A Construction Drawing Detection Method, Device and Equipment Based on Design Reply Documents

By initially detecting and parsing the received design reply files, and using preset key tables for key matching and automatic comparison, the problem of mismatch between the design reply files and audit opinions is solved, the efficiency and accuracy of construction drawing review is improved, and the cost is reduced.

CN119182526BActive Publication Date: 2025-06-20WUHAN TIESIYUAN ENG CONSULTING CO LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202411341037.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-09-25
Publication Date
2025-06-20
Estimated Expiration
2044-09-25

AI Technical Summary

Technical Problem

During the construction process of a construction project, when there are many design reply documents, it is difficult to coordinate and dispatch all participating reviewers, resulting in mismatch of the design reply documents and the review opinions, which increases the cost of manpower, material resources and time.

Method used

By initially detecting and parsing the received design reply files, the design reply data that meets the requirements is extracted, and the key matching is used to use the preset key table to automatically compare and determine the modification content of the construction drawings, reducing human errors and improving the accuracy of the review.

Benefits of technology

It realizes automated detection and parsing of design reply files, quickly filters out data that meets the requirements, improves the efficiency and accuracy of construction drawing review, reduces the allocation and use efficiency of human resources, and reduces the cost of mismatch and redistribution.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119182526B_ABST
    Figure CN119182526B_ABST
Patent Text Reader

Abstract

The present application discloses a construction drawing detection method, device and equipment based on a design reply document. The method includes: performing an initial detection on the received design reply document, and parsing the design reply document that passes the detection to obtain design reply data that meets the requirements; matching the first key in the design reply data with a first preset key table, and recording the design reply data with successful matching; parsing the design reply data with successful matching to obtain a second key and design reply opinion data corresponding to the second key; matching the second key with a second preset key table, and comparing based on the matching result to determine the modification content of the construction drawing. By matching the design reply document twice, the present invention determines the review opinions corresponding to the design reply data in the design reply document, improves the allocation accuracy, and can quickly determine the modification content of the construction drawing by comparing the design reply document data with the review opinions.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This application relates to the technical field of data matching, and more specifically, to a construction drawing detection method, device, and equipment based on design reply documents. Background Art

[0002] During the construction process of a construction project, the review unit needs to review the construction drawings and send the review opinions of the construction drawings to the design unit, and the design unit provides a reply on the modification, improvement, and processing plan for the review opinions. Since there are often multiple review opinions for the construction drawings, multiple design reply documents will be obtained. Therefore, the review opinions and the corresponding design reply documents need to be accurately matched to understand whether the design reply documents have modified the construction drawings.

[0003] In the existing review process, generally, the production scheduling department uploads the design reply documents. After all the review personnel involved in the construction drawings receive the design reply confirmation tasks, the review personnel search for the corresponding review opinions and the corresponding design reply documents, and judge whether there are any modifications to the construction drawings in the design reply by means of manual comparison.

[0004] However, when there are many review personnel involved in the existing technology, there are also many corresponding design reply documents, which are difficult to overall schedule all the review personnel involved. And there are also many distribution tasks. The large distribution workload is likely to cause incorrect matching between the design reply documents and the review opinions, and re-distribution is required, resulting in high human, material, and time costs. Summary of the Invention

[0005] In view of at least one defect or improvement requirement of the existing technology, the present invention provides a construction drawing detection method, device, and equipment based on design reply documents, which are used to solve the problems in the existing technology that when there are many design reply documents, it is difficult to overall schedule all the review personnel involved, and the large distribution workload is likely to cause incorrect matching between the design reply documents and the review opinions, and it is impossible to determine in time whether the design reply documents have modified the construction drawings.

[0006] To achieve the above object, according to the first aspect of the present invention, a construction drawing detection method based on design reply documents is provided, including:

[0007] Perform an initial detection on the received design reply documents and parse the design reply documents that pass the detection to obtain design reply data that meets the requirements;

[0008] Match the first secret key in the design reply data with the first preset secret key table, and record the design reply data that matches successfully;

[0009] Parse the design reply data for successful matching to obtain the second key and the design reply opinion data corresponding to the second key;

[0010] Match the second key with the second preset key table, and determine the modification content of the construction drawing based on the matching result.

[0011] In a possible implementation, matching the first key in the design reply data with the first preset key table further includes:

[0012] If the first key does not match the first preset key table, it indicates that an error has occurred in the matching. Generate an error log report and feedback it;

[0013] Determine whether to generate an alarm notification based on the error log report and the preset alarm indicators.

[0014] In a possible implementation, determining whether to generate an error report based on the error type and error rate further includes:

[0015] Extract the error type and error rate of the mismatch between the first key and the first preset key table from the error log report;

[0016] When it is detected that the error type is the preset error type, generate and send an error type alarm notification;

[0017] When it is detected that the error rate reaches the preset error rate threshold, generate and send an error rate alarm notification.

[0018] In a possible implementation, matching the second key with the second preset key table and determining the modification content of the construction drawing based on the matching result further includes:

[0019] If the second key does not match the second preset key table, determine the construction drawing modification content according to the design reply opinion data;

[0020] If the second key matches the second preset key table, compare the design reply opinion data with the corresponding review opinion data to determine the construction drawing modification content.

