Rural sewage treatment construction management method and system based on node management
Through the construction management method based on node management, the problem of dispersed construction sites of rural sewage treatment projects is solved, efficient construction management and coordination is achieved, and construction efficiency and quality control are improved.
Patent Information
- Application Number
- CN202411669826.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-21
- Publication Date
- 2025-01-10
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The construction sites of rural sewage treatment projects are scattered, which makes it difficult to cover supervision and control quality results, and it is difficult to efficiently manage and coordinate rural sewage treatment projects in existing technologies.
Adopt construction management methods based on node management to obtain construction location information, material entry information and acceptance standards of construction projects, determine the material entry sampling route and acceptance route, conduct material sampling, acceptance and re-inspection to achieve efficient raw material scheduling and Construction inspection.
The construction management and coordination effect of rural sewage projects has been improved, the material transfer efficiency and construction acceptance efficiency have been ensured, and the continuous construction period and manpower and material costs have been reduced.
Smart Images

Figure CN119295017A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of construction management, and more specifically, to a rural sewage treatment construction management method and system based on node management. Background Art
[0002] With the rapid development of the rural economy, the concentration of rural population and the improvement of living standards, the amount of sewage discharged has increased year by year. However, many rural areas lack systematic sewage treatment facilities and management systems, resulting in sewage being directly discharged into rivers, lakes and other water bodies, causing water pollution, ecological damage and public health hazards. In recent years, rural sewage treatment technology has gradually developed. Rural sewage treatment can not only improve the rural environment and protect water resources, but also improve the quality of life of rural residents.
[0003] Rural sewage treatment projects require site preparation before construction, which includes cleaning the construction site, excavating earthwork, preparing foundations and soil stabilization measures. During the pipeline laying phase, the sewage pipeline network needs to be laid according to the design requirements, including the laying of sewage collection pipes, drainage pipes and other pipes, and it is necessary to ensure that the pipe joints are well sealed to avoid leakage. In the construction of sewage treatment facilities, the construction team needs to build sewage treatment tanks, sedimentation tanks, aeration tanks and other facilities according to the design drawings. At the same time, necessary supporting facilities such as pump rooms and electric control rooms need to be set up. At the same time, sewage treatment equipment such as pumps, filters, aeration equipment and monitoring instruments need to be installed. The construction sites of rural sewage projects are scattered, and there are problems such as difficult supervision coverage and difficult quality results control. Existing technologies make it difficult to carry out efficient management and coordination of rural sewage treatment projects. Summary of the invention
[0004] The purpose of this application is to provide a rural sewage treatment construction management method and system based on node management, which solves the technical problem of difficulty in efficient rural sewage treatment project management and coordination, and achieves the technical effect of efficient rural sewage treatment project management and coordination.
[0005] An embodiment of the present application provides a rural sewage treatment construction management method based on node management, the method comprising: obtaining construction location information, material entry information, construction node process acceptance standards and construction node content acceptance standards for multiple construction projects; determining a material entry sampling route based on the construction location information of the multiple construction projects, performing material entry sampling, unqualified material transfer, construction node process acceptance according to the construction node process acceptance standards and construction node content acceptance according to the construction node content acceptance standards for multiple construction projects according to the material entry sampling route, and obtaining construction node process acceptance results and construction node content acceptance results; determining a re-inspection route for construction node process acceptance and construction node content acceptance based on the construction location information, construction node process acceptance results and construction node content acceptance results of the multiple construction projects.
[0006] In a possible implementation, a material sampling inspection route is determined based on construction location information of multiple construction projects, including: based on the construction location information of multiple construction projects, the material sampling inspection route is determined based on the shortest route as a planning principle.
[0007] In another possible implementation, determining the material on-site sampling route based on the construction location information of multiple construction projects also includes: obtaining the construction process information and current construction nodes of the multiple construction projects, and determining the material on-site sampling route according to the order of the current construction nodes of the multiple construction projects in the construction process information.
[0008] In another possible implementation, based on the construction location information, construction node process acceptance results and construction node content acceptance results of multiple construction projects, the re-inspection routes for the construction node process acceptance and the construction node content acceptance are determined, including: obtaining multiple first construction location information of multiple first construction projects whose construction node process acceptance results are unqualified, and determining the re-inspection route for the construction node process acceptance based on the multiple first construction location information and the shortest route as the planning principle; obtaining multiple second construction location information of multiple second construction projects whose construction node content acceptance results are unqualified, and determining the re-inspection route for the construction node content acceptance based on the multiple second construction location information and the shortest route as the planning principle.
[0009] In another possible implementation, based on the construction location information, the construction node process acceptance results and the construction node content acceptance results of multiple construction projects, determining the re-inspection route for the construction node process acceptance and the construction node content acceptance also includes: obtaining multiple first construction location information of multiple first construction projects whose construction node process acceptance results are unqualified, and obtaining the first construction process information and the first current construction node of the multiple first construction projects, determining the re-inspection route for the construction node process acceptance according to the sequence of the multiple first construction location information and the first current construction nodes of the multiple first construction projects in the first construction process information, and performing material replenishment and transportation in the construction process correction according to the re-inspection route for the construction node process acceptance; obtaining multiple second construction location information of multiple second construction projects whose construction node content acceptance results are unqualified, and obtaining the second construction process information and the second current construction nodes of the multiple second construction projects, determining the re-inspection route for the construction node content acceptance according to the sequence of the multiple second construction location information and the second current construction nodes of the multiple second construction projects in the second construction process information, and performing material replenishment and transportation in the construction content correction according to the re-inspection route for the construction node content acceptance.
[0010] In another possible implementation, based on the construction location information, construction node process acceptance results and construction node content acceptance results of multiple construction projects, the re-inspection routes for the construction node process acceptance and the construction node content acceptance are determined, which also includes: determining multiple third construction projects among the multiple first construction projects corresponding to the re-inspection route for the construction node process acceptance, there is no need for material replenishment and transfer between the current third current construction nodes of the multiple third construction projects and the first current construction nodes of other first construction projects, and the multiple third construction projects are placed at the end of the re-inspection route for the construction node process acceptance; determining multiple fourth construction projects among the multiple second construction projects corresponding to the re-inspection route for the construction node content acceptance, there is no need for material replenishment and transfer between the fourth current construction nodes of the multiple fourth construction projects and the second current construction nodes of other second construction projects, and the multiple fourth construction projects are placed at the end of the re-inspection route for the construction node content acceptance.
