Method and device for determining power grid construction scheme, equipment and storage medium

By constructing a power grid construction plan to determine the model and optimizing the voltage level sequence, the historical problems of urban distribution networks in voltage level selection and configuration are solved, the power supply capacity and resource utilization of the power grid are improved, and costs and losses are reduced.

CN119168406APending Publication Date: 2024-12-20STATE GRID SHANGHAI MUNICIPAL ELECTRIC POWER CO +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411188637.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-28
Publication Date
2024-12-20

AI Technical Summary

Technical Problem

There are historical problems in the selection and configuration of voltage levels in urban distribution networks, resulting in high investment costs and unreasonable resource allocation, making it difficult to meet the rapidly developing power supply needs.

Method used

By obtaining the construction demand information of the substation to be built and building a grid construction plan determination model based on the properties of the voltage-grade substation, scientifically formulate a reasonable power supply voltage level sequence and optimize the grid construction plan.

Benefits of technology

It improves the power supply capacity and adaptability of urban power grids, reduces network losses and construction costs, and saves space resources.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119168406A_ABST
    Figure CN119168406A_ABST
Patent Text Reader

Abstract

The invention discloses a power grid construction scheme determination method, apparatus and device, and a storage medium. The method comprises the steps of obtaining construction demand information of a to-be-constructed transformer substation; obtaining a power grid construction scheme determination model; the power grid construction scheme determination model is constructed based on attribute information of transformer substations of various voltage levels; and determining a power grid construction scheme of a to-be-constructed power grid based on the construction demand information and the power grid construction scheme determination model. By utilizing the method, a reasonable power supply voltage grade sequence is formulated based on a scientific model, and the voltage grade sequence is reasonably selected and simplified, so that the overall power supply capability of an urban power grid can be improved, and the adaptability of the power grid to loads with different properties and different installation capacities is improved; meanwhile, network loss can be reduced, limited space resources are saved, and power grid construction and operation cost is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] Embodiments of the present invention relate to the technical field of power grid construction investment, and in particular to a method, device, equipment and storage medium for determining a power grid construction plan. Background Art

[0002] The voltage level sequence is an important specification for the design, construction, equipment and operation and maintenance of all links of power system transmission, distribution and use. A voltage level sequence with reasonable level difference and appropriate number can effectively reduce the investment in power system construction and the operation and maintenance costs. In the process of my country's power grid development and voltage level series simplification, 10 kV was promoted as the medium voltage distribution voltage and 35 kV as the high voltage distribution voltage. There are a large number of 10 kV and 35 kV stock power facilities in the current power grid. If considering using 110 kV and 20 kV voltage levels to replace the current 35 kV and 10 kV voltages, the transformation costs and difficulties brought about by the adjustment must be fully considered.

[0003] In recent years, with the acceleration of urban construction and development, the tightening of resources and conditions for urban infrastructure construction, and the adjustment of investment boundaries for user power supply projects caused by the optimization of the business environment, the development of urban distribution networks faces new requirements and situations. However, the current selection of power supply voltage levels for urban distribution networks follows historical evolution. How to reasonably select and simplify the configuration of voltage level sequences and formulate a reasonable power supply voltage level sequence has become a top priority. Summary of the invention

[0004] The embodiments of the present invention provide a method, device, equipment and storage medium for determining a power grid construction plan, which are conducive to improving wind power utilization, reducing wind power abandonment, improving economic efficiency, and achieving reasonable allocation of resources.

[0005] In a first aspect, an embodiment of the present invention provides a method for determining a power grid construction plan, the method comprising:

[0006] Obtain construction demand information of the substation to be constructed;

[0007] Obtaining a power grid construction plan determination model; the power grid construction plan determination model is constructed based on attribute information of substations of various voltage levels;

[0008] A power grid construction plan for the power grid to be constructed is determined based on the construction demand information and the power grid construction plan determination model.

[0009] In a second aspect, an embodiment of the present invention further provides a device for determining a power grid construction plan, the device comprising:

[0010] A data acquisition module is used to obtain construction demand information of the substation to be constructed;

[0011] A model acquisition module is used to acquire a model for determining a power grid construction plan; the model for determining a power grid construction plan is constructed based on attribute information of substations of various voltage levels;

[0012] A plan output module is used to determine a power grid construction plan for the power grid to be constructed based on the construction demand information and the power grid construction plan determination model.

[0013] In a third aspect, an embodiment of the present disclosure further provides an electronic device, the electronic device comprising:

[0014] one or more processors;

[0015] a storage device for storing one or more programs,

[0016] When the one or more programs are executed by the one or more processors, the one or more processors implement the method for determining the power grid construction plan provided in the embodiment of the present disclosure.

