Anti-slide pile model generation method and construction method based on BIM

The generation of anti-sliding pile models through BIM technology solves the problem that construction parameters are difficult to obtain intuitively, realizes the intelligence and accuracy of construction, and improves construction efficiency and quality.

CN119129198BActive Publication Date: 2025-08-22CHINA RAILWAY BEIJING ENG GRP CO LTD +1
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202411112665.1
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-14
Publication Date
2025-08-22
Estimated Expiration
2044-08-14

AI Technical Summary

Technical Problem

The existing technology cannot intuitively understand the construction parameters in anti-slip pile construction, and lacks intelligence, resulting in high construction difficulty, high construction period pressure and high quality requirements.

Method used

BIM technology is used to generate anti-sliding pile models. By obtaining the slope support project plan and three-dimensional model during the earth and stone filling process, a digital twin model indicating the construction of anti-sliding piles is generated and displayed to the construction personnel to supervise the construction process.

Benefits of technology

It improves the intelligence and accuracy of construction, ensures the rationality and quality of construction parameters, and reduces the difficulty and construction period pressure.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119129198B_ABST
    Figure CN119129198B_ABST
Patent Text Reader

Abstract

The present invention provides a BIM-based anti-slide pile model generation method and construction method, wherein the method includes: obtaining a slope retaining engineering plan during earthwork filling; obtaining a three-dimensional model of the earthwork filling site; generating an anti-slide pile model based on the slope retaining engineering plan and the three-dimensional model of the earthwork filling site based on BIM technology; displaying the anti-slide pile model to construction personnel; and after the display is completed, supervising the construction personnel's anti-slide pile construction process. The BIM-based anti-slide pile model generation method and construction method of the present invention obtain a slope retaining engineering plan during earthwork filling, and at the same time, obtain a three-dimensional model of the earthwork filling site, introduce BIM technology, and generate a digital twin model indicating the construction of the anti-slide piles, which is convenient for subsequent construction personnel to view and is more intelligent.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of BIM technology, and in particular to a BIM-based anti-slide pile model generation method and a construction method. Background Art

[0002] Anti-slide piles are engineering structures primarily used to enhance the stability of slopes or side slopes, preventing landslides and soil instability. They can be single, double, or multiple piles, and are sometimes used in conjunction with other retaining structures (such as retaining walls and anchors). Design considerations include geological conditions, soil type, slope, and loads (such as those caused by earthquakes and rainfall).

[0003] When carrying out anti-slip pile construction, the anti-slip piles of a project are characterized by a large number, great construction difficulty, great construction period pressure and high quality requirements.

[0004] The invention patent with application number: CN202311689634.8 discloses a construction method for a combination of channel slope concrete replacement and anti-slide piles. The method includes: without changing the top and toe lines of the channel slope, the area with rich weak interlayer development in the channel slope is reinforced with a combination of concrete replacement and anti-slide piles, and the concrete replacement amount and anti-slide pile construction parameters are reasonably determined to achieve the purpose of comprehensively improving the anti-slide stability requirements of the channel slope. The above method is based on the strength reduction method. By reducing the strength parameters of the channel slope body and the weak interlayer, the concrete replacement ratio and the anti-slide pile bearing coefficient are introduced, and the two are combined to form a variety of working conditions and the corresponding safety factors are calculated. From the perspective of construction difficulty and economy, the combination scheme of concrete replacement amount and anti-slide pile parameters is comprehensively determined to complete the reinforcement construction of the channel slope.

[0005] However, when constructing anti-slip piles in the above-mentioned prior art, manual labor cannot intuitively obtain the construction parameters of the anti-slip piles and needs to perform construction according to the design data, which is not intelligent enough.

[0006] In view of this, there is an urgent need for a BIM-based anti-slide pile model generation method and construction method to at least solve the above-mentioned deficiencies. Summary of the Invention

[0007] One of the purposes of the present invention is to provide a BIM-based anti-slide pile model generation method and construction method to obtain the slope support engineering plan during the earth and stone filling process. At the same time, a three-dimensional model of the earth and stone filling site is obtained, and BIM technology is introduced to generate a digital twin model indicating the construction of anti-slide piles, which is convenient for subsequent construction personnel to view and is more intelligent.

