Pile driving barge pile overhead middle folding process
By dividing the pile frame of the pile driver into two sections and closing and docking in the air on the ship, the problem of high lifting costs caused by the weight of the super-large pile frame is solved, and a more economical and environmentally friendly installation process is achieved.
Patent Information
- Application Number
- CN202411631367.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-15
- Publication Date
- 2025-01-07
AI Technical Summary
The pile frame of the super-large pile driving ship is too heavy, which makes it impossible to install the entire dock. It requires a large floating crane for lifting, which is costly and uneconomic and environmentally friendly.
The pile frame is divided into two sections, and the 500T gantry crane is used to close and dock on the pile driving ship for air closing and docking, including installing support beams at the stern, setting up high support frames and reference support frames in the living area, and using high-hinged ear plates and transfer beams for sectional lifting. And precise positioning and docking is achieved through the hydraulic cylinder rail and the guide plate.
It saves the cost of floating crane transport and dispatch, solves the problem of the dock being unable to be lifted as a whole, and improves installation efficiency and economy.
Smart Images

Figure CN119262229A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of pile frame installation, and in particular to a process for closing a pile frame of a pile driving ship in mid-air. Background Art
[0002] The pile frame of the pile driving ship is heavy, and the total weight after being equipped exceeds 1,300 tons. Due to the heavy weight of the super-large pile frame, it cannot be installed as a whole in the dock. Therefore, the pile frame of the pile driving ship generally needs to be hoisted and installed by a large floating crane after the ship is launched: after launching, the ship is moored at the dock, and the pile frame is made and hoisted as a whole by a floating crane. It is necessary to rent a floating crane, and the dispatch and construction costs of a large floating crane are high. The construction process requires multiple tugboats for escort and consignment, which is not economical and environmentally friendly. Summary of the invention
[0003] The technical problem to be solved by the present invention is to provide a process for closing piles in mid-air by a pile-driving ship.
[0004] In order to solve the above technical problems, the technical solution of the present invention is: a pile-driving ship pile overhead closure process, the pile-driving ship is equipped with a support beam at the stern and a living area at the bow, and its innovative points are: including: S1. Barge the pile-driving ship into the dock; S2. Install a high hinged ear plate on the top of the support beam of the pile-driving ship, install a transfer beam on the bottom of the support beam, install a high support frame between the living area and the support beam and close to the support beam on the pile-driving ship, close the reference support frame between the living area and the high support frame, and install a second support frame on the top of the living area; S3, the pile frame is divided into two sections, the first section includes the pile frame head and the pile frame body, and the second section is the pile frame foot. Three first temporary platforms are installed at one end of the pile frame foot connected to the pile frame body; S4. Use a 500T gantry crane to hoist the second section of the pile frame onto the high-hinged lug plate and transfer beam on the pile-driving ship; S5. Use a 500T gantry crane to hoist the first section of the pile frame onto the second bracket and the closing reference support frame, and place the bottom connection side of the pile frame body on the three first temporary platforms and align it with the pile frame foot for closing; (For the segmented closing, a pallet should be made on the gantry and the side pipe, and a sample punch mark should be made to facilitate the closing and inspection on board.) S6. Debug and fix the first and second pile frames to complete the installation of the pile frames on the piling ship.
[0005] Furthermore, in S5, when the overall weight of the first section of the pile frame is not less than 800 tons, it is necessary to first use a 500T gantry crane to install the pile frame body, and then align the pile frame head with the pile frame body and install them; when the overall weight of the first pile frame is less than 800 tons, the pile frame head is installed on the pile frame body in advance to obtain the first pile frame, and then the obtained first pile frame is hoisted together with the second section of the pile frame by using a gantry crane.
[0006] Furthermore, two permanent platforms are installed on one end of the pile frame body connected to the pile frame head.
[0007] Furthermore, during the alignment and closing process of the first and second pile frames, the adjustment of the side pipes of the pile frame installed later (i.e., the first pile frame) is mainly performed, and the adjustment of the side pipes of the pile frame installed earlier (i.e., the second pile frame) is supplemented, and both the main and auxiliary methods are used.
