DCS control system based on mine aggregate production line and aggregate sales

By designing the DCS control system in the mine aggregate production line and sales system, dividing production line units and calculating attention, the order problem of large-scale order processing is solved, the delivery quality and safety are improved, and the production line resource allocation and order processing efficiency are optimized. .

CN119247910AActive Publication Date: 2025-01-03CCCC TDC ENVIRONMENTAL ENG
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN202411766142.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-12-04
Publication Date
2025-01-03
Estimated Expiration
2044-12-04

AI Technical Summary

Technical Problem

Traditional mining aggregate production lines have problems such as extensive layout, serious pollution, low production capacity, unstable production, unqualified product quality, inconvenient equipment maintenance and high operating costs. Especially when handling large batches of orders, how to determine the order processing order becomes important.

Method used

A DCS control system based on mining aggregate production line and aggregate sales was designed, including order demand acquisition and determination module, unit attention calculation module, order attention calculation module and order sorting module, which affects units and non-demands by dividing demand Influencing the unit, calculate the attention data of each unit, and determine the order processing order based on the order attention data.

Benefits of technology

It realizes on-time delivery of large-scale orders, improves delivery quality and operational safety, and optimizes the resource allocation and order processing efficiency of the production line.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119247910A_ABST
    Figure CN119247910A_ABST
Patent Text Reader

Abstract

The invention provides a DCS control system based on a mine aggregate production line and aggregate sales, and belongs to the technical field of mine aggregate processing control. The DCS control system based on the mine aggregate production line and the aggregate sales comprises an order demand acquisition and determination module, a unit attention calculation module, an order attention calculation module and an order sorting module. Through cooperative use of the modules, the order processing sequence is obtained, on-time delivery of large-batch orders is ensured, and the delivery quality and processing safety of the large-batch orders are improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of mine aggregate processing control, and in particular to a DCS control system based on mine aggregate production lines and aggregate sales. Background Art

[0002] An aggregate production line is an industrial production line used to produce sand and gravel aggregates for construction. The aggregates produced by the aggregate production line are widely used in the construction of infrastructure such as roads, bridges, and water conservancy projects. The DCS control system is a distributed control system designed to address the problems of traditional mining aggregate production lines, such as extensive layout, serious pollution, low production capacity, unstable output, substandard product quality, inconvenient equipment maintenance, and high operating costs. The system centrally manages the production, sales, and operation management of mining aggregates, and achieves comprehensive control of all aspects of mining production through the central control system. Generally speaking, the system will receive orders from customers and control the front-end equipment production line to manufacture aggregates and other material products based on the orders, and then transport them to the customer's designated location. When manufacturing the material products specified in the order, it is generally necessary to complete one order before processing the next one. However, when large orders appear, it is very important to determine the order processing sequence. Summary of the Invention

[0003] This application provides a DCS control system based on a mine aggregate production line and aggregate sales. The system includes an order demand acquisition and determination module, a unit attention calculation module, an order attention calculation module, and an order sorting module; The order demand acquisition and determination module is used to obtain the order content of the order received by the system and determine the product requirements mentioned in the order based on the order content, and output order demand data; the order demand data includes order delivery time, material type requirements, material quantity requirements and material transportation requirements; The unit attention calculation module is further configured to: According to the order demand data and the initial production mode of each production line unit, each production line unit is divided into a demand-affected unit and a non-demand-affected unit; the production line unit represents the production unit of each functional module of the aggregate production line, including a feeding unit, a processing unit, a screening unit, and a transportation unit; the preset order demand impact comparison table includes the order demand data, each production line unit, and the corresponding relationship between the order demand data and the production line unit; the demand-affected unit is a production line unit that adjusts its initial production mode due to the order demand; the non-demand-affected unit is a production line unit that is not affected by the order demand and does not need to adjust its initial production mode; Determining the impact attention adjustment data of the demand impact unit according to the order demand data and the preset order demand impact comparison table; Calculating the demand unit attention data of the demand influencing unit according to the basic attention data of the demand influencing unit and the attention influence adjustment data; Calculating non-demand unit attention data of non-demand impact units based on the demand unit attention data and the initial production line unit total attention data; The order attention calculation module is used to calculate order attention data based on the demand unit attention data and the non-demand unit attention data; The order sorting module is used to determine the order processing order according to the order attention data.