[0011] In another possible implementation, the method also includes: dividing multiple construction projects into multiple construction nodes according to natural days, and determining the construction node process acceptance standard and the construction node content acceptance standard for each construction node; obtaining the construction node process acceptance results and the construction node content acceptance results corresponding to each construction node according to natural days, determining the number of construction nodes with abnormal process acceptance according to the construction node process acceptance results, and determining the number of construction nodes with abnormal content acceptance according to the construction node content acceptance results, and visually displaying the total number of construction nodes, the number of construction nodes with abnormal process acceptance, and the number of construction nodes with abnormal content acceptance according to natural days through a background program; when the number of construction nodes with abnormal process acceptance or the number of construction nodes with abnormal content acceptance on the first natural day is greater than a preset number, for each construction node corresponding to the first natural day, determine the natural day re-inspection route based on the construction location information of multiple construction projects and the shortest route as the planning principle, and re-inspect each construction node on the first natural day according to the natural day re-inspection route.
[0012] An embodiment of the present application also provides a rural sewage treatment construction management system based on node management, including a unit for executing any of the methods described above.
[0013] An embodiment of the present application also provides a rural sewage treatment construction management system based on node management, including a memory, a processor, and a computer program stored in the memory and executable on the processor, and when the processor executes the computer program, it implements any of the methods described above.
[0014] An embodiment of the present application further provides a computer-readable storage medium, wherein the computer-readable storage medium stores a computer program, and when the computer program is executed by a processor, the method described in any one of the above items is implemented.
[0015] An embodiment of the present application also provides a computer program product, including a computer program, which implements the steps of any of the methods described above when executed by a processor.
[0016] Compared with the prior art, the embodiments of the present invention have the following beneficial effects:
[0017] The embodiment of the present application provides a rural sewage treatment construction management method based on node management, and the method includes: obtaining the construction location information, material entry information, construction node process acceptance criteria and construction node content acceptance criteria of multiple construction projects; according to the construction location information of multiple construction projects, determining the material entry sampling route, performing material entry sampling, unqualified material transfer, construction node process acceptance according to the construction node process acceptance criteria and construction node content acceptance according to the construction node content acceptance criteria for multiple construction projects, and obtaining the construction node process acceptance result and the construction node content acceptance result; according to the construction location information, construction node process acceptance results and construction node content acceptance results of multiple construction projects, determining the re-inspection route of construction node process acceptance and construction node content acceptance. The embodiment of the present application can determine the material entry sampling route according to the construction location information of multiple construction projects, and perform construction node process acceptance and construction node content acceptance, and obtain the construction node process acceptance result and construction node content acceptance result, and can perform efficient raw material scheduling and construction inspection on multiple construction projects, thereby improving the construction management and coordination effect of rural sewage projects. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] In order to more clearly illustrate the technical solutions in the embodiments of the present application, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.
[0019] Figure 1 A schematic diagram of a process flow of a rural sewage treatment construction management method based on node management provided in an embodiment of the present application;
[0020] Figure 2 A schematic diagram of an App interface for material on-site sampling provided in an embodiment of the present application;
[0021] Figure 3 A schematic diagram of an App interface for material on-site sampling processing provided in an embodiment of the present application;
[0022] Figure 4 A schematic diagram of an App interface for construction node content acceptance provided in an embodiment of the present application;
[0023] Figure 5 A schematic diagram of an App interface for construction node process acceptance provided in an embodiment of the present application;
[0024] Figure 6A schematic diagram of an App interface for a re-inspection route for acceptance of a construction node process provided in an embodiment of the present application;
[0025] Figure 7 A schematic diagram of the logical structure of a rural sewage treatment construction management system based on node management provided in an embodiment of the present application;
[0026] Figure 8 A schematic diagram of the physical structure of a rural sewage treatment construction management system based on node management provided in an embodiment of the present application. DETAILED DESCRIPTION
[0027] It should be understood that when used in the present specification and the appended claims, the term "comprising" indicates the presence of described features, wholes, steps, operations, elements and / or components, but does not exclude the presence or addition of one or more other features, wholes, steps, operations, elements, components and / or combinations thereof.
[0028] It should also be understood that the term “and / or” used in the specification and appended claims refers to any and all possible combinations of one or more of the associated listed items, and includes these combinations.
[0029] As used in the specification and appended claims of this application, the term "if" can be interpreted as "when" or "uponce" or "in response to determining" or "in response to detecting", depending on the context. Similarly, the phrase "if it is determined" or "if [described condition or event] is detected" can be interpreted as meaning "uponce it is determined" or "in response to determining" or "uponce [described condition or event] is detected" or "in response to detecting [described condition or event]", depending on the context.
[0030] In addition, in the description of the present application specification and the appended claims, the terms "first", "second", "third", etc. are only used to distinguish the descriptions and cannot be understood as indicating or implying relative importance.
[0031] References to "one embodiment" or "some embodiments" etc. described in the specification of this application mean that one or more embodiments of the present application include specific features, structures or characteristics described in conjunction with the embodiment. Therefore, the statements "in one embodiment", "in some embodiments", "in some other embodiments", "in some other embodiments", etc. that appear in different places in this specification do not necessarily refer to the same embodiment, but mean "one or more but not all embodiments", unless otherwise specifically emphasized in other ways. The terms "including", "comprising", "having" and their variations all mean "including but not limited to", unless otherwise specifically emphasized in other ways.
[0032] In the existing technology, the construction sites of rural sewage projects are scattered, and there are problems such as difficulty in supervision and difficulty in controlling quality results. The existing technology makes it difficult to carry out efficient management and coordination of rural sewage treatment projects.