[0017] In a fourth aspect, the embodiments of the present disclosure further provide a storage medium comprising computer executable instructions, which, when executed by a computer processor, are used to implement a method for determining a power grid construction plan provided by the embodiments of the present disclosure.

[0018] The present invention discloses a method, device, equipment and storage medium for determining a power grid construction plan, the method comprising: obtaining construction demand information of a substation to be constructed; obtaining a power grid construction plan determination model; the power grid construction plan determination model is constructed based on the attribute information of substations of various voltage levels; and determining the power grid construction plan of the power grid to be constructed based on the construction demand information and the power grid construction plan determination model. By using this method, a reasonable power supply voltage level sequence is formulated based on a scientific model, and the voltage level sequence is reasonably selected and simplified to configure, which can not only improve the overall power supply capacity of the urban power grid and improve the adaptability of the power grid to loads of different natures and different reported capacities, but also reduce network losses, save limited space resources, and reduce power grid construction and operation costs. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] The above and other features, advantages and aspects of the embodiments of the present disclosure will become more apparent with reference to the following detailed description in conjunction with the accompanying drawings. Throughout the accompanying drawings, the same or similar reference numerals represent the same or similar elements. It should be understood that the drawings are schematic and the originals and elements are not necessarily drawn to scale.

[0020] Figure 1 A flowchart of a method for determining a power grid construction plan provided by an embodiment of the present disclosure;

[0021] Figure 2A schematic diagram of double-sided power chain wiring and modeling provided in an embodiment of the present disclosure;

[0022] Figure 3 A schematic diagram of the double-sided power supply radiation wiring and modeling provided in an embodiment of the present disclosure;

[0023] Figure 4 A schematic diagram of ring network wiring and modeling provided in an embodiment of the present disclosure;

[0024] Figure 5 A schematic diagram of a 110 / 35 / 10 kV hybrid power supply sequence power supply mode provided for an embodiment of the present disclosure;

[0025] Figure 6 A schematic diagram of the structure of a device for determining a power grid construction plan provided by an embodiment of the present disclosure;

[0026] Figure 7 A schematic diagram of the structure of an electronic device provided by an embodiment of the present disclosure. DETAILED DESCRIPTION

[0027] Embodiments of the present disclosure will be described in more detail below with reference to the accompanying drawings. Although certain embodiments of the present disclosure are shown in the accompanying drawings, it should be understood that the present disclosure can be implemented in various forms and should not be construed as being limited to the embodiments described herein, which are instead provided for a more thorough and complete understanding of the present disclosure. It should be understood that the drawings and embodiments of the present disclosure are only for exemplary purposes and are not intended to limit the scope of protection of the present disclosure.

[0028] It should be understood that the various steps described in the method embodiments of the present disclosure may be performed in different orders and / or in parallel. In addition, the method embodiments may include additional steps and / or omit the steps shown. The scope of the present disclosure is not limited in this respect.

[0029] The term "including" and its variations used herein are open inclusions, i.e., "including but not limited to". The term "based on" means "based at least in part on". The term "one embodiment" means "at least one embodiment"; the term "another embodiment" means "at least one additional embodiment"; the term "some embodiments" means "at least some embodiments". The relevant definitions of other terms will be given in the following description.

[0030] It should be noted that the concepts such as "first" and "second" mentioned in the present disclosure are only used to distinguish different devices, modules or units, and are not used to limit the order or interdependence of the functions performed by these devices, modules or units.

[0031] It should be noted that the modifications of "one" and "plurality" mentioned in the present disclosure are illustrative rather than restrictive, and those skilled in the art should understand that unless otherwise clearly indicated in the context, it should be understood as "one or more".

[0032] The names of the messages or information exchanged between multiple devices in the embodiments of the present disclosure are only used for illustrative purposes and are not used to limit the scope of these messages or information.

[0033] It is understandable that before using the technical solutions disclosed in the embodiments of the present disclosure, the types, scope of use, usage scenarios, etc. of the personal information involved in the present disclosure should be informed to the user and the user's authorization should be obtained in an appropriate manner in accordance with relevant laws and regulations.

[0034] For example, in response to receiving an active request from a user, a prompt message is sent to the user to clearly prompt the user that the operation requested to be performed will require obtaining and using the user's personal information. Thus, the user can autonomously choose whether to provide personal information to software or hardware such as an electronic device, application, server, or storage medium that performs the operation of the technical solution of the present disclosure according to the prompt message.