[0008] The embodiment of the present invention provides a method for generating an anti-slide pile model based on BIM, comprising:

[0009] Step 1: Obtain the slope support engineering plan during the earthwork filling process;

[0010] Step 2: Obtain a 3D model of the earthwork filling site;

[0011] Step 3: Based on BIM technology, generate an anti-slide pile model according to the slope support engineering plan and the 3D model of the earthwork filling site.

[0012] Preferably, step 1: obtaining a slope support engineering plan during earthwork filling, including:

[0013] During the earthwork filling process, conduct a necessity analysis of slope support;

[0014] If the result of the slope support necessity analysis indicates that it is necessary to carry out slope support, the target slope is determined;

[0015] Determine the slope characteristics of the target slope;

[0016] Determine the slope support engineering plan based on the slope characteristics of the target slope.

[0017] Preferably, the slope support engineering plan is determined based on the slope characteristics of the target slope, including:

[0018] Perform slope feature clustering on the slope features to obtain slope feature clustering results;

[0019] Determine at least one first retaining platform based on the slope feature clustering results;

[0020] Traverse each first support platform in turn, use the first support platform being traversed as the second support platform, and use the slope characteristics corresponding to the second support platform as the basis for formulating the first slope support engineering plan for the second support platform;

[0021] Determine the target plan for the second retaining platform based on the basis for the first slope retaining project plan;

[0022] When all the first retaining platforms are traversed, the target plan is summarized as the slope retaining project plan.

[0023] Preferably, the target plan for the second retaining platform is determined based on the basis for formulating the first slope retaining project plan, including:

[0024] Obtain anti-slide pile support records;

[0025] Analyze the anti-slide pile support records to obtain the basis for formulating the second slope support project plan;

[0026] Determine whether the basis for formulating the second slope support engineering plan is similar to the basis for formulating the first slope support engineering plan;

[0027] If there is a similarity, obtain the first anti-slide pile specification parameters and the first anti-slide pile support point corresponding to the corresponding second slope support engineering plan, and determine the target plan based on the first anti-slide pile specification parameters and the first anti-slide pile support point;

[0028] If there is no similarity, the anti-slide pile support strategy formulation model is trained based on the anti-slide pile support records;

[0029] Obtain specification parameters of the second anti-slide pile;

[0030] Based on the anti-slide pile support strategy formulation model, the specification parameters of the third anti-slide pile and the second anti-slide pile support point are determined according to the second anti-slide pile specification parameters and the second support platform;

[0031] Retrieving an anti-slide pile simulation entity according to the third anti-slide pile specification parameters and the anti-slide pile simulation entity library;

[0032] Construct a third retaining platform that simulates the second retaining platform;

[0033] Based on the relative position of the second anti-sliding pile support point in the second support platform, simulate the anti-sliding pile simulation entity supporting in the third support platform to obtain a first simulation result;

[0034] Obtain simulation parameters of instability factors;

[0035] determining a second simulation result according to the instability factor simulation parameter and the first simulation result;

[0036] If the second simulation result meets the simulation expectations, the target plan is determined based on the third anti-slip pile specification parameters and the second anti-slip pile support points; otherwise, the second simulation result is attributed and the third anti-slip pile specification parameters and the second anti-slip pile support points are adjusted based on the attribution results, and the target plan is determined based on the adjusted third anti-slip pile specification parameters and the second anti-slip pile support points.

[0037] Preferably, obtaining the instability factor simulation parameters includes:

[0038] Obtain subsequent application information of the second support platform;

[0039] The instability factors are obtained according to the subsequent application information, and the simulation parameters of the instability factors are determined according to the conversion rules of the instability factors in the simulation platform.

[0040] Preferably, step 2: obtaining a three-dimensional model of the earthwork filling site includes:

[0041] Acquire first three-dimensional scanning data collected by a first three-dimensional scanning data acquisition party of the earthwork filling site; wherein the first three-dimensional scanning data acquisition party includes: site staff and / or site operation drones;

[0042] A three-dimensional model is constructed based on the first three-dimensional scan data.

[0043] Preferably, step 3: based on BIM technology, generating an anti-slide pile model according to the slope support engineering plan and the three-dimensional model of the earthwork filling site, including:

[0044] According to the slope support engineering plan, determine the second 3D scanning data and anti-slide pile support points of each second support platform; the second 3D scanning data is: the 3D parameters of the anti-slide piles used in the second support platform;

[0045] Based on BIM technology, the anti-slide pile model is rendered in the 3D model according to the anti-slide pile support points and the second 3D scanning data.