[0033] Based on the above reasons, the embodiment of the present application provides a rural sewage treatment construction management method based on node management, and the method includes: obtaining the construction location information, material entry information, construction node process acceptance criteria and construction node content acceptance criteria of multiple construction projects; according to the construction location information of multiple construction projects, determining the material entry sampling route, performing material entry sampling, unqualified material transfer, construction node process acceptance according to the construction node process acceptance criteria and construction node content acceptance according to the construction node content acceptance criteria for multiple construction projects, and obtaining the construction node process acceptance result and the construction node content acceptance result; according to the construction location information, construction node process acceptance results and construction node content acceptance results of multiple construction projects, determining the re-inspection route of construction node process acceptance and construction node content acceptance. The embodiment of the present application can determine the material entry sampling route according to the construction location information of multiple construction projects, and perform construction node process acceptance and construction node content acceptance, and obtain the construction node process acceptance result and construction node content acceptance result, and can efficiently dispatch raw materials and conduct construction inspections on multiple construction projects, thereby improving the construction management and coordination effect of rural sewage projects.
[0034] In some scenarios, a rural sewage treatment construction management method based on node management in an embodiment of the present application can be applied to the management of rural sewage treatment projects, and can efficiently manage and coordinate rural sewage treatment projects.
[0035] The following is a detailed description of a rural sewage treatment construction management method based on node management provided in an embodiment of the present application with reference to specific examples.
[0036] Figure 1 A flowchart of a rural sewage treatment construction management method based on node management provided in an embodiment of the present application is shown in FIG. Figure 1 As shown, the method includes S110 to S130, and S110 to S130 are described in detail below.
[0037] S110, obtaining construction location information, material entry information, construction node process acceptance criteria, and construction node content acceptance criteria for multiple construction projects.
[0038] In the construction of rural sewage treatment projects, multiple sewage treatment projects are often carried out simultaneously in a large area, and the locations of multiple rural sewage treatment projects are far apart. Therefore, when managing multiple construction projects, the construction location information of multiple construction projects can be obtained, and then the multiple construction projects can be managed according to the construction location information of multiple construction projects.
[0039] For example, when managing multiple construction projects, the multiple construction projects may be located in multiple different villages within the same area. The construction sites of multiple rural sewage projects in multiple different villages are scattered, resulting in problems such as difficulty in supervision and difficulty in controlling quality results.
[0040] When conducting construction project management, you can also obtain material entry information, construction node process acceptance standards and construction node content acceptance standards for multiple construction projects, and then manage the construction projects based on the material entry information, construction node process acceptance standards and construction node content acceptance standards.
[0041] S120. Determine the material entry sampling route based on the construction location information of multiple construction projects, conduct material entry sampling for multiple construction projects based on the material entry sampling route, transfer unqualified materials, conduct construction node process acceptance according to the construction node process acceptance standards, and conduct construction node content acceptance according to the construction node content acceptance standards, and obtain construction node process acceptance results and construction node content acceptance results.
[0042] When managing multiple construction projects, the material entry inspection route can be determined based on the construction location information of multiple construction projects, so as to achieve scientific planning of the material entry inspection route. After determining the material entry inspection route, the material entry inspection and unqualified material transfer can be carried out for multiple construction projects based on the material entry inspection route. When the material entry inspection is carried out according to the material entry inspection route, unqualified materials can be determined and then transferred.
[0043] Figure 2 A schematic diagram of an App interface for material on-site sampling provided in an embodiment of the present application, such as Figure 2 As shown, the method in the embodiment of the present application can be run on an App on a mobile terminal (such as a mobile phone). When a material on-site sampling inspection is performed on multiple construction projects according to the material on-site sampling inspection route, a material on-site sampling inspection can be performed on multiple construction projects, such as Figure 2 As shown in Figure a, a written record of the material incoming inspection can be made, such as Figure 2 As shown in Figure b, image records can be made for random inspection of incoming materials.
[0044] Figure 3A schematic diagram of an App interface for material on-site sampling processing provided in an embodiment of the present application, such as Figure 3 As shown in Figure a, qualified materials can be recorded in a timely manner, such as Figure 3 As shown in Figure b, unqualified materials can be cleared away in a timely manner. When unqualified materials are cleared away in a timely manner, the materials can be cleared away in a timely manner according to the scientifically planned material entry sampling route.
[0045] When conducting material entry sampling inspection according to the material entry sampling inspection route, construction node process acceptance can be carried out according to the construction node process acceptance standards, and construction node content acceptance can be carried out according to the construction node content acceptance standards at the same time, and the construction node process acceptance results and construction node content acceptance results can be obtained to realize the acceptance of construction processes and construction content.
[0046] S130. Determine re-inspection routes for the construction node process acceptance and the construction node content acceptance according to the construction location information, the construction node process acceptance results and the construction node content acceptance results of the plurality of construction projects.
[0047] After obtaining the construction node process acceptance results and the construction node content acceptance results, the re-inspection routes for the construction node process acceptance and the construction node content acceptance can be determined according to the construction location information of multiple construction projects, the construction node process acceptance results and the construction node content acceptance results. The re-inspection routes can be scientifically planned in combination with the construction location information of multiple construction projects, which can improve the efficiency of subsequent re-inspections of the construction node process acceptance and the construction node content acceptance.
[0048] Figure 4 A schematic diagram of an App interface for construction node content acceptance provided in an embodiment of the present application, such as Figure 4 As shown in Figure a, the result of the construction node content acceptance may be that the construction method of the diversion channel is incorrect, such as Figure 4 As shown in Figure b, the construction node content can be passed after re-inspection during acceptance.
[0049] Figure 5 A schematic diagram of an App interface for construction node process acceptance provided in an embodiment of the present application, such as Figure 5 As shown in Figure a, the construction process can be inspected and accepted according to a specific process sequence, such as Figure 5 As shown in Figure b, the construction process can be accepted according to the main control items and on-site photos.