[0035] As an optional but non-limiting implementation, in response to receiving an active request from the user, the prompt information may be sent to the user in the form of a pop-up window, in which the prompt information may be presented in text form. In addition, the pop-up window may also carry a selection control for the user to choose "agree" or "disagree" to provide personal information to the electronic device.

[0036] It is understandable that the above notification and the process of obtaining user authorization are merely illustrative and do not constitute a limitation on the implementation of the present disclosure. Other methods that meet the relevant laws and regulations may also be applied to the implementation of the present disclosure.

[0037] It is understandable that the data involved in this technical solution (including but not limited to the data itself, the acquisition or use of the data) shall comply with the requirements of relevant laws, regulations and relevant provisions.

[0038] Embodiment 1

[0039] Figure 1 A flowchart for determining a power grid construction plan provided in an embodiment of the present disclosure is applicable to situations where a reasonable selection and simplified configuration of a voltage level sequence is provided. The method can be executed by a device for determining a power grid construction plan, which can be implemented in the form of software and / or hardware, and optionally, by an electronic device, which can be a mobile terminal, a PC, a server, etc.

[0040] like Figure 1As shown, a method for determining a power grid construction plan provided by an embodiment of the present disclosure may specifically include the following steps:

[0041] S110. Obtain construction requirement information of the substation to be constructed.

[0042] The construction demand information includes: load power supply demand information and substation line circuit number demand information.

[0043] In this embodiment, the construction demand information may be the demand information of the target area to be constructed. Under the combined boundaries of load density, load structure, and power supply mode within the power supply range of the blank area, in order to ensure the power supply requirements within the power supply area, the power balance and the number of facility power line loop constraints must be met.

[0044] Specifically, obtain construction demand information in the area to be constructed.

[0045] S120. Obtain a model for determining a power grid construction plan.

[0046] Among them, the grid construction plan determination model is constructed based on the attribute information of substations at each voltage level.

[0047] Optionally, the construction process of the power grid construction plan determination model may be:

[0048] a1) Determine the construction cost impact coefficient corresponding to different attribute information of substations of different voltage levels;

[0049] b1) The sum of the product of each attribute information of each voltage level substation and the corresponding construction cost impact coefficient is used as the construction impact relationship of the power grid construction plan determination model;

[0050] c1) extracting power supply capacity information included in the attribute information of each voltage level substation, and determining the power supply impact coefficient of each voltage level substation;

[0051] d1) Determine the product of the power supply capacity information of each voltage level substation and the power supply impact coefficient, and use the sum of each product as the power supply impact relationship of the power grid construction plan determination model.

[0052] Among them, the attribute information includes: station construction cost, line cost, line length, operation cost and social resource occupation cost. The power supply capacity information includes: power supply amount and number of line loops; the power supply impact coefficient includes: power supply demand impact coefficient and line loop impact coefficient.

[0053] In this embodiment, the construction cost impact coefficient may be a corresponding impact relationship index between the construction cost and the attribute information, and the power supply impact coefficient may be an impact coefficient between the power supply capacity information and the power supply capacity of each voltage level substation.

[0054] Specifically, the construction cost impact coefficient corresponding to the different attribute information of the substations of each voltage level is determined, and the sum of the products of the attribute information of the substations of each voltage level and the corresponding construction cost impact coefficient is used as the construction impact relationship of the power grid construction plan determination model, the power supply capacity information included in the attribute information of the substations of each voltage level is extracted, and the power supply impact coefficient of the substations of each voltage level is determined, the product of the power supply capacity information of the substations of each voltage level and the power supply impact coefficient is determined, and the sum of each product is used as the power supply impact relationship of the power grid construction plan determination model.

[0055] Optionally, the method of determining the product of the power supply capacity information of each voltage level substation and the power supply impact coefficient, and taking the sum of the products as the power supply impact relationship of the power grid construction plan determination model may be:

[0056] d11) Determine the product of the power supply of each voltage level substation and the power supply demand impact coefficient.

[0057] d12) Determine the product of the number of line loops and the line loop influence coefficient of each voltage level substation.

[0058] d13) The sum of the products is used as the power supply impact relationship of the power grid construction plan to determine the model.