[0046] The BIM-based anti-slide pile construction method provided in an embodiment of the present invention includes:

[0047] Demonstrate the anti-slide pile model to construction workers;

[0048] After the demonstration is completed, supervise the construction workers' anti-slide pile construction process;

[0049] The anti-slide pile model is a model generated according to any one of the above-mentioned BIM-based anti-slide pile model generation methods.

[0050] Preferably, the anti-slide pile model is displayed to the construction personnel, including:

[0051] Obtain the construction area that the construction personnel are responsible for;

[0052] Determine the local anti-slide pile model based on the construction area;

[0053] Obtaining the first anti-slide pile simulation point, the construction worker simulation point, and the construction worker's simulated line of sight distance in the local anti-slide pile model;

[0054] An observation circle is constructed based on the construction worker's simulated point, the construction worker's line of sight, and the simulated line of sight distance. The observation circle is perpendicular to the line of sight direction and tangent to the line passing through the construction worker's simulated point, with the tangent point being the construction worker's simulated point. The construction worker's virtual line of sight falls within the observation circle, and the diameter of the observation circle is equal to the simulated line of sight distance.

[0055] Obtaining the first anti-slip pile simulation point that falls within the observation circle and using it as the second anti-slip pile simulation point;

[0056] The remaining first anti-slide pile simulation points except the second anti-slide pile simulation point in the first anti-slide pile simulation points are used as third anti-slide pile simulation points;

[0057] Based on the minimum observation circle projection rule, the minimum observation circle that can include all the third anti-slide pile simulation points is determined, and the projected observation circle is used as the area to be observed;

[0058] Plan the shortest arrival distance trajectory based on the boundary points of the area to be observed and the simulated points of the construction workers;

[0059] The shortest reach distance trajectory is sent to the construction workers as navigation information.

[0060] The BIM-based anti-slide pile construction method provided in an embodiment of the present invention further includes:

[0061] When the construction worker reaches the area boundary point corresponding to the shortest arrival distance trajectory, the center of the area to be observed corresponding to the area boundary point reached is obtained;

[0062] Based on the center of the area and the area boundary points reached by the construction workers, a viewing vector is constructed and directed to the construction workers.

[0063] The beneficial effects of the present invention are:

[0064] The present invention obtains the slope support engineering plan during the earthwork filling process. At the same time, it obtains the three-dimensional model of the earthwork filling site, introduces BIM technology, and generates a digital twin model indicating the construction of anti-slide piles, which is convenient for subsequent construction personnel to view and is more intelligent.

[0065] Other features and advantages of the present invention will be described in the following description, and in part will become apparent from the description, or will be understood by practicing the present invention. The purpose and other advantages of the present invention can be achieved and obtained through the structures specifically pointed out in this application document.

[0066] The technical solution of the present invention is further described in detail below through the accompanying drawings and embodiments. BRIEF DESCRIPTION OF THE DRAWINGS

[0067] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention. In the accompanying drawings:

[0068] Figure 1 Schematic diagram of a method for generating an anti-slide pile model based on BIM in an embodiment of the present invention. DETAILED DESCRIPTION

[0069] The preferred embodiments of the present invention are described below with reference to the accompanying drawings. It should be understood that the preferred embodiments described herein are only used to illustrate and explain the present invention, and are not used to limit the present invention.

[0070] The embodiment of the present invention provides a method for generating an anti-slide pile model based on BIM, such as Figure 1 Shown, including:

[0071] Step 1: Obtain a slope support engineering plan for the earthwork filling process. The earthwork filling process is the process of changing the original terrain through excavation, transportation, and filling of earth and rock materials in a construction project. The slope support engineering plan is an engineering plan for using anti-slide piles on slopes or side slopes to prevent soil sliding and collapse.

[0072] Step 2: Obtain a three-dimensional model of the earthwork filling site; wherein the three-dimensional model is: a 3D model constructed based on the scanning results of the earthwork filling site;

[0073] Step 3: Based on the slope support project plan and the 3D model of the earthwork filling site, generate an anti-slide pile model using BIM technology. The anti-slide pile model is a digital twin of the 3D model of the earthwork filling site, annotated with the BIM information of the required anti-slide piles.