[0021] In a possible implementation, if the second key matches the second preset key table, comparing the design reply opinion data with the corresponding review opinion data to determine the construction drawing modification content further includes:

[0022] If the comparison between the design reply opinion data and the corresponding review opinion data is consistent, there is no modification to the construction drawing;

[0023] If the comparison between the design reply opinion data and the corresponding review opinion data is inconsistent, extract the data content that is inconsistent between the design reply opinion data and the corresponding review opinion data;

[0024] Update the construction drawings with the data content where the design reply opinion data is inconsistent with the corresponding review opinion data.

[0025] In a possible implementation, if the second key does not match the second preset key table, determining the construction drawing modification content according to the design reply opinion data further includes:

[0026] Analyze the reason why the second key does not match the second preset key table to determine the unmatched reason;

[0027] Determine the construction drawing modification content based on the unmatched reason and the design reply opinion data.

[0028] In a possible implementation, initially detecting the received design reply file and parsing the detected design reply file to obtain design reply data that meets the requirements further includes:

[0029] Detect the storage capacity of the design reply file to obtain a design reply file that does not exceed the preset file capacity;

[0030] Parse the design reply file that does not exceed the preset file capacity to obtain design reply data of a preset type;

[0031] Perform a security check on the design reply data of the preset type to obtain design reply data that passes the security check.

[0032] According to the second aspect of the present invention, there is also provided a construction drawing detection device based on a design reply file, including:

[0033] An initial detection module configured to initially detect the received design reply file and parse the detected design reply file to obtain design reply data that meets the requirements;

[0034] A first matching module configured to match the first key in the design reply data with the first preset key table and record the design reply data with a successful match;

[0035] A data parsing module configured to parse the design reply data with a successful match to obtain a second key and the design reply opinion data corresponding to the second key;

[0036] A second matching module configured to match the second key with the second preset key table and determine the modification content of the construction drawing based on the matching result.

[0037] According to the third aspect of the present invention, there is also provided a construction drawing detection device based on a design reply document, which includes at least one processing unit and at least one storage unit. Among them, the storage unit stores a computer program, and when the computer program is executed by the processing unit, the processing unit is caused to execute the steps of any one of the above-mentioned construction drawing detection methods based on the design reply document.

[0038] According to the fourth aspect of the present invention, there is also provided a storage medium, which stores a computer program executable by an access authentication device. When the computer program runs on the access authentication device, the access authentication device is caused to execute the steps of any one of the above-mentioned construction drawing detection methods based on the design reply document.

[0039] Generally speaking, compared with the prior art by the above technical solutions conceived by the present invention, the following beneficial effects can be achieved:

[0040] A construction drawing detection method based on a design reply document provided by the present invention performs an initial detection on the received design reply document and parses the design reply document that passes the detection to obtain design reply data that meets the requirements. By automatically detecting and parsing the design reply document, data that meets the requirements can be quickly screened out, avoiding the cumbersome process of manual item-by-item verification, thereby significantly improving the efficiency and speed of construction drawing review. The first key in the design reply data is matched with the first preset key table, and the design reply data with successful matching is recorded. The design reply data with successful matching is parsed to obtain a second key and design reply opinion data corresponding to the second key. The second key is matched with the second preset key table, and the modification content of the construction drawing is determined based on the matching result. Through the preset key table and automatic comparison, errors caused by human factors can be reduced, and the accuracy and reliability of the review can be improved. Through the standardized key matching and data processing process, it helps different teams to better understand and execute design opinions, promotes communication and cooperation between different departments, and the automatic detection can quickly identify the design reply content that needs to be focused on, optimizing the allocation and utilization efficiency of human resources. BRIEF DESCRIPTION OF THE DRAWINGS

[0041] In order to more clearly illustrate the technical solutions in the embodiments of the present application, the accompanying drawings required for use in the embodiments will be briefly introduced below. Obviously, the accompanying drawings in the following description are only some embodiments of the present application. For those of ordinary skill in the art, without creative efforts, other drawings can be obtained based on these drawings.

[0042] Figure 1 It is a schematic flowchart of an embodiment of a construction drawing detection method based on a design reply document provided by the present invention;

[0043] Figure 2 A flowchart showing an embodiment of determining whether to generate an error report provided by the present invention;

[0044] Figure 3 A flowchart showing an embodiment of determining the revised content of the construction drawing by data comparison provided by the present invention;

[0045] Figure 4 Provided by the present invention Figure 1 A flowchart showing an embodiment of step S101 in

[0046] Figure 5 A schematic structural diagram of an embodiment of a construction drawing detection device based on a design reply document provided by the present invention;

[0047] Figure 6 A schematic structural diagram of a construction drawing detection device based on a design reply document provided by an embodiment of the present invention. Detailed implementation manners

[0048] In order to make the objectives, technical solutions and advantages of the present invention clearer, the present invention will be further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention. In addition, the technical features involved in the various embodiments of the present invention described below can be combined with each other as long as they do not conflict with each other.