[0059] Exemplarily, the construction process of the construction impact relationship in the grid construction plan determination model is as follows: It should be known that the power facility cost parameters include: unit initial investment, annual equivalent operating cost and equivalent cost of social resource occupation for substations and lines of different voltage levels such as 110 kV and 35 kV. Among them, the social resource occupation cost refers to the equivalent cost of land resources occupied by substation site selection and line selection and other social impacts generated by them. It can be calculated based on the scale of facility land combined with unit land acquisition costs. For urban scenarios where land resources are very tight, this fee can be appropriately increased. Regional power demand parameters include: regional planning scope and land area, load density and load structure. Among them, the load structure refers to the power composition of users in the region. For example: the power load level of general residential users, the power load level of large industrial users, and the power load level of non-industrial large users. In order to facilitate research, users can be classified and sorted according to the power level and interval range. The boundaries of the power supply mode include: the connection types to be adopted in the regional planning of 110 kV, 35 kV and other different voltage levels of power grids, such as double-sided power supply chain connection type, double-sided power supply radial connection type, double-sided power supply ring network connection type, etc., the correspondence between the power supply voltage level and the power consumption level, that is, the voltage level selection rules adopted by users in a specific capacity range for power supply, the number of user power supply circuits, and the maximum allowable number of power supply line circuits for unit power facilities of different voltage levels such as 110 kV and 35 kV.

[0060] A regional power supply model with associated substations and lines is established based on the requirements of the grid connection type. Assuming that the load is evenly distributed in the region, the number of substations and the length of the corresponding voltage level lines are correlated within a specific area. The more substations there are at each level, the smaller the power supply range of a single substation, and the shorter the length of the new power supply line required to meet the power supply needs of users within its power supply range. Vice versa. A model describing the relationship between the length of the power supply line and the number of substations is established based on the grid connection type.

[0061] The first type is a double-sided power chain wiring model. Figure 2 The schematic diagram of the double-side power chain wiring and modeling provided by the embodiment of the present disclosure is as follows: Figure 2 As shown in the figure, taking the 110 kV power grid as an example, chain connection refers to a "hand-in-hand" connection method formed by multiple 110 kV substations using the upper 220 kV substations on both sides as power supply points, and a new 110 kV line is built from one side of the power supply to connect the 110 kV substations in sequence, and finally reaches the power supply on the other side. The formation of N such chain connections is called N chain connections. The average line length L of a newly built single 110 kV substation is described by the power supply radius and load density of the power facilities. ρ110 :

[0062]

[0063] Where: S1, S2 is the power supply capacity of a single 220 / 110 kV substation; ρ is the average load density; k1 is the wiring length coefficient. According to the double-side power supply, N-link wiring, considering the line tortuosity coefficient Calculated as:

[0064] The second type is the double-sided power supply radial wiring model. Figure 3 The schematic diagram of the double-sided power supply radiation wiring and modeling provided in the embodiment of the present disclosure is as follows: Figure 3 As shown in the figure, taking the 35 kV power grid as an example, radial wiring refers to a wiring method in which a single 35 kV substation uses the upper 220 kV substations on both sides as power supply points, and builds a new 35 kV line from each power supply point to the station. The substation using the modified wiring type has a total of 2 power supply lines of corresponding voltage levels. The average line length L of a newly built single 35 kV substation is described by the power supply radius and load density of the power facilities. ρ35 :

[0065]

[0066] Among them: S1, S3 are the power supply capacity of a single 220 / 35 kV substation; ρ is the average load density; k2 is the wiring length coefficient. According to the double-side power supply, radial wiring, and considering the line tortuosity coefficient Calculated as:

[0067] The third type is the double-sided power ring network wiring model. Figure 4 The ring network wiring and modeling diagram provided in the embodiment of the present disclosure is as follows: Figure 4 As shown in the figure, the ring network connection type has some similarities with the double-side power chain connection model, but it allows new lines to be built from the same power source point to connect the lower-level substations in series, and the lines finally return to the power source point. To illustrate a more complex situation, taking the 10 kV power grid as an example, the more substations (including 110 kV and 35 kV substations) are distributed within a unit area, the shorter the line length required to build a 10 kV ring network connection in theory. The following relationship is used to evaluate the outgoing line length L ρ10 :

[0068]

[0069] S is the total area of ​​the power supply area; n s_110 ,n s_35 is the number of 110 kV and 35 kV power facilities in the power supply area; ρ is the average load density; k3 is the networking coefficient, and the calculation method is the same as the chain connection length coefficient.

[0070] Construct the objective function in the power grid construction plan determination model. The objective function takes economic efficiency as the optimization goal, that is, the sum of the equivalent cost of substation and line construction, operation cost and social resource occupation in the power supply plan is optimal.

[0071] The construction cost includes two parts: substation and line.