[0074] The working principle and beneficial effects of the above technical solution are:

[0075] The present invention obtains the slope support engineering plan during the earthwork filling process. At the same time, it obtains the three-dimensional model of the earthwork filling site, introduces BIM technology, and generates a digital twin model indicating the construction of anti-slide piles, which is convenient for subsequent construction personnel to view and is more intelligent.

[0076] In one embodiment, step 1: obtaining a slope support engineering plan during earthwork filling, includes:

[0077] During the earthwork filling process, the necessity analysis of slope support is carried out. The necessity analysis of slope support is to analyze whether slope support is necessary by considering factors such as geological conditions, slope and soil stability.

[0078] If the result of the slope support necessity analysis is that it is necessary to support the slope, the target slope is determined; wherein the target slope is: the slope that needs to be supported;

[0079] Determine the slope characteristics of the target slope; wherein the slope characteristics are: physical and geological properties of the target slope;

[0080] Determine the slope support engineering plan based on the slope characteristics of the target slope.

[0081] The working principle and beneficial effects of the above technical solution are:

[0082] The present invention analyzes the necessity of slope support during earthwork filling. If the analysis shows it is necessary, the target slope is determined and its slope characteristics are extracted. Based on the slope characteristics, a slope support engineering plan is determined, thereby improving the rationality of the slope support engineering plan.

[0083] In one embodiment, a slope support engineering plan is determined based on the slope characteristics of the target slope, including:

[0084] Perform slope feature clustering on the slope features to obtain slope feature clustering results; wherein, slope feature clustering refers to grouping slopes with similar features into one category;

[0085] Determine at least one first retaining platform based on the clustering results of the slope characteristics; wherein the first retaining platform is: a slope with similar characteristics;

[0086] Traverse each first support platform in turn, use the first support platform being traversed as the second support platform, and use the slope characteristics corresponding to the second support platform as the basis for formulating the first slope support engineering plan for the second support platform;

[0087] Based on the basis for the first slope retaining project plan, determine the target plan for the second retaining platform; the target plan includes: the anti-slide pile model setting plan for the second retaining platform, such as: where to set the anti-slide piles with what specifications and parameters;

[0088] When all the first retaining platforms are traversed, the target plan is summarized as the slope retaining project plan.

[0089] The working principle and beneficial effects of the above technical solution are:

[0090] Because different slope characteristics require different strategies for setting anti-slide piles, we clustered the slope characteristics and divided the retaining platforms based on the clustering results. We developed target plans based on the first slope support engineering plan for each second retaining platform, and then aggregated the target plans into the slope support engineering plan, improving the accuracy of slope support engineering plan development.

[0091] In one embodiment, based on the basis for formulating the first slope retaining project plan, determining the target plan for the second retaining platform includes:

[0092] Obtaining anti-sliding pile support records; wherein, the anti-sliding pile support records are: historical records of the anti-sliding pile support process;

[0093] Analyze the anti-slide pile support records to obtain the basis for formulating the second slope support engineering plan; the basis for formulating the second slope support engineering plan is: the basis for formulating the support operation plan in the anti-slide pile support records;

[0094] Determine whether the basis for formulating the second slope support engineering plan is similar to the basis for formulating the first slope support engineering plan;

[0095] If there is similarity, obtain the first anti-slide pile specification parameters and the first anti-slide pile support point corresponding to the basis for formulating the corresponding second slope support engineering plan, and determine the target plan based on the first anti-slide pile specification parameters and the first anti-slide pile support point; wherein the first anti-slide pile specification parameters are: when the basis for formulating the second slope support engineering plan is similar to the basis for formulating the first slope support engineering plan, the specification parameters of the anti-slide piles recorded in the corresponding anti-slide pile support record; the first anti-slide pile support point is: when the basis for formulating the second slope support engineering plan is similar to the basis for formulating the first slope support engineering plan, the distribution position of the anti-slide piles recorded in the corresponding anti-slide pile support record in the corresponding building entity;

[0096] If no similarity exists, an anti-sliding pile support strategy formulation model is trained based on the anti-sliding pile support records; wherein the anti-sliding pile support strategy formulation model is an AI model trained based on the anti-sliding pile support records to replace manual anti-sliding pile support strategy formulation;

[0097] Obtaining specification parameters of the second anti-slide pile; wherein the specification parameters of the second anti-slide pile are: specification parameters of all locally applicable anti-slide piles that can be obtained by big data;

