Multi-story building walling concrete brick forming method

Through the introduction of automated mold demolition and mold improvement structure in concrete porous bricks, solve the problem of porous porous bricks of concrete, improve production efficiency and brick quality, and reduce production costs.

CN119347924APending Publication Date: 2025-01-24SHENZHEN LVJINLONG ENVIRONMENTAL PROTECTION TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411600067.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-12-25
Publication Date
2025-01-24

AI Technical Summary

Technical Problem

In the prior art, after the concrete porous brick is formed in the mold, it is difficult to release the mold smoothly, resulting in a time-consuming and complex demolding process, affecting production efficiency and increasing costs.

Method used

Multi -story building wall -building concrete brick -type molding equipment includes the installation structure, mold demolition structure, and mold improvement structure. The automatic opening and closing of the mold and the efficient push of the brick block through the hydraulic pushing pole and the stepping motor.

Benefits of technology

It effectively reduces the complexity and labor intensity of manual operations, improves production efficiency, reduces production costs, realizes automated production, ensures brick molding quality and shortens the production cycle.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119347924A_ABST
    Figure CN119347924A_ABST
Patent Text Reader

Abstract

The invention discloses a multi-layer building walling concrete brick forming method, and particularly relates to the technical field of concrete porous brick production, multi-layer building walling concrete brick forming equipment is included, the multi-layer building walling concrete brick forming equipment comprises a mounting structure, and a form removal structure is arranged in the mounting structure; a mold lifting structure is arranged at the top of the mounting structure, a conveying mechanism is arranged on the front side of the mounting structure, and by arranging the mounting structure and the mold removing structure, the complexity and labor intensity of manual operation can be effectively reduced, so that the production efficiency is improved, and the production cost is reduced; and meanwhile, the machined and formed bricks can be pushed to the top of the conveying mechanism, the efficient and continuous production process is achieved, and the production efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of concrete porous brick production, and more specifically to a method for forming concrete bricks for wall construction of multi-story buildings. Background Art

[0002] Concrete porous bricks are a kind of concrete product with multiple rows of small holes, which is made by mixing cement with sand, stone (light aggregate), etc. through adding water, molding and curing. It is widely used in the field of building materials due to its excellent performance and significant energy-saving effect.

[0003] As disclosed in CN218053160U, the utility model relates to the technical field of concrete porous brick production, and in particular to a concrete porous brick forming device, comprising a supporting frame, a conveying assembly being arranged on the upper side of the supporting frame, the conveying assembly comprising a limiting splint, a conveyor belt and a first motor, a limiting splint being symmetrically arranged on the upper side of the supporting frame, a conveyor belt being arranged on the inner side of the limiting splint, a first motor being arranged on the outer side of the limiting splint, a mounting frame being arranged on the rear side of the top surface of the limiting splint, a molding assembly being arranged below the inner side of the mounting frame, a molding mold being driven to rotate by a second motor and a rotating shaft, so that after the porous brick is formed, the opening of the molding mold can be turned downward, and a sliding sealing pad and a push rod being arranged can slide in the molding mold, so that the molded brick can be driven to slide out of the molding mold by pushing the push rod and the sealing pad of the lower pressure plate, thereby facilitating the removal of the brick from the molding mold.

[0004] In the current production process, after the concrete porous bricks complete the molding step in the mold, it is difficult to demold them from the mold smoothly, making the demolding process time-consuming and complicated, which in turn has a negative impact on the overall production efficiency of the porous bricks. Due to the difficulty in demolding, operators need to spend more time and energy to deal with this link, which not only reduces production efficiency but may also increase production costs. Therefore, solving the problem of demolding difficulties for concrete porous bricks is of great significance to improving production efficiency and reducing production costs. Summary of the invention

[0005] In order to overcome the above-mentioned defects of the prior art, the present invention provides a method for forming concrete bricks for building walls of multi-story buildings. The technical problem to be solved by the present invention is: in the current production process, after the concrete porous bricks complete the forming steps in the mold, it is difficult to smoothly demold from the mold, which makes the demolding process time-consuming and complicated, and thus has a negative impact on the overall production efficiency of the porous bricks. Due to the difficulty in demolding, the operator needs to spend more time and energy to deal with this link, which not only reduces the production efficiency, but also may increase the production cost.