[0049] The terms "first", "second", "third", etc. in the specification and claims of this application and the above-mentioned drawings are used to distinguish different objects, rather than to describe a specific order. In addition, the terms "include" and "have" and any variations thereof are intended to cover non-exclusive inclusion. For example, a process, method, system, product or device that includes a series of steps or units is not limited to the listed steps or units, but may optionally further include steps or units not listed, or may optionally further include other steps or units inherent to these processes, methods, products or devices.

[0050] The present invention provides a construction drawing detection method, device and equipment based on a design reply document, which will be described separately below.

[0051] Please refer to Figure 1 , Figure 1 A flowchart showing an embodiment of a construction drawing detection method based on a design reply document provided by the present invention. In a specific embodiment of the present invention, a construction drawing detection method based on a design reply document is disclosed, including:

[0052] S101. Conduct an initial inspection on the received design reply file, and parse the design reply file that passes the inspection to obtain design reply data meeting the requirements;

[0053] S102. Match the first key in the design reply data with the first preset key table, and record the design reply data with successful matching;

[0054] S103. Parse the design reply data with successful matching to obtain the second key and the design reply opinion data corresponding to the second key;

[0055] S104. Match the second key with the second preset key table, and determine the modification content of the construction drawing based on the matching result.

[0056] In the above embodiment, first, receive the design reply files submitted by the design team or relevant parties. Subsequently, conduct an initial inspection on these files to ensure the integrity, format correctness of the files, and whether they contain necessary metadata. Through preliminary screening, exclude those files that do not meet the basic requirements, such as files with format errors, damages, or missing key information. For the design reply files that pass the initial inspection, further in-depth parsing is carried out. The parsing process aims to extract design reply data that meets specific requirements from the files. These data may include detailed descriptions of design changes, drawing numbers involved, specific positions or areas of modification, etc. Through parsing, this information can be organized into a structured data format to facilitate subsequent processing.

[0057] In the parsed design reply data, identify the first key. The first key usually represents key information such as different design change types, priorities, or project phases to which it belongs. The first key can determine the construction drawing corresponding to the current design reply file. For a construction drawing, generally, there will be multiple review opinions, and the design reply file generally contains the specific replies to these review opinions. Match the first key with the pre-established first preset key table. The first preset key table is a database or lookup table containing all valid keys and their corresponding meanings. Through the matching process, the design reply data that matches the keys in the preset key table can be screened out. These data with successful matching are considered valid and design change requests that need further processing. Record these data with successful matching for further analysis and processing in subsequent steps.

[0058] For the successfully matched design response data, perform a more in-depth analysis. This step is to extract more detailed information from these data, especially the second key and its corresponding design response opinion data. The second key may represent specific modification instructions, marked positions on the drawings, or information about components to be replaced, etc. Through analysis, these second keys and their corresponding design response opinion data can be organized into a form that is easy to understand and operate, and these data provide clear guidance for subsequent construction drawing modifications.

[0059] After obtaining the second key and its corresponding design response opinion data, match these second keys with the second preset key table. The second preset key table is a database or lookup table containing information such as construction drawing modification instructions, drawing annotation specifications, or component replacement standards. Through the matching process, the construction drawing modification content corresponding to each second key can be determined. These modification contents may include specific modification positions on the drawings, modification methods, required materials, or specifications of replaced components, etc. Based on the matching results, conduct comparison and analysis to finally determine the complete construction drawing modification plan. The purpose of the entire detection method is to quickly and accurately identify and process the construction drawing modification requests in the design response documents through an automated and standardized process, which can not only improve the efficiency and quality of construction drawing review, but also reduce human errors and communication costs, providing strong support for the smooth progress of the project.

[0060] Compared with the prior art, a construction drawing detection method based on design response documents provided in this embodiment performs an initial detection on the received design response documents and parses the design response documents that pass the detection to obtain design response data that meets the requirements. By automatically detecting and parsing the design response documents, it can quickly screen out the data that meets the requirements, avoiding the cumbersome process of manual item-by-item checking, thus significantly improving the efficiency and speed of construction drawing review. Match the first key in the design response data with the first preset key table, record the successfully matched design response data, parse the successfully matched design response data to obtain the second key and the design response opinion data corresponding to the second key, match the second key with the second preset key table, and determine the modification content of the construction drawing based on the matching results. Through the preset key table and automatic comparison, it can reduce errors caused by human factors and improve the accuracy and reliability of the review. Through the standardized key matching and data processing process, it helps different teams better understand and execute design opinions, promoting communication and cooperation between different departments. The automated detection can quickly identify the design response content that needs to be focused on, optimizing the allocation and utilization efficiency of human resources.

[0061] In some embodiments of the present invention, matching the first key in the design response data with the first preset key table further includes:

[0062] If the first key does not match the first preset key table, it indicates that a matching error has occurred. An error log report is generated and feedback is provided.

[0063] Based on the error log report and preset alarm metrics, determine whether to generate an alarm notification.