[0050] The beneficial effect brought about by the above-mentioned implementation method is that after the material entry sampling route is scientifically planned according to the construction location information of multiple construction projects, when the material entry sampling route is carried out, unqualified materials can be determined, and then the unqualified materials can be transported according to the optimal route, which can improve the transportation efficiency of unqualified materials.
[0051] The beneficial effect brought about by the above-mentioned implementation method is that when conducting material entry sampling inspection according to the material entry sampling route, the construction node process acceptance can be carried out according to the construction node process acceptance standards and the construction node content acceptance can be carried out according to the construction node content acceptance standards, thereby improving the acceptance of construction processes and construction contents, and improving the acceptance efficiency of construction processes and construction contents.
[0052] In some implementations, in the above S120, based on the construction location information of multiple construction projects, the material on-site inspection route is determined, including: based on the construction location information of multiple construction projects, the material on-site inspection route is determined with the shortest route as the planning principle.
[0053] When planning the route for random inspection of materials entering the site, the route for random inspection of materials entering the site can be determined based on the construction location information of multiple construction projects and the shortest route as the planning principle. This can shorten the route for random inspection of materials entering the site and construction acceptance to the greatest extent and improve the efficiency of construction acceptance.
[0054] The beneficial effect brought about by the above-mentioned implementation method is that it can shorten the route of material on-site sampling and construction acceptance to the greatest extent, and improve the efficiency of material transportation and construction acceptance.
[0055] In some implementations, in the above S110, the material inspection route is determined based on the construction location information of multiple construction projects, and the construction process information and current construction nodes of the multiple construction projects are obtained, and the material inspection route is determined according to the sequence of the current construction nodes of the multiple construction projects in the construction process information.
[0056] When planning the material entry sampling route, the construction process information and current construction nodes of multiple construction projects can be obtained. The multiple construction projects can be construction projects of the same type. The construction process information may include multiple construction nodes arranged in a specific order. The current construction node of the construction project corresponds to a certain ongoing construction step in the construction process information of the construction project.
[0057] After obtaining the construction process information and current construction nodes of multiple construction projects, the material entry sampling route can be determined according to the sequence of the current construction nodes of the multiple construction projects in the construction process information, and then the material entry sampling can be carried out in multiple construction projects according to the construction sequence of the current construction nodes of different construction projects.
[0058] Exemplarily, for construction projects A, B and C of the same type, the current construction node A1, B1 and C1 of the construction projects A, B and C of the same type respectively in progress can be obtained. When the order of the current construction node A1, B1 and C1 in the construction process information is the current construction node C1, the current construction node A1 and the current construction node B1, the material entry sampling route can be determined in the order of construction project C, construction project A and construction project B.
[0059] The beneficial effect brought about by the above-mentioned implementation method is that after obtaining the construction process information and current construction nodes of multiple construction projects, the material entry sampling route can be determined according to the sequence of the current construction nodes of the multiple construction projects in the construction process information, and the material transfer and replenishment can be given priority to the construction projects with lagging construction progress, thereby improving the construction efficiency of rural sewage treatment projects.
[0060] The beneficial effect brought about by the above-mentioned implementation method is that the material entry sampling route can be determined according to the sequence of the current construction nodes of multiple construction projects in the construction process information, which can timely reduce the material transfer volume of the current construction node, reduce the material transfer cost, and improve construction efficiency.
[0061] The beneficial effect brought about by the above-mentioned implementation method is that, according to the sequence of the current construction nodes of multiple construction projects in the construction process information, the material entry sampling route is determined, and the construction node process acceptance is carried out according to the construction node process acceptance standards and the construction node content acceptance is carried out according to the construction node content acceptance standards. This improves the efficiency of construction node process acceptance and construction node content acceptance for construction projects with lagging progress, improves the overall advancement speed of multiple construction projects in the same area, reduces the continuous construction period of multiple construction projects in the same area, and greatly saves manpower and material costs.
[0062] In some implementations, in the above S130, based on the construction location information of multiple construction projects, the acceptance results of the construction node process, and the acceptance results of the construction node content, determining the re-inspection routes for the construction node process acceptance and the construction node content acceptance includes: obtaining multiple first construction location information of multiple first construction projects whose acceptance results of the construction node process are unqualified, and determining the re-inspection routes for the construction node process acceptance based on the multiple first construction location information and the shortest route as the planning principle. Obtaining multiple second construction location information of multiple second construction projects whose acceptance results of the construction node content are unqualified, and determining the re-inspection routes for the construction node content acceptance based on the multiple second construction location information and the shortest route as the planning principle.
[0063] After obtaining the construction node process acceptance results, multiple first construction location information of multiple first construction projects whose construction node process acceptance results are unqualified can be obtained. According to the multiple first construction location information and with the shortest route as the planning principle, the re-inspection route for the construction node process acceptance can be determined, thereby shortening the distance for re-inspection of the construction node process acceptance and improving the re-inspection efficiency of the construction node process acceptance.
[0064] After obtaining the construction node content acceptance results, multiple second construction location information of multiple second construction projects whose construction node content acceptance results are unqualified can be obtained. According to the multiple second construction location information and with the shortest route as the planning principle, the re-inspection route for the construction node content acceptance can be determined, thereby shortening the distance for re-inspection of the construction node content acceptance and improving the re-inspection efficiency of the construction node content acceptance.
[0065] The beneficial effect brought about by the above-mentioned implementation method is that, based on the shortest route as the planning principle, the re-inspection route of the construction node process acceptance and the re-inspection route of the construction node content acceptance are shortened, thereby shortening the distance for re-inspection of the construction node process acceptance and the re-inspection of the construction node content acceptance, thereby greatly improving the construction efficiency.
[0066] The beneficial effect brought about by the above-mentioned implementation method is that it can dynamically plan the re-inspection routes for the acceptance of construction node processes and the re-inspection routes for the acceptance of construction node contents, thereby improving the efficiency of acceptance of multiple construction projects and increasing the advancement speed of construction projects.