[0006] To achieve the above-mentioned purpose, the present invention provides the following technical solutions, including a multi-storey building wall concrete brick forming device: the multi-storey building wall concrete brick forming device comprises a mounting structure, a mold removal structure is arranged inside the mounting structure, a mold lifting structure is arranged on the top of the mounting structure, and a conveying mechanism is arranged on the front side of the mounting structure. The specific processing method thereof comprises the following steps:

[0007] Step 1: Pour the mixed raw materials into the molding mold, making sure that the raw materials evenly fill every corner of the mold;

[0008] Step 2: Heat the mold to accelerate the curing process of the raw material;

[0009] Step 3: After the raw materials are solidified and formed, open the mold and take out the formed bricks;

[0010] Step 4: Conduct quality inspection on the formed bricks to ensure that they meet the design requirements;

[0011] Step 5: Curing qualified bricks to enhance their physical properties;

[0012] Step 6: The bricks that have completed curing can be used for construction.

[0013] As a further solution of the present invention: the installation structure includes an installation box, a rectangular frame is fixedly connected to the upper outer wall of the installation box, support legs are fixedly connected to the four corners of the bottom of the rectangular frame, rectangular through holes are opened on the left and right sides of the top of the installation box and penetrate into the interior, a plurality of mold movable holes are opened in the middle position of the top of the installation box and penetrate into the interior, and circular through holes are opened on the left and right sides of the front and rear sides of the installation box and penetrate into the interior.

[0014] As a further solution of the present invention: the demoulding structure includes a driving component, the top of the driving component is fixedly connected to a hole-opening mold movable component, and the left and right sides of the driving component are fixedly connected to two symmetrical two-way opening components.

[0015] As a further solution of the present invention: the driving assembly includes a hydraulic push rod, the top of the hydraulic push rod is fixedly connected to a connecting plate 1, the left and right sides of the connecting plate 1 are fixedly connected to a connecting plate 2, the front and rear sides of the connecting plate 2 are fixedly connected to convex blocks, the outer wall of the convex block is movably connected to a dovetail groove, the two dovetail grooves are fixedly connected to the inner wall of the installation box on one side away from each other, the bottom of the connecting plate 1 is fixedly connected to the hydraulic push rod, and the bottom of the hydraulic push rod is fixedly connected to the inner wall of the installation box.

[0016] As a further solution of the present invention: the two two-way opening components each include a connecting plate three, the two connecting plates three being close to each other and fixedly connected to the left and right sides of the connecting plate one, the two connecting plates three being hingedly connected to the front and rear sides and away from each other, the inner walls of the front and rear connecting plates four away from the connecting plate three are hingedly connected to the connecting plate five, the connecting plate five being fixedly connected to the side away from the connecting plate four with a fan-shaped tooth, the inner wall of the fan-shaped tooth is fixedly connected to a rotating rod, and the outer wall of the rotating rod is movably connected to the inner walls of the two front and rear circular through holes.

[0017] As a further solution of the present invention: the outer wall of the sector-shaped teeth is meshingly connected with a tooth plate, the top of the tooth plate is fixedly connected with a limiting plate, the top of the limiting plate is fixedly connected with a movable plate, the outer wall of the movable plate is movably connected to the inner wall of the rectangular through hole, the top of the movable plate is fixedly connected with a mold half frame, and the bottom of the mold half frame is movably connected to the top of the installation box.

[0018] As a further solution of the present invention: the hole-opening mold movable component includes an extension plate, the bottom of the extension plate is fixedly connected to the top of the connecting plate one, the top of the extension plate is fixedly connected to the fixed plate one, the top of the fixed plate one is fixedly connected to a plurality of bases, the top of the base is fixedly connected to a rectangular mold plug rod, and the outer wall of the rectangular mold plug rod is movably connected to the inner wall of the movable hole of the mold.

[0019] As a further solution of the present invention: the mold lifting structure includes a mounting block, the bottom of the mounting block is fixedly connected to the top rear side of the rectangular frame, mounting grooves are provided on the left and right sides of the front side of the mounting block, the top of the mounting block is fixedly connected to the motor housing, a circular movable hole is provided on the top of the inner wall of the mounting groove on the right and penetrates into the interior of the motor housing, and a lifting assembly is arranged inside the mounting block.