[0064] In the above embodiment, when it is found that the first key in the design reply data does not match any key in the first preset key table, it is immediately identified as a matching error. Subsequently, a detailed error log report is automatically generated, which should include the value of the unmatched first key, the timestamp of the attempted match, basic information of the source design reply file (such as file name, submitter, submission time, etc.), and other possible relevant context information. The purpose of the error log report is to record and analyze the specific situation of the matching failure, providing a basis for subsequent problem-solving and process improvement.

[0065] After generating the error log report, a feedback mechanism should be initiated to promptly notify the relevant users or teams of the error situation. This can be achieved through email, messages, workflow notifications, or other preset communication channels. The feedback content should concisely explain the reason for the matching failure and attach a link or summary of the error log report so that users can quickly understand the problem and take corresponding measures.

[0066] To further improve the system's response speed and problem-solving ability, a series of alarm metrics should be preset. These metrics can be set based on certain characteristics of the error log report (such as error type, occurrence frequency, impact scope, etc.). For example, if a large number of matching errors of the same type occur within a certain period, or the key matching of a critical design reply file fails, it may trigger an alarm.

[0067] Based on the content of the error log report and the preset alarm metrics, automatically make a judgment. If the alarm condition is met, an alarm notification is immediately generated. The alarm notification should contain sufficient information so that the recipient can quickly understand the severity and urgency of the problem and make a corresponding response. The generation method of the alarm notification can also be flexibly selected according to the actual situation, such as quickly notifying relevant personnel through text messages, phone calls, instant messaging tools, etc.

[0068] Please refer to Figure 2 , Figure 2 FIG.

[0069] S201. Extract the error type and error rate of the mismatch between the first key and the first preset key table from the error log report.

[0070] S202. When the detected error type is a preset error type, generate and send an error type alarm notification.

[0071] S203. When the detected error rate reaches the preset error rate threshold, generate and send an error rate alarm notification.

[0072] In the above embodiment, first traverse the error log report and analyze each record. In particular, attention needs to be paid to those entries related to the mismatch between the first key and the first preset key table. From these entries, extract the specific error types, such as "unknown key error", "key format error", or "insufficient key permissions", etc. At the same time, the occurrence frequency of each error type, that is, the error rate, is also calculated, which is usually obtained by dividing the number of errors of a specific type by the total number of errors.

[0073] After extracting the error type and error rate, these information are compared with the preset list of error types. If it is detected that a certain error type matches a certain type in the preset list, it indicates that this error type requires special attention. At this time, according to the preset rules and templates, a detailed error type alarm notification will be generated. This notification will clearly point out the type of error, the occurrence time, the possible impact range, and the recommended solution. Subsequently, the alarm notification will be sent to the relevant users or teams through the preset communication channels (such as email, instant messaging tools, text messages, etc.) so that they can understand and respond to the problem in a timely manner.

[0074] In addition to paying attention to the error type, it is also necessary to monitor the change of the error rate. Compare the calculated error rate of each error type with the preset error rate threshold. If the error rate of a certain error type exceeds the set threshold, it indicates that this error type occurs frequently in the current stage and may have a greater impact on the normal operation. At this time, similarly, according to the preset rules and templates, an error rate alarm notification will be generated. This notification will emphasize the abnormal situation of the error rate, the possible cause analysis, and the recommended countermeasures. Subsequently, the alarm notification will also be sent to the relevant users or teams through the same communication channels so that they can take prompt actions to reduce the error rate and restore the stable operation.

[0075] It can be understood that the preset error type and the preset error rate threshold can be specifically set according to the actual situation, and the present invention does not make further limitations on this.

[0076] In some embodiments of the present invention, matching the second key with the second preset key table and determining the modification content of the construction drawing based on the matching result further includes:

[0077] If the second key does not match the second preset key table, determine the construction drawing modification content according to the design reply opinion data;

[0078] If the second key matches the second preset key table, compare the design reply opinion data with the corresponding review opinion data to determine the construction drawing modification content.

[0079] In the above embodiment, if the second key does not match a certain key in the second preset key table, it means that the design unit has added or deleted review opinions, resulting in no corresponding review opinion for the design reply opinion data. Therefore, it is necessary to determine the specific content for modifying the construction drawing according to the design reply opinion data.

[0080] If the second key successfully matches a certain key in the second preset key table, this indicates that there is a corresponding relationship between the review opinion of the construction drawing and the design reply opinion data, that is, the review opinion has been replied to. However, in order to ensure the accuracy and integrity of the final construction drawing modification, it is still necessary to further compare the design reply opinion data with the corresponding review opinion data. The design reply opinion data provides the designer's direct feedback on the construction drawing, while the review opinion data represents the evaluation of the construction drawing's compliance, safety, etc. by professional reviewers. By comparing and analyzing the two, the system can more comprehensively identify potential problems in the construction drawing and determine more accurate and comprehensive modification content accordingly.