[0098] Based on the anti-slide pile support strategy formulation model, the specifications of the third anti-slide pile and the second anti-slide pile support point are determined according to the specifications of the second anti-slide pile and the second support platform; wherein the specifications of the third anti-slide pile and the second anti-slide pile support point are: the anti-slide pile support strategy (the selected specifications and support positions of the anti-slide piles) determined by the anti-slide pile support strategy formulation model based on the specifications of the locally applicable anti-slide piles and the first slope support engineering plan formulation basis of the second support platform for which the anti-slide pile support strategy formulation is required;

[0099] Retrieving an anti-slide pile simulation entity based on the third anti-slide pile specification parameters and an anti-slide pile simulation entity library; wherein the anti-slide pile simulation entity library is a database storing simulation data of anti-slide piles of different specification parameters in a construction engineering simulation platform; and the anti-slide pile simulation entity is a simulation parameter corresponding to the third anti-slide pile specification parameters;

[0100] Constructing a third support platform simulating the second support platform; wherein the third support platform is: the second support platform simulated in the simulation platform of the construction project;

[0101] Based on the relative position of the second anti-sliding pile support point in the second supporting platform, simulate the anti-sliding pile simulation entity supporting in the third supporting platform to obtain a first simulation result; wherein the first simulation result is: a simulation model obtained after simulating the installation of anti-sliding piles in the third supporting platform based on the relative position of the second anti-sliding pile support point in the second supporting platform;

[0102] Acquire instability factor simulation parameters; wherein the instability factor simulation parameters are: simulation data of environmental factors that affect the stability of the second retaining platform;

[0103] Determining a second simulation result based on the instability factor simulation parameter and the first simulation result; wherein the second simulation result is: a simulation result of the corresponding simulation model after applying the interference of the instability factor simulation parameter on the first simulation result;

[0104] If the second simulation results meet the simulation expectations, the target plan is determined based on the specifications and positions of the third anti-slide piles and the second anti-slide pile support points. Otherwise, the second simulation results are attributed and the specifications and positions of the third anti-slide piles and the second anti-slide pile support points are adjusted based on the attribution results. The target plan is then determined based on the adjusted specifications and positions of the third anti-slide piles and the second anti-slide pile support points. Meeting the simulation expectations means that the third support platform does not collapse, suffer from significant soil erosion, or otherwise fail to meet construction standards.

[0105] The working principle and beneficial effects of the above technical solution are:

[0106] The present invention introduces the anti-sliding pile support records of anti-sliding pile support in history. The basis for formulating the second slope support engineering plan in the anti-sliding pile support record is obtained, and the basis for formulating the first slope support engineering plan and the basis for formulating the second slope support engineering plan are matched to determine whether there is a similarity in the formulation basis. If there is a similarity, the target plan can be determined based on the same logic as the corresponding second slope support engineering plan. Otherwise, the anti-sliding pile support strategy formulation model is trained based on the anti-sliding pile support record; the third anti-sliding pile specification parameters and the second anti-sliding pile support point are determined according to the available second anti-sliding pile specification parameters and the second support platform, and a simulation platform for the construction project is introduced to simulate the anti-sliding pile simulation entity supporting in the third support platform. After the simulated support, simulation data of environmental factors that affect the stability of the second support platform are also introduced to determine the support effect; when the support effect meets expectations, the target plan corresponding to the simulation strategy is output, otherwise adaptive adjustments are made to improve the rationality of the target plan formulation.

[0107] In one embodiment, obtaining the instability factor simulation parameters includes:

[0108] Obtaining subsequent application information of the second supporting platform; wherein the subsequent application information is: subsequent use information of the second supporting platform, such as: use as a helipad;

[0109] The instability factor is obtained based on the subsequent application information, and the instability factor simulation parameters are determined based on the conversion rules of the instability factor in the simulation platform. Among them, the instability factor is, for example, the roll of the aircraft.

[0110] The working principle and beneficial effects of the above technical solution are:

[0111] The present invention introduces subsequent application information of the second retaining platform to determine the instability factor, and introduces the conversion rule of the instability factor in the simulation platform to determine the simulation parameters of the instability factor, thereby improving the standardization of the acquisition of the simulation parameters of the instability factor.