[0020] As a further solution of the present invention: a hidden groove is opened at the lower front side of the mounting block, a circular movable hole 2 is opened on the rear side of the inner wall of the hidden groove and penetrates to the outside, a support frame is fixedly connected to the lower rear side of the mounting block, a pneumatic push rod is fixedly connected to the top of the support frame, the outer wall of the output end of the pneumatic push rod is movably connected to the inner wall of the circular movable hole 2, the output end of the pneumatic push rod is fixedly connected to a push plate, and the outer wall of the push plate is movably connected to the inner wall of the hidden groove.

[0021] As a further scheme of the present invention: the lifting assembly includes an upper mold plate, the outer wall of the upper mold plate is movably connected to the upper inner walls of the two mold half frames, the top of the upper mold plate is fixedly connected with a fixed plate 2, the left and right sides of the top of the fixed plate 2 are fixedly connected with connecting blocks, the top of the connecting block is fixedly connected with an extension block, the rear side of the left extension block is fixedly connected with a sliding sleeve, the inner wall of the sliding sleeve is movably connected with a sliding rod, the upper and lower ends of the sliding rod are fixedly connected to the inner wall of the left mounting groove, and the rear side of the right extension block is fixedly connected with a sliding block, the inner wall of the sliding block is threadedly connected with a threaded rod, the bottom of the threaded rod is rotatably connected to the inner wall of the right mounting groove, the top of the threaded rod is fixedly connected with a rotating shaft, the outer wall of the rotating shaft is movably connected to the inner wall of the circular movable hole 1, the top of the rotating shaft is fixedly connected with a stepping motor, and the bottom of the stepping motor is fixedly connected to the inner wall of the motor housing.

[0022] The beneficial effects of the present invention are:

[0023] 1. The present invention can effectively reduce the complexity and labor intensity of manual operation by providing an installation structure and a demoulding structure, thereby improving production efficiency and reducing production costs, realizing automated production, ensuring the molding quality of bricks, and shortening the production cycle.

[0024] 2. The present invention is provided with a mold lifting structure and a conveying mechanism, which can lift the mold to an appropriate height, making it convenient for operators to perform raw material filling operations. At the same time, the processed bricks can be pushed to the top of the conveying mechanism, thereby achieving an efficient and continuous production process and improving production efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] Figure 1 It is a schematic diagram of the process of the present invention;

[0026] Figure 2 It is a structural schematic diagram of the present invention;

[0027] Figure 3 It is a schematic diagram of the structural cross section of the present invention;

[0028] Figure 4 It is a structural schematic diagram of the installation structure of the present invention;

[0029] Figure 5 It is a structural schematic diagram of the demoulding structure of the present invention;

[0030] Figure 6 It is a schematic diagram of the structural cross-section of the drive assembly of the present invention;

[0031] Figure 7 It is a structural schematic diagram of a two-way opening component of the present invention;

[0032] Figure 8It is a structural schematic diagram of the movable assembly of the hole-opening mold of the present invention;

[0033] Fig. 9 It is a structural schematic diagram of the mold lifting structure of the present invention;

[0034] Fig.10 It is a structural schematic diagram of the lifting assembly of the present invention.

[0035] In the figure: 1. Installation structure; 2. Demolding structure; 3. Mold lifting structure; 4. Conveying mechanism; 11. Installation box; 12. Rectangular frame; 13. Support leg; 14. Rectangular through hole; 15. Mold movable hole; 16. Circular through hole; 21. Driving assembly; 22. Two-way opening assembly; 23. Opening mold movable assembly; 211. Hydraulic push rod; 212. Connecting plate 1; 213. Connecting plate 2; 214. Convex block; 215. Dovetail groove; 221. Connecting plate 3; 222. Connecting plate 4; 223. Connecting plate 5; 224. Sector teeth; 225. Rotating rod; 226. Tooth plate; 227, limit plate; 228, movable plate; 229, mold half frame; 231, extension plate; 232, fixed plate one; 233, base; 234, rectangular mold plug rod; 31, mounting block; 32, mounting slot; 33, motor housing; 34, lifting assembly; 35, hidden slot; 36, support frame; 37, pneumatic push rod; 38, push plate; 341, upper mold plate; 342, fixed plate two; 343, connecting block; 344, extension block; 345, sliding sleeve; 346, slider; 347, threaded rod; 348, rotating shaft; 349, stepping motor; 340, sliding rod. DETAILED DESCRIPTION