[0081] Please refer to Figure 3 , Figure 3 which is a schematic flowchart of an embodiment for determining the construction drawing modification content by data comparison provided by the present invention. In some embodiments of the present invention, if the second key matches the second preset key table, compare the design reply opinion data with the corresponding review opinion data to determine the construction drawing modification content, and further include:

[0082] S301. If the design reply opinion data is consistent with the corresponding review opinion data after comparison, there is no modification to the construction drawing;

[0083] S302. If the design reply opinion data is inconsistent with the corresponding review opinion data after comparison, extract the data content where the design reply opinion data is inconsistent with the corresponding review opinion data;

[0084] S303. Update the construction drawing with the data content where the design reply opinion data is inconsistent with the corresponding review opinion data.

[0085] In the above embodiments, the comparison between the design response data and the corresponding review opinion data includes, but is not limited to, the adjustment of the design scheme, the change of technical parameters, the change of material selection, etc. If the design response data and the corresponding review opinion data are consistent at all key points, it indicates that the design party has fully replied according to the review opinion, and no additional modification requirements are proposed or key contents in the review opinion are omitted. If the comparison results are consistent, it is recorded that the construction drawing does not need further modification, and a corresponding report or notice may be generated to inform the relevant personnel that the review process has been completed and the construction drawing remains unchanged.

[0086] If any inconsistencies are found during the comparison between the design response data and the corresponding review opinion data, these inconsistent data contents should be immediately marked. The inconsistencies may manifest as the design party not fully adopting the review opinion, having a deviation in understanding the review opinion, or proposing a design scheme contrary to the review opinion, etc. It is necessary to record these inconsistent data contents in detail, including the clauses involved, specific difference points, etc., for subsequent analysis and processing.

[0087] Based on the identified inconsistent data contents, guide or automatically execute the modification work of the construction drawing, which includes, but is not limited to, adjusting the design scheme, modifying technical parameters, replacing material selection, etc. During the modification process, it should be ensured that all modifications comply with relevant laws, regulations, technical standards, and design requirements. At the same time, key information such as the time, content, and executor of each modification should be recorded for subsequent traceability and auditing. After the modification is completed, the modified construction drawing should be re-reviewed and verified to ensure that all modifications have been correctly implemented and no new errors or inconsistencies are introduced.

[0088] In some embodiments of the present invention, if the second key does not match the second preset key table, determining the construction drawing modification content according to the design response data further includes:

[0089] Analyze the reason for the mismatch between the second key and the second preset key table to determine the reason for the non-matching;

[0090] Determine the construction drawing modification content based on the reason for the non-matching and the design response data.

[0091] In the above embodiments, the analysis of the reason for the mismatch between the second key and the second preset key table may include confirming whether the second key is complete and error-free, without being damaged due to transmission errors, format problems, or human negligence; checking the usage history of the second key to confirm whether the key was correctly matched in previous uses, or whether it has been discarded and replaced with a new key; confirming whether there are any review opinions added, deleted, or modified in the second preset key table, resulting in the original key no longer matching the current review opinions; analyzing the design response opinion data to check whether it contains responses to the addition, deletion, or modification of review opinions, which may indicate that the design party has referred to the updated review opinion set when preparing the response; checking the logs and error reports to see if there are any specific error messages or abnormal records regarding the key matching failure, which may help locate the root cause of the problem.

[0092] If the reason for the non-matching is that the review opinions have changed (such as added, deleted, or modified), then determine the modification content of the construction drawings based on the latest information in the design response opinion data, which may involve adjusting the design scheme, updating technical parameters, or changing the material selection, etc.; if the design response opinion data contains self-modification suggestions for parts not covered by the review opinions, and these modifications are reasonable and in line with the specifications, then these modifications should also be included in the modification content of the construction drawings; when the reason for the non-matching or the specific meaning of the design response opinion data is uncertain, the communication process with the reviewers and the design party can be triggered automatically or manually to obtain more information and clarify doubts, which helps to ensure that the modification content of the construction drawings is accurate; based on the above analysis and confirmation results, detailed construction drawing modification instructions or reports should be generated, and these instructions should clearly indicate the specific content, location, modified effect, and possible impacts of the modifications, etc., so that the construction team can execute accurately; after the modification of the construction drawings is completed, the implementation of the modification should be tracked, and necessary verification and review work should be carried out to ensure that the modification content has been correctly implemented and meets the relevant standards and requirements. At the same time, the key information and results of the entire processing process should also be recorded for subsequent traceability and auditing.

[0093] Please refer to Figure 4 , Figure 4 provided by the present invention Figure 1 is a schematic flowchart of an embodiment of step S101 in the present invention. In some embodiments of the present invention, the initial detection of the received design response file and the parsing of the design response file that passes the detection to obtain the design response data that meets the requirements further include:

[0094] S401. Detect the storage capacity of the design response file to obtain a design response file that does not exceed the preset file capacity;

[0095] S402. Parse the design reply file that does not exceed the preset file capacity to obtain design reply data of a preset type;

[0096] S403. Perform a security check on the design reply data of the preset type to obtain design reply data that passes the security check.

