks 3, the concrete components 4 cannot be inserted between the two groups of placement racks 3 from top to bottom, and the concrete components 4 can only be inserted obliquely between the two groups of placement racks 3, which not only increases the difficulty of stacking the concrete components 4, but also makes it more troublesome for the staff to take and place the concrete components 4. In the initial state, except for the placement rack 3 located at the bottom, the support plates 302 on the other placement racks 3 are all completely located in the corresponding active cavity 3011, and the ends of all the pressure blocks 706 are extended. 3012, so when stacking concrete components 4, the staff can lift the concrete components 4 through the equipment, and then make the concrete components 4 pass through the multiple pairs of placement racks 3 from top to bottom in sequence until the concrete components 4 are close to the two sets of placement racks 3 at the bottom. Before the end of the concrete component 4 contacts the support plate 302 on the placement rack 3, the end of the concrete component 4 will be squeezed to the inverted slope 7061 of the end of the pressure block 706, so that the pressure block 706 moves along the rectangular groove 3012 toward the inside of the support plate 2, and at the same time, the pressure block 706 drives the corresponding T-shaped rack 705 to move The T-shaped rack 705 drives the gear 703 to rotate, so that the gear 703 drives another set of T-shaped racks 705 to move in the opposite direction, and the gear 703 screws the two sets of torsion springs 704, and then the other set of T-shaped racks 705 drives the driven block 707 together with the corresponding support plate 302 to move together, so that the end of the support plate 302 moves to the outside of the active cavity 3011, until the end of the concrete component 4 falls on the support plate 302 on the lowermost placement rack 3, so as to place the first set of concrete components 4, and at the same time, the end of the support plate 302 on the second set of placement racks 3 located directly above the lowermost placement rack 3 moves out of the active cavity. 3011, the staff places the remaining concrete components 4 on the device in turn in the same way. Conversely, when removing the concrete component 4 from the placement rack 3, after the concrete component 4 is separated from the placement rack 3, under the action of the counter-torque force of the torsion spring 704, the support plate 302 on the placement rack 3 above the concrete component 4 is moved into the movable cavity 3011, thereby removing the obstruction caused by the upper support plate 302 to the removal of the concrete component 4. Therefore, through the setting of the opening and closing mechanism 7, the staff can lift the concrete component 4 from the device through the equipment, which is convenient for the staff to take and place the concrete component 4.

[0037] Embodiment 2

[0038] like Figure 8 and Fig. 9As shown, compared with Example 1, another implementation of the present invention is: the placement frame 3 also includes a hinge shaft 304, the hinge shaft 304 is hinged in a hinge groove 3013 opened at the end of the main frame body 301, a baffle 303, the end of the baffle 303 is fixedly connected to the hinge shaft 304, the upper end of the hinge shaft 304 is fixedly sleeved with a worm gear 305, the worm gear 305 engages with the worm 306, and the worm 306 is rotatably installed on the end of the main frame body 301, the baffle 303 is used to limit the concrete component 4, and a plurality of groups of rollers 3021 are rotatably installed on the support plate 302.

[0039] Specifically, if the concrete components 4 are placed for a long time, some defective products will appear, and the staff needs to take down the defective products for recycling. Since the concrete components 4 are stacked on the device, if the defective products are located in the lower area, the staff needs to lift the good concrete components 4 above the defective products, and then take down the defective products, which makes it troublesome for the staff to recycle the defective products, reducing the efficiency of the recycling of the defective products. In the initial state, the baffle 303 is perpendicular to the main frame 301, and the baffle 303 blocks the concrete components 4. Therefore, when recycling defective products, the worm 306 is rotated to rotate the worm wheel 305 together with the hinge shaft 304 and the baffle 303 until the baffle 303 is parallel to the main frame 301, and the limit of the baffle 303 on the concrete component 4 is released. Since the roller 3021 is installed on the support plate 302, the defective products that have been released from the limit will slide along the inclined support plate 302 until the defective products are completely separated from the two groups of placement racks 3, so that the defective products can be taken off the device. The operation is simple and fast, which is convenient for the staff to recycle the defective products.

[0040] Working principle: tap water is input into the water inlet pipe 602 through a water pump, and the tap water flows into the main pipe 601 along the water inlet pipe 602, and then the tap water is diverted into a plurality of spray pipes 603 through the main pipe 601, and the tap water is sprayed onto the concrete component 4 through the spray holes 6031 on the spray pipes 603. In this process, the screw rod 604 is driven by a motor to rotate, so that the main pipe 601 moves together with the plurality of spray pipes 603, so that the tap water sprayed from the spray holes 6031 is evenly distributed on the concrete component 4, and the excess water sprayed on the concrete component 4 will fall into the base 1 along the inclined concrete component 4, and then be discharged through the drain pipe 5, so as to realize the maintenance of the concrete component 4;

[0041] When stacking concrete components 4, the staff can lift the concrete components 4 through the equipment, and then make the concrete components 4 pass through multiple pairs of placement racks 3 from top to bottom in sequence until the concrete components 4 are close to the two lowest groups of placement racks 3. Before the end of the concrete component 4 contacts the support plate 302 on the placement rack 3, the end of the concrete component 4 will be squeezed to the inverted slope 7061 at the end of the pressure block 706, so that the pressure block 706 moves toward the inside of the support plate 2 along the rectangular groove 3012. At the same time, the pressure block 706 drives the corresponding T-shaped rack 705 to move, and the T-shaped rack 705 drives the gear 703 to rotate, so that the gear 703 drives another group of T-shaped racks 705 to move in the opposite direction, and the gear 703 screws the two groups of torsion springs 704, and then the other group of T-shaped racks 705 drives the driven block 707 moves together with the corresponding support plate 302, so that the end of the support plate 302 moves to the outside of the active cavity 3011, until the end of the concrete component 4 falls on the support plate 302 on the lowest placement rack 3, so as to place the first group of concrete components 4, and at the same time, the end of the support plate 302 on the second group of placement racks 3 located just above the lowest placement rack 3 moves out of the active cavity 3011, and the staff places the remaining concrete components 4 on the device in sequence in the same way. Conversely, when the concrete component 4 is removed from the placement rack 3, after the concrete component 4 is separated from the placement rack 3, under the action of the counter torque force of the torsion spring 704, the support plate 302 on the placement rack 3 above the concrete component 4 moves into the active cavity 3011, so as to remove the obstruction caused by the upper support plate 302 to the removal of the concrete component 4;