[0036] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0037] like Figure 1-3 As shown, the present invention provides a method for forming multi-story building wall concrete bricks, including a porous building wall concrete brick forming device: the multi-story building wall concrete brick forming device includes a mounting structure 1, a demolding structure 2 is arranged inside the mounting structure 1, a mold lifting structure 3 is arranged on the top of the mounting structure 1, and a conveying mechanism 4 is arranged on the front side of the mounting structure 1. The specific processing method includes the following steps:

[0038] Step 1: Pour the mixed raw materials into the molding mold, making sure that the raw materials evenly fill every corner of the mold;

[0039] Step 2: Heat the mold to accelerate the curing process of the raw material;

[0040] Step 3: After the raw materials are solidified and formed, open the mold and take out the formed bricks;

[0041] Step 4: Conduct quality inspection on the formed bricks to ensure that they meet the design requirements;

[0042] Step 5: Curing qualified bricks to enhance their physical properties;

[0043] Step 6: The bricks that have completed curing can be used for construction.

[0044] like Figure 4-8 As shown, the installation structure 1 includes an installation box 11, a rectangular frame 12 is fixedly connected to the upper outer wall of the installation box 11, and support legs 13 are fixedly connected to the four corners of the bottom of the rectangular frame 12. Rectangular through holes 14 that penetrate into the interior are opened on the left and right sides of the top of the installation box 11, and a plurality of mold movable holes 15 that penetrate into the interior are opened in the middle position of the top of the installation box 11. Circular through holes 16 that penetrate into the interior are opened on the left and right sides of the front and rear sides of the installation box 11. When the two mold half frames 229 are closed and the lifting assembly 34 is in the lifted state, the staff pours the raw materials into the interior of the two mold half frames 229. A heating module is arranged inside the mold half frame 229. The heating module can be an electric heating wire. The mold half frame 229 is heated by the electric heating wire to accelerate the solidification of the raw materials.

[0045] The demoulding structure 2 includes a driving component 21, the top of the driving component 21 is fixedly connected to a hole-opening mold movable component 23, the left and right sides of the driving component 21 are fixedly connected to two symmetrical two-way opening components 22, the driving component 21 includes a hydraulic push rod 211, the top of the hydraulic push rod 211 is fixedly connected to a connecting plate 1 212, the left and right sides of the connecting plate 1 212 are fixedly connected to a connecting plate 213, the front and rear sides of the connecting plate 213 are fixedly connected to a convex block 214, the outer wall of the convex block 214 is movably connected to a dovetail groove 215, and the two The sides of the dovetail grooves 215 that are away from each other are fixedly connected to the inner wall of the installation box 11, and the bottom of the connecting plate 212 is fixedly connected with a hydraulic push rod 211, and the bottom of the hydraulic push rod 211 is fixedly connected to the inner wall of the installation box 11. By starting the hydraulic push rod 211, the hydraulic push rod 211 pushes the connecting plate 212 to move, and the movement of the connecting plate 212 drives the two connecting plates 213 to move, and then drives the convex block 214 to move on the inner wall of the dovetail groove 215, thereby improving the stability of the connecting plate 212 when moving.

