Method and system for changing and optimizing construction plan based on BIM model

The method addresses inefficiencies in BIM-based construction plans by integrating real-time data synchronization and change reminders to optimize construction plans, enhancing project collaboration and efficiency.

CN119204479APending Publication Date: 2024-12-27CHINA CONSTR THIRD ENG BUREAU GRP CO LTD +1

Patent Information

Application Number
CN202411012806.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-26
Publication Date
2024-12-27

AI Technical Summary

Technical Problem

Existing construction plan optimization methods based on BIM technology fail to account for changes during the construction process, leading to inefficiencies and potential economic losses.

Method used

A method and system that integrates model change acquisition, reminder, construction period adjustment, and plan rescheduling, utilizing message queues and API interfaces for real-time data synchronization, and includes change reminders and detailed calculations to optimize the construction plan.

Benefits of technology

The method effectively responds to BIM model changes, improving user participation, collaboration efficiency, and ensuring smooth project progress by optimizing labor, material, and construction period calculations.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119204479A_ABST
    Figure CN119204479A_ABST
Patent Text Reader

Abstract

The invention discloses a method and a system for changing and optimizing a construction plan based on a BIM model. The method comprises the following steps: acquiring change information and latest engineering quantity data of the BIM model; performing change reminding based on the change information; based on the change reminding, combining the latest project amount data, and calculating manpower, materials and a construction period required by the changed project; the calculated construction period is optimized; and based on the optimized construction period, the construction plan is re-planned in combination with manpower and materials required by the changed project, and an optimized construction plan is obtained. According to the method, a series of steps of efficiently obtaining the change data of the BIM model, providing reminding for the user, recalculating the project amount and the construction period, and timely and reasonably coping with the construction plan change caused by the change of the BIM model are carried out, so that the construction plan is powerfully optimized, and meanwhile, the participation degree of the user and the cooperation efficiency of a project team are also remarkably improved; and the smooth proceeding of a project is powerfully promoted.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of BIM, and in particular relates to a method and system for optimizing a construction plan based on BIM model changes. Background Art

[0002] In the traditional construction field, the planning and resource allocation of engineering projects are often based on experience or starting from scratch, which not only consumes a lot of manpower and time, but is also likely to lead to chaos and inefficiency in construction due to improper planning or miscalculation, and may even cause serious economic losses. Therefore, how to optimize the construction plan scientifically and efficiently is the goal that the construction industry has always pursued.

[0003] In recent years, with the rapid development of information technology, BIM technology has gradually been widely used in the construction industry. By creating a virtual model of a building, BIM technology can achieve full information integration, thereby improving construction efficiency and reducing construction costs. However, the existing construction plan optimization method based on BIM technology often ignores various changes that may occur during the construction process, such as design changes, construction errors, and construction delays. Once such changes occur, the original construction plan will be seriously disrupted. Summary of the invention

[0004] In order to overcome the above-mentioned deficiencies of the prior art, the present invention provides a method and system for optimizing construction plans based on BIM model changes, which solves the construction problems caused by model changes through the interaction of model change acquisition and reminder, construction period adjustment and plan rescheduling.

[0005] According to one aspect of the present invention, there is provided a method for optimizing a construction plan based on a BIM model change, comprising: Obtain BIM model change information and the latest engineering quantity data; Providing a change reminder based on the change information; Based on the change reminder and combined with the latest engineering quantity data, calculate the labor, materials and construction period required for the changed project; Optimize the calculated construction period; Based on the optimized construction period, the construction plan is replanned in combination with the labor and materials required for the changed project to obtain an optimized construction plan.

[0006] The above technical solution has effectively optimized the construction plan through a series of steps, from efficiently acquiring the change data of the BIM model to providing reminders to users, to recalculating the project quantity and duration, and responding to the changes in the construction plan caused by the BIM model changes in a timely and reasonable manner. It has also significantly improved the user participation and the collaboration efficiency of the project team, and effectively promoted the smooth progress of the project.

[0007] As a further technical solution, the method also includes: acquiring BIM model change data by combining message queue and API interface synchronization.

[0008] This technical solution adopts the dual insurance measures of message queue and API interface to ensure that accurate and timely data can be obtained under any circumstances, and synchronize the latest data of the BIM model in real time after receiving the message of BIM model change.

[0009] As a further technical solution, the change reminder also includes: sending a message to the user to remind the user of the change.

