Wind power tower drum foundation construction device and method
By designing the foundation construction device of wind power tower and using technologies such as rotary support and hydraulic cylinder, the problems of uneven casting, working fatigue and difficulty in leveling embedded parts are solved, and stability and efficiency are improved, and in severe weather. Reduced losses.
Patent Information
- Application Number
- CN202411626924.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-14
- Publication Date
- 2025-01-14
AI Technical Summary
Uneven concrete pouring during wind power tower foundation construction leads to hollowing, handheld concrete pouring pipes lead to work fatigue, and leveling embedded parts is difficult and time-consuming, and it is difficult to quickly perform primary or secondary molding to cope with bad weather.
A wind power tower foundation construction device was designed, including the foundation main body and casting auxiliary parts. The foundation main body is composed of an inner base and a main support, built-in anchor and split pipe, and casting auxiliary parts include rotating brackets, hydraulic cylinders and knocking The strike rod is driven to shake the strike rod by rotating the support to avoid hollowing, and the hydraulic cylinder and the cone are used to improve stability, the gripping ring adjusts the position of the cast pipe, and the separation pipe fittings control the forming steps and drying time.
Even pouring is achieved, reducing the construction labor burden, improving the calibration efficiency of embedded plates, shortening construction time, and reducing losses in bad weather.
Smart Images

Figure CN119308312A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of wind power tower foundation construction, and in particular to a wind power tower foundation construction device and method. Background Art
[0002] The main processes of wind turbine tower foundation construction include cleaning the topsoil, mechanical excavation, manual bottom cleaning, compaction, cushion construction and embedded parts installation, steel engineering machine anchor bolt assembly leveling, concrete maintenance and other steps, which are the basis for wind turbine installation. However, in the existing wind turbine tower foundation construction process, when the concrete is poured and formed, due to the large demand for concrete and the large number of internal structural layers of the steel bars, it is easy to cause uneven pouring and hollowing problems, which reduces the stability of the foundation; and in the process of concrete pouring, it is necessary to manually hold the concrete pouring pipe, move the pouring position, and pour evenly, which is easy to cause work fatigue; before installing the embedded parts, the embedded parts need to be leveled horizontally. Due to the large foundation pit and the large number of embedded parts, leveling the embedded parts one by one increases the construction difficulty and time, and it is difficult to quickly level the embedded parts; during the construction process, since it takes about a month to dry after pouring once, if there is a sudden bad weather, the quality of concrete molding is affected, and even a second pouring is required. The loss of construction is relatively large, and it is difficult to selectively perform a first molding pouring or a second molding pouring to reduce the loss. Summary of the invention
[0003] In view of this, the present invention provides a wind turbine tower foundation construction device and method to solve the problems of uneven pouring and easy hollowing, easy fatigue of holding the concrete pouring pipe, difficult and time-consuming leveling of embedded parts, and difficulty in selective primary or secondary molding and pouring during the foundation construction process.
[0004] The present invention provides a wind power tower foundation construction device, comprising: a foundation body and a pouring auxiliary part; the foundation body is formed by pouring concrete, the foundation body comprises an inner base, the interior of the inner base is pre-installed with built-in anchors and a main support member; the main support member comprises an embedded plate, the top surface of the embedded plate is provided with a horizontal leveling member; the built-in anchor member is installed inside the main support member, and a dividing pipe is installed inside the built-in anchor member; the pouring auxiliary part comprises a connecting frame, the top surface of the connecting frame is provided with a rotating support member; the rotating support member is composed of a connecting turntable and a grasping member, the grasping member is rotatably clamped on the top surface of the connecting turntable, and a concrete pouring pipe is clamped inside the grasping member.
[0005] Optionally, a connecting threaded hole is opened inside the built-in anchor, and an inclined steel bar is connected inside the connecting threaded hole. The inclined steel bar is connected to the bottom surface of the foundation pit. The inclined steel bar can be connected to the built-in anchor through the connecting threaded hole, thereby ensuring that the outer body and the inner base are fixed as one after pouring concrete.