[0008] Furthermore, when the side pipes of the pile frame are butted, they are first slowly inserted into the guide plate, and then the gantry crane is adjusted and the precise positioning pins are driven in.
[0009] Furthermore, the pile frame foot is assembled on a unified stand to ensure closing accuracy.
[0010] Furthermore, the side of the pile frame close to the hull is set as the rear side, and the side away from the hull is set as the front side, a high connecting ear plate is installed on the front side of the pile frame foot, a supporting section is installed on the rear side of the pile frame body close to one end of the pile frame head, and a hydraulic cylinder slide rail is laid between the front side of the pile frame body and the rear side of the pile frame foot; The second bracket includes a support platform, which is installed on the top of the living area through a support frame and just accommodates the support section.
[0011] Furthermore, the support platform is U-shaped, including a bottom plate and two side limit plates; A rectangular groove is provided on the bottom side of the pile frame body to accommodate the support platform portion, and the inclination of the rectangular groove is consistent with the inclination of the bottom side of the pile frame body; The support section includes a top fixing block, a middle vertical connecting block and a bottom gasket which are arranged in sequence from top to bottom, and the top fixing block is obliquely fixed on the inner wall of the rectangular groove, and the middle vertical connecting block and the bottom gasket are placed in the support platform.
[0012] The advantages of the present invention are: In the present invention, the pile frame is divided into two parts, namely, a first pile frame and a second pile frame, according to weight, and the two parts are hoisted on board a ship for aerial closure and docking. After the ship is launched, the dock pile frame can be debugged, thus eliminating the cost of floating crane hoisting and dispatching, being more economical and environmentally friendly, and solving the problem that a general dock cannot be hoisted as a whole and an extra-large pile frame is difficult to install in a dock. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] Figure 1 It is a stereogram of the present invention.
[0014] Figure 2 It is a top view of the present invention.
[0015] Figure 3It is a state structure schematic diagram of the present invention.
[0016] Figure 4 It is a state structure schematic diagram of the present invention.
[0017] Figure 5 It is a schematic diagram of the pile frame structure of the present invention. DETAILED DESCRIPTION
[0018] In order to further explain the technical means and effects adopted by the present invention to achieve the predetermined invention purpose, the specific implementation mode, structure, characteristics and effects of the present invention are described in detail below in combination with the accompanying drawings and preferred embodiments.
[0019] The pile frame 1 of the pile-driving ship is heavy, and the total weight after the equipment exceeds 1300 tons. A support beam 2 is installed at the stern of the pile-driving ship, and a living area is provided at the bow. The pile frame 1 is divided into two sections, such as Figure 5 As shown, the first section includes a pile frame head 11 and a pile frame body 12, and the second section is a pile frame foot 13. The pile frame foot 13 is assembled on a unified stand to ensure closing accuracy.
[0020] The side of the pile frame 1 close to the hull is set as the rear side, and the side away from the hull is set as the front side. A high connecting ear plate is installed on the front side of the pile frame foot 13, and a supporting section is installed on the rear side of the pile frame body 12 close to one end of the pile frame head 11. A hydraulic cylinder slide rail is laid between the front side of the pile frame body 12 and the rear side of the pile frame foot 13.
[0021] The support section includes a top fixing block, a middle vertical connecting block and a bottom gasket which are arranged in sequence from top to bottom, and the top fixing block is obliquely fixed on the inner wall of the rectangular groove, and the middle vertical connecting block and the bottom gasket are placed in the support platform.
[0022] In this embodiment, the weights of the pile frame head 11, the pile frame body 12 and the pile frame foot 13 are 200 tons, 500 tons and 350 tons respectively. The pile frame body 12 is also installed with 35 tons of outfitting parts and a 55-ton pulley block. The pile frame foot 13 is also installed with 25 tons of outfitting parts, 5 tons of piping, 5 tons of winch, 60 tons of pile gripper and 10 tons of plug-in pins.
[0023] A process for closing a pile frame 1 of a pile driving ship in mid-air comprises the following steps: S1. Barge the pile-driving barge into the dock.