[0010] As a further technical solution, the change reminder also includes: making a change reminder by way of a model content change reminder.

[0011] As a further technical solution, after receiving the change reminder, the user also includes: Obtain labor quota, material quota and construction period quota after the model is changed based on the latest engineering quantity data of the model; According to the labor quota, material quota and construction period quota, the actual number of labor, material and equipment and time required to complete each process are obtained respectively.

[0012] As a further technical solution, the method further includes: According to the time required for each process, calculate the project duration after the model is changed; The construction period of the project is optimized according to the construction relationship to obtain an optimized construction period.

[0013] As a further technical solution, the method further includes: Determine re-planning objectives for the construction program; According to the re-planning objectives, the project is re-planned in combination with the labor, materials and optimized construction period required for the changed project to obtain an optimized construction plan.

[0014] As a further technical solution, the re-planning objectives include project progress, project cost and / or resource utilization efficiency.

[0015] According to one aspect of the present invention, a system for optimizing a construction plan based on a BIM model change is provided, comprising: Model change module, used to obtain BIM model change information and the latest engineering quantity data; A change reminder module, used for making a change reminder based on the change information; The construction plan quantity calculation module is used to calculate the labor, materials and construction period required for the changed project based on the change reminder and the latest engineering quantity data; The construction period adjustment module is used to optimize the calculated construction period; The plan rescheduling module is used to re-plan the construction plan based on the optimized construction period and the labor and materials required for the changed project to obtain an optimized construction plan.

[0016] As a further technical solution, the change reminder module is also used to execute the following instructions: Change reminders are made by sending messages to users, or by reminding users of changes in model content.

[0017] Compared with the prior art, the present invention has the following beneficial effects: The present invention has a series of steps from efficiently acquiring the change data of the BIM model to providing reminders to users, to recalculating the project quantity and construction period, and promptly and reasonably responding to the changes in the construction plan caused by the BIM model changes. It has effectively optimized the construction plan, and also significantly improved the user participation and the collaboration efficiency of the project team, which has effectively promoted the smooth progress of the project.

[0018] The present invention specifically optimizes the construction plan according to the model changes during the construction process. It has the ability to understand and predict the construction process, further enhances the controllability of the construction process, and significantly improves the stability and accuracy of the construction plan, which can promote construction management to a more scientific and refined level. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Figure 1 The present invention is a flowchart of a method for optimizing a construction plan based on BIM model changes according to an embodiment of the present invention.

[0020] Figure 2 A schematic diagram of obtaining BIM model changes according to an embodiment of the present invention.

[0021] Figure 3 FIG. 4 is a schematic diagram of plan rearrangement according to an embodiment of the present invention. DETAILED DESCRIPTION

[0022] Existing construction plan optimization based on BIM technology often ignores various changes that may occur during the construction process, resulting in serious disruption of the original construction plan due to changes, affecting the construction process. To this end, the present invention proposes a construction plan optimization method based on BIM technology specifically for model changes during the construction process. Through the interaction of model change acquisition and reminder, construction period adjustment and plan rescheduling, the construction problems caused by model changes are solved, ensuring the smooth progress of the construction project.

[0023] In some processes described in the specification and claims of the present invention and the above-mentioned drawings, multiple operations appearing in a specific order are included, but it should be clearly understood that these operations may not be performed in the order in which they appear in this document or may be performed in parallel. For example, step 1, step 2, etc. are only used to distinguish different operations, and the sequence number itself does not represent any execution order. In addition, these processes may include more or fewer operations, and these operations may be performed in sequence or in parallel.

[0024] The following will clearly and completely describe the technical solutions of various embodiments of the present invention in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present invention. Example 1

[0025] This embodiment provides a method for optimizing construction plans based on BIM model changes, which is used to optimize construction plans after model changes and ensure the smooth progress of construction projects.

[0026] like Figure 1 As shown, the method includes: Step 1: Obtain the change information and latest engineering quantity data of the BIM model.

[0027] In one implementation, a message queue (MQ) and API interface synchronization are combined to efficiently obtain changes and the latest data of the BIM model. This solution is highly reliable and flexible, and can meet various business needs, ensuring that the BIM model can be accurately obtained after changes, such as Figure 2 shown.

[0028] Specifically, by using message queues, you can monitor model changes in real time and ensure the real-time nature of data. This MQ-based real-time monitoring mechanism ensures that the latest model data is obtained in a timely manner so that you can respond when needed.