[0067] In some implementations, in the above S130, the re-inspection routes for the acceptance of the construction node process and the acceptance of the construction node content are determined based on the construction location information, the acceptance results of the construction node process, and the acceptance results of the construction node content of the multiple construction projects, and further include: obtaining multiple first construction location information of multiple first construction projects whose acceptance results of the construction node process are unqualified, and obtaining the first construction process information and the first current construction node of multiple first construction projects, determining the re-inspection route for the acceptance of the construction node process according to the sequence of the multiple first construction location information and the first current construction nodes of multiple first construction projects in the first construction process information, and supplementing and transferring materials in the correction of the construction process according to the re-inspection route for the acceptance of the construction node process. Obtaining multiple second construction location information of multiple second construction projects whose acceptance results of the construction node content are unqualified, and obtaining the second construction process information and the second current construction nodes of multiple second construction projects, determining the re-inspection route for the acceptance of the construction node content according to the sequence of the multiple second construction location information and the second current construction nodes of multiple second construction projects in the second construction process information, and supplementing and transferring materials in the correction of the construction content according to the re-inspection route for the acceptance of the construction node content.
[0068] When planning the re-inspection route for the construction node process acceptance, multiple first construction location information of multiple first construction projects with unqualified construction node process acceptance results can be obtained, and the first construction process information and the first current construction node of the multiple first construction projects can be obtained. Then, the re-inspection route for the construction node process acceptance can be dynamically planned based on the first construction process information and the first current construction node of the multiple first construction projects.
[0069] When planning the re-inspection route for the acceptance of construction node processes, the re-inspection route for the acceptance of construction node processes can be determined based on multiple first construction location information and the order of the first current construction nodes of multiple first construction projects in the first construction process information, and the materials in the construction process correction can be supplemented and transported according to the re-inspection route for the acceptance of construction node processes, so as to give priority to correcting the construction process of the first construction node that lags behind in construction progress, thereby improving the coordination of the overall progress of multiple first construction projects.
[0070] Exemplarily, for the first construction project A, the first construction project B and the first construction project C whose construction node process acceptance results are unqualified, the first current construction node A1 in which the first construction project A is in progress, the first current construction node B1 in which the first construction project B is in progress and the first current construction node C1 in which the first construction project C is in progress can be obtained; when the order of the first current construction node A1, the first current construction node B1 and the first current construction node C1 in the construction process information is the first current construction node C1, the first current construction node A1 and the first current construction node B1, the material entry sampling route can be determined in the order of the first construction project C, the first construction project A and the first construction project B.
[0071] When planning the re-inspection route for the acceptance of the construction node content, multiple second construction location information of multiple second construction projects with unqualified acceptance results of the construction node content can be obtained, and the second construction process information and the second current construction nodes of the multiple second construction projects can be obtained. Then, the re-inspection route for the acceptance of the construction node process can be dynamically planned based on the second construction process information and the second current construction nodes of the multiple second construction projects.
[0072] When planning the re-inspection route for the acceptance of construction node contents, the re-inspection route for the acceptance of construction node contents can be determined based on the sequence of multiple second construction location information and the second current construction nodes of multiple second construction projects in the second construction process information, and the materials in the construction content correction can be supplemented and transported according to the re-inspection route for the acceptance of construction node contents, so as to give priority to correcting the construction process of the second construction nodes that lag behind in construction progress, thereby improving the coordination of the overall progress of multiple second construction projects.
[0073] Exemplarily, for the second construction project A, the second construction project B and the second construction project C whose construction node content acceptance results are unqualified, the second current construction node A1 in which the second construction project A is in progress, the second current construction node B1 in which the second construction project B is in progress, and the second current construction node C1 in which the second construction project C is in progress can be obtained. When the order of the second current construction node A1, the second current construction node B1 and the second current construction node C1 in the construction process information is the second current construction node C1, the second current construction node A1 and the second current construction node B1, the material entry sampling route can be determined in the order of the second construction project C, the second construction project A and the second construction project B.
[0074] The beneficial effect brought about by the above implementation method is that, for the first construction project whose construction node process acceptance result is unqualified, the construction process of the first construction node with lagging construction progress is corrected first, thereby improving the coordination of the overall progress of multiple construction projects.
[0075] The beneficial effect brought about by the above implementation method is that, for the second construction project whose construction node content acceptance result is unqualified, the construction process of the second construction node with lagging construction progress is corrected first, thereby improving the coordination of the overall progress of multiple construction projects.
[0076] The beneficial effect brought about by the above-mentioned implementation method is that it can dynamically plan the re-inspection routes for the acceptance of construction node processes and the re-inspection routes for the acceptance of construction node contents, while ensuring the coordination of the construction progress of multiple construction projects, improving the uniformity of the construction progress of multiple construction projects, and improving the overall advancement speed of multiple construction projects in the same area. It reduces the continuous construction period of multiple construction projects in the same area, and greatly saves manpower and material costs.
[0077] In some implementations, in the above S130, based on the construction location information of multiple construction projects, the construction node process acceptance results, and the construction node content acceptance results, the re-inspection routes for the construction node process acceptance and the construction node content acceptance are determined, and the following is further included: determining multiple third construction projects among the multiple first construction projects corresponding to the re-inspection route for the construction node process acceptance, and there is no need for material replenishment and transfer between the current third current construction nodes of the multiple third construction projects and the first current construction nodes of other first construction projects, and placing the multiple third construction projects at the end of the re-inspection route for the construction node process acceptance. Determining multiple fourth construction projects among the multiple second construction projects corresponding to the re-inspection route for the construction node content acceptance, and there is no need for material replenishment and transfer between the fourth current construction nodes of the multiple fourth construction projects and the second current construction nodes of other second construction projects, and placing the multiple fourth construction projects at the end of the re-inspection route for the construction node content acceptance.
[0078] When planning the re-inspection route for the acceptance of construction node processes, after obtaining the re-inspection route for the acceptance of construction node processes, multiple third construction projects can also be determined among the multiple first construction projects corresponding to the re-inspection route for the acceptance of construction node processes. There is no need for material replenishment and transfer between the third current construction nodes of the multiple third construction projects and the first current construction nodes of other first construction projects, that is, the third current construction node of the third construction project does not have the need for material replenishment and transfer from other first current construction nodes. Therefore, the multiple third construction projects can be placed at the end of the re-inspection route for the acceptance of construction node processes.