[0006] Optionally, the bottom surface of the connecting turntable is clamped on the top of the connecting plate by rotating the axis, and the top surface of the connecting turntable is fixedly connected to a supporting plate by a round rod. The supporting plate is an arc-shaped structural plate, and the inner diameter of the supporting plate is larger than the outer diameter of the concrete pouring pipe. An inner slot is provided inside the grip, and the supporting plate is clamped inside the inner slot. The circular hole provided at the bottom of the grip is penetrated by the round rod at the top of the connecting turntable, and gripping rings are welded on the left and right sides of the grip respectively. The interior of the grip is penetrated by the concrete pouring pipe. After the concrete pouring pipe is placed into the grip, when the concrete output pump is started for pouring, the operator can adjust the discharge port position of the concrete pouring pipe by gripping the two gripping rings, and the pouring position can be changed by rotating the grip, thereby achieving uniform pouring.
[0007] Optionally, the horizontal leveling member is an arc-shaped strip structure, a connecting head is provided at one end of the horizontal leveling member, a connecting pipe is provided at the other end of the horizontal leveling member, the end of the connecting head is a threaded rod structure, a threaded groove is provided inside the connecting pipe, and an embedded horizontal pipe is pre-buried inside the connecting head, the interior of the embedded horizontal pipe is filled with liquid for the horizontal calibrator, and the top surface height of the embedded horizontal pipe is lower than the highest point of the connecting head, and the number and position of the connecting head are adapted to the embedded plate.
[0008] Optionally, the pouring auxiliary parts also include a hydraulic cylinder and a knocking rod. A base is provided at the bottom of the hydraulic cylinder, and three groups of telescopic rods are connected to the bottom surface of the base. A cone is fixedly connected to the bottom end of the telescopic rod, and the diameter of the cone is smaller than the gap between the steel frame connections. A rod is fixedly welded to the top end of the push rod of the hydraulic cylinder, and a connecting plate is fixedly welded on the rod. A connecting frame is fixedly welded to the end of the rod, and a clamping ring is sleeved on the front end cross bar of the connecting frame. A knocking rod is fixedly welded to the bottom of the clamping ring. When the concrete pouring pipe is pouring, the vibration of the concrete output pump will cause the concrete pouring pipe to vibrate. The rotating support will drive the connecting frame to vibrate synchronously, which will drive the knocking rod to vibrate, and the knocking rod will knock on the steel frame, so that the concrete can settle better during the pouring process, avoid accumulation in one place and cause internal hollowing, and ensure the internal forming of the foundation body.
[0009] Optionally, the main support member also includes connecting steel bars and connecting rings, the bottom end of the connecting steel bars is fixed and vertically welded to the top surface of the embedded plate, the top end of the connecting steel bars is fixedly connected to the connecting ring, a circular hole is provided inside the connecting ring, and a top card slot is provided on the top surface of the embedded plate. The top card slot has an arc-shaped structure and the diameter of the middle section of the slot is larger than the diameter of the slots on both sides.
[0010] Optionally, the partition pipe is composed of two half-tube structures, and rectangular plates are respectively provided on the upper edges of both sides of the two half-tubes. Connecting holes are opened inside the rectangular plates. When choosing to use the partition pipe, the inside of the built-in anchor can be molded first, or the outside of the built-in anchor can be molded first. At the same time, the steps of concrete pouring and drying time can be controlled step by step.
[0011] Optionally, the foundation body also includes an outer body, which is formed by pouring concrete and is cast on the outside of the inner base. A steel bar frame is pre-installed inside the outer body and the inner base, and the inner base and the outer body are internally fixed and supported by the steel bar frame, so that they can be well formed during the concrete pouring process.