[0097] In the above embodiment, first, according to requirements or industry specifications, set a reasonable upper limit for the preset file capacity. This upper limit is designed to prevent overly large files from causing a decline in processing efficiency or excessive resource consumption. When the design reply file is received, immediately detect its storage capacity (i.e., file size). This step is usually completed by reading the size information in the file attributes. Compare the detected file size with the preset file capacity. If the file size does not exceed the preset value, it is considered that the file meets the requirements in terms of storage capacity and can continue with subsequent processing; otherwise, record the error information, reject processing the file, and send a notification to relevant personnel to remind them that the file is too large.

[0098] After confirming that the file storage capacity is compliant, prepare the necessary environment and tools for file parsing. This may include setting up the correct parser, loading the necessary libraries or modules, etc. Before parsing, verify whether the type of the design reply file meets the preset requirements (such as PDF, Word, XML, etc.). This step helps to ensure the effectiveness of subsequent parsing operations and avoid parsing incompatible file types. Use appropriate parsing methods or tools to parse the file to extract the design reply data. The specific implementation of this step will depend on the type and content structure of the file. Convert the parsed data into a preset type that can be recognized and processed (such as structured data, object model, etc.). This step helps to ensure data consistency and the convenience of subsequent processing.

[0099] According to security requirements and industry specifications, set a series of security check standards. These standards may include detecting malicious code, the risk of sensitive information leakage, data integrity and consistency verification, etc. Perform a security check on the design reply data that has been parsed and converted into a preset type. This step may involve using professional security check tools or libraries to scan for potential security threats in the data. Evaluate the security of the design reply data based on the output results of the security check. If all data items pass the security check, the data is considered to be qualified for the security check; otherwise, record the specific security issues and take corresponding handling measures (such as deleting the data, notifying relevant personnel, etc.). Record the problems found and the handling measures taken during the security check for subsequent tracking and auditing. At the same time, send a notification to relevant personnel to inform them of the security check results and suggestions for subsequent operations.

[0100] To better implement the construction drawing detection method based on the design reply document in the embodiments of the present invention, on the basis of the construction drawing detection method based on the design reply document, correspondingly, please refer to Figure 5 , Figure 5 FIG. Figure 5 is a schematic structural diagram of an embodiment of a construction drawing detection device based on a design reply document provided by the present invention. An embodiment of the present invention provides a construction drawing detection device 500 based on a design reply document, including:

[0101] An initial detection module 510, which is configured to perform an initial detection on the received design reply document and parse the design reply document that passes the detection to obtain design reply data that meets the requirements;

[0102] A first matching module 520, which is configured to match the first key in the design reply data with a first preset key table and record the design reply data that matches successfully;

[0103] A data parsing module 530, which is configured to parse the design reply data that matches successfully to obtain a second key and design reply opinion data corresponding to the second key;

[0104] A second matching module 540, which is configured to match the second key with a second preset key table and determine the modification content of the construction drawing based on the matching result.

[0105] It should be noted here that: The device 500 provided in the above embodiment can implement the technical solutions described in the above method embodiments. The specific implementation principles of the above modules or units can be referred to the corresponding content in the above method embodiments, and will not be elaborated here.

[0106] Please refer to Figure 6 , Figure 6 FIG. Figure 6 is a schematic structural diagram of a construction drawing detection device based on a design reply document provided by an embodiment of the present invention. Based on the above construction drawing detection method based on a design reply document, the present invention also correspondingly provides a construction drawing detection device based on a design reply document. The construction drawing detection device based on a design reply document can be a computing device such as a mobile terminal, a desktop computer, a notebook, a palm computer, and a server. The construction drawing detection device 600 based on a design reply document includes a processor 610, a memory 620, and a display 630. Figure 6 Only some components of the synchronous tracking flight welding device for real-time measurement of battery height are shown, but it should be understood that it is not required to implement all the shown components, and more or fewer components can be alternatively implemented.

[0107] The memory 620 can be the internal storage unit of the construction drawing inspection device 600 based on the design response file in some embodiments, such as the hard disk or memory of the construction drawing inspection device 600 based on the design response file. The memory 620 can also be an external storage device of the construction drawing inspection device 600 based on the design response file in some other embodiments, such as the plug-in hard disk, Smart Media Card (SMC), Secure Digital (SD) card, Flash Card, etc. equipped on the construction drawing inspection device 600 based on the design response file. Further, the memory 620 can also include both the internal storage unit and the external storage device of the construction drawing inspection device 600 based on the design response file. The memory 620 is used to store the application software and various types of data installed on the construction drawing inspection device 600 based on the design response file, such as the program code installed on the construction drawing inspection device 600 based on the design response file. The memory 620 can also be used to temporarily store the data that has been output or will be output. In one embodiment, a construction drawing inspection program 640 based on the design response file is stored on the memory 620, and the construction drawing inspection program 640 based on the design response file can be executed by the processor 610, so as to implement the construction drawing inspection method based on the design response file in various embodiments of the present application.

[0108] The processor 610 can be a Central Processing Unit (CPU), a microprocessor or other data processing chips in some embodiments, and is used to run the program code stored in the memory 620 or process data, such as executing the construction drawing inspection method based on the design response file, etc.