[0072] Investment in the construction of the power substation part of the power grid project f1:

[0073]

[0074] Investment in construction of power grid line part f2:

[0075]

[0076] in:

[0077] n s_220 ,n s_110 ,n s_35 ,n s_10 is the number of 220 / 110 / 35 kV substations and 10 kV grid switch stations to be newly built, i is the facility number;

[0078] C s220 ,C s110 ,C s35 ,C s10The proposed new single 220 / 110 / 35 kV substation and 10 kV switch station investment, i is the facility number; C l220 ,C l110 ,C l35 ,C l10 The cost per kilometer of the proposed new 220 / 110 / 35 / 10 kV line; L ρ110 ,L ρ35 ,L ρ10 The average length of the 110 / 35 / 10 kV power line is used to build a single 110 / 35 / 10 power facility. The total cost over the entire life cycle is calculated based on the operating cost. The annual operating cost is estimated by averaging a certain proportion of the construction cost incurred in each year of the life cycle, as shown in the following formula:

[0079]

[0080]

[0081] In the formula: t1, t2 are the annual operating cost ratios of substation equipment and line equipment respectively; i% ​​is the discount rate; N is the operating life of the equipment. The social resource equivalent cost further considers the social resource occupation attribute correction item, as shown in the following formula:

[0082]

[0083]

[0084] Among them: k1 is the cost item of land resources occupied by the introduced site, k2 and k3 are the cost items of channel resources occupied by the introduced lines. At the site level, the power supply capacity of a single 110 kV substation is stronger than that of a 35 kV substation, so the site resource demand is small; but the channel resource demand occupied by the corresponding 110 kV line is higher than that of the 35 kV line. Therefore, different comparison results may be obtained under different parameter combinations.

[0085] Exemplarily, the construction process of the power supply impact relationship in the power grid construction plan determination model is as follows: construct the power supply voltage level sequence to select the optimization model constraint conditions. Under the combined boundary of load density, load structure, and power supply mode within the power supply range of the blank area, in order to ensure the power supply requirements within the power supply area, the power balance and the number of facility power line loop constraints must be met.

[0086] Power balance constraints: Substations built in the power supply area must meet the power supply needs of loads at different levels:

[0087]

[0088]

[0089]

[0090]

[0091]

[0092] in:

[0093] S 220 ,S 110 ,S 35 It is the power supply capacity that a single 220 / 110 / 35 kV substation can meet under the N-1 mode, that is, the maximum allowable load rate of a single substation that can meet the N-1 verification, such as 50% for two main substations and 67% for three main substations;

[0094] S L∑ ,S L_10 ,S L_0.4 It is total load / 10 kV and below / 0.4 kV load demand;

[0095] The load demand at non-residential user j that intends to adopt 110 / 35 / 10 kV power supply; A collection of users who adopt the switch station power supply mode;

[0096] Provide economical power supply capacity for a single 110 / 35 / 10 kV switch station;

[0097] n s_220 ,n s_110 ,n s_35 The number of 220 / 110 / 35 kV substations to be newly built;

[0098] The number of power line loops of the facility is constrained. The maximum number of power lines that the proposed new substation in the area can provide should not be less than the total number of power lines required by users under the established power supply mode. The scale of the facility that can provide a certain voltage level interval outgoing line must match the number of required circuits for the interval of that voltage level.

[0099] The 110 kV interval meets the supply and demand constraints:

[0100]

[0101]

[0102] in:

[0103] The number of outgoing line circuits of 110 kV lines can be obtained for the construction of a single 220 kV substation;

[0104] The number of 110 kV line outgoing circuits available for the construction of a single 110 kV substation and a 110 kV switch station;

[0105] The number of 110 kV line incoming circuits required to supply power to the unit's 110 kV substation, 110 kV switch station and 110 kV users.

[0106] The 35 kV interval meets the supply and demand constraints:

[0107]

[0108]

[0109] in:

[0110] The number of outgoing line circuits of 35 kV lines can be obtained for the construction of a single 220 kV substation;

[0111] The number of outgoing line circuits of 110 kV lines can be obtained for the construction of a single 100 kV substation and a 110 kV switch station;

[0112] The number of 35 kV line incoming circuits required to supply power to the unit 35 kV substation, 35 kV switch station and 35 kV users.

[0113] The 10 kV interval meets the supply and demand constraints:

[0114]

[0115]

[0116] in:

[0117] The number of 10 kV line outgoing circuits can be obtained for the construction of a single 110 kV substation / 35 kV substation / 10 kV switch station (grid project investment);

[0118] The number of 10 kV line outgoing circuits can be obtained for the construction of a single 10 kV switch station (non-grid project investment);

[0119] The number of 10 kV line incoming circuits required for unit 10 kV switch stations (grid project investment), 10 kV switch stations (non-grid project investment) and 10 kV user power supply.

[0120] S130. Determine a power grid construction plan for the power grid to be constructed based on the construction demand information and the power grid construction plan determination model.