[0012] Optional construction method:
[0013] 1) Use an excavator to dig the foundation pit for foundation construction, and flatten and compact the bottom layer of the foundation pit;
[0014] 2) Determine the pouring center point of the foundation body, set up a steel frame, and place the embedded plate around the center point. After the horizontal leveling piece is connected through the connector and the connecting pipe, it is placed on the top surface of the embedded plate, and the embedded horizontal pipe is used to perform horizontal leveling of the embedded plate;
[0015] 3) Weld the connecting steel bar to the top surface of the embedded plate, fasten the top of the connecting steel bar to the connecting ring, and fix the connecting sleeve inside the connecting ring;
[0016] 4) Pre-install steel bars inside the outer body and the inner base, connect the inclined steel bars inside the threaded holes on the built-in anchors, and connect the inclined steel bars to the bottom of the foundation pit;
[0017] 5) Set up the pouring auxiliary parts to the position where pouring is required, penetrate the concrete pouring pipe into the inside of the handle, and start the concrete output pump for pouring;
[0018] 6) Through the circular hole inside the connecting ring, drive the anchor rod into the casing fixedly connected inside the circular hole, and drive the bottom end of the anchor rod into the ground.
[0019] Beneficial Effects
[0020] According to a wind power tower foundation construction device of each embodiment of the present invention, compared with a traditional construction device, when the concrete pouring pipe is poured, the vibration of the concrete output pump will cause the concrete pouring pipe to vibrate, and the rotating bracket will drive the connecting frame to vibrate synchronously, which will drive the knocking rod to vibrate, and the knocking rod will knock the steel frame, so that the concrete can settle better during the pouring process, avoiding accumulation in one place and causing internal hollowing, and ensuring the internal forming of the foundation body;
[0021] In the process of using the pouring auxiliary parts, the clamping cone can be used to clamp the hydraulic cylinder to the steel frame, thereby improving the stability of the pouring auxiliary parts. In the pouring process, the position of the concrete pouring pipe can be stably supported, so there is no need to hold the concrete pouring pipe for pouring, which reduces the labor required for construction;
[0022] In addition, after the connector is connected to the next connector pipe through threaded engagement, the horizontal leveling piece can form a complete circular structure, and the connection between the connector and the connector pipe is clamped in the middle section of the top clamping groove, which can limit and fix the connection between the connector and the connector pipe, and at the same time, all embedded plates can be horizontally leveled, so there is no need to calibrate the horizontal position one by one, which improves the efficiency of calibrating the embedded plates and shortens the time.
[0023] In addition, when starting the concrete output pump for pouring, the operator can adjust the outlet position of the concrete pouring pipe by grasping the two grasping rings, and the pouring position can be changed by turning the grasping piece, so as to achieve uniform pouring and reduce the fatigue of the operator caused by the over-sinking of the concrete pouring pipe;
[0024] In addition, when choosing to use separator pipes, the inside of the built-in anchor can be molded first, and the steps of concrete pouring and drying time can be controlled in steps. Under special conditions such as the need for additional reinforcement of anchor rods, sudden heavy rains, tornadoes and other severe weather conditions, step-by-step molding can better reduce the losses caused by emergencies during construction. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] In order to more clearly illustrate the technical solution of the embodiment of the present invention, the drawings of the embodiment are briefly introduced below.
[0026] The drawings described below are only related to some embodiments of the present invention, but are not intended to limit the present invention.
[0027] In the attached picture:
[0028] Figure 1 A schematic diagram of the front side view structure of the test subject according to the present invention is shown;
[0029] Figure 2 It shows a schematic structural diagram of a test subject according to the present invention;
[0030] Figure 3 A schematic structural diagram of a drawer according to the present invention is shown;
[0031] Figure 4 A schematic structural diagram of a second clamping assembly according to the present invention is shown;
[0032] Figure 5 It shows a schematic structural diagram of a first clamping assembly according to the present invention;
[0033] Figure 6 A schematic diagram of a partial cross-sectional structure of a test body according to the present invention is shown;
[0034] Figure 7 It shows a schematic structural diagram of a mobile test board according to the present invention;
[0035] Figure 8 A schematic structural diagram of a test connection board according to the present invention is shown.