[0109] The display 630 can be an LED display, a liquid crystal display, a touch liquid crystal display, and an OLED (Organic Light-Emitting Diode) toucher, etc. in some embodiments. The display 630 is used to display the information on the construction drawing inspection device 600 based on the design response file and to display the visual user interface. The components 610 - 630 of the construction drawing inspection device 600 based on the design response file communicate with each other through the system bus.

[0110] In one embodiment, when the processor 610 executes the construction drawing inspection program 640 in the memory 620, the steps in the above construction drawing inspection method based on the design response file are implemented.

[0111] This embodiment also provides a computer-readable storage medium, on which a construction drawing inspection program based on the design response file is stored. When the construction drawing inspection program based on the design response file is executed by the processor, the following steps are implemented:

[0112] Perform an initial inspection on the received design reply file and parse the design reply file that passes the inspection to obtain design reply data that meets the requirements;

[0113] Match the first key in the design reply data with the first preset key table and record the design reply data with successful matches;

[0114] Parse the design reply data with successful matches to obtain a second key and design reply opinion data corresponding to the second key;

[0115] Match the second key with the second preset key table and determine the modification content of the construction drawing based on the matching result.

[0116] In summary, a method for inspecting construction drawings based on a design reply file provided in this embodiment performs an initial inspection on the received design reply file and parses the design reply file that passes the inspection to obtain design reply data that meets the requirements. By automatically detecting and parsing the design reply file, data that meets the requirements can be quickly screened out, avoiding the cumbersome process of manual item-by-item checking, thereby significantly improving the efficiency and speed of construction drawing review. Match the first key in the design reply data with the first preset key table, record the design reply data with successful matches, parse the design reply data with successful matches to obtain a second key and design reply opinion data corresponding to the second key, match the second key with the second preset key table, and determine the modification content of the construction drawing based on the matching result. Through the preset key table and automatic comparison, errors caused by human factors can be reduced, and the accuracy and reliability of the review can be improved. Through the standardized key matching and data processing process, it helps different teams to better understand and execute design opinions, promotes communication and cooperation between different departments, and the automatic detection can quickly identify the design reply content that needs to be focused on, optimizing the allocation and utilization efficiency of human resources.

[0117] This application also provides a computer-readable storage medium, on which a computer program is stored, and when the program is executed by a processor, the steps of the above method are implemented. Among them, the computer-readable storage medium may include, but is not limited to, any type of disk, including floppy disks, optical disks, DVDs, CD-ROMs, microdrives, and magneto-optical disks, ROMs, RAMs, EPROMs, EEPROMs, DRAMs, VRAMs, flash memory devices, magnetic cards or optical cards, nanosystems (including molecular memory ICs), or any type of medium or device suitable for storing instructions and / or data.

[0118] It should be noted that, for the foregoing method embodiments, for the sake of simple description, they are all expressed as a series of action combinations. However, those skilled in the art should know that this application is not limited by the described action sequence, because according to this application, certain steps can be performed in other sequences or simultaneously. Secondly, those skilled in the art should also know that the embodiments described in the specification are all preferred embodiments, and the actions and modules involved are not necessarily essential to this application.

[0119] In the above embodiments, the descriptions of the respective embodiments have their own emphases. For the parts not detailed in a certain embodiment, reference can be made to the relevant descriptions of other embodiments.

[0120] In the several embodiments provided by this application, it should be understood that the disclosed device can be implemented in other ways. For example, the device embodiments described above are only illustrative. For example, the division of the units is only a logical function division. In actual implementation, there can be other division methods. For example, multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the displayed or discussed couplings or direct couplings or communication connections to each other can be through some service interfaces. The indirect couplings or communication connections of the devices or units can be in electrical or other forms.

[0121] The units described as separate components may or may not be physically separated, and the components displayed as units may or may not be physical units, that is, they can be located in one place, or distributed to multiple network units. Some or all of the units can be selected according to actual needs to achieve the purpose of the solution of this embodiment.

[0122] In addition, in each embodiment of this application, the functional units can be integrated in a processing unit, or each unit can exist physically alone, or two or more units can be integrated in one unit. The above integrated units can be implemented in the form of hardware or in the form of software functional units.

[0123] When the integrated unit is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a computer-readable memory. Based on this understanding, the technical solution of this application, in essence, or the part that contributes to the prior art, or all or part of this technical solution, can be embodied in the form of a software product. This computer software product is stored in a memory and includes several instructions for causing a computer device (which can be a personal computer, a server, or a network device, etc.) to execute all or part of the steps of the methods described in various embodiments of this application. The aforementioned memory includes various media that can store program codes, such as USB flash drives, read-only memories (ROM), random access memories (RAM), mobile hard disks, magnetic disks, or optical discs.

[0124] Those of ordinary skill in the art can understand that all or part of the steps in the various methods of the above embodiments can be completed by instructing relevant hardware through a program. This program can be stored in a computer-readable memory, and the memory can include: flash drives, read-only memories (ROM), random access memories (RAM), magnetic disks, or optical discs, etc.