[0112] In one embodiment, step 2: obtaining a three-dimensional model of the earthwork filling site includes:

[0113] Acquire first three-dimensional scanning data collected by a first three-dimensional scanning data acquisition party of the earthwork filling site; wherein the first three-dimensional scanning data acquisition party includes: site staff and / or site operation drones;

[0114] A three-dimensional model is constructed based on the first three-dimensional scan data.

[0115] The working principle and beneficial effects of the above technical solution are:

[0116] The present invention obtains first three-dimensional scanning data by site staff and site operation drones to construct a three-dimensional model, and the process of constructing the three-dimensional model is more suitable.

[0117] In one embodiment, step 3: Based on BIM technology, an anti-slide pile model is generated according to the slope support engineering plan and the three-dimensional model of the earthwork filling site, including:

[0118] According to the slope support engineering plan, determine the second 3D scanning data and anti-slide pile support points of each second support platform; the second 3D scanning data is: the 3D parameters of the anti-slide piles used in the second support platform;

[0119] Based on BIM technology, the anti-slide pile model is rendered in the 3D model according to the anti-slide pile support points and the second 3D scanning data.

[0120] The working principle and beneficial effects of the above technical solution are:

[0121] The present invention constructs a BIM model based on the slope retaining engineering plan, thereby improving the rationality of rendering.

[0122] An embodiment of the present invention provides a BIM-based anti-slide pile construction method, comprising:

[0123] Demonstrate the anti-slide pile model to the construction personnel; wherein, demonstrating the anti-slide pile model to the construction personnel means displaying the construction parameters of the anti-slide pile in the earthwork filling site (e.g., anti-slide pile specifications and locations) to the construction personnel through BIM information display equipment;

[0124] After the demonstration is completed, the construction workers will be supervised in the anti-slip pile construction process. Supervising the construction workers' anti-slip pile construction process means supervising whether the construction workers have carried out the anti-slip pile construction in a standardized manner, that is, whether the construction results meet the planned requirements.

[0125] The anti-slide pile model is a model generated by the BIM-based anti-slide pile model generation method described in any one of the above embodiments.

[0126] The working principle and beneficial effects of the above technical solution are:

[0127] The present invention displays the anti-slip pile model to the construction workers to instruct them on the anti-slip pile construction, which is more intelligent and timely monitors the anti-slip pile construction process, thereby improving the accuracy of the construction.

[0128] In one embodiment, the anti-slide pile model is displayed to construction personnel, including:

[0129] Obtain the construction area that the construction personnel are responsible for; the responsible construction area is: the earthwork filling site that the construction personnel need to be responsible for construction;

[0130] Determine a local anti-slide pile model based on the responsible construction area; wherein the local anti-slide pile model is: a local model for simulating anti-slide pile construction in the responsible construction area;

[0131] Obtain the first anti-slide pile simulation point, the construction worker simulation point, and the construction worker's simulated line of sight distance in the local anti-slide pile model; wherein the first anti-slide pile simulation point is: the distribution of the simulated anti-slide piles in the local anti-slide pile model; the construction worker simulation point is: the construction worker's real-time position corresponding to the simulated position in the local anti-slide pile model; the construction worker's simulated line of sight distance is: the construction worker's line of sight distance in the display device;

[0132] An observation circle is constructed based on the construction worker's simulated point, the construction worker's line of sight, and the simulated line of sight distance. The observation circle is perpendicular to the line of sight direction and tangent to the line passing through the construction worker's simulated point, with the tangent point being the construction worker's simulated point. The construction worker's virtual line of sight falls within the observation circle, and the diameter of the observation circle is equal to the simulated line of sight distance.

[0133] The first anti-slip pile simulation point falling within the observation circle is obtained and used as the second anti-slip pile simulation point; the remaining first anti-slip pile simulation points except the second anti-slip pile simulation point are used as the third anti-slip pile simulation point;

[0134] Based on the minimum observation circle projection rule, the minimum observation circle that can include all the third anti-slide pile simulation points is determined, and the projected observation circle is used as the area to be observed;

[0135] Plan the shortest reach distance trajectory based on the regional boundary points of the area to be observed and the construction personnel simulation points; each regional boundary point on the shortest reach distance trajectory has only one corresponding area to be observed, and the areas to be observed are different from each other;

[0136] The shortest reach distance trajectory is sent to the construction workers as navigation information.