[0004] Furthermore, the unit attention calculation module is further configured to determine the attention adjustment data of the demand-affected unit according to the order demand data and the preset order demand impact comparison table, including: Determining the production operation steps included in the initial production mode corresponding to the demand influencing unit according to the initial production mode of each production line unit; Determining additional operation steps based on the order demand data and the preset order demand impact comparison table; Obtain a comparison table of the number of steps of the added operation steps and the impact of the attention of the preset steps; Determining the impact attention adjustment data of the demand impact unit according to the number of steps and the preset step attention impact comparison table; The preset step attention impact comparison table includes the corresponding relationship between the number of steps and the attention impact adjustment data.

[0005] Furthermore, the unit attention calculation module is further configured such that the demand unit attention data is the sum of the basic attention data of the demand impact unit and the impact attention adjustment data.

[0006] Furthermore, the unit attention calculation module is further configured to calculate the non-demand unit attention data of the non-demand impact unit based on the demand unit attention data and the initial production line unit total attention data, including: Calculating demand unit total attention data according to the demand unit attention data of each demand unit; the demand unit total attention data is the sum of the demand unit attention data of each demand unit; Calculating the non-demand unit total attention data based on the demand unit total attention data and the initial production line unit total attention data; the non-demand unit total attention data is the difference between the initial production line unit total attention data and the demand unit total attention data; The non-demand unit attention data of the non-demand influencing unit is calculated according to the non-demand unit total attention data and the non-demand unit basic attention data.

[0007] Furthermore, the unit attention calculation module is further configured to calculate the non-demand unit attention data using the following method: There are n non-demand impact units. , then the basic attention data of the i-th non-demand influence unit is ; ; Where, is the non-demand unit attention data of the i-th non-demand impact unit, is the total attention data of the demand unit; the total attention data of the initial production line unit is 1.

[0008] Furthermore, the unit attention calculation module is further configured to: Suppose there are x demand-affected units and y non-demand-affected units; then, ; Then the basic attention data of the u-th demand influence unit is ; The basic attention data of the vth non-demand influence unit is ;but, in, .

[0009] It should be understood that the contents described in the Summary of the Invention are not intended to limit the key or important features of the embodiments of the present application, nor are they intended to limit the scope of the present application. Other features of the present application will become readily understood through the following description. BRIEF DESCRIPTION OF THE DRAWINGS

[0010] The above and other features, advantages and aspects of the embodiments of the present application will become more apparent with reference to the following detailed description in conjunction with the accompanying drawings. In the accompanying drawings, the same or similar reference numerals represent the same or similar elements, wherein: Figure 1 A block diagram of a DCS control system based on a mine aggregate production line and aggregate sales in an embodiment of the present application is shown. DETAILED DESCRIPTION

[0011] To make the purpose, technical solutions, and advantages of the embodiments of this application more clear, the technical solutions in the embodiments of this application will be clearly and completely described below in conjunction with the drawings in the embodiments of this application. Obviously, the described embodiments are part of the embodiments of this application, not all of the embodiments. Based on the embodiments in this application, all other embodiments obtained by ordinary technicians in this field without making creative efforts are within the scope of protection of this application.

[0012] In this document, the term "and / or" simply describes a relationship between related objects, indicating that three possible relationships exist. For example, "A and / or B" can represent: A exists alone, A and B exist simultaneously, or B exists alone. Furthermore, the character " / " in this document generally indicates that the related objects are in an "or" relationship.

[0013] This application provides a DCS control system based on a mine aggregate production line and aggregate sales, which can ensure the on-time delivery of large-volume orders and improve the delivery quality and operational safety of large-volume orders.