[0042] When the defective products are to be recycled, the worm 306 is rotated to rotate the worm wheel 305 together with the hinge shaft 304 and the baffle 303 until the baffle 303 is parallel to the main frame 301, thereby releasing the limit of the baffle 303 on the concrete member 4. Since the roller 3021 is installed on the support plate 302, the defective products that have been released from the limit will slide along the inclined support plate 302 until the defective products are completely separated from between the two sets of placement racks 3.

[0043] The above shows and describes the basic principles, main features and advantages of the present invention. It should be understood by those skilled in the art that the present invention is not limited to the above embodiments. The above embodiments and descriptions are only for explaining the principles of the present invention. Without departing from the spirit and scope of the present invention, the present invention may have various changes and improvements, which fall within the scope of the present invention. The scope of protection of the present invention is defined by the attached claims and their equivalents.

Claims

1. A concrete component anti-cracking maintenance device, comprising a base (1), characterized in that: Two groups of support plates (2) are symmetrically fixedly mounted on the base (1); a plurality of groups of placement frames (3) for supporting concrete components (4) are fixedly mounted at equal distances on one side of the two groups of support plates (2); a drainage pipe (5) is connected to one side of the base (1); and a spray mechanism (6) is provided on the other side of the base (1); The spray mechanism (6) comprises: A main pipe (601), the lower end of the main pipe (601) is located inside the base (1); One side of the main pipe (601) is connected to a water inlet pipe (602), and the other side of the main pipe (601) is provided with a plurality of spray pipes (603) at equal distances, and the spray pipes (603) are provided with a plurality of spray holes (6031); A screw rod (604) is screwed to the lower end of the main pipe (601), and the screw rod (604) is rotatably mounted in the base (1); The placement frame (3) comprises a main frame body (301), and a support plate (302) for supporting the concrete component (4) is arranged on the main frame body (301).

2. A concrete component anti-cracking maintenance device according to claim 1, characterized in that: Two sets of linear bearings (605) are embedded and installed at the lower end of the main pipe (601), and the two sets of linear bearings (605) are slidably connected to two sets of sliding rods (606) respectively, and the sliding rods (606) are fixedly installed in the base (1).

3. A concrete component anti-cracking maintenance device according to claim 2, characterized in that: A plurality of groups of opening and closing mechanisms (7) are arranged at equal distances in the support plate (2), and the opening and closing mechanisms (7) include: Two groups of fixing blocks (702), the two groups of fixing blocks (702) being fixedly installed in the supporting plate (2); A rotating shaft (701), wherein two ends of the rotating shaft (701) are rotatably connected to two sets of fixed blocks (702); A gear (703) fixedly mounted on the rotating shaft (701); Two groups of torsion springs (704) symmetrically arranged on both sides of the gear (703); Two sets of T-shaped racks (705) meshing with the gear (703); One group of the T-shaped racks (705) is fixedly connected to the pressure block (706), and the other group of the T-shaped racks (705) is fixedly connected to the driven block (707).

4. A concrete component anti-cracking maintenance device according to claim 3, characterized in that: The torsion spring (704) is sleeved on the rotating shaft (701), one end of the torsion spring (704) is fixedly connected to the fixing block (702), and the other end of the torsion spring (704) is fixedly connected to the gear (703).

5. A concrete component anti-cracking maintenance device according to claim 4, characterized in that: The main frame (301) is provided with a movable cavity (3011), the support plate (302) is movably plugged into the movable cavity (3011), and one end of the support plate (302) is fixedly connected to the driven block (707).

6. A concrete component anti-cracking maintenance device according to claim 5, characterized in that: A rectangular groove (3012) is provided on the main frame (301), a plurality of groups of second guide holes (202) are provided on one side of the support plate (2), the pressure block (706) passes through the second guide holes (202) and extends into the rectangular groove (3012), and an inverted slope (7061) is provided at the end of the pressure block (706).

7. A concrete component anti-cracking maintenance device according to claim 6, characterized in that: A plurality of groups of first guide holes (201) are also provided on one side of the support plate (2), and the driven block (707) passes through the first guide holes (201).

8. A concrete component anti-cracking maintenance device according to claim 7, characterized in that: The placement rack (3) also includes: A hinge shaft (304), wherein the hinge shaft (304) is hinged in a hinge groove (3013) provided at the end of the main frame body (301); A baffle (303), the end of which is fixedly connected to a hinge shaft (304); A worm gear (305) is fixedly mounted on the upper end of the hinge shaft (304); The worm wheel (305) meshes with the worm (306).

9. A concrete component anti-cracking maintenance device according to claim 8, characterized in that: The worm (306) is rotatably mounted on the end of the main frame (301), and the baffle (303) is used to limit the concrete component (4).

10. A concrete component anti-cracking maintenance device according to claim 9, characterized in that: A plurality of groups of rollers (3021) are rotatably mounted on the support plate (302).

Citation Information

Cited By

  • Prefabricated reinforced concrete component pre-curing device

    CN119704376A

  • Pre-curing device for reinforced concrete prefabricated components

    CN119704376B