[0121] Optionally, the method of determining the grid construction plan of the grid to be constructed based on the construction demand information and the grid construction plan determination model may be: substituting the construction demand information into the grid construction plan determination model, and outputting the grid construction plan of the grid to be constructed.

[0122] Specifically, the construction demand information is input into the power supply impact relationship, and when the power supply impact relationship is established, the minimum value of the construction impact relationship is calculated.

[0123] On the basis of the above embodiments, it also includes: conducting sensitivity analysis on key parameters that have an important impact on the output conclusions, such as load density indicators, power supply modes, etc., to obtain recommended conclusions and development strategies for power supply voltage level sequence selection that are suitable for regions at different development stages.

[0124] The present invention discloses a method for determining a power grid construction plan, the method comprising: obtaining construction demand information of a substation to be constructed; obtaining a power grid construction plan determination model; the power grid construction plan determination model is constructed based on the attribute information of substations of various voltage levels; and determining the power grid construction plan of the power grid to be constructed based on the construction demand information and the power grid construction plan determination model. By using this method, a reasonable power supply voltage level sequence is formulated based on a scientific model, and the voltage level sequence is reasonably selected and simplified to configure, which can not only improve the overall power supply capacity of the urban power grid, and improve the adaptability of the power grid to loads of different natures and different reported capacities, but also reduce network losses, save limited space resources, and reduce power grid construction and operation costs.

[0125] Embodiment 2

[0126] Figure 6 The present invention also provides a schematic diagram of a structure of a device for determining a power grid construction plan. Figure 6 As shown, the device includes: a data acquisition module 210, a model acquisition module 220 and a solution output module 230.

[0127] The data acquisition module 210 is used to obtain the construction demand information of the substation to be constructed;

[0128] The model acquisition module 220 is used to acquire a model for determining a power grid construction plan; the model for determining a power grid construction plan is constructed based on the attribute information of substations of various voltage levels;

[0129] The plan output module 230 is used to determine the power grid construction plan of the power grid to be constructed based on the construction demand information and the power grid construction plan determination model.

[0130] The technical solution provided in the embodiment of the present disclosure utilizes this method to formulate a reasonable power supply voltage level sequence based on a scientific model. Reasonable selection and simplified configuration of the voltage level sequence can not only improve the overall power supply capacity of the urban power grid and improve the adaptability of the power grid to loads of different natures and different reported capacities, but also reduce network losses, save limited space resources, and reduce power grid construction and operation costs.

[0131] Furthermore, the model acquisition module 220 may be used to:

[0132] Determine the construction cost impact coefficient corresponding to the different attribute information of each voltage level substation;

[0133] The sum of the product of each of the attribute information of each of the voltage level substations and the corresponding construction cost impact coefficient is used as the construction impact relationship of the power grid construction plan determination model;

[0134] Extracting power supply capacity information included in the attribute information of each voltage level substation, and determining the power supply impact coefficient of each voltage level substation;

[0135] The product of the power supply capacity information of each voltage level substation and the power supply impact coefficient is determined, and the sum of each product is used as the power supply impact relationship of the power grid construction plan determination model.

[0136] Furthermore, the model acquisition module 220 may be used to:

[0137] The attribute information includes: station construction cost, line cost, line length, operation cost and social resource occupation cost.

[0138] Furthermore, the model acquisition module 220 may also be used to:

[0139] The power supply capacity information includes: power supply amount and number of line loops; the power supply impact coefficient includes: power supply demand impact coefficient and line loop impact coefficient.

[0140] Furthermore, the model acquisition module 220 may be used to:

[0141] The determining the product of the power supply capacity information of each voltage level substation and the power supply impact coefficient, and taking the sum of each product as the power supply impact relationship of the power grid construction plan determination model, includes:

[0142] Determine the product of the power supply of each voltage level substation and the power supply demand impact coefficient;

[0143] Determine the product of the number of line loops and the line loop influence coefficient of each voltage level substation;

[0144] The sum of the products is used as the power supply impact relationship of the power grid construction plan determination model.

[0145] Furthermore, the solution output module 230 may also be used to:

[0146] The construction demand information is substituted into the power grid construction plan determination model, and the power grid construction plan of the power grid to be constructed is output.

[0147] The above device can execute the methods provided by all the above embodiments of the present invention, and has the corresponding functional modules and beneficial effects of executing the above methods. For technical details not described in detail in this embodiment, please refer to the methods provided by all the above embodiments of the present invention.