[0029] In order to avoid the failure of data acquisition due to MQ problems, the API interface is added as a backup solution. In this way, even if MQ fails, the change data of the BIM model can still be obtained through the API interface.

[0030] This double insurance measure ensures that accurate and timely data can be obtained in any situation. After receiving the message of BIM model change, the latest data of the BIM model is synchronized in real time.

[0031] Step 2: Providing a change reminder based on the change information.

[0032] For changes to the BIM model, users need to be reminded in a timely manner so that they can understand the details of the changes and take appropriate countermeasures.

[0033] Specifically, changes in the model will automatically trigger the calculation, and push reminders to users to remind them to pay attention to the changes.

[0034] To achieve this goal, we can do so in the following ways: a) Message reminder: Users can be reminded of changes in BIM models by sending in-site messages, SMS or email notifications. These messages may include the time, reason, scope of impact and model status after the change. In addition, personalized message reminder services can be customized according to the actual needs of users to better meet their needs.

[0035] b) Model content change reminder: In addition to message reminders, model content change reminders can also be used to let users know the details of BIM model changes. Specifically, some marks or prompts can be added to the model to inform users which parts have changed and the impact these changes may have on the project.

[0036] Through the above methods, users can be informed of BIM model changes in a timely manner and ensure that they understand the details of the changes. These reminder methods help improve user participation and project team collaboration efficiency, thereby better promoting the smooth progress of the project.

[0037] Step 3: Based on the change reminder and in combination with the latest engineering quantity data, calculate the labor, materials and construction period required for the changed project.

[0038] Based on the BIM model, detailed engineering quantity data of all processes can be obtained. These data cover key factors such as labor quota, material quota and construction period quota. By carefully analyzing these data and performing reasonable calculations and evaluations on them, accurate data on labor, materials and construction period required for the changed project can be obtained.

[0039] Drawing changes will lead to changes in the amount of work, that is, model version drawing differences. It is known that the amount of work = labor quota * number of people * construction period. By determining two of the values, the other can be accurately calculated. The labor quota is fixed, that is, how much work a person can complete in a day. The construction period is within a range for the project. The construction period can be adjusted by adjusting the construction plan, and the adjustment of the construction plan is mainly the adjustment of labor. For example, if it takes 15 days to complete a certain work standard, the time can be shortened by adding labor, but it must not be less than 7 days.

[0040] Specifically, labor quotas can help plan and manage human resources by understanding the actual number of workers required to complete a specific process. Material quotas provide the number of materials and equipment required for each process, making it easier to purchase and manage inventory in advance. Duration quotas provide the time required to complete each process, helping to develop a reasonable and efficient project plan and ensure that the project is completed on time.

[0041] Step 4: Optimize the calculated construction period.

[0042] Through step 3, we can obtain the preliminary expected duration of the project, and then fine-tune and optimize it by using various complex construction relationships. These relationships include the connection between each process, cross-operation, and parallel construction of multiple work lines. In addition, we need to fully consider various factors in the actual construction process, such as environmental conditions, resource allocation, personnel arrangements, etc., in order to make fine adjustments to the duration.

[0043] Step 5: Based on the optimized construction period, the construction plan is replanned in combination with the labor and materials required for the changed project to obtain an optimized construction plan.

[0044] After the adjustment of the construction period, the construction plan needs to be re-planned and arranged. This process involves the following steps, such as Figure 3 As shown: a) Comprehensively evaluate the current plan: Conduct a comprehensive evaluation of the existing construction plan to identify its strengths and weaknesses. The evaluation should be considered from multiple perspectives such as project progress, resource utilization and cost-effectiveness.

[0045] i. Collect data: Collect all relevant data about the current construction plan, including project progress, resource usage, cost expenditure, etc.

[0046] ii. Analyze progress: Compare actual progress with planned progress and identify causes of delays and potential risk points.

[0047] iii. Evaluate resources: Analyze the efficiency of resource utilization, including human, material, and financial resources, and identify areas of waste or shortage.

[0048] iv. Cost-Benefit Analysis: Compare the actual cost with the target cost to evaluate the economic benefits of the project.

[0049] b) Determine the rescheduling objectives: clarify the direction and objectives of the new construction plan. These objectives may include optimizing the project schedule, reducing costs, and improving resource utilization efficiency.

[0050] i. Clarify goals: Based on the evaluation results, clarify the goals that need to be achieved in the new plan, such as shortening construction period, reducing costs, improving quality, etc.