[0046] The two two-way opening components 22 each include a connecting plate three 221, the sides of the two connecting plates three 221 that are close to each other are fixedly connected to the left and right sides of the connecting plate one 212, the front and rear sides of the two connecting plates three 221 and the sides that are away from each other are hinged with connecting plates four 222, the inner walls of the front and rear connecting plates four 222 that are away from the connecting plate three 221 are hinged with connecting plates five 223, the side of the connecting plate five 223 that is away from the connecting plate four 222 is fixedly connected with a fan-shaped tooth 224, the inner wall of the fan-shaped tooth 224 is fixedly connected with a rotating rod 225, the outer wall of the rotating rod 225 is movably connected to the inner walls of the front and rear circular through holes 16, the outer wall of the fan-shaped tooth 224 is meshedly connected with a tooth plate 226, the top of the tooth plate 226 is fixedly connected to a limiting plate 227, the top of the limiting plate 227 is fixedly connected to a movable plate 228, the outer wall of the movable plate 228 is movably connected to the inner wall of the rectangular through hole 14, and the top of the movable plate 228 is fixedly connected to a mold half frame 229. The bottom of the mold half frame 229 is movably connected to the top of the installation box 11. The downward movement of the connecting plate 1 212 drives the connecting plate 3 221 to descend synchronously, and then pulls the connecting plate 4 222 to move downward and rotate. The other end of the connecting plate 4 222 is connected to one end of the connecting plate 5 223 in a hinged manner, so that the connecting plate 4 222 pulls the connecting plate 5 223 to rotate, so that the connecting plate 5 223 can drive the fan-shaped teeth 224 to perform corresponding rotational movements during the rotation process. The rotation of the fan-shaped teeth 224 drives the rotating rod 225 to rotate. The rotating rod 225 makes the fan-shaped teeth 224 more stable when rotating. The rotation of the fan-shaped teeth 224 drives the tooth plate 226 to slide. The sliding of the tooth plate 226 causes the limit plate 227 and the movable plate 228 to move accordingly. The movement of the movable plate 228 causes the mold half frame 229 to open and close, thereby realizing the opening and closing actions of the mold, thereby realizing the opening and closing of the mold.

[0047] The hole-opening mold movable component 23 includes an extension plate 231, the bottom of the extension plate 231 is fixedly connected to the top of the connecting plate 212, the top of the extension plate 231 is fixedly connected to a fixed plate 232, the top of the fixed plate 232 is fixedly connected to a plurality of bases 233, the top of the base 233 is fixedly connected to a rectangular mold plug rod 234, the outer wall of the rectangular mold plug rod 234 is movably connected to the inner wall of the mold movable hole 15, and at the same time, by moving the connecting plate 212 downward and driving the extension plate 231 to move, the extension plate 231 drives the fixed plate 232 and the base 233 to move downward, and then the rectangular mold plug rod 234 moves on the inner wall of the mold movable hole 15, so as to conveniently take out the formed bricks and complete the brick production process, thereby greatly improving the production efficiency and brick quality.

[0048] like Figure 9-10As shown, the mold lifting structure 3 includes a mounting block 31, the bottom of the mounting block 31 is fixedly connected to the top rear side of the rectangular frame 12, mounting grooves 32 are provided on the left and right sides of the front side of the mounting block 31, the top of the mounting block 31 is fixedly connected to a motor housing 33, a circular movable hole 1 is provided on the top of the inner wall of the right mounting groove 32 and penetrates into the motor housing 33, a lifting component 34 is arranged inside the mounting block 31, a hidden groove 35 is provided at the lower front side of the mounting block 31, a circular movable hole 2 is provided at the rear side of the inner wall of the hidden groove 35 and penetrates to the outside, a support frame 36 is fixedly connected to the lower rear side of the mounting block 31, a pneumatic push rod 37 is fixedly connected to the top of the support frame 36, and the outer wall of the output end of the pneumatic push rod 37 is connected to the circular movable hole 2 The inner wall is movably connected, and the output end of the pneumatic push rod 37 is fixedly connected with a push plate 38. The outer wall of the push plate 38 is movably connected to the inner wall of the hidden groove 35. The pneumatic push rod 37 is started at the same time or later as the stepper motor 349 is started, and the push plate 38 is pushed to move forward along the inner wall of the hidden groove 35, and further pushes the formed brick into the top of the conveying mechanism 4. The whole process is automated, which not only improves the production efficiency, but also ensures the quality and consistency of the bricks. The lifting component 34 includes an upper mold plate 341, and the outer wall of the upper mold plate 341 is movably connected to the upper inner wall of the two mold half frames 229. The top of the upper mold plate 341 is fixedly connected with a fixed plate 242, and the left and right sides of the top of the fixed plate 242 are fixedly connected with a connecting block 3 43, the top of the connecting block 343 is fixedly connected with an extension block 344, the rear side of the left extension block 344 is fixedly connected with a sliding sleeve 345, the inner wall of the sliding sleeve 345 is movably connected with a sliding rod 340, the upper and lower ends of the sliding rod 340 are fixedly connected with the inner wall of the left mounting groove 32, the rear side of the right extension block 344 is fixedly connected with a slider 346, the inner wall of the slider 346 is threadedly connected with a threaded rod 347, the bottom of the threaded rod 347 is rotatably connected with the inner wall of the right mounting groove 32, the top of the threaded rod 347 is fixedly connected with a rotating shaft 348, the outer wall of the rotating shaft 348 is movably connected with the inner wall of the circular movable hole 1, the top of the rotating shaft 348 is fixedly connected with a stepping motor 349, the bottom of the stepping motor 349 is connected to the inner wall of the motor housing 33 The wall is fixedly connected, and by starting the stepper motor 349, the rotating shaft 348 is driven to rotate. The rotation of the rotating shaft 348 is caused by the threaded action of the threaded rod 347, so that the slider 346 moves up and down along the inner wall of the right mounting groove 32. The movement of the slider 346 drives the right extension block 344 and the connecting block 343 to move, and then drives the fixed plate 2 342 and the upper mold plate 341 to move. The movement of the fixed plate 2 342 drives the left connecting block 343 and the extension block 344 to move, so that the sliding sleeve 345 slides up and down in the left sliding rod 340 and the mounting groove 32, and then the upper mold plate 341 moves upward along the inner wall of the mold half frame 229. The lifting of the upper mold plate 341 causes the bricks to be separated from the mold.