[0014] like Figure 1 As shown, a DCS control system based on a mine aggregate production line and aggregate sales includes an order demand acquisition and determination module 110, a unit attention calculation module 120, an order attention calculation module 130 and an order sorting module 140; wherein, the order demand acquisition and determination module 110 is used to obtain the order content of the order received by the system and determine the product demand mentioned in the order according to the order content, and output order demand data; the order demand data includes order delivery time, material type demand, total material demand and material transportation demand; the unit attention calculation module 120 is further configured to divide each production line unit into demand-affected units and non-demand-affected units according to the order demand data and the initial production mode of each production line unit; the production line unit represents the production unit of each functional module of the aggregate production line, including a feeding unit, a processing unit, a screening unit and a transportation unit; the preset order demand impact comparison table includes order demand data , the correspondence between each production line unit and the order demand data and the production line unit; the demand affecting unit is a production line unit that adjusts the initial production mode due to the influence of order demand; the non-demand affecting unit is a production line unit that is not affected by order demand and does not need to adjust the initial production mode; the impact attention adjustment data of the demand affecting unit is determined according to the order demand data and the preset order demand impact comparison table; the demand unit attention data of the demand affecting unit is calculated according to the basic attention data of the demand affecting unit and the impact attention adjustment data; the non-demand unit attention data of the non-demand affecting unit is calculated according to the demand unit attention data and the total attention data of the initial production line unit; the order attention calculation module 130 is used to calculate the order attention data according to the demand unit attention data and the non-demand unit attention data; the order sorting module 140 is used to determine the order processing order according to the order attention data.

[0015] It is understood that in the embodiment of the present application, the aggregate production line is divided into four units: a feeding unit, a processing unit, a screening unit, and a transportation unit. However, for different aggregate production lines, it can be divided into more or fewer units. It should be noted that the orders that need to be sorted here are all orders that meet the pre-time screening conditions; specifically, the orders that need to be sorted are determined based on the order delivery time and the preset delivery time threshold contained in the order demand data; it is understood that here, orders are screened based on the order delivery time, and orders with an order delivery time greater than the preset delivery time threshold are sorted, while orders with an order delivery time not greater than the preset delivery time threshold are sorted according to the urgency of the order delivery time; the urgency sorting here refers to determining the remaining delivery time of the order based on the order delivery time, and sorting the orders from short to long according to the remaining delivery time; and for orders with an order delivery time greater than the preset delivery time threshold, they have sufficient delivery time and are sorted according to the solution of the present application.

[0016] It can be understood that material type demand refers to the type of aggregate required by the order, such as 0-5mm machine-made sand and stone powder, 5-10mm crushed stone, 10-20mm crushed stone, 20-28mm crushed stone, four specifications of stone, etc.; since different types of aggregates require different levels of processing machines and different screening methods, in the preset order demand impact comparison table, the corresponding units associated with material type demand are processing units and screening units; and the corresponding unit associated with total material demand is the feeding unit; because the total material quantity determines the total amount of material that needs to be processed for this order, and these materials need to enter the processing unit from the feeding unit in batches for material processing, the total material quantity demand is associated with the feeding unit; and the material transportation demand is correspondingly associated with the transportation unit; it can be understood that the transportation unit here refers to the unit for transporting the material products that have been processed and screened, and does not refer to the unit for transporting unfinished materials during the processing and screening process.

[0017] It can be understood that the basic attention data for each production line unit here can be represented as the degree of computing resource allocation of the control system to each unit; for example, the basic attention data of the feeding unit is 15%, indicating that 15% of the computing resources are allocated to the feeding unit; the basic attention data of the processing unit is 40%, indicating that 40% of the computing resources are allocated to the processing unit; the basic attention data of the screening unit is 35%, indicating that 35% of the computing resources are allocated to the screening unit; the basic attention data of the transportation unit is 10%, indicating that 10% of the computing resources are allocated to the transportation unit.

[0018] Specifically, in an embodiment of the present application, the unit attention calculation module 120 is further configured to determine the impact attention adjustment data of the demand impact unit based on the order demand data and the preset order demand impact comparison table, including: determining the production operation steps included in the initial production mode corresponding to the demand impact unit based on the initial production mode of each production line unit; determining the additional operation steps based on the order demand data and the preset order demand impact comparison table; obtaining the number of steps of the additional operation steps and the preset step attention impact comparison table; determining the impact attention adjustment data of the demand impact unit based on the number of steps and the preset step attention impact comparison table; the preset step attention impact comparison table contains the correspondence between the number of steps and the impact attention adjustment data.