[0137] The working principle and beneficial effects of the above technical solution are:

[0138] The present invention obtains the local anti-slip pile model of the construction area that the construction worker is responsible for. Considering that the construction area is too large and the construction workers cannot see all the BIM information of the construction they are responsible for at one time, an observation circle is constructed according to the construction workers' simulation points, the construction workers' line of sight direction and the simulated line of sight distance; the anti-slip pile monomer model corresponding to the second anti-slip pile simulation point falling into the observation circle is able to be viewed in time by the construction workers, and the anti-slip pile monomer model corresponding to the third anti-slip pile simulation point is waiting for the construction workers to view; in order to improve the observation efficiency, the minimum observation circle projection rule is introduced to determine the area to be observed, and the shortest arrival distance trajectory is planned according to the regional boundary points of the area to be observed and the construction workers' simulation points, and the navigation information is sent to the construction workers. The construction workers can subsequently view their own construction tasks with the highest efficiency in the construction site based on the shortest arrival distance trajectory, which is more humane.

[0139] An embodiment of the present invention provides a BIM-based anti-slide pile construction method, further comprising:

[0140] When the construction worker reaches the area boundary point corresponding to the shortest arrival distance trajectory, the center of the area to be observed corresponding to the area boundary point reached is obtained;

[0141] Based on the center of the area and the boundary point where the construction workers arrive, a look vector is constructed and used to instruct the construction workers. The direction of the look vector is the direction from the boundary point where the construction workers arrive to the center of the area.

[0142] The working principle and beneficial effects of the above technical solution are:

[0143] After the construction workers arrive at the actual position corresponding to the boundary point of the area, there is a situation where the observation line of sight does not fall into the area to be observed. Therefore, according to the center of the area circle and the boundary point of the area arrived by the construction workers, a viewing vector is constructed, and the vector angle is calculated based on the current viewing vector of the construction workers and the viewing vector, prompting the construction workers to adjust their line of sight, further improving the display efficiency.

[0144] Obviously, those skilled in the art may make various changes and modifications to the present invention without departing from the spirit and scope of the present invention. Thus, if such changes and modifications fall within the scope of the claims and their equivalents, the present invention is intended to include such changes and modifications.

Claims

1. The anti-slide pile model generation method based on BIM is characterized by: include: Step 1: Obtain the slope support engineering plan during the earthwork filling process; Step 2: Obtain a 3D model of the earthwork filling site; Step 3: Generate an anti-slide pile model based on the slope support engineering plan and the 3D model of the earthwork filling site using BIM technology; Step 1: Obtaining the slope support engineering plan during the earthwork filling process, including: During the earthwork filling process, conduct a necessity analysis of slope support; If the result of the slope support necessity analysis indicates that it is necessary to carry out slope support, the target slope is determined; Determine the slope characteristics of the target slope; According to the slope characteristics of the target slope, determine the slope support engineering plan, including: Perform slope feature clustering on the slope features to obtain slope feature clustering results; Determine at least one first retaining platform based on the slope feature clustering results; Traverse each first support platform in turn, use the first support platform being traversed as the second support platform, and use the slope characteristics corresponding to the second support platform as the basis for formulating the first slope support engineering plan for the second support platform; Determine the target plan for the second retaining platform based on the basis for the first slope retaining project plan; When all the first retaining platforms are traversed, the target plan is summarized as the slope retaining project plan.

2. The method for generating an anti-slide pile model based on BIM according to claim 1, wherein: Based on the basis for the first slope retaining project plan, determine the target plan for the second retaining platform, including: Obtain anti-slide pile support records; Analyze the anti-slide pile support records to obtain the basis for formulating the second slope support project plan; Determine whether the basis for formulating the second slope support engineering plan is similar to the basis for formulating the first slope support engineering plan; If there is a similarity, obtain the first anti-slide pile specification parameters and the first anti-slide pile support point corresponding to the corresponding second slope support engineering plan, and determine the target plan based on the first anti-slide pile specification parameters and the first anti-slide pile support point; If there is no similarity, the anti-slide pile support strategy formulation model is trained based on the anti-slide pile support records; Obtain specification parameters of the second anti-slide pile; Based on the anti-slide pile support strategy formulation model, the specification parameters of the third anti-slide pile and the second anti-slide pile support point are determined according to the second anti-slide pile specification parameters and the second support platform; Retrieving an anti-slide pile simulation entity according to the third anti-slide pile specification parameters and the anti-slide pile simulation entity library; Construct a third retaining platform that simulates the second retaining platform; Based on the relative position of the second anti-sliding pile support point in the second support platform, simulate the anti-sliding pile simulation entity supporting in the third support platform to obtain a first simulation result; Obtain simulation parameters of instability factors; determining a second simulation result according to the instability factor simulation parameter and the first simulation result; If the second simulation result meets the simulation expectations, the target plan is determined based on the third anti-slip pile specification parameters and the second anti-slip pile support points; otherwise, the second simulation result is attributed and the third anti-slip pile specification parameters and the second anti-slip pile support points are adjusted based on the attribution results, and the target plan is determined based on the adjusted third anti-slip pile specification parameters and the second anti-slip pile support points.