[0079] Exemplarily, the third current construction node of the third construction project can be used to adjust the process of landfilling the pipeline. There is no need to replenish and transport materials when adjusting the process of landfilling the pipeline. Therefore, the third construction project can be placed at the end of the re-inspection route for the acceptance of the construction node process.
[0080] For example, when the first current construction node of the first construction project is to adjust the process of laying graphite sand on the top layer of the pipeline, there is a need to replenish and transport graphite sand materials when adjusting the process of laying graphite sand on the top layer of the pipeline. Therefore, the original sequence of the re-inspection route of the first construction project in the construction node process acceptance can be retained, which can ensure timely material replenishment and transportation of the first construction project, and can also ensure material replenishment and transportation from other first construction projects nearby.
[0081] Figure 6 A schematic diagram of an App interface for a re-inspection route for acceptance of a construction node process provided in an embodiment of the present application, such as Figure 6 As shown, when the re-inspection route for the acceptance of the construction node process is adjusted, the adjusted re-inspection route can be a plurality of construction items arranged in sequence from top to bottom.
[0082] When planning the re-inspection route for the acceptance of construction node content, multiple fourth construction projects can also be determined among the multiple second construction projects corresponding to the re-inspection route for the acceptance of construction node content. There is no need for material replenishment and transportation at the fourth current construction nodes of the multiple fourth construction projects and the second current construction nodes of other second construction projects, that is, the fourth current construction node of the fourth construction project does not have the need for material replenishment and transportation from other second current construction nodes, and thus the multiple fourth construction projects can be placed at the end of the re-inspection route for the acceptance of construction node content.
[0083] Exemplarily, the fourth current construction node of the fourth construction project can be used to adjust the construction content of pipe landfill. There is no need for material replenishment and transportation for the adjustment of the construction content of pipe landfill, and thus the fourth construction project can be placed at the end of the re-inspection route for the acceptance of the construction node content.
[0084] Exemplarily, the second current construction node of the second construction project can be used to adjust the construction content of replacing the pipeline. The adjustment of the construction content of replacing the pipeline requires material replenishment and transportation, and thus the original sequence of the second construction project in the re-inspection route of the construction node content acceptance can be retained, which can ensure timely material replenishment and transportation for the second construction project, and can also ensure material replenishment and transportation from other second construction projects nearby.
[0085] The beneficial effect brought about by the above-mentioned implementation method is that the third current construction node of the third construction project does not have the need to replenish and transfer materials from other first current construction nodes, and multiple third construction projects are placed at the end of the re-inspection route for construction node process acceptance, which avoids the re-inspection process of the third construction project affecting the material replenishment and transfer progress of other first construction projects, improves the re-inspection efficiency of the first construction project, and improves the advancement speed of multiple construction projects in the same area.
[0086] The beneficial effect brought about by the above-mentioned implementation method is that the fourth current construction node of the fourth construction project does not need to replenish and transfer materials from other second current construction nodes, and multiple fourth construction projects are placed at the end of the re-inspection route for construction node content acceptance, which avoids the re-inspection process of the fourth construction project affecting the material replenishment and transfer progress of other fourth construction projects, improves the re-inspection efficiency of the second construction project, and improves the advancement speed of multiple construction projects in the same area.
[0087] The beneficial effect brought about by the above-mentioned implementation method is that the re-inspection routes for the acceptance of construction node processes and the re-inspection routes for the acceptance of construction node contents are dynamically adjusted, thereby reducing the transportation costs of material transportation and replenishment and improving the progress of multiple construction projects in the same area.
[0088] In some implementations, the above method further includes S210 to S230, and S210 to S230 are described in detail below.
[0089] S210. Divide the multiple construction projects into multiple construction nodes according to natural days, and determine the construction node process acceptance standard and construction node content acceptance standard for each construction node.
[0090] At work, multiple construction projects can also be divided into multiple construction nodes according to natural days, and the construction node process acceptance standards and construction node content acceptance standards for each construction node can be determined, thereby realizing the management of workload and work progress according to natural days.
[0091] For example, the engineering design drawings can be used to decompose the construction quantities of primary and secondary pipelines and sites of multiple construction projects in multiple villages by natural days. Standard construction procedures and contents can be set for each day's quantity, and the achievement of the day's quantity target can be confirmed through acceptance of the construction procedures and contents.
[0092] S220. Obtain the construction node process acceptance results and construction node content acceptance results corresponding to each construction node according to natural days, determine the number of construction nodes with abnormal process acceptance according to the construction node process acceptance results, and determine the number of construction nodes with abnormal content acceptance according to the construction node content acceptance results, and visualize the total number of construction nodes, the number of construction nodes with abnormal process acceptance, and the number of construction nodes with abnormal content acceptance according to natural days through the background program.
[0093] When working, the acceptance results of the construction node process and the construction node content corresponding to each construction node can be obtained according to the natural day, and the acceptance results of the construction node process and the construction node content can be obtained.
[0094] During work, the number of construction nodes with abnormal process acceptance can be determined based on the construction node process acceptance results, and the number of construction nodes with abnormal content acceptance can be determined based on the construction node content acceptance results. Then, the abnormal status of work on the day can be counted based on the number of construction nodes with abnormal process acceptance and the number of construction nodes with abnormal content acceptance.
[0095] When working, the total number of construction nodes, the number of abnormal construction nodes for process acceptance, and the number of abnormal construction nodes for content acceptance can be visualized according to natural days through the background program, so as to realize the management and display of construction progress through the management background, realize daily progress management and abnormal node warning, and realize closed-loop management of rural sewage treatment project construction project nodes.