[0019] It can be understood that the initial production mode here is represented by the simplest production mode, the basic production mode with the least energy consumption and the least steps; and based on the order requirements, it can be determined to add additional production steps to the basic production mode; for example, the basic production mode of the feeding unit is the preset basic material quantity, which corresponds to adding materials three times in the feeding unit; the basic production mode of the processing unit is to process the stone with the largest diameter once, and the corresponding production steps are 4 steps; the basic production mode of the screening unit is to perform 1 screening; the basic production mode of the transportation unit is no need for transportation; it can be understood that the basic production mode of each production line unit illustrated in the above examples is characterized by the fact that there is no additional demand for materials in the corresponding order, so when additional demand appears in the order, such as the material type demand is greater than the preset type quantity, the total material demand is greater than the preset material quantity, and the material transportation demand is that transportation is required, the unit corresponding to the above demand is the demand-affecting unit; similarly, when there is no physical transportation demand, the transportation unit is a non-demand-affected unit.

[0020] It can be understood that since the processing method of the aggregate production line is fixed, the products that can be processed and produced are also fixed. Therefore, when the order demand is obtained, based on the total material quantity demand and material type demand in the order demand, combined with the historical processing records, the production steps that need to be added to the corresponding demand in the order demand can be determined; that is, the additional operation steps are determined according to the order demand data and the preset order demand impact comparison table; and for each additional production step, the system needs to allocate an additional portion of computing power resources to the unit, that is, the impact attention adjustment data of the demand impact unit is determined according to the number of steps and the preset step attention impact comparison table; for example, for each additional step, the attention data will be increased by 2%, etc.

[0021] Furthermore, the demand unit attention data is the sum of the basic attention data of the demand influencing unit and the influence attention adjustment data.

[0022] Furthermore, the calculation of the non-demand unit attention data of the non-demand influencing unit based on the demand unit attention data and the initial production line unit total attention data includes: calculating the demand unit total attention data based on the demand unit attention data of each demand unit; the demand unit total attention data is the sum of the demand unit attention data of each demand unit; calculating the non-demand unit total attention data based on the demand unit total attention data and the initial production line unit total attention data; the non-demand unit total attention data is the difference between the initial production line unit total attention data and the demand unit total attention data; calculating the non-demand unit attention data of the non-demand influencing unit based on the non-demand unit total attention data and the basic attention data of the non-demand unit.

[0023] In the embodiment of the present application, it should be noted that the unit attention calculation module 120 is further configured to have x demand-affecting units and y non-demand-affecting units; then, ; Then the basic attention data of the u-th demand influence unit is ; The basic attention data of the vth non-demand influence unit is ;but, in, .

[0024] The calculation method of the non-demand unit attention data includes: There are n non-demand impact units. , then the basic attention data of the i-th non-demand influence unit is ; ; Where, is the non-demand unit attention data of the i-th non-demand impact unit, is the total attention data of the demand unit; the total attention data of the initial production line unit is 1.

[0025] It can be understood that in the embodiment of the present application, the computing power resources of the system are considered to be fixed. Therefore, when the attention of any unit increases, the corresponding computing power resources will also increase; the attention of some units in the remaining units will decrease, and the corresponding computing power resources will also decrease.

[0026] After obtaining the attention data of each unit corresponding to each order, the order attention data can be calculated in combination with the preset unit attention score; and then the order processing order is obtained by sorting the order attention data from high to low.

[0027] It can be understood that the preset unit attention scores of different units are different. Therefore, through the calculation formula, the demand unit attention data of the demand-influencing units contained in the order * the corresponding preset unit attention score + the non-demand unit attention data of the non-demand-influencing units contained in the order * the corresponding preset unit attention score = order attention data.

[0028] It should be noted that for the aforementioned method embodiments, for the sake of simplicity, they are all expressed as a series of action combinations, but those skilled in the art should be aware that this application is not limited by the order of the actions described, because according to the embodiments of this application, certain steps can be performed in other orders or simultaneously. Secondly, those skilled in the art should also be aware that the embodiments described in the specification are all optional embodiments, and the actions and modules involved are not necessarily required for this application.

[0029] Those skilled in the art can clearly understand that, for the convenience and brevity of description, the specific working process of the described device can refer to the corresponding process in the aforementioned method embodiment, and will not be repeated here.

[0030] The above description is merely a preferred embodiment of the present application and an illustration of the technical principles employed. Those skilled in the art should understand that the scope of disclosure in this application is not limited to the technical solutions formed by a specific combination of the above-mentioned technical features, but also encompasses other technical solutions formed by any combination of the above-mentioned technical features or their equivalents without departing from the aforementioned disclosed concepts. For example, a technical solution formed by replacing the above-mentioned features with (but not limited to) technical features with similar functions disclosed in this application.