[0051] ii. Prioritize: Prioritize goals based on the overall project strategy and stakeholder needs.

[0052] c) Analyze influencing factors: Carefully analyze various factors that may affect the new construction plan, such as weather conditions, policy changes, resource supply, and actual on-site conditions.

[0053] i. External factors: Analyze the impact of external factors such as weather, policies, and market environment on the construction plan.

[0054] ii. Internal factors: Evaluate the project team’s capabilities, technical level, resource supply and other internal factors.

[0055] iii. Risk identification: Identify potential construction risks, such as technical difficulties, supply chain disruptions, etc. d) Develop a new plan: Based on the previous assessment and the determined rescheduling goals, develop a new construction plan. This plan should take into account various influencing factors and try to optimize various indicators to achieve the established goals.

[0056] i. Critical Path Method (CPM): Identify the critical tasks in the project and ensure that these tasks are completed on time to ensure the progress of the entire project.

[0057] ii. Resource balance: According to the availability and demand of resources, reasonably arrange the start and end time of each task to avoid resource conflict or waste.

[0058] iii. Risk Management: Consider risk mitigation measures in the plan, such as backup suppliers, emergency plans, etc.

[0059] iv. Comparison of multiple options: Develop multiple alternative options and select the best option by comparing the advantages and disadvantages of different options.

[0060] e) Review and revise the new plan: The new plan needs to be rigorously reviewed and revised to ensure its feasibility in practical operations. This may require discussions with members of the project team and necessary revisions and improvements to the plan.

[0061] i. Team discussion: Organize project team members to discuss the new plan and collect their opinions and suggestions.

[0062] ii. Simulation test: Use project management software to conduct simulation tests to evaluate the feasibility of the new plan in actual operations.

[0063] iii. Revision and improvement: Based on the results of team discussions and simulation tests, make necessary revisions and improvements to the new plan.

[0064] iv. Approval for release: After review and revision, the new plan is approved by the relevant responsible persons and released.

[0065] In general, the present invention presents an innovative solution based on the optimization of the construction plan of the general contractor management after the BIM model is changed. This method covers a series of steps from efficiently obtaining the change data of the BIM model to providing reminders to users, to recalculating the engineering quantity and duration, and timely and reasonably responding to the changes in the construction plan caused by the BIM model changes. This series of measures has effectively optimized the construction plan, and also significantly improved the user participation and the collaboration efficiency of the project team, which has effectively promoted the smooth progress of the project. Example 2

[0066] Based on the same inventive concept as that of Example 1, this embodiment provides a system for optimizing construction plans based on BIM model changes, including: Model change module, used to obtain BIM model change information and the latest engineering quantity data; A change reminder module, used for making a change reminder based on the change information; The construction plan quantity calculation module is used to calculate the labor, materials and construction period required for the changed project based on the change reminder and the latest engineering quantity data; The construction period adjustment module is used to optimize the calculated construction period; The plan rescheduling module is used to re-plan the construction plan based on the optimized construction period and the labor and materials required for the changed project to obtain an optimized construction plan.

[0067] The above modules can be implemented by referring to the method embodiment, which will not be described in detail here. It should be noted that: The change reminder module is also used to execute the following instructions: Change reminders are made by sending messages to users, or by reminding users of changes in model content.

[0068] It should be noted that the implementation solution provided by the device to solve the problem is similar to the implementation solution recorded in the above method. Therefore, the specific limitations in the implementation methods of the aforementioned modules can be referred to the limitations of a method for optimizing construction plans based on BIM model changes mentioned above, which will not be repeated here.

[0069] In summary, the present invention achieves the following technical effects: 1. Efficiently obtain BIM model change data: Use a combination of message queue (MQ) and API interface synchronization to ensure real-time and accurate acquisition of BIM model changes and the latest data.

[0070] 2. Provide change reminders: Through various means such as in-site messages, text messages, and emails, timely convey information about BIM model changes to users, thereby improving user participation and the collaboration efficiency of the project team.

[0071] 3. Construction plan quantity calculation: Based on the BIM model, obtain detailed engineering quantity data of all processes, and perform accurate calculations and evaluations to obtain accurate data on the labor, materials and construction period required for the changed project.

[0072] 4. Adjustment of construction period: By considering the complex construction relationships and various actual construction factors, the construction period is finely adjusted to ensure the rationality and efficiency of the construction plan.