[0125] The above are only exemplary embodiments of the present disclosure, and the scope of the present disclosure cannot be limited thereby. That is, any equivalent changes and modifications made in accordance with the teachings of the present disclosure still fall within the scope covered by the present disclosure. Those skilled in the art will easily think of other implementation manners of the present disclosure after considering the specification and practicing the present disclosure here. This application aims to cover any variations, uses, or adaptive changes of the present disclosure. These variations, uses, or adaptive changes follow the general principles of the present disclosure and include common general knowledge or conventional technical means in the technical field not recorded in the present disclosure. The specification and embodiments are only regarded as exemplary, and the scope and spirit of the present disclosure are defined by the claims.

[0126] The technical features of the above embodiments can be combined arbitrarily. For the sake of brevity of description, not all possible combinations of the technical features in the above embodiments are described. However, as long as there is no contradiction in the combination of these technical features, it should be considered as the scope recorded in this specification.

[0127] Those skilled in the art can easily understand that the above are only the preferred embodiments of the present invention and are not used to limit the present invention. Any modifications, equivalent replacements, and improvements made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims

1. A construction drawing detection method based on design response files, characterized in that: include: Perform initial testing on the received design response files and parse the design response files that pass the test to obtain design response data that meets the requirements; Matching the first key in the design reply data with the first preset key table, and recording the successfully matched design reply data; Parsing the successfully matched design reply data to obtain the second key and the design reply opinion data corresponding to the second key; The second key is matched with a second preset key table, and the modification content of the construction drawing is determined based on the matching result.

2. The construction drawing detection method based on the design reply file according to claim 1, characterized in that: The matching of the first key in the design reply data with the first preset key table further includes: If the first key does not match the first preset key table, it indicates that an error occurs in the match, and an error log report is generated and fed back; Determine whether to generate an alarm notification based on the error log report and preset alarm indicators.

3. The construction drawing detection method based on the design reply file as claimed in claim 2, characterized in that: The determining whether to generate an alarm notification according to the error log report and the preset alarm indicator also includes: Extracting the error type and error rate of the mismatch between the first key and the first preset key table from the error log report; When it is detected that the error type is a preset error type, generating and sending an error type alarm notification; When it is detected that the error rate reaches a preset error rate threshold, an error rate alarm notification is generated and sent.

4. The construction drawing detection method based on the design reply file according to claim 1, characterized in that: The matching of the second key with the second preset key table and determining the modification content of the construction drawing based on the matching result further includes: If the second key does not match the second preset key table, determining the modification content of the construction drawing according to the design reply opinion data; If the second key matches the second preset key table, the design response opinion data is compared with the corresponding review opinion data to determine the modification content of the construction drawing.

5. The construction drawing detection method based on the design reply file according to claim 4 is characterized in that: If the second key matches the second preset key table, the design reply opinion data is compared with the corresponding review opinion data to determine the modification content of the construction drawing, and further includes: If the design response opinion data is consistent with the corresponding review opinion data, the construction drawing is not modified; If the design reply opinion data is inconsistent with the corresponding audit opinion data, extract the inconsistent data content between the design reply opinion data and the corresponding audit opinion data; The construction drawing is updated with data content that is inconsistent between the design response opinion data and the corresponding review opinion data.

6. The construction drawing detection method based on the design reply file according to claim 4 is characterized in that: If the second key does not match the second preset key table, determining the modification content of the construction drawing according to the design reply opinion data, further comprising: Analyzing the mismatch between the second key and the second preset key table to determine the mismatch reason; The modification content of the construction drawing is determined based on the mismatch reason and the design response opinion data.

7. The construction drawing detection method based on design reply file according to claim 1, characterized in that: The initial detection of the received design response file and parsing the design response file that passes the detection to obtain the design response data that meets the requirements also includes: Detecting the storage capacity of the design response file to obtain a design response file that does not exceed a preset file capacity; Parsing the design response file that does not exceed the preset file capacity to obtain the preset type of design response data; A security check is performed on the preset type of design response data to obtain the design response data that passes the security check.

8. A construction drawing detection device based on design reply files, characterized in that: include: An initial detection module is configured to perform an initial detection on the received design response file and parse the design response file that passes the detection to obtain design response data that meets the requirements; A first matching module, configured to match the first key in the design reply data with a first preset key table, and record the design reply data that successfully matches; A data parsing module, configured to parse the successfully matched design reply data to obtain a second key and design reply opinion data corresponding to the second key; The second matching module is configured to match the second key with a second preset key table, and determine the modification content of the construction drawing based on the matching result.

9. A construction drawing detection device based on a design reply file, characterized in that: It includes at least one processing unit and at least one storage unit, wherein the storage unit stores a computer program, and when the computer program is executed by the processing unit, the processing unit executes the steps of the construction drawing detection method based on the design response file as described in any one of claims 1 to 7.

10. A storage medium, characterized in that: It stores a computer program executable by an access authentication device. When the computer program runs on the access authentication device, the access authentication device executes the steps of the construction drawing detection method based on the design response file as described in any one of claims 1 to 7.

Citation Information

Patent Citations