[0148] Embodiment 3

[0149] Figure 7 The present invention is a block diagram of an electronic device 10 that can be used to implement an embodiment of the present invention. The electronic device is intended to represent various forms of digital computers, such as laptop computers, desktop computers, workstations, personal digital assistants, servers, blade servers, mainframe computers, and other suitable computers. The electronic device can also represent various forms of mobile devices, such as personal digital processing, cellular phones, smart phones, wearable devices (such as helmets, glasses, watches, etc.) and other similar computing devices. The components shown herein, their connections and relationships, and their functions are merely examples and are not intended to limit the implementation of the present invention described and / or required herein.

[0150] like Figure 7 The electronic device 10 includes at least one processor 11, and a memory connected to the at least one processor 11, such as a read-only memory (ROM) 12, a random access memory (RAM) 13, etc., wherein the memory stores a computer program that can be executed by at least one processor, and the processor 11 can perform various appropriate actions and processes according to the computer program stored in the read-only memory (ROM) 12 or the computer program loaded from the storage unit 18 to the random access memory (RAM) 13. In the RAM 13, various programs and data required for the operation of the electronic device 10 can also be stored. The processor 11, the ROM 12, and the RAM 13 are connected to each other through a bus 14. An input / output (I / O) interface 15 is also connected to the bus 14.

[0151] A number of components in the electronic device 10 are connected to the I / O interface 15, including: an input unit 16, such as a keyboard, a mouse, etc.; an output unit 17, such as various types of displays, speakers, etc.; a storage unit 18, such as a disk, an optical disk, etc.; and a communication unit 19, such as a network card, a modem, a wireless communication transceiver, etc. The communication unit 19 allows the electronic device 10 to exchange information / data with other devices through a computer network such as the Internet and / or various telecommunication networks.

[0152] The processor 11 may be a variety of general and / or special processing components with processing and computing capabilities. Some examples of the processor 11 include, but are not limited to, a central processing unit (CPU), a graphics processing unit (GPU), various special artificial intelligence (AI) computing chips, various processors running machine learning model algorithms, a digital signal processor (DSP), and any appropriate processor, controller, microcontroller, etc. The processor 11 executes the various methods and processes described above, such as a method for determining a power grid construction plan.

[0153] In some embodiments, the method for determining a power grid construction solution may be implemented as a computer program, which is tangibly contained in a computer-readable storage medium, such as a storage unit 18. In some embodiments, part or all of the computer program may be loaded and / or installed on the electronic device 10 via the ROM 12 and / or the communication unit 19. When the computer program is loaded into the RAM 13 and executed by the processor 11, one or more steps of the method for determining a power grid construction solution described above may be performed. Alternatively, in other embodiments, the processor 11 may be configured to execute the method for determining a power grid construction solution in any other appropriate manner (e.g., by means of firmware).

[0154] Various implementations of the systems and techniques described above herein can be implemented in digital electronic circuit systems, integrated circuit systems, field programmable gate arrays (FPGAs), application specific integrated circuits (ASICs), application specific standard products (ASSPs), systems on chips (SOCs), load programmable logic devices (CPLDs), computer hardware, firmware, software, and / or combinations thereof. These various implementations can include: being implemented in one or more computer programs that can be executed and / or interpreted on a programmable system including at least one programmable processor, which can be a special purpose or general purpose programmable processor that can receive data and instructions from a storage system, at least one input device, and at least one output device, and transmit data and instructions to the storage system, the at least one input device, and the at least one output device.

[0155] Computer programs for implementing the methods of the present invention may be written in any combination of one or more programming languages. These computer programs may be provided to a processor of a general-purpose computer, a special-purpose computer, or other programmable data processing device, so that when the computer program is executed by the processor, the functions / operations specified in the flow chart and / or block diagram are implemented. The computer program may be executed entirely on the machine, partially on the machine, partially on the machine and partially on a remote machine as a stand-alone software package, or entirely on a remote machine or server.

[0156] In the context of the present invention, a computer-readable storage medium may be a tangible medium that may contain or store a computer program for use by or in combination with an instruction execution system, device or equipment. A computer-readable storage medium may include, but is not limited to, electronic, magnetic, optical, electromagnetic, infrared, or semiconductor systems, devices or equipment, or any suitable combination of the foregoing. Alternatively, a computer-readable storage medium may be a machine-readable signal medium. A more specific example of a machine-readable storage medium may include an electrical connection based on one or more lines, a portable computer disk, a hard disk, a random access memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), an optical fiber, a portable compact disk read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination of the foregoing.

[0157] To provide interaction with a user, the systems and techniques described herein may be implemented on an electronic device having: a display device (e.g., a CRT (cathode ray tube) or LCD (liquid crystal display) monitor) for displaying information to the user; and a keyboard and a pointing device (e.g., a mouse or trackball) through which the user can provide input to the electronic device. Other types of devices may also be used to provide interaction with the user; for example, the feedback provided to the user may be any form of sensory feedback (e.g., visual feedback, auditory feedback, or tactile feedback); and input from the user may be received in any form (including acoustic input, voice input, or tactile input).