[0024] S2. A high hinged ear plate is installed on the top of the supporting beam 2 of the pile-driving ship, and a transfer beam 6 is installed on the bottom of the supporting beam 2. The transfer beam 6 can bear 350 tons. A high support frame 4 is installed between the living area and the supporting beam 2 and close to the supporting beam 2 on the pile-driving ship. The high support frame 4 can bear 80 tons. A closing reference support frame 5 is installed between the living area and the high support frame 4. The closing reference support frame 5 can bear 80 tons. A second bracket 3 is installed on the top of the living area.
[0025] The second support 3 comprises a support platform, which is mounted on the top of the living area through a support frame and just accommodates the support section.
[0026] The support platform is U-shaped and includes a bottom plate and limiting plates on both sides.
[0027] A rectangular groove is provided on the bottom side of the pile frame body 12 to accommodate the support platform part extending therein, and the inclination of the rectangular groove is consistent with the inclination of the bottom side of the pile frame body 12 .
[0028] S3. Three first temporary platforms 14 are installed at one end of the pile frame foot 13 connected to the pile frame body 12, and two permanent platforms 15 are installed at one end of the pile frame body 12 connected to the pile frame head 11.
[0029] S4, such as Figure 1 As shown, the second section of the pile frame 1 is hoisted onto the high-hinged ear plate and the transfer beam 6 on the pile-driving ship by using a 500T gantry crane.
[0030] S5. Use two 500T gantry cranes to hoist the first section of the pile frame 1 (i.e., the pile frame body 12) onto the second bracket 3 and the closing reference support frame 5, and place the bottom connecting side of the pile frame body 12 in the three first temporary platforms 14 and align it with the pile frame foot 13 for closing. For the segmented closing, a clamping plate 7 should be made on the gantry and the side pipe, and a sample punching mark should be made to facilitate the closing use and inspection on board.
[0031] like Figure 3-4 As shown, there are four clamping plates 7 distributed around the side of the side pipe. The middle part of the inner side of the clamping plate 7 has an inwardly concave arc groove, and one end of the inner side of the clamping plate 7 has an inclined guide surface 8 to accommodate the insertion of the side pipe of the pile frame 1 installed later. A gap of 2 mm is left between the inwardly concave arc groove and the inclined guide surface 8 on the inner side of the clamping plate 7 and the side pipe, which can effectively reduce the centering error and improve the assembly accuracy.
[0032] When the overall weight of the first pile frame 1 is not less than 800 tons, it is necessary to first use a 500T gantry crane to install the pile frame body 12, and then align and close the pile frame head 11 with the pile frame body 12 for installation. When the overall weight of the first pile frame 1 is less than 800 tons, the pile frame head 11 is installed on the pile frame body 12 in advance to obtain the first pile frame 1, and then the obtained first pile frame 1 is hoisted together with the second pile frame 1 by using a gantry crane.
[0033] In this embodiment, the overall weight of the first section of the pile frame 1 (i.e., the pile frame head 11, the pile frame body 12, and the outfitting and pulley block on the pile frame body 12) is not less than 800 tons. It is necessary to first use a 500T gantry crane to install the pile frame body 12, and then align the pile frame head 11 and the pile frame body 12 for installation. Figure 2 shown.
[0034] S6. Debugging and fixing the first section pile frame 1 and the second section pile frame 1 to complete the installation of the pile frame 1 on the piling ship.
[0035] During the alignment and closing process of the first and second pile frames 1, the adjustment of the side pipe of the pile frame 1 installed later (i.e., the first pile frame 1) is mainly performed, and the adjustment of the side pipe of the pile frame 1 installed earlier (i.e., the second pile frame 1) is supplemented, and both the main and auxiliary methods are used.
[0036] When the side pipe of the pile frame 1 is butted, it is first slowly inserted into the guide plate, and then the gantry crane is adjusted and the precise positioning pin is driven in.