[0036] Reference numerals list
[0037] 1. Basic body; 11. External body; 12. Internal base;
[0038] 2. Built-in anchors;
[0039] 3. Main support member; 31. Embedded plate; 3101. Top card slot; 32. Connecting steel bar; 33. Connecting ring;
[0040] 4. Horizontal leveling piece; 401. Connector; 4011. Embedded horizontal pipe; 402. Connecting pipe;
[0041] 5. Separation pipe fittings;
[0042] 6. Casting auxiliary parts; 61. Hydraulic cylinder; 6101. Cone; 6102. Push rod; 62. Connecting frame; 6201. Connecting plate; 63. Knocking rod;
[0043] 7. Rotating support; 71. Connecting turntable; 7101. Support plate; 72. Grip member; 7201. Internal card slot; 7202. Grip ring;
[0044] 8. Concrete pouring pipe. DETAILED DESCRIPTION
[0045] In order to make the purpose, scheme and advantages of the technical solution of the present invention clearer, the technical solution of the embodiment of the present invention will be clearly and completely described in conjunction with the drawings of the specific embodiments of the present invention. Unless otherwise specified, the terms used herein have the usual meanings in the art. The same reference numerals in the drawings represent the same components.
[0046] Example: Please refer to Figures 1 to 8 :
[0047] The present invention proposes a wind power tower foundation construction device, comprising: a foundation body 1 and a casting auxiliary component 6; the foundation body 1 is formed by casting concrete, and the foundation body 1 includes an inner base 12, and the inner base 12 is pre-installed with a built-in anchor 2 and a main support 3; the main support 3 includes an embedded plate 31, and the top surface of the embedded plate 31 is provided with a horizontal leveling component 4; the built-in anchor 2 is installed inside the main support 3, and a dividing pipe 5 is installed inside the built-in anchor 2; the casting auxiliary component 6 includes a connecting frame 62, and a rotating bracket 7 is installed on the top surface of the connecting frame 62; the rotating bracket 7 is composed of a connecting turntable 71 and a grasping component 72, and the grasping component 72 is rotatably clamped on the top surface of the connecting turntable 71, and a concrete casting pipe 8 is clamped inside the grasping component 72.
[0048] In addition, if attached Figure 2 As shown, a connecting threaded hole is opened inside the built-in anchor 2, and an inclined steel bar is connected inside the connecting threaded hole. The inclined steel bar is connected to the bottom surface of the foundation pit. The inclined steel bar can be connected to the built-in anchor 2 through the connecting threaded hole, thereby ensuring that the outer body 11 and the inner base 12 are fixed as one after pouring concrete.
[0049] In addition, if attached Figure 2 and attached Figure 3 As shown, the partition pipe 5 is composed of two half-tube structures, and rectangular plates are respectively provided on the upper edges of both sides of the two half-tubes. Connecting holes are opened inside the rectangular plates. When the partition pipe 5 is selected, the inside of the built-in anchor 2 can be molded first, or the outside of the built-in anchor 2 can be molded first. At the same time, the steps of concrete pouring and the drying time can be controlled step by step. Under special conditions, step-by-step molding can better reduce the losses caused by emergencies during the construction process.
[0050] In addition, if attached Figure 1 As shown, the foundation body 1 also includes an outer body 11, which is formed by pouring concrete, and the outer body 11 is poured on the outside of the inner base 12. The inner base 12 and the outer body 11 are internally fixed and supported by the steel bars, so that they can be well formed during the concrete pouring process. At the same time, the casting and molding are carried out by two sets of templates, which can better control the molding quality.
[0051] In addition, if attached Figure 3 and attached Figure 6As shown, the main support member 3 also includes a connecting steel bar 32 and a connecting ring 33. The bottom end of the connecting steel bar 32 is fixed and vertically welded to the top surface of the embedded plate 31. The top end of the connecting steel bar 32 is fixedly connected to the connecting ring 33. A circular hole is opened inside the connecting ring 33. A top card groove 3101 is opened on the top surface of the embedded plate 31. The top card groove 3101 is an arc-shaped structure and the diameter of the middle section groove is larger than the diameter of the grooves on both sides. After the connecting sleeve is fixed in the circular hole inside the connecting ring 33, an anchor rod is driven into the sleeve to fix the connecting ring 33 to the ground. The stability of the connection is reinforced by the anchor rod to ensure the stability of the main support member 3. After the wind turbine tower is assembled through the circular hole inside the connecting ring 33, the stability of the wind turbine tower can be ensured.