[0073] 5. Plan rescheduling: After a comprehensive evaluation of the current plan, clarify the goals of the new construction plan, carefully analyze various factors that may affect the new construction plan, formulate a new construction plan, and conduct strict review and revision to ensure its feasibility and effectiveness in actual operation.

[0074] This series of measures has effectively optimized the construction plan, while also significantly improving user participation and the collaboration efficiency of the project team, effectively promoting the smooth progress of the project.

[0075] It will be appreciated by those skilled in the art that embodiments of the present invention may be provided as methods, systems, or computer program products. Therefore, the present invention may take the form of a complete hardware embodiment, a complete software embodiment, or an embodiment combining software and hardware. Furthermore, the present invention may take the form of a computer program product implemented on one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) containing computer-usable program code.

[0076] The present invention is described with reference to flowcharts and / or block diagrams of methods, devices (systems), and computer program products according to embodiments of the present invention. It should be understood that each process and / or block in the flowchart and / or block diagram, as well as the combination of processes and / or blocks in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to produce a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.

[0077] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce an article of manufacture comprising an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.

[0078] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.

[0079] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or replace some or all of the technical features therein with equivalents. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the technical solutions of the embodiments of the present invention.

Claims

1. A method for optimizing construction plans based on BIM model changes, characterized in that: include: Obtain BIM model change information and the latest engineering quantity data; Providing a change reminder based on the change information; Based on the change reminder and combined with the latest engineering quantity data, calculate the labor, materials and construction period required for the changed project; Optimize the calculated construction period; Based on the optimized construction period, the construction plan is replanned in combination with the labor and materials required for the changed project to obtain an optimized construction plan.

2. A method for optimizing construction plans based on BIM model changes according to claim 1, characterized in that: The method also includes: acquiring BIM model change data by combining message queue and API interface synchronization.

3. According to claim 1, a method for optimizing construction plan based on BIM model change is characterized in that: Providing a change reminder also includes: providing a change reminder by sending a message to the user.

4. The method for optimizing construction plan based on BIM model change according to claim 1, characterized in that: Providing change reminders also includes: providing change reminders by way of model content change reminders.

5. The method for optimizing construction plan based on BIM model change according to claim 1, characterized in that: After receiving the change notification, the user will also receive: Obtain labor quota, material quota and construction period quota after the model is changed based on the latest engineering quantity data of the model; According to the labor quota, material quota and construction period quota, the actual number of labor, material and equipment and time required to complete each process are obtained respectively.

6. A method for optimizing construction plans based on BIM model changes according to claim 5, characterized in that: The method further comprises: According to the time required for each process, calculate the project duration after the model is changed; The construction period of the project is optimized according to the construction relationship to obtain an optimized construction period.

7. The method for optimizing construction plan based on BIM model change according to claim 1, characterized in that: The method further comprises: Determine re-planning objectives for the construction program; According to the re-planning objectives, the project is re-planned in combination with the labor, materials and optimized construction period required for the changed project to obtain an optimized construction plan.

8. A method for optimizing construction plans based on BIM model changes according to claim 7, characterized in that: The re-planning objectives include project schedule, project cost and / or resource utilization efficiency.

9. A system for optimizing construction plans based on BIM model changes, characterized in that: include: Model change module, used to obtain BIM model change information and the latest engineering quantity data; A change reminder module, used for making a change reminder based on the change information; The construction plan quantity calculation module is used to calculate the labor, materials and construction period required for the changed project based on the change reminder and the latest engineering quantity data; The construction period adjustment module is used to optimize the calculated construction period; The plan rescheduling module is used to re-plan the construction plan based on the optimized construction period and the labor and materials required for the changed project to obtain an optimized construction plan.

10. A system for optimizing construction plans based on BIM model changes according to claim 9, characterized in that: The change reminder module is also used to execute the following instructions: Change reminders are made by sending messages to users, or by reminding users of changes in model content.

Citation Information

Patent Citations

  • Change control method based on BIM

    CN103500371A

  • Browser-based BIM progress plan management method and system

    CN107918831A

  • BIM rapid changing method

    CN111651818A

  • Engineering construction progress plan management and control system and method based on BIM model

    CN111754138A

  • Method and system for calculating construction period quota based on BIM model, and medium

    CN117391264A

Cited By

  • Artificial intelligence computing power center construction management method and system

    CN120805231A