[0037] The above description is only a preferred embodiment of the present invention and does not limit the present invention in any form. Although the present invention has been disclosed as a preferred embodiment as above, it is not used to limit the present invention. Any technical personnel in this field can make some changes or modify the technical contents disclosed above into equivalent embodiments without departing from the scope of the technical solution of the present invention. However, any brief modifications, equivalent changes and modifications made to the above embodiments based on the technical essence of the present invention without departing from the content of the technical solution of the present invention are still within the scope of the technical solution of the present invention.
Claims
1. A pile closure process in the air of a pile driving ship, wherein a support beam is installed at the stern of the pile driving ship and a living area is provided at the bow, characterized in that: include S1. Barge the pile-driving ship into the dock; S2. Install a high hinged ear plate on the top of the support beam of the pile-driving ship, install a transfer beam on the bottom of the support beam, install a high support frame between the living area and the support beam and close to the support beam on the pile-driving ship, close the reference support frame between the living area and the high support frame, and install a second support frame on the top of the living area; S3, the pile frame is divided into two sections, the first section includes the pile frame head and the pile frame body, and the second section is the pile frame foot, and a first temporary platform is installed at one end of the pile frame foot connected to the pile frame body; S4, hoisting the second section of the pile frame onto the high hinged lug plate and the transfer beam on the pile driving ship; S5, hoisting the first section of the pile frame on the second bracket and the closing reference support frame, and placing the bottom connection side of the pile frame body in the first temporary platform and aligning it with the pile frame foot for closing; S6. Debug and fix the first and second pile frames to complete the installation of the pile frames on the piling ship.
2. The process for assembling piles in mid-air by a pile-driving ship according to claim 1, characterized in that: In S5, when the overall weight of the first section of the pile frame is not less than 800 tons, it is necessary to first use a 500T gantry crane to install the pile frame body, and then align the pile frame head with the pile frame body and install them together; when the overall weight of the first pile frame is less than 800 tons, the pile frame head is installed on the pile frame body in advance to obtain the first pile frame, and then the obtained first pile frame is hoisted together with the second section of the pile frame by using a gantry crane.
3. The process for assembling piles in mid-air by a pile-driving ship according to claim 2, characterized in that: A permanent platform is installed at one end of the pile frame body connected to the pile frame head.
4. The process for assembling piles in mid-air by a pile-driving ship according to claim 1, characterized in that: During the alignment and closing process of the first-stage pile frame and the second-stage pile frame, the adjustment of the side pipe of the pile frame installed later is mainly carried out, and the adjustment of the side pipe of the pile frame installed earlier is supplemented, and both the main and auxiliary methods are used.
5. The process for assembling piles in mid-air by a pile-driving ship according to claim 1, characterized in that: When the side pipes of the pile frame are butt-jointed, they are first slowly inserted into the guide plate, and then the gantry crane is adjusted and the precise positioning pins are driven in.
6. The process for assembling piles in mid-air by a pile-driving ship according to claim 1, characterized in that: The pile frame foot is assembled on a unified stand to ensure closing accuracy.
7. The process for assembling piles in mid-air by a pile-driving ship according to claim 1, characterized in that: The side of the pile frame close to the hull is set as the rear side, and the side away from the hull is set as the front side. A high connecting ear plate is installed on the front side of the pile frame foot, a supporting section is installed on the rear side of the pile frame body close to one end of the pile frame head, and a hydraulic cylinder slide rail is laid between the front side of the pile frame body and the rear side of the pile frame foot. The second bracket includes a support platform, which is installed on the top of the living area through a support frame and just accommodates the support section.
8. The process for assembling piles in mid-air by a pile-driving ship according to claim 7, characterized in that: The support platform is U-shaped and includes a bottom plate and two side limit plates; A rectangular groove is provided on the bottom side of the pile frame body to accommodate the support platform portion, and the inclination of the rectangular groove is consistent with the inclination of the bottom side of the pile frame body; The support section includes a top fixing block, a middle vertical connecting block and a bottom gasket which are arranged in sequence from top to bottom, and the top fixing block is obliquely fixed on the inner wall of the rectangular groove, and the middle vertical connecting block and the bottom gasket are placed in the support platform.