[0052] In addition, if attached Figure 5 As shown, the bottom surface of the connecting turntable 71 is clamped on the top of the connecting plate 6201 by rotating the axis, and the top surface of the connecting turntable 71 is fixedly connected to the supporting plate 7101 through a round rod. The supporting plate 7101 is an arc-shaped structural plate, and the inner diameter of the supporting plate 7101 is larger than the outer diameter of the concrete pouring pipe 8. An inner slot 7201 is provided inside the gripping piece 72, and the supporting plate 7101 is clamped inside the inner slot 7201. The circular hole provided at the bottom of the gripping piece 72 is penetrated by the round rod at the top of the connecting turntable 71, and gripping rings 7202 are welded on the left and right sides of the gripping piece 72 respectively. The interior of the gripping piece 72 is penetrated by the concrete pouring pipe 8. After the concrete pouring pipe 8 is placed into the gripping piece 72, when the concrete output pump is started for pouring, the operator can adjust the discharge port position of the concrete pouring pipe 8 by gripping the two gripping rings 7202, and the pouring position can be changed by rotating the gripping piece 72.
[0053] In addition, if attached Figure 3 As shown, the horizontal leveling member 4 is an arc-shaped strip structure, one end of the horizontal leveling member 4 is provided with a connector 401, the other end of the horizontal leveling member 4 is provided with a connecting pipe 402, the end of the connector 401 is a threaded rod structure, the interior of the connecting pipe 402 is provided with a threaded groove, and the interior of the connector 401 is pre-buried with an embedded horizontal pipe 4011, the interior of the embedded horizontal pipe 4011 is filled with liquid for the horizontal calibration instrument, and the top surface height of the embedded horizontal pipe 4011 is lower than the highest point of the connector 401, and the number of connectors 401 The horizontal leveling member 4 can form a complete circular structure, and the connection between the connecting head 401 and the connecting tube 402 is clamped in the middle section of the top clamping groove 3101, so that the connection between the connecting head 401 and the connecting tube 402 can be limited and fixed, and all the embedded plates 31 can be horizontally leveled at the same time, so that there is no need to calibrate the horizontal position one by one, thereby improving the efficiency of calibrating the embedded plates 31 and shortening the time.
[0054] In addition, if attached Figure 4 and attached Figure 5 As shown, the pouring auxiliary part 6 also includes a hydraulic cylinder 61 and a knocking rod 63. A base is provided at the bottom of the hydraulic cylinder 61. Three sets of telescopic rods are connected to the bottom surface of the base. A clamping cone 6101 is fixedly connected to the bottom end of the telescopic rod. The diameter of the clamping cone 6101 is smaller than the gap between the steel frame connections. A rod is fixedly welded to the top of the push rod 6102 of the hydraulic cylinder 61. A connecting plate 6201 is fixedly welded to the rod. A connecting frame 62 is fixedly welded to the end of the rod. A clamping ring is sleeved on the front cross bar of the connecting frame 62. The knocking rod 63 is fixedly welded to the bottom of the clamping ring. When the concrete pouring pipe 8 is poured, the vibration of the concrete output pump will cause the concrete pouring pipe 8 to vibrate. The rotating support 7 drives the connecting frame 62 to vibrate synchronously, which will drive the knocking rod 63 to vibrate, and the knocking rod 63 will knock on the steel frame, so that the concrete can be better settled during the pouring process to avoid accumulation in one place and causing internal hollowing, thereby ensuring the internal forming of the foundation body 1. In the process of using the pouring auxiliary part 6, the clamping cone 6101 is used to make it possible to clamp the hydraulic cylinder 61 to the steel frame, thereby improving the stability of the pouring auxiliary part 6. In the pouring process, the position of the concrete pouring pipe 8 can be stably supported, so there is no need to hold the concrete pouring pipe 8 for pouring, thereby reducing the labor required for construction.