[0049] Working principle of the present invention:

[0050] When the two mold half frames 229 are closed and the lifting assembly 34 is in the lifted state, the staff pours the raw materials into the two mold half frames 229. A heating module is provided inside the mold half frames 229. The heating module can be an electric heating wire. The mold half frames 229 are heated by the electric heating wire to accelerate the solidification of the raw materials. The hydraulic push rod 211 is started so that the hydraulic push rod 211 pushes the connecting plate 1 212 to move. The movement of the connecting plate 1 212 drives the two connecting plates 213 to move, and then drives the convex block 214 to move on the inner wall of the dovetail groove 215, thereby improving the stability of the connecting plate 1 212 during movement. The downward movement of the connecting plate 1 212 drives the connecting plate 3 221 to drop synchronously, and then pulls the connecting plate 4 222 to move downward and rotate. The other end of the connecting plate 4 222 is connected to one end of the connecting plate 5 223 in a hinged manner, so that the connecting plate 4 222 pulls the connecting plate 5 223 to rotate. The rotation of the sector teeth 224 drives the rotating rod 225 to rotate, and the rotating rod 225 makes the sector teeth 224 more stable when rotating. The rotation of the sector teeth 224 drives the tooth plate 226 to slide, and the sliding of the tooth plate 226 causes the limit plate 227 and the movable plate 228 to move accordingly. The movement of the movable plate 228 causes the opening and closing of the mold half frame 229, thereby realizing the opening and closing of the mold, thereby realizing the opening and closing of the mold. At the same time, the downward movement of the connecting plate 1 212 drives the extension plate 231 to move, so that the extension plate 231 drives the fixed plate 1 232 and the base 233 to move downward, and then the rectangular mold insertion rod 234 moves on the inner wall of the mold movable hole 15, so as to conveniently take out the formed bricks, complete the brick production process, and greatly improve the production efficiency and brick quality.

[0051] By starting the stepper motor 349, the shaft 348 is driven to rotate. The rotation of the shaft 348 causes the slider 346 to move up and down along the inner wall of the right mounting groove 32 through the threaded action of the threaded rod 347. The movement of the slider 346 drives the right extension block 344 and the connecting block 343 to move, thereby driving the fixed plate 342 and the upper mold plate 341 to move. The movement of the fixed plate 342 drives the left connecting block 343 and the extension block 344 to move, thereby causing the sliding sleeve 345 to move in a certain direction. The left slide bar 340 and the mounting groove 32 slide up and down, so that the upper mold plate 341 moves upward along the inner wall of the mold half frame 229. The lifting of the upper mold plate 341 causes the formed bricks to be separated. At the same time, the pneumatic push rod 37 is started at the same time as or later when the stepper motor 349 is started, pushing the push plate 38 to move forward along the inner wall of the hidden groove 35, further pushing the formed bricks into the top of the conveying mechanism 4. The whole process is automated, which not only improves production efficiency, but also ensures the quality and consistency of bricks.