[0096] S230. When the number of abnormal construction nodes for process acceptance or the number of abnormal construction nodes for content acceptance on the first natural day is greater than the preset number, for each construction node corresponding to the first natural day, the natural day re-inspection route is determined based on the construction location information of multiple construction projects and the shortest route is used as the planning principle, and each construction node on the first natural day is re-inspected according to the natural day re-inspection route.
[0097] When conducting construction management, when the number of abnormal construction nodes for process acceptance or the number of abnormal construction nodes for content acceptance on the first natural day is greater than the preset number, it means that the number of abnormal construction nodes for process acceptance or the number of abnormal construction nodes for content acceptance on the first natural day is large, and there may be large-scale construction quality problems or implementation problems of the random inspection standards for the construction processes and construction contents corresponding to the first natural day. Therefore, random inspections can be carried out on the construction processes and construction contents corresponding to the first natural day to improve the accuracy of construction quality monitoring.
[0098] Exemplarily, the preset number may be 10% to 20% of the number of construction nodes on the first natural day.
[0099] For each construction node corresponding to the first natural day, the natural day re-inspection route can be determined based on the construction location information of multiple construction projects with the shortest route as the planning principle, and each construction node on the first natural day can be re-inspected according to the natural day re-inspection route. Furthermore, each construction node on the first natural day, including those with normal spot inspections, can be re-inspected to achieve a review of the construction quality of the first natural day and avoid large-scale construction quality problems or problems in the implementation of spot inspection standards.
[0100] The beneficial effect brought about by the above-mentioned implementation method is that when the number of abnormal construction nodes in process acceptance or content acceptance on a certain natural day is large, the construction quality of a certain natural day can be reviewed to avoid large-scale construction quality problems or problems in the implementation of random inspection standards.
[0101] The beneficial effect brought about by the above implementation method is that when reviewing the construction quality of a certain natural day, the natural day review route is determined based on the construction location information of multiple construction projects with the shortest route as the planning principle, thereby improving the efficiency of construction quality review.
[0102] An embodiment of the present application also provides a rural sewage treatment construction management system based on node management, including a unit for executing any of the methods described above.
[0103] Figure 7 A schematic diagram of the logical structure of a rural sewage treatment construction management system based on node management provided in an embodiment of the present application is shown in FIG. Figure 7 As shown, the system 1 of this embodiment includes a processing unit 11, a storage unit 12 and a transceiver unit 13, the processing unit 11 is used to process data, the storage unit 12 is used to store data, and the transceiver unit 13 is used to send and receive data, and the processing unit 11, the storage unit 12 and the transceiver unit 13 cooperate with each other to implement the above method. The beneficial effects brought about by the embodiment of the present application have been described in the above method, and will not be repeated here. The beneficial effects brought about by the embodiment of the present application have been described in the above method, and will not be repeated here.
[0104] An embodiment of the present application also provides a rural sewage treatment construction management system based on node management, including a memory, a processor, and a computer program stored in the memory and executable on the processor, and when the processor executes the computer program, it implements any of the methods described above.
[0105] Figure 8 A schematic diagram of the physical structure of a rural sewage treatment construction management system based on node management provided in an embodiment of the present application is shown in FIG. Figure 8 As shown, the system 2 of this embodiment includes: at least one processor 20 ( Figure 8 Only one processor 20 is shown in the figure), a memory 21, and a computer program 22 stored in the memory 21 and executable on the at least one processor 20. When the processor 20 executes the computer program 22, the steps in any of the above-mentioned method embodiments are implemented. The beneficial effects brought about by the embodiments of the present application have been described in the above-mentioned methods and will not be repeated here. The beneficial effects brought about by the embodiments of the present application have been described in the above-mentioned methods and will not be repeated here.
[0106] It should be noted that the information interaction, execution process, etc. between the above-mentioned devices / units are based on the same concept as the method embodiment of the present application. Their specific functions and technical effects can be found in the method embodiment part and will not be repeated here.
[0107] The technicians in the relevant field can clearly understand that for the convenience and simplicity of description, only the division of the above-mentioned functional units and modules is used as an example for illustration. In practical applications, the above-mentioned function allocation can be completed by different functional units and modules as needed, that is, the internal structure of the device can be divided into different functional units or modules to complete all or part of the functions described above. The functional units and modules in the embodiment can be integrated in a processing unit, or each unit can exist physically separately, or two or more units can be integrated in one unit. The above-mentioned integrated unit can be implemented in the form of hardware or in the form of software functional units. In addition, the specific names of the functional units and modules are only for the convenience of distinguishing each other, and are not used to limit the scope of protection of this application. The specific working process of the units and modules in the above-mentioned system can refer to the corresponding process in the aforementioned method embodiment, which will not be repeated here.
[0108] An embodiment of the present application further provides a computer-readable storage medium, wherein the computer-readable storage medium stores a computer program, and when the computer program is executed by a processor, the steps in the above-mentioned method embodiments can be implemented.
[0109] An embodiment of the present application provides a computer program product. When the computer program product runs on a mobile terminal, the mobile terminal can implement the steps in the above-mentioned method embodiments when executing the computer program product.
[0110] If the integrated unit is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a computer-readable storage medium. Based on this understanding, the present application implements all or part of the processes in the above-mentioned embodiment method, which can be completed by instructing the relevant hardware through a computer program. The computer program can be stored in a computer-readable storage medium, and the computer program can implement the steps of the above-mentioned various method embodiments when executed by the processor. Among them, the computer program includes computer program code, and the computer program code can be in source code form, object code form, executable file or some intermediate form. The computer-readable medium can at least include: any entity or device that can carry the computer program code to the camera / terminal device, recording medium, computer memory, read-only memory (ROM, Read-Only Memory), random access memory (RAM, RandomAccess Memory), electric carrier signal, telecommunication signal and software distribution medium. For example, a USB flash drive, a mobile hard disk, a magnetic disk or an optical disk. In some jurisdictions, according to legislation and patent practice, computer-readable media cannot be electric carrier signals and telecommunication signals.
[0111] In the above embodiments, the description of each embodiment has its own emphasis. For parts that are not described or recorded in detail in a certain embodiment, reference can be made to the relevant descriptions of other embodiments.