[0055] A method for constructing a wind power tower foundation, comprising the following steps:
[0056] 1) Use an excavator to dig the foundation pit for foundation construction, and flatten and compact the bottom layer of the foundation pit;
[0057] 2) Determine the pouring center point of the foundation body 1, set up a steel frame, and place the embedded plate 31 around the center point. After the horizontal leveling member 4 is connected to the connecting head 401 and the connecting pipe 402, it is placed on the top surface of the embedded plate 31, and the embedded horizontal pipe 4011 is used to perform horizontal leveling of the embedded plate 31;
[0058] 3) Weld the connecting steel bar 32 to the top surface of the embedded plate 31, the top of the connecting steel bar 32 is tightly connected to the connecting ring 33, and the connecting sleeve is fixed inside the connecting ring 33;
[0059] 4) A steel bar frame is pre-installed inside the outer body 11 and the inner base 12, and the threaded holes on the built-in anchor 2 are connected to the inclined steel bars, which are connected to the bottom surface of the foundation pit;
[0060] 5) Set the pouring auxiliary part 6 to the position where pouring is required, penetrate the concrete pouring pipe 8 into the inside of the handle 72, and start the concrete output pump for pouring;
[0061] 6) The anchor rod is driven into the casing fixedly connected inside the circular hole through the circular hole inside the connecting ring 33, and the bottom end of the anchor rod is driven into the ground.
[0062] The specific usage and function of this embodiment are as follows:
[0063] In the present invention, the excavator excavates the foundation pit for foundation construction, flattens and compacts the bottom layer in the foundation pit, determines the casting center point of the foundation body 1, sets up a steel frame, and places the embedded plate 31 around the center point. The horizontal leveling member 4 is connected to the connecting head 401 and the connecting pipe 402 through the connecting head 401, and is placed on the top surface of the embedded plate 31. The embedded horizontal pipe 4011 is used to perform horizontal leveling of the embedded plate 31. The separator pipe 5 is selected to be used, and the interior of the built-in anchor 2 is first formed. The threaded hole on the built-in anchor 2 is connected to the inclined steel bar, and the inclined steel bar is connected to the bottom surface of the foundation pit. The casting auxiliary member 6 is set to the position where it needs to be cast. The concrete casting pipe 8 passes through the interior of the gripping member 72, and the concrete output pump is started for casting. The operator can adjust the discharge port position of the concrete casting pipe 8 by gripping the two gripping rings 7202, and the casting position can be changed by rotating the gripping member 72, thereby achieving uniform casting.
Claims
1. A wind power tower foundation construction device, comprising: A foundation body (1) and a pouring auxiliary part (6); characterized in that the foundation body (1) is formed by pouring concrete, the foundation body (1) includes an inner base (12), the interior of the inner base (12) is pre-installed with an internal anchor (2) and a main support (3); the main support (3) includes an embedded plate (31), the top surface of the embedded plate (31) is provided with a horizontal leveling part (4); the internal anchor (2) is installed inside the main support (3), and a dividing pipe (5) is installed inside the internal anchor (2); the pouring auxiliary part (6) includes a connecting frame (62), the top surface of the connecting frame (62) is provided with a rotating bracket (7); the rotating bracket (7) is composed of a connecting turntable (71) and a gripping member (72), the gripping member (72) is rotatably clamped on the top surface of the connecting turntable (71), and a concrete pouring pipe (8) is clamped inside the gripping member (72).
2. A wind power tower foundation construction device according to claim 1, characterized in that: The foundation body (1) also includes an outer body (11), which is formed by pouring concrete. The outer body (11) is poured outside the inner base (12), and a steel bar frame is pre-installed inside the outer body (11) and inside the inner base (12). The inner base 12 and the outer body 11 are internally fixed and supported by the steel bar frame, so that they can be well formed during the concrete pouring process.
3. A wind power tower foundation construction device according to claim 2, characterized in that: A connecting threaded hole is provided inside the built-in anchor (2), an inclined steel bar is connected inside the connecting threaded hole, and the inclined steel bar is connected to the bottom surface of the foundation pit.
4. A wind power tower foundation construction device according to claim 1, characterized in that: The main support member (3) further comprises a connecting steel bar (32) and a connecting ring (33), wherein the bottom end of the connecting steel bar (32) is fixed and vertically welded to the top surface of the embedded plate (31), the top end of the connecting steel bar (32) is fixedly connected to the connecting ring (33), a circular hole is provided inside the connecting ring (33), and a top clamping groove (3101) is provided on the top surface of the embedded plate (31), wherein the top clamping groove (3101) is in an arc-shaped structure and the diameter of the middle section groove is larger than the diameter of the grooves on both sides.