[0052] Finally, a few points should be explained: First, in the description of this application, it should be noted that, unless otherwise specified and limited, the terms "installed", "connected" and "connected" should be understood in a broad sense, which can be a mechanical connection or an electrical connection, or the internal communication of two components, or a direct connection. "upper", "lower", "left" and "right" are only used to indicate relative positional relationships. When the absolute position of the object being described changes, the relative positional relationship may change;

[0053] Secondly: In the drawings of the embodiments disclosed in the present invention, only the structures related to the embodiments disclosed in the present invention are involved, and other structures can refer to the general design. In the absence of conflict, the same embodiment and different embodiments of the present invention can be combined with each other;

[0054] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical scheme and inventive concept of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.

Claims

1. A method for forming multi-story building wall concrete bricks, comprising a porous building wall concrete brick forming device, characterized in that: The multi-storey building wall concrete brick forming equipment comprises a mounting structure (1), a demoulding structure (2) is arranged inside the mounting structure (1), a mold lifting structure (3) is arranged on the top of the mounting structure (1), and a conveying mechanism (4) is arranged on the front side of the mounting structure (1). The specific processing method comprises the following steps: Step 1: Pour the mixed raw materials into the molding mold, making sure that the raw materials evenly fill every corner of the mold; Step 2: Heat the mold to accelerate the curing process of the raw material; Step 3: After the raw materials are solidified and formed, open the mold and take out the formed bricks; Step 4: Conduct quality inspection on the formed bricks to ensure that they meet the design requirements; Step 5: Curing qualified bricks to enhance their physical properties; Step 6: The bricks that have completed curing can be used for construction.

2. The method for forming multi-story building wall concrete bricks according to claim 1, characterized in that: The installation structure (1) comprises an installation box (11), a rectangular frame (12) is fixedly connected to the upper part of the outer wall of the installation box (11), and support legs (13) are fixedly connected to the four corners of the bottom of the rectangular frame (12), rectangular through holes (14) are opened on the left and right sides of the top of the installation box (11) and penetrate to the interior, a plurality of mold movable holes (15) are opened in the middle position of the top of the installation box (11) and penetrate to the interior, and circular through holes (16) are opened on the left and right sides of the front and rear sides of the installation box (11) and penetrate to the interior.

3. The method for forming multi-storey building wall concrete bricks according to claim 1, characterized in that: The demoulding structure (2) comprises a driving component (21), the top of which is fixedly connected to a hole-opening mold movable component (23), and the left and right sides of the driving component (21) are fixedly connected to two symmetrical two-way opening components (22).

4. The method for forming multi-storey building wall concrete bricks according to claim 3, characterized in that: The driving assembly (21) comprises a hydraulic push rod (211), the top of the hydraulic push rod (211) is fixedly connected to a connecting plate 1 (212), the left and right sides of the connecting plate 1 (212) are fixedly connected to connecting plate 2 (213), the front and rear sides of the connecting plate 2 (213) are fixedly connected to convex blocks (214), the outer wall of the convex block (214) is movably connected to a dovetail groove (215), the two dovetail grooves (215) are fixedly connected to the inner wall of the installation box (11) on the side away from each other, the bottom of the connecting plate 1 (212) is fixedly connected to the hydraulic push rod (211), and the bottom of the hydraulic push rod (211) is fixedly connected to the inner wall of the installation box (11).