3. The method for generating an anti-slide pile model based on BIM according to claim 2, wherein: Get the simulation parameters of instability factors, including: Obtain subsequent application information of the second supporting platform; The instability factors are obtained according to the subsequent application information, and the simulation parameters of the instability factors are determined according to the conversion rules of the instability factors in the simulation platform.

4. The method for generating an anti-slide pile model based on BIM according to claim 1, wherein: Step 2: Obtain a 3D model of the earthwork filling site, including: Acquire first three-dimensional scanning data collected by a first three-dimensional scanning data acquisition party of the earthwork filling site; wherein the first three-dimensional scanning data acquisition party includes: site staff and / or site operation drones; A three-dimensional model is constructed based on the first three-dimensional scan data.

5. The method for generating an anti-slide pile model based on BIM according to claim 1, wherein: Step 3: Based on the slope support engineering plan and the 3D model of the earthwork filling site, an anti-slide pile model is generated using BIM technology, including: According to the slope support engineering plan, determine the second 3D scanning data and anti-slide pile support points of each second support platform; the second 3D scanning data is: the 3D parameters of the anti-slide piles used in the second support platform; Based on BIM technology, the anti-slide pile model is rendered in the 3D model according to the anti-slide pile support points and the second 3D scanning data.

6. The BIM-based anti-slide pile construction method is characterized by: include: Demonstrate the anti-slide pile model to construction workers; After the demonstration is completed, supervise the construction workers' anti-slide pile construction process; Wherein, the anti-slide pile model is a model generated according to the BIM-based anti-slide pile model generation method according to any one of claims 1 to 5.

7. The BIM-based anti-slide pile construction method according to claim 6, characterized in that: Demonstrate the anti-slide pile model to the construction personnel, including: Obtain the construction area that the construction personnel are responsible for; Determine the local anti-slide pile model based on the construction area; Obtaining the first anti-slide pile simulation point, the construction worker simulation point, and the construction worker's simulated line of sight distance in the local anti-slide pile model; An observation circle is constructed based on the construction worker's simulated point, the construction worker's line of sight, and the simulated line of sight distance. The observation circle is perpendicular to the line of sight direction and tangent to the line passing through the construction worker's simulated point, with the tangent point being the construction worker's simulated point. The construction worker's virtual line of sight falls within the observation circle, and the diameter of the observation circle is equal to the simulated line of sight distance. Obtaining the first anti-slip pile simulation point that falls within the observation circle and using it as the second anti-slip pile simulation point; The remaining first anti-slide pile simulation points except the second anti-slide pile simulation point in the first anti-slide pile simulation points are used as third anti-slide pile simulation points; Based on the minimum observation circle projection rule, the minimum observation circle that can include all the third anti-slide pile simulation points is determined, and the projected observation circle is used as the area to be observed; Plan the shortest arrival distance trajectory based on the boundary points of the area to be observed and the simulated points of the construction workers; The shortest reach distance trajectory is sent to the construction workers as navigation information.

8. The BIM-based anti-slide pile construction method according to claim 7, characterized in that: Also includes: When the construction worker reaches the area boundary point corresponding to the shortest arrival distance trajectory, the center of the area to be observed corresponding to the area boundary point reached is obtained; Based on the center of the area and the area boundary points reached by the construction workers, a viewing vector is constructed and directed to the construction workers.

Citation Information

Patent Citations

  • A construction method for channel slope concrete replacement and anti-slide pile combination

    CN117604975B