5. A wind power tower foundation construction device according to claim 4, characterized in that: The horizontal leveling member (4) is an arc-shaped strip structure member, a connector (401) is provided at one end of the horizontal leveling member (4), a connecting pipe (402) is provided at the other end of the horizontal leveling member (4), the end of the connecting head (401) is a threaded rod structure, a thread groove is provided inside the connecting pipe (402), and an embedded horizontal pipe (4011) is pre-buried inside the connecting head (401), the embedded horizontal pipe (4011) is filled with liquid for a horizontal calibration instrument, and the top surface height of the embedded horizontal pipe (4011) is lower than the highest point of the connecting head (401), and the number and position of the connecting heads (401) are compatible with the embedded plate (31).
6. A wind power tower foundation construction device according to claim 1, characterized in that: The partition pipe (5) is composed of two half-tube structures. Rectangular plates are respectively arranged on the upper edges of both sides of the two half-tubes, and connecting holes are opened inside the rectangular plates.
7. A wind power tower foundation construction device according to claim 1, characterized in that: The pouring auxiliary component (6) also includes a hydraulic cylinder (61) and a knocking rod (63). A base is provided at the bottom of the hydraulic cylinder (61). The bottom surface of the base is connected to three groups of telescopic rods. The bottom ends of the telescopic rods are fixedly connected to a clamping cone (6101). The diameter of the clamping cone (6101) is smaller than the gap between the steel bar frames. A rod is fixedly welded to the top end of the push rod (6102) of the hydraulic cylinder (61). A connecting plate (6201) is fixedly welded to the rod. A connecting frame (62) is fixedly welded to the end of the rod. A clamping ring is sleeved on the front end cross bar of the connecting frame (62). The knocking rod (63) is fixedly welded to the bottom of the clamping ring.
8. A wind power tower foundation construction device according to claim 1, characterized in that: The bottom surface of the connecting turntable (71) is connected to the top of the connecting plate (6201) by rotating the shaft, and the top surface of the connecting turntable (71) is fixedly connected to a supporting plate (7101) by a round rod. The supporting plate (7101) is an arc-shaped structural plate, and the inner diameter of the supporting plate (7101) is larger than the outer diameter of the concrete pouring pipe (8). An inner slot (7201) is provided inside the gripping member (72), and the supporting plate (7101) is clamped inside the inner slot (7201). The round hole provided at the bottom of the gripping member (72) is penetrated by the round rod at the top of the connecting turntable (71), and gripping rings (7202) are respectively welded on the left and right sides of the gripping member (72), and the interior of the gripping member (72) is penetrated by the concrete pouring pipe (8).
9. A method for constructing a wind power tower foundation according to any one of claims 1 to 8, characterized in that: The following steps are involved: 1) Use an excavator to dig the foundation pit for foundation construction, and flatten and compact the bottom layer of the foundation pit; 2) Determine the pouring center point of the foundation body (1), set up a steel frame, and place the embedded plate (31) around the center point. After the horizontal leveling member (4) is connected to the connecting head (401) and the connecting pipe (402), it is placed on the top surface of the embedded plate (31), and the embedded horizontal pipe (4011) is used to perform horizontal leveling of the embedded plate (31); 3) Weld the connecting steel bar (32) to the top surface of the embedded plate (31), the top end of the connecting steel bar (32) is tightly connected to the connecting ring (33), and the connecting sleeve is fixed inside the connecting ring (33); 4) A steel bar frame is pre-installed inside the outer body (11) and the inner base (12), and the threaded holes on the built-in anchor (2) are connected to the inclined steel bars, which are connected to the bottom surface of the foundation pit; 5) The pouring auxiliary part (6) is set to the position where pouring is required, the concrete pouring pipe (8) is inserted into the interior of the gripping part (72), and the concrete output pump is started to pour; 6) The anchor rod is driven into the casing fixedly connected inside the circular hole through the circular hole inside the connecting ring (33), and the bottom end of the anchor rod is driven into the ground.