5. The method for forming multi-story building wall concrete bricks according to claim 3, characterized in that: The two bidirectional opening components (22) each include a connecting plate three (221), the sides of the two connecting plates three (221) close to each other are fixedly connected to the left and right sides of the connecting plate one (212), the front and rear sides of the two connecting plates three (221) and the sides away from each other are hinged with connecting plates four (222), the inner walls of the front and rear connecting plates four (222) away from the connecting plate three (221) are hinged with connecting plates five (223), the side of the connecting plate five (223) away from the connecting plate four (222) is fixedly connected with fan-shaped teeth (224), the inner wall of the fan-shaped teeth (224) is fixedly connected with a rotating rod (225), and the outer wall of the rotating rod (225) is movably connected to the inner walls of the two front and rear circular through holes (16).

6. The method for forming multi-story building wall concrete bricks according to claim 5, characterized in that: The outer wall of the sector teeth (224) is meshingly connected with a tooth plate (226), the top of the tooth plate (226) is fixedly connected with a limit plate (227), the top of the limit plate (227) is fixedly connected with a movable plate (228), the outer wall of the movable plate (228) is movably connected to the inner wall of the rectangular through hole (14), the top of the movable plate (228) is fixedly connected with a mold half frame (229), and the bottom of the mold half frame (229) is movably connected to the top of the installation box (11).

7. The method for forming multi-story building wall concrete bricks according to claim 3, characterized in that: The hole-opening mold movable component (23) comprises an extension plate (231), the bottom of the extension plate (231) is fixedly connected to the top of the connecting plate 1 (212), the top of the extension plate (231) is fixedly connected to the fixing plate 1 (232), the top of the fixing plate 1 (232) is fixedly connected to a plurality of bases (233), the top of the base (233) is fixedly connected to a rectangular mold insert rod (234), and the outer wall of the rectangular mold insert rod (234) is movably connected to the inner wall of the mold movable hole (15).

8. The method for forming multi-story building wall concrete bricks according to claim 1, characterized in that: The mold lifting structure (3) comprises a mounting block (31), the bottom of the mounting block (31) is fixedly connected to the top rear side of the rectangular frame (12), the left and right sides of the front side of the mounting block (31) are both provided with mounting grooves (32), the top of the mounting block (31) is fixedly connected to a motor housing (33), the top of the inner wall of the right mounting groove (32) is provided with a circular movable hole that penetrates into the inside of the motor housing (33), and a lifting component (34) is arranged inside the mounting block (31).

9. The method for forming multi-story building wall concrete bricks according to claim 8, characterized in that: A hidden groove (35) is provided at the lower front side of the mounting block (31); a second circular movable hole penetrating to the outside is provided at the rear side of the inner wall of the hidden groove (35); a support frame (36) is fixedly connected to the lower rear side of the mounting block (31); a pneumatic push rod (37) is fixedly connected to the top of the support frame (36); an outer wall of an output end of the pneumatic push rod (37) is movably connected to the inner wall of the second circular movable hole; a push plate (38) is fixedly connected to the output end of the pneumatic push rod (37); and an outer wall of the push plate (38) is movably connected to the inner wall of the hidden groove (35).

10. The method for forming multi-story building wall concrete bricks according to claim 9, characterized in that: The lifting assembly (34) comprises an upper mold plate (341), the outer wall of which is movably connected to the upper inner walls of the two mold half frames (229), the top of the upper mold plate (341) is fixedly connected to a second fixing plate (342), the left and right sides of the top of the second fixing plate (342) are fixedly connected to connecting blocks (343), the top of the connecting block (343) is fixedly connected to an extension block (344), the rear side of the left extension block (344) is fixedly connected to a sliding sleeve (345), the inner wall of the sliding sleeve (345) is movably connected to a sliding rod (340), the upper and lower ends of the sliding rod (340) are fixedly connected to the upper and lower ends of the sliding rod (340). The end is fixedly connected to the inner wall of the left mounting groove (32), the rear side of the right extension block (344) is fixedly connected with a slider (346), the inner wall of the slider (346) is threadedly connected with a threaded rod (347), the bottom of the threaded rod (347) is rotatably connected to the inner wall of the right mounting groove (32), the top of the threaded rod (347) is fixedly connected with a rotating shaft (348), the outer wall of the rotating shaft (348) is movably connected to the inner wall of the circular movable hole 1, the top of the rotating shaft (348) is fixedly connected with a stepping motor (349), and the bottom of the stepping motor (349) is fixedly connected to the inner wall of the motor housing (33).