Claims

1. A DCS control system based on mine aggregate production line and aggregate sales, characterized in that: It includes an order demand acquisition and determination module (110), a unit attention calculation module (120), an order attention calculation module (130) and an order sorting module (140); The order demand acquisition and determination module (110) is used to acquire the order content of the order received by the system and determine the product demand mentioned in the order according to the order content, and output order demand data; the order demand data includes order delivery time, material type requirement, material total quantity requirement and material transportation requirement; The unit attention calculation module (120) is further configured to: According to the order demand data and the initial production mode of each production line unit, each production line unit is divided into a demand-affected unit and a non-demand-affected unit; the production line unit represents the production unit of each functional module of the aggregate production line, including a feeding unit, a processing unit, a screening unit and a transportation unit; the demand-affected unit is a production line unit that adjusts the initial production mode due to the order demand; the non-demand-affected unit is a production line unit that is not affected by the order demand and does not need to adjust the initial production mode; Determine the impact attention adjustment data of the demand impact unit according to the order demand data and a preset order demand impact comparison table; the preset order demand impact comparison table includes the order demand data, each production line unit and the corresponding relationship between the order demand data and the production line unit; Calculate the demand unit attention data of the demand influencing unit according to the basic attention data of the demand influencing unit and the attention influencing adjustment data; Calculate the non-demand unit attention data of the non-demand impact unit according to the demand unit attention data and the initial production line unit total attention data; The order attention calculation module (130) is used to calculate order attention data according to the demand unit attention data and the non-demand unit attention data; The order sorting module (140) is used to determine the order processing order according to the order attention data.

2. The system according to claim 1, characterized in that The unit attention calculation module (120) is further configured to determine the attention adjustment data of the demand impact unit according to the order demand data and the preset order demand impact comparison table, including: Determining the production operation steps included in the initial production mode corresponding to the demand influencing unit according to the initial production mode of each production line unit; Determine additional operation steps according to the order demand data and the preset order demand impact comparison table; Obtain a comparison table of the number of steps of the added operation steps and the impact of the attention of the preset steps; Determine the impact attention adjustment data of the demand impact unit according to the number of steps and the preset step attention impact comparison table; The preset step attention impact comparison table includes the corresponding relationship between the number of steps and the attention impact adjustment data.

3. The system according to claim 2, characterized in that The unit attention calculation module (120) is further configured such that the demand unit attention data is the sum of the basic attention data of the demand influencing unit and the influencing attention adjustment data.

4. The system according to claim 3, characterized in that The unit attention calculation module (120) is further configured to calculate the non-demand unit attention data of the non-demand impact unit according to the demand unit attention data and the initial production line unit total attention data, including: Calculate the demand unit total attention data according to the demand unit attention data of each demand unit; the demand unit total attention data is the sum of the demand unit attention data of each demand unit; Calculate the total attention data of non-demand units according to the total attention data of demand units and the total attention data of initial production line units; the total attention data of non-demand units is the difference between the total attention data of initial production line units and the total attention data of demand units; The non-demand unit attention data of the non-demand influencing unit is calculated according to the non-demand unit total attention data and the non-demand unit basic attention data.

5. The system according to claim 4, characterized in that The unit attention calculation module (120) is further configured such that a method for calculating the non-demand unit attention data includes: Suppose there are n non-demand-affecting units, , then the basic attention data of the i-th non-demand influence unit is ; ; Wherein, is the non-demand unit attention data of the i-th non-demand impact unit, is the total attention data of the demand unit; the total attention data of the initial production line unit is 1.

6. The system according to claim 5, characterized in that The unit attention calculation module (120) is further configured to: Suppose there are x demand-affected units and y non-demand-affected units; then, ; Then the basic attention data of the u-th demand influence unit is ; The basic attention data of the vth non-demand influence unit is but, in, .

Citation Information

Patent Citations

  • Training method of order production scheduling model and order production scheduling method and device

    CN112561390A

  • Intelligent production line configuration method and system for multi-variety and small-batch production

    CN117094838A

  • Balanced production scheduling method and system based on genetic algorithm and pulling mode

    CN117521320A

  • Customized production and flexible production line cooperative control method and system

    CN118466430A

  • Production plan scheduling method and system based on order data analysis