[0112] Those of ordinary skill in the art will appreciate that the units and algorithm steps of each example described in conjunction with the embodiments disclosed herein can be implemented in electronic hardware, or a combination of computer software and electronic hardware. Whether these functions are performed in hardware or software depends on the specific application and design constraints of the technical solution. Professional and technical personnel can use different methods to implement the described functions for each specific application, but such implementation should not be considered to be beyond the scope of this application.
[0113] In the embodiments provided in the present application, it should be understood that the disclosed devices and methods can be implemented in other ways. For example, the device embodiments described above are only schematic. For example, the division of the modules or units is only a logical function division. There may be other division methods in actual implementation, such as multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be through some interfaces, indirect coupling or communication connection of devices or units, which can be electrical, mechanical or other forms.
[0114] The units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed on multiple network units. Some or all of the units may be selected according to actual needs to achieve the purpose of the solution of this embodiment.
[0115] The embodiments described above are only used to illustrate the technical solutions of the present application, rather than to limit them. Although the present application has been described in detail with reference to the aforementioned embodiments, a person skilled in the art should understand that the technical solutions described in the aforementioned embodiments may still be modified, or some of the technical features may be replaced by equivalents. Such modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present application, and should all be included in the protection scope of the present application.
Claims
1. A rural sewage treatment construction management method based on node management, characterized in that: The method comprises: Obtain construction location information, material delivery information, construction node process acceptance standards, and construction node content acceptance standards for multiple construction projects; According to the construction location information of multiple construction projects, determine the material entry sampling route, conduct material entry sampling for multiple construction projects according to the material entry sampling route, transfer unqualified materials, conduct construction node process acceptance according to the construction node process acceptance standards, and conduct construction node content acceptance according to the construction node content acceptance standards, and obtain the construction node process acceptance results and construction node content acceptance results; Based on the construction location information, construction node process acceptance results and construction node content acceptance results of multiple construction projects, the re-inspection routes for construction node process acceptance and construction node content acceptance are determined.
2. The method according to claim 1, characterized in that Based on the construction location information of multiple construction projects, determine the material on-site sampling route, including: Based on the construction location information of multiple construction projects, the material entry sampling route is determined with the shortest route as the planning principle.
3. The method according to claim 2, characterized in that According to the construction location information of multiple construction projects, determine the material on-site sampling route, including: Obtain the construction process information and current construction nodes of multiple construction projects, and determine the material entry sampling route according to the sequence of the current construction nodes of the multiple construction projects in the construction process information.
4. The method according to claim 3, characterized in that According to the construction location information, construction node process acceptance results and construction node content acceptance results of multiple construction projects, determine the re-inspection route for construction node process acceptance and construction node content acceptance, including: Acquire multiple first construction location information of multiple first construction projects whose construction node process acceptance results are unqualified, and determine the re-inspection route for the construction node process acceptance based on the multiple first construction location information and the shortest route as the planning principle; acquire multiple second construction location information of multiple second construction projects whose construction node content acceptance results are unqualified, and determine the re-inspection route for the construction node content acceptance based on the multiple second construction location information and the shortest route as the planning principle.
5. The method according to claim 4, characterized in that According to the construction location information, construction node process acceptance results and construction node content acceptance results of multiple construction projects, the re-inspection route of the construction node process acceptance and the construction node content acceptance is determined, which also includes: Acquire multiple first construction location information of multiple first construction projects whose construction node process acceptance results are unqualified, and acquire the first construction process information and the first current construction node of the multiple first construction projects; determine the re-inspection route for the construction node process acceptance according to the sequence of the multiple first construction location information and the first current construction nodes of the multiple first construction projects in the first construction process information, and perform material replenishment and transportation in the construction process correction according to the re-inspection route for the construction node process acceptance; acquire multiple second construction location information of multiple second construction projects whose construction node content acceptance results are unqualified, and acquire the second construction process information and the second current construction node of the multiple second construction projects; determine the re-inspection route for the construction node content acceptance according to the sequence of the multiple second construction location information and the second current construction nodes of the multiple second construction projects in the second construction process information, and perform material replenishment and transportation in the construction content correction according to the re-inspection route for the construction node content acceptance.
6. The method according to claim 5, characterized in that According to the construction location information, construction node process acceptance results and construction node content acceptance results of multiple construction projects, the re-inspection route of the construction node process acceptance and the construction node content acceptance is determined, which also includes: Multiple third construction projects are determined among the multiple first construction projects corresponding to the re-inspection route of the construction node process acceptance, and there is no demand for material replenishment and transfer between the current third current construction nodes of the multiple third construction projects and the first current construction nodes of other first construction projects, and the multiple third construction projects are placed at the end of the re-inspection route of the construction node process acceptance; multiple fourth construction projects are determined among the multiple second construction projects corresponding to the re-inspection route of the construction node content acceptance, and there is no demand for material replenishment and transfer between the fourth current construction nodes of the multiple fourth construction projects and the second current construction nodes of other second construction projects, and the multiple fourth construction projects are placed at the end of the re-inspection route of the construction node content acceptance.
7. A rural sewage treatment construction management system based on node management, characterized in that: Comprising means for performing the method according to any one of claims 1 to 6.
8. A rural sewage treatment construction management system based on node management, comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, characterized in that: When the processor executes the computer program, the method according to any one of claims 1 to 6 is implemented.
9. A computer-readable storage medium storing a computer program, characterized in that: When the computer program is executed by a processor, the method according to any one of claims 1 to 6 is implemented.
10. A computer program product, comprising a computer program, characterized in that When the computer program is executed by a processor, the steps of the method according to any one of claims 1 to 6 are implemented.
Citation Information
Patent Citations
Method and system for construction quality acceptance of building engineering based on BIM
CN107748951A
Process acceptance management method and storage medium
CN109345103A
BIM-based informatization quality management method and system
CN111369158A
BIM-based engineering quality management and control method and system
CN112288302A
Engineering project quality staged acceptance intelligent supervision management system based on big data and artificial intelligence
CN112949977A