[0158] The systems and techniques described herein may be implemented in a computing system that includes backend components (e.g., as a data server), or a computing system that includes middleware components (e.g., an application server), or a computing system that includes frontend components (e.g., a user computer with a graphical user interface or a web browser through which a user can interact with implementations of the systems and techniques described herein), or a computing system that includes any combination of such backend components, middleware components, or frontend components. The components of the system may be interconnected by any form or medium of digital data communication (e.g., a communication network). Examples of communication networks include: a local area network (LAN), a wide area network (WAN), a blockchain network, and the Internet.

[0159] A computing system may include a client and a server. The client and the server are generally remote from each other and usually interact through a communication network. The client and server relationship is generated by computer programs running on the corresponding computers and having a client-server relationship with each other. The server may be a cloud server, also known as a cloud computing server or cloud host, which is a host product in the cloud computing service system to solve the defects of difficult management and weak business scalability in traditional physical hosts and VPS services.

[0160] It should be understood that the various forms of processes shown above can be used to reorder, add or delete steps. For example, the steps described in the present invention can be executed in parallel, sequentially or in different orders, as long as the desired results of the technical solution of the present invention can be achieved, and this document does not limit this.

[0161] The above specific implementations do not constitute a limitation on the protection scope of the present invention. It should be understood by those skilled in the art that various modifications, combinations, sub-combinations and substitutions can be made according to design requirements and other factors. Any modification, equivalent substitution and improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims

1. A method for determining a power grid construction plan, characterized in that: include: Obtain construction demand information of the substation to be constructed; Obtain the model for determining the power grid construction plan; The grid construction plan determination model is constructed based on the attribute information of substations of various voltage levels; A power grid construction plan for the power grid to be constructed is determined based on the construction demand information and the power grid construction plan determination model.

2. The method according to claim 1, characterized in that: The construction process of the power grid construction plan determination model includes: Determine the construction cost impact coefficient corresponding to the different attribute information of each voltage level substation; The sum of the product of each of the attribute information of each of the voltage level substations and the corresponding construction cost impact coefficient is used as the construction impact relationship of the power grid construction plan determination model; Extracting power supply capacity information included in the attribute information of each voltage level substation, and determining the power supply impact coefficient of each voltage level substation; The product of the power supply capacity information of each voltage level substation and the power supply impact coefficient is determined, and the sum of each product is used as the power supply impact relationship of the power grid construction plan determination model.

3. The method according to claim 2, characterized in that: The attribute information includes: station construction cost, line cost, line length, operation cost and social resource occupation cost.

4. The method according to claim 2, characterized in that: The power supply capacity information includes: power supply amount and number of line loops; the power supply impact coefficient includes: power supply demand impact coefficient and line loop impact coefficient.

5. The method according to claim 4, characterized in that The determining the product of the power supply capacity information of each voltage level substation and the power supply impact coefficient, and taking the sum of each product as the power supply impact relationship of the power grid construction plan determination model, includes: Determine the product of the power supply of each voltage level substation and the power supply demand impact coefficient; Determine the product of the number of line loops and the line loop influence coefficient of each voltage level substation; The sum of the products is used as the power supply impact relationship of the power grid construction plan determination model.

6. The method according to claim 1, characterized in that The determining of the power grid construction plan of the power grid to be constructed based on the construction demand information and the power grid construction plan determination model includes: The construction demand information is substituted into the power grid construction plan determination model, and the power grid construction plan of the power grid to be constructed is output.

7. The method according to claim 1, characterized in that The construction demand information includes: load power supply demand information and substation line circuit number demand information.

8. A device for determining a power grid construction plan, characterized in that: include: A data acquisition module is used to obtain construction demand information of the substation to be constructed; A model acquisition module is used to acquire a model for determining a power grid construction plan; The grid construction plan determination model is constructed based on the attribute information of substations of various voltage levels; A plan output module is used to determine a power grid construction plan for the power grid to be constructed based on the construction demand information and the power grid construction plan determination model.

9. An electronic device, characterized in that: The electronic device comprises: at least one processor; and a memory communicatively connected to the at least one processor; wherein, The memory stores a computer program executable by the at least one processor, and the computer program is executed by the at least one processor so that the at least one processor can execute the method for determining a power grid construction plan according to any one of claims 1 to 7.

10. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores computer instructions, and the computer instructions are used to enable a processor to implement the method for determining a power grid construction plan according to any one of claims 1 to 7 when executed.